TIME SCHEDULE
PROYEK :
PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LINGKUNGAN PENDIDIKAN KEAGAMAAN (LPK) LOKASI 3
PEKERJAAN :
LOKASI : PONPES PANCASILA REO KELURAHANA MATA AIR, KECAMATAN REOK KABUPATEN MANGGARAI
TAHUN ANGGARAN : 2022
26-Jul-22 2-Aug-22 9-Aug-22 16-Aug-22 23-Aug-22 30-Aug-22 6-Sep-22 13-Sep-22 20-Sep-22 27-Sep-22 4-Oct-22 11-Oct-22 17-Oct-22
1 2 3 4 26
II PEKERJAAN STRUKTUR 44,578,761.95 24.74 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09
III PEKERJAAN ARSITEKTUR 56,218,222.62 31.20 3.90 3.90 3.90 3.90 3.90 3.90 3.90 3.90
C PEKERJAAN BAK SETLLER & AF 38,746,520.37 21.50 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69
F PEKERJAAN LAIN LAIN 9,037,692.37 5.02 0.72 0.72 0.72 0.72 0.72 0.72 0.72
JUMLAH 180,200,016.51 100.00 0.20 0.20 1.27 3.80 8.09 10.77 10.77 10.77 14.09 14.09 14.09 8.55 3.30
KOMULATIF RENCANA BOBOT MINGGUAN 0.20 0.40 1.67 5.47 13.56 24.33 35.10 45.88 59.97 74.06 88.15 96.70 100.00
REALISASI BOBOT MINGGUAN 0.20
KOMULATIF REALISASI BOBOT MINGGUAN 0.20
DEVIASI 0.00
Dibuat Oleh,
Kontraktor Pelaksanan
Deddy Susanto
Kuasa Direktur
Bank NTT Cabang Waikabubak
TIME SCHEDULE
PROYEK :
PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LINGKUNGAN PENDIDIKAN KEAGAMAAN (LPK) LOKASI 3
PEKERJAAN :
LOKASI : PONPES PANCASILA REO KELURAHANA MATA AIR, KECAMATAN REOK KABUPATEN MANGGARAI
TAHUN ANGGARAN : 2022
26-Jul-22 2-Aug-22 9-Aug-22 16-Aug-22 23-Aug-22 30-Aug-22 6-Sep-22 13-Sep-22 20-Sep-22 27-Sep-22 4-Oct-22 11-Oct-22 17-Oct-22
1 2 3 4 26
II PEKERJAAN STRUKTUR 44,578,761.95 24.74 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09
III PEKERJAAN ARSITEKTUR 56,218,222.62 31.20 3.90 3.90 3.90 3.90 3.90 3.90 3.90 3.90
C PEKERJAAN BAK SETLLER & AF 38,746,520.37 21.50 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69
F PEKERJAAN LAIN LAIN 9,037,692.37 5.02 0.72 0.72 0.72 0.72 0.72 0.72 0.72
JUMLAH 180,200,016.51 100.00 0.20 0.20 1.27 3.80 8.09 10.77 10.77 10.77 14.09 14.09 14.09 8.55 3.30
KOMULATIF RENCANA BOBOT MINGGUAN 0.20 0.40 1.67 5.47 13.56 24.33 35.10 45.88 59.97 74.06 88.15 96.70 100.00
REALISASI BOBOT MINGGUAN 0.20 0.37
KOMULATIF REALISASI BOBOT MINGGUAN 0.20 0.37
DEVIASI 0.00 -0.03
Dibuat Oleh,
Kontraktor Pelaksanan
Deddy Susanto
Kuasa Direktur