ENGINEER'S ESTIMATE ( EE )

REKAPITULASI ANGGARAN BIAYA

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA


PENDIDIKAN KEAGAMAAN PONPES SMAK SANTA FILOMENA MENA
PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA
LOKASI : KABUPATEN TTU PROVINSI NTT
TAHUN ANGGARAN : 2022

JUMLAH HARGA
NO URAIAN PEKERJAAN
( Rp )
1 2 3
I PEKERJAAN PERSIAPAN 2,884,542.12
II PEKERJAAN STRUKTUR 46,154,946.07
III PEKERJAAN ARSITEKTUR 59,724,364.10
IV PEKERJAAN ELEKTRIKAL DAN PLUMBING 15,139,758.65
V PEKERJAAN IPAL NON-PABRIKASI
A PEKERJAAN TANAH DAN LANDASAN 2,496,563.77
B PEKERJAAN BAK INLET 2,065,701.30
C PEKERJAAN BAK SETLLER & AF 38,352,180.70
D PEKERJAAN BAK DESINFEKTAN 2,140,485.25
E PEKERJAAN LAIN LAIN 8,325,118.02
F COMISSIONING TEST 400,000.00
TOTAL BIAYA UMUM + KEUNTUNGAN 177,683,659.97
PAJAK PERTAMBAHAN NILAI ( PPN ) 11% 19,545,202.60
TOTAL BIAYA KESELURUHAN 197,228,862.57
DIBULATKAN 197,200,000.00

TERBILANG DUA RATUS JUTA RUPIAH

Kupang, 16 Juni 2022

Disetujui Oleh : Disusun Oleh :


Kepala Satuan Kerja Satker Pelaksanaan Prasarana Permukiman
Pelaksanaan Prasarana Permukiman Wilayah II Balai PPW NTT
Wilayah II Balai PPW NTT

Septina Rachmawati, ST., M.Sc. Tinny Touselak, ST., MT.


NIP. 19770912 200502 2 001 NIP. 19841023 200903 2 002

Diketahui Oleh :
Kepala Balai Prasarana Permukiman
Wilayah Nusa Tenggara Timur

Normansjah Wartabone, S.T., M.Si.


NIP. 19681206 200012 1 001
LAPORAN PROGRES MINGGU - I I
01 Agustus 2022 SD 07 Agustus 2022

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA PENDIDIKAN KEAGAMAAN (LPK) Lokasi 4
PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA
LOKASI : PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

PROGRESS PEKERJAAN
HARGA SATUAN JUMLAH HARGA Bobot (%)
NO URAIAN PEKERJAAN VOLUME SAT MINGGU LALU MINGGU INI SD MINGGU INI
( Rp ) ( Rp )

VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP


ITEM TOTAL ITEM TOTAL ITEM TOTAL
1 2 3 4 5 6 = 3X5 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan area 40.89 m2 8,480.00 346,747.20 0.19% 40.89 100.00% 0.19% 0.00 0.00% 0.00% 40.89 100.00% 0.19%
2 Pekerjaan Bowplank 25.70 m 38,435.60 987,794.92 0.55% 1.00 3.89% 0.02% 10.70 41.63% 0.23% 11.70 45.53% 0.25%
3 Papan Informasi Proyek & K3 1.00 Unit 250,000.00 250,000.00 0.14%
4 Helm Proyek 5.00 Bh 25,000.00 125,000.00 0.07%
5 Rompi Proyek 5.00 Bh 40,000.00 200,000.00 0.11%
6 Sepatu keselamatan untuk pekerja (Rubber safety shoes) 5.00 Psg 95,000.00 475,000.00 0.26%
7 Peralatan P3K (Kotak P3K, Obat Luka, Perban, dll) 1.00 Unit 200,000.00 200,000.00 0.11%
8 Pelindung pernapasan dan mulut, masker (protokol covid) 4.00 Pack 25,000.00 100,000.00 0.06%
9 Tempat cuci tangan portable 1.00 Unit 200,000.00 200,000.00 0.11%
SUB TOTAL I 2,884,542.12 0.21% 0.23% 0.44%
II PEKERJAAN STRUKTUR
1 Pekerjaan Tanah
a. Pekerjaan galian Pondasi 11.37 m3 76,320.00 867,758.40 0.48%
2 Pekerjaan Pondasi
a. Pekerjaan Urugan Pasir di bawah Pondasi 1.42 m3 222,600.00 316,537.20 0.18%
b. Pekerjaan Pasangan Pondasi Batu Belah 10.12 m3 779,674.52 7,892,255.33 4.38%
3 Pekerjaan Sloof 15X20
a. Beton camp 1pc : 2psr : 3 krl 1.04 m3 1,117,939.85 1,162,657.45 0.65%
b. Pembesian 217.79 Kg 21,091.35 4,593,399.17 2.55%
c. Bekisting Sloof 2x pakai 12.61 m2 124,625.00 1,571,521.25 0.87%
4 Pekerjaan Urugan pasir di bawah lantai kerja 1.72 m3 222,600.00 382,872.00 0.21%
5 Rabat beton camp 1pc : 3psr : 5 krl 2.61 m3 954,869.96 2,492,210.59 1.38%
6 Pekerjaan Kolom beton 12 x 12
a. Beton camp 1pc : 2psr : 3 krl 0.77 m3 1,117,939.85 860,813.69 0.48%
b. Pembesian 324.00 Kg 21,091.35 6,833,597.40 3.79%
c. Bekisting Kolom 2x pakai 12.96 m2 160,700.00 2,082,672.00 1.16%
7 Pekerjaan Balok 12x20 Elv. 1.30 & 2.25 m
a. Beton camp 1pc : 2psr : 3 krl 0.66 m3 1,117,939.85 737,840.30 0.41%
b. Pembesian 151.34 Kg 21,091.35 3,191,964.91 1.77%
c. Bekisting Balok 2x pakai 11.00 m2 162,500.00 1,787,500.00 0.99%
8 Pekerjaan Balok 12 x 20 (ring balk) Elv. 2.75 m
a. Beton camp 1pc : 2psr : 3 krl 0.48 m3 1,117,939.85 536,611.13 0.30%
b. Pembesian 105.31 Kg 21,091.35 2,221,130.07 1.23%
c. Bekisting Balok 2x pakai 8.00 m2 162,500.00 1,300,000.00 0.72%
9 Pekerjaan Rangka Atap
a. Pekerjaan rangka atap baja Ringan 48.13 m2 152,163.00 7,323,605.19 4.07%
SUB TOTAL II 46,154,946.07
III PEKERJAAN ARSITEKTUR
1 Pekerjaan Dinding
a. Pekerjaan pasangan Dinding bata merah 1 sp : 6 pp 30.80 m2 287,698.84 8,861,124.27 4.92%
b. Pekerjaan Plesteran 1 sp : 5 pp 76.81 m2 32,903.88 2,527,347.33 1.40%
c. Pekerjaan Acian 76.81 m2 30,620.75 2,351,979.81 1.31%
2 Pekerjaan Penutup Lantai dan dinding
a. Pekerjaan Penutup Lantai dan dinding Kamar Mandi 1
1 Pasangan Keramik lantai 20x20 1.32 m2 201,903.50 266,512.62 0.15%
2 Pasangan Keramik dinding 20x25 3.85 m2 289,145.74 1,113,211.10 0.62%
b. Pekerjaan Penutup Lantai dan dinding Kamar Mandi 2
1 Pasangan Keramik lantai 20x20 1.32 m2 201,903.50 266,512.62 0.15%
2 Pasangan Keramik dinding 20x25 3.85 m2 289,145.74 1,113,211.10 0.62%
c. Pekerjaan Penutup Lantai dan dinding Kakus 1
1 Pasangan Keramik lantai 20x20 1.74 m2 201,903.50 351,312.09 0.20%
2 Pasangan Keramik dinding 20x25 4.31 m2 289,145.74 1,246,218.14 0.69%
d. Pekerjaan Penutup Lantai dan dinding Kakus 2
1 Pasangan Keramik lantai 20x20 1.74 m2 201,903.50 351,312.09 0.20%
2 Pasangan Keramik dinding 20x25 4.31 m2 289,145.74 1,246,218.14 0.69%
e. Pekerjaan Penutup Lantai dan dinding Kakus 3
1 Pasangan Keramik lantai 20x20 1.74 m2 201,903.50 351,312.09 0.20%
2 Pasangan Keramik dinding 20x25 4.31 m2 289,145.74 1,246,218.14 0.69%
f. Pekerjaan Penutup Lantai dan dinding Kakus 4
1 Pasangan Keramik lantai 20x20 1.32 m2 201,903.50 266,512.62 0.15%
2 Pasangan Keramik dinding 20x25 3.85 m2 289,145.74 1,113,211.10 0.62%
3
Pekerjaan Penutup Lantai selasar depan Kakus, lantai area bak cuci
tangan, Lantai Area Tempat Wudhu dan Tempat Cuci Bersama

a. Pasangan Keramik lantai 20x20 25.75 m2 201,903.50 5,199,015.13 2.89%


PROGRESS PEKERJAAN
HARGA SATUAN JUMLAH HARGA Bobot (%)
NO URAIAN PEKERJAAN VOLUME SAT MINGGU LALU MINGGU INI SD MINGGU INI
( Rp ) ( Rp )

VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP


ITEM TOTAL ITEM TOTAL ITEM TOTAL
1 2 3 4 5 6 = 3X5 7 8 9 10 11 12 13 14 15 16
4 Pekerjaan Bak Cuci Tangan
a. Pekerjaan Beton
1 Beton camp 1pc : 2psr : 3 krl 0.19 m3 1,117,939.85 212,408.57 0.12%
2 Pembesian 27.00 kg 21,091.35 569,466.45 0.32%
3 Bekisting 3.98 m2 124,625.00 496,007.50 0.28%
b. Pasangan Keramik lantai 20x20 0.90 m2 201,903.50 181,713.15 0.10%
c. Pasangan Keramik dinding 20x25 2.95 m2 289,145.74 852,979.93 0.47%
d. Waterproofing 3.98 m2 27,666.00 110,110.68 0.06%
e. Pasangan Pipa PVC AW 3/4 inch 1.50 m 21,814.80 32,722.20 0.02%
f. Pasangan Pipa PVC AW 1/2 Inch 0.30 m 27,538.80 8,261.64 0.00%
g. pasangan pipa PVC AW 2 inch 5.20 m 52,120.20 271,025.04 0.15%
5 Pekerjaan Tempat Wudhu
a. Pasangan Keramik lantai 20x20 2.20 m2 201,903.50 444,187.70 0.25%
b. Pasangan Keramik dinding 20x25 6.34 m2 289,145.74 1,833,183.99 1.02%
c. Pasangan Pipa PVC AW 3/4 inch instalasi utama 4.00 m 21,814.80 87,259.20 0.05%
d. Pasangan Pipa PVC AW 1/2 Inch dari instalasi utama
ke fixture 0.60 m 27,538.80 16,523.28 0.01%
e. Pasangan pipa PVC AW 3 inch buangan air bekas 1.00 m 88,992.30 88,992.30 0.05%
f. Grill Besi 1.00 Unit 1,393,916.51 1,393,916.51 0.77%
6 Pekerjaan Tempat Cuci Bersama
a. Pasangan Keramik lantai 20x20 1.21 m2 201,903.50 244,303.24 0.14%
b. Pasangan Keramik dinding 20x25 3.00 m2 289,145.74 867,437.22 0.48%
c. Pasangan Pipa PVC AW 3/4 inch instalasi utama 1.50 m 21,814.80 32,722.20 0.02%
d. Pasangan Pipa PVC AW 1/2 Inch dari instalasi utama
ke fixture 0.30 m 27,538.80 8,261.64 0.00%
e. Pasangan pipa PVC AW 3 inch buangan air bekas 1.50 m 88,992.30 133,488.45 0.07%
7 Pekerjaan Penutup Atap
a. Penutup Atap / Spandek 48.13 m2 133,878.00 6,443,548.14 3.58%
b. Listplank GRC tebal 10 mm lebar 20 cm 27.70 m 61,280.72 1,697,475.94 0.94%
8 Pekerjaan Pintu dan Ventilasi
a. Pintu Aluminium Strip Komplit terpasang 6.00 bh 756,866.50 4,541,199.00 2.52%
b. Bouvenlicht kisi-kisi Besi hollo 2 x2 cm finish cat 2.16 m2 357,887.80 773,037.65 0.43%
9 Pekerjaan Pengecatan
a. Pengecatan Tembok 76.81 m2 38,960.30 2,992,540.64 1.66%
10 Pekerjaan Sanitary
a. Pemasangan Closet Jongkok 4.00 bh 601,846.80 2,407,387.20 1.34%
b. Pemasangan Kran air 11.00 bh 116,003.75 1,276,041.25 0.71%
c. Pemasangan head shower lengkap dengan Kran
ganda 5.00 unit 352,980.00 1,764,900.00 0.98%
d. Pemasangan Floordrain 9.00 bh 43,778.00 394,002.00 0.22%
e. Tempat Sabun 8.00 bh 74,862.50 598,900.00 0.33%
11 Pekerjaan Logo dan tulisan
a. Logo PU 1.00 bh 765,373.00 765,373.00 0.42%
b. Tulisan "Indonesia Maju" 1.00 SET 313,760.00 313,760.00 0.17%
SUB TOTAL III 59,724,364.10
IV PEKERJAAN ELEKTRIKAL DAN PLUMBING
1 Pekerjaan Elektrikal dan Plambing
a. Pek. MCB 1.00 bh 165,000.00 165,000.00 0.09%
b. Pek. Box MCB 1.00 unit 130,000.00 130,000.00 0.07%
c. Pek. Instalasi lampu 12.00 titik 151,166.60 1,813,999.20 1.01%
d. Pek. Pemasangan lampu tempel plafond fitting lampu kotak 12.00 bh 102,926.00 1,235,112.00
0.69%
e. Pek. Pemasangan Sakelar 10.00 bh 31,789.40 317,894.00 0.18%
2 Pekerjaan pipa air bekas
a. Pipa PVC 4 inch 29.00 m 38,748.30 1,123,700.70 0.62%
b. Fitting 14.00 bh 22,000.00 308,000.00 0.17%
3 Pekerjaan pipa air Kotor/Tinja
a. Pipa PVC 4 inch 13.00 m 38,748.30 503,727.90 0.28%
b. Fitting 10.00 bh 22,000.00 220,000.00 0.12%
4 Pekerjaan Torn Air
a. Menara Air 1.00 unit 1,200,000.00 1,200,000.00 0.67%
b. Galian tanah manual pondasi FP 3.59 m3 79,582.95 285,702.79 0.16%
c. Pondasi FP 60x60, sloof, kolom pedestal
1 Beton camp 1pc : 2psr : 3 krl 0.57 m3 1,117,939.85 637,225.72 0.35%
2 Pembesian 68.70 Kg 21,091.35 1,448,975.75 0.80%
3 Bekisting 6.16 m2 124,625.00 767,690.00 0.43%
d. Tangki Air 1000 liter fiber 1.00 unit 1,350,000.00 1,350,000.00 0.75%
d. Jet pompa 250 W 1.00 unit 2,200,000.00 2,200,000.00 1.22%
e. Pek. Instalasi power pompa 1.00 titik 151,166.60 151,166.60 0.08%
f. Pek. Instalasi WLC 1.00 titik 190,800.00 190,800.00 0.11%
g. Pipa 3/4 inch dari tangki air ke jaringan 10.00 m 21,814.80 218,148.00 0.12%
h. Pipa 1 inch dari sumber air ke Tangki 20.00 m 25,630.80 512,616.00 0.28%
i. Pek. Stopkran 4.00 bh 90,000.00 360,000.00 0.20%
SUB TOTAL IV 15,139,758.65
V PEKERJAAN IPAL NON-PABRIKASI
A PEKERJAAN TANAH DAN LANDASAN
1 Galian tanah manual 18.57 m3 76,320.00 1,417,262.40 0.79%
2 Urugan tanah kembali 5.98 m3 42,400.00 253,552.00 0.14%
3 Pasir urug, tebal 5 cm 1.05 m3 222,600.00 233,730.00 0.13%
4 Rabat beton camp 1pc : 3psr : 5 krl , tebal 5 cm 0.62 m3 954,869.96 592,019.37 0.33%
SUB TOTAL A 2,496,563.77
PROGRESS PEKERJAAN
HARGA SATUAN JUMLAH HARGA Bobot (%)
NO URAIAN PEKERJAAN VOLUME SAT MINGGU LALU MINGGU INI SD MINGGU INI
( Rp ) ( Rp )

VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP


ITEM TOTAL ITEM TOTAL ITEM TOTAL
1 2 3 4 5 6 = 3X5 7 8 9 10 11 12 13 14 15 16
B PEKERJAAN BAK INLET
1 Pelat Lantai dasar
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi 8.96 kg 21,091.35 188,978.50 0.10%
c. Pemasangan bekisting lantai 0.50 m2 189,200.00 94,600.00 0.05%
2 Dinding
a. Beton camp 1pc : 2psr : 3 krl 0.18 m3 1,117,939.85 201,229.17 0.11%
b. Tulangan besi polos 19.17 kg 21,091.35 404,321.18 0.22%
c. Pemasangan bekisting dinding 2.20 m2 196,700.00 432,740.00 0.24%
3 Pelat Atap
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi polos 8.96 kg 21,091.35 188,978.50 0.10%
c. Pemasangan bekisting lantai 1.16 m2 189,200.00 219,472.00 0.12%
SUB TOTAL B 2,065,701.30
C PEKERJAAN BAK SETLLER & AF
1 Pelat Lantai dasar
a. Beton camp 1pc : 2psr : 3 krl 1.25 m3 1,117,939.85 1,397,424.82 0.78%
b. Tulangan besi polos 70.00 kg 21,091.35 1,476,394.50 0.82%
c. Pemasangan bekisting lantai 2.32 m2 189,200.00 438,944.00 0.24%
2 Dinding
a. Beton camp 1pc : 2psr : 3 krl 6.17 m3 1,117,939.85 6,897,688.89 3.83%
b. Tulangan besi polos 338.00 kg 21,091.35 7,128,876.30 3.96%
c. Pemasangan bekisting dinding 80.96 m2 196,700.00 15,924,832.00 8.84%
3 Balok konsol dudukan media filter
a. Beton camp 1pc : 2psr : 3 krl 0.09 m3 1,117,939.85 100,614.59 0.06%
b. Tulangan besi polos 18.65 kg 21,091.35 393,353.68 0.22%
c. Pemasangan bekisting balok 0.28 m2 162,500.00 45,500.00 0.03%
4 Atap
a. Beton camp 1pc : 2psr : 3 krl 1.25 m3 1,117,939.85 1,397,424.82 0.78%
b. Tulangan besi polos 70.00 kg 21,091.35 1,476,394.50 0.82%
c. Pemasangan bekisting lantai 7.00 m2 189,200.00 1,324,400.00 0.74%
6 Ring balk praktis 10/15 1.00 m 140,491.87 140,491.87 0.08%
7 Pasangan batu bata (1/2 bata) 1Pc : 3 Ps 0.45 m2 294,276.67 132,424.50 0.07%
8 Plesteran 1Pc : 3 Ps 0.90 m2 55,397.30 49,857.57 0.03%
9 Acian 0.90 m2 30,620.75 27,558.68 0.02%
SUB TOTAL C 38,352,180.70
D PEKERJAAN BAK DESINFEKTAN
1 Pelat Lantai dasar
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi polos 4.48 kg 21,091.35 94,489.25 0.05%
c. Pemasangan bekisting lantai 0.51 m2 189,200.00 96,492.00 0.05%
2 Dinding
a. Beton camp 1pc : 2psr : 3 krl 0.30 m3 1,117,939.85 335,381.96 0.19%
b. Tulangan besi polos 10.77 kg 21,091.35 227,153.84 0.13%
c. Pemasangan bekisting dinding 3.75 m2 196,700.00 737,625.00 0.41%
3 Atap
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi polos 4.48 kg 21,091.35 94,489.25 0.05%
c. Pemasangan bekisting lantai 1.16 m2 189,200.00 219,472.00 0.12%
SUB TOTAL D 2,140,485.25
E PEKERJAAN RESAPAN
a Galian tanah 2.16 m3 76,320.00 164,851.20 0.09%
b. Pasangan Dinding 6.60 m2 287,698.84 1,898,812.34 1.05%
Atap
a. Beton camp 1pc : 2psr : 3 krl 0.22 m3 1,117,939.85 241,475.01 0.13%
b. Tulangan besi polos 4.48 21,091.35 94,489.25 0.05%
c. Pemasangan bekisting lantai 0.15 m3 189,200.00 28,380.00 0.02%
SUB TOTAL D 2,428,007.80
F PEKERJAAN LAIN LAIN
1 Pemasangan dudukan media filter
0.14 m3 1,058,584.40 148,201.82 0.08%
2 Pemasangan media filter
2.43 m3 1,800,000.00 4,374,000.00 2.43%
3 Pemasangan inflow dan outflow pipa PVC tipe AW
dia. 4" 8.00 m 38,748.30 309,986.40 0.17%
4 Pemasangan penghubung antar bak pipa PVC tipe AW
dia.4" 7.50 m 38,748.30 290,612.25 0.16%
5 Pemasangan Tee PVC tipe AW dia.4" 7.00 bh 37,084.10 259,588.70 0.14%
6 Pemasangan penghubung antar bak inlet dengan bak
settler pipa PVC tipe AW dia.3" 1.50 m 88,992.30 133,488.45 0.07%
7 Pemasangan sirkulasi antar bak pipa PVC tipe AW
dia. 2" 2.00 m 52,120.20 104,240.40 0.06%
8 Pemasangan vent pipa Galvanish dia. 1" 1.00 bh 400,000.00 400,000.00 0.22%
9 Tutup Manhole plat bordes t = 2 mm (lengkap dengan
kait dan cat anti karat) 7.00 bh 310,000.00 2,170,000.00 1.20%
10 Floating Clorin feeder (pengumpan klorin apung) 1.00 unit 125,000.00 125,000.00 0.07%
11 Khlorin Tablet 1.00 kg 10,000.00 10,000.00 0.01%
SUB TOTAL E 8,325,118.02
G COMISSIONING TEST 0.00%
1 Uji Aliran Bak IPL 1.00 ls 200,000.00 200,000.00 0.11%
2 Uji Kebocoran Bak IPL 1.00 ls 200,000.00 200,000.00 0.11%
SUB TOTAL F 400,000.00

180,111,667.77 100.00% 0.43% 0.23% 0.44%

PROGRESS REALISASI 0.44%


PROGRESS RENCANA 1.60%
DEVIASI -1.16%
REKAPITULASI LAPORAN PROGRES MINGGU - I I
01 Agustus 2022 SD 07 Agustus 2022

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA


PENDIDIKAN KEAGAMAAN (LPK) LOKASI 4

PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA


LOKASI : PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

JUMLAH HARGA Bobot (%) PROGRESS PEKERJAAN


NO URAIAN PEKERJAAN
( Rp ) BOBOT (%) MINGGU LALU BOBOT (%) MINGGU INI
TERHADAP BOBOT (%) SD MINGGU INI
TERHADAP
TERHADAP ITEM TERHADAP TOTAL TERHADAP ITEM TOTAL TERHADAP ITEM TOTAL
1 2 3 4 5 6
1 2 3
I PEKERJAAN PERSIAPAN 2,884,542.12 1.60% 0.21% 0.23% 0.44%
II PEKERJAAN STRUKTUR 46,154,946.07 25.63%
III PEKERJAAN ARSITEKTUR 59,724,364.10 33.16%
IV PEKERJAAN ELEKTRIKAL DAN PLUMBING 15,139,758.65 8.41%
V PEKERJAAN IPAL NON-PABRIKASI 0.00%
A PEKERJAAN TANAH DAN LANDASAN 2,496,563.77 1.39%
B PEKERJAAN BAK INLET 2,065,701.30 1.15%
C PEKERJAAN BAK SETLLER & AF 38,352,180.70 21.29%
D PEKERJAAN BAK DESINFEKTAN 2,140,485.25 1.19%
E PEKERJAAN RESAPAN 2,428,007.80 1.35%
F PEKERJAAN LAIN LAIN 8,325,118.02 4.62%
G COMISSIONING TEST 400,000.00 0.22%
TOTAL BIAYA UMUM + KEUNTUNGAN 180,111,667.77 100.00% 0.21% 0.23% 0.44%
PAJAK PERTAMBAHAN NILAI ( PPN ) 11% 19,812,283.45
TOTAL BIAYA KESELURUHAN 199,923,951.22
DIBULATKAN 199,923,000.00

TERBILANG SERATUS SEMBILAN PULUH SEMBILAN JUTA SEMBILAN RATUS RIBU

CV. GASINDO

John Riupassa
Kuasa Direktur
REKAPITULASI LAPORAN PROGRES MINGGU - I
25 JULI 2022 SD 31 JULI 2022

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA


PENDIDIKAN KEAGAMAAN (LPK) LOKASI 4

PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA


LOKASI : PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

JUMLAH HARGA Bobot (%) PROGRESS PEKERJAAN


NO URAIAN PEKERJAAN
( Rp ) BOBOT (%) MINGGU LALU BOBOT (%) MINGGU INI
TERHADAP BOBOT (%) SD MINGGU INI
TERHADAP
TERHADAP ITEM TERHADAP TOTAL TERHADAP ITEM TOTAL TERHADAP ITEM TOTAL
1 2 3 4 5 6
1 2 3
I PEKERJAAN PERSIAPAN 2,884,542.12 1.60% 0.00% 0.21% 0.21%
II PEKERJAAN STRUKTUR 46,154,946.07 25.63%
III PEKERJAAN ARSITEKTUR 59,724,364.10 33.16%
IV PEKERJAAN ELEKTRIKAL DAN PLUMBING 15,139,758.65 8.41%
V PEKERJAAN IPAL NON-PABRIKASI 0.00%
A PEKERJAAN TANAH DAN LANDASAN 2,496,563.77 1.39%
B PEKERJAAN BAK INLET 2,065,701.30 1.15%
C PEKERJAAN BAK SETLLER & AF 38,352,180.70 21.29%
D PEKERJAAN BAK DESINFEKTAN 2,140,485.25 1.19%
E PEKERJAAN RESAPAN 2,428,007.80 1.35%
F PEKERJAAN LAIN LAIN 8,325,118.02 4.62%
G COMISSIONING TEST 400,000.00 0.22%
TOTAL BIAYA UMUM + KEUNTUNGAN 180,111,667.77 100.00% 0.00% 0.21% 0.21%
PAJAK PERTAMBAHAN NILAI ( PPN ) 11% 19,812,283.45
TOTAL BIAYA KESELURUHAN 199,923,951.22
DIBULATKAN 199,923,000.00

TERBILANG SERATUS SEMBILAN PULUH SEMBILAN JUTA SEMBILAN RATUS RIBU

CV. GASINDO

John Riupassa
Kuasa Direktur
LAPORAN PROGRES MINGGU - I
25 JULI 2022 SD 31 JULI 2022

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA PENDIDIKAN KEAGAMAAN (LPK) Lokasi 4
PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA
LOKASI : PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

PROGRESS PEKERJAAN
HARGA SATUAN JUMLAH HARGA Bobot (%)
NO URAIAN PEKERJAAN VOLUME SAT MINGGU LALU MINGGU INI SD MINGGU INI
( Rp ) ( Rp )

VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP


ITEM TOTAL ITEM TOTAL ITEM TOTAL
1 2 3 4 5 6 = 3X5 7 8 9 10 11 12 13 14 15 16
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan area 40.89 m2 8,480.00 346,747.20 0.19% - 0.00% 0.00% 40.89 100.00% 0.19% 40.89 100.00% 0.19%
2 Pekerjaan Bowplank 25.70 m 38,435.60 987,794.92 0.55% - 0.00% 0.00% 1.00 3.89% 0.02% 1.00 3.89% 0.02%
3 Papan Informasi Proyek & K3 1.00 Unit 250,000.00 250,000.00 0.14%
4 Helm Proyek 5.00 Bh 25,000.00 125,000.00 0.07%
5 Rompi Proyek 5.00 Bh 40,000.00 200,000.00 0.11%
6 Sepatu keselamatan untuk pekerja (Rubber safety shoes) 5.00 Psg 95,000.00 475,000.00 0.26%
7 Peralatan P3K (Kotak P3K, Obat Luka, Perban, dll) 1.00 Unit 200,000.00 200,000.00 0.11%
8 Pelindung pernapasan dan mulut, masker (protokol covid) 4.00 Pack 25,000.00 100,000.00 0.06%
9 Tempat cuci tangan portable 1.00 Unit 200,000.00 200,000.00 0.11%
SUB TOTAL I 2,884,542.12 0.00% 0.21% 0.21%
II PEKERJAAN STRUKTUR
1 Pekerjaan Tanah
a. Pekerjaan galian Pondasi 11.37 m3 76,320.00 867,758.40 0.48%
2 Pekerjaan Pondasi
a. Pekerjaan Urugan Pasir di bawah Pondasi 1.42 m3 222,600.00 316,537.20 0.18%
b. Pekerjaan Pasangan Pondasi Batu Belah 10.12 m3 779,674.52 7,892,255.33 4.38%
3 Pekerjaan Sloof 15X20
a. Beton camp 1pc : 2psr : 3 krl 1.04 m3 1,117,939.85 1,162,657.45 0.65%
b. Pembesian 217.79 Kg 21,091.35 4,593,399.17 2.55%
c. Bekisting Sloof 2x pakai 12.61 m2 124,625.00 1,571,521.25 0.87%
4 Pekerjaan Urugan pasir di bawah lantai kerja 1.72 m3 222,600.00 382,872.00 0.21%
5 Rabat beton camp 1pc : 3psr : 5 krl 2.61 m3 954,869.96 2,492,210.59 1.38%
6 Pekerjaan Kolom beton 12 x 12
a. Beton camp 1pc : 2psr : 3 krl 0.77 m3 1,117,939.85 860,813.69 0.48%
b. Pembesian 324.00 Kg 21,091.35 6,833,597.40 3.79%
c. Bekisting Kolom 2x pakai 12.96 m2 160,700.00 2,082,672.00 1.16%
7 Pekerjaan Balok 12x20 Elv. 1.30 & 2.25 m
a. Beton camp 1pc : 2psr : 3 krl 0.66 m3 1,117,939.85 737,840.30 0.41%
b. Pembesian 151.34 Kg 21,091.35 3,191,964.91 1.77%
c. Bekisting Balok 2x pakai 11.00 m2 162,500.00 1,787,500.00 0.99%
8 Pekerjaan Balok 12 x 20 (ring balk) Elv. 2.75 m
a. Beton camp 1pc : 2psr : 3 krl 0.48 m3 1,117,939.85 536,611.13 0.30%
b. Pembesian 105.31 Kg 21,091.35 2,221,130.07 1.23%
c. Bekisting Balok 2x pakai 8.00 m2 162,500.00 1,300,000.00 0.72%
9 Pekerjaan Rangka Atap
a. Pekerjaan rangka atap baja Ringan 48.13 m2 152,163.00 7,323,605.19 4.07%
SUB TOTAL II 46,154,946.07
III PEKERJAAN ARSITEKTUR
1 Pekerjaan Dinding
a. Pekerjaan pasangan Dinding bata merah 1 sp : 6 pp 30.80 m2 287,698.84 8,861,124.27 4.92%
b. Pekerjaan Plesteran 1 sp : 5 pp 76.81 m2 32,903.88 2,527,347.33 1.40%
c. Pekerjaan Acian 76.81 m2 30,620.75 2,351,979.81 1.31%
2 Pekerjaan Penutup Lantai dan dinding
a. Pekerjaan Penutup Lantai dan dinding Kamar Mandi 1
1 Pasangan Keramik lantai 20x20 1.32 m2 201,903.50 266,512.62 0.15%
2 Pasangan Keramik dinding 20x25 3.85 m2 289,145.74 1,113,211.10 0.62%
b. Pekerjaan Penutup Lantai dan dinding Kamar Mandi 2
1 Pasangan Keramik lantai 20x20 1.32 m2 201,903.50 266,512.62 0.15%
2 Pasangan Keramik dinding 20x25 3.85 m2 289,145.74 1,113,211.10 0.62%
c. Pekerjaan Penutup Lantai dan dinding Kakus 1
1 Pasangan Keramik lantai 20x20 1.74 m2 201,903.50 351,312.09 0.20%
2 Pasangan Keramik dinding 20x25 4.31 m2 289,145.74 1,246,218.14 0.69%
d. Pekerjaan Penutup Lantai dan dinding Kakus 2
1 Pasangan Keramik lantai 20x20 1.74 m2 201,903.50 351,312.09 0.20%
2 Pasangan Keramik dinding 20x25 4.31 m2 289,145.74 1,246,218.14 0.69%
e. Pekerjaan Penutup Lantai dan dinding Kakus 3
1 Pasangan Keramik lantai 20x20 1.74 m2 201,903.50 351,312.09 0.20%
2 Pasangan Keramik dinding 20x25 4.31 m2 289,145.74 1,246,218.14 0.69%
f. Pekerjaan Penutup Lantai dan dinding Kakus 4
1 Pasangan Keramik lantai 20x20 1.32 m2 201,903.50 266,512.62 0.15%
2 Pasangan Keramik dinding 20x25 3.85 m2 289,145.74 1,113,211.10 0.62%
3
Pekerjaan Penutup Lantai selasar depan Kakus, lantai area bak cuci
tangan, Lantai Area Tempat Wudhu dan Tempat Cuci Bersama

a. Pasangan Keramik lantai 20x20 25.75 m2 201,903.50 5,199,015.13 2.89%


PROGRESS PEKERJAAN
HARGA SATUAN JUMLAH HARGA Bobot (%)
NO URAIAN PEKERJAAN VOLUME SAT MINGGU LALU MINGGU INI SD MINGGU INI
( Rp ) ( Rp )

VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP


ITEM TOTAL ITEM TOTAL ITEM TOTAL
1 2 3 4 5 6 = 3X5 7 8 9 10 11 12 13 14 15 16
4 Pekerjaan Bak Cuci Tangan
a. Pekerjaan Beton
1 Beton camp 1pc : 2psr : 3 krl 0.19 m3 1,117,939.85 212,408.57 0.12%
2 Pembesian 27.00 kg 21,091.35 569,466.45 0.32%
3 Bekisting 3.98 m2 124,625.00 496,007.50 0.28%
b. Pasangan Keramik lantai 20x20 0.90 m2 201,903.50 181,713.15 0.10%
c. Pasangan Keramik dinding 20x25 2.95 m2 289,145.74 852,979.93 0.47%
d. Waterproofing 3.98 m2 27,666.00 110,110.68 0.06%
e. Pasangan Pipa PVC AW 3/4 inch 1.50 m 21,814.80 32,722.20 0.02%
f. Pasangan Pipa PVC AW 1/2 Inch 0.30 m 27,538.80 8,261.64 0.00%
g. pasangan pipa PVC AW 2 inch 5.20 m 52,120.20 271,025.04 0.15%
5 Pekerjaan Tempat Wudhu
a. Pasangan Keramik lantai 20x20 2.20 m2 201,903.50 444,187.70 0.25%
b. Pasangan Keramik dinding 20x25 6.34 m2 289,145.74 1,833,183.99 1.02%
c. Pasangan Pipa PVC AW 3/4 inch instalasi utama 4.00 m 21,814.80 87,259.20 0.05%
d. Pasangan Pipa PVC AW 1/2 Inch dari instalasi utama
ke fixture 0.60 m 27,538.80 16,523.28 0.01%
e. Pasangan pipa PVC AW 3 inch buangan air bekas 1.00 m 88,992.30 88,992.30 0.05%
f. Grill Besi 1.00 Unit 1,393,916.51 1,393,916.51 0.77%
6 Pekerjaan Tempat Cuci Bersama
a. Pasangan Keramik lantai 20x20 1.21 m2 201,903.50 244,303.24 0.14%
b. Pasangan Keramik dinding 20x25 3.00 m2 289,145.74 867,437.22 0.48%
c. Pasangan Pipa PVC AW 3/4 inch instalasi utama 1.50 m 21,814.80 32,722.20 0.02%
d. Pasangan Pipa PVC AW 1/2 Inch dari instalasi utama
ke fixture 0.30 m 27,538.80 8,261.64 0.00%
e. Pasangan pipa PVC AW 3 inch buangan air bekas 1.50 m 88,992.30 133,488.45 0.07%
7 Pekerjaan Penutup Atap
a. Penutup Atap / Spandek 48.13 m2 133,878.00 6,443,548.14 3.58%
b. Listplank GRC tebal 10 mm lebar 20 cm 27.70 m 61,280.72 1,697,475.94 0.94%
8 Pekerjaan Pintu dan Ventilasi
a. Pintu Aluminium Strip Komplit terpasang 6.00 bh 756,866.50 4,541,199.00 2.52%
b. Bouvenlicht kisi-kisi Besi hollo 2 x2 cm finish cat 2.16 m2 357,887.80 773,037.65 0.43%
9 Pekerjaan Pengecatan
a. Pengecatan Tembok 76.81 m2 38,960.30 2,992,540.64 1.66%
10 Pekerjaan Sanitary
a. Pemasangan Closet Jongkok 4.00 bh 601,846.80 2,407,387.20 1.34%
b. Pemasangan Kran air 11.00 bh 116,003.75 1,276,041.25 0.71%
c. Pemasangan head shower lengkap dengan Kran
ganda 5.00 unit 352,980.00 1,764,900.00 0.98%
d. Pemasangan Floordrain 9.00 bh 43,778.00 394,002.00 0.22%
e. Tempat Sabun 8.00 bh 74,862.50 598,900.00 0.33%
11 Pekerjaan Logo dan tulisan
a. Logo PU 1.00 bh 765,373.00 765,373.00 0.42%
b. Tulisan "Indonesia Maju" 1.00 SET 313,760.00 313,760.00 0.17%
SUB TOTAL III 59,724,364.10
IV PEKERJAAN ELEKTRIKAL DAN PLUMBING
1 Pekerjaan Elektrikal dan Plambing
a. Pek. MCB 1.00 bh 165,000.00 165,000.00 0.09%
b. Pek. Box MCB 1.00 unit 130,000.00 130,000.00 0.07%
c. Pek. Instalasi lampu 12.00 titik 151,166.60 1,813,999.20 1.01%
d. Pek. Pemasangan lampu tempel plafond fitting lampu kotak 12.00 bh 102,926.00 1,235,112.00
0.69%
e. Pek. Pemasangan Sakelar 10.00 bh 31,789.40 317,894.00 0.18%
2 Pekerjaan pipa air bekas
a. Pipa PVC 4 inch 29.00 m 38,748.30 1,123,700.70 0.62%
b. Fitting 14.00 bh 22,000.00 308,000.00 0.17%
3 Pekerjaan pipa air Kotor/Tinja
a. Pipa PVC 4 inch 13.00 m 38,748.30 503,727.90 0.28%
b. Fitting 10.00 bh 22,000.00 220,000.00 0.12%
4 Pekerjaan Torn Air
a. Menara Air 1.00 unit 1,200,000.00 1,200,000.00 0.67%
b. Galian tanah manual pondasi FP 3.59 m3 79,582.95 285,702.79 0.16%
c. Pondasi FP 60x60, sloof, kolom pedestal
1 Beton camp 1pc : 2psr : 3 krl 0.57 m3 1,117,939.85 637,225.72 0.35%
2 Pembesian 68.70 Kg 21,091.35 1,448,975.75 0.80%
3 Bekisting 6.16 m2 124,625.00 767,690.00 0.43%
d. Tangki Air 1000 liter fiber 1.00 unit 1,350,000.00 1,350,000.00 0.75%
d. Jet pompa 250 W 1.00 unit 2,200,000.00 2,200,000.00 1.22%
e. Pek. Instalasi power pompa 1.00 titik 151,166.60 151,166.60 0.08%
f. Pek. Instalasi WLC 1.00 titik 190,800.00 190,800.00 0.11%
g. Pipa 3/4 inch dari tangki air ke jaringan 10.00 m 21,814.80 218,148.00 0.12%
h. Pipa 1 inch dari sumber air ke Tangki 20.00 m 25,630.80 512,616.00 0.28%
i. Pek. Stopkran 4.00 bh 90,000.00 360,000.00 0.20%
SUB TOTAL IV 15,139,758.65
V PEKERJAAN IPAL NON-PABRIKASI
A PEKERJAAN TANAH DAN LANDASAN
1 Galian tanah manual 18.57 m3 76,320.00 1,417,262.40 0.79%
2 Urugan tanah kembali 5.98 m3 42,400.00 253,552.00 0.14%
3 Pasir urug, tebal 5 cm 1.05 m3 222,600.00 233,730.00 0.13%
4 Rabat beton camp 1pc : 3psr : 5 krl , tebal 5 cm 0.62 m3 954,869.96 592,019.37 0.33%
SUB TOTAL A 2,496,563.77
PROGRESS PEKERJAAN
HARGA SATUAN JUMLAH HARGA Bobot (%)
NO URAIAN PEKERJAAN VOLUME SAT MINGGU LALU MINGGU INI SD MINGGU INI
( Rp ) ( Rp )

VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)

TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP TERCAPAI TERHADAP TERHADAP


ITEM TOTAL ITEM TOTAL ITEM TOTAL
1 2 3 4 5 6 = 3X5 7 8 9 10 11 12 13 14 15 16
B PEKERJAAN BAK INLET
1 Pelat Lantai dasar
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi 8.96 kg 21,091.35 188,978.50 0.10%
c. Pemasangan bekisting lantai 0.50 m2 189,200.00 94,600.00 0.05%
2 Dinding
a. Beton camp 1pc : 2psr : 3 krl 0.18 m3 1,117,939.85 201,229.17 0.11%
b. Tulangan besi polos 19.17 kg 21,091.35 404,321.18 0.22%
c. Pemasangan bekisting dinding 2.20 m2 196,700.00 432,740.00 0.24%
3 Pelat Atap
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi polos 8.96 kg 21,091.35 188,978.50 0.10%
c. Pemasangan bekisting lantai 1.16 m2 189,200.00 219,472.00 0.12%
SUB TOTAL B 2,065,701.30
C PEKERJAAN BAK SETLLER & AF
1 Pelat Lantai dasar
a. Beton camp 1pc : 2psr : 3 krl 1.25 m3 1,117,939.85 1,397,424.82 0.78%
b. Tulangan besi polos 70.00 kg 21,091.35 1,476,394.50 0.82%
c. Pemasangan bekisting lantai 2.32 m2 189,200.00 438,944.00 0.24%
2 Dinding
a. Beton camp 1pc : 2psr : 3 krl 6.17 m3 1,117,939.85 6,897,688.89 3.83%
b. Tulangan besi polos 338.00 kg 21,091.35 7,128,876.30 3.96%
c. Pemasangan bekisting dinding 80.96 m2 196,700.00 15,924,832.00 8.84%
3 Balok konsol dudukan media filter
a. Beton camp 1pc : 2psr : 3 krl 0.09 m3 1,117,939.85 100,614.59 0.06%
b. Tulangan besi polos 18.65 kg 21,091.35 393,353.68 0.22%
c. Pemasangan bekisting balok 0.28 m2 162,500.00 45,500.00 0.03%
4 Atap
a. Beton camp 1pc : 2psr : 3 krl 1.25 m3 1,117,939.85 1,397,424.82 0.78%
b. Tulangan besi polos 70.00 kg 21,091.35 1,476,394.50 0.82%
c. Pemasangan bekisting lantai 7.00 m2 189,200.00 1,324,400.00 0.74%
6 Ring balk praktis 10/15 1.00 m 140,491.87 140,491.87 0.08%
7 Pasangan batu bata (1/2 bata) 1Pc : 3 Ps 0.45 m2 294,276.67 132,424.50 0.07%
8 Plesteran 1Pc : 3 Ps 0.90 m2 55,397.30 49,857.57 0.03%
9 Acian 0.90 m2 30,620.75 27,558.68 0.02%
SUB TOTAL C 38,352,180.70
D PEKERJAAN BAK DESINFEKTAN
1 Pelat Lantai dasar
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi polos 4.48 kg 21,091.35 94,489.25 0.05%
c. Pemasangan bekisting lantai 0.51 m2 189,200.00 96,492.00 0.05%
2 Dinding
a. Beton camp 1pc : 2psr : 3 krl 0.30 m3 1,117,939.85 335,381.96 0.19%
b. Tulangan besi polos 10.77 kg 21,091.35 227,153.84 0.13%
c. Pemasangan bekisting dinding 3.75 m2 196,700.00 737,625.00 0.41%
3 Atap
a. Beton camp 1pc : 2psr : 3 krl 0.15 m3 1,117,939.85 167,690.98 0.09%
b. Tulangan besi polos 4.48 kg 21,091.35 94,489.25 0.05%
c. Pemasangan bekisting lantai 1.16 m2 189,200.00 219,472.00 0.12%
SUB TOTAL D 2,140,485.25
E PEKERJAAN RESAPAN
a Galian tanah 2.16 m3 76,320.00 164,851.20 0.09%
b. Pasangan Dinding 6.60 m2 287,698.84 1,898,812.34 1.05%
Atap
a. Beton camp 1pc : 2psr : 3 krl 0.22 m3 1,117,939.85 241,475.01 0.13%
b. Tulangan besi polos 4.48 21,091.35 94,489.25 0.05%
c. Pemasangan bekisting lantai 0.15 m3 189,200.00 28,380.00 0.02%
SUB TOTAL D 2,428,007.80
F PEKERJAAN LAIN LAIN
1 Pemasangan dudukan media filter
0.14 m3 1,058,584.40 148,201.82 0.08%
2 Pemasangan media filter
2.43 m3 1,800,000.00 4,374,000.00 2.43%
3 Pemasangan inflow dan outflow pipa PVC tipe AW
dia. 4" 8.00 m 38,748.30 309,986.40 0.17%
4 Pemasangan penghubung antar bak pipa PVC tipe AW
dia.4" 7.50 m 38,748.30 290,612.25 0.16%
5 Pemasangan Tee PVC tipe AW dia.4" 7.00 bh 37,084.10 259,588.70 0.14%
6 Pemasangan penghubung antar bak inlet dengan bak
settler pipa PVC tipe AW dia.3" 1.50 m 88,992.30 133,488.45 0.07%
7 Pemasangan sirkulasi antar bak pipa PVC tipe AW
dia. 2" 2.00 m 52,120.20 104,240.40 0.06%
8 Pemasangan vent pipa Galvanish dia. 1" 1.00 bh 400,000.00 400,000.00 0.22%
9 Tutup Manhole plat bordes t = 2 mm (lengkap dengan
kait dan cat anti karat) 7.00 bh 310,000.00 2,170,000.00 1.20%
10 Floating Clorin feeder (pengumpan klorin apung) 1.00 unit 125,000.00 125,000.00 0.07%
11 Khlorin Tablet 1.00 kg 10,000.00 10,000.00 0.01%
SUB TOTAL E 8,325,118.02
G COMISSIONING TEST 0.00%
1 Uji Aliran Bak IPL 1.00 ls 200,000.00 200,000.00 0.11%
2 Uji Kebocoran Bak IPL 1.00 ls 200,000.00 200,000.00 0.11%
SUB TOTAL F 400,000.00

180,111,667.77 100.00% 0.00% 0.21% 0.21%

PROGRESS REALISASI 0.21%


PROGRESS RENCANA 38%
DEVIASI -37.79%
DAFTAR ANALISA HARGA SATUAN

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA PENDIDIKAN KEAGAMAAN (LPK) LOKASI 4

PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA


LOKASI : PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

Nama Item Pekerjaan : (K3) Pembersihan 1 m2 lapangan dan perataan


Kode : A.2.2.1.9.
Satuan : m2
Acuan : Permen PUPR 28-2016-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.1000 80,000.00 8,000.00
2 Tukang Batu Org / Hari 85,000.00 -
1 Kepala Tukang Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 8,000.00
II BAHAN
SUB TOTAL BAHAN -
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 8,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 480.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 8,480.00

Nama Item Pekerjaan : Pengukuran dan pemasangan 1 m’ Bouwplank


Kode : A.1.1.d (c)
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.1000 80,000.00 8,000.00
3 Tukang Kayu L.02.04 Org / Hari 0.1000 85,000.00 8,500.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 16,500.00
II BAHAN
25 Tiang Perancah ( Dolken ) Btg 0.1200 14,250.00 1,710.00
43 Paku Kg 0.0200 27,500.00 550.00
24 Kayu Kelas III M3 0.0070 2,500,000.00 17,500.00
SUB TOTAL BAHAN 19,760.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 36,260.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,175.60
VI HARGA SATUAN PEKERJAAN ( IV + V ) 38,435.60

Nama Item Pekerjaan : Penggalian 1m3 Tanah Biasa sedalam lebih dari 1 s/d 2m untuk volume s.d 200 m3
Kode : 1.7.7.1.1.e.(a)
Satuan : m3
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.9000 80,000.00 72,000.00
2 Tukang Batu Org / Hari 85,000.00 -
1 Kepala Tukang Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 72,000.00
II BAHAN
SUB TOTAL BAHAN -
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 72,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 4,320.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 76,320.00
Nama Item Pekerjaan : Pengurugan 1 m3 dengan pasir urug
Kode : A.1.7.2.d.
Satuan : m3
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.3000 80,000.00 24,000.00
2 Tukang Batu Org / Hari 85,000.00 -
1 Kepala Tukang Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 24,000.00
II BAHAN
15 Pasir Urug M3 1.2000 155,000.00 186,000.00
SUB TOTAL BAHAN 186,000.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 210,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 12,600.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 222,600.00

Nama Item Pekerjaan : Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP
Kode : A.2.1.2.a.4.b.(c)
Satuan : m3 bata
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 1.5000 80,000.00 120,000.00
2 Tukang Batu L.02.03 Org / Hari 0.7500 85,000.00 63,750.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 183,750.00
II BAHAN
12 Batu Kali / Gunung M3 1.2000 208,000.00 249,600.00
31 Semen Portland Kg 136.0000 1,350.00 183,600.00
13 Pasir Pasang M3 0.5440 218,000.00 118,592.00
SUB TOTAL BAHAN 551,792.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 735,542.00
V OVERHEAD DAN PROFIT < 15 % 6% 44,132.52
VI HARGA SATUAN PEKERJAAN ( IV + V ) 779,674.52

Nama Item Pekerjaan : Pemasangan 1 m3 pondasi rolag


Kode : -
Satuan : m3
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 1.9600 80,000.00 156,800.00
2 Tukang Batu L.01.01 Org / Hari 0.6500 85,000.00 55,250.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 212,050.00
II BAHAN
31 Semen Portland Kg 63.3100 1,350.00 85,468.50
13 Pasir Pasang M3 0.2900 218,000.00 63,220.00
17 Batu Bata Bh 457.000 3,100.00 1,416,700.00
SUB TOTAL BAHAN 1,565,388.50
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 1,777,438.50
V OVERHEAD DAN PROFIT < 15 % 6% 106,646.31
VI HARGA SATUAN PEKERJAAN ( IV + V ) 1,884,084.81
*Catatan : analisa koef pas bata 1/2 bata merah 1 sp : 5 pp dikali koef 6.54, angka koef ini didapatkan dari hasil
kebutuhan bata 1 m3 dibagi kebutuhan 1 m2
Nama Item Pekerjaan : Pembuatan 1m3 Beton Mutu Fc = 7,4 Mpa (K100)
Kode : A.4.1.1.1
Satuan : m3
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 1.6500 80,000.00 132,000.00
2 Tukang Batu L.02 Org / Hari 0.2750 85,000.00 23,375.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 155,375.00
II BAHAN
31 Semen Portland Kg 247.0000 1,350.00 333,450.00
14 Pasir Beton M3 0.6207 218,000.00 135,315.71
16 Batu split M3 0.740 367,500.00 271,950.00
102 Air Ltr 215.000 22.00 4,730.00
SUB TOTAL BAHAN 745,445.71
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 900,820.71
V OVERHEAD DAN PROFIT < 15 % 6% 54,049.24
VI HARGA SATUAN PEKERJAAN ( IV + V ) 954,869.96
*Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

Nama Item Pekerjaan : Pembuatan 1 m3 Beton Mutu F'c = 14,5 Mpa (K 175) slump (12 ±2) cm, w/c = 0,66
Kode : A.4.1.1.5.
Satuan : m3
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 1.6500 80,000.00 132,000.00
2 Tukang Batu L.02 Org / Hari 0.2750 85,000.00 23,375.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 155,375.00
II BAHAN
31 Semen Portland Kg 326.0000 1,350.00 440,100.00
14 Pasir Beton M3 0.5429 218,000.00 118,342.86
16 Batu split M3 0.762 367,500.00 280,116.67
102 Air Ltr 215.000 22.00 4,730.00
SUB TOTAL BAHAN 843,289.52
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 998,664.52
V OVERHEAD DAN PROFIT < 15 % 6% 59,919.87
VI HARGA SATUAN PEKERJAAN ( IV + V ) 1,058,584.40
*Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

Nama Item Pekerjaan : Pembuatan 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58
Kode : A.4.1.1.7.
Satuan : m3
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 1.6500 80,000.00 132,000.00
2 Tukang Batu L.02 Org / Hari 0.2750 85,000.00 23,375.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 155,375.00
II BAHAN
31 Semen Portland Kg 371.0000 1,350.00 500,850.00
14 Pasir Beton M3 0.4986 218,000.00 108,688.57
16 Batu split M3 0.776 367,500.00 285,016.67
102 Air Ltr 215.000 22.00 4,730.00
SUB TOTAL BAHAN 899,285.24
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 1,054,660.24
V OVERHEAD DAN PROFIT < 15 % 6% 63,279.61
VI HARGA SATUAN PEKERJAAN ( IV + V ) 1,117,939.85
*Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
Nama Item Pekerjaan : Penulangan 100 kg dengan besi Polos atau Besi Sirip
Kode : A.2.2.6.1.b.(c)
Satuan : kg
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0070 80,000.00 560.00
4 Tukang Besi L.02.03 Org / Hari 0.0070 85,000.00 595.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 1,155.00
II BAHAN
35 Besi Beton (Polos/Ulir) Kg 1.0500 17,400.00 18,270.00
39 Kawat Beton / Benrad Kg 0.0150 31,500.00 472.50

SUB TOTAL BAHAN 18,742.50


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 19,897.50
V OVERHEAD DAN PROFIT < 15 % 6% 1,193.85
VI HARGA SATUAN PEKERJAAN ( IV + V ) 21,091.35
*Catatan : analisa dibagi 100 sbg dasar mata pembayaran /kg

Nama Item Pekerjaan : Pemasangan 1 m2 Bekisting untuk sloof Bangunan Gedung


Kode : A.4.1.1.19
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 0.5200 80,000.00 41,600.00
3 Tukang Kayu L.02 Org / Hari 0.2600 85,000.00 22,100.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 63,700.00
II BAHAN
24 Kayu Kelas III M3 0.0450 2,500,000.00 112,500.00
43 Paku Kg 0.3000 27,500.00 8,250.00
26 Minyak bekisting Liter 0.1000 11,000.00 1,100.00

SUB TOTAL BAHAN 121,850.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 185,550.00
V OVERHEAD DAN PROFIT < 15 % 6% 11,133.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 196,683.00
2x pakai bahan 124,625.00

Nama Item Pekerjaan : Pemasangan 1 m2 bekisting untuk Kolom Beton Bangunan Gedung
Kode : A.4.1.1.20
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.6600 80,000.00 52,800.00
3 Tukang Kayu L.02.03 Org / Hari 0.3300 85,000.00 28,050.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 80,850.00
II BAHAN
24 Kayu Kelas III M3 0.0400 2,500,000.00 100,000.00
43 Paku Kg 0.4000 27,500.00 11,000.00
26 Minyak bekisting Liter 0.2000 11,000.00 2,200.00
23 Papan/ Kayu Bekisting M3 0.0150 1,200,000.00 18,000.00
28 Multiplek tebal 0,9 cm lembar 125,000.00 -
25 Tiang Perancah ( Dolken ) Btg 2.0000 14,250.00 28,500.00
SUB TOTAL BAHAN 159,700.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 240,550.00
V OVERHEAD DAN PROFIT < 15 % 6% 14,433.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 254,983.00
2x pakai bahan 160,700.00
Nama Item Pekerjaan : Pemasangan 1 m2 bekisting untuk Balok Bangunan Gedung
Kode : A.4.1.1.21
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.6600 80,000.00 52,800.00
3 Tukang Kayu L.02.03 Org / Hari 0.3300 85,000.00 28,050.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 80,850.00
II BAHAN
24 Kayu Kelas III M3 0.0400 2,500,000.00 100,000.00
43 Paku Kg 0.4000 27,500.00 11,000.00
26 Minyak bekisting Liter 0.2000 11,000.00 2,200.00
23 Papan/ Kayu Bekisting M3 0.0180 1,200,000.00 21,600.00
28 Multiplek tebal 0,9 cm lembar 125,000.00 -
25 Tiang Perancah ( Dolken ) Btg 2.0000 14,250.00 28,500.00
SUB TOTAL BAHAN 163,300.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 244,150.00
V OVERHEAD DAN PROFIT < 15 % 6% 14,649.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 258,799.00
2x pakai bahan 162,500.00

Nama Item Pekerjaan : Pemasangan 1 m2 bekisting untuk Plat Lantai Beton Bangunan Gedung
Kode : A.4.1.1.22
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.6600 80,000.00 52,800.00
3 Tukang Kayu L.02.03 Org / Hari 0.3300 85,000.00 28,050.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 80,850.00
II BAHAN
24 Kayu Kelas III M3 0.0400 2,500,000.00 100,000.00
43 Paku Kg 0.4000 27,500.00 11,000.00
26 Minyak bekisting Liter 0.2000 11,000.00 2,200.00
23 Papan/ Kayu Bekisting M3 0.0150 1,200,000.00 18,000.00
28 Multiplek tebal 0,9 cm lembar 125,000.00 -
25 Tiang Perancah ( Dolken ) Btg 6.0000 14,250.00 85,500.00
SUB TOTAL BAHAN 216,700.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 297,550.00
V OVERHEAD DAN PROFIT < 15 % 6% 17,853.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 315,403.00
2x pakai bahan 189,200.00

Nama Item Pekerjaan : (K3) Pemasangan 1 m2 bekisting untuk dinding


Kode : A.4.1.1.23
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.6600 80,000.00 52,800.00
3 Tukang Kayu L.02.03 Org / Hari 0.3300 85,000.00 28,050.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 80,850.00
II BAHAN
24 Kayu Kelas III M3 0.0300 2,500,000.00 75,000.00
43 Paku Kg 0.4000 27,500.00 11,000.00
26 Minyak bekisting Liter 0.2000 11,000.00 2,200.00
23 Papan/ Kayu Bekisting M3 0.0200 1,200,000.00 24,000.00
28 Multiplek tebal 0,9 cm lembar 0.3500 125,000.00 43,750.00
25 Tiang Perancah ( Dolken ) Btg 3.0000 14,250.00 42,750.00
29 Formtie/penjaga jarak bekesting/spacer buah 3.0000 11,000.00 33,000.00
SUB TOTAL BAHAN 231,700.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 312,550.00
V OVERHEAD DAN PROFIT < 15 % 6% 18,753.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 331,303.00
2x pakai bahan 196,700.00
Nama Item Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1 SP :6 PP
Kode : A.4.4.1.11
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 0.3000 80,000.00 24,000.00
2 Tukang Batu L.02 Org / Hari 0.1000 85,000.00 8,500.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 32,500.00
II BAHAN
17 Batu Bata Bh 70.0000 3,100.00 217,000.00
31 Semen Portland Kg 8.3200 1,350.00 11,232.00
13 Pasir Pasang M3 0.0490 218,000.00 10,682.00

SUB TOTAL BAHAN 238,914.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 271,414.00
V OVERHEAD DAN PROFIT < 15 % 6% 16,284.84
VI HARGA SATUAN PEKERJAAN ( IV + V ) 287,698.84

Nama Item Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


Kode : A.4.4.2.19.
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 0.1500 80,000.00 12,000.00
2 Tukang Batu L.02 Org / Hari 0.0750 85,000.00 6,375.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 18,375.00
II BAHAN
31 Semen Portland Kg 5.1840 1,350.00 6,998.40
13 Pasir Pasang M3 0.0260 218,000.00 5,668.00

SUB TOTAL BAHAN 12,666.40


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 31,041.40
V OVERHEAD DAN PROFIT < 15 % 6% 1,862.48
VI HARGA SATUAN PEKERJAAN ( IV + V ) 32,903.88

Nama Item Pekerjaan : Pemasangan 1 m2 acian.


Kode : 3.2.2.c
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 0.2000 80,000.00 16,000.00
2 Tukang Batu L.02 Org / Hari 0.1000 85,000.00 8,500.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 24,500.00
II BAHAN
31 Semen Portland Kg 3.2500 1,350.00 4,387.50

SUB TOTAL BAHAN 4,387.50


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 28,887.50
V OVERHEAD DAN PROFIT < 15 % 6% 1,733.25
VI HARGA SATUAN PEKERJAAN ( IV + V ) 30,620.75
Nama Item Pekerjaan : Pemasangan 1m2 Lantai Keramik Ukuran 20cm x 20cm
Kode : A.4.4.3.35.
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.7000 80,000.00 56,000.00
2 Tukang Batu L.02.03 Org / Hari 0.3500 85,000.00 29,750.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 85,750.00
II BAHAN
19 Keramik Ukuran 20 x 20 Doos 1.0500 67,500.00 70,875.00
31 Semen Portland Kg 10.4000 1,350.00 14,040.00
13 Pasir Pasang M3 0.0450 218,000.00 9,810.00
32 Semen Warna ( 40 Kg ) Kg 0.5000 20,000.00 10,000.00
SUB TOTAL BAHAN 104,725.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 190,475.00
V OVERHEAD DAN PROFIT < 15 % 6% 11,428.50
VI HARGA SATUAN PEKERJAAN ( IV + V ) 201,903.50

Nama Item Pekerjaan : Pemasangan 1 m2 dinding keramik 20cm x 25cm


Kode : A.4.4.3.53.
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 0.9000 80,000.00 72,000.00
2 Tukang Batu L.02 Org / Hari 0.4500 85,000.00 38,250.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 110,250.00
II BAHAN
20 Keramik Ukuran 20 x 25 Doos 1.3000 82,500.00 107,250.00
31 Semen Portland Kg 9.3000 1,350.00 12,555.00
13 Pasir Pasang M3 0.0180 218,000.00 3,924.00
32 Semen Warna ( 40 Kg ) Zak 0.0485 800,000.00 38,800.00
SUB TOTAL BAHAN 162,529.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 272,779.00
V OVERHEAD DAN PROFIT < 15 % 6% 16,366.74
VI HARGA SATUAN PEKERJAAN ( IV + V ) 289,145.74

Nama Item Pekerjaan : Pemasangan 1 m2 Waterproofing


Kode : -
Satuan : m2
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0150 80,000.00 1,200.00
7 Tukang Cat L.02.03 Org / Hari 0.1500 85,000.00 12,750.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 13,950.00
II BAHAN
33 Waterproofing cementitious Kg 0.4500 27,000.00 12,150.00

SUB TOTAL BAHAN 12,150.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 26,100.00
V OVERHEAD DAN PROFIT < 15 % 6% 1,566.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 27,666.00
Nama Item Pekerjaan : Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”
Kode : A.5.1.1. 26.
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01 Org / Hari 0.0360 80,000.00 2,880.00
5 Tukang Pipa L.02 Org / Hari 0.0600 85,000.00 5,100.00
1 Kepala Tukang L.03 Org / Hari 100,000.00 -
10 Mandor L.04 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 7,980.00
II BAHAN
95 Pipa PVC AW 3/4" m 1.2000 10,500.00 12,600.00

SUB TOTAL BAHAN 12,600.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 20,580.00
V OVERHEAD DAN PROFIT < 15 % 6% 1,234.80
VI HARGA SATUAN PEKERJAAN ( IV + V ) 21,814.80

Nama Item Pekerjaan : Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”


Kode : A.5.1.1 25.
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0360 80,000.00 2,880.00
5 Tukang Pipa L.02.03 Org / Hari 0.0600 85,000.00 5,100.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 7,980.00
II BAHAN
79 Pipa PVC Dia 1/2" ( AW ) m 1.2000 15,000.00 18,000.00

SUB TOTAL BAHAN 18,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 25,980.00
V OVERHEAD DAN PROFIT < 15 % 6% 1,558.80
VI HARGA SATUAN PEKERJAAN ( IV + V ) 27,538.80

Nama Item Pekerjaan : Pemasangan 1 m’ pipa PVC tipe AW diameter 3”


Kode : A.5.1.1 31.
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0810 80,000.00 6,480.00
5 Tukang Pipa L.02.03 Org / Hari 0.1350 85,000.00 11,475.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 17,955.00
II BAHAN
92 Pipa PVC tipe AW Ø 3" panjang 4 m m 1.2000 55,000.00 66,000.00

SUB TOTAL BAHAN 66,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 83,955.00
V OVERHEAD DAN PROFIT < 15 % 6% 5,037.30
VI HARGA SATUAN PEKERJAAN ( IV + V ) 88,992.30
Nama Item Pekerjaan : Pemasangan 1 m’ pipa PVC tipe AW diameter 2”
Kode : A.5.1.1 29.
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0540 80,000.00 4,320.00
5 Tukang Pipa L.02.03 Org / Hari 0.0900 85,000.00 7,650.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 11,970.00
II BAHAN
93 Pipa PVC tipe AW Ø 2" panjang 4 m m 1.2000 31,000.00 37,200.00

SUB TOTAL BAHAN 37,200.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 49,170.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,950.20
VI HARGA SATUAN PEKERJAAN ( IV + V ) 52,120.20

Nama Item Pekerjaan : Grill Besi


Kode : -
Satuan : Unit
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.3920 80,000.00 31,360.00
7 Tukang Cat L.02.03 Org / Hari 0.2700 85,000.00 22,950.00
6 Tukang Las L.03.01 Org / Hari 2.1200 85,000.00 180,200.00
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 234,510.00
II BAHAN
40 Profil besi siku L.40.40.4 Kg 30.2371 17,400.00 526,124.93
38 Besi Beton panjang 12 meter dia 16 Kg 24.1393 17,400.00 420,024.08
59 Cat Menie (Minyak) Kg 0.0873 27,000.00 2,356.56
46 Kawat las bh 24.0000 5,500.00 132,000.00
SUB TOTAL BAHAN 1,080,505.58
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 1,315,015.58
V OVERHEAD DAN PROFIT < 15 % 6% 78,900.93
VI HARGA SATUAN PEKERJAAN ( IV + V ) 1,393,916.51

Nama Item Pekerjaan : Pemasangan 1 m2 penutup atap


Kode : -
Satuan : m2
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.1200 80,000.00 9,600.00
3 Tukang Kayu L.02.03 Org / Hari 0.0600 85,000.00 5,100.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 14,700.00
II BAHAN
52 Atap Spandek berpasir M2 1.0500 100,000.00 105,000.00
53 Screw Cteks 12-4 x 50 bh 6.0000 825.00 4,950.00
54 Screw Cteks 10 x 16 -16 bh 2.0000 825.00 1,650.00

SUB TOTAL BAHAN 111,600.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 126,300.00
V OVERHEAD DAN PROFIT < 15 % 6% 7,578.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 133,878.00
Nama Item Pekerjaan : Lisplank GRC
Kode : -
Satuan : m
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.1000 80,000.00 8,000.00
3 Tukang Kayu L.02.03 Org / Hari 0.2000 85,000.00 17,000.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 25,000.00
II BAHAN
55 GRC plank tebal 10 mm lebar 10 cm panjang 2,4 m btg 0.4368 65,000.00 28,392.00
62 Cat Penutup (Tembok dan Plafond) Kg 0.0520 85,000.00 4,420.00

SUB TOTAL BAHAN 32,812.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 57,812.00
V OVERHEAD DAN PROFIT < 15 % 6% 3,468.72
VI HARGA SATUAN PEKERJAAN ( IV + V ) 61,280.72

Nama Item Pekerjaan : Pemasangan Pintu Aluminium Strip Lebar 8 cm (Komplit)


Kode : A.4. 2. 1. 25
Satuan : bh
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0850 80,000.00 6,800.00
3 Tukang Khusus Aluminium L.02.03 Org / Hari 0.0850 85,000.00 7,225.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 14,025.00
II BAHAN
71 Pintu Alumunium Strip Kamar Mandi Bh 1.0000 700,000.00 700,000.00

SUB TOTAL BAHAN 700,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 714,025.00
V OVERHEAD DAN PROFIT < 15 % 6% 42,841.50
VI HARGA SATUAN PEKERJAAN ( IV + V ) 756,866.50

Nama Item Pekerjaan : Bouvenlicht kisi-kisi Besi hollo 2 x2 cm finish cat


Kode : -
Satuan : m2
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.2800 80,000.00 22,400.00
6 Tukang Las L.02.03 Org / Hari 0.9500 85,000.00 80,750.00
7 Tukang Cat L.03.01 Org / Hari 0.2000 85,000.00 17,000.00
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 120,150.00
II BAHAN
42 Profil besi hollow Kg 7.5800 16,000.00 121,280.00
59 Cat Menie (Minyak) Kg 0.1000 27,000.00 2,700.00
46 Kawat las bh 17.0000 5,500.00 93,500.00
SUB TOTAL BAHAN 217,480.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 337,630.00
V OVERHEAD DAN PROFIT < 15 % 6% 20,257.80
VI HARGA SATUAN PEKERJAAN ( IV + V ) 357,887.80
Nama Item Pekerjaan : Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Kode : 3.3.10.c
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0200 80,000.00 1,600.00
7 Tukang Cat L.02.03 Org / Hari 0.0630 85,000.00 5,355.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 6,955.00
II BAHAN
57 Plamuur Kg 0.1000 50,000.00 5,000.00
60 Cat Dasar (Tembok) Kg 0.1000 27,000.00 2,700.00
61 Cat Penutup (Minyak) Kg 0.2600 85,000.00 22,100.00
SUB TOTAL BAHAN 29,800.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 36,755.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,205.30
VI HARGA SATUAN PEKERJAAN ( IV + V ) 38,960.30

Nama Item Pekerjaan : Pemasangan 1 buah closet jongkok porslen


Kode : A.5.1.1 3.
Satuan : bh
Acuan : Permen PUPR 28-2016-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 1.000 80,000.00 80,000.00
2 Tukang Batu L.02.03 Org / Hari 1.500 85,000.00 127,500.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 207,500.00
II BAHAN
65 Kloset Jongkok Bh 1.0000 350,000.00 350,000.00
31 Semen Portland Kg 6.0000 1,350.00 8,100.00
13 Pasir Pasang M3 0.0100 218,000.00 2,180.00
SUB TOTAL BAHAN 360,280.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 567,780.00
V OVERHEAD DAN PROFIT < 15 % 6% 34,066.80
VI HARGA SATUAN PEKERJAAN ( IV + V ) 601,846.80

Nama Item Pekerjaan : Pemasangan 1 buah kran diameter ½” atau 3/4”


Kode : A.5.1.1 35.
Satuan : bh
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0100 80,000.00 800.00
2 Tukang Batu L.02.03 Org / Hari 0.4000 85,000.00 34,000.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 34,800.00
II BAHAN
66 Kran Air dia 3/4" tipe tuas Bh 1.0000 74,500.00 74,500.00
97 Sealtape Bh 0.0250 5,500.00 137.50

SUB TOTAL BAHAN 74,637.50


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 109,437.50
V OVERHEAD DAN PROFIT < 15 % 6% 6,566.25
VI HARGA SATUAN PEKERJAAN ( IV + V ) 116,003.75
Nama Item Pekerjaan : Pemasangan head shower lengkap dengan Kran Ganda
Kode : -
Satuan : Unit
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.2000 80,000.00 16,000.00
2 Tukang Batu L.02.03 Org / Hari 0.2000 85,000.00 17,000.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 33,000.00
II BAHAN
67 Head shower tanam Lengkap dengan kran ganda bh 1.0000 300,000.00 300,000.00

SUB TOTAL BAHAN 300,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 333,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 19,980.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 352,980.00

Nama Item Pekerjaan : Pemasangan 1 buah floor drain


Kode : A.5.1.1 36.
Satuan : bh
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0100 80,000.00 800.00
2 Tukang Batu L.02.03 Org / Hari 0.1000 85,000.00 8,500.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 9,300.00
II BAHAN
69 Saringan Floordrain 10x10 cm steinless steel Bh 1.0000 32,000.00 32,000.00

SUB TOTAL BAHAN 32,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 41,300.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,478.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 43,778.00

Nama Item Pekerjaan : Pemasangan Tempat Sabun


Kode : -
Satuan : bh
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.1250 80,000.00 10,000.00
2 Tukang Batu L.02.03 Org / Hari 0.1250 85,000.00 10,625.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 20,625.00
II BAHAN
68 Tempat sabun bh 1.0000 50,000.00 50,000.00

SUB TOTAL BAHAN 50,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 70,625.00
V OVERHEAD DAN PROFIT < 15 % 6% 4,237.50
VI HARGA SATUAN PEKERJAAN ( IV + V ) 74,862.50
Nama Item Pekerjaan : Logo PU steinles Steel
Kode : -
Satuan : bh
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.2500 80,000.00 20,000.00
2 Tukang Batu L.02.03 Org / Hari 0.2500 85,000.00 21,250.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 41,250.00
II BAHAN
21 Logo PU Alumunium steel Bh 1.0000 592,000.00 592,000.00
Material Pendukung Ls 0.1500 592,000.00 88,800.00

SUB TOTAL BAHAN 680,800.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 722,050.00
V OVERHEAD DAN PROFIT < 15 % 6% 43,323.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 765,373.00

Nama Item Pekerjaan : Tulisan "Indonesia Maju" Steinless steel


Kode : -
Satuan : set
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.4000 80,000.00 32,000.00
6 Tukang Las L.02.03 Org / Hari 0.4000 85,000.00 34,000.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 66,000.00
II BAHAN
47 Alumunium steel set 1.0000 200,000.00 200,000.00
Material Pendukung Ls 0.1500 200,000.00 30,000.00

SUB TOTAL BAHAN 230,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 296,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 17,760.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 313,760.00

Nama Item Pekerjaan : Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
Kode : A.4.4.1.8
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.3000 80,000.00 24,000.00
2 Tukang Batu L.02.03 Org / Hari 0.1000 85,000.00 8,500.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 32,500.00
II BAHAN
17 Batu Bata Bh 70.0000 3,100.00 217,000.00
31 Semen Portland Kg 14.3700 1,350.00 19,399.50
13 Pasir Pasang M3 0.0400 218,000.00 8,720.00

SUB TOTAL BAHAN 245,119.50


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 277,619.50
V OVERHEAD DAN PROFIT < 5 % 6% 16,657.17
VI HARGA SATUAN PEKERJAAN ( IV + V ) 294,276.67
Nama Item Pekerjaan : Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.
Kode : 3.2.1 (c)
Satuan : m2
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.3000 80,000.00 24,000.00
2 Tukang Batu L.02.03 Org / Hari 0.1500 85,000.00 12,750.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 36,750.00
II BAHAN
31 Semen Portland Kg 7.7760 1,350.00 10,497.60
13 Pasir Pasang M3 0.0230 218,000.00 5,014.00

SUB TOTAL BAHAN 15,511.60


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 52,261.60
V OVERHEAD DAN PROFIT < 15 % 6% 3,135.70
VI HARGA SATUAN PEKERJAAN ( IV + V ) 55,397.30

Nama Item Pekerjaan : Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedalam 1 M
Kode : 1.7.2.a. c
Satuan : m3
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.5000 80,000.00 40,000.00
2 Tukang Batu Org / Hari 85,000.00 -
1 Kepala Tukang Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 40,000.00
II BAHAN
SUB TOTAL BAHAN -
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 40,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,400.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 42,400.00

Nama Item Pekerjaan : Pemasangan 1 m’ pipa PVC tipe AW diameter 4”


Kode : A.5.1.1 32.
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0810 80,000.00 6,480.00
5 Tukang Pipa L.02.03 Org / Hari 0.1350 85,000.00 11,475.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 17,955.00
II BAHAN
88 Pipa PVC Dia 4" ( Biasa/D) m 1.2000 15,500.00 18,600.00

SUB TOTAL BAHAN 18,600.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 36,555.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,193.30
VI HARGA SATUAN PEKERJAAN ( IV + V ) 38,748.30
Nama Item Pekerjaan : Pemasangan 1 buah Tee Ø 100 mm
Kode : 4. 3. 15. c
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP Lampiran Bagian 1 Umum

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.1060 80,000.00 8,480.00
5 Tukang Pipa L.02.03 Org / Hari 0.0530 85,000.00 4,505.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 12,985.00
II BAHAN
91 Tee pipa PVC diameter 4” m 1.0000 22,000.00 22,000.00

SUB TOTAL BAHAN 22,000.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 34,985.00
V OVERHEAD DAN PROFIT < 15 % 6% 2,099.10
VI HARGA SATUAN PEKERJAAN ( IV + V ) 37,084.10

Nama Item Pekerjaan : Pemasangan 1 m’ pipa PVC tipe AW diameter 1”


Kode : A.5.1.1 27.
Satuan : m
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0360 80,000.00 2,880.00
5 Tukang Pipa L.02.03 Org / Hari 0.0600 85,000.00 5,100.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 7,980.00
II BAHAN
94 Pipa PVC tipe AW Ø 1" panjang 4 m m 1.2000 13,500.00 16,200.00

SUB TOTAL BAHAN 16,200.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 24,180.00
V OVERHEAD DAN PROFIT < 15 % 6% 1,450.80
VI HARGA SATUAN PEKERJAAN ( IV + V ) 25,630.80

Nama Item Pekerjaan : Pemasangan 1 m2 Rangka Atap Baja Ringan


Kode : -
Satuan : m2
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.2000 80,000.00 16,000.00
4 Tukang Besi L.02.03 Org / Hari 0.4500 85,000.00 38,250.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 54,250.00
II BAHAN
50 Canal C.75.75 M' 3.2000 17,500.00 56,000.00
51 Reng R.34 M' 3.0000 10,000.00 30,000.00
53 Screw Cteks 12-4 x 50 bh 4.0000 825.00 3,300.00

SUB TOTAL BAHAN 89,300.00


III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 143,550.00
V OVERHEAD DAN PROFIT < 15 % 6% 8,613.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 152,163.00
Nama Item Pekerjaan : Pemasangan 1 Buah Titik Lampu
Kode : A.6. 2. 1. 1.
Satuan : bh
Acuan : Permen PUPR Nomor 1-2022-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 80,000.00 -
8 Tukang Listrik L.02.03 Org / Hari 0.3500 85,000.00 29,750.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 29,750.00
II BAHAN
73 Pipa Listrik 5/8" btg 0.2830 20,000.00 5,660.00
85 Kabel NYM 3x2,5 mm2 m 3.0000 13,000.00 39,000.00
74 Tee Doos bh 3.0000 2,200.00 6,600.00
75 L.Bow bh 4.0000 1,650.00 6,600.00
76 Las Dop bh 3.0000 8,250.00 24,750.00
77 Klem Pipa Listrik bh 24.0000 1,100.00 26,400.00
78 Mangkok (Listrik) Inbow Dus bh 1.0000 3,850.00 3,850.00

84
82
SUB TOTAL BAHAN 112,860.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 142,610.00
V OVERHEAD DAN PROFIT < 15 % 6% 8,556.60
VI HARGA SATUAN PEKERJAAN ( IV + V ) 151,166.60

Nama Item Pekerjaan : Pek. Pemasangan lampu tempel plafond fitting lampu kotak
Kode :
Satuan : bh
Acuan :

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0330 80,000.00 2,640.00
8 Tukang Listrik L.02.03 Org / Hari 0.0560 85,000.00 4,760.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 7,400.00
II BAHAN
73 Lampu Tempel Plafon bh 1.0000 78,000.00 78,000.00
85 Material Pendukung Ls 1.0000 11,700.00 11,700.00
74 -
75 -
76 -
77 -
78 -
84 -
82 -
SUB TOTAL BAHAN 89,700.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 97,100.00
V OVERHEAD DAN PROFIT < 15 % 6% 5,826.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 102,926.00

Nama Item Pekerjaan : Pek. Pemasangan Sakelar


Kode :
Satuan : bh
Acuan :

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.0280 80,000.00 2,240.00
8 Tukang Listrik L.02.03 Org / Hari 0.0560 85,000.00 4,760.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 7,000.00
II BAHAN
73 Saklar (standar) bh 1.0000 22,000.00 22,000.00
85 Material Pendukung Ls 0.3000 3,300.00 990.00
74 -
75 -
76 -
77 -
78 -
84 Saklar (standar) -
82 -
SUB TOTAL BAHAN 22,990.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 29,990.00
V OVERHEAD DAN PROFIT < 15 % 6% 1,799.40
VI HARGA SATUAN PEKERJAAN ( IV + V ) 31,789.40
Nama Item Pekerjaan : Membuat 1 m’ ring balok beton bertulang (10 x 15) cm
Kode : A.4.1.1.36
Satuan : m
Acuan : Permen PUPR 28-2016-AHSP bidang cipta karya

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.2970 80,000.00 23,760.00
2 Tukang Batu L.02.03 Org / Hari 0.0330 85,000.00 2,805.00
3 Tukang Kayu L.02.03 Org / Hari 0.0330 85,000.00 2,805.00
4 Tukang Besi L.02.03 Org / Hari 0.0330 85,000.00 2,805.00
1 Kepala Tukang L.03.01 Org / Hari 100,000.00 -
10 Mandor L.04.01 Org / Hari 120,000.00 -
SUB TOTAL TENAGA 32,175.00
II BAHAN
24 Kayu Kelas III M3 0.0030 2,500,000.00 7,500.00
43 Paku Kg 0.0200 27,500.00 550.00
26 Minyak bekisting Liter 1.2000 11,000.00 13,200.00
35 Besi Beton Kg 3.6000 17,400.00 62,640.00
39 Kawat Beton Kg 0.0500 31,500.00 1,575.00
31 Semen Portland Kg 5.5000 1,350.00 7,425.00
14 Pasir Beton M3 0.0090 218,000.00 1,962.00
16 Batu split M3 0.0150 367,500.00 5,512.50
SUB TOTAL BAHAN 100,364.50
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 132,539.50
V OVERHEAD DAN PROFIT < 15 % 6% 7,952.37
VI HARGA SATUAN PEKERJAAN ( IV + V ) 140,491.87

Nama Item Pekerjaan : Instalasi WLC


Kode : -
Satuan : titik
Acuan : -

HARGA SATUAN JUMLAH HARGA


NO URAIAN KODE SAT KOEF
( Rp ) ( Rp )
I TENAGA
9 Pekerja L.01.01 Org / Hari 0.5000 80,000.00 40,000.00
5 Tukang Pipa L.02.03 Org / Hari 1.0000 85,000.00 85,000.00
SUB TOTAL TENAGA 125,000.00
II BAHAN
100 Water level control bh 1.0000 55,000.00 55,000.00
SUB TOTAL BAHAN 55,000.00
III PERALATAN
SUB TOTAL PERALATAN -
IV JUMLAH ( I + II + III ) 180,000.00
V OVERHEAD DAN PROFIT < 15 % 6% 10,800.00
VI HARGA SATUAN PEKERJAAN ( IV + V ) 190,800.00
DAFTAR HARGA UPAH DAN BAHAN

PROYEK : PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA PENDIDIKAN KEAGAMAAN


LOKASI 4
PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA
LOKASI : PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

HARGA SATUAN LOKASI


NO URAIAN SATUAN
( Rp )
1 2 3 4
I UPAH
1 Kepala Tukang Org / Hari 100,000.00
2 Tukang Batu Org / Hari 85,000.00
3 Tukang Kayu Org / Hari 85,000.00
4 Tukang Besi Org / Hari 85,000.00
5 Tukang Pipa Org / Hari 85,000.00
6 Tukang Las Org / Hari 85,000.00
7 Tukang Cat Org / Hari 85,000.00
8 Tukang Listrik Org / Hari 85,000.00
9 Pekerja Org / Hari 80,000.00
10 Mandor Org / Hari 120,000.00

II. BAHAN
A BAHAN BATU-BATUAN
1 Batu Kali / Gunung M3 208,000.00
2 Pasir Pasang M3 218,000.00
3 Pasir Beton M3 218,000.00
4 Pasir Urug M3 155,000.00
5 Batu Krikil M3 367,500.00
6 Batu Merah Bh 3,100.00
7 Batu Bata Bh 1,300.00
8 Keramik Ukuran 20 x 20 Doos 67,500.00
9 Keramik Ukuran 20 x 25 Doos 82,500.00
10 Logo PU Bh 592,000.00
B BAHAN KAYU
1 Papan/ Kayu Bekisting M3 1,200,000.00
2 Kayu Kelas III M3 2,500,000.00
3 Tiang Perancah ( Dolken ) Btg 14,250.00
4 Minyak bekisting Liter 11,000.00
5 Bambu cerucuk Ø 15 cm panjang 600 cm Batang 11,000.00
6 Multiplek tebal 0,9 cm lembar 125,000.00
7 Formtie/penjaga jarak bekesting/spacer buah 11,000.00
C SEMEN
1 Semen Portland Kg 1,350.00
2 Semen Warna ( 40 Kg ) Zak 800,000.00
3 Waterproofing cementitious Kg 27,000.00
D BAHAN BESI DAN KAWAT
1 Besi Beton panjang 12 meter dia 8 Kg 17,400.00
2 Besi Beton panjang 12 meter dia 10 Kg 17,400.00
3 Besi Beton panjang 12 meter dia 13 Kg 17,400.00
4 Besi Beton panjang 12 meter dia 16 Kg 17,400.00
5 Kawat Beton Kg 31,500.00
6 Profil besi siku L.30.30.3 Kg 17,400.00
7 Profil besi siku L.50.50.5 Kg 17,400.00
8 Profil besi hollow Kg 16,000.00
9 Paku Kg 27,500.00
10 Paku Seng Kg 27,500.00
11 Plat embaded (konekting rangka) bh 29,000.00
12 Kawat las bh 5,500.00
13 Alumunium steel set 200,000.00
HARGA SATUAN LOKASI
NO URAIAN SATUAN
( Rp )
1 2 3 4
E BAHAN ATAP
1 Lem Kayu Kaleng 50,000.00
2 Canal C.75.75 M' 17,500.00
3 Reng Kecil Kencana 0,40 mm M' 10,000.00
4 Atap Spandek warna M2 100,000.00
5 Screw Cteks 12-4 x 50 bh 825.00
6 Screw Cteks 10 x 16 -16 bh 825.00
7 GRC plank tebal 10 mm lebar 10 cm panjang 2,4 m btg 65,000.00
F BAHAN CAT
1 Plamuur Kg 50,000.00
2 Amplas Lbr 10,000.00
3 Cat Menie (Minyak) Kg 27,000.00
4 Cat Dasar (Tembok) Kg 27,000.00
5 Cat Penutup (Minyak) Kg 85,000.00
6 Cat Penutup (Tembok dan Plafond) Kg 85,000.00
7 Pengencer/Minyak Cat Kg 29,700.00
G SANITAIR
1 Kloset Jongkok Bh 350,000.00
2 Kran Air dia 3/4" tipe tuas Bh 74,500.00
3 Head shower tanam Lengkap dengan kran ganda bh 300,000.00
4 Tempat sabun bh 50,000.00
5 Saringan Floordrain 10x10 cm steinless steel Bh 32,000.00
H BAHAN PINTU
1 Pintu Alumunium Kamar Mandi Bh 700,000.00
I BAHAN LISTRIK
1 Pipa Listrik 5/8" btg 20,000.00
2 Tee Doos bh 2,200.00
3 L.Bow bh 1,650.00
4 Las Dop bh 8,250.00
5 Klem Pipa Listrik bh 1,100.00
6 Mangkok (Listrik) Inbow Dus bh 3,850.00
7 Pipa PVC Dia 1/2" ( AW ) Btg 60,000.00
8 MCB + Pemasangan bh 165,000.00
9 Box MCB + Pemasangan bh 130,000.00
10 Lampu 18W + Fitting Lampu bh 78,000.00
11 Isolasi roll 16,500.00
12 Saklar (standar) bh 22,000.00
13 Kabel NYM 3x2,5 mm2 m 13,000.00
J BAHAN PLUMBING
1 Pipa PVC Dia 4" ( Biasa/ D) Btg 62,000.00
2 Pipa PVC Dia 4" ( Biasa/D) m 15,500.00
3 Pipa PVC tipe AW Ø 4" panjang 4 m m 78,000.00
4 Elbow PVC L 90 Derajat Diameter 4" Bh 22,000.00
5 Tee pipa PVC diameter 4” m 22,000.00
6 Socket Pipa PVC 4" m 22,000.00
7 Pipa PVC tipe AW Ø 3" panjang 4 m m 55,000.00
8 Pipa PVC tipe AW Ø 2" panjang 4 m m 31,000.00
9 Pipa PVC tipe AW Ø 1" panjang 4 m m 13,500.00
10 Pipa PVC AW 3/4" m 10,500.00
11 Lem Pipa PVC Bh 33,000.00
12 Sealtape Bh 5,500.00
13 Tangki air fiberglass 1100 liter bh 1,350,000.00
14 Pompa air 250 watt bh 2,200,000.00
15 Menara Air Unit 1,200,000.00
15 Water level control bh 55,000.00
16 Stopkran bh 90,000.00
17 Air Liter 22.00
Time Schedule

PROYEK : PENYEDIAAN SARANA DAN PRASARANA


PENYEDIAAN SARANA DAN PRASARANA SANITASI DI LEMBAGA PENDIDIKAN KEAGAMAAN (LPK) Lokasi 4
PEKERJAAN : PEMBANGUNAN BILIK MCK PRIA PEMBANGUNAN BILIK MCK PRIA
LOKASI : PONPES MIFTAHUDDIN OEEKAM DES PONPES MIFTAHUDDIN OEEKAM DESA OEEKAM, KECAMATAN
: AMANUBAN TIMUR KABUPATEN TIMO
AMANUBAN TIMUR KABUPATEN TIMOR TENGAH SELATAN
TAHUN ANGGARAN : 2022

BULAN I BULAN II BULAN III


JUMLAH HARGA APBN BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13
NO URAIAN PEKERJAAN KET
25-Jul-22 1-Aug-22 8-Aug-22 15-Aug-22 22-Aug-22 29-Aug-22 5-Sep-22 12-Sep-22 19-Sep-22 26-Sep-22 3-Oct-22 10-Oct-22 17-Oct-22
(Rp) (%)
31-Jul-22 7-Aug-22 14-Aug-22 21-Aug-22 28-Aug-22 4-Sep-22 11-Sep-22 18-Sep-22 25-Sep-22 2-Oct-22 9-Oct-22 16-Oct-22 22-Oct-22
1 2 3
I PEKERJAAN PERSIAPAN 2,884,542.12 1.60153 0.380 0.380 0.842
II PEKERJAAN STRUKTUR 46,154,946.07 25.62574 ` 3.661 3.661 3.661 3.661 3.661 3.661 3.661
III PEKERJAAN ARSITEKTUR 59,724,364.10 33.15963 5.527 5.527 5.527 5.527 5.527 5.527
IV PEKERJAAN ELEKTRIKAL DAN PLUMBING 15,139,758.65 8.405762 2.101 2.101 2.101 2.101
V PEKERJAAN IPAL NON-PABRIKASI
A PEKERJAAN TANAH DAN LANDASAN 2,496,563.77 1.38612 1.386
B PEKERJAAN BAK INLET 2,065,701.30 1.1469 1.147
C PEKERJAAN BAK SETLLER & AF 38,352,180.70 21.29356 5.323 5.323 5.323 5.323
D PEKERJAAN BAK DESINFEKTAN 2,140,485.25 1.188421 1.188
E PEKERJAAN RESAPAN 2,428,007.80 1.348057 1.348
F PEKERJAAN LAIN LAIN 8,325,118.02 4.622198 2.311 2.311
G COMISSIONING TEST 400,000.00 0.222084 0.222

TOTAL 180,111,667.77 100


PROGRES RENCANA MINGGUAN (%) 0.380 0.380 0.842 3.661 3.661 9.187 9.187 11.289 13.822 16.612 12.951 10.171 7.857
PROGRES KOMULATIF RENCANA (%) 0.380 0.760 1.602 5.262 8.923 18.111 27.298 38.587 52.409 69.021 81.972 92.143 100.000

PROGRES REALISASI MINGGUAN (%) 0.193


PROGRES KOMULATIF REALISASI (%) 0.200 0.393

-0.367 CV. GASINDO

John Riupassa
Kuasa Direktur