CV GEOPENTRA

REKAP
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM POLDA SULAWESI TENGAH
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022

REKAPITULASI
No URAIAN PEKERJAAN JUMLAH BIAYA PPN (11%) JUMLAH HARGA
A PEKERJAAN KONSTRUKSI GEDUNG :
1 PERSIAPAN Rp 11,103,130.00 Rp 1,221,344.30 Rp 12,324,474.30
2 PEKERJAAN TANAH Rp 34,065,788.68 Rp 3,747,236.75 Rp 37,813,025.43
3 PEKERJAAN STRUKTUR Rp 1,023,240,071.01 Rp 112,556,407.81 Rp 1,135,796,478.82
4 PEKERJAAN ARSITEKTUR Rp 1,095,213,595.45 Rp 120,473,495.50 Rp 1,215,687,090.95
5 PEKERJAAN MEKANIKAL / PLUMBING Rp 341,733,964.70 Rp 37,590,736.12 Rp 379,324,700.81
6 PEKERJAAN ELEKTRKAL Rp 158,761,062.76 Rp 17,463,716.90 Rp 176,224,779.66
SUB JUMLAH A Rp 2,664,117,612.60 Rp 293,052,937.39 Rp 2,957,170,549.99
B PEKERJAAN FASILITAS UMUM (FASUM)
1 PEKERJAAN JALAN DAN LANDSCAPE Rp 33,580,598.88 Rp 3,693,865.88 Rp 37,274,464.75
2 PEKERJAAN SALURAN Rp 212,615,593.87 Rp 23,387,715.33 Rp 236,003,309.20
SUB JUMLAH B Rp 246,196,192.75 Rp 27,081,581.20 Rp 273,277,773.95

JUMLAH TOTAL A + B 3,230,448,323.94


DIBULATKAN Rp 3,230,450,000.00
Terbilang : TIGA MILYAR DUA RATUS TIGA PULUH JUTA EMPAT RATUS LIMA PULUH RIBU RUPIAH

Manado, 27 April 2022


Dibuat Oleh
Kontraktor Pelaksana
CV GEOPENTRA

SYANNE RAWUNG
Direktur
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022

RINCIAN

Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg

PERSIAPAN
I PEKERJAAN PERSIAPAN
1 Standar Biaya Manajemen Kesehatan Dan Keselamatan Kerja Set 1.00 6,103,130.00 6,103,130.00
2 Standar Pek. Direksi Keet luas 12 m2 (Rangka kayu lokal + multipleks 6 mm + Atap seng) lS 1.00 5,000,000.00 5,000,000.00
JUMLAHPEKERJAAN PERSIAPAN 11,103,130.00
TOTAL BIAYA SITE WORK 11,103,130.00
PEKERJAAN TANAH
II.1 PEKERJAAN TANAH
A Pondasi Poer Plat
1 1.5.1.1 Standar Pek. Galian Tanah M3 57.53 69,300.00 3,986,829.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 38.35 23,100.00 885,885.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 2.84 126,720.00 359,884.80
B Pondasi Batu Kali -
1 1.5.1.1 Standar Pek. Galian Tanah M3 23.71 69,300.00 1,643,103.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 6.02 23,100.00 139,062.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 3.53 126,720.00 447,321.60
C Plat lantai 1 -
1 1.5.1.14 Standar Pek. Timbunan Peninggi Lantai M3 215.31 91,300.00 19,657,803.00
2 1.5.1.10 Standar Pek. Urugan Pasir M3 25.53 126,720.00 3,235,161.60
3 1.5.1.10 Standar Pek. Urugan Pasir Rabat Keliling M3 2.97 126,720.00 376,231.68
C Sloof -
1 1.5.1.10 Standar Pek. Urugan Pasir M3 3.30 126,720.00 418,176.00
D Pot Bunga -
1 1.5.1.T6 Standar Pek. Tanah Subur M3 12.15 93,720.00 1,138,698.00
2 T19 Standar Pek. Rumput Gajah Mini M2 20.15 88,220.00 1,777,633.00
JUMLAH PEKERJAAN TANAH 34,065,788.68
PEKERJAAN STRUKTUR
III.1 PEKERJAAN STRUKTUR BAWAH
A Pekerjaan Pondasi Batu Kali
1 3.1.1.3 Standar Pek. Pondasi Batu Kali M3 23.80 703,120.00 16,734,256.00
2 3.1.1.9 Standar Pek. Batu Kosong (Aanstamping) M3 7.10 360,888.00 2,562,304.80
B Pekerjaan Pondasi Poer pLat -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 2.84 795,508.36 2,259,243.74
2 4.1.1.8 Standar Pek. Beton K 250 M3 11.75 1,058,542.89 12,437,878.98
3 4.1.1.15 Standar Pek. Pembesian KG 1340.96 16,100.15 21,589,592.83
4 4.1.1.18a Standar Pek. Bekisting M2 47.00 122,562.00 5,760,414.00
C Pekerjaan Kolom Pedestal 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 3.23 1,058,542.89 3,419,093.54
2 4.1.1.15 Standar Pek. Pembesian KG 1110.49 16,100.15 17,879,047.76
3 4.1.1.18a Standar Pek. Bekisting M2 51.70 122,562.00 6,336,455.40
D Pekerjaan Sloof 25x35 -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 3.30 795,508.36 2,625,177.59
1 4.1.1.8 Standar Pek. Beton K 250 M3 23.78 1,058,542.89 25,172,149.96
2 4.1.1.15 Standar Pek. Pembesian KG 4106.22 16,100.15 66,110,723.79
3 4.1.1.18a Standar Pek. Bekisting M2 190.24 122,562.00 23,316,194.88
JUMLAH PEKERJAAN STRUKTUR BAWAH 206,202,533.26
III.2 PEKERJAAN STRUKTUR LANTAI 1
A Pekerjaan Plat Lantai 1
1 4.1.1.4 Standar Pek. Lantai Kerja M3 26.12 795,508.36 20,778,678.36
2 4.1.1.8 Standar Pek. Beton K 250 M3 37.37 1,058,542.89 39,557,747.86
3 4.1.1.15 Standar Pek. Pembesian KG 1374.20 16,100.15 22,124,813.48
4 4.1.1.4 Standar Pek. Rabat Keliling M3 2.97 795,508.36 2,361,864.32
B Pekerjaan Kolom 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 11.70 1,058,542.89 12,384,951.83
2 4.1.1.15 Standar Pek. Pembesian KG 2323.52 16,100.15 37,409,018.06
3 4.1.1.20a Standar Pek. Bekisting M2 188.00 263,290.50 49,498,614.00
C Pekerjaan Kolom 10x40 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.19 1,058,542.89 201,123.15
2 4.1.1.15 Standar Pek. Pembesian KG 27.53 16,100.15 443,275.72
3 4.1.1.20a Standar Pek. Bekisting M2 3.20 263,290.50 842,529.60
D Pekerjaan Dinding Beton -
1 4.1.1.8 Standar Pek. Beton K 250 M3 27.77 1,058,542.89 29,395,736.10
2 4.1.1.15 Standar Pek. Pembesian KG 2487.93 16,100.15 40,056,104.00
3 4.1.1.23a Standar Pek. Bekisting M2 337.20 359,114.25 121,093,325.10
E Pekerjaan Kolom Praktis dan Balok Praktis -
1 4.1.1.26 Standar Pek. Kolom (Termasuk Bekisting Dan Pembesian) M 135.56 93,522.00 12,677,426.67
2 4.1.1.27 Standar Pek. Balok (Termasuk Bekisting Dan Pembesian) M 118.22 113,740.00 13,446,595.56
F Pekerjaan Meja Beton Ruang Besuk -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.33 1,058,542.89 349,319.15
2 4.1.1.15 Standar Pek. Pembesian KG 32.04 16,100.15 515,820.98
3 4.1.1.22a Standar Pek. Bekisting M2 4.15 321,753.21 1,335,275.81
4 4.4.3.T11 Standar Pek. Keramik Ukuran 40x40 M2 4.15 227,749.50 945,160.43
JUMLAH PEKERJAAN STRUKTUR LANTAI 1 405,417,380.17
III.3 PEKERJAAN STRUKTUR ATAS
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022

RINCIAN

Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
B Pekerjaan Ring Balok 25x25
1 4.1.1.8 Standar Pek. Beton K 250 M3 16.99 1,058,542.89 17,984,643.73
2 4.1.1.15 Standar Pek. Pembesian KG 3744.64 16,100.15 60,289,275.83
3 4.1.1.21a Standar Pek. Bekisting M2 135.92 258,351.96 35,115,198.18
B Pekerjaan Ring Balok 15x20 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 3.14 1,058,542.89 3,323,824.68
2 4.1.1.15 Standar Pek. Pembesian KG 947.02 16,100.15 15,247,202.20
3 4.1.1.21a Standar Pek. Bekisting M2 41.87 258,351.96 10,816,335.32
E Pekerjaan Plat Kanopi -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.51 1,058,542.89 539,856.87
2 4.1.1.15 Standar Pek. Pembesian KG 43.13 16,100.15 694,325.54
3 4.1.1.22a Standar Pek. Bekisting M2 5.95 321,753.21 1,914,431.59
E Pekerjaan Listplank Beton -
1 4.1.1.8 Standar Pek. Beton K 250 M3 1.37 1,058,542.89 1,450,203.76
2 4.1.1.15 Standar Pek. Pembesian KG 447.54 16,100.15 7,205,485.55
3 4.1.1.22a Standar Pek. Bekisting M2 56.68 321,753.21 18,236,971.85
A Pekerjaan Plat Atap -
1 4.1.1.8 Standar Pek. Beton K 250 M3 37.40 1,058,542.89 39,589,504.14
2 4.1.1.15 Standar Pek. Pembesian KG 2950.71 16,100.15 47,506,858.61
3 4.1.1.22a Standar Pek. Bekisting M2 338.80 321,753.21 109,009,986.98
4 T16 Standar Pek. Waterproofing M2 429.27 99,462.00 42,696,052.74
JUMLAH PEKERJAAN STRUKTUR ATAS 411,620,157.58
JUMLAH PEKERJAAN STRUKTUR 1,023,240,071.01
PEKERJAAN ARSITEKTUR
IV,1 PEKERJAAN FINISHING DINDING
A PEKERJAAN FINISHING DINDING LANTAI 1
1 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps M2 875.96 142,175.00 124,539,613.00
2 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps (Area Pot Bunga) M2 23.74 142,175.00 3,375,234.50
3 4.4.2.5 Standar Pek. Plesteran Dinding M2 1514.14 61,753.12 93,502,869.12
4 4.4.2.5 Standar Pek. Plesteran Pondasi Batu Kali M2 14.92 61,753.12 921,356.55
5 4.4.2.27 Standar Pek. Acian M2 1818.22 38,967.50 70,851,487.85
6 4.4.3.55 Standar Pek. Keramik Dinding 20x40 (Km/Wc) M2 34.72 302,738.95 10,511,096.48
7 4.4.1.25a Standar Pek. Keramik Dinding Batu alam Type Palimanan M2 14.85 274,422.50 4,075,174.13
8 4.4.1.25a Standar Pek. Keramik Dinding Batu alam Type Andesit M2 17.05 274,422.50 4,678,903.63
9 T30 Standar Pek. Logo Set 1.00 1,363,541.67 1,363,541.67
JUMLAH PEKERJAAN FINISHING DINDING 313,819,276.91
IV,2 PEKERJAAN FINISHING LANTAI
A PEKERJAAN FINISHING LANTAI 1
1 4.4.3.T11 Standar Pek. Keramik Ukuran 40x40 M2 138.07 227,749.50 31,445,373.47
2 4.4.3.T11 Standar Pek. Keramik Ukuran 40x40 M2 14.43 227,749.50 3,286,425.29
3 4.4.3.T11 Standar Pek. Keramik Unpolished Ukuran 40x40 (Km/Wc) M2 6.87 227,749.50 1,564,639.07
4 4.4.3.T14 Standar Pek. Lantai Epoxy M2 297.40 232,320.00 69,091,968.00
5 4.4.3.63 Standar Pek. Paving Blok M2 335.17 193,551.60 64,872,689.77
6 4.1.1.4 Standar Pek. Lantai Kerja Pengancing Tepi Paving M3 1.51 795,508.36 1,198,512.89
JUMLAH PEKERJAAN FINISHING LANTAI 171,459,608.48
IV,3 PEKERJAAN PINTU DAN JENDELA ALLUMUNIUM
A PEKERJAAN PINTU DAN JENDELA ALLUMUNIUM LANTAI 1
1 4.2.1.T83 Standar Pekerjaan Pintu Utama (P1) Set 1.00 8,320,015.74 8,320,015.74
2 4.2.1.T83 Standar Pekerjaan Pintu (P2) Set 3.00 6,012,342.90 18,037,028.69
3 4.2.1.T84 Standar Pekerjaan Pintu (P3) Set 5.00 6,658,381.28 33,291,906.40
4 4.2.1.T84 Standar Pekerjaan Pintu (P4) Set 1.00 8,435,276.36 8,435,276.36
5 4.2.1.T84 Standar Pekerjaan Pintu (P5) Set 10.00 8,605,616.62 86,056,166.18
6 4.2.1.T85 Standar Pekerjaan Pintu (P6) Set 1.00 1,394,896.24 1,394,896.24
7 4.2.1.T85 Standar Pekerjaan Pintu (P7) Set 1.00 1,197,766.16 1,197,766.16
8 4.2.1.T85 Standar Pekerjaan Pintu (P8) Set 2.00 7,833,692.40 15,667,384.80
9 4.2.1.T86 Standar Pekerjaan Pintu (P9) Set 2.00 3,703,961.22 7,407,922.45
8 4.2.1.T85 Standar Pekerjaan Jendela (J1) Set 1.00 3,278,422.39 3,278,422.39
9 4.2.1.T86 Standar Pekerjaan Jendela (J2) Set 1.00 6,353,743.32 6,353,743.32
9 4.2.1.T86 Standar Pekerjaan Ventilasi (V1) Set 5.00 1,482,264.86 7,411,324.32
10 4.2.1.T86 Standar Pekerjaan Ventilasi (V2) Set 1.00 1,482,579.45 1,482,579.45
11 4.2.1.T86 Standar Pekerjaan Ventilasi (V3) Set 10.00 905,423.87 9,054,238.67
12 4.2.1.T87 Standar Pekerjaan Ventilasi (V4) Set 12.00 2,843,578.52 34,122,942.29
13 4.2.1.T87 Standar Pekerjaan Ventilasi (V5) Set 4.00 1,362,126.50 5,448,506.02
14 4.2.1.T87 Standar Pekerjaan Trali Void Koridor Set 1.00 5,633,161.11 5,633,161.11
15 4.2.1.T88 Standar Pekerjaan Penutup Atap Acrylic Set 1.00 57,522,162.78 57,522,162.78
16 4.2.1.T87 Standar Pekerjaan Partisi Ruang Besuk (PR) Set 2.00 8,847,363.46 17,694,726.92
17 4.2.1.T88 Standar Pekerjaan Finishing Meja Ruang Jaga Set 1.00 825,870.33 825,870.33
JUMLAH PEKERJAAN PINTU DAN JENDELA ALLUMUNIUM LANTAI 1 328,636,040.60
IV,4 PEKERJAAN ATAP DAN LANGIT-LANGIT
A PEKERJAAN LANGIT-LANGIT LANTAI 1
1 4.5.1.T1 Standar Pek. Langit-Langit Gypsum + Rangka Hollow M2 83.75 164,899.02 13,810,292.93
2 4.5.1.T5 Standar Pek. List Gypsum M 122.92 38,478.00 4,729,715.76
3 4.5.1.T2 Standar Pek. Langit-Langit Kalsiboard + Rangka Hollow M2 8.43 160,783.03 1,355,400.92
JUMLAH PEKERJAAN ATAP DAN LANGIT-LANGIT 19,895,409.61
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022

RINCIAN

Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
IV,5 PEKERJAAN PENGECATAN
A PEKERJAAN PENGECATAN LANTAI 1
1 4.7.1.10 Standar Pek. Cat Dinding M2 2249.84 24,409.00 54,916,344.56
2 4.7.1.15 Standar Pek. Cat Langit Langit M2 92.18 17,842.00 1,644,675.56
JUMLAH PEKERJAAN PENGECATAN 56,561,020.12
I.1 PEKERJAAN PAGAR ANTAR GEDUNG
I.1,1 PEKERJAAN TANAH
A Pondasi Poer Plat (P1)
1 1.5.1.1 Standar Pek. Galian Tanah M3 5.76 69,300.00 399,168.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 4.29 23,100.00 99,099.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 0.36 126,720.00 45,619.20
B Pondasi Poer Plat (P2) -
1 1.5.1.1 Standar Pek. Galian Tanah M3 2.88 69,300.00 199,584.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 2.56 23,100.00 59,136.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 0.12 126,720.00 15,206.40
C Pondasi Batu Kali -
1 1.5.1.1 Standar Pek. Galian Tanah M3 6.55 69,300.00 453,915.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 2.18 23,100.00 50,435.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 0.82 126,720.00 103,910.40
JUMLAH PEKERJAAN TANAH 1,426,073.00
I.1,2 PEKERJAAN STRUKTUR
A Pekerjaan Pondasi Batu Kali
1 3.1.1.3 Standar Pek. Pondasi Batu Kali M3 7.21 703,120.00 5,069,495.20
2 3.1.1.9 Standar Pek. Batu Kosong (Aanstamping) M3 1.63 360,888.00 588,247.44
B Pekerjaan Pondasi Poer Plat (P1) -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 0.36 795,508.36 286,383.01
2 4.1.1.8 Standar Pek. Beton K 250 M3 1.00 1,058,542.89 1,058,542.89
3 4.1.1.15 Standar Pek. Pembesian KG 110.62 16,100.15 1,781,049.82
4 4.1.1.18a Standar Pek. Bekisting M2 4.00 122,562.00 490,248.00
C Pekerjaan Pondasi Poer Plat (P2) -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 0.12 795,508.36 95,461.00
2 4.1.1.8 Standar Pek. Beton K 250 M3 0.32 1,058,542.89 338,733.73
3 4.1.1.15 Standar Pek. Pembesian KG 37.76 16,100.15 607,908.05
4 4.1.1.18a Standar Pek. Bekisting M2 0.80 122,562.00 98,049.60
D Pekerjaan Kolom Pedestal 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.47 1,058,542.89 497,515.16
2 4.1.1.15 Standar Pek. Pembesian KG 89.78 16,100.15 1,445,391.38
3 4.1.1.18a Standar Pek. Bekisting M2 0.47 122,562.00 57,604.14
E Pekerjaan Sloof 25x35 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 1.51 1,058,542.89 1,598,399.77
2 4.1.1.15 Standar Pek. Pembesian KG 205.29 16,100.15 3,305,207.13
3 4.1.1.18a Standar Pek. Bekisting M2 12.21 122,562.00 1,496,482.02
F Pekerjaan Kolom 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 2.86 1,058,542.89 3,027,432.67
2 4.1.1.15 Standar Pek. Pembesian KG 395.49 16,100.15 6,367,492.44
3 4.1.1.20a Standar Pek. Bekisting M2 45.98 263,290.50 12,106,097.19
G Pekerjaan Ring Balok 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 1.51 1,058,542.89 1,598,399.77
2 4.1.1.15 Standar Pek. Pembesian KG 205.29 16,100.15 3,305,207.13
3 4.1.1.21a Standar Pek. Bekisting M2 12.21 258,351.96 3,154,477.41
JUMLAH PEKERJAAN STRUKTUR 48,373,824.95
I.1,3 PEKERJAAN FINISHING DINDING
1 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps M2 129.20 142,175.00 18,369,010.00
2 4.4.2.5 Standar Pek. Plesteran Dinding M2 258.40 61,753.12 15,957,006.21
3 4.4.2.5 Standar Pek. Plesteran Pondasi Batu Kali M2 13.50 61,753.12 833,667.12
4 4.4.2.27 Standar Pek. Acian M2 271.90 38,967.50 10,595,263.25
5 T31 Standar Pek. Kawat Silet Include Tiang M 17.60 222,526.56 3,916,467.50
JUMLAH PEKERJAAN FINISHING DINDING 49,671,414.08
I.1,4 PEKERJAAN PENGECATAN
1 4.7.1.10 Standar Pek. Cat Dinding M2 271.90 24,409.00 6,636,807.10
JUMLAH PEKERJAAN PENGECATAN 6,636,807.10
JUMLAH PEKERJAAN PAGAR ANTAR GEDUNG 106,108,119.12
II.2 PEKERJAAN SALURAN KELILING GEDUNG
A Pekerjaan Saluran Keliling
1 T30 Standar Pek. Saluran Keliling Bangunan Pas 1/2 Bata M 92.50 327,317.25 30,276,845.81
2 T31 Standar Pek.Bak Kontrol Bh 6.00 257,239.77 1,543,438.64
B Pekerjaan Plat Penutup Saluran Depan Bangunan
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.18 1,058,542.89 190,537.72
2 4.1.1.15 Standar Pek. Pembesian KG 16.24 16,100.15 261,543.31
3 4.1.1.22a Standar Pek. Bekisting M2 1.79 321,753.21 575,938.24
JUMLAH PEKERJAAN SALURAN KELILING GEDUNG 32,848,303.72
II.3 PEKERJAAN SALURAN LINGKUNGAN
A Pekerjaan Saluran
1 T30 Standar Pek. Saluran Keliling Pas Batu Kali M 51.85 620,417.96 32,168,671.25
B Pekerjaan Plat Penutup Saluran Jalan -
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022

RINCIAN

Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
1 4.1.1.8 Standar Pek. Beton K 250 M3 2.08 1,058,542.89 2,201,769.21
2 4.1.1.15 Standar Pek. Pembesian KG 1465.12 16,100.15 23,588,709.63
3 4.1.1.22a Standar Pek. Bekisting M2 13.87 321,753.21 4,461,644.49
A Pekerjaan Saluran -
1 T30 Standar Pek. Saluran Pas Batu Kali Satu Sisi Area Dinding Penahan Tanah M 2.70 620,417.96 1,675,128.49
2 4.1.1.4 Standar Pek. Lantai Kerja M3 2.25 795,508.36 1,789,893.81
JUMLAH PEKERJAAN SALURAN LINGKUNGAN 65,885,816.88
JUMLAH PEKERJAAN ARSITEKTUR 1,095,213,595.45
PEKERJAAN MEKANIKAL / PLUMBING
V.1 PEKERJAAN MEKANIKAL
A PEKERJAAN SISTEM TATA UDARA
1 T11 Standar AC Split Wall Mounted 1PK Bh 4.00 5,150,000.00 20,600,000.00
1 T38 Standar Instalasi Pipa Refrigerant 1/4''x3/8' dan Kabel Kontrol NYM 3x2.5mm M' 18.00 105,000.00 1,890,000.00
2 T39 Standar Instalasi Pipa Drain AC, PVC AW Ø 3/4'' M' 12.00 23,250.00 279,000.00
3 Standar Test and Commisioning Ls 1.00 600,000.00 600,000.00
JUMLAH PEKERJAAN SISTEM TATA UDARA 23,369,000.00
V.2 PEKERJAAN PLUMBING
A PEKERJAAN INSTALASI AIR HUJAN
1 8.4.1.T5 Standar Pipa PVC Type AW Diameter 3" M' 92.40 95,150.00 8,791,860.00
2 5.1.1.T33 Standar Roof Drain Unit 12.00 290,000.00 3,480,000.00
3 Standar Aksessories dan Material Bantu Ls 1.00 1,840,779.00 1,840,779.00
JUMLAH PEKERJAAN INSTALASI AIR HUJAN 14,112,639.00
V.3 PEKERJAAN SUMBER AIR BERSIH DAN PERPOMPAAN
A Pek. Sumber Air Bersih
1 T16 Standar Pek. Sumur Dalam Unit 1.00 95,650,000.00 95,650,000.00
Standar Pengadaan dan pemasangan Pompa Sumur Dalam
Standar Type : Submersible Pump
Standar Daya : 3 HP
Standar Lengkap Dengan Screen, proteksi, instalasi kabel daya/pemipaan (casing), dll
Standar Kabel jenis waterproof, lengkap Panel Kontrol, dll
Standar Pemipaan sampai ke Ground Water Tank (GWT)
Standar Peralatan penunjang, Gate Valve, Check Valve, Meter air, Bak Kontrol, dan accessories lainnya.
Standar Pengeboran dalam sampai mendapatkan Kapasitas air Min. 2liter/Detik (Jernih)
Standar Pekerjaan harus mengikuti/memenuhi Standard DepKes-RI
2 5.1.1.T26 Standar Check Valve dia 40 mm Unit 1.00 700,000.00 700,000.00
3 5.1.1.T18 Standar Gate Valve dia 1 1/2 mm Bh 1.00 2,650,000.00 2,650,000.00
B Pek. Mesin Pompa Transfer
1 5.1.1.T12 Standar Pompa Transfer, Semi Jet Pump Unit 3.00 11,000,000.00 33,000,000.00
Kapasitas 120 Lpm, Head 62 m
Include dengan WLC
2 5.1.1.T22 Standar Gate Valve dia 1" Bh 3.00 265,000.00 795,000.00
3 5.1.1.T26 Standar Check Valve Dia. 1'' Unit 3.00 670,000.00 2,010,000.00
4 5.1.1.T26 Standar Foot Valve Dia. 1 1/4'' Unit 3.00 513,500.00 1,540,500.00
4 5.1.1.T26 Standar Pressure Gauge Bh 3.00 718,600.00 2,155,800.00
5 T1 Standar Panel Control - Pompa Transfer Unit 1.00 5,000,000.00 5,000,000.00
C PEKERJAAN RUMAH POMPA
1 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps M2 4.25 142,175.00 604,243.75
2 4.4.2.5 Standar Pek. Plesteran Dinding M2 10.45 61,753.12 645,320.10
3 4.4.2.27 Standar Pek. Acian M2 10.45 38,967.50 407,210.38
4 4.1.1.26 Standar Pek. Kolom (Termasuk Bekisting Dan Pembesian) M 4.00 93,522.00 374,088.00
5 4.1.1.27 Standar Pek. Balok (Termasuk Bekisting Dan Pembesian) M 5.00 113,740.00 568,700.00
6 4.2.1.T81 Standar Pek. Plat Penutup Set 1.00 219,479.47 219,479.47
JUMLAH PEKERJAAN SUMBER AIR BERSIH DAN PERPOMPAAN 146,320,341.70
V.4 INSTALASI PIPA UTAMA AIR BERSIH
1 8.4.1.T9 Standar Pipa transfer dari GWT ke Tandon, Pipa PVC AW Ø 1'' M' 66.00 170,000.00 11,220,000.00
2 8.4.1.T9 Standar Pipa Pembagi dari Tandon ke Tandon, Pipa PVC AW Ø 1/2'' M' 19.80 75,000.00 1,485,000.00
3 8.4.1.T5 Standar Pipa Balancing Air Tandon, Pipa PVC AW Ø 2'' M' 11.00 55,000.00 605,000.00
4 5.1.1.T23 Standar Gate Valve 1/2'' M' 4.00 220,000.00 880,000.00
6 5.1.1.T27 Standar Valve 2'' M' 6.00 750,000.00 4,500,000.00
7 Aksessories dan Material Bantu Ls 1.00 3,444,507.00 3,444,507.00
8 GWT Kap. 25 m³ Ls 1.00 25,800,000.00 25,800,000.00
9 5.1.1.T29 Standar Water Tank Stainless Steel Kapasitas 1500 L + Dudukan, berikut pelampung Unit 4.00 5,500,000.00 22,000,000.00
JUMLAH INSTALASI PIPA UTAMA AIR BERSIH 69,934,507.00
V.5 INSTALASI AIR BERSIH
1 8.4.1.T5 Standar Pipa PVC AW Ø 2'' M' 93.50 56,974.50 5,327,115.75
2 8.4.1.T1 Standar Pipa PVC AW Ø 1/2'' M' 77.00 23,487.75 1,808,556.75
3 5.1.1.T27 Standar Gate Valve 2'' Bh 2.00 760,950.67 1,521,901.33
4 Standar Aksessories dan Material Bantu Ls 1.00 1,427,134.50 1,427,134.50
JUMLAH INSTALASI AIR BERSIH 10,084,708.33
V.6 INSTALASI AIR KOTOR DAN BEKAS
1 8.4.1.T5 Standar Pipa PVC Type AW Diameter 3" M' 97.90 56,974.50 5,577,803.55
2 8.4.1.T6 Standar Pipa PVC Type AW Diameter 4" M' 73.70 155,787.50 11,481,538.75
3 8.4.1.T6 Standar Pipa PVC Type AW Diameter 4" (Outlet Ke Saluran) M' 44.00 155,787.50 6,854,650.00
4 5.1.1.T31 Standar CO 2'' Set 8.00 187,742.50 1,501,940.00
5 5.1.1.T30 Standar CO 4'' Set 6.00 283,167.50 1,699,005.00
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022

RINCIAN

Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
6 5.1.1.T30 Standar Septictank 20 m³ + Sumur Resapan Unit 3.00 10,375,000.00 31,125,000.00
JUMLAH INSTALASI AIR KOTOR DAN BEKAS 58,239,937.30
V.7 PEKERJAAN SANITAIR
1 5.1.1.3 Standar Kloset Duduk Unit 2.00 3,343,725.00 6,687,450.00
2 5.1.1.T1 Standar Jet Washer Toilet Unit 2.00 297,398.75 594,797.50
3 5.1.1.T4 Standar Wastafel Type Meja Unit 3.00 952,875.00 2,858,625.00
4 5.1.1.18 Standar Floor Drain (Toto/Amstad) Unit 12.00 211,598.75 2,539,185.00
5 5.1.1.6 Standar Closet Jongkok Unit 10.00 502,488.80 5,024,888.00
6 5.1.1.T7 Standar Kran Unit 10.00 143,673.75 1,436,737.50
7 Aksessories dan Material Bantu Ls 1.00 531,148.37 531,148.37
JUMLAH PEKERJAAN SANITAIR 19,672,831.37
JUMLAH PEKERJAAN MEKANIKAL 341,733,964.70
PEKERJAAN ELEKTRKAL
VI.1 PEKERJAAN INSTALASI DAYA DAN ARMATUR PENERANGAN
1 Standar Sambung Daya Listrik PLN 35 KVA berikut SLO + UJL Ls 1.00 61,820,000.00 61,820,000.00
2 T38 Standar Panel Listrik Utama Type Outdoor Set 1.00 20,000,000.00 20,000,000.00
3 T39 Standar Panel PP Pompa Type Outdoor Set 1.00 7,850,000.00 7,850,000.00
4 T39 Standar Panel Listrik Rutan Umum Set 1.00 3,612,400.92 3,612,400.92
5 T11 Standar Kabel Power dari Panel Utama ke KWH PLN, Kabel NYY 4x25mm M' 10.00 370,837.50 3,708,375.00
6 T15 Standar Kabel Power dari Panel Utama ke Panel Rutan Teroris, Kabel NYY 4x2.5mm M' 19.80 52,421.88 1,037,953.13
7 T15 Standar Kabel Power dari Panel Utama ke Panel Rutan Umum, Kabel NYY 4x2.5mm M' 41.80 52,421.88 2,191,234.38
8 T14 Standar Kabel Power dari Panel Utama ke Panel Pompa, Kabel NYY 4x6mm M' 28.60 106,260.00 3,039,036.00
9 T91 Standar Lampu Downlight LED 13 W Bh 22.00 169,262.50 3,723,775.00
10 T92 Standar Lampu Downlight LED 7 W Bh 2.00 158,125.00 316,250.00
11 T86 Standar Lampu TKO LED 2x18 Watt Bh 6.00 387,420.00 2,324,520.00
12 T68 Standar Saklar Tunggal Bh 6.00 77,742.50 466,455.00
13 T69 Standar Saklar Ganda Bh 4.00 77,187.00 308,748.00
14 T75 Standar Stop Kontak Bh 5.00 102,740.00 513,700.00
15 T76 Standar Stop Kontak Pompa + Waterproof Bh 3.00 251,377.50 754,132.50
16 T76 Standar Stop Kontak AC Bh 2.00 112,739.00 225,478.00
17 T30 Standar Instalasi penerangan, NYM 3 x 2,5 mm2 + Pipa Conduit Titik 24.00 337,457.02 8,098,968.56
18 T23a Standar Instalasi stop kontak, Kabel NYM 3 x 2,5 mm2 + Pipa Conduit Titik 8.00 382,144.20 3,057,153.58
19 T29 Standar Instalasi stop kontak AC, Kabel NYM 3 x 2,5 mm2 + Pipa Conduit Titik 2.00 440,027.50 880,055.00
20 Standar Test and Commisioning Ls 1.00 3,500,000.00 3,500,000.00
JUMLAH PEKERJAAN INSTALASI DAYA DAN ARMATUR PENERANGAN 127,428,235.06
VI.2 PEKERJAAN INSTALASI FIRE ALARM
A Pekerjaan Instalasi dan Armature Fire Alarm
1 T130 Standar TB-FA Set 1.00 2,000,000.00 2,000,000.00
2 T126 Standar Smoke Detector Unit 10.00 845,020.00 8,450,200.00
3 T137 Standar Manual Breack Glass Unit 1.00 229,102.50 229,102.50
4 T139 Standar Bell Alarm Unit 1.00 850,000.00 850,000.00
5 T125 Standar Indicator Lamp Unit 1.00 309,650.00 309,650.00
6 T36 Standar Instalasi Fire Alarm, Kabel NYA 2(1x 1,5) mm didalam Pipa Conduit PVC 20mm Titik 13.00 300,238.20 3,903,096.57
JUMLAH PEKERJAAN INSTALASI FIRE ALARM 15,742,049.07
VI.3 PEKERJAAN INSTALASI CCTV
A Instalasi beserta Armatur CCTV
1 T122 Standar Pemasangan Monitor TV LED 32" + Bracket Full Motion Unit 1.00 5,600,000.00 5,600,000.00
2 T124 Standar Pemasangan Fixed Camera Unit 6.00 553,000.00 3,318,000.00
3 T123 Standar Pemasangan Dome Camera Unit 4.00 675,000.00 2,700,000.00
4 T35 Standar Instalasi kabel CCTV, Kabel UTP Cat.6 dalam Pipa Conduit PVC 20mm Unit 10.00 350,000.00 3,500,000.00
5 Standar Test and Commisioning Ls 1.00 472,778.63 472,778.63
JUMLAH PEKERJAAN INSTALASI CCTV 15,590,778.63
JUMLAH PEKERJAAN ELEKTRKAL 158,761,062.76
PEKERJAAN FASILITAS UMUM (FASUM)
PEKERJAAN JALAN DAN LANDSCAPE
I.1 PEKERJAAN JALAN DAN LANDSCAPE
A Pekerjaan Jalan
1 1.5.1.15 Standar Pek. Timbunan Pilihan M3 272.99 123,010.36 33,580,598.88
JUMLAH PEKERJAAN JALAN DAN LANDSCAPE 33,580,598.88
PEKERJAAN SALURAN
II.1 PEKERJAAN SALURAN LINGKUNGAN
A Pekerjaan Saluran
1 T30 Standar Pek. Saluran Keliling Pas Batu Kali M 205.40 620,417.96 127,433,849.06
2 T25 Standar Pek. Kansteen M 426.21 150,726.03 64,240,942.67
B Pekerjaan Plat Penutup Saluran Jalan
1 4.1.1.8 Standar Pek. Beton K 250 M3 2.40 1,058,542.89 2,540,502.94
2 4.1.1.15 Standar Pek. Pembesian KG 823.11 16,100.15 13,252,247.87
3 4.1.1.22a Standar Pek. Bekisting M2 16.00 321,753.21 5,148,051.33
JUMLAH PEKERJAAN SALURAN LINGKUNGAN 212,615,593.87
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Biaya Manajemen Keselamatan Dan Kesehatan Kerja
Kode AHSP = 1.1.2.1
A TENAGA
OH -
OH -
OH -
JUMLAH TENAGA KERJA -
B BAHAN
Liter -
Liter -
JUMLAH HARGA BAHAN -
C PERALATAN
Helm C109 Bh 10.000 65,100.00 651,000.00
Sepatu C110 Psg 10.000 90,000.00 900,000.00
Sarung Tangan C111 Psg 10.000 50,000.00 500,000.00
Kacamata Pelindung C112 Bh 3.000 60,600.00 181,800.00
Rompi K3 C113 Bh 10.000 115,000.00 1,150,000.00
Kotak P3K C114 Bh 1.000 200,500.00 200,500.00
APAR 3kg C115 Bh 1.000 1,013,000.00 1,013,000.00
Rambu-Rambu Keselamatan C117 Bh 1.000 202,000.00 202,000.00
Penanganan Covid 19 Ls 1.000 750,000.00 750,000.00
- Masker 500 buah
- Wastafel Cuci Tangah
- Sabun cuci tangan dan Hand sanitizer
JUMLAH HARGA ALAT 5,548,300.00
D Jumlah (A+B+C) 5,548,300.00
E Overhead & Profit 10% 554,830.00
F Harga Satuan Pekerjaan (D+E) 6,103,130.00

Pembuatan 1 m2 pagar sementara dari kayu Tinggi 2 meter


Kode AHSP = 1.1.1.1
A TENAGA
Pekerja C9 OH 0.400 80,000.00 32,000.00
Tukang Kayu C19 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.020 120,000.00 2,400.00
JUMLAH TENAGA KERJA 62,400.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 Batang 1.250 20,900.00 26,125.00
Semen portland C363 Kg 5.000 1,300.00 6,500.00
Pasir beton C97 m3 0.005 100,000.00 500.00
Koral beton C92 m3 0.009 275,000.00 2,475.00
Kayu Balok 5/7 Kelas III C78 m3 0.072 1,600,000.00 115,200.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.060 21,000.00 1,260.00
Residu C356 Liter 0.400 15,000.00 6,000.00
JUMLAH HARGA BAHAN 158,060.00
C PERALATAN
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 220,460.00
E Overhead & Profit 10% 22,046.00
F Harga Satuan Pekerjaan (D+E) 242,506.00

Pembuatan 1 m2 pagar sementara dari seng gelombang Tinggi, 2 Meter


Kode AHSP = 1.1.1.2
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Kayu C19 OH 0.400 125,000.00 50,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.020 120,000.00 2,400.00
JUMLAH TENAGA KERJA 71,400.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 Batang 1.250 20,900.00 26,125.00
Semen portland C363 Kg 2.500 1,300.00 3,250.00
Seng Gelombang BJLS 20 C367 Lbr 1.200 76,400.00 91,680.00
Pasir beton C97 m3 0.005 100,000.00 500.00
Koral beton C92 m3 0.009 275,000.00 2,475.00
Kayu Balok 5/7 Kelas III C78 m3 0.072 1,600,000.00 115,200.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.060 21,000.00 1,260.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Meni besi C301 Liter 0.450 17,000.00 7,650.00
JUMLAH HARGA BAHAN 248,140.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 319,540.00
E Overhead & Profit 10% 31,954.00
F Harga Satuan Pekerjaan (D+E) 351,494.00

Pembuatan 1 m2 pagar sementara dari kawat duri, 1,8 meter


Kode AHSP = 1.1.1.3
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Kayu C19 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.020 120,000.00 2,400.00
JUMLAH TENAGA KERJA 58,900.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 Batang 1.000 20,900.00 20,900.00
Semen portland C363 Kg 2.000 1,300.00 2,600.00
Kawat duri C269 M’ 25.000 24,500.00 612,500.00
Pasir beton C97 m3 0.005 100,000.00 500.00
Koral beton C92 m3 0.009 275,000.00 2,475.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.060 21,000.00 1,260.00
-
-
JUMLAH HARGA BAHAN 640,235.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 699,135.00
E Overhead & Profit 10% 69,913.50
F Harga Satuan Pekerjaan (D+E) 769,048.50

Pengukuran dan pemasangan 1 m' Bouwplank


Kode AHSP = 1.1.1.4
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Kayu Balok 5/7 Kelas III C78 m3 0.120 1,600,000.00 192,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.020 21,000.00 420.00
Kayu papan 3/20 Kelas III C87 m3 0.007 1,600,000.00 11,200.00

JUMLAH HARGA BAHAN 203,620.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 226,220.00
E Overhead & Profit 10% 22,622.00
F Harga Satuan Pekerjaan (D+E) 248,842.00

Pembuatan 1 m2 kantor sementara lantai plesteran


Kode AHSP = 1.1.1.5
A TENAGA
Pekerja C9 OH 2.000 80,000.00 160,000.00
Tukang Kayu C19 OH 2.000 125,000.00 250,000.00
Tukang Batu C18 OH 1.000 125,000.00 125,000.00
Kepala Tukang C39 OH 0.300 150,000.00 45,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 586,000.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 m3 1.250 20,900.00 26,125.00
Kayu kelas III C86 m3 0.180 1,600,000.00 288,000.00
Paku biasa C318 Kg 0.080 21,000.00 1,680.00
Besi strip C198 Kg 1.100 11,250.00 12,375.00
Semen Portland C363 Kg 35.000 1,300.00 45,500.00
Pasir pasang C99 m3 0.150 100,000.00 15,000.00
Pasir beton C97 m3 0.100 100,000.00 10,000.00
Koral beton C92 m3 0.150 275,000.00 41,250.00
Bata merah C142 Bh 30.000 1,000.00 30,000.00
Seng Plat BJLS 20 C370 Lbr 0.250 56,600.00 14,150.00
Jendela naco C258 Bh 0.200 185,000.00 37,000.00
Kaca Bening 5 mm C544 m2 0.080 128,000.00 10,240.00
Kunci Tanam Pintu 2 Slaag C573 Bh 0.150 450,000.00 67,500.00
Plywood 4 mm C347 Lbr 0.060 111,800.00 6,708.00
JUMLAH HARGA BAHAN 605,528.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,191,528.00
E Overhead & Profit 10% 119,152.80
F Harga Satuan Pekerjaan (D+E) 1,310,680.80
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pembuatan 1 m2 gudang semen dan peralatan
Kode AHSP = 1.1.1.6
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 2.000 125,000.00 250,000.00
Kepala Tukang C39 OH 0.200 150,000.00 30,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 366,000.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 Batang 1.700 20,900.00 35,530.00
Kayu kelas III C86 m3 0.210 1,600,000.00 336,000.00
Paku Biasa C318 Kg 0.300 21,000.00 6,300.00
Semen Portland C363 Kg 10.500 1,300.00 13,650.00
Pasir beton C97 m3 0.030 100,000.00 3,000.00
Koral beton C92 m3 0.050 275,000.00 13,750.00
Seng Gelombang BJLS 20 C367 Lbr 1.500 76,400.00 114,600.00
Seng Plat BJLS 20 C370 Lbr 0.250 56,600.00 14,150.00
JUMLAH HARGA BAHAN 536,980.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 902,980.00
E Overhead & Profit 10% 90,298.00
F Harga Satuan Pekerjaan (D+E) 993,278.00

Pembuatan 1 m2 rumah jaga (Konstruksi Kayu)


Kode AHSP = 1.1.1.7
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 1.500 125,000.00 187,500.00
Kepala Tukang C39 OH 0.150 150,000.00 22,500.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 296,000.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 Batang 3.000 20,900.00 62,700.00
Kayu kelas III C86 m3 0.276 1,600,000.00 441,600.00
Paku Biasa C318 Kg 0.700 21,000.00 14,700.00
Seng Gelombang BJLS 20 C367 Lbr 1.500 76,400.00 114,600.00

JUMLAH HARGA BAHAN 633,600.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 929,600.00
E Overhead & Profit 10% 92,960.00
F Harga Satuan Pekerjaan (D+E) 1,022,560.00

Pembuatan 1 m2 bedeng pekerja


Kode AHSP = 1.1.1.9
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 2.000 125,000.00 250,000.00
Kepala Tukang C39 OH 0.200 150,000.00 30,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 366,000.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 Batang 1.250 20,900.00 26,125.00
Kayu kelas III C86 m3 0.186 1,600,000.00 297,600.00
Paku biasa C318 Kg 0.300 21,000.00 6,300.00
Semen Portland C363 Kg 18.000 1,300.00 23,400.00
Pasir beton C97 m3 0.030 100,000.00 3,000.00
Koral beton C92 m3 0.050 275,000.00 13,750.00
Seng Gelombang BJLS 20 C367 Lbr 1.500 76,400.00 114,600.00
Plywood 4 mm C347 Lbr 1.350 111,800.00 150,930.00
JUMLAH HARGA BAHAN 635,705.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,001,705.00
E Overhead & Profit 10% 100,170.50
F Harga Satuan Pekerjaan (D+E) 1,101,875.50

Pembersihan 1 m2 lapangan dan perataan


Kode AHSP = 1.1.1.8
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00

JUMLAH TENAGA KERJA 14,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 14,000.00
E Overhead & Profit 10% 1,400.00
F Harga Satuan Pekerjaan (D+E) 15,400.00

Pembuatan 1 buah kotak adukan ukuran 40cm x 50cm x 25cm


Kode AHSP = 1.1.1.10
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 2.000 125,000.00 250,000.00
Kepala Tukang C39 OH 0.200 150,000.00 30,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 366,000.00
B BAHAN
Bambu Ø 6 - 8 / 600 cm C70 Batang 1.250 12,500.00 15,625.00
Tali ijuk C393 m3 0.186 61,800.00 11,494.80

JUMLAH HARGA BAHAN 27,119.80


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 393,119.80
E Overhead & Profit 10% 39,311.98
F Harga Satuan Pekerjaan (D+E) 432,431.78

Pembuatan 1 m2 Stegger/ perancah dari bambu s.d Tinggi 6 meter


Kode AHSP = 1.1.1.11
A TENAGA
Tukang Kayu C19 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.030 150,000.00 4,500.00

JUMLAH TENAGA KERJA 42,000.00


B BAHAN
Papan kayu kelas III C96 m3 0.036 1,600,000.00 57,600.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kayu Balok 5/7 Kelas III C78 m3 1,600,000.00 -
Paku biasa C318 kg 0.080 21,000.00 1,680.00

JUMLAH HARGA BAHAN 59,280.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 101,280.00
E Overhead & Profit 10% 10,128.00
F Harga Satuan Pekerjaan (D+E) 111,408.00

Pembuatan 1 m2 jalan sementara


Kode AHSP = 1.1.1.12
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Mandor C47 OH 0.005 120,000.00 600.00

JUMLAH TENAGA KERJA 80,600.00


B BAHAN
Batu belah 15 cm/20 cm C73 m3 0.150 145,000.00 21,750.00
Koral Beton C92 m3 0.090 275,000.00 24,750.00
Pasir pasang C99 m3 0.010 100,000.00 1,000.00

JUMLAH HARGA BAHAN 47,500.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 128,100.00
E Overhead & Profit 10% 12,810.00
F Harga Satuan Pekerjaan (D+E) 140,910.00

Pembongkaran 1 m3 beton bertulang


Kode AHSP = 1.1.1.14
A TENAGA
Pekerja C9 OH 13.334 80,000.00 1,066,720.00
Mandor C47 OH 0.666 120,000.00 79,920.00

JUMLAH TENAGA KERJA 1,146,640.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,146,640.00
E Overhead & Profit 10% 114,664.00
F Harga Satuan Pekerjaan (D+E) 1,261,304.00

Pembongkaran 1 m3 Plesteran
Kode AHSP = 1.1.1.13
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja C9 OH 8.889 80,000.00 711,146.67
Mandor C47 OH 0.444 120,000.00 53,280.00

JUMLAH TENAGA KERJA 764,426.67


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 764,426.67
E Overhead & Profit 10% 76,442.67
F Harga Satuan Pekerjaan (D+E) 840,869.33

Pembongkaran 1 m2 dinding tembok bata


Kode AHSP = 1.1.1.15
A TENAGA
Pekerja C9 OH 6.667 80,000.00 533,360.00
Mandor C47 OH 0.333 120,000.00 39,960.00

JUMLAH TENAGA KERJA 573,320.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 573,320.00
E Overhead & Profit 10% 57,332.00
F Harga Satuan Pekerjaan (D+E) 630,652.00

Pemasangan 1 m2 kawat jaring galvanis panjang 240 cm


Kode AHSP = 1.1.1.16
A TENAGA
Pekerja C9 OH 0.042 80,000.00 3,360.00
Tukang Kayu C19 OH 0.004 125,000.00 500.00
Kepala Tukang C39 OH 0.002 150,000.00 300.00
Mandor C47 OH 0.042 120,000.00 5,040.00
JUMLAH TENAGA KERJA 9,200.00
B BAHAN
Kawat jaring C271 Lbr 0.143 75,000.00 10,755.00

JUMLAH HARGA BAHAN 10,755.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 19,955.00
E Overhead & Profit 10% 1,995.50
F Harga Satuan Pekerjaan (D+E) 21,950.50

Pemasangan 1 m2 pagar beton pracetak 50x50x240 cm untuk pagar


Kode AHSP = 1.1.1.17
A TENAGA
Pekerja C9 OH 0.375 80,000.00 30,000.00
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.019 120,000.00 2,280.00
JUMLAH TENAGA KERJA 49,705.00
B BAHAN
Panel Pracetak C327 Lbr 0.986 325,000.00 320,450.00
Kolom Pracetak C290 Btg 0.525 125,000.00 65,625.00
Semen Portland C363 Kg 45.000 1,300.00 58,500.00
Pasir beton C97 m3 0.074 100,000.00 7,400.00
Koral Beton C92 m3 0.146 275,000.00 40,150.00

JUMLAH HARGA BAHAN 492,125.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 541,830.00
E Overhead & Profit 10% 54,183.00
F Harga Satuan Pekerjaan (D+E) 596,013.00

Pembongkaran 1 m3 Pondasi batu


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = 1.1.1.T1
A TENAGA
Pekerja C9 OH 6.667 80,000.00 533,360.00
Mandor C47 OH 0.333 120,000.00 39,960.00

JUMLAH TENAGA KERJA 573,320.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 573,320.00
E Overhead & Profit 10% 57,332.00
F Harga Satuan Pekerjaan (D+E) 630,652.00

Pembongkaran 1 m2 Lantai Kerja + Keramik


Kode AHSP = 1.1.1.T2
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Mandor C47 OH 0.025 120,000.00 3,000.00

JUMLAH TENAGA KERJA 23,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 23,000.00
E Overhead & Profit 10% 2,300.00
F Harga Satuan Pekerjaan (D+E) 25,300.00

Pembongkaran 1 m2 Penutup Plafond


Kode AHSP = 1.1.1.T3
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Mandor C47 OH 0.020 120,000.00 2,400.00

JUMLAH TENAGA KERJA 18,400.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 18,400.00
E Overhead & Profit 10% 1,840.00
F Harga Satuan Pekerjaan (D+E) 20,240.00

Pembongkaran 1 m2 Dinding Partisi


Kode AHSP = 1.1.1.T4
A TENAGA
Pekerja C9 OH 1.802 80,000.00 144,151.35
Mandor C47 OH 0.111 120,000.00 13,320.00

JUMLAH TENAGA KERJA 157,471.35


B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 157,471.35
E Overhead & Profit 10% 15,747.14
F Harga Satuan Pekerjaan (D+E) 173,218.49

Pembongkaran 1 Unit Kusen + Pintu


Kode AHSP = 1.1.1.T5
A TENAGA
Pekerja C9 OH 2.667 80,000.00 213,344.00
Mandor C47 OH 0.133 120,000.00 15,984.00

JUMLAH TENAGA KERJA 229,328.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 229,328.00
E Overhead & Profit 10% 22,932.80
F Harga Satuan Pekerjaan (D+E) 252,260.80

Pemindahan 1 Unit Kusen + Pintu


Kode AHSP = 1.1.1.T6
A TENAGA
Pekerja C9 OH 6.667 80,000.00 533,360.00
Mandor C47 OH 0.333 120,000.00 39,960.00

JUMLAH TENAGA KERJA 573,320.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 573,320.00
E Overhead & Profit 10% 57,332.00
F Harga Satuan Pekerjaan (D+E) 630,652.00

Pembongkaran 1 M2 Penutup Atap


Kode AHSP = 1.1.1.T7
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00

JUMLAH TENAGA KERJA 18,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 18,000.00
E Overhead & Profit 10% 1,800.00
F Harga Satuan Pekerjaan (D+E) 19,800.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pembongkaran 1 M2 Rangka Atap + Penutup Atap


Kode AHSP = 1.1.1.T8
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Mandor C47 OH 0.060 120,000.00 7,200.00

JUMLAH TENAGA KERJA 55,200.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 55,200.00
E Overhead & Profit 10% 5,520.00
F Harga Satuan Pekerjaan (D+E) 60,720.00

Buangan Hasil Galian/Bongkaran 1 Ret Menggunakan Truck


Kode AHSP = 1.1.1.T9
A TENAGA
Pekerja C9 OH 0.330 80,000.00 26,400.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 27,600.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
Sewa Dump Truck + Supir C1586 Jam 1.000 255,157.14 255,157.14
- - -
JUMLAH HARGA ALAT 255,157.14
D Jumlah (A+B+C) 282,757.14
E Overhead & Profit 10% 28,275.71
F Harga Satuan Pekerjaan (D+E) 311,032.86

Sewa 1 Set/Bln Skafollding


Kode AHSP = 1.1.1.T10
A TENAGA
Pekerja C9 OH 0.010 80,000.00 800.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 2,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
Sewa Skafolding 1 Set (Bulan) C1594 Bln 1.000 151,500.00 151,500.00
- - -
JUMLAH HARGA ALAT 151,500.00
D Jumlah (A+B+C) 153,500.00
E Overhead & Profit 10% 15,350.00
F Harga Satuan Pekerjaan (D+E) 168,850.00

HARGA SATUAN PEKERJAAN TANAH Kode AHSP = 1.5.1.


Penggalian 1 m3 tanah biasa sedalam 1 m
Kode AHSP = 1.5.1.1
A TENAGA
Pekerja C9 OH 0.750 80,000.00 60,000.00
Mandor C47 OH 0.025 120,000.00 3,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 63,000.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 63,000.00
E Overhead & Profit 10% 6,300.00
F Harga Satuan Pekerjaan (D+E) 69,300.00

Penggalian 1 m3 tanah biasa sedalam 2 m


Kode AHSP = 1.5.1.2
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Mandor C47 OH 0.045 120,000.00 5,400.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 77,400.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 77,400.00
E Overhead & Profit 10% 7,740.00
F Harga Satuan Pekerjaan (D+E) 85,140.00

Penggalian 1 m3 tanah biasa sedalam 3 m


Kode AHSP = 1.5.1.3
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Mandor C47 OH 0.067 120,000.00 8,040.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 92,040.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 92,040.00
E Overhead & Profit 10% 9,204.00
F Harga Satuan Pekerjaan (D+E) 101,244.00

Penggalian 1 m3 tanah keras sedalam 1 m


Kode AHSP = 1.5.1.4
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Mandor C47 OH 0.032 120,000.00 3,840.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 83,840.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 83,840.00
E Overhead & Profit 10% 8,384.00
F Harga Satuan Pekerjaan (D+E) 92,224.00

Penggalian 1 m3 tanah cadas sedalam 1 m


Kode AHSP = 1.5.1.5
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Mandor C47 OH 0.060 120,000.00 7,200.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 127,200.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 127,200.00
E Overhead & Profit 10% 12,720.00
F Harga Satuan Pekerjaan (D+E) 139,920.00

Penggalian 1 m3 tanah lumpur sedalam 1 m


Kode AHSP = 1.5.1.6
A TENAGA
Pekerja C9 OH 1.200 80,000.00 96,000.00
Mandor C47 OH 0.045 120,000.00 5,400.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 101,400.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 101,400.00
E Overhead & Profit 10% 10,140.00
F Harga Satuan Pekerjaan (D+E) 111,540.00

Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter


Kode AHSP = 1.5.1.7
A TENAGA
Pekerja C9 OH 0.050 80,000.00 4,000.00
Mandor C47 OH 0.005 120,000.00 600.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 4,600.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,600.00
E Overhead & Profit 10% 460.00
F Harga Satuan Pekerjaan (D+E) 5,060.00

Pembuangan tanah 1 m3 sejauh 30m


Kode AHSP = 1.5.1.8
A TENAGA
Pekerja C9 OH 0.330 80,000.00 26,400.00
Mandor C47 OH 0.010 120,000.00 1,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 27,600.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 27,600.00
E Overhead & Profit 10% 2,760.00
F Harga Satuan Pekerjaan (D+E) 30,360.00

Pemadatan tanah per 20 cm


Kode AHSP = 1.5.1.9
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00

JUMLAH TENAGA KERJA 46,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
Sewa Stamper - Alat/hari 0.050 150,000.00 7,500.00
- - -
JUMLAH HARGA ALAT 7,500.00
D Jumlah (A+B+C) 53,500.00
E Overhead & Profit 10% 5,350.00
F Harga Satuan Pekerjaan (D+E) 58,850.00

Pengurugan 1 m3 dengan pasir urug


Kode AHSP = 1.5.1.10
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 25,200.00


B BAHAN
Pasir urug C100 m3 1.200 75,000.00 90,000.00

JUMLAH HARGA BAHAN 90,000.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 115,200.00
E Overhead & Profit 10% 11,520.00
F Harga Satuan Pekerjaan (D+E) 126,720.00

Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL


Kode AHSP = 1.5.1.11
A TENAGA
Pekerja C9 OH 0.800 80,000.00 64,000.00
Tukang C17 OH 0.400 125,000.00 50,000.00
Kepala Tukang C39 OH 0.040 150,000.00 6,000.00
Mandor C47 OH 0.080 120,000.00 9,600.00
JUMLAH TENAGA KERJA 129,600.00
B BAHAN
Kapur Padam C262 m3 0.135 200,000.00 27,000.00
Pasir Pasang C99 m3 0.400 100,000.00 40,000.00
Tanah Liat C104 m3 0.948 50,000.00 47,400.00
JUMLAH HARGA BAHAN 114,400.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 244,000.00
E Overhead & Profit 10% 24,400.00
F Harga Satuan Pekerjaan (D+E) 268,400.00

Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan


Kode AHSP = 1.5.1.13
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Mandor C47 OH 0.015 120,000.00 1,800.00

JUMLAH TENAGA KERJA 13,800.00


B BAHAN
Ijuk C256 Kg 6.000 40,000.00 240,000.00

JUMLAH HARGA BAHAN 240,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 253,800.00
E Overhead & Profit 10% 25,380.00
F Harga Satuan Pekerjaan (D+E) 279,180.00

Pengurugan 1 m3 sirtu padat


Kode AHSP = 1.5.1.14
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Mandor C47 OH 0.025 120,000.00 3,000.00

JUMLAH TENAGA KERJA 23,000.00


B BAHAN
Sirtu C103 m3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 83,000.00
E Overhead & Profit 10% 8,300.00
F Harga Satuan Pekerjaan (D+E) 91,300.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pembentukan 1 m3 Badan Jalan Menggunakan Sirtu


Kode AHSP = 1.5.1.15
A TENAGA
Pekerja C9 OH 0.040 80,000.00 3,200.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 4,400.00


B BAHAN
Sirtu C103 m3 1.250 50,000.00 62,500.00

JUMLAH HARGA BAHAN 62,500.00


C PERALATAN - -
Sewa Tandem Roller + Operator - 0.013 708,225.30 9,490.22
Sewa Water Tanker + Operator - 0.070 363,391.19 25,437.38
Alat bantu - 1.000 10,000.00 10,000.00
JUMLAH HARGA ALAT 44,927.60
D Jumlah (A+B+C) 111,827.60
E Overhead & Profit 10% 11,182.76
F Harga Satuan Pekerjaan (D+E) 123,010.36

Pengurugan 1 m3 Tanah Urug


Kode AHSP = 1.5.1.T1
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 25,200.00


B BAHAN
Tanah Urug C105 m3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 85,200.00
E Overhead & Profit 10% 8,520.00
F Harga Satuan Pekerjaan (D+E) 93,720.00

Pengurugan 1 m3 Tanah Taman


Kode AHSP = 1.5.1.T2
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Mandor C47 OH 0.025 120,000.00 3,000.00

JUMLAH TENAGA KERJA 23,000.00


B BAHAN
Tanah Taman C106 m3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 83,000.00
E Overhead & Profit 10% 8,300.00
F Harga Satuan Pekerjaan (D+E) 91,300.00

Menggali 1 m3 tanah biasa dengan Alat Excavator


Kode AHSP = 1.5.1.T3
A TENAGA
Operator Alat Berat C31 OH 0.125 200,000.00 25,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH TENAGA KERJA 25,000.00


B BAHAN
Solar C389 Ltr 0.656 16,200.00 10,631.25

JUMLAH HARGA BAHAN 10,631.25


C PERALATAN - - -
Sewa Exavator C1587 Jam 0.025 450,000.00 11,250.00
- - -
JUMLAH HARGA ALAT 11,250.00
D Jumlah (A+B+C) 46,881.25
E Overhead & Profit 10% 4,688.13
F Harga Satuan Pekerjaan (D+E) 51,569.38

1 Hari Sewa Alat Exavator (Galian/bongkaran)


Kode AHSP = 1.5.1.T4
A TENAGA
Operator Alat Berat C31 OH 1.000 200,000.00 200,000.00

JUMLAH TENAGA KERJA 200,000.00


B BAHAN
Solar C389 Ltr 210.000 16,200.00 3,402,000.00

JUMLAH HARGA BAHAN 3,402,000.00


C PERALATAN - - -
Sewa Exavator C1587 Jam 8.000 450,000.00 3,600,000.00
- - -
JUMLAH HARGA ALAT 3,600,000.00
D Jumlah (A+B+C) 7,202,000.00
E Overhead & Profit 10% 720,200.00
F Harga Satuan Pekerjaan (D+E) 7,922,200.00

Pemadatan tanah per 20 cm (Menggunakan Stamper)


Kode AHSP = 1.5.1.T5
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00

JUMLAH TENAGA KERJA 46,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
Sewa Stamper C1602 Alat/hari 0.050 150,000.00 7,500.00
- - -
JUMLAH HARGA ALAT 7,500.00
D Jumlah (A+B+C) 53,500.00
E Overhead & Profit 10% 5,350.00
F Harga Satuan Pekerjaan (D+E) 58,850.00
Mengurug 1 m3 tanah subur
Kode AHSP = 1.5.1.T6
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 25,200.00


B BAHAN
Tanah Subur C107 M3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 85,200.00
E Overhead & Profit 10% 8,520.00
F Harga Satuan Pekerjaan (D+E) 93,720.00

Pengurugan kembali 1 m3 galian


Kode AHSP = 1.5.1.T7
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00

JUMLAH TENAGA KERJA 46,000.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 46,000.00
E Overhead & Profit 10% 4,600.00
F Harga Satuan Pekerjaan (D+E) 50,600.00

HARGA SATUAN PEKERJAAN PONDASI Kode AHSP = 3.1.1.


Pemasangan 1 m3 pondasi batu belah campuran 1PC : 3PP
Kode AHSP = 3.1.1.1
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 202.000 1,300.00 262,600.00
Pasir Pasang C99 m3 0.485 100,000.00 48,500.00
JUMLAH HARGA BAHAN 485,100.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 719,100.00
E Overhead & Profit 10% 71,910.00
F Harga Satuan Pekerjaan (D+E) 791,010.00

Pemasangan 1 m3 pondasi batu belah campuran 1PC : 4PP


Kode AHSP = 3.1.1.2
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 163.000 1,300.00 211,900.00
Pasir Pasang C99 m3 0.520 100,000.00 52,000.00
JUMLAH HARGA BAHAN 437,900.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 671,900.00
E Overhead & Profit 10% 67,190.00
F Harga Satuan Pekerjaan (D+E) 739,090.00

Pemasangan 1 m3 pondasi batu belah campuran 1PC : 5PP


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = 3.1.1.3
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 136.000 1,300.00 176,800.00
Pasir Pasang C99 m3 0.544 100,000.00 54,400.00
JUMLAH HARGA BAHAN 405,200.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 639,200.00
E Overhead & Profit 10% 63,920.00
F Harga Satuan Pekerjaan (D+E) 703,120.00

Pemasangan 1 m3 pondasi batu belah campuran 1PC : 6PP


Kode AHSP = 3.1.1.4
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 117.000 1,300.00 152,100.00
Pasir Pasang C99 m3 0.561 100,000.00 56,100.00
JUMLAH HARGA BAHAN 382,200.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 616,200.00
E Overhead & Profit 10% 61,620.00
F Harga Satuan Pekerjaan (D+E) 677,820.00

Pemasangan 1 m3 pondasi batu belah campuran 1PC : 8PP


Kode AHSP = 3.1.1.5
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 91.000 1,300.00 118,300.00
Pasir Pasang C99 m3 0.584 100,000.00 58,400.00
JUMLAH HARGA BAHAN 350,700.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 584,700.00
E Overhead & Profit 10% 58,470.00
F Harga Satuan Pekerjaan (D+E) 643,170.00

Pemasangan 1 m3 pondasi batu belah campuran 1KP : 1SM : 2PP


Kode AHSP = 3.1.1.6
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Kapur Padam C262 m3 0.170 200,000.00 34,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Semen Portland C363 Kg 0.170 1,300.00 221.00
Pasir Pasang C99 m3 0.340 100,000.00 34,000.00
JUMLAH HARGA BAHAN 242,221.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 476,221.00
E Overhead & Profit 10% 47,622.10
F Harga Satuan Pekerjaan (D+E) 523,843.10

Pemasangan 1 m3 pondasi batu belah campuran 1 PC : 3 KP : 10 PP


Kode AHSP = 3.1.1.7
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 61.000 1,300.00 79,300.00
Kapur Padam C262 m3 0.147 200,000.00 29,400.00
Pasir Pasang C99 m3 0.492 100,000.00 49,200.00
JUMLAH HARGA BAHAN 331,900.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 565,900.00
E Overhead & Profit 10% 56,590.00
F Harga Satuan Pekerjaan (D+E) 622,490.00

Pemasangan 1 m3 pondasi batu belah campuran ¼ PC : 1 KP : 4PP


Kode AHSP = 3.1.1.8
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 41.000 1,300.00 53,300.00
Kapur Padam C262 m3 0.131 200,000.00 26,200.00
Pasir Pasang C99 m3 0.523 100,000.00 52,300.00
JUMLAH HARGA BAHAN 305,800.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 539,800.00
E Overhead & Profit 10% 53,980.00
F Harga Satuan Pekerjaan (D+E) 593,780.00

Pemasangan 1 m3 batu kosong (aanstamping) untuk pondasi gedung


Kode AHSP = 3.1.1.9
A TENAGA
Pekerja C9 OH 0.780 80,000.00 62,400.00
Tukang Batu C18 OH 0.390 125,000.00 48,750.00
Kepala Tukang C39 OH 0.039 150,000.00 5,850.00
Mandor C47 OH 0.039 120,000.00 4,680.00
JUMLAH TENAGA KERJA 121,680.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Pasir urug C100 m3 0.432 75,000.00 32,400.00

JUMLAH HARGA BAHAN 206,400.00


C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 328,080.00
E Overhead & Profit 10% 32,808.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 360,888.00

Pemasangan 1 m3 pondasi siklop. 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
Kode AHSP = 3.1.1.10
A TENAGA
Pekerja C9 OH 3.400 80,000.00 272,000.00
Tukang Batu C18 OH 0.850 125,000.00 106,250.00
Kepala Tukang C39 OH 0.085 150,000.00 12,750.00
Mandor C47 OH 0.170 120,000.00 20,400.00
JUMLAH TENAGA KERJA 411,400.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 0.480 145,000.00 69,600.00
Semen Portland C363 Kg 194.000 1,300.00 252,200.00
Pasir Beton C97 m3 0.312 100,000.00 31,200.00
Batu Kerikil C74 m3 0.468 400,000.00 187,200.00
Besi Beton (Polos/ulir) C161 Kg 126.000 12,000.00 1,512,000.00
Kawat beton C267 Kg 1.800 29,900.00 53,820.00
JUMLAH HARGA BAHAN 2,106,020.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2,517,420.00
E Overhead & Profit 10% 251,742.00
F Harga Satuan Pekerjaan (D+E) 2,769,162.00

Pemasangan 1 m3 pondasi sumuran. diameter 100 cm


Kode AHSP = 3.1.1.11
A TENAGA
Pekerja C9 OH 2.400 80,000.00 192,000.00
Tukang Batu C18 OH 0.800 125,000.00 100,000.00
Kepala Tukang C39 OH 0.080 150,000.00 12,000.00
Mandor C47 OH 0.119 120,000.00 14,280.00
JUMLAH TENAGA KERJA 318,280.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 0.450 145,000.00 65,250.00
Semen Portland C363 Kg 194.000 1,300.00 252,200.00
Pasir Beton C97 m3 0.312 100,000.00 31,200.00
Batu Kerikil C74 m3 0.468 400,000.00 187,200.00

JUMLAH HARGA BAHAN 535,850.00


C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 854,130.00
E Overhead & Profit 10% 85,413.00
F Harga Satuan Pekerjaan (D+E) 939,543.00

Mengerjakan 1 m' Tiang Pancang Berongga Dia. 50cm


Kode AHSP = 3.1.1.T1
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Tukang Las Konstruksi C28 OH 0.050 125,000.00 6,250.00
Mandor C47 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 49,250.00
B BAHAN
Tiang Pancang Berongga Dia. 50cm C407 m' 1.050 836,000.00 877,800.00
Kayu kelas II C81 M3 0.022 2,100,000.00 45,360.00
Kawat Las C272 Btg 10.000 3,250.00 32,500.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 955,660.00
C PERALATAN
Sewa Jack In Pile Hammer + Operator C1589 Jam 0.192 1,400,000.00 269,410.98
Sewa Crane Kapasitas 10-15 Ton C1584 Jam 0.199 1,608,257.14 320,252.01
JUMLAH HARGA ALAT JUMLAH HARGA ALAT 589,662.99
D Jumlah (A+B+C) 1,594,572.99
E Overhead & Profit 10% 159,457.30
F Harga Satuan Pekerjaan (D+E) 1,754,030.28

Mengerjakan 1 m' Tiang Pancang Berongga Dia. 40cm


Kode AHSP = 3.1.1.T2
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.500 80,000.00 40,000.00
Tukang Las Konstruksi C28 OH 0.050 125,000.00 6,250.00
Mandor C47 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 49,250.00
B BAHAN
Tiang Pancang Berongga Dia. 40cm C408 m' 1.050 563,000.00 591,150.00
Kayu kelas II C81 M3 0.022 2,100,000.00 45,360.00
Kawat Las C272 Btg 10.000 3,250.00 32,500.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 669,010.00
C PERALATAN
Sewa Jack In Pile Hammer + Operator C1589 Jam 0.192 1,400,000.00 269,410.98
Sewa Crane Kapasitas 10-15 Ton C1584 Jam 0.199 1,608,257.14 320,252.01
JUMLAH HARGA ALAT JUMLAH HARGA ALAT 589,662.99
D Jumlah (A+B+C) 1,307,922.99
E Overhead & Profit 10% 130,792.30
F Harga Satuan Pekerjaan (D+E) 1,438,715.28

Memotong 1 Titik Kepala Tiang Pancang


Kode AHSP = 3.1.1.T3
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Mandor C47 OH 0.500 120,000.00 60,000.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 144,000.00
B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 144,000.00
E Overhead & Profit 10% 14,400.00
F Harga Satuan Pekerjaan (D+E) 158,400.00

Menyambung 1 Titik Tiang Pancang


Kode AHSP = 3.1.1.T4
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Tukang Las Konstruksi C28 OH 0.050 125,000.00 6,250.00
Mandor C47 OH 0.500 120,000.00 60,000.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 150,250.00
B BAHAN
Kawat Las C272 Bh 12.500 3,250.00 40,625.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 40,625.00
C PERALATAN
Sewa Alat Las C1579 Jam 0.125 10,000.00 1,250.00
JUMLAH HARGA ALAT JUMLAH HARGA ALAT 1,250.00
D Jumlah (A+B+C) 192,125.00
E Overhead & Profit 10% 19,212.50
F Harga Satuan Pekerjaan (D+E) 211,337.50

Mengerjakan 1 m' Pengeboran Lubang Pondasi Dia.40 cm


Kode AHSP = 3.1.1.T5
A TENAGA
Pekerja OH
Mandor OH
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA -
B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN
Pressure Tank Kap. 1000 Ltr C1448 M 1.000 35,350,000.00 35,350,000.00

JUMLAH HARGA ALAT JUMLAH HARGA ALAT 35,350,000.00


D Jumlah (A+B+C) 35,350,000.00
E Overhead & Profit 10% 3,535,000.00
F Harga Satuan Pekerjaan (D+E) 38,885,000.00

Mengerjakan 1 m' Pengeboran Lubang Pondasi Dia.30 cm


Kode AHSP = 3.1.1.T6
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja OH
Mandor OH
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA -
B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN
Roof Drain C1449 M 1.000 252,500.00 252,500.00

JUMLAH HARGA ALAT JUMLAH HARGA ALAT 252,500.00


D Jumlah (A+B+C) 252,500.00
E Overhead & Profit 10% 25,250.00
F Harga Satuan Pekerjaan (D+E) 277,750.00

Mengerjakan 1 Titik Dewatering


Kode AHSP = 3.1.1.T7
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 17,200.00
B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN
Staight Way Valve Ø 63mm PPR C1465 Jam 1.000 871,226.00 871,226.00

JUMLAH HARGA ALAT JUMLAH HARGA ALAT 871,226.00


D Jumlah (A+B+C) 888,426.00
E Overhead & Profit 10% 88,842.60
F Harga Satuan Pekerjaan (D+E) 977,268.60

Mengerjakan 1 m3 Talud Camp. 1 PC : 5 PP + Pipa Resapan 2"


Kode AHSP = 3.1.1.T8
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu Kali C72 m3 1.200 200,000.00 240,000.00
Sabun C361 Kg 136.000 7,500.00 1,020,000.00
Pasir Pasang C99 m3 0.544 100,000.00 54,400.00
Kran Air Wudhu (TOTO Type TX130L) C1300 m' 1.500 437,000.00 655,500.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 1,969,900.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2,203,900.00
E Overhead & Profit 10% 220,390.00
F Harga Satuan Pekerjaan (D+E) 2,424,290.00

HARGA SATUAN PEKERJAAN BETON Kode AHSP = 4.1.1.


Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Kode AHSP = 4.1.1.1
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 247.000 1,300.00 321,100.00
Pasir beton (Kg) C98 Kg 869.000 71.43 62,071.43
Koral Beton (Kg) C93 Kg 999.000 203.70 203,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 608,171.43
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 788,706.43
E Overhead & Profit 10% 78,870.64
F Harga Satuan Pekerjaan (D+E) 867,577.07

Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Kode AHSP = 4.1.1.2
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 276.000 1,300.00 358,800.00
Pasir beton (Kg) C98 Kg 828.000 71.43 59,142.86
Koral Beton (Kg) C93 Kg 1012.000 203.70 206,148.15
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 645,591.01
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 826,126.01
E Overhead & Profit 10% 82,612.60
F Harga Satuan Pekerjaan (D+E) 908,738.61

Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Kode AHSP = 4.1.1.3
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 299.000 1,300.00 388,700.00
Pasir beton (Kg) C98 Kg 799.000 71.43 57,071.43
Koral Beton (Kg) C93 Kg 1017.000 203.70 207,166.67
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 674,438.10
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 854,973.10
E Overhead & Profit 10% 85,497.31
F Harga Satuan Pekerjaan (D+E) 940,470.40

Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),slump (3-6) cm, w/c = 0,87
Kode AHSP = 4.1.1.4
A TENAGA
Pekerja C9 OH 1.200 80,000.00 96,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.060 120,000.00 7,200.00
JUMLAH TENAGA KERJA 131,200.00
B BAHAN
Semen Portland C363 Kg 230.000 1,300.00 299,000.00
Pasir beton (Kg) C98 Kg 893.000 71.43 63,785.71
Koral Beton (Kg) C93 Kg 1027.000 203.70 209,203.70
Air C120 Ltr 200.000 100.00 20,000.00
JUMLAH HARGA BAHAN 591,989.42
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 723,189.42
E Overhead & Profit 10% 72,318.94
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 795,508.36

Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Kode AHSP = 4.1.1.5
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 326.000 1,300.00 423,800.00
Pasir beton (Kg) C98 Kg 760.000 71.43 54,285.71
Koral Beton (Kg) C93 Kg 1029.000 203.70 209,611.11
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 709,196.83
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 889,731.83
E Overhead & Profit 10% 88,973.18
F Harga Satuan Pekerjaan (D+E) 978,705.01

Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Kode AHSP = 4.1.1.6
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 352.000 1,300.00 457,600.00
Pasir beton (Kg) C98 Kg 731.000 71.43 52,214.29
Koral Beton (Kg) C93 Kg 1031.000 203.70 210,018.52
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 741,332.80
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 921,867.80
E Overhead & Profit 10% 92,186.78
F Harga Satuan Pekerjaan (D+E) 1,014,054.58

Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,5
Kode AHSP = 4.1.1.7
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 371.000 1,300.00 482,300.00
Pasir beton (Kg) C98 Kg 698.000 71.43 49,857.14
Koral Beton (Kg) C93 Kg 1047.000 203.70 213,277.78
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 766,934.92
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 947,469.92
E Overhead & Profit 10% 94,746.99
F Harga Satuan Pekerjaan (D+E) 1,042,216.91

Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Kode AHSP = 4.1.1.8
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 384.000 1,300.00 499,200.00
Pasir beton (Kg) C98 Kg 692.000 71.43 49,428.57
Koral Beton (Kg) C93 Kg 1039.000 203.70 211,648.15
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 781,776.72
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 962,311.72
E Overhead & Profit 10% 96,231.17
F Harga Satuan Pekerjaan (D+E) 1,058,542.89

Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Kode AHSP = 4.1.1.9
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Kepala tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 406.000 1,300.00 527,800.00
Pasir beton (Kg) C98 Kg 684.000 71.43 48,857.14
Koral Beton (Kg) C93 Kg 1026.000 203.70 209,000.00
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 807,157.14
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 987,692.14
E Overhead & Profit 10% 98,769.21
F Harga Satuan Pekerjaan (D+E) 1,086,461.36

Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Kode AHSP = 4.1.1.10
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 413.000 1,300.00 536,900.00
Pasir beton (Kg) C98 Kg 681.000 71.43 48,642.86
Koral Beton (Kg) C93 Kg 1021.000 203.70 207,981.48
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 815,024.34
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 995,559.34
E Overhead & Profit 10% 99,555.93
F Harga Satuan Pekerjaan (D+E) 1,095,115.27

Membuat 1 m3 beton kedap air dengan strorox – 100


Kode AHSP = 4.1.1.11
A TENAGA
Pekerja C9 OH 2.100 80,000.00 168,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.105 120,000.00 12,600.00
JUMLAH TENAGA KERJA 229,600.00
B BAHAN
Semen Portland C363 Kg 448.000 1,300.00 582,400.00
Pasir beton (Kg) C98 Kg 667.000 71.43 47,642.86
Koral Beton (Kg) C93 Kg 1000.000 203.70 203,703.70
Strorox – 100 C390 Ltr 215.000 25,000.00 5,375,000.00
JUMLAH HARGA BAHAN 6,208,746.56
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 6,438,346.56
E Overhead & Profit 10% 643,834.66
F Harga Satuan Pekerjaan (D+E) 7,082,181.22

Pemasangan 1 m' PVC Waterstop lebar 150mm


Kode AHSP = 4.1.1.12
A TENAGA
Pekerja C9 OH 0.060 80,000.00 4,800.00
Tukang Batu C18 OH 0.030 125,000.00 3,750.00
Kepala Tukang C39 OH 0.003 150,000.00 450.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 9,360.00
B BAHAN
Teak oil C404 M 1.050 1.00 1.05
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 1.05
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 9,361.05
E Overhead & Profit 10% 936.11
F Harga Satuan Pekerjaan (D+E) 10,297.16
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pembuatan 1 m3 Beton Kedap Air Dengan Aditif Kedap Air
Kode AHSP = 4.1.1.13
A TENAGA
Pekerja C9 OH 2.100 80,000.00 168,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.105 120,000.00 12,600.00
JUMLAH TENAGA KERJA 229,600.00
B BAHAN
Semen Portland C363 kg 400.000 1,300.00 520,000.00
Pasir beton (Kg) C98 m3 0.480 71.43 34.29
Koral Beton (Kg) C93 m3 0.800 203.70 162.96
Strorox – 100 C390 kg 1.200 25,000.00 30,000.00
air C120 Ltr 210.000 100.00 21,000.00

JUMLAH HARGA BAHAN 571,197.25


C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 800,797.25
E Overhead & Profit 10% 80,079.72
F Harga Satuan Pekerjaan (D+E) 880,876.97

Pemasangan 1 m' PVC Waterstop lebar 200mm


Kode AHSP = 4.1.1.13a
A TENAGA
Pekerja C9 OH 0.070 80,000.00 5,600.00
Tukang Batu C18 OH 0.035 125,000.00 4,375.00
Kepala Tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 11,415.00
B BAHAN
Waterstop lebar 200 mm C423 M 1.050 50,000.00 52,500.00

JUMLAH HARGA BAHAN 52,500.00


C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 63,915.00
E Overhead & Profit 10% 6,391.50
F Harga Satuan Pekerjaan (D+E) 70,306.50

Pemasangan 1 m' PVC Waterstop lebar 230-320mm


Kode AHSP = 4.1.1.14
A TENAGA
Pekerja C9 OH 0.080 80,000.00 6,400.00
Tukang Batu C18 OH 0.040 125,000.00 5,000.00
Kepala Tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 12,480.00
B BAHAN
Waterstop lebar 230-320 mm C424 M 1.050 75,000.00 78,750.00

JUMLAH HARGA BAHAN 78,750.00


C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 91,230.00
E Overhead & Profit 10% 9,123.00
F Harga Satuan Pekerjaan (D+E) 100,353.00

Pembesian 1 Kg dengan besi polos atau ulir


Kode AHSP = 4.1.1.15
A TENAGA
Pekerja C9 OH 0.007 80,000.00 560.00
Tukang Batu C18 OH 0.007 125,000.00 875.00
Kepala Tukang C39 OH 0.001 150,000.00 105.00
Mandor C47 OH 0.000 120,000.00 48.00
JUMLAH TENAGA KERJA 1,588.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Besi beton (polos/ulir) C161 Kg 1.050 12,000.00 12,600.00
Kawat beton C267 Kg 0.015 29,900.00 448.50
JUMLAH HARGA BAHAN 13,048.50
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 14,636.50
E Overhead & Profit 10% 1,463.65
F Harga Satuan Pekerjaan (D+E) 16,100.15

Pemasangan 10 kg kabel presstressed polos/strands


Kode AHSP = 4.1.1.16
A TENAGA
Pekerja C9 OH 0.050 80,000.00 4,000.00
Tukang Batu C18 OH 0.050 125,000.00 6,250.00
Kepala Tukang C39 OH 0.005 150,000.00 750.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 11,360.00
B BAHAN
Besi beton (polos/ulir) C161 Kg 10.500 12,000.00 126,000.00
Kawat beton C267 Kg 0.100 29,900.00 2,990.00
JUMLAH HARGA BAHAN 128,990.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 140,350.00
E Overhead & Profit 10% 14,035.00
F Harga Satuan Pekerjaan (D+E) 154,385.00

Pemasangan 1 kg Jaring kawat baja (wiremesh) M6-M8


Kode AHSP = 4.1.1.17
A TENAGA
Pekerja C9 OH 0.003 80,000.00 200.00
Tukang Batu C18 OH 0.003 125,000.00 312.50
Kepala Tukang C39 OH 0.003 150,000.00 375.00
Mandor C47 OH 0.000 120,000.00 12.00
JUMLAH TENAGA KERJA 899.50
B BAHAN
Wiremesh C426 Kg 1.020 12,380.64 12,628.26
Kawat beton C267 Kg 0.005 29,900.00 149.50
JUMLAH HARGA BAHAN 12,777.76
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 13,677.26
E Overhead & Profit 10% 1,367.73
F Harga Satuan Pekerjaan (D+E) 15,044.98

Pemasangan 1 m2 bekisting untuk pondasi


Kode AHSP = 4.1.1.18
A TENAGA
Pekerja C9 OH 0.520 80,000.00 41,600.00
Tukang Batu C18 OH 0.260 125,000.00 32,500.00
Kepala Tukang C39 OH 0.026 150,000.00 3,900.00
Mandor C47 OH 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 81,120.00
B BAHAN
Kayu kelas III C86 m3 0.040 1,600,000.00 64,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.300 21,000.00 6,300.00
Minyak bekisting C302 Liter 0.100 5,100.00 510.00
JUMLAH HARGA BAHAN 70,300.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 151,420.00
E Overhead & Profit 10% 15,142.00
F Harga Satuan Pekerjaan (D+E) 166,562.00

Pemasangan 1 m2 bekisting untuk pondasi (2x)


Kode AHSP = 4.1.1.18a
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja C9 OH 0.520 80,000.00 41,600.00
Tukang Batu C18 OH 0.260 125,000.00 32,500.00
Kepala Tukang C39 OH 0.026 150,000.00 3,900.00
Mandor C47 OH 0.0260 120,000.00 3,120.00
JUMLAH TENAGA KERJA 81,120.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 24,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.300 21,000.00 6,300.00
Minyak bekisting C302 Liter 0.100 5,100.00 510.00
JUMLAH HARGA BAHAN 30,300.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 111,420.00
E Overhead & Profit 10% 11,142.00
F Harga Satuan Pekerjaan (D+E) 122,562.00

Pemasangan 1 m2 bekisting untuk sloof


Kode AHSP = 4.1.1.19
A TENAGA
Pekerja C9 OH 0.520 80,000.00 41,600.00
Tukang Batu C18 OH 0.260 125,000.00 32,500.00
Kepala Tukang C39 OH 0.026 150,000.00 3,900.00
Mandor C47 OH 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 81,120.00
B BAHAN
Kayu kelas III C86 m3 0.045 1,600,000.00 72,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.300 21,000.00 6,300.00
Minyak bekisting C302 Liter 0.100 5,100.00 510.00
JUMLAH HARGA BAHAN 78,810.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 159,930.00
E Overhead & Profit 10% 15,993.00
F Harga Satuan Pekerjaan (D+E) 175,923.00

Pemasangan 1 m2 bekisting untuk sloof (2x)


Kode AHSP = 4.1.1.19a
A TENAGA
Pekerja C9 OH 0.520 80,000.00 41,600.00
Tukang Batu C18 OH 0.260 125,000.00 32,500.00
Kepala Tukang C39 OH 0.026 150,000.00 3,900.00
Mandor C47 OH 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 81,120.00
B BAHAN
Kayu kelas III C86 m3 0.034 1,600,000.00 27,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.300 21,000.00 6,300.00
Minyak bekisting C302 Liter 0.100 5,100.00 510.00
JUMLAH HARGA BAHAN 33,810.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 114,930.00
E Overhead & Profit 10% 11,493.00
F Harga Satuan Pekerjaan (D+E) 126,423.00

Pemasangan 1 m2 bekisting untuk kolom


Kode AHSP = 4.1.1.20
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.040 1,600,000.00 64,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.015 2,250,000.00 33,750.00
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 2.000 20,900.00 41,800.00
JUMLAH HARGA BAHAN 178,720.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 281,680.00
E Overhead & Profit 10% 28,168.00
F Harga Satuan Pekerjaan (D+E) 309,848.00

Pemasangan 1 m2 bekisting untuk kolom (2x)


Kode AHSP = 4.1.1.20a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.011 2,250,000.00 25,312.50
Plywood 9 mm C350 Lbr 0.263 85,000.00 22,312.50
Dolken kayu, φ8-10/400 cm C77 Batang 1.500 20,900.00 31,350.00
JUMLAH HARGA BAHAN 136,395.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 239,355.00
E Overhead & Profit 10% 23,935.50
F Harga Satuan Pekerjaan (D+E) 263,290.50

Pemasangan 1 m2 bekisting untuk balok


Kode AHSP = 4.1.1.21
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.040 1,600,000.00 64,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.018 2,250,000.00 40,500.00
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 2.000 20,900.00 41,800.00
JUMLAH HARGA BAHAN 185,470.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 288,430.00
E Overhead & Profit 10% 28,843.00
F Harga Satuan Pekerjaan (D+E) 317,273.00

Pemasangan 1 m2 bekisting untuk balok (2x)


Kode AHSP = 4.1.1.21a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.014 2,250,000.00 30,375.00
Tripleks 9 mm C413 Lbr 0.263 48,611.11 12,760.42
Dolken kayu, φ8-10/400 cm C77 Batang 1.500 20,900.00 31,350.00
JUMLAH HARGA BAHAN 131,905.42
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 234,865.42
E Overhead & Profit 10% 23,486.54
F Harga Satuan Pekerjaan (D+E) 258,351.96

Pemasangan 1 m2 bekisting untuk plat lantai beton bangunan gedung


Kode AHSP = 4.1.1.22
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.040 1,600,000.00 64,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.015 2,250,000.00 33,750.00
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 6.000 20,900.00 125,400.00
JUMLAH HARGA BAHAN 262,320.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 365,280.00
E Overhead & Profit 10% 36,528.00
F Harga Satuan Pekerjaan (D+E) 401,808.00

Pemasangan 1 m2 bekisting untuk plat lantai beton bangunan gedung (2x)


Kode AHSP = 4.1.1.22a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.011 2,250,000.00 25,312.50
Tripleks 9 mm C413 Lbr 0.263 48,611.11 12,760.42
Dolken kayu, φ8-10/400 cm C77 Batang 4.500 20,900.00 94,050.00
JUMLAH HARGA BAHAN 189,542.92
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 292,502.92
E Overhead & Profit 10% 29,250.29
F Harga Satuan Pekerjaan (D+E) 321,753.21

Pemasangan 1 m2 bekisting untuk dinding sheerwall


Kode AHSP = 4.1.1.23
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.020 2,250,000.00 45,000.00
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 3.000 20,900.00 62,700.00
Penjaga jarak bekisting/spacer C335 Buah 4.000 25,000.00 100,000.00
JUMLAH HARGA BAHAN 294,870.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 397,830.00
E Overhead & Profit 10% 39,783.00
F Harga Satuan Pekerjaan (D+E) 437,613.00

Pemasangan 1 m2 bekisting untuk dinding sheerwall (2x)


Kode AHSP = 4.1.1.23a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.023 1,600,000.00 36,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.015 2,250,000.00 33,750.00
Plywood 9 mm C350 Lbr 0.263 85,000.00 22,312.50
Dolken kayu, φ8-10/400 cm C77 Batang 2.250 20,900.00 47,025.00
Penjaga jarak bekisting/spacer C335 Buah 3.000 25,000.00 75,000.00
JUMLAH HARGA BAHAN 223,507.50
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 326,467.50
E Overhead & Profit 10% 32,646.75
F Harga Satuan Pekerjaan (D+E) 359,114.25

Pemasangan 1 m2 bekisting untuk tangga


Kode AHSP = 4.1.1.24
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.150 5,100.00 765.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Balok kayu kelas II C67 m3 0.015 2,250,000.00 33,750.00
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 2.000 20,900.00 41,800.00
JUMLAH HARGA BAHAN 162,465.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 265,425.00
E Overhead & Profit 10% 26,542.50
F Harga Satuan Pekerjaan (D+E) 291,967.50

Pemasangan 1 m2 bekisting untuk tangga (2x)


Kode AHSP = 4.1.1.24a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.023 1,600,000.00 36,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.150 5,100.00 765.00
Balok kayu kelas II C67 m3 0.011 2,250,000.00 25,312.50
Plywood 9 mm C350 Lbr 0.263 85,000.00 22,312.50
Dolken kayu, φ8-10/400 cm C77 Batang 1.500 20,900.00 31,350.00
JUMLAH HARGA BAHAN 124,140.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 227,100.00
E Overhead & Profit 10% 22,710.00
F Harga Satuan Pekerjaan (D+E) 249,810.00

Pemasangan 1 m2 bekisting untuk tangga beton bangunan gedung


Kode AHSP = 4.1.1.25
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.150 5,100.00 765.00
Balok kayu kelas II C67 m3 0.015 2,250,000.00 33,750.00
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 2.000 20,900.00 41,800.00
JUMLAH HARGA BAHAN 162,465.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 265,425.00
E Overhead & Profit 10% 26,542.50
F Harga Satuan Pekerjaan (D+E) 291,967.50

Pemasangan 1 m2 bekisting untuk tangga beton bangunan gedung (2x)


Kode AHSP = 4.1.1.25a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.023 1,600,000.00 36,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.150 5,100.00 765.00
Balok kayu kelas II C67 m3 0.011 2,250,000.00 25,312.50
Plywood 9 mm C350 Lbr 0.350 85,000.00 29,750.00
Dolken kayu, φ8-10/400 cm C77 Batang 2.000 20,900.00 41,800.00
JUMLAH HARGA BAHAN 142,027.50
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 244,987.50
E Overhead & Profit 10% 24,498.75
F Harga Satuan Pekerjaan (D+E) 269,486.25

Pembuatan 1 m' kolom praktis beton bertulang (11x11)


Kode AHSP = 4.1.1.26
A TENAGA
Pekerja C9 OH 0.180 80,000.00 14,400.00
Tukang batu C18 OH 0.020 125,000.00 2,500.00
Tukang kayu C19 OH 0.020 125,000.00 2,500.00
Tukang besi C20 OH 0.020 125,000.00 2,500.00
Kepala tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 23,880.00
B BAHAN
Kayu kelas III C86 m3 0.002 1,600,000.00 3,200.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.010 21,000.00 210.00
Minyak bekisting C302 Ltr 5,100.00 -
Besi Beton (Polos/ulir) C161 Kg 3.000 12,000.00 36,000.00
Kawat beton C267 Kg 0.450 29,900.00 13,455.00
Semen Portland C363 Kg 4.000 1,300.00 5,200.00
Pasir Beton C97 M3 0.006 100,000.00 600.00
koral beton C92 M3 0.009 275,000.00 2,475.00
JUMLAH HARGA BAHAN 61,140.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 85,020.00
E Overhead & Profit 10% 8,502.00
F Harga Satuan Pekerjaan (D+E) 93,522.00

Pembuatan 1 m' ring balok beton bertulang (10x15)


Kode AHSP = 4.1.1.27
A TENAGA
Pekerja C9 OH 0.297 80,000.00 23,760.00
Tukang batu C18 OH 0.033 125,000.00 4,125.00
Tukang kayu C19 OH 0.033 125,000.00 4,125.00
Tukang besi C20 OH 0.033 125,000.00 4,125.00
Kepala tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,435.00
B BAHAN
Kayu kelas III C86 m3 0.003 1,600,000.00 4,800.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.020 21,000.00 420.00
Minyak bekisting C302 Ltr 5,100.00 -
Besi Beton (Polos/ulir) C161 Kg 3.600 12,000.00 43,200.00
Kawat beton C267 Kg 0.050 29,900.00 1,495.00
Semen Portland C363 Kg 5.500 1,300.00 7,150.00
Pasir Beton C97 M3 0.009 100,000.00 900.00
Batu Kerikil C74 M3 0.015 400,000.00 6,000.00
JUMLAH HARGA BAHAN 63,965.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 103,400.00
E Overhead & Profit 10% 10,340.00
F Harga Satuan Pekerjaan (D+E) 113,740.00

Pemasangan 1 m2 jembatan untuk pengecoran beton


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = 4.1.1.28
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang batu C18 OH 0.050 125,000.00 6,250.00
Kepala tukang C39 OH 0.005 150,000.00 750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 19,960.00
B BAHAN
Kayu kelas III C86 m3 0.023 1,600,000.00 36,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Ltr 0.150 5,100.00 765.00
JUMLAH HARGA BAHAN 45,165.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 65,125.00
E Overhead & Profit 10% 6,512.50
F Harga Satuan Pekerjaan (D+E) 71,637.50

Pembuatan 1 m3 pondasi beton bertulang (150 kg besi)


Kode AHSP = 4.1.1.T1
A TENAGA
Pekerja C9 OH 5.300 80,000.00 424,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.300 125,000.00 162,500.00
Tukang besi C20 OH 1.050 125,000.00 131,250.00
Kepala tukang C39 OH 0.262 150,000.00 39,300.00
Mandor C47 OH 0.265 120,000.00 31,800.00
JUMLAH TENAGA KERJA 823,225.00
B BAHAN
Kayu kelas III C86 m3 0.023 1,600,000.00 36,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.023 21,000.00 472.50
Minyak bekisting C302 Ltr 0.023 5,100.00 114.75
Besi Beton (Polos/ulir) C161 Kg 0.023 12,000.00 270.00
Kawat beton C267 Kg 0.023 29,900.00 672.75
Semen Portland C363 Kg 0.023 1,300.00 29.25
Pasir Beton C97 M3 0.400 100,000.00 40,000.00
Batu Kerikil C74 M3 0.150 400,000.00 60,000.00
JUMLAH HARGA BAHAN 137,559.25
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 960,784.25
E Overhead & Profit 10% 96,078.43
F Harga Satuan Pekerjaan (D+E) 1,056,862.68

Pembuatan 1 m3 sloof beton bertulang (200 kg besi)


Kode AHSP = 4.1.1.T2
A TENAGA
Pekerja C9 OH 5.650 80,000.00 452,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.560 125,000.00 195,000.00
Tukang besi C20 OH 1.400 125,000.00 175,000.00
Kepala tukang C39 OH 0.323 150,000.00 48,450.00
Mandor C47 OH 0.283 120,000.00 33,960.00
JUMLAH TENAGA KERJA 938,785.00
B BAHAN
Kayu kelas III C86 m3 0.270 1,600,000.00 432,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 2.000 21,000.00 42,000.00
Minyak bekisting C302 Ltr 0.600 5,100.00 3,060.00
Besi Beton (Polos/ulir) C161 Kg 210.000 12,000.00 2,520,000.00
Kawat beton C267 Kg 3.000 29,900.00 89,700.00
Semen Portland C363 Kg 336.000 1,300.00 436,800.00
Pasir Beton C97 M3 0.540 100,000.00 54,000.00
Batu Kerikil C74 M3 0.810 400,000.00 324,000.00
JUMLAH HARGA BAHAN 3,901,560.00
C PERALATAN - - -
- - -
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,840,345.00
E Overhead & Profit 10% 484,034.50
F Harga Satuan Pekerjaan (D+E) 5,324,379.50

Pembuatan 1 m3 kolom beton bertulang (300 kg besi)


Kode AHSP = 4.1.1.T3
A TENAGA
Pekerja C9 OH 7.050 80,000.00 564,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.650 125,000.00 206,250.00
Tukang besi C20 OH 2.100 125,000.00 262,500.00
Kepala tukang C39 OH 0.403 150,000.00 60,450.00
Mandor C47 OH 0.353 120,000.00 42,360.00
JUMLAH TENAGA KERJA 1,169,935.00
B BAHAN
Kayu kelas III C86 m3 0.400 1,600,000.00 640,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 4.000 21,000.00 84,000.00
Minyak bekisting C302 Ltr 2.000 5,100.00 10,200.00
Besi Beton (Polos/ulir) C161 Kg 315.000 12,000.00 3,780,000.00
Kawat beton C267 Kg 4.500 29,900.00 134,550.00
Semen Portland C363 Kg 336.000 1,300.00 436,800.00
Pasir Beton C97 M3 0.540 100,000.00 54,000.00
Batu Kerikil C74 M3 0.810 400,000.00 324,000.00
Balok Kayu Kelas II C67 M3 0.150 2,250,000.00 337,500.00
Plywood 9 mm C350 Lbr 3.500 85,000.00 297,500.00
Dolken kayu, φ8-10/400 cm C77 Btg 20.000 20,900.00 418,000.00
JUMLAH HARGA BAHAN 6,516,550.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 7,686,485.00
E Overhead & Profit 10% 768,648.50
F Harga Satuan Pekerjaan (D+E) 8,455,133.50

Pembuatan 1 m3 balok beton bertulang (200 kg besi)


Kode AHSP = 4.1.1.T4
A TENAGA
Pekerja C9 OH 6.350 80,000.00 508,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.650 125,000.00 206,250.00
Tukang besi C20 OH 1.400 125,000.00 175,000.00
Kepala tukang C39 OH 0.333 150,000.00 49,950.00
Mandor C47 OH 0.318 120,000.00 38,160.00
JUMLAH TENAGA KERJA 1,011,735.00
B BAHAN
Kayu kelas III C86 m3 0.320 1,600,000.00 512,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 3.200 21,000.00 67,200.00
Minyak bekisting C302 Ltr 1.600 5,100.00 8,160.00
Besi Beton (Polos/ulir) C161 Kg 210.000 12,000.00 2,520,000.00
Kawat beton C267 Kg 3.000 29,900.00 89,700.00
Semen Portland C363 Kg 336.000 1,300.00 436,800.00
Pasir Beton C97 M3 0.540 100,000.00 54,000.00
Batu Kerikil C74 M3 0.810 400,000.00 324,000.00
Balok Kayu Kelas II C67 M3 0.140 2,250,000.00 315,000.00
Plywood 9 mm C350 Lbr 2.800 85,000.00 238,000.00
Dolken kayu, φ8-10/400 cm C77 Btg 16.000 20,900.00 334,400.00
JUMLAH HARGA BAHAN 4,899,260.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 5,910,995.00
E Overhead & Profit 10% 591,099.50
F Harga Satuan Pekerjaan (D+E) 6,502,094.50

Pembuatan 1 m3 plat beton bertulang (150 kg besi)


Kode AHSP = 4.1.1.T5
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja C9 OH 5.300 80,000.00 424,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.300 125,000.00 162,500.00
Tukang besi C20 OH 1.050 125,000.00 131,250.00
Kepala tukang C39 OH 0.265 150,000.00 39,750.00
Mandor C47 OH 0.265 120,000.00 31,800.00
JUMLAH TENAGA KERJA 823,675.00
B BAHAN
Kayu kelas III C86 m3 0.320 1,600,000.00 512,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 3.200 21,000.00 67,200.00
Minyak bekisting C302 Ltr 1.600 5,100.00 8,160.00
Besi Beton (Polos/ulir) C161 Kg 157.500 12,000.00 1,890,000.00
Kawat beton C267 Kg 2.250 29,900.00 67,275.00
Semen Portland C363 Kg 336.000 1,300.00 436,800.00
Pasir Beton C97 M3 0.540 100,000.00 54,000.00
Batu Kerikil C74 M3 0.810 400,000.00 324,000.00
Balok Kayu Kelas II C67 M3 0.120 2,250,000.00 270,000.00
Plywood 9 mm C350 Lbr 2.800 85,000.00 238,000.00
Dolken kayu, φ8-10/400 cm C77 Btg 32.000 20,900.00 668,800.00
JUMLAH HARGA BAHAN 4,536,235.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 5,359,910.00
E Overhead & Profit 10% 535,991.00
F Harga Satuan Pekerjaan (D+E) 5,895,901.00

Pembuatan 1 m3 dinding beton bertulang (150 kg besi)


Kode AHSP = 4.1.1.T6
A TENAGA
Pekerja C9 OH 5.300 80,000.00 424,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.300 125,000.00 162,500.00
Tukang besi C20 OH 1.050 125,000.00 131,250.00
Kepala tukang C39 OH 0.262 150,000.00 39,300.00
Mandor C47 OH 0.265 120,000.00 31,800.00
JUMLAH TENAGA KERJA 823,225.00
B BAHAN
Kayu kelas III C86 m3 0.240 1,600,000.00 384,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 3.200 21,000.00 67,200.00
Minyak bekisting C302 Ltr 1.600 5,100.00 8,160.00
Besi Beton (Polos/ulir) C161 Kg 157.500 12,000.00 1,890,000.00
Kawat beton C267 Kg 2.250 29,900.00 67,275.00
Semen Portland C363 Kg 336.000 1,300.00 436,800.00
Pasir Beton C97 M3 0.540 100,000.00 54,000.00
Batu Kerikil C74 M3 0.810 400,000.00 324,000.00
Balok Kayu Kelas II C67 M3 0.160 2,250,000.00 360,000.00
Plywood 9 mm C350 Lbr 2.800 85,000.00 238,000.00
Dolken kayu, φ8-10/400 cm C77 Btg 24.000 20,900.00 501,600.00
JUMLAH HARGA BAHAN 4,331,035.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 5,154,260.00
E Overhead & Profit 10% 515,426.00
F Harga Satuan Pekerjaan (D+E) 5,669,686.00

Pembuatan 1 m3 dinding beton bertulang (200 kg besi)


Kode AHSP = 4.1.1.T7
A TENAGA
Pekerja C9 OH 5.650 80,000.00 452,000.00
Tukang batu C18 OH 0.275 125,000.00 34,375.00
Tukang kayu C19 OH 1.560 125,000.00 195,000.00
Tukang besi C20 OH 1.400 125,000.00 175,000.00
Kepala tukang C39 OH 0.323 150,000.00 48,450.00
Mandor C47 OH 0.283 120,000.00 33,960.00
JUMLAH TENAGA KERJA 938,785.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Kayu kelas III C86 m3 0.250 1,600,000.00 400,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 3.000 21,000.00 63,000.00
Minyak bekisting C302 Ltr 1.200 5,100.00 6,120.00
Besi Beton (Polos/ulir) C161 Kg 210.000 12,000.00 2,520,000.00
Kawat beton C267 Kg 3.000 29,900.00 89,700.00
Semen Portland C363 Kg 336.000 1,300.00 436,800.00
Pasir Beton C97 M3 0.540 100,000.00 54,000.00
Batu Kerikil C74 M3 0.810 400,000.00 324,000.00
Balok Kayu Kelas II C67 M3 0.105 2,250,000.00 236,250.00
Plywood 9 mm C350 Lbr 2.500 85,000.00 212,500.00
Dolken kayu, φ8-10/400 cm C77 Btg 14.000 20,900.00 292,600.00
JUMLAH HARGA BAHAN 4,634,970.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 5,573,755.00
E Overhead & Profit 10% 557,375.50
F Harga Satuan Pekerjaan (D+E) 6,131,130.50

Mengerjakan 1 m3 beton ready mix mutu K400


Kode AHSP = 4.1.1.T8
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang batu C18 OH 0.250 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.100 120,000.00 12,000.00
JUMLAH TENAGA KERJA 127,000.00
B BAHAN
Ready Mix K-400 C360 m3 1.050 1,300,000.00 1,365,000.00
Curing Beton (Penyiraman Min. 2x selama 3 hari) C1540 Ls 1.000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 1,375,000.00


C PERALATAN
Sewa Alat Concrete Pump C1578 Jam 0.200 625,000.00 125,000.00
- - -
JUMLAH HARGA ALAT 125,000.00
D Jumlah (A+B+C) 1,627,000.00
E Overhead & Profit 10% 162,700.00
F Harga Satuan Pekerjaan (D+E) 1,789,700.00

Mengerjakan 1 m3 beton ready mix mutu K350


Kode AHSP = 4.1.1.T9
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang batu C18 OH 0.250 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.100 120,000.00 12,000.00
JUMLAH TENAGA KERJA 127,000.00
B BAHAN
Ready Mix K-350 C359 m3 1.050 1,210,000.00 1,270,500.00
Curing Beton (Penyiraman Min. 2x selama 3 hari) C1540 Ls 1.000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 1,280,500.00


C PERALATAN
Sewa Alat Concrete Pump C1578 Jam 0.200 625,000.00 125,000.00
- - -
JUMLAH HARGA ALAT 125,000.00
D Jumlah (A+B+C) 1,532,500.00
E Overhead & Profit 10% 153,250.00
F Harga Satuan Pekerjaan (D+E) 1,685,750.00

Mengerjakan 1 m3 beton ready mix mutu K300


Kode AHSP = 4.1.1.T10
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang batu C18 OH 0.250 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.100 120,000.00 12,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 127,000.00
B BAHAN
Ready Mix K-300 C358 m3 1.050 1,110,000.00 1,165,500.00
Curing Beton (Penyiraman Min. 2x selama 3 hari) C1540 Ls 1.000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 1,175,500.00


C PERALATAN
Sewa Alat Concrete Pump C1578 Jam 0.200 625,000.00 125,000.00
- - -
JUMLAH HARGA ALAT 125,000.00
D Jumlah (A+B+C) 1,427,500.00
E Overhead & Profit 10% 142,750.00
F Harga Satuan Pekerjaan (D+E) 1,570,250.00

Mengerjakan 1 m3 beton ready mix mutu K250


Kode AHSP = 4.1.1.T11
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang batu C18 OH 0.250 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.100 120,000.00 12,000.00
JUMLAH TENAGA KERJA 127,000.00
B BAHAN
Ready Mix K-250 C357 m3 1.050 1,030,000.00 1,081,500.00
Curing Beton (Penyiraman Min. 2x selama 3 hari) C1540 Ls 1.000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 1,091,500.00


C PERALATAN
Sewa Alat Concrete Pump C1578 Jam 0.200 625,000.00 125,000.00
- - -
JUMLAH HARGA ALAT 125,000.00
D Jumlah (A+B+C) 1,343,500.00
E Overhead & Profit 10% 134,350.00
F Harga Satuan Pekerjaan (D+E) 1,477,850.00

pemasangan 1 m2 Floor Deck


Kode AHSP = 4.1.1.T12
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Pekerja Las Kontruksi C16 OH 0.100 80,000.00 8,000.00
Kepala tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 17,620.00
B BAHAN
Stud Connector C392 Bh 40.000 2,500.00 100,000.00
Floor Deck C220 m2 1.100 151,000.00 166,100.00
JUMLAH HARGA BAHAN 266,100.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 283,720.00
E Overhead & Profit 10% 28,372.00
F Harga Satuan Pekerjaan (D+E) 312,092.00

Membuat 1 m3 beton tumbuk 1 PC : 3 PP : 5 KR


Kode AHSP = 4.1.1.T13
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang C17 OH 0.250 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.080 120,000.00 9,600.00
JUMLAH TENAGA KERJA 176,600.00
B BAHAN
Semen Portland C363 Kg 218.000 1,300.00 283,400.00
Pasir beton C97 m3 0.520 100,000.00 52,000.00
Koral beton C92 m3 0.870 275,000.00 239,250.00
JUMLAH HARGA BAHAN 574,650.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 751,250.00
E Overhead & Profit 10% 75,125.00
F Harga Satuan Pekerjaan (D+E) 826,375.00

Membuat 1 m' profil beton, t = 1 cm - 10 cm


Kode AHSP = 4.1.1.T14
A TENAGA
Pekerja C9 OH 0.550 80,000.00 44,000.00
Tukang terampil C37 OH 0.900 150,000.00 135,000.00

JUMLAH TENAGA KERJA 179,000.00


B BAHAN
Semen Portland C363 Kg 3.500 1,300.00 4,550.00
Pasir pasang C99 m3 0.0055 100,000.00 550.00
Besi Beton (Polos/Ulir) C161 Kg 0.197 12,000.00 2,366.30
JUMLAH HARGA BAHAN 7,466.30
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 186,466.30
E Overhead & Profit 10% 18,646.63
F Harga Satuan Pekerjaan (D+E) 205,112.93

Membuat 1 m' profil beton, t = 11 cm - 30 cm


Kode AHSP = 4.1.1.T15
A TENAGA
Pekerja C9 OH 0.850 80,000.00 68,000.00
Tukang terampil C37 OH 1.100 150,000.00 165,000.00

JUMLAH TENAGA KERJA 233,000.00


B BAHAN
Semen Portland C363 Kg 17.500 1,300.00 22,750.00
Pasir pasang C99 m3 0.0165 100,000.00 1,650.00
Besi Beton (Polos/Ulir) C161 Kg 0.394 12,000.00 4,732.61
JUMLAH HARGA BAHAN 29,132.61
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 262,132.61
E Overhead & Profit 10% 26,213.26
F Harga Satuan Pekerjaan (D+E) 288,345.87

Membuat 1 m' profil beton, t = 31 cm - 50 cm


Kode AHSP = 4.1.1.T16
A TENAGA
Pekerja C9 OH 1.100 80,000.00 88,000.00
Tukang terampil C37 OH 1.500 150,000.00 225,000.00

JUMLAH TENAGA KERJA 313,000.00


B BAHAN
Semen Portland C363 Kg 15.000 1,300.00 19,500.00
Pasir pasang C99 m3 0.0275 100,000.00 2,750.00
Besi Beton (Polos/Ulir) C161 Kg 0.592 12,000.00 7,098.91
JUMLAH HARGA BAHAN 29,348.91
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 342,348.91
E Overhead & Profit 10% 34,234.89
F Harga Satuan Pekerjaan (D+E) 376,583.80

Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = 4.1.1.T17
A TENAGA
Pekerja C9 OH 2.100 80,000.00 168,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.105 120,000.00 12,600.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 229,600.00
B BAHAN
Semen Portland C363 Kg 439.000 1,300.00 570,700.00
Pasir pasang C99 Kg 670.000 100,000.00 67,000,000.00
Papan kayu kelas I C94 Kg 1006.000 4,000,000.00 4,024,000,000.00
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 4,091,592,200.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,091,821,800.00
E Overhead & Profit 10% 409,182,180.00
F Harga Satuan Pekerjaan (D+E) 4,501,003,980.00

Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Kode AHSP =
A TENAGA
Pekerja C9 OH 2.100 80,000.00 168,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.105 120,000.00 12,600.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 229,600.00
B BAHAN
Semen Portland C363 Kg 448.000 1,300.00 582,400.00
Pasir pasang C99 Kg 667.000 100,000.00 66,700,000.00
Papan kayu kelas I C94 Kg 1000.000 4,000,000.00 4,000,000,000.00
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 4,067,303,900.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,067,533,500.00
E Overhead & Profit 10% 406,753,350.00
F Harga Satuan Pekerjaan (D+E) 4,474,286,850.00

Pembuatan 1 m2 lahan produksi tebal 8cm beton f’c 14.5 Mpa (K 175) slump (12 ± 2)
Kode AHSP = 4.1.2.1
A TENAGA
Pekerja C9 OH 0.132 80,000.00 10,560.00
Tukang batu C18 OH 0.022 125,000.00 2,750.00
Kepala tukang C39 OH 0.002 150,000.00 300.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 14,450.00
B BAHAN
Semen Portland C363 Kg 26.080 1,300.00 33,904.00
Pasir beton (Kg) C98 Kg 60.8000 71.43 4,342.86
Koral Beton (Kg) C93 Kg 82.320 203.70 16,768.89
Air C120 Ltr 17.200 100.00 1,720.00
JUMLAH HARGA BAHAN 56,735.75
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 71,185.75
E Overhead & Profit 10% 7,118.57
F Harga Satuan Pekerjaan (D+E) 78,304.32

Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14.5 Mpa (K 175) slump (12 ±2) cm
Kode AHSP = 4.1.2.2
A TENAGA
Pekerja C9 OH 0.165 80,000.00 13,200.00
Tukang batu C18 OH 0.028 125,000.00 3,500.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 18,110.00
B BAHAN
Semen Portland C363 Kg 32.600 1,300.00 42,380.00
Pasir beton (Kg) C98 Kg 76.0000 71.43 5,428.57
Koral Beton (Kg) C93 Kg 102.900 203.70 20,961.11
Air C120 Ltr 21.500 100.00 2,150.00
JUMLAH HARGA BAHAN 70,919.68
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 89,029.68
E Overhead & Profit 10% 8,902.97
F Harga Satuan Pekerjaan (D+E) 97,932.65

Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14.5 Mpa (K 175) slump (12 ±2) cm
Kode AHSP = 4.1.2.3
A TENAGA
Pekerja C9 OH 0.198 80,000.00 15,840.00
Tukang batu C18 OH 0.033 125,000.00 4,125.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 21,615.00
B BAHAN
Semen Portland C363 Kg 32.120 1,300.00 41,756.00
Pasir beton (Kg) C98 Kg 91.2000 71.43 6,514.29
Koral Beton (Kg) C93 Kg 123.480 203.70 25,153.33
Air C120 Ltr 25.800 100.00 2,580.00
JUMLAH HARGA BAHAN 76,003.62
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 97,618.62
E Overhead & Profit 10% 9,761.86
F Harga Satuan Pekerjaan (D+E) 107,380.48

Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14.5 Mpa (K 175) slump (12 ±2) cm
Kode AHSP = 4.1.2.4
A TENAGA
Pekerja C9 OH 0.248 80,000.00 19,840.00
Tukang batu C18 OH 0.041 125,000.00 5,125.00
Kepala tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 27,125.00
B BAHAN
Semen Portland C363 Kg 48.900 1,300.00 63,570.00
Pasir beton (Kg) C98 Kg 114.0000 71.43 8,142.86
Koral Beton (Kg) C93 Kg 154.350 203.70 31,441.67
Air C120 Ltr 32.250 100.00 3,225.00
JUMLAH HARGA BAHAN 106,379.52
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 133,504.52
E Overhead & Profit 10% 13,350.45
F Harga Satuan Pekerjaan (D+E) 146,854.98

Pembuatan 1 m2 bekisting untuk plat beton pracetak ( 5 kali pakai)


Kode AHSP = 4.1.2.5
A TENAGA
Pekerja C9 OH 0.007 80,000.00 560.00
Tukang batu C18 OH 0.076 125,000.00 9,500.00
Kepala tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 11,380.00
B BAHAN
Lantai kerja tebal 10cm m3 0.080 795,508.36 63,640.67
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Besi Hollow 5x5 cm C173 kg 9.3940 22,166.67 208,233.67
Kayu Balok 5/7 Kelas III C78 m3 0.005 1,600,000.00 8,000.00
Phenol film 12mm C337 lbr 0.080 320,000.00 25,600.00
Minyak bekisting C302 ltr 0.200 5,100.00 1,020.00
Dynabolt dia- 12 x 120 mm C508 bh 3.882 12,500.00 48,525.00
JUMLAH HARGA BAHAN 355,019.34
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 366,399.34
E Overhead & Profit 10% 36,639.93
F Harga Satuan Pekerjaan (D+E) 403,039.27

Pembuatan 1 m2 bekisting untuk balok beton pracetak ( 10-12 kali pakai)


Kode AHSP = 4.1.2.6
A TENAGA
Pekerja C9 OH 0.004 80,000.00 320.00
Tukang batu C18 OH 0.038 125,000.00 4,750.00
Kepala tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 5,790.00
B BAHAN
Kayu Balok 5/7 Kelas III C78 m3 0.005 1,600,000.00 8,000.00
Phenol film 12mm C337 lbr 0.043 320,000.00 13,760.00
Minyak bekisting C302 ltr 0.200 5,100.00 1,020.00
Paku biasa 2” – 5” (5-10 cm) C317 ltr 0.046 21,000.00 966.00
Dynabolt dia- 12 x 120 mm C508 bh 0.693 12,500.00 8,662.50
JUMLAH HARGA BAHAN 32,408.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 38,198.50
E Overhead & Profit 10% 3,819.85
F Harga Satuan Pekerjaan (D+E) 42,018.35

Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai)


Kode AHSP = 4.1.2.7
A TENAGA
Pekerja C9 OH 0.004 80,000.00 320.00
Tukang batu C18 OH 0.038 125,000.00 4,750.00
Kepala tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 5,790.00
B BAHAN
Kayu Balok 5/7 Kelas III C78 m3 0.004 1,600,000.00 6,400.00
Phenol film 12mm C337 lbr 0.048 320,000.00 15,360.00
Minyak bekisting C302 ltr 0.200 5,100.00 1,020.00
Paku biasa 2” – 5” (5-10 cm) C317 bh 0.046 21,000.00 966.00
Dynabolt dia- 12 x 120 mm C508 bh 0.693 12,500.00 8,662.50
JUMLAH HARGA BAHAN 32,408.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 38,198.50
E Overhead & Profit 10% 3,819.85
F Harga Satuan Pekerjaan (D+E) 42,018.35

Pemasangan dan membuka bekisting 1 buah komponen plat beton pracetak


Kode AHSP = 4.1.2.8
A TENAGA
Pekerja C9 OH 0.053 80,000.00 4,240.00
Tukang kayu C19 OH 0.018 125,000.00 2,250.00
Mandor C47 OH 0.005 120,000.00 600.00

JUMLAH TENAGA KERJA 7,090.00


B BAHAN
-
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
-
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 7,090.00
E Overhead & Profit 10% 709.00
F Harga Satuan Pekerjaan (D+E) 7,799.00

Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak


Kode AHSP = 4.1.2.9
A TENAGA
Pekerja C9 OH 0.089 80,000.00 7,120.00
Tukang kayu C19 OH 0.030 125,000.00 3,750.00
Mandor C47 OH 0.005 120,000.00 600.00

JUMLAH TENAGA KERJA 11,470.00


B BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 11,470.00
E Overhead & Profit 10% 1,147.00
F Harga Satuan Pekerjaan (D+E) 12,617.00

Pemasangan dan membuka bekisting 1 buah komponen Kolom beton pracetak


Kode AHSP = 4.1.2.10
A TENAGA
Pekerja C9 OH 0.071 80,000.00 5,680.00
Tukang kayu C19 OH 0.024 125,000.00 3,000.00
Mandor C47 OH 0.005 120,000.00 600.00

JUMLAH TENAGA KERJA 9,280.00


B BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 9,280.00
E Overhead & Profit 10% 928.00
F Harga Satuan Pekerjaan (D+E) 10,208.00

Penuangan/menebar beton untuk 1 buah komponen plat pracetak


Kode AHSP = 4.1.2.11
A TENAGA
Pekerja C9 OH 0.064 80,000.00 5,120.00
Tukang batu C18 OH 0.244 125,000.00 30,500.00
Tukang vibrator C30 OH 0.128 125,000.00 16,000.00
Kepala Tukang C39 OH 0.034 150,000.00 5,100.00
Mandor C47 OH 0.073 120,000.00 8,760.00
JUMLAH TENAGA KERJA 65,480.00
B BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 65,480.00
E Overhead & Profit 10% 6,548.00
F Harga Satuan Pekerjaan (D+E) 72,028.00

Penuangan/menebar beton untuk 1 buah komponen balok pracetak


Kode AHSP = 4.1.2.12
A TENAGA
Pekerja C9 OH 0.069 80,000.00 5,520.00
Tukang batu C18 OH 0.242 125,000.00 30,250.00
Tukang vibrator C30 OH 0.138 125,000.00 17,250.00
Kepala Tukang C39 OH 0.037 150,000.00 5,550.00
Mandor C47 OH 0.073 120,000.00 8,760.00
JUMLAH TENAGA KERJA 67,330.00
B BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 67,330.00
E Overhead & Profit 10% 6,733.00
F Harga Satuan Pekerjaan (D+E) 74,063.00

Penuangan/menebar beton untuk 1 buah komponen kolom pracetak


Kode AHSP = 4.1.2.13
A TENAGA
Pekerja C9 OH 0.061 80,000.00 4,880.00
Tukang batu C18 OH 0.213 125,000.00 26,625.00
Tukang vibrator C30 OH 0.122 125,000.00 15,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.073 120,000.00 8,760.00
JUMLAH TENAGA KERJA 60,465.00
B BAHAN
-
-
-
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 60,465.00
E Overhead & Profit 10% 6,046.50
F Harga Satuan Pekerjaan (D+E) 66,511.50

Mendirikan 1 buah komponen plat pracetak beserta indeks kenaikan lantai ereksi plat hingga 24 lantai
Kode AHSP = 4.1.2.14
A TENAGA
Pekerja C9 OH 0.067 80,000.00 5,360.00
Tukang batu C18 OH 0.067 125,000.00 8,375.00
Tukang erection C29 OH 0.134 125,000.00 16,750.00
Operator crane C33 OH 0.067 200,000.00 13,400.00
Operator Crane (Pembantu) C34 OH 0.067 75,000.00 5,025.00
Kepala Tukang C39 OH 0.067 150,000.00 10,050.00
Mandor C47 OH 0.067 120,000.00 8,040.00
JUMLAH TENAGA KERJA 48,910.00
B BAHAN
Solar C389 ltr 6.676 16,200.00 108,151.20
-
-
JUMLAH HARGA BAHAN 108,151.20
C PERALATAN
Sewa Crane C1585 UH 0.067 1,608,257.14 107,753.23
Sewa Skafolding 1 Set (Hari) C1595 UH 1.100 5,050.00 5,555.00
JUMLAH HARGA ALAT 113,308.23
D Jumlah (A+B+C) 270,369.43
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 27,036.94
F Harga Satuan Pekerjaan (D+E) 297,406.37

Mendirikan 1 buah komponen balok pracetak beserta indeks kenaikan lantai ereksi balok hingga 24 lantai
Kode AHSP = 4.1.2.15
A TENAGA
Pekerja C9 OH 0.061 80,000.00 4,880.00
Tukang batu C18 OH 0.061 125,000.00 7,625.00
Tukang erection C29 OH 0.122 125,000.00 15,250.00
Operator crane C33 OH 0.061 200,000.00 12,200.00
Operator Crane (Pembantu) C34 OH 0.061 75,000.00 4,575.00
Kepala Tukang C39 OH 0.061 150,000.00 9,150.00
Mandor C47 OH 0.061 120,000.00 7,320.00
JUMLAH TENAGA KERJA 61,000.00
B BAHAN
Solar C389 ltr 6.110 16,200.00 98,982.00
-
-
JUMLAH HARGA BAHAN 98,982.00
C PERALATAN
Sewa Crane C1585 UH 0.061 1,608,257.14 98,103.69
Sewa Skafolding 1 Set (Hari) C1595 UH 1.100 5,050.00 5,555.00
JUMLAH HARGA ALAT 103,658.69
D Jumlah (A+B+C) 263,640.69
E Overhead & Profit 10% 26,364.07
F Harga Satuan Pekerjaan (D+E) 290,004.75

Mendirikan 1 buah komponen kolom pracetak beserta indeks kenaikan lantai ereksi kolom hingga 24 lantai
Kode AHSP = 4.1.2.16
A TENAGA
Pekerja C9 OH 0.083 80,000.00 6,640.00
Tukang batu C18 OH 0.083 125,000.00 10,375.00
Tukang erection C29 OH 0.166 125,000.00 20,750.00
Operator crane C33 OH 0.083 200,000.00 16,600.00
Operator Crane (Pembantu) C34 OH 0.083 75,000.00 6,225.00
Kepala Tukang C39 OH 0.083 150,000.00 12,450.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 83,000.00
B BAHAN
Solar C389 ltr 8.277 16,200.00 134,087.40
-
-
JUMLAH HARGA BAHAN 134,087.40
C PERALATAN
Sewa Crane C1585 UH 0.083 1,608,257.14 133,485.34
Sewa pipe support C1592 UH 2.200 75,000.00 165,000.00
JUMLAH HARGA ALAT 298,485.34
D Jumlah (A+B+C) 515,572.74
E Overhead & Profit 10% 51,557.27
F Harga Satuan Pekerjaan (D+E) 567,130.02

Melangsir 1 buah komponen plat pracetak ( ± 20 m)


Kode AHSP = 4.1.2.17
A TENAGA
Pekerja C9 OH 0.019 80,000.00 1,520.00
Tukang batu C18 OH 0.038 125,000.00 4,750.00
Operator crane C33 OH 0.019 200,000.00 3,800.00
Operator Crane (Pembantu) C34 OH 0.019 75,000.00 1,425.00
JUMLAH TENAGA KERJA 11,495.00
B BAHAN
Solar C389 ltr 1.897 16,200.00 30,731.40
-
-
JUMLAH HARGA BAHAN 30,731.40
C PERALATAN
Sewa Crane C1585 UH 0.019 1,608,257.14 30,556.89

JUMLAH HARGA ALAT 30,556.89


D Jumlah (A+B+C) 72,783.29
E Overhead & Profit 10% 7,278.33
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 80,061.61

Melangsir 1 buah komponen balok pracetak ( ± 20 m)


Kode AHSP = 4.1.2.18
A TENAGA
Pekerja C9 OH 0.019 80,000.00 1,520.00
Tukang batu C18 OH 0.038 125,000.00 4,750.00
Operator crane C33 OH 0.019 200,000.00 3,800.00
Operator Crane (Pembantu) C34 OH 0.019 75,000.00 1,425.00
JUMLAH TENAGA KERJA 11,495.00
B BAHAN
Solar C389 ltr 1.897 16,200.00 30,731.40
-
-
JUMLAH HARGA BAHAN 30,731.40
C PERALATAN
Sewa Crane C1585 UH 0.019 1,608,257.14 30,556.89

JUMLAH HARGA ALAT 30,556.89


D Jumlah (A+B+C) 72,783.29
E Overhead & Profit 10% 7,278.33
F Harga Satuan Pekerjaan (D+E) 80,061.61

Melangsir 1 buah komponen kolom pracetak ( ± 20 m)


Kode AHSP = 4.1.2.19
A TENAGA
Pekerja C9 OH 0.019 80,000.00 1,520.00
Tukang batu C18 OH 0.038 125,000.00 4,750.00
Operator crane C33 OH 0.019 200,000.00 3,800.00
Operator Crane (Pembantu) C34 OH 0.019 75,000.00 1,425.00
JUMLAH TENAGA KERJA 11,495.00
B BAHAN
Solar C389 ltr 1.897 16,200.00 30,731.40
-
-
JUMLAH HARGA BAHAN 30,731.40
C PERALATAN
Sewa Crane C1585 UH 0.019 1,608,257.14 30,556.89

JUMLAH HARGA ALAT 30,556.89


D Jumlah (A+B+C) 72,783.29
E Overhead & Profit 10% 7,278.33
F Harga Satuan Pekerjaan (D+E) 80,061.61

Bahan 1 m3 grouting campuran


Kode AHSP = 4.1.2.20
A TENAGA

JUMLAH TENAGA KERJA -


B BAHAN
Semen grout C364 Kg 1200.000 3,000.00 3,600,000.00
Screening C362 Kg 650.000 2,500.00 1,625,000.00
Air C120 ltr 350.000 100.00 35,000.00
JUMLAH HARGA BAHAN 5,260,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,260,000.00
E Overhead & Profit 10% 526,000.00
F Harga Satuan Pekerjaan (D+E) 5,786,000.00

Bahan 1 m3 grouting tidak campuran


Kode AHSP = 4.1.2.21
A TENAGA

JUMLAH TENAGA KERJA -


B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Semen grout C364 Kg 1850.000 3,000.00 5,550,000.00
Air C120 ltr 400.000 100.00 40,000.00
-
JUMLAH HARGA BAHAN 5,590,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,590,000.00
E Overhead & Profit 10% 559,000.00
F Harga Satuan Pekerjaan (D+E) 6,149,000.00

Upah melakukan 1 titik grouting pada join pracetak


Kode AHSP = 4.1.2.22
A TENAGA
Tukang batu C18 OH 0.367 125,000.00 45,875.00
Kepala tukang C39 OH 0.074 150,000.00 11,100.00
Mandor C47 OH 0.037 120,000.00 4,440.00
JUMLAH TENAGA KERJA 61,415.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 61,415.00
E Overhead & Profit 10% 6,141.50
F Harga Satuan Pekerjaan (D+E) 67,556.50

Pemasangan 1 titik Bekisting join pracetak


Kode AHSP = 4.1.2.23
A TENAGA
Pekerja C9 OH 0.147 80,000.00 11,760.00
Tukang kayu C19 OH 0.147 125,000.00 18,375.00
Kepala tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 32,985.00
B BAHAN
Balok Kayu Kelas III C68 m3 0.012 1,700,000.00 20,400.00
Kayu papan 3/20 Kelas III C87 m3 0.004 1,600,000.00 6,400.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.264 21,000.00 5,544.00
JUMLAH HARGA BAHAN 32,344.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 65,329.00
E Overhead & Profit 10% 6,532.90
F Harga Satuan Pekerjaan (D+E) 71,861.90

Upah 1 titik Join dengan Sling


Kode AHSP = 4.1.2.24
A TENAGA
Pekerja C9 OH 0.220 80,000.00 17,600.00
Tukang kayu C19 OH 0.022 125,000.00 2,750.00
Tukang besi C20 OH 0.220 125,000.00 27,500.00
Mandor C47 OH 0.011 120,000.00 1,320.00
JUMLAH TENAGA KERJA 49,170.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 49,170.00
E Overhead & Profit 10% 4,917.00
F Harga Satuan Pekerjaan (D+E) 54,087.00

Pemasangan 1 kg baja profil


Kode AHSP = 4.2.1.1
A TENAGA
Pekerja Las Kontruksi C16 OH 0.060 80,000.00 4,800.00
Tukang Las Konstruksi C28 OH 0.060 125,000.00 7,500.00
Kepala Tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 13,560.00
B BAHAN
Besi Profil UNP 5 C194 Kg 1.150 50,000.00 57,500.00

JUMLAH HARGA BAHAN 57,500.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 71,060.00
E Overhead & Profit 10% 7,106.00
F Harga Satuan Pekerjaan (D+E) 78,166.00

Pemasangan 1 kg rangka kuda-kuda baja IWF


Kode AHSP = 4.2.1.2
A TENAGA
Pekerja Las Kontruksi C16 OH 0.060 80,000.00 4,800.00
Tukang Las Konstruksi C28 OH 0.060 125,000.00 7,500.00
Kepala Tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 13,560.00
B BAHAN
Besi Baja WF C156 Kg 1.150 21,086.31 24,249.26

JUMLAH HARGA BAHAN 24,249.26


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 37,809.26
E Overhead & Profit 10% 3,780.93
F Harga Satuan Pekerjaan (D+E) 41,590.18

Pengerjaan 100 kg pekerjaan perakitan


Kode AHSP = 4.2.1.3
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Besi C20 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.001 150,000.00 150.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 21,250.00
B BAHAN
Solar C389 Liter 1.000 16,200.00 16,200.00
Minyak Pelumas C304 Liter 0.100 15,000.00 1,500.00

JUMLAH HARGA BAHAN 17,700.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 38,950.00
E Overhead & Profit 10% 3,895.00
F Harga Satuan Pekerjaan (D+E) 42,845.00

Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap. rangka baja siku
Kode AHSP = 4.2.1.4
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Tukang Las Konstruksi C28 OH 1.050 125,000.00 131,250.00
Kepala Tukang C39 OH 0.105 150,000.00 15,750.00
Mandor C47 OH 0.052 120,000.00 6,240.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 237,240.00
B BAHAN
Besi Siku L 30.30.3 C179 Kg 15.000 1.00 15.00
Besi Plat C183 Kg 32.800 28,000.00 918,400.00
Kawat Las C272 Kg 0.050 3,250.00 162.50

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 918,577.50


C PERALATAN

JUMLAH HARGA ALAT JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,155,817.50
E Overhead & Profit 10% 115,581.75
F Harga Satuan Pekerjaan (D+E) 1,271,399.25

Pengerjaan 10 cm pengelasan dengan las listrik


Kode AHSP = 4.2.1.5
A TENAGA
Pekerja C9 OH 0.040 80,000.00 3,200.00
Tukang Besi C20 OH 0.020 125,000.00 2,500.00
Kepala Tukang C39 OH 0.002 150,000.00 300.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 6,240.00
B BAHAN
Kawat Las C272 Kg 0.400 3,250.00 1,300.00
Solar C389 Kg 0.300 16,200.00 4,860.00
Minyak Pelumas C304 Kg 0.040 15,000.00 600.00
JUMLAH HARGA BAHAN 6,760.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 13,000.00
E Overhead & Profit 10% 1,300.00
F Harga Satuan Pekerjaan (D+E) 14,300.00

Pembuatan 1 m2 rangka jendela besi scuare tube (25 x 5) cm


Kode AHSP = 4.2.1.6
A TENAGA
Pekerja C9 OH 0.650 80,000.00 52,000.00
Tukang Las Konstruksi C28 OH 0.650 125,000.00 81,250.00
Kepala Tukang C39 OH 0.065 150,000.00 9,750.00
Mandor C47 OH 0.032 120,000.00 3,840.00
JUMLAH TENAGA KERJA 146,840.00
B BAHAN
Besi Scuare Tube C197 m 0.400 1.00 0.40
Besi Lis Kaca (1x1) cm C201 m 0.300 1.00 0.30
Pengelasan C334 cm 0.040 15,000.00 600.00
JUMLAH HARGA BAHAN 600.70
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 147,440.70
E Overhead & Profit 10% 14,744.07
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 162,184.77

Pemasangan 1 m2 pintu rolling door besi


Kode AHSP = 4.2.1.7
A TENAGA
Pekerja C9 OH 1.200 80,000.00 96,000.00
Tukang Las Konstruksi C28 OH 1.200 125,000.00 150,000.00
Kepala Tukang C39 OH 0.120 150,000.00 18,000.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 264,720.00
B BAHAN
Pintu Gulung Besi C595 m2 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 264,721.00
E Overhead & Profit 10% 26,472.10
F Harga Satuan Pekerjaan (D+E) 291,193.10

Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC


Kode AHSP = 4.2.1.8
A TENAGA
Pekerja C9 OH 0.440 80,000.00 35,200.00
Tukang C17 OH 0.440 125,000.00 55,000.00
Kepala Tukang C39 OH 0.044 150,000.00 6,600.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 99,440.00
B BAHAN
Pintu Lipat C594 m2 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 99,441.00
E Overhead & Profit 10% 9,944.10
F Harga Satuan Pekerjaan (D+E) 109,385.10

Pemasangan 1 m2 sunscreen alluminium


Kode AHSP = 4.2.1.9
A TENAGA
Pekerja C9 OH 0.080 80,000.00 6,400.00
Tukang C17 OH 0.800 125,000.00 100,000.00
Kepala Tukang C39 OH 0.080 150,000.00 12,000.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 118,880.00
B BAHAN
Sunscreen Allumunium C630 m2 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 118,881.00
E Overhead & Profit 10% 11,888.10
F Harga Satuan Pekerjaan (D+E) 130,769.10

Pemasangan 1 m2 rolling door alluminium


Kode AHSP = 4.2.1.10
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Allumunium C26 OH 1.000 125,000.00 125,000.00
Kepala Tukang C39 OH 0.100 150,000.00 15,000.00
Mandor C47 OH 0.040 120,000.00 4,800.00
JUMLAH TENAGA KERJA 224,800.00
B BAHAN
Rolling Dor Allumunium C629 m2 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 224,801.00
E Overhead & Profit 10% 22,480.10
F Harga Satuan Pekerjaan (D+E) 247,281.10

Pemasangan 1 m kusen pintu alluminium


Kode AHSP = 4.2.1.11
A TENAGA
Pekerja C9 OH 0.043 80,000.00 3,440.00
Tukang Besi C20 OH 0.043 125,000.00 5,375.00
Kepala Tukang C39 OH 0.004 150,000.00 645.00
Mandor C47 OH 0.002 120,000.00 252.00
JUMLAH TENAGA KERJA 9,712.00
B BAHAN
Profil Allumunium C624 m 1.100 50,000.00 55,000.00
Skrup Fixer C658 Buah 2.000 650.00 1,300.00
Sealant C656 Tube 0.060 6,000.00 360.00

JUMLAH HARGA BAHAN 56,660.00


C PERALATAN
Sewa Alat Las C1579 Jam 0.170 10,000.00 1,700.00

JUMLAH HARGA ALAT 1,700.00


D Jumlah (A+B+C) 68,072.00
E Overhead & Profit 10% 6,807.20
F Harga Satuan Pekerjaan (D+E) 74,879.20

Pemasangan 1 m2 pintu alluminium strip lebar 8 cm


Kode AHSP = 4.2.1.12
A TENAGA
Pekerja C9 OH 0.085 80,000.00 6,800.00
Tukang Allumunium C26 OH 0.085 125,000.00 10,625.00
Kepala Tukang C39 OH 0.009 150,000.00 1,275.00
Mandor C47 OH 0.004 120,000.00 504.00
JUMLAH TENAGA KERJA 19,204.00
B BAHAN
Profil Allumunium C624 m 4.400 50,000.00 220,000.00
Profil Alluminium Strip C619 m 14.600 13,683.33 199,776.67

JUMLAH HARGA BAHAN 419,776.67


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 438,980.67
E Overhead & Profit 10% 43,898.07
F Harga Satuan Pekerjaan (D+E) 482,878.73

Pemasangan 1 m2 pintu kaca rangka alluminium


Kode AHSP = 4.2.1.13
A TENAGA
Pekerja C9 OH 0.085 80,000.00 6,800.00
Tukang Allumunium C26 OH 0.085 125,000.00 10,625.00
Kepala Tukang C39 OH 0.009 150,000.00 1,275.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 19,300.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Profil alluminium "Ambang Datar Tegak" C611 m 4.400 37,770.67 166,190.93
Profil Kaca C631 m 2.000 15,000.00 30,000.00
Sealant C656 tube 0.270 6,000.00 1,620.00

JUMLAH HARGA BAHAN 197,810.93


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 217,110.93
E Overhead & Profit 10% 21,711.09
F Harga Satuan Pekerjaan (D+E) 238,822.03

Pemasangan 1 m2 venetions blinds dan Vertical blinds


Kode AHSP = 4.2.1.14
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang C17 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 79,160.00
B BAHAN
Venetions blinds dan vertical blinds (tirai) C418 m2 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 79,161.00
E Overhead & Profit 10% 7,916.10
F Harga Satuan Pekerjaan (D+E) 87,077.10

Pemasangan 1 m2 terali besi strip (2 x 3) mm


Kode AHSP = 4.2.1.15
A TENAGA
Pekerja C9 OH 1.670 80,000.00 133,600.00
Tukang Las Konstruksi C28 OH 1.670 125,000.00 208,750.00
Kepala Tukang C39 OH 0.167 150,000.00 25,050.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 377,360.00
B BAHAN
Besi Strip C198 Kg 6.177 11,250.00 69,491.25
Pengelasan C334 cm 27.080 15,000.00 406,200.00
JUMLAH HARGA BAHAN 475,691.25
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 853,051.25
E Overhead & Profit 10% 85,305.13
F Harga Satuan Pekerjaan (D+E) 938,356.38

Pemasangan 1 m2 kawat nyamuk


Kode AHSP = 4.2.1.16
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang C17 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Kawat Nyamuk C572 m2 6.177 75,000.00 463,275.00
Pengelasan C334 cm 27.080 15,000.00 406,200.00
Baja Strip (0,2 x 2) cm C155 Kg 27.080 1.00 27.08

JUMLAH HARGA BAHAN 869,502.08


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 892,102.08
E Overhead & Profit 10% 89,210.21
F Harga Satuan Pekerjaan (D+E) 981,312.29

Pemasangan 1 m2 jendela nako & tralis


Kode AHSP = 4.2.1.17
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang C17 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 44,120.00
B BAHAN
Jendela nako (rangka + kaca 5 mm) C542 m2 1.100 1,250,000.00 1,375,000.00
Paku Skrup 1 cm -2,5 cm C324 buah 10.000 1.00 10.00
Besi Strip C198 m 7.000 11,250.00 78,750.00

JUMLAH HARGA BAHAN 1,453,760.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,497,880.00
E Overhead & Profit 10% 149,788.00
F Harga Satuan Pekerjaan (D+E) 1,647,668.00

Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm


Kode AHSP = 4.2.1.18
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang C17 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 44,120.00
B BAHAN
Seng Plat BJLS 20 C370 m 1.050 56,600.00 59,430.00
Paku Biasa C318 Kg 0.015 21,000.00 315.00
Kayu papan 3/20 Kelas III C87 m3 0.019 1,600,000.00 30,400.00
JUMLAH HARGA BAHAN 90,145.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 134,265.00
E Overhead & Profit 10% 13,426.50
F Harga Satuan Pekerjaan (D+E) 147,691.50

Pemasangan 1 m talang ½ lingkaran D-15 cm. seng plat bjls 30 lebar 45 cm


Kode AHSP = 4.2.1.19
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Allumunium C26 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.030 150,000.00 4,500.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 54,960.00
B BAHAN
Seng Plat BJLS 20 C370 m 1.050 56,600.00 59,430.00
Paku Biasa C318 Kg 0.015 21,000.00 315.00
Besi Strip C198 Kg 0.019 11,250.00 213.75

JUMLAH HARGA BAHAN 59,958.75


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 114,918.75
E Overhead & Profit 10% 11,491.88
F Harga Satuan Pekerjaan (D+E) 126,410.63
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm. modul 60 x 120 cm. dinding partisi
Kode AHSP = 4.2.1.20
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Besi C20 OH 0.250 125,000.00 31,250.00
Kepala Tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 56,560.00
B BAHAN
Besi Hollow 4x4 cm C171 m1 3.500 17,000.00 59,500.00
Assesoris perkuatan, las dll C131 Ls 3.500 12,000.00 42,000.00
JUMLAH HARGA BAHAN 101,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 158,060.00
E Overhead & Profit 10% 15,806.00
F Harga Satuan Pekerjaan (D+E) 173,866.00

Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm. modul 60 x 60 cm. plafon


Kode AHSP = 4.2.1.21
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang Besi C20 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 79,160.00
B BAHAN
Besi Hollow 4x4 cm C171 m1 4.000 17,000.00 68,000.00
Assesoris perkuatan, las dll C131 Ls 4.000 12,000.00 48,000.00

JUMLAH HARGA BAHAN 116,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 195,160.00
E Overhead & Profit 10% 19,516.00
F Harga Satuan Pekerjaan (D+E) 214,676.00

Pemasangan 1 m2 Arap pelana rangka atap baja ringan (canai dingin) profil C75
Kode AHSP = 4.2.1.22
A TENAGA
Pekerja C9 OH 0.734 80,000.00 58,720.00
Tukang Besi C20 OH 0.734 125,000.00 91,750.00
Kepala Tukang C39 OH 0.073 150,000.00 10,950.00
Mandor C47 OH 0.037 120,000.00 4,440.00
JUMLAH TENAGA KERJA 165,860.00
B BAHAN
Smartruss C 75.75 C654 btg 0.873 21,000.00 18,333.00
Assesoris perkuatan, las dll C131 Ls 0.873 12,000.00 10,476.00

JUMLAH HARGA BAHAN 28,809.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 194,669.00
E Overhead & Profit 10% 19,466.90
F Harga Satuan Pekerjaan (D+E) 214,135.90

Pemasangan 1 m2 atap jurai / limasan rangka atap baja ringan (canai dingin) profil C75
Kode AHSP = 4.2.1.23
A TENAGA
Pekerja C9 OH 0.760 80,000.00 60,832.00
Tukang Besi C20 OH 0.760 125,000.00 95,050.00
Kepala Tukang C39 OH 0.076 150,000.00 11,400.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.038 120,000.00 4,560.00
JUMLAH TENAGA KERJA 171,842.00
B BAHAN
Smartruss C 75.75 C654 btg 0.873 21,000.00 18,333.00
Assesoris perkuatan, las dll C131 Ls 0.873 12,000.00 10,476.00

JUMLAH HARGA BAHAN 28,809.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 200,651.00
E Overhead & Profit 10% 20,065.10
F Harga Satuan Pekerjaan (D+E) 220,716.10

Pemasangan 1 m2 Kusen aluminium


Kode AHSP = 4.2.1.24
A TENAGA
Pekerja C9 OH 0.043 80,000.00 3,440.00
Tukang Besi C20 OH 0.043 125,000.00 5,375.00
Kepala Tukang C39 OH 0.004 150,000.00 645.00
Mandor C47 OH 0.002 120,000.00 252.00
JUMLAH TENAGA KERJA 9,712.00
B BAHAN
Profil All. Kusen (4" x 1_3/4") C625 m 1.100 120,000.00 132,000.00
Skrup Fixer C658 buah 2.000 650.00 1,300.00
Sealant C656 tube 0.060 6,000.00 360.00

JUMLAH HARGA BAHAN 133,660.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 143,372.00
E Overhead & Profit 10% 14,337.20
F Harga Satuan Pekerjaan (D+E) 157,709.20

Pemasangan 1 m2 Kusen aluminium


Kode AHSP = 4.2.1.24
A TENAGA
Pekerja C9 OH 0.085 80,000.00 6,800.00
Tukang Allumunium C26 OH 0.085 125,000.00 10,625.00
Kepala Tukang C39 OH 0.009 150,000.00 1,275.00
Mandor C47 OH 0.004 120,000.00 504.00
JUMLAH TENAGA KERJA 19,204.00
B BAHAN
Profil Allumunium C624 m 4.400 50,000.00 220,000.00
Profil Alluminium Strip C619 m 14.600 13,683.33 199,776.67

JUMLAH HARGA BAHAN 419,776.67


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 438,980.67
E Overhead & Profit 10% 43,898.07
F Harga Satuan Pekerjaan (D+E) 482,878.73

Pemasangan 1 m2 pintu kaca rangka aluminium


Kode AHSP = 4.2.1.26
A TENAGA
Pekerja C9 OH 0.085 80,000.00 6,800.00
Tukang Allumunium C26 OH 0.085 125,000.00 10,625.00
Kepala Tukang C39 OH 0.009 150,000.00 1,275.00
Mandor C47 OH 0.004 120,000.00 504.00
JUMLAH TENAGA KERJA 19,204.00
B BAHAN
Profil Allumunium C624 m 4.400 50,000.00 220,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Profil Kaca C631 m 4.500 15,000.00 67,500.00
Sealant C656 tube 0.270 6,000.00 1,620.00
JUMLAH HARGA BAHAN 289,120.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 308,324.00
E Overhead & Profit 10% 30,832.40
F Harga Satuan Pekerjaan (D+E) 339,156.40

Pemasangan 1 m2 venetions blinds dan vertical blinds


Kode AHSP = 4.2.1.27
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang Allumunium C26 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 79,160.00
B BAHAN
Venetions blinds dan vertical blinds (tirai) C418 m 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 79,161.00
E Overhead & Profit 10% 7,916.10
F Harga Satuan Pekerjaan (D+E) 87,077.10

Pemasangan 1 Set Curtain Wall 4


Kode AHSP = 4.2.1.T
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 7,500,000.00 7,500,000.00

JUMLAH TENAGA KERJA 7,500,000.00


B BAHAN
Profil alluminium Curtain Wall C608 M 64.075 118,000.00 7,560,850.00
Profil alluminium "Stoper Casement" C612 M 20.160 25,571.33 515,518.08
Profil alluminium "Frame Casement" C613 M 20.160 34,173.33 688,934.40
Profil alluminium "Bead Casement" C615 M 20.160 13,020.11 262,485.44
Kaca Stopsol Tempered 6 mm C553 M2 34.859 650,000.00 22,658,350.00
Sealant C656 M' 64.075 6,000.00 384,450.00
Allumunium Spigot C491 M 27.000 22,500.00 607,500.00

JUMLAH HARGA BAHAN 32,678,087.92


C Aksesoris
Friction Stay (Engsel Casement) 14" C526 bh 12.000 154,070.00 1,848,840.00
Casement Handle C495 bh 6.000 28,000.00 168,000.00
JUMLAH HARGA ALAT 2,016,840.00
D Jumlah (A+B+C) 42,194,927.92
E Overhead & Profit 10% 4,219,492.79
F Harga Satuan Pekerjaan (D+E) 46,414,420.71

Pemasangan 1 Set Curtain Wall 5


Kode AHSP = 4.2.1.T1
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 5,400,000.00 5,400,000.00

JUMLAH TENAGA KERJA 5,400,000.00


B BAHAN
Profil alluminium Curtain Wall C608 M 92.400 118,000.00 10,903,200.00
Kaca Stopsol Tempered 5 mm C554 M2 38.759 584,000.00 22,634,964.00
Sealant C656 M' 184.800 6,000.00 1,108,800.00
Allumunium Spigot C491 M 27.000 22,500.00 607,500.00

JUMLAH HARGA BAHAN 35,254,464.00


C Aksesoris
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 40,654,464.00
E Overhead & Profit 10% 4,065,446.40
F Harga Satuan Pekerjaan (D+E) 44,719,910.40

Pemasangan 1 Set Curtain Wall 6


Kode AHSP = 4.2.1.T2
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 18,000,000.00 18,000,000.00

JUMLAH TENAGA KERJA 18,000,000.00


B BAHAN
Profil alluminium Curtain Wall C608 M 242.550 118,000.00 28,620,900.00
Kaca Stopsol Tempered 5 mm C554 M2 106.252 584,000.00 62,051,022.00
Sealant C656 M' 485.100 6,000.00 2,910,600.00
Profil alluminium "Stoper Casement" C612 M 35.200 25,571.33 900,110.93
Profil alluminium "Frame Casement" C613 M 35.200 34,173.33 1,202,901.33
Profil alluminium "Bead Casement" C615 M 35.200 13,020.11 458,307.91
Allumunium Spigot C491 M 52.000 22,500.00 1,170,000.00

JUMLAH HARGA BAHAN 97,313,842.18


C Aksesoris
Friction Stay (Engsel Casement) 14" C526 bh 16.000 154,070.00 2,465,120.00
Casement Handle C495 bh 8.000 28,000.00 224,000.00
JUMLAH HARGA ALAT 2,689,120.00
D Jumlah (A+B+C) 118,002,962.18
E Overhead & Profit 10% 11,800,296.22
F Harga Satuan Pekerjaan (D+E) 129,803,258.40

Pemasangan 1 Set Curtain Wall 7


Kode AHSP = 4.2.1.T3
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 3,500,000.00 3,500,000.00

JUMLAH TENAGA KERJA 3,500,000.00


B BAHAN
Profil alluminium Curtain Wall C608 M 51.920 118,000.00 6,126,560.00
Kaca bening 5 mm C544 M2 16.060 128,000.00 2,055,680.00
Sealant C656 M' 103.840 6,000.00 623,040.00
Profil alluminium "Stoper Casement" C612 M 7.920 25,571.33 202,524.96
Profil alluminium "Frame Casement" C613 M 7.920 34,173.33 270,652.80
Profil alluminium "Bead Casement" C615 M 7.920 13,020.11 103,119.28
Allumunium Spigot C491 M 23.000 22,500.00 517,500.00

JUMLAH HARGA BAHAN 9,899,077.04


C Aksesoris
Friction Stay (Engsel Casement) 14" C526 bh 4.000 154,070.00 616,280.00
Casement Handle C495 bh 2.000 28,000.00 56,000.00
JUMLAH HARGA ALAT 672,280.00
D Jumlah (A+B+C) 14,071,357.04
E Overhead & Profit 10% 1,407,135.70
F Harga Satuan Pekerjaan (D+E) 15,478,492.74

Pemasangan 1 M' Pillar Atap Pipa BSP 10" Finish Coating


Kode AHSP = 4.2.1.T4
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang besi C20 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.013 120,000.00 1,500.00
JUMLAH TENAGA KERJA 62,250.00
B BAHAN
Pipa BSP Dia. 10" C1317 M 1.100 866,916.67 953,608.33
Besi Plat 3 mm C185 M2 0.100 541,666.67 54,166.67
Cat Besi C203 Kg 2.000 74,200.00 148,400.00
Pengelasan C334 Ls 1.000 20,000.00 20,000.00

JUMLAH HARGA BAHAN 1,176,175.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,238,425.00
E Overhead & Profit 10% 123,842.50
F Harga Satuan Pekerjaan (D+E) 1,362,267.50

Pemasangan 1 Set Ventilasi (V1) + Aksesoris


Kode AHSP = 4.2.1.T5
A TENAGA
Pengerjaan dan Pemasangan Ls 1.000 175,000.00 175,000.00

JUMLAH TENAGA KERJA 175,000.00


B BAHAN
Profil alluminium "M" C605 M 3.960 41,666.67 165,000.00
Kaca Warna (Dark Blue) 5 mm C569 M2 0.506 260,714.99 131,921.79
Allumunium Spigot C491 m 5.000 22,500.00 112,500.00

JUMLAH HARGA BAHAN 409,421.79


C Aksesoris
Sealant C656 m 3.256 6,000.00 19,536.00

JUMLAH HARGA ALAT 19,536.00


D Jumlah (A+B+C) 603,957.79
E Overhead & Profit 10% 60,395.78
F Harga Satuan Pekerjaan (D+E) 664,353.56

Pemasangan 1 m2 Partisi
Kode AHSP = 4.2.1.T6
A TENAGA
Pekerja Plafond C13 OH 0.300 80,000.00 24,000.00
Tukang Plafond C25 OH 0.600 125,000.00 75,000.00
Mandor Plafond C42 OH 0.375 120,000.00 45,000.00
JUMLAH TENAGA KERJA 144,000.00
B BAHAN
Smartruss C 75.65 C655 m’ 4.180 19,500.00 81,510.00
Dynabolt dia- 10 x 50 mm C509 Bh 6.000 3,500.00 21,000.00
Perban Gypsum C336 Roll 0.200 10,000.00 2,000.00
Tepung Gypsum C403 kg 0.150 4,000.00 600.00
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 0.728 65,000.00 47,320.00
Screw Bremick C649 Bh 6.000 120.00 720.00

JUMLAH HARGA BAHAN 153,150.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 297,150.00
E Overhead & Profit 10% 29,715.00
F Harga Satuan Pekerjaan (D+E) 326,865.00

Pemasangan 1 m2 Partisi WPC


Kode AHSP = 4.2.1.T7
A TENAGA
Pekerja C9 OH 0.850 80,000.00 68,000.00
Tukang kayu C19 OH 1.700 125,000.00 212,500.00
Kepala tukang C39 OH 0.400 150,000.00 60,000.00
Mandor C47 OH 0.150 120,000.00 18,000.00
JUMLAH TENAGA KERJA 358,500.00
B BAHAN
WPC Kisi-kisi C425 M2 1.000 865,000.00 865,000.00
Material Bantu lS 1.000 150,000.00 150,000.00

JUMLAH HARGA BAHAN 1,015,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,373,500.00
E Overhead & Profit 10% 137,350.00
F Harga Satuan Pekerjaan (D+E) 1,510,850.00

Pemasangan 1 m2 Partisi Cubicle


Kode AHSP = 4.2.1.T8
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Tukang Allumunium C26 OH 1.000 125,000.00 125,000.00
Kepala tukang C39 OH 0.250 150,000.00 37,500.00
Mandor C47 OH 0.100 120,000.00 12,000.00
JUMLAH TENAGA KERJA 214,500.00
B BAHAN
Phenolic Board 12mm C592 M2 1.200 1,200,000.00 1,440,000.00
Aksesoris & Material Bantu lS 1.000 144,000.00 144,000.00

JUMLAH HARGA BAHAN 1,584,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,798,500.00
E Overhead & Profit 10% 179,850.00
F Harga Satuan Pekerjaan (D+E) 1,978,350.00

Pemasangan 1 Set Partisi PR1 + Aksesoris bpkb


Kode AHSP = 4.2.1.T9
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00

JUMLAH TENAGA KERJA 3,000,000.00


B BAHAN
Profil alluminium "M" C605 M 47.960 41,666.67 1,998,333.33
Profil alluminium "Tutup Kaca Mati" C616 M 29.348 14,500.00 425,546.00
Profil alluminium "Ambang Datar Atas" C609 M2 0.990 28,855.83 28,567.28
Profil alluminium "Ambang Datar Bawah" C610 M2 0.990 44,574.00 44,128.26
Profil alluminium "Ambang Datar Tegak" C611 M2 5.302 37,770.67 200,260.07
Sticker Sandblast C689 M2 4.674 252,500.00 1,180,159.75
Kaca bening 5 mm C544 M2 14.322 128,000.00 1,833,216.00
Allumunium Spigot C491 M 40.000 22,500.00 900,000.00

JUMLAH HARGA BAHAN 6,610,210.69


C Aksesoris
Rell Pintu Dorong C642 Bh 1.000 550,000.00 550,000.00
Lockset Sliding Door C583 Bh 1.000 270,000.00 270,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sealant C656 Bh 35.610 6,000.00 213,660.00

JUMLAH HARGA ALAT 1,033,660.00


D Jumlah (A+B+C) 10,643,870.69
E Overhead & Profit 10% 1,064,387.07
F Harga Satuan Pekerjaan (D+E) 11,708,257.76

Pemasangan 1 Set Partisi PJ1 + Aksesoris bpkb


Kode AHSP = 4.2.1.T10
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 2,000,000.00 2,000,000.00

JUMLAH TENAGA KERJA 2,000,000.00


B BAHAN
Profil alluminium "M" C605 M 44.803 41,666.67 1,866,791.67
Profil alluminium "Tutup Kaca Mati" C616 M 7.491 14,500.00 108,619.50
Profil alluminium "Ambang Datar Atas" C609 M2 0.990 28,855.83 28,567.28
Profil alluminium "Ambang Datar Bawah" C610 M2 4.290 44,574.00 191,222.46
Profil alluminium "Ambang Datar Tegak" C611 M2 0.990 37,770.67 37,392.96
Kaca Warna (Dark Blue) 5 mm C569 M2 14.883 260,714.99 3,880,221.21
Allumunium Spigot C491 M 40.000 22,500.00 900,000.00
Profil alluminium "Stoper Casement" C612 M 4.444 25,571.33 113,639.01
Profil alluminium "Frame Casement" C613 M 4.444 34,173.33 151,866.29
Profil alluminium "Bead Casement" C615 M 4.444 13,020.11 57,861.37
Sticker Sandblast C689 M2 3.364 252,500.00 849,410.00

JUMLAH HARGA BAHAN 8,185,591.75


C Aksesoris
Friction Stay (Engsel Casement) 16" C527 Bh 6.000 245,000.00 1,470,000.00
Casement Handle C495 Bh 3.000 28,000.00 84,000.00
Engsel Pintu Kupu-kupu Allumunium C514 Set 3.000 143,000.00 429,000.00
Handle Set Tube Lever Handle C539 Set 1.000 710,000.00 710,000.00
Sealant C656 M 35.610 6,000.00 213,660.00

JUMLAH HARGA ALAT 2,906,660.00


D Jumlah (A+B+C) 13,092,251.75
E Overhead & Profit 10% 1,309,225.17
F Harga Satuan Pekerjaan (D+E) 14,401,476.92

Pemasangan 1 Set Partisi PJ2 + Aksesoris bpkb


Kode AHSP = 4.2.1.T11
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 750,000.00 750,000.00

JUMLAH TENAGA KERJA 750,000.00


B BAHAN
Profil alluminium "M" C605 M 10.780 41,666.67 449,166.67
Profil alluminium "Tutup Kaca Mati" C616 M 11.022 14,500.00 159,819.00
Profil alluminium "Ambang Datar Atas" C609 M2 0.990 28,855.83 28,567.28
Profil alluminium "Ambang Datar Bawah" C610 M2 4.620 44,574.00 205,931.88
Profil alluminium "Ambang Datar Tegak" C611 M2 0.990 37,770.67 37,392.96
Kaca Warna (Dark Blue) 5 mm C569 M2 5.181 260,714.99 1,350,764.37
Allumunium Spigot C491 M 10.000 22,500.00 225,000.00
Sticker Sandblast C689 M2 0.413 252,500.00 104,232.00

JUMLAH HARGA BAHAN 2,560,874.15


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Handle Set Tube Lever Handle C539 Bh 1.000 710,000.00 710,000.00
Sealant C656 M 27.460 6,000.00 164,760.00

JUMLAH HARGA ALAT 1,303,760.00


D Jumlah (A+B+C) 4,614,634.15
E Overhead & Profit 10% 461,463.42
F Harga Satuan Pekerjaan (D+E) 5,076,097.57

Pemasangan 1 Set Partisi PR2 + Aksesoris bpkb


Kode AHSP = 4.2.1.T12
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH TENAGA KERJA 3,000,000.00


B BAHAN
Profil alluminium "M" C605 M 60.870 41,666.67 2,536,250.00
Profil alluminium "Tutup Kaca Mati" C616 M 35.475 14,500.00 514,387.50
Profil alluminium "Ambang Datar Atas" C609 M2 1.760 28,855.83 50,786.27
Profil alluminium "Ambang Datar Bawah" C610 M2 1.760 44,574.00 78,450.24
Profil alluminium "Ambang Datar Tegak" C611 M2 9.240 37,770.67 349,000.96
Kaca bening 5 mm C544 M2 26.213 128,000.00 3,355,264.00
Sticker Sandblast C689 M2 8.129 252,500.00 2,052,572.50
Allumunium Spigot C491 M 25.000 22,500.00 562,500.00

JUMLAH HARGA BAHAN 9,499,211.47


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Mortise Lock C584 Bh 1.000 235,000.00 235,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Flush Bolt / Grandel Pintu Engsel Tanam C523 Bh 1.000 165,000.00 165,000.00
Sealant C656 M 102.030 6,000.00 612,180.00

JUMLAH HARGA ALAT 3,670,660.00


D Jumlah (A+B+C) 16,169,871.47
E Overhead & Profit 10% 1,616,987.15
F Harga Satuan Pekerjaan (D+E) 17,786,858.61

Pemasangan 1 Set Partisi PR3 + Aksesoris bpkb


Kode AHSP = 4.2.1.T13
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,500,000.00 1,500,000.00

JUMLAH TENAGA KERJA 1,500,000.00


B BAHAN
Profil alluminium "M" C605 M 26.334 41,666.67 1,097,250.00
Profil alluminium "Tutup Kaca Mati" C616 M 10.692 14,500.00 155,034.00
Profil alluminium "Ambang Datar Atas" C609 M2 0.880 28,855.83 25,393.13
Profil alluminium "Ambang Datar Bawah" C610 M2 0.880 44,574.00 39,225.12
Profil alluminium "Ambang Datar Tegak" C611 M2 4.620 37,770.67 174,500.48
Kaca bening 5 mm C544 M2 9.603 128,000.00 1,229,184.00
Sticker Sandblast C689 M2 2.964 252,500.00 748,511.00
Allumunium Spigot C491 M 15.000 22,500.00 337,500.00

JUMLAH HARGA BAHAN 3,806,597.73


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Mortise Lock C584 Bh 1.000 235,000.00 235,000.00
Pull Handle Stainless 32x300 C633 Bh 2.000 450,120.00 900,240.00
Sealant C656 M 35.130 6,000.00 210,780.00

JUMLAH HARGA ALAT 1,775,020.00


D Jumlah (A+B+C) 7,081,617.73
E Overhead & Profit 10% 708,161.77
F Harga Satuan Pekerjaan (D+E) 7,789,779.51

Pemasangan 1 Set Partisi PR4 + Aksesoris bpkb


Kode AHSP = 4.2.1.T14
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,500,000.00 1,500,000.00

JUMLAH TENAGA KERJA 1,500,000.00


B BAHAN
Profil alluminium "M" C605 M 25.641 41,666.67 1,068,375.00
Profil alluminium "Tutup Kaca Mati" C616 M 10.692 14,500.00 155,034.00
Profil alluminium "Ambang Datar Atas" C609 M2 0.880 28,855.83 25,393.13
Profil alluminium "Ambang Datar Bawah" C610 M2 0.880 44,574.00 39,225.12
Profil alluminium "Ambang Datar Tegak" C611 M2 4.620 37,770.67 174,500.48
Kaca bening 5 mm C544 M2 8.943 128,000.00 1,144,704.00
Sticker Sandblast C689 M2 2.759 252,500.00 696,546.50
Allumunium Spigot C491 M 15.000 22,500.00 337,500.00

JUMLAH HARGA BAHAN 3,641,278.23


C Aksesoris
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Mortise Lock C584 Bh 1.000 235,000.00 235,000.00
Pull Handle Stainless 32x300 C633 Bh 2.000 450,120.00 900,240.00
Sealant C656 M 34.290 6,000.00 205,740.00

JUMLAH HARGA ALAT 1,769,980.00


D Jumlah (A+B+C) 6,911,258.23
E Overhead & Profit 10% 691,125.82
F Harga Satuan Pekerjaan (D+E) 7,602,384.06

Pemasangan 1 Set Partisi PR5 + Aksesoris bpkb


Kode AHSP = 4.2.1.T15
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00

JUMLAH TENAGA KERJA 3,000,000.00


B BAHAN
Profil alluminium "M" C605 M 67.342 41,666.67 2,805,916.67
Profil alluminium "Tutup Kaca Mati" C616 M 29.898 14,500.00 433,521.00
Profil alluminium "Ambang Datar Atas" C609 M2 1.760 28,855.83 50,786.27
Profil alluminium "Ambang Datar Bawah" C610 M2 1.760 44,574.00 78,450.24
Profil alluminium "Ambang Datar Tegak" C611 M2 9.240 37,770.67 349,000.96
Kaca bening 5 mm C544 M2 26.037 128,000.00 3,332,736.00
Sticker Sandblast C689 M2 8.075 252,500.00 2,038,962.75
Allumunium Spigot C491 M 15.000 22,500.00 337,500.00

JUMLAH HARGA BAHAN 9,426,873.88


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Mortise Lock C584 Bh 1.000 235,000.00 235,000.00
Flush Bolt / Grandel Pintu Engsel Tanam C523 Bh 1.000 165,000.00 165,000.00
Sealant C656 M 96.080 6,000.00 576,480.00

JUMLAH HARGA ALAT 3,634,960.00


D Jumlah (A+B+C) 16,061,833.88
E Overhead & Profit 10% 1,606,183.39
F Harga Satuan Pekerjaan (D+E) 17,668,017.27

Pemasangan 1 Set Partisi PR6 + Aksesoris bpkb


Kode AHSP = 4.2.1.T16
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 2,000,000.00 2,000,000.00

JUMLAH TENAGA KERJA 2,000,000.00


B BAHAN
Profil alluminium "M" C605 M 39.138 41,666.67 1,630,750.00
Profil alluminium "Tutup Kaca Mati" C616 M 21.373 14,500.00 309,908.50
Kaca bening 5 mm C544 M2 13.123 128,000.00 1,679,744.00
Sticker Sandblast C689 M2 4.783 252,500.00 1,207,631.75
Allumunium Spigot C491 M 15.000 22,500.00 337,500.00

JUMLAH HARGA BAHAN 5,165,534.25


C Aksesoris
Sealant C656 M 53.570 6,000.00 321,420.00

JUMLAH HARGA ALAT 321,420.00


D Jumlah (A+B+C) 7,486,954.25
E Overhead & Profit 10% 748,695.43
F Harga Satuan Pekerjaan (D+E) 8,235,649.68

Pemasangan 1 Set Partisi PR7 + Aksesoris bpkb


Kode AHSP = 4.2.1.T17
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,000,000.00 1,000,000.00

JUMLAH TENAGA KERJA 1,000,000.00


B BAHAN
Profil alluminium "M" C605 M 26.631 41,666.67 1,109,625.00
Profil alluminium "Tutup Kaca Mati" C616 M 12.749 14,500.00 184,860.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kaca bening 5 mm C544 M2 9.449 128,000.00 1,209,472.00
Sticker Sandblast C689 M2 2.940 252,500.00 742,324.75
Allumunium Spigot C491 M 10.000 22,500.00 225,000.00

JUMLAH HARGA BAHAN 3,471,282.25


C Aksesoris
Sealant C656 M 34.920 6,000.00 209,520.00

JUMLAH HARGA ALAT 209,520.00


D Jumlah (A+B+C) 4,680,802.25
E Overhead & Profit 10% 468,080.23
F Harga Satuan Pekerjaan (D+E) 5,148,882.48

Pemasangan 1 Set Partisi PR8 + Aksesoris bpkb


Kode AHSP = 4.2.1.T18
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,000,000.00 1,000,000.00

JUMLAH TENAGA KERJA 1,000,000.00


B BAHAN
Profil alluminium "M" C605 M 26.070 41,666.67 1,086,250.00
Profil alluminium "Tutup Kaca Mati" C616 M 12.562 14,500.00 182,149.00
Kaca bening 5 mm C544 M2 8.921 128,000.00 1,141,888.00
Sticker Sandblast C689 M2 2.773 252,500.00 700,258.25
Allumunium Spigot C491 M 10.000 22,500.00 225,000.00

JUMLAH HARGA BAHAN 3,335,545.25


C Aksesoris
Sealant C656 M 34.240 6,000.00 205,440.00

JUMLAH HARGA ALAT 205,440.00


D Jumlah (A+B+C) 4,540,985.25
E Overhead & Profit 10% 454,098.53
F Harga Satuan Pekerjaan (D+E) 4,995,083.78

Pemasangan 1 Set Partisi PR9 + Aksesoris bpkb


Kode AHSP = 4.2.1.T19
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00

JUMLAH TENAGA KERJA 3,000,000.00


B BAHAN
Sticker Sandblast C689 m2 10.362 252,500.00 2,616,405.00
Kaca Temperet 12 mm C560 M2 28.260 922,000.00 26,055,720.00

JUMLAH HARGA BAHAN 28,672,125.00


C Aksesoris
Engsel Tanam C516 Bh 2.000 781,200.00 1,562,400.00
Patch Fitting PT40 C588 Bh 2.000 779,960.00 1,559,920.00
Patch Fitting PT20 C589 Bh 2.000 469,960.00 939,920.00
Patch Fitting PT10 C590 Bh 2.000 469,960.00 939,920.00
Glass Clip Temperet + Dinabolt C690 Bh 32.000 100,000.00 3,200,000.00
Profil alluminium "M" C605 M' 9.420 41,666.67 392,500.00
Profil alluminium "Tutup Kaca Mati" C616 M' 9.420 14,500.00 136,590.00
Patch Lock C591 Bh 2.000 877,920.00 1,755,840.00
Pull Handle Stainless 38x1000 C632 Bh 4.000 1,070,120.00 4,280,480.00
Sticker Sandblast C689 M2 9.012 252,500.00 2,275,403.75
Sealant C656 M 56.520 6,000.00 339,120.00

JUMLAH HARGA ALAT 17,382,093.75


D Jumlah (A+B+C) 49,054,218.75
E Overhead & Profit 10% 4,905,421.88
F Harga Satuan Pekerjaan (D+E) 53,959,640.63

Pemasangan 1 Set Partisi PR10 + Aksesoris bpkb


Kode AHSP = 4.2.1.T20
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00

JUMLAH TENAGA KERJA 3,000,000.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Kaca Temperet 12 mm C560 M2 3.620 922,000.00 3,337,640.00

JUMLAH HARGA BAHAN 3,337,640.00


C Aksesoris
Engsel Tanam C516 Bh 1.000 781,200.00 781,200.00
Patch Fitting PT40 C588 Bh 1.000 779,960.00 779,960.00
Patch Fitting PT20 C589 Bh 1.000 469,960.00 469,960.00
Patch Fitting PT10 C590 Bh 1.000 469,960.00 469,960.00
Glass Clip Temperet + Dinabolt C690 Bh 10.000 100,000.00 1,000,000.00
Profil alluminium "M" C605 M' 1.800 41,666.67 75,000.00
Profil alluminium "Tutup Kaca Mati" C616 M' 1.800 14,500.00 26,100.00
Patch Lock C591 Bh 1.000 877,920.00 877,920.00
Pull Handle Stainless 32x300 C633 Bh 2.000 450,120.00 900,240.00
Sealant C656 M 7.200 6,000.00 43,200.00

JUMLAH HARGA ALAT 5,423,540.00


D Jumlah (A+B+C) 11,761,180.00
E Overhead & Profit 10% 1,176,118.00
F Harga Satuan Pekerjaan (D+E) 12,937,298.00

Pemasangan 1 Set Pintu PJ5 + Aksesoris


Kode AHSP = 4.2.1.T21
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,850,000.00 1,850,000.00

JUMLAH TENAGA KERJA 1,850,000.00


B BAHAN
Profil alluminium "Profil C" C599 M 13.695 35,333.33 483,890.00
Profil alluminium "Tutup Polos" C617 M 7.150 14,333.33 102,483.33
Kaca Temperet 12 mm C560 M2 2.254 922,000.00 2,078,298.64
Kaca Stopsol Tempered 5 mm C554 M2 4.095 584,000.00 2,391,334.00
Allumunium Spigot C491 M 20.000 22,500.00 450,000.00
Profil alluminium "Stoper Casement" C612 M 5.544 25,571.33 141,767.47
Profil alluminium "Frame Casement" C613 M 5.544 34,173.33 189,456.96
Profil alluminium "Bead Casement" C615 M 5.544 13,020.11 72,183.50

JUMLAH HARGA BAHAN 5,909,413.90


C Aksesoris
Friction Stay (Engsel Casement) 14" C526 Bh 2.000 154,070.00 308,140.00
Casement Handle C495 Bh 1.000 28,000.00 28,000.00
Engsel Tanam C516 Bh 1.000 781,200.00 781,200.00
Patch Fitting PT20 C589 Bh 1.000 469,960.00 469,960.00
Patch Fitting PT10 C590 Bh 1.000 469,960.00 469,960.00
Patch Lock C591 Bh 1.000 877,920.00 877,920.00
Pull Handle Stainless 38x1000 C632 Bh 2.000 1,070,120.00 2,140,240.00
Sealant C656 M 27.390 6,000.00 164,340.00

JUMLAH HARGA ALAT 5,239,760.00


D Jumlah (A+B+C) 12,999,173.90
E Overhead & Profit 10% 1,299,917.39
F Harga Satuan Pekerjaan (D+E) 14,299,091.29

Pemasangan 1 Set Pintu PJ6 + Aksesoris


Kode AHSP = 4.2.1.T22
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 2,700,000.00 2,700,000.00

JUMLAH TENAGA KERJA 2,700,000.00


B BAHAN
Profil alluminium "Profil C" C599 M 19.547 35,333.33 690,660.67
Profil alluminium "Tutup Polos" C617 M 7.975 14,333.33 114,308.33
Kaca Stopsol Tempered 5 mm C554 M2 5.291 584,000.00 3,089,944.00
Allumunium Spigot C491 M 20.000 22,500.00 450,000.00
Pintu Emergency Pabrikasi (Double Door) C596 Set 1.000 18,300,000.00 18,300,000.00

JUMLAH HARGA BAHAN 22,644,913.00


C Aksesoris
Sealant C656 M 39.094 6,000.00 234,564.00

JUMLAH HARGA ALAT 234,564.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 25,579,477.00
E Overhead & Profit 10% 2,557,947.70
F Harga Satuan Pekerjaan (D+E) 28,137,424.70

Pemasangan 1 Set Pintu Emergency + Aksesoris


Kode AHSP = 4.2.1.T23
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,700,000.00 1,700,000.00

JUMLAH TENAGA KERJA 1,700,000.00


B BAHAN
Pintu Emergency Pabrikasi (Single Door) C597 Set 1.000 11,800,000.00 11,800,000.00

JUMLAH HARGA BAHAN 11,800,000.00


C Aksesoris
Sealant C656 M 7.744 6,000.00 46,464.00

JUMLAH HARGA ALAT 46,464.00


D Jumlah (A+B+C) 13,546,464.00
E Overhead & Profit 10% 1,354,646.40
F Harga Satuan Pekerjaan (D+E) 14,901,110.40

pemasangan 1 Set Partisi PR1 + Aksesoris


Kode AHSP = 4.2.1.T24
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 8,000,000.00 8,000,000.00

JUMLAH TENAGA KERJA 8,000,000.00


B BAHAN
Profil alluminium "M" C605 M 39.138 41,666.67 1,630,750.00
Profil alluminium "Tutup Kaca Mati" C616 M 21.967 14,500.00 318,521.50
Sticker Sandblast C689 M2 5.148 252,500.00 1,299,870.00
Kaca bening 6 mm C545 M2 10.219 135,000.00 1,379,565.00
Allumunium Spigot C491 M 40.000 22,500.00 900,000.00

JUMLAH HARGA BAHAN 5,528,706.50


C Aksesoris
Rell Pintu Dorong C642 Bh 1.000 550,000.00 550,000.00
Lockset Sliding Door C583 Bh 1.000 270,000.00 270,000.00
Sealant C656 Bh 166.430 6,000.00 998,580.00

JUMLAH HARGA ALAT 1,818,580.00


D Jumlah (A+B+C) 15,347,286.50
E Overhead & Profit 10% 1,534,728.65
F Harga Satuan Pekerjaan (D+E) 16,882,015.15

pemasangan 1 Set Partisi PR2 + Aksesoris


Kode AHSP = 4.2.1.T25
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 6,000,000.00 6,000,000.00

JUMLAH TENAGA KERJA 6,000,000.00


B BAHAN
Sticker Sandblast C689 m2 33.438 252,500.00 8,442,968.75
Kaca Temperet 12 mm C560 M2 66.875 922,000.00 61,658,750.00

JUMLAH HARGA BAHAN 70,101,718.75


C Aksesoris
Engsel Tanam C516 Bh 4.000 781,200.00 3,124,800.00
Patch Fitting PT40 C588 Bh 4.000 779,960.00 3,119,840.00
Patch Fitting PT20 C589 Bh 4.000 469,960.00 1,879,840.00
Patch Fitting PT10 C590 Bh 4.000 469,960.00 1,879,840.00
Patch Lock C591 Bh 4.000 877,920.00 3,511,680.00
Glass Clip Temperet + Dinabolt C690 Bh 84.000 100,000.00 8,400,000.00
Profil alluminium "M" C605 M' 26.700 41,666.67 1,112,500.00
Profil alluminium "Tutup Kaca Mati" C616 M' 26.700 14,500.00 387,150.00
Pull Handle Stainless 38x1000 C632 Bh 8.000 1,070,120.00 8,560,960.00
Sealant C656 M 133.750 6,000.00 802,500.00

JUMLAH HARGA ALAT 32,779,110.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 108,880,828.75
E Overhead & Profit 10% 10,888,082.88
F Harga Satuan Pekerjaan (D+E) 119,768,911.63

pemasangan 1 Set Partisi PR3 + Aksesoris


Kode AHSP = 4.2.1.T26
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00

JUMLAH TENAGA KERJA 3,000,000.00


B BAHAN
Sticker Sandblast C689 m2 7.313 252,500.00 1,846,406.25
Kaca Temperet 12 mm C560 M2 14.625 922,000.00 13,484,250.00

JUMLAH HARGA BAHAN 15,330,656.25


C Aksesoris
Engsel Tanam C516 Bh 1.000 781,200.00 781,200.00
Patch Fitting PT40 C588 Bh 1.000 779,960.00 779,960.00
Patch Fitting PT20 C589 Bh 1.000 469,960.00 469,960.00
Patch Fitting PT10 C590 Bh 1.000 469,960.00 469,960.00
Patch Lock C591 Bh 1.000 877,920.00 877,920.00
Glass Clip Temperet + Dinabolt C690 Bh 15.000 100,000.00 1,500,000.00
Profil alluminium "M" C605 M' 5.850 41,666.67 243,750.00
Profil alluminium "Tutup Kaca Mati" C616 M' 5.850 14,500.00 84,825.00
Pull Handle Stainless 38x1000 C632 Bh 2.000 1,070,120.00 2,140,240.00
Sealant C656 M 29.250 6,000.00 175,500.00

JUMLAH HARGA ALAT 7,523,315.00


D Jumlah (A+B+C) 25,853,971.25
E Overhead & Profit 10% 2,585,397.13
F Harga Satuan Pekerjaan (D+E) 28,439,368.38

pemasangan 1 Set Partisi PR4 + Aksesoris


Kode AHSP = 4.2.1.T27
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 6,000,000.00 6,000,000.00

JUMLAH TENAGA KERJA 6,000,000.00


B BAHAN
Sticker Sandblast C689 m2 31.875 252,500.00 8,048,437.50
Kaca Temperet 12 mm C560 M2 63.750 922,000.00 58,777,500.00

JUMLAH HARGA BAHAN 66,825,937.50


C Aksesoris
Engsel Tanam C516 Bh 4.000 781,200.00 3,124,800.00
Patch Fitting PT40 C588 Bh 4.000 779,960.00 3,119,840.00
Patch Fitting PT20 C589 Bh 4.000 469,960.00 1,879,840.00
Patch Fitting PT10 C590 Bh 4.000 469,960.00 1,879,840.00
Patch Lock C591 Bh 4.000 877,920.00 3,511,680.00
Glass Clip Temperet + Dinabolt C690 Bh 87.000 100,000.00 8,700,000.00
Profil alluminium "M" C605 M' 22.770 41,666.67 948,750.00
Profil alluminium "Tutup Kaca Mati" C616 M' 22.770 14,500.00 330,165.00
Pull Handle Stainless 38x1000 C632 Bh 8.000 1,070,120.00 8,560,960.00
Sealant C656 M 137.500 6,000.00 825,000.00

JUMLAH HARGA ALAT 32,880,875.00


D Jumlah (A+B+C) 105,706,812.50
E Overhead & Profit 10% 10,570,681.25
F Harga Satuan Pekerjaan (D+E) 116,277,493.75

pemasangan 1 Set Partisi PR5 + Aksesoris


Kode AHSP = 4.2.1.T28
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,800,000.00 3,800,000.00

JUMLAH TENAGA KERJA 3,800,000.00


B BAHAN
Sticker Sandblast C689 m2 19.360 252,500.00 4,888,400.00
Kaca Temperet 12 mm C560 M2 38.720 922,000.00 35,699,840.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 40,588,240.00
C Aksesoris
Engsel Tanam C516 Bh 4.000 781,200.00 3,124,800.00
Patch Fitting PT40 C588 Bh 4.000 779,960.00 3,119,840.00
Patch Fitting PT20 C589 Bh 4.000 469,960.00 1,879,840.00
Patch Fitting PT10 C590 Bh 4.000 469,960.00 1,879,840.00
Profil alluminium "M" C605 M' 58.700 41,666.67 2,445,833.33
Profil alluminium "Tutup Jeep" C618 M' 58.700 19,159.00 1,124,633.30
Patch Lock C591 Bh 4.000 877,920.00 3,511,680.00
Pull Handle Stainless 38x1000 C632 Bh 8.000 1,070,120.00 8,560,960.00
Sealant C656 M 137.500 6,000.00 825,000.00

JUMLAH HARGA ALAT 26,472,426.63


D Jumlah (A+B+C) 70,860,666.63
E Overhead & Profit 10% 7,086,066.66
F Harga Satuan Pekerjaan (D+E) 77,946,733.30

pemasangan 1 Set Partisi PR6 + Aksesoris


Kode AHSP = 4.2.1.T29
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,000,000.00 3,000,000.00

JUMLAH TENAGA KERJA 3,000,000.00


B BAHAN
Sticker Sandblast C689 m2 11.500 252,500.00 2,903,750.00
Kaca Temperet 12 mm C560 M2 23.000 922,000.00 21,206,000.00

JUMLAH HARGA BAHAN 24,109,750.00


C Aksesoris
Engsel Tanam C516 Bh 1.000 781,200.00 781,200.00
Patch Fitting PT40 C588 Bh 1.000 779,960.00 779,960.00
Patch Fitting PT20 C589 Bh 1.000 469,960.00 469,960.00
Patch Fitting PT10 C590 Bh 1.000 469,960.00 469,960.00
Glass Clip Temperet + Dinabolt C690 Bh 18.000 100,000.00 1,800,000.00
Profil alluminium "M" C605 M' 9.200 41,666.67 383,333.33
Profil alluminium "Tutup Kaca Mati" C616 M' 9.200 14,500.00 133,400.00
Patch Lock C591 Bh 1.000 877,920.00 877,920.00
Pull Handle Stainless 38x1000 C632 Bh 2.000 1,070,120.00 2,140,240.00
Sealant C656 M 46.000 6,000.00 276,000.00

JUMLAH HARGA ALAT 8,111,973.33


D Jumlah (A+B+C) 35,221,723.33
E Overhead & Profit 10% 3,522,172.33
F Harga Satuan Pekerjaan (D+E) 38,743,895.67

pemasangan 1 Set Partisi PR7 + Aksesoris


Kode AHSP = 4.2.1.T30
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,500,000.00 3,500,000.00

JUMLAH TENAGA KERJA 3,500,000.00


B BAHAN
Sticker Sandblast C689 m2 18.913 252,500.00 4,775,406.25
Kaca Temperet 12 mm C560 M2 37.825 922,000.00 34,874,650.00

JUMLAH HARGA BAHAN 39,650,056.25


C Aksesoris
Engsel Tanam C516 Bh 3.000 781,200.00 2,343,600.00
Patch Fitting PT40 C588 Bh 3.000 779,960.00 2,339,880.00
Patch Fitting PT20 C589 Bh 3.000 469,960.00 1,409,880.00
Patch Fitting PT10 C590 Bh 3.000 469,960.00 1,409,880.00
Glass Clip Temperet + Dinabolt C690 Bh 32.000 100,000.00 3,200,000.00
Profil alluminium "M" C605 M' 15.130 41,666.67 630,416.67
Profil alluminium "Tutup Kaca Mati" C616 M' 15.130 14,500.00 219,385.00
Patch Lock C591 Bh 3.000 877,920.00 2,633,760.00
Pull Handle Stainless 38x1000 C632 Bh 6.000 1,070,120.00 6,420,720.00
Sealant C656 M 75.650 6,000.00 453,900.00

JUMLAH HARGA ALAT 21,061,421.67


D Jumlah (A+B+C) 64,211,477.92
E Overhead & Profit 10% 6,421,147.79
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 70,632,625.71

pemasangan 1 Set Partisi PR8 + Aksesoris


Kode AHSP = 4.2.1.T31
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,700,000.00 1,700,000.00

JUMLAH TENAGA KERJA 1,700,000.00


B BAHAN
Profil alluminium "M" C605 M 83.215 41,666.67 3,467,291.67
Profil alluminium "Tutup Kaca Mati" C616 M 55.605 14,500.00 806,272.50
Sticker Sandblast C689 M2 5.005 252,500.00 1,263,762.50
Kaca Stopsol Tempered 5 mm C554 M2 36.575 584,000.00 21,359,800.00
Allumunium Spigot C491 M 40.000 22,500.00 900,000.00

JUMLAH HARGA BAHAN 27,797,126.67


C Aksesoris
Rell Pintu Dorong C642 Bh 1.000 550,000.00 550,000.00
Lockset Sliding Door C583 Bh 1.000 270,000.00 270,000.00
Sealant C656 Bh 166.430 6,000.00 998,580.00

JUMLAH HARGA ALAT 1,818,580.00


D Jumlah (A+B+C) 31,315,706.67
E Overhead & Profit 10% 3,131,570.67
F Harga Satuan Pekerjaan (D+E) 34,447,277.33

pemasangan 1 Set Partisi PR9 + Aksesoris


Kode AHSP = 4.2.1.T32
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,700,000.00 1,700,000.00

JUMLAH TENAGA KERJA 1,700,000.00


B BAHAN
Profil alluminium "M" C605 M 31.042 41,666.67 1,293,416.67
Profil alluminium Openbek "Profil C" C604 M 5.830 35,333.33 205,993.33
Profil alluminium "Tutup Kaca Mati" C616 M 20.570 14,500.00 298,265.00
Kaca Bening 5 mm C544 M2 15.089 128,000.00 1,931,328.00
Allumunium Spigot C491 M 21.000 22,500.00 472,500.00
Panil MDF 9mm C586 M2 4.259 175,000.00 745,360.00
Panil MDF 18mm C587 M2 1.496 280,000.00 418,880.00
High Laminate Pressure (HPL) C255 M2 4.259 85,382.51 363,661.20
Profil Allumunium List U C622 M' 4.422 6,334.25 28,010.05
Kaca Buram 5 mm C547 M2 2.211 180,000.00 397,980.00

JUMLAH HARGA BAHAN 6,155,394.26


C Aksesoris
Engsel Pintu Kupu-kupu C513 Bh 3.000 82,550.00 247,650.00
Lever Handle Plate C580 Bh 2.000 118,750.00 237,500.00
Mortise Lock C584 Bh 1.000 235,000.00 235,000.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Bh 1.000 35,400.00 35,400.00
Sealant C656 M 8.844 6,000.00 53,064.00

JUMLAH HARGA ALAT 808,614.00


D Jumlah (A+B+C) 8,664,008.26
E Overhead & Profit 10% 866,400.83
F Harga Satuan Pekerjaan (D+E) 9,530,409.08

pemasangan 1 Set Pintu P1 + Aksesoris


Kode AHSP = 4.2.1.T33
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 400,000.00 400,000.00

JUMLAH TENAGA KERJA 400,000.00


B BAHAN
Steel Door Type Single C668 set 1.000 4,850,000.00 4,850,000.00

JUMLAH HARGA BAHAN 4,850,000.00


C Aksesoris
Aksesoris Pintu (Engsel, Handle, dll) Bh 1.000 727,500.00 727,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT 727,500.00
D Jumlah (A+B+C) 5,977,500.00
E Overhead & Profit 10% 597,750.00
F Harga Satuan Pekerjaan (D+E) 6,575,250.00

pemasangan 1 Set Pintu P2 + Aksesoris (kamuflase)


Kode AHSP = 4.2.1.T34
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,000,000.00 1,000,000.00

JUMLAH TENAGA KERJA 1,000,000.00


B BAHAN
Panil MDF 9mm C586 M2 4.257 175,000.00 744,975.00
Panil MDF 18mm C587 M2 1.474 280,000.00 412,720.00
High Laminate Pressure (HPL) C255 M2 4.257 85,382.51 363,473.36

JUMLAH HARGA BAHAN 1,521,168.36


C Aksesoris
Engsel Pintu Kupu-kupu C513 Bh 3.000 82,550.00 247,650.00
Door Closer C504 Bh 1.000 540,000.00 540,000.00

JUMLAH HARGA ALAT 787,650.00


D Jumlah (A+B+C) 3,308,818.36
E Overhead & Profit 10% 330,881.84
F Harga Satuan Pekerjaan (D+E) 3,639,700.20

pemasangan 1 Set Pintu P3 + Aksesoriss (difable)


Kode AHSP = 4.2.1.T35
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 750,000.00 750,000.00

JUMLAH TENAGA KERJA 750,000.00


B BAHAN
Profil alluminium "Profil C" C599 M2 5.940 35,333.33 209,880.00
Panil MDF 9mm C586 M2 5.082 175,000.00 889,350.00
Panil MDF 18mm C587 M2 1.584 280,000.00 443,520.00
High Laminate Pressure (HPL) C255 M2 5.082 85,382.51 433,913.93

JUMLAH HARGA BAHAN 1,976,663.93


C Aksesoris
Engsel Pintu Kupu-kupu C513 Bh 3.000 82,550.00 247,650.00
Handle Set Tube Lever Handle C539 Bh 1.000 710,000.00 710,000.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Bh 1.000 35,400.00 35,400.00

JUMLAH HARGA ALAT 993,050.00


D Jumlah (A+B+C) 3,719,713.93
E Overhead & Profit 10% 371,971.39
F Harga Satuan Pekerjaan (D+E) 4,091,685.33

pemasangan 1 Set Pintu P4 + Aksesoris (emergency)


Kode AHSP = 4.2.1.T36
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 750,000.00 750,000.00

JUMLAH TENAGA KERJA 750,000.00


B BAHAN
Fire Door Single C521 unit 1.000 11,800,000.00 11,800,000.00

JUMLAH HARGA BAHAN 11,800,000.00


C Aksesoris
Aksesoris Pintu (Engsel, Handle, dll) Ls 1.000 1,770,000.00 1,770,000.00

JUMLAH HARGA ALAT 1,770,000.00


D Jumlah (A+B+C) 14,320,000.00
E Overhead & Profit 10% 1,432,000.00
F Harga Satuan Pekerjaan (D+E) 15,752,000.00

pemasangan 1 Set Pintu P5 + Aksesoris (sliding)


Kode AHSP = 4.2.1.T37
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pengerjaan Dan Pemasangan Ls 1.000 1,250,000.00 1,250,000.00

JUMLAH TENAGA KERJA 1,250,000.00


B BAHAN
Profil alluminium "Ambang Datar Tegak" C611 M 5.456 37,770.67 206,076.76
Profil alluminium "Ambang Datar Bawah" C610 M 0.990 44,574.00 44,128.26
Profil alluminium "Ambang Datar Atas" C609 M 0.990 28,855.83 28,567.28
Kaca bening 5 mm C544 M2 1.522 128,000.00 194,839.04
Sticker Sandblast C689 M2 0.666 252,500.00 168,165.00
Sealant C656 M 7.722 6,000.00 46,332.00

JUMLAH HARGA BAHAN 688,108.33


C Aksesoris
Rell Pintu Dorong C642 Bh 1.000 550,000.00 550,000.00
Lockset Sliding Door C583 Set 1.000 270,000.00 270,000.00

JUMLAH HARGA ALAT 820,000.00


D Jumlah (A+B+C) 2,758,108.33
E Overhead & Profit 10% 275,810.83
F Harga Satuan Pekerjaan (D+E) 3,033,919.17

pemasangan 1 Set Pintu P6 + Aksesoris


Kode AHSP = 4.2.1.T38
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,250,000.00 1,250,000.00

JUMLAH TENAGA KERJA 1,250,000.00


B BAHAN
Profil alluminium "Ambang Datar Tegak" C611 Lbr 9.240 37,770.67 349,000.96
Profil alluminium "Ambang Datar Bawah" C610 Lbr 1.760 44,574.00 78,450.24
Profil alluminium "Ambang Datar Atas" C609 Lbr 1.760 28,855.83 50,786.27
Profil alluminium "M" C605 M' 11.000 41,666.67 458,333.33
Kaca Bening 5 mm C544 M2 4.103 128,000.00 525,184.00
Sticker Sandblast C689 M2 1.254 252,500.00 316,736.00

JUMLAH HARGA BAHAN 1,778,490.80


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Mortise Lock C584 Bh 1.000 235,000.00 235,000.00
Flush Bolt / Grandel Pintu Engsel Tanam C523 Bh 1.000 165,000.00 165,000.00
Sealant C656 M 18.337 6,000.00 110,022.00

JUMLAH HARGA ALAT 3,168,502.00


D Jumlah (A+B+C) 6,196,992.80
E Overhead & Profit 10% 619,699.28
F Harga Satuan Pekerjaan (D+E) 6,816,692.08

pemasangan 1 Set Pintu P7 + Aksesoris


Kode AHSP = 4.2.1.T39
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,250,000.00 1,250,000.00

JUMLAH TENAGA KERJA 1,250,000.00


B BAHAN
Profil alluminium "Ambang Datar Tegak" C611 Lbr 9.240 37,770.67 349,000.96
Profil alluminium "Ambang Datar Bawah" C610 Lbr 1.760 44,574.00 78,450.24
Profil alluminium "Ambang Datar Atas" C609 Lbr 1.760 28,855.83 50,786.27
Profil alluminium "M" C605 M' 11.000 41,666.67 458,333.33
Kaca Bening 5 mm C544 M2 4.103 128,000.00 525,184.00
Sticker Sandblast C689 M2 1.254 252,500.00 316,736.00

JUMLAH HARGA BAHAN 1,778,490.80


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Digital Lock Fingerprint Pintu Allumunium C501 Bh 1.000 4,950,000.00 4,950,000.00
Sealant C656 M 18.337 6,000.00 110,022.00

JUMLAH HARGA ALAT 5,918,022.00


D Jumlah (A+B+C) 8,946,512.80
E Overhead & Profit 10% 894,651.28
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 9,841,164.08

pemasangan 1 Set Jendela (J1) + Aksesoris


Kode AHSP = 4.2.1.T40
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 250,000.00 250,000.00

JUMLAH TENAGA KERJA 250,000.00


B BAHAN
Profil alluminium "M" C605 M 3.784 41,666.67 157,666.67
Profil alluminium "Stoper Casement" C612 M 3.432 25,571.33 87,760.82
Profil alluminium "Frame Casement" C613 M 3.432 34,173.33 117,282.88
Profil alluminium "Bead Casement" C615 M 3.432 13,020.11 44,685.02
Kaca Warna (Dark Blue) 5 mm C569 M2 0.506 260,714.99 131,921.79
Allumunium Spigot C491 M 5.000 22,500.00 112,500.00

JUMLAH HARGA BAHAN 651,817.17


C Aksesoris
Friction Stay (Engsel Casement) 14" C526 Bh 2.000 154,070.00 308,140.00
Casement Handle C495 Bh 1.000 28,000.00 28,000.00
Sealant C656 M 47.520 6,000.00 285,120.00

JUMLAH HARGA ALAT 621,260.00


D Jumlah (A+B+C) 1,523,077.17
E Overhead & Profit 10% 152,307.72
F Harga Satuan Pekerjaan (D+E) 1,675,384.89

pemasangan 1 Set Jendela (J2) + Aksesoris


Kode AHSP = 4.2.1.T41
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,500,000.00 1,500,000.00

JUMLAH TENAGA KERJA 1,500,000.00


B BAHAN
Profil alluminium "M" C605 M 10.263 41,666.67 427,625.00
Profil alluminium "Tutup Polos" C617 M 0.891 14,333.33 12,771.00
Profil alluminium "Stoper Casement" C612 M 4.554 25,571.33 116,451.85
Profil alluminium "Frame Casement" C613 M 4.554 34,173.33 155,625.36
Profil alluminium "Bead Casement" C615 M 4.554 13,020.11 59,293.59
Kaca Warna (Dark Blue) 5 mm C569 M2 2.178 260,714.99 567,837.25
Allumunium Spigot C491 M 10.000 22,500.00 225,000.00
Sticker Sandblast C689 M2 0.551 252,500.00 139,051.75

JUMLAH HARGA BAHAN 1,703,655.80


C Aksesoris
Friction Stay (Engsel Casement) 16" C527 Bh 2.000 245,000.00 490,000.00
Casement Handle C495 Bh 1.000 28,000.00 28,000.00
Sealant C656 M 7.293 6,000.00 43,758.00

JUMLAH HARGA ALAT 561,758.00


D Jumlah (A+B+C) 3,765,413.80
E Overhead & Profit 10% 376,541.38
F Harga Satuan Pekerjaan (D+E) 4,141,955.18

pemasangan 1 Set Jendela (J3) + Aksesoris


Kode AHSP = 4.2.1.T42
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,300,000.00 1,300,000.00

JUMLAH TENAGA KERJA 1,300,000.00


B BAHAN
Profil alluminium "M" C605 M 20.790 41,666.67 866,250.00
Profil alluminium "Tutup Polos" C617 M 3.240 14,333.33 46,440.00
Profil alluminium "Stoper Casement" C612 M 5.852 25,571.33 149,643.44
Profil alluminium "Frame Casement" C613 M 5.852 34,173.33 199,982.35
Profil alluminium "Bead Casement" C615 M 5.852 13,020.11 76,193.69
Kaca Warna (Dark Blue) 5 mm C569 M2 6.140 260,714.99 1,600,790.05
Allumunium Spigot C491 M 10.000 22,500.00 225,000.00

JUMLAH HARGA BAHAN 3,164,299.52


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C Aksesoris
Friction Stay (Engsel Casement) 16" C527 Bh 4.000 245,000.00 980,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 M 24.470 6,000.00 146,820.00

JUMLAH HARGA ALAT 1,182,820.00


D Jumlah (A+B+C) 5,647,119.52
E Overhead & Profit 10% 564,711.95
F Harga Satuan Pekerjaan (D+E) 6,211,831.48

pemasangan 1 Set Jendela (J4) + Aksesoris


Kode AHSP = 4.2.1.T43
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 300,000.00 300,000.00

JUMLAH TENAGA KERJA 300,000.00


B BAHAN
Profil alluminium "M" C605 M 2.530 41,666.67 105,416.67
Kaca Warna (Dark Blue) 5 mm C569 M2 0.616 260,714.99 160,600.43
Allumunium Spigot C491 M 5.000 22,500.00 112,500.00

JUMLAH HARGA BAHAN 378,517.10


C Aksesoris
Sealant C656 M 4.240 6,000.00 25,440.00

JUMLAH HARGA ALAT 25,440.00


D Jumlah (A+B+C) 703,957.10
E Overhead & Profit 10% 70,395.71
F Harga Satuan Pekerjaan (D+E) 774,352.81

pemasangan 1 Set Jendela (J5) + Aksesoris


Kode AHSP = 4.2.1.T44
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 300,000.00 300,000.00

JUMLAH TENAGA KERJA 300,000.00


B BAHAN
Profil alluminium "M" C605 M 2.530 41,666.67 105,416.67
Profil Alluminium Strip C619 m 11.935 13,683.33 163,310.58
Allumunium Spigot C491 M 5.000 22,500.00 112,500.00

JUMLAH HARGA BAHAN 381,227.25


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 681,227.25
E Overhead & Profit 10% 68,122.73
F Harga Satuan Pekerjaan (D+E) 749,349.98

pemasangan 1 Set Jendela (J6) + Aksesoris


Kode AHSP = 4.2.1.T45
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,500,000.00 1,500,000.00

JUMLAH TENAGA KERJA 1,500,000.00


B BAHAN
Profil alluminium "M" C605 M 10.296 41,666.67 429,000.00
Profil alluminium "Tutup Polos" C617 M 1.144 14,333.33 16,397.33
Profil alluminium "Stoper Casement" C612 M 3.740 25,571.33 95,636.79
Profil alluminium "Frame Casement" C613 M 3.740 34,173.33 127,808.27
Profil alluminium "Bead Casement" C615 M 3.740 13,020.11 48,695.22
Kaca Warna (Dark Blue) 5 mm C569 M2 1.463 260,714.99 381,426.03
Allumunium Spigot C491 M 10.000 22,500.00 225,000.00

JUMLAH HARGA BAHAN 1,323,963.63


C Aksesoris
Friction Stay (Engsel Casement) 14" C526 Bh 2.000 154,070.00 308,140.00
Casement Handle C495 Bh 1.000 28,000.00 28,000.00
Sealant C656 M 7.293 6,000.00 43,758.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT 379,898.00
D Jumlah (A+B+C) 3,203,861.63
E Overhead & Profit 10% 320,386.16
F Harga Satuan Pekerjaan (D+E) 3,524,247.80

pemasangan 1 Set Ventilasi (V2) + Aksesoris


Kode AHSP = 4.2.1.T46
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 100,000.00 100,000.00

JUMLAH TENAGA KERJA 100,000.00


B BAHAN
Profil alluminium "Profil C" C599 M 2.200 35,333.33 77,733.33
Profil Allumunium List U C622 M 0.880 6,334.25 5,574.14
Kaca Warna (Dark Blue) 5 mm C569 M2 0.360 260,714.99 93,857.40
Allumunium Spigot C491 M 4.000 22,500.00 90,000.00

JUMLAH HARGA BAHAN 267,164.87


C Aksesoris
Sealant C656 M 3.014 6,000.00 18,084.00

JUMLAH HARGA ALAT 18,084.00


D Jumlah (A+B+C) 385,248.87
E Overhead & Profit 10% 38,524.89
F Harga Satuan Pekerjaan (D+E) 423,773.76

pemasangan 1 Set Pintu Shat (PS) + Aksesoris


Kode AHSP = 4.2.1.T47
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 200,000.00 200,000.00

JUMLAH TENAGA KERJA 200,000.00


B BAHAN
Profil alluminium "Profil C" C599 M 1.199 35,333.33 42,364.67
Profil alluminium "Stoper Casement" C612 M 2.200 25,571.33 56,256.93
Profil alluminium "Frame Casement" C613 M 2.200 34,173.33 75,181.33
Profil alluminium "Bead Casement" C615 M 2.200 13,020.11 28,644.24
Profil Alluminium Strip C619 M 1.980 13,683.33 27,093.00

JUMLAH HARGA BAHAN 229,540.18


C Aksesoris
Material bantu Ls 1.000 45,908.04 45,908.04

JUMLAH HARGA ALAT 45,908.04


D Jumlah (A+B+C) 475,448.21
E Overhead & Profit 10% 47,544.82
F Harga Satuan Pekerjaan (D+E) 522,993.03

Pemasangan 1 m2 Partisi Akustik


Kode AHSP = 4.2.1.T48
A TENAGA
Pekerja Plafond C13 OH 0.400 80,000.00 32,000.00
Tukang Plafond C25 OH 0.800 125,000.00 100,000.00
Mandor Plafond C42 OH 0.375 120,000.00 45,000.00
JUMLAH TENAGA KERJA 177,000.00
B BAHAN
Smartruss C 75.65 C655 M' 4.180 19,500.00 81,510.00
Dynabolt dia- 10 x 50 mm C509 Bh 6.000 3,500.00 21,000.00
Perban Gypsum C336 Roll 0.200 10,000.00 2,000.00
Tepung Gypsum C403 kg 0.150 4,000.00 600.00
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 0.728 65,000.00 47,320.00
Rock Wool C1545 M2 1.100 258,111.11 283,922.22
High Laminate Pressure (HPL) C255 M2 1.100 85,382.51 93,920.77
Profil Stainless List U C634 M' 2.250 8,834.25 19,877.06
Screw Bremick C649 Bh 6.000 120.00 720.00

JUMLAH HARGA BAHAN 550,870.05


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 727,870.05
E Overhead & Profit 10% 72,787.00
F Harga Satuan Pekerjaan (D+E) 800,657.05

Pemasangan 1 Set Sekat Rg. Genset (besi hollow)


Kode AHSP = 4.2.1.T49
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Tukang besi C20 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.250 150,000.00 37,500.00
Mandor C47 OH 0.250 120,000.00 30,000.00
JUMLAH TENAGA KERJA 170,000.00
B BAHAN
Besi Hollow 2x4 cm C170 M' 25.080 15,500.00 388,740.00
Besi Hollow 4x4 cm C171 M' 7.854 17,000.00 133,518.00
pengelasan C334 Cm 164.670 7,487.92 1,233,035.79
Cat Besi C203 M2 2.635 74,200.00 195,496.22

JUMLAH HARGA BAHAN 1,950,790.01


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2,120,790.01
E Overhead & Profit 10% 212,079.00
F Harga Satuan Pekerjaan (D+E) 2,332,869.01

Pemasangan 1 Set Pintu Besi Hollow (P1)


Kode AHSP = 4.2.1.T50
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang besi C20 OH 1.000 125,000.00 125,000.00
Kepala tukang C39 OH 0.500 150,000.00 75,000.00
Mandor C47 OH 0.500 120,000.00 60,000.00
JUMLAH TENAGA KERJA 340,000.00
B BAHAN
Besi Hollow 2x4 cm C170 M' 39.160 15,500.00 606,980.00
Besi Hollow 4x4 cm C171 M' 19.052 17,000.00 323,884.00
pengelasan C334 Cm 291.060 7,487.92 2,179,434.00
Cat Besi C203 M2 4.657 74,200.00 345,546.43
Engsel pintu besi C515 Bh 6.000 126,000.00 756,000.00
JUMLAH HARGA BAHAN 4,211,844.43
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,551,844.43
E Overhead & Profit 10% 455,184.44
F Harga Satuan Pekerjaan (D+E) 5,007,028.87

Pemasangan 1 Set Pintu Besi Hollow (P2)


Kode AHSP = 4.2.1.T51
A TENAGA
Pekerja C9 OH 0.500 80,000.00 40,000.00
Tukang besi C20 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.250 150,000.00 37,500.00
Mandor C47 OH 0.250 120,000.00 30,000.00
JUMLAH TENAGA KERJA 170,000.00
B BAHAN
Besi Hollow 2x4 cm C170 M' 19.580 15,500.00 303,490.00
Besi Hollow 4x4 cm C171 M' 10.912 17,000.00 185,504.00
pengelasan C334 Cm 152.460 7,487.92 1,141,608.28
Cat Besi C203 M2 2.439 74,200.00 181,000.51
Engsel pintu besi C515 Bh 3.000 126,000.00 378,000.00
JUMLAH HARGA BAHAN 2,189,602.80
C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 2,359,602.80
E Overhead & Profit 10% 235,960.28
F Harga Satuan Pekerjaan (D+E) 2,595,563.07

Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 1) Kaca Abu-abu
Kode AHSP = 4.2.1.T52
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 19,795,295.00 19,795,295.00

JUMLAH TENAGA KERJA 19,795,295.00


B BAHAN
Profil alluminium Curtain Wall C608 M 288.860 118,000.00 34,085,480.00
Kaca Stopsol 6 mm C557 M 96.100 465,000.00 44,686,500.00
Sealant C656 M 68.200 6,000.00 409,200.00

JUMLAH HARGA BAHAN 79,181,180.00


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 98,976,475.00
E Overhead & Profit 10% 9,897,647.50
F Harga Satuan Pekerjaan (D+E) 108,874,122.50

Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 2) Kaca Abu-Abu
Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 2) Kaca Abu-Abu
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 12,906,000.00 12,906,000.00

JUMLAH TENAGA KERJA 12,906,000.00


B BAHAN
Profil alluminium Curtain Wall C608 M 231.000 118,000.00 27,258,000.00
Kaca Stopsol 6 mm C557 M 51.520 465,000.00 23,956,800.00
Sealant C656 M 68.200 6,000.00 409,200.00

JUMLAH HARGA BAHAN 51,624,000.00


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 64,530,000.00
E Overhead & Profit 10% 6,453,000.00
F Harga Satuan Pekerjaan (D+E) 70,983,000.00

Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 3) Kaca Abu-Abu
Pemasangan 1 Set Ventilasi Balai Bahasa (V1)
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 6,443,200.00 6,443,200.00

JUMLAH TENAGA KERJA 6,443,200.00


B BAHAN
Profil alluminium Curtain Wall C608 M 121.000 118,000.00 14,278,000.00
Kaca Stopsol 6 mm C557 M 23.840 465,000.00 11,085,600.00
Sealant C656 M 68.200 6,000.00 409,200.00

JUMLAH HARGA BAHAN 25,772,800.00


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 32,216,000.00
E Overhead & Profit 10% 3,221,600.00
F Harga Satuan Pekerjaan (D+E) 35,437,600.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 Kamuflase AC Outdoor


Kode AHSP = 4.2.1.T54
A TENAGA
Perakitan, Pemasangan Perapian Dan Pengelasan Ls 1.000 771,375.00 771,375.00

JUMLAH TENAGA KERJA 771,375.00


B BAHAN
Besi Hollow 4x4 cm C171 M 181.500 17,000.00 3,085,500.00

JUMLAH HARGA BAHAN 3,085,500.00


C Aksesoris
Engsel Jendela Kupu-kupu C512 M 6.000 15,800.00 94,800.00

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,856,875.00
E Overhead & Profit 10% 385,687.50
F Harga Satuan Pekerjaan (D+E) 4,242,562.50

Pemasangan 1 Set Pintu Utama Balai Bahasa (P1)


Kode AHSP = 4.2.1.T55
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 12,179,212.50 12,179,212.50

JUMLAH TENAGA KERJA 12,179,212.50


B BAHAN
Profil alluminium "M" C605 M 27.610 41,666.67 1,150,416.67
Profil alluminium "Tutup Kaca Mati" C616 M 3.520 14,500.00 51,040.00
Profil alluminium "Tutup Polos" C617 M 7.150 14,333.33 102,483.33
Profil alluminium "Ambang Datar Atas" C609 M 2.310 28,855.83 66,656.98
Profil alluminium "Ambang Datar Bawah" C610 M 2.310 44,574.00 102,965.94
Profil alluminium "Ambang Datar Tegak" C611 M 1.980 37,770.67 74,785.92
Profil alluminium "Daun Jendela" C614 M 6.820 20,166.67 137,536.67
Sticker Sandblast C689 M2 7.150 252,500.00 1,805,375.00
Kaca Bening 8 mm C546 M2 7.150 275,000.00 1,966,250.00
Kaca Temperet 12 mm C560 M2 4.136 922,000.00 3,813,392.00
Allumunium Spigot C491 M 2.420 22,500.00 54,450.00
Sealant C656 M 75.020 6,000.00 450,120.00

JUMLAH HARGA BAHAN 9,775,472.50


C Aksesoris
Friction Stay (Engsel Casement) 12" C525 Bh 4.000 106,700.00 426,800.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Pull Handle Stainless 38x1000 C632 Bh 4.000 1,070,120.00 4,280,480.00
Patch Fitting PT20 C589 Bh 4.000 469,960.00 1,879,840.00
Patch Lock C591 Bh 2.000 877,920.00 1,755,840.00
Floor Hinge C522 Bh 2.000 608,000.00 1,216,000.00

JUMLAH HARGA ALAT 9,614,960.00


D Jumlah (A+B+C) 31,569,645.00
E Overhead & Profit 10% 3,156,964.50
F Harga Satuan Pekerjaan (D+E) 34,726,609.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 Set Pintu Balai Bahasa (P2)


Kode AHSP = 4.2.1.T56
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 985,167.04 985,167.04

JUMLAH TENAGA KERJA 985,167.04


B BAHAN
Profil alluminium "Profil C" C599 M 6.160 35,333.33 217,653.33
Profil alluminium "M" C605 M 2.640 41,666.67 110,000.00
Profil alluminium "Tutup Kaca Mati" C616 M 1.540 14,500.00 22,330.00
Profil alluminium "Ambang Datar Atas" C609 M 1.540 28,855.83 44,437.98
Profil alluminium "Ambang Datar Bawah" C610 M 3.080 44,574.00 137,287.92
Profil alluminium "Ambang Datar Tegak" C611 M 9.240 37,770.67 349,000.96
Tripleks 9 mm C413 M2 6.116 48,611.11 297,305.56
Kaca Bening 5 mm C544 M2 2.530 128,000.00 323,840.00
High Laminate Pressure (HPL) C255 M2 6.116 85,382.51 522,199.45

JUMLAH HARGA BAHAN 2,024,055.21


C Aksesoris
Engsel Pintu Kupu-kupu C513 Bh 6.000 82,550.00 495,300.00
Flush Bolt / Grandel Pintu Engsel Tanam C523 Bh 2.000 165,000.00 330,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Sealant C656 M 46.000 6,000.00 276,000.00

JUMLAH HARGA ALAT 2,901,780.00


D Jumlah (A+B+C) 5,911,002.25
E Overhead & Profit 10% 591,100.22
F Harga Satuan Pekerjaan (D+E) 6,502,102.47

Pemasangan 1 Set Pintu Ventilasi Balai Bahasa (PV1)


Kode AHSP = 4.2.1.T57
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 1,285,278.81 1,285,278.81

JUMLAH TENAGA KERJA 1,285,278.81


B BAHAN
Profil alluminium "M" C605 M 9.680 41,666.67 403,333.33
Profil alluminium "Profil C" C599 M 4.620 35,333.33 163,240.00
Profil alluminium "Tutup Kaca Mati" C616 M 1.650 14,500.00 23,925.00
Profil alluminium "Ambang Datar Atas" C609 M2 3.080 28,855.83 88,875.97
Profil alluminium "Ambang Datar Bawah" C610 M2 1.540 44,574.00 68,643.96
Profil alluminium "Ambang Datar Tegak" C611 M2 9.240 37,770.67 349,000.96
Kaca Bening 5 mm C544 M 4.422 128,000.00 566,016.00
Sealant C656 M 50.600 6,000.00 303,600.00

JUMLAH HARGA BAHAN 1,966,635.22


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Flush Bolt / Grandel Pintu Engsel Tanam C523 Bh 2.000 165,000.00 330,000.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00

JUMLAH HARGA ALAT 3,174,480.00


D Jumlah (A+B+C) 6,426,394.03
E Overhead & Profit 10% 642,639.40
F Harga Satuan Pekerjaan (D+E) 7,069,033.43

Pemasangan 1 Set Pintu Ventilasi Balai Bahasa (PV1 Baru)


Kode AHSP = 4.2.1.T58
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 1,196,814.36 1,196,814.36

JUMLAH TENAGA KERJA 1,196,814.36


B BAHAN
Profil alluminium "M" C605 M 13.420 41,666.67 559,166.67
Profil alluminium "Profil C" C599 M 9.350 35,333.33 330,366.67
Profil alluminium "Tutup Kaca Mati" C616 M 3.630 14,500.00 52,635.00
Profil alluminium "Ambang Datar Atas" C609 M2 3.960 28,855.83 114,269.10
Profil alluminium "Ambang Datar Bawah" C610 M2 1.760 44,574.00 78,450.24
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Profil alluminium "Ambang Datar Tegak" C611 M2 2.354 37,770.67 88,912.15
Kaca Bening 5 mm C544 M 8.074 128,000.00 1,033,472.00
Sealant C656 M 82.720 6,000.00 496,320.00

JUMLAH HARGA BAHAN 2,753,591.82


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Flush Bolt / Grandel Pintu Engsel Tanam C523 Bh 2.000 165,000.00 330,000.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00

JUMLAH HARGA ALAT 3,230,480.00


D Jumlah (A+B+C) 7,180,886.19
E Overhead & Profit 10% 718,088.62
F Harga Satuan Pekerjaan (D+E) 7,898,974.81
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 Set Pintu Balai Bahasa (P3)
Kode AHSP = 4.2.1.T59
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 803,977.81 803,977.81

JUMLAH TENAGA KERJA 803,977.81


B BAHAN
Profil alluminium "M" C605 M 2.310 41,666.67 96,250.00
Profil alluminium "Profil C" C599 M 5.830 35,333.33 205,993.33
Profil alluminium "Tutup Kaca Mati" C616 M 1.210 14,500.00 17,545.00
Profil alluminium "Ambang Datar Atas" C609 M2 2.420 28,855.83 69,831.12
Profil alluminium "Ambang Datar Bawah" C610 M2 1.210 44,574.00 53,934.54
Profil alluminium "Ambang Datar Tegak" C611 M2 9.240 37,770.67 349,000.96
Tripleks 9 mm C413 M2 4.906 48,611.11 238,486.11
Kaca bening 5 mm C544 M2 0.781 128,000.00 99,968.00

JUMLAH HARGA BAHAN 1,131,009.06


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 6.000 143,000.00 858,000.00
Pull Handle Stainless 32x300 C633 Bh 4.000 450,120.00 1,800,480.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00
Sealant C656 m 7.400 6,000.00 44,400.00

JUMLAH HARGA ALAT 2,888,880.00


D Jumlah (A+B+C) 4,823,866.87
E Overhead & Profit 10% 482,386.69
F Harga Satuan Pekerjaan (D+E) 5,306,253.56

Pemasangan 1 Set Pintu Balai Bahasa (P4)


Kode AHSP = 4.2.1.T60
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 453,686.23 453,686.23

JUMLAH TENAGA KERJA 453,686.23


B BAHAN
Profil alluminium "M" C605 M 2.090 41,666.67 87,083.33
Profil alluminium "Profil C" C599 M 5.500 35,333.33 194,333.33
Profil alluminium "Tutup Kaca Mati" C616 M 0.880 14,500.00 12,760.00
Profil alluminium "Ambang Datar Atas" C609 M2 1.760 28,855.83 50,786.27
Profil alluminium "Ambang Datar Bawah" C610 M2 0.880 44,574.00 39,225.12
Profil alluminium "Ambang Datar Tegak" C611 M2 4.620 37,770.67 174,500.48
Tripleks 9 mm C413 M2 3.599 48,611.11 174,961.11
High Laminate Pressure (HPL) C255 M2 7.198 85,382.51 614,617.49
Kaca bening 5 mm C544 M2 0.088 128,000.00 11,264.00

JUMLAH HARGA BAHAN 1,359,531.13


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Lever Handle Plate C580 Bh 2.000 118,750.00 237,500.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00
Sealant C656 m 9.400 6,000.00 56,400.00

JUMLAH HARGA ALAT 908,900.00


D Jumlah (A+B+C) 2,722,117.36
E Overhead & Profit 10% 272,211.74
F Harga Satuan Pekerjaan (D+E) 2,994,329.09
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 Set Pintu Balai Bahasa (PJ3) Baru
Kode AHSP = 4.2.1.T61
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 1,123,000.01 1,123,000.01

JUMLAH TENAGA KERJA 1,123,000.01


B BAHAN
Profil alluminium "M" C605 M 22.000 41,666.67 916,666.67
Profil alluminium "Profil C" C599 M 7.700 35,333.33 272,066.67
Profil alluminium "Tutup Kaca Mati" C616 M 16.390 14,500.00 237,655.00
Profil alluminium "Ambang Datar Atas" C609 M2 1.760 28,855.83 50,786.27
Profil alluminium "Ambang Datar Bawah" C610 M2 0.880 44,574.00 39,225.12
Profil alluminium "Ambang Datar Tegak" C611 M2 46.200 37,770.67 1,745,004.80
Tripleks 9 mm C413 M2 2.890 48,611.11 140,471.53
Kaca bening 5 mm C544 M2 7.183 128,000.00 919,424.00

JUMLAH HARGA BAHAN 4,321,300.05


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Lever Handle Plate C580 Bh 2.000 118,750.00 237,500.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00
Sealant C656 m 64.200 6,000.00 385,200.00
Casement Handle C495 m 2.000 28,000.00 56,000.00

JUMLAH HARGA ALAT 1,293,700.00


D Jumlah (A+B+C) 6,738,000.06
E Overhead & Profit 10% 673,800.01
F Harga Satuan Pekerjaan (D+E) 7,411,800.06

Pemasangan 1 Set Pintu Balai Bahasa (P5)


Kode AHSP = 4.2.1.T62
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 293,440.83 293,440.83

JUMLAH TENAGA KERJA 293,440.83


B BAHAN
Profil alluminium "Profil C" C599 M 5.500 35,333.33 194,333.33
Profil Alluminium Strip C619 M2 19.800 13,683.33 270,930.00

JUMLAH HARGA BAHAN 465,263.33


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 2.000 143,000.00 286,000.00
Lever Handle Plate C580 Bh 2.000 118,750.00 237,500.00
Kunci Tanam Kamar Mandi (Silinder) C576 Bh 1.000 185,000.00 185,000.00

JUMLAH HARGA ALAT 708,500.00


D Jumlah (A+B+C) 1,467,204.17
E Overhead & Profit 10% 146,720.42
F Harga Satuan Pekerjaan (D+E) 1,613,924.58
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 Set Pintu Balai Bahasa (PJ1)
Kode AHSP = 4.2.1.T63
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 791,328.69 791,328.69

JUMLAH TENAGA KERJA 791,328.69


B BAHAN
Profil alluminium "Profil C" C599 M 11.660 35,333.33 411,986.67
Profil alluminium "Tutup Polos" C617 M 2.750 14,333.33 39,416.67
Profil alluminium "Ambang Datar Atas" C609 M2 1.540 28,855.83 44,437.98
Profil alluminium "Ambang Datar Bawah" C610 M2 0.770 44,574.00 34,321.98
Profil alluminium "Ambang Datar Tegak" C611 M2 4.620 37,770.67 174,500.48
Kaca bening 5 mm C544 M2 2.792 128,000.00 357,376.00
Allumunium Spigot C491 M 4.070 22,500.00 91,575.00
Profil alluminium "Daun Jendela" C614 M 3.960 20,166.67 79,860.00
Profil Alluminium Jalusi C620 M 9.900 1.00

JUMLAH HARGA BAHAN 1,233,474.78


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Pull Handle Stainless 32x300 C633 Bh 2.000 450,120.00 900,240.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00
Friction Stay (Engsel Casement) 12" C525 Bh 2.000 106,700.00 213,400.00
Casement Handle C495 Bh 1.000 28,000.00 28,000.00
Sealant C656 m 29.200 6,000.00 175,200.00

JUMLAH HARGA ALAT 1,931,840.00


D Jumlah (A+B+C) 3,956,643.47
E Overhead & Profit 10% 395,664.35
F Harga Satuan Pekerjaan (D+E) 4,352,307.82

Pemasangan 1 Set Pintu Balai Bahasa (PJ2)


Kode AHSP = 4.2.1.T64
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,089,514.13 1,089,514.13

JUMLAH TENAGA KERJA 1,089,514.13


B BAHAN
Profil alluminium "Profil C" C599 M 5.500 35,333.33 194,333.33
Profil alluminium "M" C605 M 17.930 41,666.67 747,083.33
Profil alluminium "Tutup Kaca Mati" C616 M 9.570 14,500.00 138,765.00
Profil alluminium "Ambang Datar Atas" C609 M2 1.540 28,855.83 44,437.98
Profil alluminium "Ambang Datar Bawah" C610 M2 0.770 44,574.00 34,321.98
Profil alluminium "Ambang Datar Tegak" C611 M2 4.620 37,770.67 174,500.48
Kaca bening 5 mm C544 M2 4.917 128,000.00 629,376.00
Tripleks 9 mm C413 M2 4.642 48,611.11 225,652.78
High Laminate Pressure (HPL) C255 M2 4.642 85,382.51 396,345.63

JUMLAH HARGA BAHAN 2,584,816.52


C Aksesoris
Engsel Pintu Kupu-kupu Allumunium C514 Bh 3.000 143,000.00 429,000.00
Pull Handle Stainless 32x300 C633 Bh 2.000 450,120.00 900,240.00
Kunci Tanam Pintu Allumunium C575 Bh 1.000 186,000.00 186,000.00
Sealant C656 m 43.000 6,000.00 258,000.00

JUMLAH HARGA ALAT 1,773,240.00


D Jumlah (A+B+C) 5,447,570.65
E Overhead & Profit 10% 544,757.06
F Harga Satuan Pekerjaan (D+E) 5,992,327.71
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 Set Jendela Balai Bahasa (J1)
Kode AHSP = 4.2.1.T65
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 976,549.67 976,549.67

JUMLAH TENAGA KERJA 976,549.67


B BAHAN
Profil alluminium "M" C605 M 2.310 41,666.67 96,250.00
Profil alluminium "Profil C" C599 M 12.980 35,333.33 458,626.67
Profil alluminium "Tutup Polos" C617 M 1.540 14,333.33 22,073.33
Profil alluminium "Tutup Kaca Mati" C616 M 6.160 14,500.00 89,320.00
Profil alluminium "Daun Jendela" C614 M2 13.640 20,166.67 275,073.33
Kaca Stopsol 6 mm C557 M2 3.817 465,000.00 1,774,905.00
Allumunium Spigot C491 M 13.640 22,500.00 306,900.00

JUMLAH HARGA BAHAN 3,023,148.33


C Aksesoris
Friction Stay (Engsel Casement) 12" C525 Bh 4.000 106,700.00 426,800.00
Friction Stay (Engsel Casement) 20" C529 Bh 4.000 275,000.00 1,100,000.00
Casement Handle C495 Bh 4.000 28,000.00 112,000.00
Sealant C656 m 36.800 6,000.00 220,800.00

JUMLAH HARGA ALAT 1,859,600.00


D Jumlah (A+B+C) 5,859,298.00
E Overhead & Profit 10% 585,929.80
F Harga Satuan Pekerjaan (D+E) 6,445,227.80

Pemasangan 1 Set Jendela Balai Bahasa (J6 Baru)


Kode AHSP = 4.2.1.T66
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 967,162.00 967,162.00

JUMLAH TENAGA KERJA 967,162.00


B BAHAN
Profil alluminium "M" C605 M 22.000 41,666.67 916,666.67
Profil alluminium "Profil C" C599 M 6.160 35,333.33 217,653.33
Profil alluminium "Tutup Kaca Mati" C616 M 15.400 14,500.00 223,300.00
Profil alluminium "Daun Jendela" C614 M 5.500 20,166.67 110,916.67
Kaca Stopsol 6 mm C557 M 8.789 465,000.00 4,086,885.00
Allumunium Spigot C491 M 1.650 22,500.00 37,125.00

JUMLAH HARGA BAHAN 5,592,546.67


C Aksesoris
Friction Stay (Engsel Casement) 10" C524 Bh 4.000 82,500.00 330,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 m 78.200 6,000.00 469,200.00

JUMLAH HARGA ALAT 855,200.00


D Jumlah (A+B+C) 7,414,908.67
E Overhead & Profit 10% 741,490.87
F Harga Satuan Pekerjaan (D+E) 8,156,399.53

Pemasangan 1 Set Jendela Balai Bahasa (J2)


Kode AHSP = 4.2.1.T67
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 491,696.11 491,696.11

JUMLAH TENAGA KERJA 491,696.11


B BAHAN
Profil alluminium "Profil C" C599 M 10.230 35,333.33 361,460.00
Profil alluminium "Tutup Polos" C617 M 3.300 14,333.33 47,300.00
Profil alluminium "Daun Jendela" C614 M2 12.760 20,166.67 257,326.67
Kaca Stopsol 5 mm C556 M2 2.035 268,691.59 546,787.38
Allumunium Spigot C491 M 12.760 22,500.00 287,100.00

JUMLAH HARGA BAHAN 1,499,974.05


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C Aksesoris
Friction Stay (Engsel Casement) 12" C525 Bh 4.000 106,700.00 426,800.00
Friction Stay (Engsel Casement) 20" C529 Bh 4.000 275,000.00 1,100,000.00
Casement Handle C495 Bh 4.000 28,000.00 112,000.00
Sealant C656 m 23.200 6,000.00 139,200.00

JUMLAH HARGA ALAT 1,778,000.00


D Jumlah (A+B+C) 3,769,670.16
E Overhead & Profit 10% 376,967.02
F Harga Satuan Pekerjaan (D+E) 4,146,637.17

Pemasangan 1 Set Jendela Balai Bahasa (J3)


Kode AHSP = 4.2.1.T68
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 245,069.65 245,069.65

JUMLAH TENAGA KERJA 245,069.65


B BAHAN
Profil alluminium "M" C605 M 10.010 41,666.67 417,083.33
Profil alluminium "Profil C" C599 M 6.270 35,333.33 221,540.00
Profil alluminium "Tutup Polos" C617 M 2.640 14,333.33 37,840.00
Profil alluminium "Tutup Kaca Mati" C616 M 5.610 14,500.00 81,345.00
Profil Alluminium Jalusi C620 M2 21.120 1.00 21.12
Kaca Stopsol 5 mm C556 M2 2.684 268,691.59 721,168.22

JUMLAH HARGA BAHAN 1,478,997.68


C Aksesoris
Sealant C656 m 25.800 6,000.00 154,800.00

JUMLAH HARGA ALAT 154,800.00


D Jumlah (A+B+C) 1,878,867.33
E Overhead & Profit 10% 187,886.73
F Harga Satuan Pekerjaan (D+E) 2,066,754.06

Pemasangan 1 Set Jendela Balai Bahasa (J4)


Kode AHSP = 4.2.1.T69
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 330,180.04 330,180.04

JUMLAH TENAGA KERJA 330,180.04


B BAHAN
Profil alluminium "Profil C" C599 M 9.570 35,333.33 338,140.00
Profil alluminium "Tutup Polos" C617 M 3.080 14,333.33 44,146.67
Profil alluminium "Daun Jendela" C614 M 6.820 20,166.67 137,536.67
Kaca Stopsol 5 mm C556 M2 1.122 268,691.59 301,471.96
Allumunium Spigot C491 M 6.490 22,500.00 146,025.00

JUMLAH HARGA BAHAN 967,320.30


C Aksesoris
Friction Stay (Engsel Casement) 20" C529 Bh 4.000 275,000.00 1,100,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 m 12.980 6,000.00 77,880.00

JUMLAH HARGA ALAT 1,233,880.00


D Jumlah (A+B+C) 2,531,380.34
E Overhead & Profit 10% 253,138.03
F Harga Satuan Pekerjaan (D+E) 2,784,518.37

Pemasangan 1 Set Jendela Balai Bahasa (J5)


Kode AHSP = 4.2.1.T70
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 556,978.50 556,978.50

JUMLAH TENAGA KERJA 556,978.50


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Profil alluminium "M" C605 M 28.160 41,666.67 1,173,333.33
Profil alluminium "Tutup Polos" C617 M 8.360 14,333.33 119,826.67
Profil alluminium "Tutup Kaca Mati" C616 M 9.020 14,500.00 130,790.00
Profil alluminium "Daun Jendela" C614 M2 7.920 20,166.67 159,720.00
Kaca Bening 5 mm C544 M2 6.765 128,000.00 865,920.00

JUMLAH HARGA BAHAN 2,449,590.00


C Aksesoris
Rell Jendela Geser C643 Set 1.000 545,000.00 545,000.00
Handle Pintu Geser dekson C538 Set 2.000 126,500.00 253,000.00
Sealant C656 m 77.600 6,000.00 465,600.00

JUMLAH HARGA ALAT 1,263,600.00


D Jumlah (A+B+C) 4,270,168.50
E Overhead & Profit 10% 427,016.85
F Harga Satuan Pekerjaan (D+E) 4,697,185.35

Pemasangan 1 Set Ventilasi Balai Bahasa (V1)


Kode AHSP = 4.2.1.T71
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 169,028.10 169,028.10

JUMLAH TENAGA KERJA 169,028.10


B BAHAN
Profil alluminium "Profil C" C599 M 4.620 35,333.33 163,240.00
Profil alluminium "M" C605 M 2.750 41,666.67 114,583.33
Profil alluminium "Tutup Polos" C617 M 1.100 14,333.33 15,766.67
Profil alluminium "Daun Jendela" C614 M2 5.280 20,166.67 106,480.00
Kaca bening 5 mm C544 M2 1.078 128,000.00 137,984.00
Allumunium Spigot C491 M 5.280 22,500.00 118,800.00

JUMLAH HARGA BAHAN 656,854.00


C Aksesoris
Friction Stay (Engsel Casement) 10" C524 Bh 4.000 82,500.00 330,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 m 14.000 6,000.00 84,000.00

JUMLAH HARGA ALAT 470,000.00


D Jumlah (A+B+C) 1,295,882.10
E Overhead & Profit 10% 129,588.21
F Harga Satuan Pekerjaan (D+E) 1,425,470.31

Pemasangan 1 Set Ventilasi Balai Bahasa (V1)


Kode AHSP = 4.2.1.T71
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 400,000.00 400,000.00

JUMLAH TENAGA KERJA 400,000.00


B BAHAN
Profil alluminium "Profil C" C599 M 6.600 35,333.33 233,200.00
Profil alluminium "M" C605 M 4.070 41,666.67 169,583.33
Profil alluminium "Tutup Kaca Mati" C616 M 1.650 14,500.00 23,925.00
Profil alluminium "Daun Jendela" C614 M2 5.280 20,166.67 106,480.00
Kaca bening 5 mm C544 M2 1.496 128,000.00 191,488.00
Allumunium Spigot C491 M2 1.650 22,500.00 37,125.00

JUMLAH HARGA BAHAN 761,801.33


C Aksesoris
Friction Stay (Engsel Casement) 10" C524 Bh 4.000 82,500.00 330,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 m 19.000 6,000.00 114,000.00

JUMLAH HARGA ALAT 500,000.00


D Jumlah (A+B+C) 1,661,801.33
E Overhead & Profit 10% 166,180.13
F Harga Satuan Pekerjaan (D+E) 1,827,981.47

Pemasangan 1 Set Ventilasi Balai Bahasa (V3)


Kode AHSP = 4.2.1.T72
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 129,007.45 129,007.45

JUMLAH TENAGA KERJA 129,007.45


B BAHAN
Profil alluminium "Profil C" C599 M 5.170 35,333.33 182,673.33
Profil alluminium "Tutup Polos" C617 M 0.550 14,333.33 7,883.33
Profil alluminium "Daun Jendela" C614 M2 5.280 20,166.67 106,480.00
Kaca bening 5 mm C544 M2 0.671 128,000.00 85,888.00
Allumunium Spigot C491 M2 1.650 22,500.00 37,125.00

JUMLAH HARGA BAHAN 420,049.67


C Aksesoris
Friction Stay (Engsel Casement) 10" C524 Bh 4.000 82,500.00 330,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 m 9.000 6,000.00 54,000.00

JUMLAH HARGA ALAT 440,000.00


D Jumlah (A+B+C) 989,057.12
E Overhead & Profit 10% 98,905.71
F Harga Satuan Pekerjaan (D+E) 1,087,962.83

Pemasangan 1 Set Ventilasi Balai Bahasa (V4)


Kode AHSP = 4.2.1.T73
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 52,495.86 52,495.86

JUMLAH TENAGA KERJA 52,495.86


B BAHAN
Profil alluminium "Profil C" C599 M 3.740 35,333.33 132,146.67
Kaca Stopsol 5 mm C556 M2 0.737 268,691.59 198,025.70

JUMLAH HARGA BAHAN 330,172.37


C Aksesoris
Sealant C656 m 3.300 6,000.00 19,800.00

JUMLAH HARGA ALAT 19,800.00


D Jumlah (A+B+C) 402,468.22
E Overhead & Profit 10% 40,246.82
F Harga Satuan Pekerjaan (D+E) 442,715.05

Pemasangan 1 Set Ventilasi Balai Bahasa (V2)


Kode AHSP = 4.2.1.T80
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 189,270.20 189,270.20

JUMLAH TENAGA KERJA 189,270.20


B BAHAN
Profil alluminium "Profil C" C599 M 6.600 35,333.33 233,200.00
Profil alluminium "M" C605 M 4.070 41,666.67 169,583.33
Profil alluminium "Tutup Kaca Mati" C616 M 1.650 14,500.00 23,925.00
Profil alluminium "Daun Jendela" C614 M2 5.280 20,166.67 106,480.00
Kaca bening 5 mm C544 M2 1.496 128,000.00 191,488.00
Allumunium Spigot C491 M2 1.650 22,500.00 37,125.00

JUMLAH HARGA BAHAN 761,801.33


C Aksesoris
Friction Stay (Engsel Casement) 10" C524 Bh 4.000 82,500.00 330,000.00
Casement Handle C495 Bh 2.000 28,000.00 56,000.00
Sealant C656 m 19.000 6,000.00 114,000.00

JUMLAH HARGA ALAT 500,000.00


D Jumlah (A+B+C) 1,451,071.53
E Overhead & Profit 10% 145,107.15
F Harga Satuan Pekerjaan (D+E) 1,596,178.69

Pemasangan 1 Set Railling Difabel


Kode AHSP = 4.2.1.T81
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 562,595.00 562,595.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH TENAGA KERJA 562,595.00


B BAHAN
Stainless Steel Dia. 50mm C664 M 84.920 44,166.67 3,750,633.33

JUMLAH HARGA BAHAN 3,750,633.33


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,313,228.33
E Overhead & Profit 10% 431,322.83
F Harga Satuan Pekerjaan (D+E) 4,744,551.17

Pemasangan 1 Set Railling Tangga


Kode AHSP = 4.2.1.T82
A TENAGA
Pengiriman Barang, Pengerjaan Dan Pemasangan Ls 1.000 2,481,641.67 2,481,641.67

JUMLAH TENAGA KERJA 2,481,641.67


B BAHAN
Tiang Railing Exclusive Motif Kayu C671 bh 14.000 469,000.00 6,566,000.00
Handling UPVC C540 M 11.140 125,000.00 1,392,500.00
Stainless Steel Dia. 50mm C664 M 44.560 44,166.67 1,968,066.67

JUMLAH HARGA BAHAN 9,926,566.67


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 12,408,208.33
E Overhead & Profit 10% 1,240,820.83
F Harga Satuan Pekerjaan (D+E) 13,649,029.17

Pemasangan 1 Set Wall Panel Area Lobby Balai Bahasa


Kode AHSP = 4.2.1.T74
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,622,077.57 1,622,077.57

JUMLAH TENAGA KERJA 1,622,077.57


B BAHAN
Tripleks 18 mm C414 M2 36.651 86,805.56 3,181,501.74
High Laminate Pressure (HPL) C255 M2 31.812 85,382.51 2,716,188.52
Lem Kayu C292 Kg 5.000 32,500.00 162,500.00
Paku skrup C323 Kg 2.000 114,700.00 229,400.00
Dempul C218 Kg 2.000 39,900.00 79,800.00
Amplas C124 Lbr 10.000 6,900.00 69,000.00

JUMLAH HARGA BAHAN 6,438,390.26


C Aksesoris
Kaca Bening 5 mm C544 m 0.390 128,000.00 49,920.00
Logo dan Tulisan Material Acrylic Interior Balai Bahasa M2 0.260 1,772,916.67 460,958.33
Material Bantu Ls 1.000 324,415.51 324,415.51
JUMLAH HARGA ALAT 835,293.85
D Jumlah (A+B+C) 8,895,761.67
E Overhead & Profit 10% 889,576.17
F Harga Satuan Pekerjaan (D+E) 9,785,337.84
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 Set Meja Area Lobby Balai Bahasa
Kode AHSP = 4.2.1.T75
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 785,476.43 785,476.43

JUMLAH TENAGA KERJA 785,476.43


B BAHAN
Tripleks 18 mm C414 M2 13.508 86,805.56 1,172,569.44
High Laminate Pressure (HPL) C255 M2 18.579 85,382.51 1,586,321.72
Lem Kayu C292 Kg 2.000 32,500.00 65,000.00
Paku skrup C323 Kg 1.000 114,700.00 114,700.00
Dempul C218 Kg 1.000 39,900.00 39,900.00
Amplas C124 Lbr 2.000 6,900.00 13,800.00

JUMLAH HARGA BAHAN 2,992,291.17


C Aksesoris
Material bantu Ls 1.000 149,614.56 149,614.56

JUMLAH HARGA ALAT 149,614.56


D Jumlah (A+B+C) 3,927,382.16
E Overhead & Profit 10% 392,738.22
F Harga Satuan Pekerjaan (D+E) 4,320,120.37

Pemasangan 1 Set Wall Panel Area ULT Balai Bahasa


Kode AHSP = 4.2.1.T76
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 2,856,305.81 2,856,305.81

JUMLAH TENAGA KERJA 2,856,305.81


B BAHAN
Tripleks 18 mm C414 M2 35.706 86,805.56 3,099,479.17
High Laminate Pressure (HPL) C255 M2 63.580 85,382.51 5,428,620.22
Lem Kayu C292 Kg 10.000 32,500.00 325,000.00
Paku skrup C323 Kg 5.000 114,700.00 573,500.00
Dempul C218 Kg 5.000 39,900.00 199,500.00
Amplas C124 Lbr 20.000 6,900.00 138,000.00

JUMLAH HARGA BAHAN 9,764,099.39


C Aksesoris
Engsel Sendok C517 m 10.000 57,875.00 578,750.00
Kunci Tanam Pintu Lemari C579 m 9.000 33,000.00 297,000.00
Logo dan Tulisan Material Acrylic Interior Balai Bahasa M2 0.260 1,772,916.67 460,958.33
Material Bantu Ls 1.000 324,415.51 324,415.51
JUMLAH HARGA ALAT 1,661,123.85
D Jumlah (A+B+C) 14,281,529.04
E Overhead & Profit 10% 1,428,152.90
F Harga Satuan Pekerjaan (D+E) 15,709,681.94

Pemasangan 1 Set Meja Area ULT Balai Bahasa


Kode AHSP = 4.2.1.T77
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 813,114.28 813,114.28

JUMLAH TENAGA KERJA 813,114.28


B BAHAN
Tripleks 18 mm C414 M2 13.805 86,805.56 1,198,350.69
High Laminate Pressure (HPL) C255 M2 16.760 85,382.51 1,431,010.93
Lem Kayu C292 Kg 2.000 32,500.00 65,000.00
Paku skrup C323 Kg 1.000 114,700.00 114,700.00
Dempul C218 Kg 1.000 39,900.00 39,900.00
Amplas C124 Lbr 2.000 6,900.00 13,800.00

JUMLAH HARGA BAHAN 2,862,761.62


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C Aksesoris
Kaca Bening 5 mm C544 Lbr 0.510 128,000.00 65,280.00
Material Bantu Ls 1.000 324,415.51 324,415.51
JUMLAH HARGA ALAT 389,695.51
D Jumlah (A+B+C) 4,065,571.42
E Overhead & Profit 10% 406,557.14
F Harga Satuan Pekerjaan (D+E) 4,472,128.56

Pemasangan 1 Set Wall Panel A Area Ruang Kepala Balai Bahasa


Kode AHSP = 4.2.1.T78
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 2,992,199.03 2,992,199.03

JUMLAH TENAGA KERJA 2,992,199.03


B BAHAN
Tripleks 18 mm C414 M2 46.376 86,805.56 4,025,694.44
High Laminate Pressure (HPL) C255 M2 62.942 85,382.51 5,374,146.17
Lem Kayu C292 Kg 10.000 32,500.00 325,000.00
Paku skrup C323 Kg 5.000 114,700.00 573,500.00
Dempul C218 Kg 5.000 39,900.00 199,500.00
Amplas C124 Lbr 20.000 6,900.00 138,000.00

JUMLAH HARGA BAHAN 10,635,840.62


C Aksesoris
Engsel Sendok C517 m 12.000 57,875.00 694,500.00
Kunci Tanam Pintu Lemari C579 m 3.000 33,000.00 99,000.00
Kaca Bening 5 mm C544 m 1.680 128,000.00 215,040.00
Material Bantu Ls 1.000 324,415.51 324,415.51
JUMLAH HARGA ALAT 1,332,955.51
D Jumlah (A+B+C) 14,960,995.17
E Overhead & Profit 10% 1,496,099.52
F Harga Satuan Pekerjaan (D+E) 16,457,094.68

Pemasangan 1 Set Wall Panel B Area Ruang Kepala Balai Bahasa


Kode AHSP = 4.2.1.T79
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 814,231.21 814,231.21

JUMLAH TENAGA KERJA 814,231.21


B BAHAN
Tripleks 18 mm C414 M2 11.286 86,805.56 979,687.50
High Laminate Pressure (HPL) C255 M2 14.135 85,382.51 1,206,881.83
Lem Kayu C292 Kg 2.000 32,500.00 65,000.00
Paku skrup C323 Kg 1.000 114,700.00 114,700.00
Dempul C218 Kg 1.000 39,900.00 39,900.00
Amplas C124 Lbr 2.000 6,900.00 13,800.00

JUMLAH HARGA BAHAN 2,419,969.33


C Aksesoris
Engsel Sendok C517 m 4.000 57,875.00 231,500.00
Kunci Tanam Pintu Lemari C579 m 2.000 33,000.00 66,000.00
Kaca Bening 5 mm C544 m 1.680 128,000.00 215,040.00
Material Bantu Ls 1.000 324,415.51 324,415.51
JUMLAH HARGA ALAT 836,955.51
D Jumlah (A+B+C) 4,071,156.05
E Overhead & Profit 10% 407,115.61
F Harga Satuan Pekerjaan (D+E) 4,478,271.66

Pemasangan 1 Set Wall Panel B Area Ruang Aula


Kode AHSP = 4.2.1.T80
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 394,428.95 394,428.95

JUMLAH TENAGA KERJA 394,428.95


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Tripleks 18 mm C414 M2 3.916 86,805.56 339,930.56
High Laminate Pressure (HPL) C255 M2 12.144 85,382.51 1,036,885.25
Lem Kayu C292 Kg 1.000 32,500.00 32,500.00
Paku skrup C323 Kg 1.000 114,700.00 114,700.00
Dempul C218 Kg 1.000 39,900.00 39,900.00
Amplas C124 Lbr 2.000 6,900.00 13,800.00

JUMLAH HARGA BAHAN 1,577,715.80


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,972,144.75
E Overhead & Profit 10% 197,214.48
F Harga Satuan Pekerjaan (D+E) 2,169,359.23

Pemasangan 1 Set Panggung Area Ruang Aula


Kode AHSP = 4.2.1.T81
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 3,745,793.54 3,745,793.54

JUMLAH TENAGA KERJA 3,745,793.54


B BAHAN
Tripleks 18 mm C414 M2 37.704 86,805.56 3,272,916.67
High Laminate Pressure (HPL) C255 M2 4.059 85,382.51 346,567.62
Karpet Bali C458 M 12.320 700,000.00 8,624,000.00
Underlayer C416 M 27.760 83,544.30 2,319,189.87
Lem Kayu C292 Kg 3.000 32,500.00 97,500.00
Paku skrup C323 Kg 2.000 114,700.00 229,400.00
Dempul C218 Kg 2.000 39,900.00 79,800.00
Amplas C124 Lbr 2.000 6,900.00 13,800.00

JUMLAH HARGA BAHAN 14,983,174.16


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 18,728,967.70
E Overhead & Profit 10% 1,872,896.77
F Harga Satuan Pekerjaan (D+E) 20,601,864.47

Pemasangan 1 Set Wall Panel B Area Ruang Mushollah


Kode AHSP = 4.2.1.T82
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,807,058.03 1,807,058.03

JUMLAH TENAGA KERJA 1,807,058.03


B BAHAN
Tripleks 18 mm C414 M2 14.069 86,805.56 1,221,267.36
High Laminate Pressure (HPL) C255 M2 11.429 85,382.51 975,836.75
List profil Gypsum C294 M2 15.840 20,000.00 316,800.00
Kaca Bening 5 mm C544 M2 0.176 128,000.00 22,528.00
Ornamen GRC M2 4.422 900,000.00 3,979,800.00
Lem Kayu C292 Kg 7.000 32,500.00 227,500.00
Paku skrup C323 Kg 3.000 114,700.00 344,100.00
Dempul C218 Kg 3.000 39,900.00 119,700.00
Amplas C124 Lbr 3.000 6,900.00 20,700.00

JUMLAH HARGA BAHAN 7,228,232.11


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 9,035,290.14
E Overhead & Profit 10% 903,529.01
F Harga Satuan Pekerjaan (D+E) 9,938,819.15
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 Set Wall Panel Area Ruang Kasubag
Kode AHSP = 4.2.1.T83
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 655,354.58 655,354.58

JUMLAH TENAGA KERJA 655,354.58


B BAHAN
Tripleks 18 mm C414 M2 10.505 86,805.56 911,892.36
High Laminate Pressure (HPL) C255 M2 15.466 85,382.51 1,320,525.96
Lem Kayu C292 Kg 7.000 32,500.00 227,500.00
Paku skrup C323 Kg 1.000 114,700.00 114,700.00
Dempul C218 Kg 1.000 39,900.00 39,900.00
Amplas C124 Lbr 1.000 6,900.00 6,900.00

JUMLAH HARGA BAHAN 2,621,418.32


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,276,772.90
E Overhead & Profit 10% 327,677.29
F Harga Satuan Pekerjaan (D+E) 3,604,450.19

Pemasangan 1 Set Kolom Ruang Lab Komputer


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 635,661.32 635,661.32

JUMLAH TENAGA KERJA 635,661.32


B BAHAN
Tripleks 18 mm C414 M2 13.640 86,805.56 1,184,027.78
High Laminate Pressure (HPL) C255 M2 13.640 85,382.51 1,164,617.49
Lem Kayu C292 Kg 1.000 32,500.00 32,500.00
Paku skrup C323 Kg 1.000 114,700.00 114,700.00
Dempul C218 Kg 1.000 39,900.00 39,900.00
Amplas C124 Lbr 1.000 6,900.00 6,900.00

JUMLAH HARGA BAHAN 2,542,645.26


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,178,306.58
E Overhead & Profit 10% 317,830.66
F Harga Satuan Pekerjaan (D+E) 3,496,137.24

Pemasangan 1 Set Pintu P1 Rutan Teroris


Kode AHSP = 4.2.1.T83
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,512,730.13 1,512,730.13

JUMLAH TENAGA KERJA 1,512,730.13


B BAHAN
Besi Baja UNP C158 Kg 63.941 28,000.00 1,790,342.40
Besi Beton (Polos/ulir) C161 Kg 24.593 12,000.00 295,111.75
Besi Plat C183 Kg 50.461 28,000.00 1,412,894.56
Kawat Ornamesh C264 Kg 8.672 26,966.80 233,866.88
Pengelasan C334 m 0.400 15,000.00 6,000.00
Amplas C124 Lbr 30.000 6,900.00 207,000.00
Cat Besi C203 Kg 3.945 74,200.00 292,719.00
Thinner C405 Kg 0.132 51,300.00 6,745.95

JUMLAH HARGA BAHAN 4,244,680.54


C Aksesoris
Engsel Pintu Besi C515 bh 6.000 126,000.00 756,000.00
Grandel Pintu Besi C534 bh 1.000 150,000.00 150,000.00
Pull Handle Stainless 32x300 C633 psg 2.000 450,120.00 900,240.00

JUMLAH HARGA ALAT 1,806,240.00


D Jumlah (A+B+C) 7,563,650.67
E Overhead & Profit 10% 756,365.07
F Harga Satuan Pekerjaan (D+E) 8,320,015.74
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 Set Pintu P2 Rutan Teroris


Kode AHSP = 4.2.1.T83
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,093,153.25 1,093,153.25

JUMLAH TENAGA KERJA 1,093,153.25


B BAHAN
Besi Baja UNP C158 Kg 51.762 28,000.00 1,449,324.80
Besi Plat C183 Kg 53.917 28,000.00 1,509,668.16
Besi Kotak 4x4 cm tebal 3mm C174 m 7.590 33,333.33 253,000.00
Kaca Mika/Acrylic 5mm C564 m 0.440 520,833.33 229,166.67
Pengelasan C334 m 0.800 15,000.00 12,000.00
Amplas C124 Lbr 15.000 6,900.00 103,500.00
Cat Besi C203 Kg 2.229 74,200.00 165,391.80
Thinner C405 Kg 0.074 51,300.00 3,811.59

JUMLAH HARGA BAHAN 3,725,863.02


C Aksesoris
Engsel Pintu Besi C515 bh 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 bh 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 5,465,766.27
E Overhead & Profit 10% 546,576.63
F Harga Satuan Pekerjaan (D+E) 6,012,342.90

Pemasangan 1 Set Pintu P3 Rutan Teroris


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,008,845.65 1,008,845.65

JUMLAH TENAGA KERJA 1,008,845.65


B BAHAN
Besi Baja UNP C158 Kg 98.956 28,000.00 2,770,768.00
Besi Beton (Polos/ulir) C161 Kg 76.225 12,000.00 914,699.62
Besi Plat C183 Kg 7.776 28,000.00 217,740.60
Besi Siku 5x5 C179 m 7.271 38,250.00 278,115.75
Pengelasan C334 m 2.690 15,000.00 40,350.00
Amplas C124 Lbr 15.000 6,900.00 103,500.00
Cat Besi C203 Kg 0.953 74,200.00 70,675.50
Thinner C405 Kg 0.032 51,300.00 1,628.78

JUMLAH HARGA BAHAN 4,397,478.24


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 6,053,073.89
E Overhead & Profit 10% 605,307.39
F Harga Satuan Pekerjaan (D+E) 6,658,381.28

Pemasangan 1 Set Pintu P4 Rutan Teroris


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,533,686.61 1,533,686.61

JUMLAH TENAGA KERJA 1,533,686.61


B BAHAN
Besi Baja UNP C158 Kg 42.247 28,000.00 1,182,904.80
Besi Beton (Polos/ulir) C161 Kg 79.577 12,000.00 954,928.78
Besi Plat C183 Kg 50.115 28,000.00 1,403,217.20
Besi Kotak 4x4 cm tebal 3mm C174 m 13.057 33,333.33 435,233.33
Besi Siku 5x5 C179 m 11.253 38,250.00 430,427.25
Pengelasan C334 m 5.500 15,000.00 82,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 3.771 74,200.00 279,836.03
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Thinner C405 Kg 0.126 51,300.00 6,449.05

JUMLAH HARGA BAHAN 4,809,996.44


C Aksesoris
Engsel Pintu Besi C515 Kg 6.000 126,000.00 756,000.00
Grandel Pintu Besi C534 Kg 3.000 150,000.00 450,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 1,324,750.00


D Jumlah (A+B+C) 7,668,433.05
E Overhead & Profit 10% 766,843.31
F Harga Satuan Pekerjaan (D+E) 8,435,276.36

Pemasangan 1 Set Pintu P5 Rutan Teroris


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,303,881.31 1,303,881.31

JUMLAH TENAGA KERJA 1,303,881.31


B BAHAN
Besi Baja UNP C158 Kg 107.405 28,000.00 3,007,348.96
Besi Beton (Polos/ulir) C161 Kg 177.532 12,000.00 2,130,383.86
Besi Plat C183 Kg 13.998 28,000.00 391,933.08
Besi Siku 5x5 C179 m 4.598 38,250.00 175,873.50
Pengelasan C334 m 2.500 15,000.00 37,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 1.253 74,200.00 92,974.46
Thinner C405 Kg 0.042 51,300.00 2,142.67

JUMLAH HARGA BAHAN 5,872,656.53


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 7,823,287.83
E Overhead & Profit 10% 782,328.78
F Harga Satuan Pekerjaan (D+E) 8,605,616.62

Pemasangan 1 Set Pintu P6 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 253,617.50 253,617.50

JUMLAH TENAGA KERJA 253,617.50


B BAHAN
Profil alluminium "Profil C" C599 Kg 5.588 35,333.33 197,442.67
Profil alluminium "Ambang Datar Atas" C609 Kg 1.078 28,855.83 31,106.59
Profil alluminium "Ambang Datar Bawah" C610 Kg 1.078 44,574.00 48,050.77
Profil alluminium "Ambang Datar Tegak" C611 m 2.200 37,770.67 83,095.47
Profil Alluminium Strip C619 m 26.070 13,683.33 356,724.50

JUMLAH HARGA BAHAN 716,419.99


C Aksesoris
Engsel Pintu Kupu-kupu C513 Kg 3.000 82,550.00 247,650.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Kg 1.000 35,400.00 35,400.00
Handle Pintu Aluminium C536 Kg 1.000 15,000.00 15,000.00

JUMLAH HARGA ALAT 298,050.00


D Jumlah (A+B+C) 1,268,087.49
E Overhead & Profit 10% 126,808.75
F Harga Satuan Pekerjaan (D+E) 1,394,896.24

Pemasangan 1 Set Pintu P7 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pengerjaan Dan Pemasangan Ls 1.000 217,775.67 217,775.67

JUMLAH TENAGA KERJA 217,775.67


B BAHAN
Profil alluminium "Profil C" C599 Kg 5.291 35,333.33 186,948.67
Profil alluminium "Ambang Datar Atas" C609 Kg 0.627 28,855.83 18,092.61
Profil alluminium "Ambang Datar Bawah" C610 Kg 0.627 44,574.00 27,947.90
Profil alluminium "Ambang Datar Tegak" C611 m 2.189 37,770.67 82,679.99
Profil Alluminium Strip C619 m 18.810 13,683.33 257,383.50

JUMLAH HARGA BAHAN 573,052.66


C Aksesoris
Engsel Pintu Kupu-kupu C513 Kg 3.000 82,550.00 247,650.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Kg 1.000 35,400.00 35,400.00
Handle Pintu Aluminium C536 Kg 1.000 15,000.00 15,000.00

JUMLAH HARGA ALAT 298,050.00


D Jumlah (A+B+C) 1,088,878.33
E Overhead & Profit 10% 108,887.83
F Harga Satuan Pekerjaan (D+E) 1,197,766.16

Pemasangan 1 Set Pintu P8 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,424,307.71 1,424,307.71

JUMLAH TENAGA KERJA 1,424,307.71


B BAHAN
Besi Baja UNP C158 Kg 51.762 28,000.00 1,449,324.80
Besi Plat C183 Kg 107.833 28,000.00 3,019,336.32
Besi Kotak 4x4 cm tebal 3mm C174 m 7.590 33,333.33 253,000.00
Besi Beton (Polos/ulir) C161 Kg 9.176 12,000.00 110,116.33
Pengelasan C334 m 1.000 15,000.00 15,000.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 2.229 74,200.00 165,391.80
Thinner C405 Kg 0.074 51,300.00 3,811.59

JUMLAH HARGA BAHAN 5,050,480.84


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 7,121,538.55
E Overhead & Profit 10% 712,153.85
F Harga Satuan Pekerjaan (D+E) 7,833,692.40

Pemasangan 1 Set Pintu P9 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 673,447.50 673,447.50

JUMLAH TENAGA KERJA 673,447.50


B BAHAN
Besi Baja UNP C158 Kg 37.299 28,000.00 1,044,366.40
Besi Plat C183 Kg 27.650 28,000.00 774,188.80
Besi Kotak 4x4 cm tebal 3mm C174 m 6.160 33,333.33 205,333.33
Pengelasan C334 m 1.000 15,000.00 15,000.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 1.217 74,200.00 90,319.95
Thinner C405 Kg 0.041 51,300.00 2,081.50

JUMLAH HARGA BAHAN 2,165,789.98


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT 528,000.00
D Jumlah (A+B+C) 3,367,237.48
E Overhead & Profit 10% 336,723.75
F Harga Satuan Pekerjaan (D+E) 3,703,961.22

Pemasangan 1 Set Jendela J1 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 596,076.80 596,076.80

JUMLAH TENAGA KERJA 596,076.80


B BAHAN
Besi Baja UNP C158 Kg 49.935 28,000.00 1,398,172.16
Besi Beton (Polos/ulir) C161 Kg 41.135 12,000.00 493,614.79
Kawat Ornamesh C264 Kg 12.366 26,966.80 333,476.84
Pengelasan C334 m 6.560 15,000.00 98,400.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.344 74,200.00 25,554.48
Thinner C405 Kg 0.011 51,300.00 588.92

JUMLAH HARGA BAHAN 2,384,307.19


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2,980,383.99
E Overhead & Profit 10% 298,038.40
F Harga Satuan Pekerjaan (D+E) 3,278,422.39

Pemasangan 1 Set Jendela J2 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,155,226.06 1,155,226.06

JUMLAH TENAGA KERJA 1,155,226.06


B BAHAN
Besi Baja UNP C158 Kg 99.717 28,000.00 2,792,081.60
Besi Beton (Polos/ulir) C161 Kg 85.157 12,000.00 1,021,879.51
Kawat Ornamesh C264 Kg 24.893 26,966.80 671,284.55
Pengelasan C334 m 3.290 15,000.00 49,350.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.683 74,200.00 50,641.50
Thinner C405 Kg 0.023 51,300.00 1,167.08

JUMLAH HARGA BAHAN 4,620,904.23


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,776,130.29
E Overhead & Profit 10% 577,613.03
F Harga Satuan Pekerjaan (D+E) 6,353,743.32

Pemasangan 1 Set Ventilasi V1 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 269,502.70 269,502.70

JUMLAH TENAGA KERJA 269,502.70


B BAHAN
Besi Baja UNP C158 Kg 25.043 28,000.00 701,217.44
Besi Beton (Polos/ulir) C161 Kg 13.214 12,000.00 158,567.51
Kawat Ornamesh C264 Kg 4.497 26,966.80 121,264.31
Pengelasan C334 m 3.290 15,000.00 49,350.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.173 74,200.00 12,816.20
Thinner C405 Kg 0.006 51,300.00 295.36

JUMLAH HARGA BAHAN 1,078,010.81


C Aksesoris

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 1,347,513.51
E Overhead & Profit 10% 134,751.35
F Harga Satuan Pekerjaan (D+E) 1,482,264.86

Pemasangan 1 Set Ventilasi V2 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 269,559.90 269,559.90

JUMLAH TENAGA KERJA 269,559.90


B BAHAN
Besi Baja UNP C158 Kg 24.663 28,000.00 690,560.64
Kaca Mika/Acrylic 5mm C564 m 0.560 520,833.33 291,666.67
Pengelasan C334 m 3.240 15,000.00 48,600.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.170 74,200.00 12,621.42
Thinner C405 Kg 0.006 51,300.00 290.87

JUMLAH HARGA BAHAN 1,078,239.60


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,347,799.50
E Overhead & Profit 10% 134,779.95
F Harga Satuan Pekerjaan (D+E) 1,482,579.45

Pemasangan 1 Set Ventilasi V3 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 164,622.52 164,622.52

JUMLAH TENAGA KERJA 164,622.52


B BAHAN
Besi Baja UNP C158 Kg 19.030 28,000.00 532,840.00
Besi Beton (Polos/ulir) C161 Kg 3.303 12,000.00 39,641.88
Kawat Ornamesh C264 Kg 0.150 26,966.80 4,045.02
Pengelasan C334 m 2.500 15,000.00 37,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.131 74,200.00 9,738.75
Thinner C405 Kg 0.004 51,300.00 224.44

JUMLAH HARGA BAHAN 658,490.08


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 823,112.61
E Overhead & Profit 10% 82,311.26
F Harga Satuan Pekerjaan (D+E) 905,423.87

Pemasangan 1 Set Ventilasi V4 Rutan Teroris


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 430,845.23 430,845.23

JUMLAH TENAGA KERJA 430,845.23


B BAHAN
Besi Baja UNP C158 Kg 61.657 28,000.00 1,726,401.60
Besi Beton (Polos/ulir) C161 Kg 18.108 12,000.00 217,296.22
Kawat Ornamesh C264 Kg 0.825 26,966.80 22,247.61
Pengelasan C334 m 8.100 15,000.00 121,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.425 74,200.00 31,553.55
Thinner C405 Kg 0.014 51,300.00 727.18

JUMLAH HARGA BAHAN 2,154,226.15


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2,585,071.39
E Overhead & Profit 10% 258,507.14
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 2,843,578.52

Pemasangan 1 Set Ventilasi V5 Rutan Teroris


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 247,659.36 247,659.36

JUMLAH TENAGA KERJA 247,659.36


B BAHAN
Besi Baja UNP C158 Kg 28.164 28,000.00 788,603.20
Besi Beton (Polos/ulir) C161 Kg 7.341 12,000.00 88,093.06
Kawat Ornamesh C264 Kg 0.341 26,966.80 9,195.68
Pengelasan C334 m 3.700 15,000.00 55,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.194 74,200.00 14,413.35
Thinner C405 Kg 0.006 51,300.00 332.17

JUMLAH HARGA BAHAN 990,637.46


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,238,296.82
E Overhead & Profit 10% 123,829.68
F Harga Satuan Pekerjaan (D+E) 1,362,126.50

Pemasangan 1 Set Trali Rutan Teroris


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,024,211.11 1,024,211.11

JUMLAH TENAGA KERJA 1,024,211.11


B BAHAN
Besi Beton (Polos/ulir) C161 Kg 255.131 12,000.00 3,061,571.44
Pengelasan C334 m 67.500 15,000.00 1,012,500.00
Cat Besi C203 Kg 0.300 74,200.00 22,260.00
Thinner C405 Kg 0.010 51,300.00 513.00

JUMLAH HARGA BAHAN 4,096,844.44


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,121,055.55
E Overhead & Profit 10% 512,105.56
F Harga Satuan Pekerjaan (D+E) 5,633,161.11

Pemasangan 1 Set Penutup Atap Acrylic


Kode AHSP = 4.2.1.T88
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 9,429,862.75 9,429,862.75

JUMLAH TENAGA KERJA 9,429,862.75


B BAHAN
Besi Kotak 4x4 cm tebal 3mm C174 m 114.906 33,333.33 3,830,200.00
Kaca Mika/Acrylic 5mm C564 m 74.943 520,833.33 39,032,812.50

JUMLAH HARGA BAHAN 42,863,012.50


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 52,292,875.25
E Overhead & Profit 10% 5,229,287.53
F Harga Satuan Pekerjaan (D+E) 57,522,162.78

Pemasangan 1 Set Partisi Ruang Pembesuk


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,608,611.54 1,608,611.54

JUMLAH TENAGA KERJA 1,608,611.54


B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tripleks 18 mm C414 m2 8.270 86,805.56 717,881.94
Kaca Mika/Acrylic 12mm C570 m2 3.720 1,145,833.33 4,262,500.00
High Laminate Pressure (HPL) C255 m2 17.030 85,382.51 1,454,064.21

JUMLAH HARGA BAHAN 6,434,446.15


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,043,057.69
E Overhead & Profit 10% 804,305.77
F Harga Satuan Pekerjaan (D+E) 8,847,363.46

Pemasangan 1 Finishing Meja Jaga


Kode AHSP = 4.2.1.T88
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 150,158.24 150,158.24

JUMLAH TENAGA KERJA 150,158.24


B BAHAN
Tripleks 9 mm C413 m2 4.240 48,611.11 206,111.11
High Laminate Pressure (HPL) C255 m2 4.240 85,382.51 362,021.86
Lem Kayu C292 Kg 1.000 32,500.00 32,500.00

JUMLAH HARGA BAHAN 600,632.97


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 750,791.21
E Overhead & Profit 10% 75,079.12
F Harga Satuan Pekerjaan (D+E) 825,870.33

Pemasangan 1 Set Penutup Manhole


Kode AHSP = 4.2.1.T81
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 39,905.36 39,905.36

JUMLAH TENAGA KERJA 39,905.36


B BAHAN
Besi Siku 4x4 C180 m 1.600 20,250.00 32,400.00
Besi Plat 3 mm C185 m 0.230 541,666.67 124,583.33
Pengecatan m2 0.230 11,470.00 2,638.10

JUMLAH HARGA BAHAN 159,621.43


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 199,526.79
E Overhead & Profit 10% 19,952.68
F Harga Satuan Pekerjaan (D+E) 219,479.47

Pemasangan 1m dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :2PP
Kode AHSP = 4.4.1.1
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 43.5 1,300.00 56,550.00
Pasir Pasang C99 m3 0.08 100,000.00 8,000.00
JUMLAH HARGA BAHAN 204,550.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 284,150.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 28,415.00
F Harga Satuan Pekerjaan (D+E) 312,565.00

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP
Kode AHSP = 4.4.1.2
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 32.95 1,300.00 42,835.00
Pasir Pasang C99 m3 0.091 100,000.00 9,100.00
JUMLAH HARGA BAHAN 191,935.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 271,535.00
E Overhead & Profit 10% 27,153.50
F Harga Satuan Pekerjaan (D+E) 298,688.50

Pemasangan 1m dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :4PP
Kode AHSP = 4.4.1.3
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 26.55 1,300.00 34,515.00
Pasir Pasang C99 m3 0.093 100,000.00 9,300.00
JUMLAH HARGA BAHAN 183,815.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 263,415.00
E Overhead & Profit 10% 26,341.50
F Harga Satuan Pekerjaan (D+E) 289,756.50

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP
Kode AHSP = 4.4.1.4
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 Kg 140.000 1,000.00 140,000.00
Semen Portland C363 Kg 22.200 1,300.00 28,860.00
Pasir Pasang C99 Kg 0.102 100,000.00 10,200.00
JUMLAH HARGA BAHAN 179,060.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 258,660.00
E Overhead & Profit 10% 25,866.00
F Harga Satuan Pekerjaan (D+E) 284,526.00

Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1SP :6PP
Kode AHSP = 4.4.1.5
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 18.5 1,300.00 24,050.00
Pasir Pasang C99 m3 0.122 100,000.00 12,200.00
JUMLAH HARGA BAHAN 176,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 255,850.00
E Overhead & Profit 10% 25,585.00
F Harga Satuan Pekerjaan (D+E) 281,435.00

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :3KP : 10PP
Kode AHSP = 4.4.1.6
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 10.08 1,300.00 13,104.00
Kapur Padam C262 m3 0.0275 200,000.00 5,500.00
Pasir Pasang C99 m3 0.0925 100,000.00 9,250.00
JUMLAH HARGA BAHAN 167,854.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 247,454.00
E Overhead & Profit 10% 24,745.40
F Harga Satuan Pekerjaan (D+E) 272,199.40

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :2PP
Kode AHSP = 4.4.1.7
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 18.95 1,300.00 24,635.00
Pasir Pasang C99 m3 0.038 100,000.00 3,800.00
JUMLAH HARGA BAHAN 98,435.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 138,235.00
E Overhead & Profit 10% 13,823.50
F Harga Satuan Pekerjaan (D+E) 152,058.50

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :3PP
Kode AHSP = 4.4.1.8
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Semen Portland C363 Kg 14.37 1,300.00 18,681.00
Pasir Pasang C99 m3 0.04 100,000.00 4,000.00
JUMLAH HARGA BAHAN 92,681.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 132,481.00
E Overhead & Profit 10% 13,248.10
F Harga Satuan Pekerjaan (D+E) 145,729.10

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
Kode AHSP = 4.4.1.9
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 11.5 1,300.00 14,950.00
Pasir Pasang C99 m3 0.043 100,000.00 4,300.00
JUMLAH HARGA BAHAN 89,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 129,050.00
E Overhead & Profit 10% 12,905.00
F Harga Satuan Pekerjaan (D+E) 141,955.00

Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP:5PP
Kode AHSP = 4.4.1.10
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 11.5 1,300.00 14,950.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 89,450.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 129,250.00
E Overhead & Profit 10% 12,925.00
F Harga Satuan Pekerjaan (D+E) 142,175.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :6PP
Kode AHSP = 4.4.1.11
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 8.32 1,300.00 10,816.00
Pasir Pasang C99 m3 0.049 100,000.00 4,900.00
JUMLAH HARGA BAHAN 85,716.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 125,516.00
E Overhead & Profit 10% 12,551.60
F Harga Satuan Pekerjaan (D+E) 138,067.60

Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP:8PP
Kode AHSP = 4.4.1.12
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 6.5 1,300.00 8,450.00
Pasir Pasang C99 m3 0.05 100,000.00 5,000.00
JUMLAH HARGA BAHAN 83,450.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 123,250.00
E Overhead & Profit 10% 12,325.00
F Harga Satuan Pekerjaan (D+E) 135,575.00

Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :3KP :10PP
Kode AHSP = 4.4.1.13
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 4.5 1,300.00 5,850.00
Kapur Padam C262 m3 0.015 200,000.00 3,000.00
Pasir Pasang C99 m3 0.05 100,000.00 5,000.00
JUMLAH HARGA BAHAN 83,850.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 123,650.00
E Overhead & Profit 10% 12,365.00
F Harga Satuan Pekerjaan (D+E) 136,015.00

Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SM :1KP :1PP
Kode AHSP = 4.4.1.14
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Merah C366 Kg 0.018 20,700.00 372.60
Kapur Padam C262 m3 0.018 200,000.00 3,600.00
Pasir Pasang C99 m3 0.018 100,000.00 1,800.00
JUMLAH HARGA BAHAN 75,772.60
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 115,572.60
E Overhead & Profit 10% 11,557.26
F Harga Satuan Pekerjaan (D+E) 127,129.86

Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM :1KP :2PP
Kode AHSP = 4.4.1.15
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Merah C366 Kg 0.014 20,700.00 289.80
Kapur Padam C262 m3 0.014 200,000.00 2,800.00
Pasir Pasang C99 m3 0.028 100,000.00 2,800.00
JUMLAH HARGA BAHAN 75,889.80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 115,689.80
E Overhead & Profit 10% 11,568.98
F Harga Satuan Pekerjaan (D+E) 127,258.78

Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 3PP


Kode AHSP = 4.4.1.16
A TENAGA
Pekerja C9 OH 0.35 80,000.00 28,000.00
Tukang Batu C18 OH 0.15 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 51,160.00
B BAHAN
HB-20 C239 m3 12.5 - -
Semen Portland C363 Kg 30.32 1,300.00 39,416.00
Pasir Pasang C99 m3 0.728 100,000.00 72,800.00
Besi angker diameter 8 C160 Kg 0.28 1.00 0.28
JUMLAH HARGA BAHAN 112,216.28
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 163,376.28
E Overhead & Profit 10% 16,337.63
F Harga Satuan Pekerjaan (D+E) 179,713.91

Pemasangan 1m2 dinding conblock HB20 campuran 1SP :4PP


Kode AHSP = 4.4.1.17
A TENAGA
Pekerja C9 OH 0.35 80,000.00 28,000.00
Tukang Batu C18 OH 0.15 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 51,160.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
HB-20 C239 m3 12.5 - -
Semen Portland C363 Kg 24.26 1,300.00 31,538.00
Pasir Pasang C99 m3 0.772 100,000.00 77,200.00
Besi angker diameter 8 C160 Kg 0.28 1.00 0.28
JUMLAH HARGA BAHAN 108,738.28
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 159,898.28
E Overhead & Profit 10% 15,989.83
F Harga Satuan Pekerjaan (D+E) 175,888.11

Pemasangan 1m2 dinding conblock HB15 campuran 1SP :3PP


Kode AHSP = 4.4.1.18
A TENAGA
Pekerja C9 OH 0.32 80,000.00 25,600.00
Tukang Batu C18 OH 0.12 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.016 120,000.00 1,920.00
JUMLAH TENAGA KERJA 44,320.00
B BAHAN
HB-15 C240 m3 12.5 - -
Semen Portland C363 Kg 22.74 1,300.00 29,562.00
Pasir Pasang C99 m3 0.55 100,000.00 55,000.00
Besi angker diameter 8 C160 Kg 0.28 1.00 0.28
JUMLAH HARGA BAHAN 84,562.28
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 128,882.28
E Overhead & Profit 10% 12,888.23
F Harga Satuan Pekerjaan (D+E) 141,770.51

Pemasangan 1 cm2 dinding conblock HB15 campuran 1SP :4PP


Kode AHSP = 4.4.1.19
A TENAGA
Pekerja C9 OH 0.32 80,000.00 25,600.00
Tukang Batu C18 OH 0.12 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.016 120,000.00 1,920.00
JUMLAH TENAGA KERJA 44,320.00
B BAHAN
HB-15 C240 m3 12.5 - -
Semen Portland C363 Kg 18.2 1,300.00 23,660.00
Pasir Pasang C99 m3 0.582 100,000.00 58,200.00
Besi angker diameter 8 C160 Kg 0.28 1.00 0.28
JUMLAH HARGA BAHAN 81,860.28
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 126,180.28
E Overhead & Profit 10% 12,618.03
F Harga Satuan Pekerjaan (D+E) 138,798.31

Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :3PP


Kode AHSP = 4.4.1.20
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
HB-10 C241 m3 12.5 - -
Semen Portland C363 Kg 15.16 1,300.00 19,708.00
Pasir Pasang C99 m3 0.364 100,000.00 36,400.00
Besi angker diameter 8 C160 Kg 0.28 1.00 0.28
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 56,108.28
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 95,908.28
E Overhead & Profit 10% 9,590.83
F Harga Satuan Pekerjaan (D+E) 105,499.11

Pemasangan 1 cm2 dinding conblock HB10 campuran 1SP :4PP


Kode AHSP = 4.4.1.21
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
HB-10 C241 m3 12.5 - -
Semen Portland C363 Kg 12.13 1,300.00 15,769.00
Pasir Pasang C99 m3 0.388 100,000.00 38,800.00
Besi angker diameter 8 C160 Kg 0.28 1.00 0.28
JUMLAH HARGA BAHAN 54,569.28
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 94,369.28
E Overhead & Profit 10% 9,436.93
F Harga Satuan Pekerjaan (D+E) 103,806.21

Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :3PP


Kode AHSP = 4.4.1.22
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata rooster C145 m3 30 1.00 30.00
Semen Portland C363 Kg 11 1,300.00 14,300.00
Pasir Pasang C99 m3 0.035 100,000.00 3,500.00
JUMLAH HARGA BAHAN 17,830.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 57,630.00
E Overhead & Profit 10% 5,763.00
F Harga Satuan Pekerjaan (D+E) 63,393.00

Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :4PP


Kode AHSP = 4.4.1.23
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Terawang (Roster) C402 bh 30 16,600.00 498,000.00
Semen Portland C363 Kg 11 1,300.00 14,300.00
Pasir Pasang C99 m3 0.035 100,000.00 3,500.00
JUMLAH HARGA BAHAN 515,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 555,600.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 55,560.00
F Harga Satuan Pekerjaan (D+E) 611,160.00

Pemasangan 1 cm2 dinding bata berongga ekspose 12x11x24 campuran 1SP:3PP


Kode AHSP = 4.4.1.24
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.15 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Bata rooster C145 m3 70 1.00 70.00
Semen Portland C363 Kg 14 1,300.00 18,200.00
Pasir Pasang C99 m3 0.032 100,000.00 3,200.00
JUMLAH HARGA BAHAN 21,470.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 68,270.00
E Overhead & Profit 10% 6,827.00
F Harga Satuan Pekerjaan (D+E) 75,097.00

Pemasangan 1 m2 Dinding Bata Ringan Tebal 7,5 cm


Kode AHSP = 4.4.1.25
A TENAGA
Pekerja C9 OH 0.67 80,000.00 53,600.00
Tukang Batu C18 OH 0.13 125,000.00 16,250.00
Kepala Tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 72,160.00
B BAHAN
Bata Ringan 200 x 600 x 100 C144 Bh 8.40 15,476.19 130,000.00
Mortar Utama C306 Zak 0.473 150,000.00 70,950.00
JUMLAH HARGA BAHAN 200,950.00
C PERALATAN
Alat Bantu % (bahan) Ls 10.000 20,095.00

JUMLAH HARGA ALAT 20,095.00


D Jumlah (A+B+C) 293,205.00
E Overhead & Profit 10% 29,320.50
F Harga Satuan Pekerjaan (D+E) 322,525.50

Pemasangan 1 M2 dinding Batu Alam


Kode AHSP = 4.4.1.25a
A TENAGA
Pekerja C9 OH 0.5 80,000.00 40,000.00
Tukang Batu C18 OH 0.25 125,000.00 31,250.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 80,700.00
B BAHAN
Batu Alam C146 m3 50 3,000.00 150,000.00
Semen Portland C363 Kg 11.75 1,300.00 15,275.00
Pasir Pasang C99 m3 0.035 100,000.00 3,500.00
JUMLAH HARGA BAHAN 168,775.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 249,475.00
E Overhead & Profit 10% 24,947.50
F Harga Satuan Pekerjaan (D+E) 274,422.50

Pemasangan 1 m2 Dinding Bata Ringan Tebal 10 cm


Kode AHSP = 4.4.1.26
A TENAGA
Pekerja C9 OH 0.671 80,000.00 53,680.00
Tukang Batu C18 OH 0.13 125,000.00 16,250.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala Tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 72,240.00
B BAHAN
Bata Ringan 200 x 600 x 100 C144 Bh 8.40 15,476.19 130,000.00
Mortar Utama C306 Zak 0.063 150,000.00 9,450.00
JUMLAH HARGA BAHAN 139,450.00
C PERALATAN
Alat Bantu % (bahan) Ls 10.000 13,945.00

JUMLAH HARGA ALAT 13,945.00


D Jumlah (A+B+C) 225,635.00
E Overhead & Profit 10% 22,563.50
F Harga Satuan Pekerjaan (D+E) 248,198.50

Pemasangan 1 m2 Dinding Bata Ringan


Kode AHSP = 4.4.1.T2
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 39,200.00
B BAHAN
Bata Ringan 200 x 600 x 100 C144 Bh 8.33 15,476.19 128,968.25
Mortar Utama C306 Zak 0.105 150,000.00 15,750.00
JUMLAH HARGA BAHAN 144,718.25
C PERALATAN
Alat Bantu Ls 1.000

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 183,918.25
E Overhead & Profit 10% 18,391.83
F Harga Satuan Pekerjaan (D+E) 202,310.08

Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm


Kode AHSP = 4.4.2.1
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 15.504 1,300.00 20,155.20
Pasir pasang C99 m3 0.016 100,000.00 1,600.00

JUMLAH HARGA BAHAN 21,755.20


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 68,555.20
E Overhead & Profit 10% 6,855.52
F Harga Satuan Pekerjaan (D+E) 75,410.72

Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm


Kode AHSP = 4.4.2.2
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 10.224 1,300.00 13,291.20
Pasir pasang C99 m3 0.020 100,000.00 2,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 15,291.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 62,091.20
E Overhead & Profit 10% 6,209.12
F Harga Satuan Pekerjaan (D+E) 68,300.32

Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm


Kode AHSP = 4.4.2.3
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 7.776 1,300.00 10,108.80
Pasir pasang C99 m3 0.023 100,000.00 2,300.00

JUMLAH HARGA BAHAN 12,408.80


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 59,208.80
E Overhead & Profit 10% 5,920.88
F Harga Satuan Pekerjaan (D+E) 65,129.68
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm
Kode AHSP = 4.4.2.4
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 6.240 1,300.00 8,112.00
Pasir pasang C99 m3 0.024 100,000.00 2,400.00

JUMLAH HARGA BAHAN 10,512.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 57,312.00
E Overhead & Profit 10% 5,731.20
F Harga Satuan Pekerjaan (D+E) 63,043.20

Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


Kode AHSP = 4.4.2.5
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 5.184 1,300.00 6,739.20
Pasir pasang C99 m3 0.026 100,000.00 2,600.00

JUMLAH HARGA BAHAN 9,339.20


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56,139.20
E Overhead & Profit 10% 5,613.92
F Harga Satuan Pekerjaan (D+E) 61,753.12

Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm


Kode AHSP = 4.4.2.6
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 4.416 1,300.00 5,740.80
Pasir pasang C99 m3 0.027 100,000.00 2,700.00

JUMLAH HARGA BAHAN 8,440.80


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 55,240.80
E Overhead & Profit 10% 5,524.08
F Harga Satuan Pekerjaan (D+E) 60,764.88

Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm


Kode AHSP = 4.4.2.7
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 3.936 1,300.00 5,116.80
Pasir pasang C99 m3 0.028 100,000.00 2,800.00

JUMLAH HARGA BAHAN 7,916.80


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 54,716.80
E Overhead & Profit 10% 5,471.68
F Harga Satuan Pekerjaan (D+E) 60,188.48

Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm


Kode AHSP = 4.4.2.8
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 3.456 1,300.00 4,492.80
Pasir pasang C99 m3 0.029 100,000.00 2,900.00

JUMLAH HARGA BAHAN 7,392.80


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 54,192.80
E Overhead & Profit 10% 5,419.28
F Harga Satuan Pekerjaan (D+E) 59,612.08

Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm


Kode AHSP = 4.4.2.9
A TENAGA
Pekerja C9 OH 0.360 80,000.00 28,800.00
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 47,760.00
B BAHAN
Semen Portland C363 Kg 5.760 1,300.00 7,488.00
Kapur Padam C262 m3 0.003 200,000.00 600.00
Pasir pasang C99 m3 0.013 100,000.00 1,300.00

JUMLAH HARGA BAHAN 9,388.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 57,148.00
E Overhead & Profit 10% 5,714.80
F Harga Satuan Pekerjaan (D+E) 62,862.80

Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm


Kode AHSP = 4.4.2.10
A TENAGA
Pekerja C9 OH 0.360 80,000.00 28,800.00
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 47,760.00
B BAHAN
Semen Portland C363 Kg 3.000 1,300.00 3,900.00
Kapur Padam C262 m3 0.005 200,000.00 1,000.00
Pasir pasang C99 m3 0.020 100,000.00 2,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 6,900.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 54,660.00
E Overhead & Profit 10% 5,466.00
F Harga Satuan Pekerjaan (D+E) 60,126.00

Pemasangan 1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm


Kode AHSP = 4.4.2.11
A TENAGA
Pekerja C9 OH 0.360 80,000.00 28,800.00
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 47,760.00
B BAHAN
Mortar Utama' C432 m3 0.009 8,000,000.00 72,000.00
Kapur Padam C262 m3 0.009 200,000.00 1,800.00
Pasir pasang C99 m3 0.009 100,000.00 900.00

JUMLAH HARGA BAHAN 74,700.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 122,460.00
E Overhead & Profit 10% 12,246.00
F Harga Satuan Pekerjaan (D+E) 134,706.00

Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm


Kode AHSP = 4.4.2.12
A TENAGA
Pekerja C9 OH 0.360 80,000.00 28,800.00
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 47,760.00
B BAHAN
Mortar Utama' C432 m3 0.007 8,000,000.00 56,000.00
Kapur Padam C262 m3 0.007 200,000.00 1,400.00
Pasir pasang C99 m3 0.015 100,000.00 1,500.00

JUMLAH HARGA BAHAN 58,900.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 106,660.00
E Overhead & Profit 10% 10,666.00
F Harga Satuan Pekerjaan (D+E) 117,326.00

Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20 mm


Kode AHSP = 4.4.2.13
A TENAGA
Pekerja C9 OH 0.400 80,000.00 32,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 62,640.00
B BAHAN
Semen Portland C363 Kg 13.632 1,300.00 17,721.60
Pasir pasang C99 m3 0.027 100,000.00 2,700.00

JUMLAH HARGA BAHAN 20,421.60


C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 83,061.60
E Overhead & Profit 10% 8,306.16
F Harga Satuan Pekerjaan (D+E) 91,367.76

Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm


Kode AHSP = 4.4.2.14
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 50,360.00
B BAHAN
Semen Portland C363 Kg 10.368 1,300.00 13,478.40
Pasir pasang C99 m3 0.031 100,000.00 3,100.00

JUMLAH HARGA BAHAN 16,578.40


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 66,938.40
E Overhead & Profit 10% 6,693.84
F Harga Satuan Pekerjaan (D+E) 73,632.24

Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm


Kode AHSP = 4.4.2.15
A TENAGA
Pekerja C9 OH 0.400 80,000.00 32,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 62,640.00
B BAHAN
Semen Portland C363 Kg 8.320 1,300.00 10,816.00
Pasir pasang C99 m3 0.032 100,000.00 3,200.00

JUMLAH HARGA BAHAN 14,016.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 76,656.00
E Overhead & Profit 10% 7,665.60
F Harga Satuan Pekerjaan (D+E) 84,321.60

Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm


Kode AHSP = 4.4.2.16
A TENAGA
Pekerja C9 OH 0.400 80,000.00 32,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 62,640.00
B BAHAN
Semen Portland C363 Kg 6.912 1,300.00 8,985.60
Pasir pasang C99 m3 0.035 100,000.00 3,500.00

JUMLAH HARGA BAHAN 12,485.60


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 75,125.60
E Overhead & Profit 10% 7,512.56
F Harga Satuan Pekerjaan (D+E) 82,638.16

Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm


Kode AHSP = 4.4.2.17
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.400 80,000.00 32,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 62,640.00
B BAHAN
Semen Portland C363 Kg 5.888 1,300.00 7,654.40
Pasir pasang C99 m3 0.036 100,000.00 3,600.00

JUMLAH HARGA BAHAN 11,254.40


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 73,894.40
E Overhead & Profit 10% 7,389.44
F Harga Satuan Pekerjaan (D+E) 81,283.84

Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 20 mm


Kode AHSP = 4.4.2.18
A TENAGA
Pekerja C9 OH 0.440 80,000.00 35,200.00
Tukang Batu C18 OH 0.220 125,000.00 27,500.00
Kepala Tukang C39 OH 0.022 150,000.00 3,300.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 68,640.00
B BAHAN
Mortar Utama' C432 m3 0.009 8,000,000.00 72,000.00
Kapur Padam C262 m3 0.009 200,000.00 1,800.00
Pasir pasang C99 m3 0.018 100,000.00 1,800.00

JUMLAH HARGA BAHAN 75,600.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 144,240.00
E Overhead & Profit 10% 14,424.00
F Harga Satuan Pekerjaan (D+E) 158,664.00

Pemasangan 1 m2 berapen 1SP : 5PP tebal 15 mm


Kode AHSP = 4.4.2.19
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Batu C18 OH 0.075 125,000.00 9,375.00
Kepala Tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,535.00
B BAHAN
Semen Portland C363 Kg 5.184 1,300.00 6,739.20
Pasir pasang C99 m3 0.026 100,000.00 2,600.00

JUMLAH HARGA BAHAN 9,339.20


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 32,874.20
E Overhead & Profit 10% 3,287.42
F Harga Satuan Pekerjaan (D+E) 36,161.62

Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm


Kode AHSP = 4.4.2.20
A TENAGA
Pekerja C9 OH 0.080 80,000.00 6,400.00
Tukang Batu C18 OH 0.400 125,000.00 50,000.00
Kepala Tukang C39 OH 0.040 150,000.00 6,000.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 62,880.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Semen Portland C363 Kg 0.500 1,300.00 650.00
Pasir pasang C99 m3 0.013 100,000.00 1,300.00

JUMLAH HARGA BAHAN 1,950.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 64,830.00
E Overhead & Profit 10% 6,483.00
F Harga Satuan Pekerjaan (D+E) 71,313.00

Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1cm


Kode AHSP = 4.4.2.21
A TENAGA
Pekerja C9 OH 0.450 80,000.00 36,000.00
Tukang Batu C18 OH 0.225 125,000.00 28,125.00
Kepala Tukang C39 OH 0.023 150,000.00 3,450.00
Mandor C47 OH 0.023 120,000.00 2,760.00
JUMLAH TENAGA KERJA 70,335.00
B BAHAN
Semen Portland C363 Kg 10.000 1,300.00 13,000.00
Batu Granit C428 Kg 15.000 10,000.00 150,000.00

JUMLAH HARGA BAHAN 163,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 233,335.00
E Overhead & Profit 10% 23,333.50
F Harga Satuan Pekerjaan (D+E) 256,668.50

Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1cm


Kode AHSP = 4.4.2.22
A TENAGA
Pekerja C9 OH 0.450 80,000.00 36,000.00
Tukang Batu C18 OH 0.225 125,000.00 28,125.00
Kepala Tukang C39 OH 0.023 150,000.00 3,450.00
Mandor C47 OH 0.023 120,000.00 2,760.00
JUMLAH TENAGA KERJA 70,335.00
B BAHAN
Semen Portland C363 Kg 10.000 1,300.00 13,000.00
Batu Traso C429 Kg 15.000 5,000.00 75,000.00

JUMLAH HARGA BAHAN 88,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 158,335.00
E Overhead & Profit 10% 15,833.50
F Harga Satuan Pekerjaan (D+E) 174,168.50

Pemasangan 1 m2 plesteran ciprat 1SP : 2PP


Kode AHSP = 4.4.2.23
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Semen Portland C363 Kg 4.320 1,300.00 5,616.00
Pasir Pasang C99 m3 0.006 100,000.00 600.00

JUMLAH HARGA BAHAN 6,216.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 46,016.00
E Overhead & Profit 10% 4,601.60
F Harga Satuan Pekerjaan (D+E) 50,617.60

Pemasangan 1 m2 finishing siar pasangan bata merah


Kode AHSP = 4.4.2.24
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Batu C18 OH 0.075 125,000.00 9,375.00
Kepala Tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,535.00
B BAHAN
Semen Portland C363 Kg 3.108 1,300.00 4,040.40

JUMLAH HARGA BAHAN 4,040.40


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 27,575.40
E Overhead & Profit 10% 2,757.54
F Harga Satuan Pekerjaan (D+E) 30,332.94

Pemasangan 1 m2 finishing siar pasangan conblock ekspose


Kode AHSP = 4.4.2.25
A TENAGA
Pekerja C9 OH 0.070 80,000.00 5,600.00
Tukang Batu C18 OH 0.035 125,000.00 4,375.00
Kepala Tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 11,055.00
B BAHAN
Semen Portland C363 Kg 1.600 1,300.00 2,080.00

JUMLAH HARGA BAHAN 2,080.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 13,135.00
E Overhead & Profit 10% 1,313.50
F Harga Satuan Pekerjaan (D+E) 14,448.50

Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP


Kode AHSP = 4.4.2.26
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 6.340 1,300.00 8,242.00
Pasir pasang C99 m3 0.012 100,000.00 1,200.00

JUMLAH HARGA BAHAN 9,442.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56,242.00
E Overhead & Profit 10% 5,624.20
F Harga Satuan Pekerjaan (D+E) 61,866.20

Pemasangan 1 m2 acian
Kode AHSP = 4.4.2.27
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Batu C18 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Semen Portland C363 Kg 3.250 1,300.00 4,225.00

JUMLAH HARGA BAHAN 4,225.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 35,425.00
E Overhead & Profit 10% 3,542.50
F Harga Satuan Pekerjaan (D+E) 38,967.50

Pemasangan 1 m2 acian semen putih


Kode AHSP = 4.4.2.T1
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Batu C18 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Tepung Gypsum C403 Kg 3.250 4,000.00 13,000.00

JUMLAH HARGA BAHAN 13,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 44,200.00
E Overhead & Profit 10% 4,420.00
F Harga Satuan Pekerjaan (D+E) 48,620.00

Pemasangan 1m2 lantai ubin PC abu-abu ukuran 40cm x40cm


Kode AHSP = 4.4.3.1
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin abu-abu C440 Bh 6.630 2,000.00 13,260.00
Semen Portland C363 kg 9.800 1,300.00 12,740.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 30,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 69,635.00
E Overhead & Profit 10% 6,963.50
F Harga Satuan Pekerjaan (D+E) 76,598.50

Pemasangan 1m2 lantai ubin PC abu-abu ukuran 30cm x30 cm


Kode AHSP = 4.4.3.2
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin abu-abu C440 Bh 11.870 2,000.00 23,740.00
Semen Portland C363 kg 10.000 1,300.00 13,000.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 41,240.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 80,375.00
E Overhead & Profit 10% 8,037.50
F Harga Satuan Pekerjaan (D+E) 88,412.50

Pemasangan 1m2 lantai ubin PC abu-abu ukuran 20cm x20 cm


Kode AHSP = 4.4.3.3
A TENAGA
Pekerja C9 OH 0.270 80,000.00 21,600.00
Tukang Batu C18 OH 0.135 125,000.00 16,875.00
Kepala tukang C39 OH 0.014 150,000.00 2,100.00
Mandor C47 OH 0.014 120,000.00 1,680.00
JUMLAH TENAGA KERJA 42,255.00
B BAHAN
Ubin abu-abu C440 Bh 26.500 2,000.00 53,000.00
Semen Portland C363 kg 10.400 1,300.00 13,520.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 71,020.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 113,275.00
E Overhead & Profit 10% 11,327.50
F Harga Satuan Pekerjaan (D+E) 124,602.50

Pemasangan 1m2 lantai ubin warna ukuran 40cm x40 cm


Kode AHSP = 4.4.3.4
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin warna C441 Bh 6.630 3,500.00 23,205.00
Semen Portland C363 Bh 9.800 1,300.00 12,740.00
Semen warna C365 kg 1.300 20,700.00 26,910.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 67,355.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 106,490.00
E Overhead & Profit 10% 10,649.00
F Harga Satuan Pekerjaan (D+E) 117,139.00

Pemasangan 1m2 lantai ubin warna ukuran 30cm x30cm


Kode AHSP = 4.4.3.5
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Ubin warna C441 Bh 11.870 3,500.00 41,545.00
Semen Portland C363 Bh 10.000 1,300.00 13,000.00
Semen warna C365 kg 1.500 20,700.00 31,050.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 90,095.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 130,655.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 13,065.50
F Harga Satuan Pekerjaan (D+E) 143,720.50

Pemasangan 1m2 lantai ubin warna ukuran 20cm x20cm


Kode AHSP = 4.4.3.6
A TENAGA
Pekerja C9 OH 0.270 80,000.00 21,600.00
Tukang Batu C18 OH 0.135 125,000.00 16,875.00
Kepala tukang C39 OH 0.014 150,000.00 2,100.00
Mandor C47 OH 0.014 120,000.00 1,680.00
JUMLAH TENAGA KERJA 42,255.00
B BAHAN
Ubin warna C441 Bh 26.500 3,500.00 92,750.00
Semen Portland C363 Bh 10.400 1,300.00 13,520.00
Semen warna C365 kg 1.620 20,700.00 33,534.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 144,304.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 186,559.00
E Overhead & Profit 10% 18,655.90
F Harga Satuan Pekerjaan (D+E) 205,214.90

Pemasangan 1m2 lantai ubin teraso ukuran 40cm x40cm


Kode AHSP = 4.4.3.7
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin teraso C442 Bh 6.630 2,500.00 16,575.00
Semen Portland C363 Bh 9.800 1,300.00 12,740.00
Semen warna C365 kg 1.300 20,700.00 26,910.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 60,725.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 99,860.00
E Overhead & Profit 10% 9,986.00
F Harga Satuan Pekerjaan (D+E) 109,846.00

Pemasangan 1m2 lantai ubin teraso ukuran 30cm x30cm


Kode AHSP = 4.4.3.8
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Ubin teraso C442 Bh 11.870 2,500.00 29,675.00
Semen Portland C363 Bh 10.000 1,300.00 13,000.00
Semen warna C365 kg 1.500 20,700.00 31,050.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 78,225.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 118,785.00
E Overhead & Profit 10% 11,878.50
F Harga Satuan Pekerjaan (D+E) 130,663.50

Pemasangan 1m2 lantai ubin granit ukuran 40cm x40cm


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = 4.4.3.9
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin granit 40 x 40 C443 Bh 6.630 50,000.00 331,500.00
Semen Portland C363 kg 9.800 1,300.00 12,740.00
Semen warna C365 Kg 1.300 20,700.00 26,910.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 375,650.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 414,785.00
E Overhead & Profit 10% 41,478.50
F Harga Satuan Pekerjaan (D+E) 456,263.50

Pemasangan 1m2 lantai ubin granit ukuran 30cm x30cm


Kode AHSP = 4.4.3.10
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Ubin granit 30 x 30 C444 Bh 11.870 30,000.00 356,100.00
Semen Portland C363 kg 10.000 1,300.00 13,000.00
Semen warna C365 Kg 1.500 20,700.00 31,050.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 404,650.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 445,210.00
E Overhead & Profit 10% 44,521.00
F Harga Satuan Pekerjaan (D+E) 489,731.00

Pemasangan 1m2 lantai ubin teralux ukuran 40cm x40cm


Kode AHSP = 4.4.3.11
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin teralux C445 Bh 6.630 2,500.00 16,575.00
Semen Portland C363 kg 9.800 1,300.00 12,740.00
Semen warna C365 Kg 1.300 20,700.00 26,910.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 60,725.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 99,860.00
E Overhead & Profit 10% 9,986.00
F Harga Satuan Pekerjaan (D+E) 109,846.00

Pemasangan 1m2 lantai ubin teralux ukuran 30cm x30cm


Kode AHSP = 4.4.3.12
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.130 125,000.00 16,250.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Ubin teralux C445 Bh 11.870 2,500.00 29,675.00
Semen Portland C363 kg 10.000 1,300.00 13,000.00
Semen warna C365 Kg 1.500 20,700.00 31,050.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 78,225.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 118,785.00
E Overhead & Profit 10% 11,878.50
F Harga Satuan Pekerjaan (D+E) 130,663.50

Pemasangan 1m2 lantai ubin teralux marmer ukuran 60cm x60cm


Kode AHSP = 4.4.3.13
A TENAGA
Pekerja C9 OH 0.240 80,000.00 19,200.00
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.012 120,000.00 1,440.00
JUMLAH TENAGA KERJA 37,440.00
B BAHAN
Ubin teralux marmer 60 x 60 C446 Bh 3.100 70,000.00 217,000.00
Semen Portland C363 kg 9.600 1,300.00 12,480.00
Semen warna C365 Kg 1.500 20,700.00 31,050.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 265,030.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 302,470.00
E Overhead & Profit 10% 30,247.00
F Harga Satuan Pekerjaan (D+E) 332,717.00

Pemasangan 1m2 lantai ubin teralux marmer ukuran 40cm x40cm


Kode AHSP = 4.4.3.14
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
Ubin teralux marmer 40 x 40 C447 Bh 6.630 60,000.00 397,800.00
Semen Portland C363 kg 9.800 1,300.00 12,740.00
Semen warna C365 Kg 1.300 20,700.00 26,910.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 441,950.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 481,085.00
E Overhead & Profit 10% 48,108.50
F Harga Satuan Pekerjaan (D+E) 529,193.50

Pemasangan 1m2 lantai ubin teralux marmer ukuran 30cm x30cm


Kode AHSP = 4.4.3.15
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Ubin teralux marmer 30 x 30 C448 Bh 11.870 45,000.00 534,150.00
Semen Portland C363 kg 10.000 1,300.00 13,000.00
Semen warna C365 Kg 1.500 20,700.00 31,050.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 582,700.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 623,260.00
E Overhead & Profit 10% 62,326.00
F Harga Satuan Pekerjaan (D+E) 685,586.00

Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 20 s.d < 30cm


Kode AHSP = 4.4.3.16
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin PC C449 Bh 5.300 2,500.00 13,250.00
Semen Portland C363 kg 1.650 1,300.00 2,145.00
Pasir pasang C99 M3 0.004 100,000.00 400.00

JUMLAH HARGA BAHAN 15,795.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 36,195.00
E Overhead & Profit 10% 3,619.50
F Harga Satuan Pekerjaan (D+E) 39,814.50

Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 30 s.d < 40cm


Kode AHSP = 4.4.3.17
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin PC C449 Bh 3.530 2,500.00 8,825.00
Semen Portland C363 kg 1.240 1,300.00 1,612.00
Pasir pasang C99 M3 0.003 100,000.00 300.00

JUMLAH HARGA BAHAN 10,737.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 31,137.00
E Overhead & Profit 10% 3,113.70
F Harga Satuan Pekerjaan (D+E) 34,250.70

Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 40 s.d <50cm


Kode AHSP = 4.4.3.18
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin PC C449 Bh 2.650 2,500.00 6,625.00
Semen Portland C363 kg 1.240 1,300.00 1,612.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 8,537.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 28,937.00
E Overhead & Profit 10% 2,893.70
F Harga Satuan Pekerjaan (D+E) 31,830.70

Pemasangan 1 m’ plint ubin warna ukuran 20 <30cm


Kode AHSP = 4.4.3.19
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin warna C450 Bh 5.300 3,000.00 15,900.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 19,752.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 40,152.00
E Overhead & Profit 10% 4,015.20
F Harga Satuan Pekerjaan (D+E) 44,167.20

Pemasangan 1 m’ plint ubin warna ukuran 30 s.d <40cm


Kode AHSP = 4.4.3.20
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin warna C450 Bh 3.530 3,000.00 10,590.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 14,442.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 34,842.00
E Overhead & Profit 10% 3,484.20
F Harga Satuan Pekerjaan (D+E) 38,326.20

Pemasangan 1 m’ plint ubin warna ukuran 40 s.d <50cm


Kode AHSP = 4.4.3.21
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin warna C450 Bh 2.650 3,000.00 7,950.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 11,802.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 32,202.00
E Overhead & Profit 10% 3,220.20
F Harga Satuan Pekerjaan (D+E) 35,422.20

Pemasangan 1 m’ plint ubin teraso ukuran 30 s.d <40cm


Kode AHSP = 4.4.3.22
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin teraso C451 Bh 3.530 9,000.00 31,770.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 35,622.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56,022.00
E Overhead & Profit 10% 5,602.20
F Harga Satuan Pekerjaan (D+E) 61,624.20

Pemasangan 1 m’ plint ubin teraso ukuran 40 s.d <50cm


Kode AHSP = 4.4.3.23
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin teraso C451 Bh 2.650 9,000.00 23,850.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 27,702.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 48,102.00
E Overhead & Profit 10% 4,810.20
F Harga Satuan Pekerjaan (D+E) 52,912.20

Pemasangan 1 m’ plint ubin granit ukuran 30 s.d <40 cm


Kode AHSP = 4.4.3.24
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin granit C452 Bh 3.530 10,000.00 35,300.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 39,152.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 59,552.00
E Overhead & Profit 10% 5,955.20
F Harga Satuan Pekerjaan (D+E) 65,507.20
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m’ plint ubin granit ukuran 40 s.d <50cm


Kode AHSP = 4.4.3.25
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint Ubin granit C452 Bh 2.650 10,000.00 26,500.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 30,352.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 50,752.00
E Overhead & Profit 10% 5,075.20
F Harga Satuan Pekerjaan (D+E) 55,827.20

Pemasangan 1 m’ plint ubin teralux kerang ukuran 30 s.d <40cm


Kode AHSP = 4.4.3.26
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint teralux kerang C453 Bh 3.350 9,000.00 30,150.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 34,002.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 54,402.00
E Overhead & Profit 10% 5,440.20
F Harga Satuan Pekerjaan (D+E) 59,842.20

Pemasangan 1 m’ plint ubin teralux kerang ukuran 40 s.d <50cm


Kode AHSP = 4.4.3.27
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint teralux kerang C453 Bh 2.630 9,000.00 23,670.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 27,522.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 47,922.00
E Overhead & Profit 10% 4,792.20
F Harga Satuan Pekerjaan (D+E) 52,714.20

Pemasangan 1 m’ plint ubin teralux marmer ukuran 30 s.d <40cm


Kode AHSP = 4.4.3.28
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint teralux marmer C454 Bh 3.350 25,000.00 83,750.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 87,602.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 108,002.00
E Overhead & Profit 10% 10,800.20
F Harga Satuan Pekerjaan (D+E) 118,802.20

Pemasangan 1 m’ plint ubin teralux marmer ukuran 40 s.d<50cm


Kode AHSP = 4.4.3.29
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint teralux marmer C454 Bh 2.650 25,000.00 66,250.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 70,102.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 90,502.00
E Overhead & Profit 10% 9,050.20
F Harga Satuan Pekerjaan (D+E) 99,552.20

Pemasangan 1 m’ plint ubin teralux marmer ukuran 60 s.d <70cm


Kode AHSP = 4.4.3.30
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Plint teralux marmer C454 Bh 1.700 25,000.00 42,500.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
JUMLAH HARGA BAHAN 46,352.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 66,752.00
E Overhead & Profit 10% 6,675.20
F Harga Satuan Pekerjaan (D+E) 73,427.20

Pemasangan 1m2 lantai teraso cor di tempat, tebal 3cm


Kode AHSP = 4.4.3.31
A TENAGA
Pekerja C9 OH 0.360 80,000.00 28,800.00
Tukang Batu C18 OH 0.180 125,000.00 22,500.00
Kepala tukang C39 OH 0.018 150,000.00 2,700.00
Mandor C47 OH 0.018 120,000.00 2,160.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 56,160.00
B BAHAN
Teraso Cor C455 M3 0.036 3,500,000.00 126,000.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00

JUMLAH HARGA BAHAN 128,070.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 184,230.00
E Overhead & Profit 10% 18,423.00
F Harga Satuan Pekerjaan (D+E) 202,653.00

Pemasangan 1m2 lantai keramik artistik 10 s.d <20cm


Kode AHSP = 4.4.3.32
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Ubin Keramik C456 Bh 106.000 3,000.00 318,000.00
Semen Portland C363 Kg 8.190 1,300.00 10,647.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 3.200 20,700.00 66,240.00
JUMLAH HARGA BAHAN 399,387.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 508,587.00
E Overhead & Profit 10% 50,858.70
F Harga Satuan Pekerjaan (D+E) 559,445.70

Pemasangan 1m2 lantai keramik artistik ukuran 20 s.d<30 cm


Kode AHSP = 4.4.3.33
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Ubin Keramik C456 Bh 53.000 3,000.00 159,000.00
Semen Portland C363 Kg 8.190 1,300.00 10,647.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 2.750 20,700.00 56,925.00
JUMLAH HARGA BAHAN 231,072.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 340,272.00
E Overhead & Profit 10% 34,027.20
F Harga Satuan Pekerjaan (D+E) 374,299.20

Pemasangan 1m2 lantai keramik ukuran 20s.d<30cm


Kode AHSP = 4.4.3.34
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Keramik 33x33 cm C471 Bh 10.000 8,500.00 85,000.00
Semen Portland C363 Kg 8.190 1,300.00 10,647.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 1.620 20,700.00 33,534.00
JUMLAH HARGA BAHAN 133,681.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 242,881.00
E Overhead & Profit 10% 24,288.10
F Harga Satuan Pekerjaan (D+E) 267,169.10

Pemasangan 1m2 lantai keramik ukuran 20 s.d<30cm


Kode AHSP = 4.4.3.35
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Keramik 30x30 cm' C278 dus 1.050 1.00 1.05
Semen Portland C363 Kg 10.400 1,300.00 13,520.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 0.500 20,700.00 10,350.00
JUMLAH HARGA BAHAN 28,371.05
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 137,571.05
E Overhead & Profit 10% 13,757.11
F Harga Satuan Pekerjaan (D+E) 151,328.16

Pemasangan 1m2 lantai keramik ukuran 30 s.d <40cm


Kode AHSP = 4.4.3.36
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Keramik 20x20 cm' C280 dus 1.050 1.00 1.05
Semen Portland C363 Kg 10.000 1,300.00 13,000.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 0.500 20,700.00 10,350.00
JUMLAH HARGA BAHAN 27,851.05
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 137,051.05
E Overhead & Profit 10% 13,705.11
F Harga Satuan Pekerjaan (D+E) 150,756.16

Pemasangan 1m2 lantai keramik ukuran 30 s.d < <40 cm untuk variasi/border
Kode AHSP = 4.4.3.37
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Tukang Batu C18 OH 0.525 125,000.00 65,625.00
Kepala tukang C39 OH 0.053 150,000.00 7,950.00
Mandor C47 OH 0.053 120,000.00 6,360.00
JUMLAH TENAGA KERJA 163,935.00
B BAHAN
Keramik 33x33 cm C471 Bh 33.000 8,500.00 280,500.00
Semen Portland C363 Kg 9.800 1,300.00 12,740.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 4.370 20,700.00 90,459.00
JUMLAH HARGA BAHAN 388,199.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 552,134.00
E Overhead & Profit 10% 55,213.40
F Harga Satuan Pekerjaan (D+E) 607,347.40
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1m2 lantai keramik mozaik ukuran 10 s.d <20cm
Kode AHSP = 4.4.3.38
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Keramik Mozaik C287 Bh 11.870 25,000.00 296,750.00
Semen Portland C363 Kg 14.150 1,300.00 18,395.00
Pasir pasang C99 M3 0.039 100,000.00 3,900.00
Semen warna C365 Kg 2.000 20,700.00 41,400.00
JUMLAH HARGA BAHAN 360,445.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 469,645.00
E Overhead & Profit 10% 46,964.50
F Harga Satuan Pekerjaan (D+E) 516,609.50

Pemasangan 1 m’ plint keramik ukuran 10 s.d < 20cm


Kode AHSP = 4.4.3.39
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 24,300.00
B BAHAN
Plint keramik 10 x 20 cm C472 Bh 10.600 15,000.00 159,000.00
Semen Portland C363 Kg 1.140 1,300.00 1,482.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
Semen warna C365 Kg 0.025 20,700.00 517.50
JUMLAH HARGA BAHAN 161,299.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 185,599.50
E Overhead & Profit 10% 18,559.95
F Harga Satuan Pekerjaan (D+E) 204,159.45
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m’ plint keramik ukuran 20 .sd < 30cm
Kode AHSP = 4.4.3.40
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 24,300.00
B BAHAN
Keramik 10x10 cm C289 Bh 5.300 1,350.00 7,155.00
Semen Portland C363 Kg 1.140 1,300.00 1,482.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
Semen warna C365 Kg 0.025 20,700.00 517.50
JUMLAH HARGA BAHAN 9,454.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 33,754.50
E Overhead & Profit 10% 3,375.45
F Harga Satuan Pekerjaan (D+E) 37,129.95

Pemasangan 1 m’ plint internal cove artistik 5cm x 5cm x 20cm


Kode AHSP = 4.4.3.41
A TENAGA
Pekerja C9 OH 0.750 80,000.00 60,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.038 120,000.00 4,560.00
JUMLAH TENAGA KERJA 169,560.00
B BAHAN
Internal Cove C457 Bh 5.300 8,000.00 42,400.00
Semen Portland C363 Kg 1.140 1,300.00 1,482.00
Pasir pasang C99 M3 0.003 100,000.00 300.00
Semen warna C365 Kg 0.100 20,700.00 2,070.00
JUMLAH HARGA BAHAN 46,252.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 215,812.00
E Overhead & Profit 10% 21,581.20
F Harga Satuan Pekerjaan (D+E) 237,393.20

Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm


Kode AHSP = 4.4.3.42
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Marmer C300 Bh 1.060 2,800,000.00 2,968,000.00
Semen Portland C363 Kg 8.190 1,300.00 10,647.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 0.134 20,700.00 2,773.80
JUMLAH HARGA BAHAN 2,985,920.80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,095,120.80
E Overhead & Profit 10% 309,512.08
F Harga Satuan Pekerjaan (D+E) 3,404,632.88

Pemasangan 1 m2 lantai karpet


Kode AHSP = 4.4.3.43
A TENAGA
Pekerja C9 OH 0.170 80,000.00 13,600.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Kayu C19 OH 0.170 125,000.00 21,250.00
Kepala tukang C39 OH 0.017 150,000.00 2,550.00
Mandor C47 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 38,480.00
B BAHAN
Karpet Tile C298 m2 1.050 450,000.00 472,500.00
Lem Kayu C292 Kg 0.350 32,500.00 11,375.00

JUMLAH HARGA BAHAN 483,875.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 522,355.00
E Overhead & Profit 10% 52,235.50
F Harga Satuan Pekerjaan (D+E) 574,590.50

Pemasangan 1 m2 underlayer (pelapis bawah karpet)


Kode AHSP = 4.4.3.44
A TENAGA
Pekerja C9 OH 0.120 80,000.00 9,600.00
Tukang Kayu C19 OH 0.120 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,120.00
B BAHAN
Underlayer C416 m2 1.050 83,544.30 87,721.52
Lem Kayu C292 Kg 0.350 32,500.00 11,375.00

JUMLAH HARGA BAHAN 99,096.52


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 126,216.52
E Overhead & Profit 10% 12,621.65
F Harga Satuan Pekerjaan (D+E) 138,838.17

Pemasangan 1 m2 lantai parquet kayu


Kode AHSP = 4.4.3.45
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Kayu C19 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Parquet C316 m2 1.050 296,803.65 311,643.84
Lem Kayu C283 Kg 0.600 32,500.00 19,500.00

JUMLAH HARGA BAHAN 331,143.84


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 440,343.84
E Overhead & Profit 10% 44,034.38
F Harga Satuan Pekerjaan (D+E) 484,378.22

Pemasangan 1 m2 lantai kayu gymfloor


Kode AHSP = 4.4.3.46
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Kayu C19 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Parquet C316 m2 1.050 296,803.65 311,643.84
Lem Kayu C283 Kg 0.600 32,500.00 19,500.00

JUMLAH HARGA BAHAN 331,143.84


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 440,343.84
E Overhead & Profit 10% 44,034.38
F Harga Satuan Pekerjaan (D+E) 484,378.22

Pemasangan 1 m2 dinding porslen 11cm x 11cm


Kode AHSP = 4.4.3.47
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Batu C18 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 156,000.00
B BAHAN
Porselen ( 11 x 11 ) cm C342 dos 1.050 1,987.95 2,087.35
Semen Portland C350 Kg 9.300 1,300.00 12,090.00
Pasir pasang C97 M3 0.018 100,000.00 1,800.00
Semen warna C352 Kg 0.500 20,700.00 10,350.00
JUMLAH HARGA BAHAN 26,327.35
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 182,327.35
E Overhead & Profit 10% 18,232.73
F Harga Satuan Pekerjaan (D+E) 200,560.08

Pemasangan 1 m2 dinding porslen 10cm x 20cm


Kode AHSP = 4.4.3.48
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Porselen ( 10 x 20 ) cm C460 m2 53.000 1.00 53.00
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 2.750 20,700.00 56,925.00

JUMLAH HARGA BAHAN 70,868.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 211,268.00
E Overhead & Profit 10% 21,126.80
F Harga Satuan Pekerjaan (D+E) 232,394.80

Pemasangan 1 m2 dinding porslen 20cm x 20cm


Kode AHSP = 4.4.3.49
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Porselen ( 20 x 20 ) cm C461 m2 26.000 1.00 26.00
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 1.940 20,700.00 40,158.00
JUMLAH HARGA BAHAN 54,074.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 194,474.00
E Overhead & Profit 10% 19,447.40
F Harga Satuan Pekerjaan (D+E) 213,921.40

Pemasangan 1 m2 dinding keramik artistik 10cm x 20cm


Kode AHSP = 4.4.3.50
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik Artistilk C462 m2 52.000 1.00 52.00
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 2.750 20,700.00 56,925.00
JUMLAH HARGA BAHAN 70,867.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 211,267.00
E Overhead & Profit 10% 21,126.70
F Harga Satuan Pekerjaan (D+E) 232,393.70

Pemasangan 1 m2 dinding keramik artistik 5cm x 20cm


Kode AHSP = 4.4.3.51
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik Artistilk C462 m2 104.000 1.00 104.00
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 2.900 20,700.00 60,030.00
JUMLAH HARGA BAHAN 74,024.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 214,424.00
E Overhead & Profit 10% 21,442.40
F Harga Satuan Pekerjaan (D+E) 235,866.40

Pemasangan 1 m2 dinding keramik 10cm x 20cm


Kode AHSP = 4.4.3.52
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik dinding 10x20 cm C463 buah 52.000 1.00 52.00
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 2.750 20,700.00 56,925.00
JUMLAH HARGA BAHAN 70,867.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 211,267.00
E Overhead & Profit 10% 21,126.70
F Harga Satuan Pekerjaan (D+E) 232,393.70

Pemasangan 1 m2 dinding keramik 20cm x 20cm


Kode AHSP = 4.4.3.53
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik dinding 20x20 cm C464 buah 26.000 1.00 26.00
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 1.940 20,700.00 40,158.00
JUMLAH HARGA BAHAN 54,074.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 194,474.00
E Overhead & Profit 10% 19,447.40
F Harga Satuan Pekerjaan (D+E) 213,921.40

Pemasangan 1 m2 dinding keramik 25cm x 50cm


Kode AHSP = 4.4.3.54
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Keramik dinding 20x20 cm C464 buah 8.000 1.00 8.00
Semen Portland C363 Kg 9.600 1,300.00 12,480.00
Pasir pasang C99 M3 0.020 100,000.00 2,000.00
Semen warna C365 Kg 1.980 20,700.00 40,986.00
JUMLAH HARGA BAHAN 55,474.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 164,674.00
E Overhead & Profit 10% 16,467.40
F Harga Satuan Pekerjaan (D+E) 181,141.40

Pemasangan 1 m2 dinding keramik 20cm x 40cm


Kode AHSP = 4.4.3.55
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik 20x40 cm C283 buah 10.000 8,076.92 80,769.23
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 1.940 20,700.00 40,158.00
JUMLAH HARGA BAHAN 134,817.23
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 275,217.23
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 27,521.72
F Harga Satuan Pekerjaan (D+E) 302,738.95

Pemasangan 1 m2 dinding marmer 100cm x 100cm


Kode AHSP = 4.4.3.54
A TENAGA
Pekerja C9 OH 1.300 80,000.00 104,000.00
Tukang Batu C18 OH 0.650 125,000.00 81,250.00
Kepala tukang C39 OH 0.065 150,000.00 9,750.00
Mandor C47 OH 0.065 120,000.00 7,800.00
JUMLAH TENAGA KERJA 202,800.00
B BAHAN
Marmer C300 bh 1.060 2,800,000.00 2,968,000.00
Semen Portland C363 Kg 12.440 1,300.00 16,172.00
Pasir pasang C99 M3 0.025 100,000.00 2,500.00
Semen warna C365 Kg 0.650 20,700.00 13,455.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 3.030 21,000.00 63,630.00
JUMLAH HARGA BAHAN 3,063,757.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,266,557.00
E Overhead & Profit 10% 326,655.70
F Harga Satuan Pekerjaan (D+E) 3,593,212.70

Pemasangan 1 m2 dinding bata pelapis (super) 3cm x 7cm x 24cm


Kode AHSP = 4.4.3.55
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Batu C18 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 156,000.00
B BAHAN
Bata Pelapis C465 bh 63.000 1.00 63.00
Semen Portland C363 Kg 12.440 1,300.00 16,172.00
Pasir pasang C99 M3 0.025 100,000.00 2,500.00
Semen warna C365 Kg 2.750 20,700.00 56,925.00
JUMLAH HARGA BAHAN 75,660.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 231,660.00
E Overhead & Profit 10% 23,166.00
F Harga Satuan Pekerjaan (D+E) 254,826.00

Pemasangan 1 m2 dinding batu paras


Kode AHSP = 4.4.3.56
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Batu Paras C466 bh 1.100 1.00 1.10
Semen Portland C363 Kg 11.750 1,300.00 15,275.00
Pasir pasang C99 M3 0.035 100,000.00 3,500.00

JUMLAH HARGA BAHAN 18,776.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 127,976.10
E Overhead & Profit 10% 12,797.61
F Harga Satuan Pekerjaan (D+E) 140,773.71
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 dinding batu tempel hitam
Kode AHSP = 4.4.3.57
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Batu tempel hitam C467 bh 1.100 1.00 1.10
Semen Portland C363 Kg 11.750 1,300.00 15,275.00
Pasir pasang C99 M3 0.035 100,000.00 3,500.00

JUMLAH HARGA BAHAN 18,776.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 127,976.10
E Overhead & Profit 10% 12,797.61
F Harga Satuan Pekerjaan (D+E) 140,773.71

Pemasangan 1 m2 lantai vynil ukuran 30cm x 30cm


Kode AHSP = 4.4.3.58
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 33,960.00
B BAHAN
Vynil C468 bh 11.870 11,346.15 134,678.85
Lem Kayu C292 Kg 0.350 32,500.00 11,375.00

JUMLAH HARGA BAHAN 146,053.85


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 180,013.85
E Overhead & Profit 10% 18,001.38
F Harga Satuan Pekerjaan (D+E) 198,015.23

Pemasangan 1 m2 wallpaper lebar 50 cm


Kode AHSP = 4.4.3.59
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang Batu C18 OH 0.175 125,000.00 21,875.00
Kepala tukang C39 OH 0.017 150,000.00 2,550.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 52,665.00
B BAHAN
Wallpaper C419 m 2.200 48,076.92 105,769.23
Lem Kayu C292 Kg 0.250 32,500.00 8,125.00

JUMLAH HARGA BAHAN 113,894.23


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 166,559.23
E Overhead & Profit 10% 16,655.92
F Harga Satuan Pekerjaan (D+E) 183,215.15

Pemasangan 1m2 floor harderner


Kode AHSP = 4.4.3.60
A TENAGA
Pekerja C9 OH 0.120 80,000.00 9,600.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,120.00
B BAHAN
Floor Hardener C219 Kg 5.000 25,000.00 125,000.00

JUMLAH HARGA BAHAN 125,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 152,120.00
E Overhead & Profit 10% 15,212.00
F Harga Satuan Pekerjaan (D+E) 167,332.00

Pemasangan 1 m’ plint vynil 15cm x 30cm


Kode AHSP = 4.4.3.61
A TENAGA
Pekerja C9 OH 0.080 80,000.00 6,400.00
Tukang Batu C18 OH 0.080 125,000.00 10,000.00
Kepala tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 18,080.00
B BAHAN
Vynil C468 Bh 3.100 11,346.15 35,173.08
Lem Kayu C292 Kg 0.080 32,500.00 2,600.00

JUMLAH HARGA BAHAN 37,773.08


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 55,853.08
E Overhead & Profit 10% 5,585.31
F Harga Satuan Pekerjaan (D+E) 61,438.38

Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm


Kode AHSP = 4.4.3.62
A TENAGA
Pekerja C9 OH 0.120 80,000.00 9,600.00
Tukang Batu C18 OH 0.120 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,120.00
B BAHAN
Papan kayu kelas I C94 M3 0.003 4,000,000.00 12,000.00
Paku Skrup C323 Kg 0.050 114,700.00 5,735.00

JUMLAH HARGA BAHAN 17,735.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 44,855.00
E Overhead & Profit 10% 4,485.50
F Harga Satuan Pekerjaan (D+E) 49,340.50

Pemasangan 1 m paving block (blok beton) natural tebal 6cm


Kode AHSP = 4.4.3.63
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.001 120,000.00 156.00
JUMLAH TENAGA KERJA 90,156.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Paving Blok 6 cm K-300 C331 M2 1.010 80,000.00 80,800.00
pasir beton C97 m3 0.050 100,000.00 5,000.00

JUMLAH HARGA BAHAN 85,800.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 175,956.00
E Overhead & Profit 10% 17,595.60
F Harga Satuan Pekerjaan (D+E) 193,551.60

Pemasangan 1 m2 dinding granit ukuran (30 x 60) cm


Kode AHSP = 4.4.3.T1
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Granit 30x60 C235 Buah 6.000 64,000.00 384,000.00
Semen Portland C363 kg 9.600 68,000.00 652,800.00
Pasir Pasang C99 m3 0.020 68,001.00 1,360.02
Semen warna C365 kg 1.980 68,002.00 134,643.96
JUMLAH HARGA BAHAN 1,172,803.98
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,313,203.98
E Overhead & Profit 10% 131,320.40
F Harga Satuan Pekerjaan (D+E) 1,444,524.38

Pemasangan 1m Step Nozing


Kode AHSP = 4.4.3.T2
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Batu C18 OH 0.090 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Nozing Step 10 x 60 C316 Buah 1.700 46,750.00 79,475.00
Semen Portland C363 kg 1.140 1,300.00 1,482.00
Pasir Pasang C99 m3 0.003 100,000.00 300.00
Semen warna C365 kg 0.100 20,700.00 2,070.00
JUMLAH HARGA BAHAN 83,327.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 103,727.00
E Overhead & Profit 10% 10,372.70
F Harga Satuan Pekerjaan (D+E) 114,099.70

Pemasangan 1m2 lantai Granit ukuran (60 x 60) cm


Kode AHSP = 4.4.3.T3
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang Batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Granit 60x60 C237 Buah 3.000 80,000.00 240,000.00
Semen Portland C363 kg 9.700 1,300.00 12,610.00
Pasir Pasang C99 m3 0.050 100,000.00 5,000.00
Semen warna C365 kg 1.550 20,700.00 32,085.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 289,695.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 330,255.00
E Overhead & Profit 10% 33,025.50
F Harga Satuan Pekerjaan (D+E) 363,280.50

Pemasangan 1 m' Plint Granit ukuran (10 x 60) cm


Kode AHSP = 4.4.3.T4
A TENAGA
Pekerja C9 OH 0.060 80,000.00 4,800.00
Tukang Batu C18 OH 0.030 125,000.00 3,750.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 9,360.00
B BAHAN
Granit 60x60 C237 Buah 0.620 80,000.00 49,600.00
Semen Portland C363 kg 2.400 1,300.00 3,120.00
Pasir Pasang C99 m3 0.011 100,000.00 1,125.00
Semen warna C365 kg 0.375 20,700.00 7,762.50
JUMLAH HARGA BAHAN 61,607.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 70,967.50
E Overhead & Profit 10% 7,096.75
F Harga Satuan Pekerjaan (D+E) 78,064.25

Pemasangan 1 m2 lantai parquet


Kode AHSP = 4.4.3.T5
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang kayu C19 OH 0.350 125,000.00 43,750.00
Kepala tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 109,200.00
B BAHAN
Parquet C328 M2 1.050 296,803.65 311,643.84
Lem Kayu C292 kg 0.600 32,500.00 19,500.00

JUMLAH HARGA BAHAN 331,143.84


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 440,343.84
E Overhead & Profit 10% 44,034.38
F Harga Satuan Pekerjaan (D+E) 484,378.22

Pemasangan 1 m2 dinding keramik ukuran (30 x 60) cm


Kode AHSP = 4.4.3.T6
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik 30x60 cm C286 Buah 6.000 50,000.00 300,000.00
Semen Portland C363 kg 9.600 68,000.00 652,800.00
Pasir Pasang C99 m3 0.020 68,001.00 1,360.02
Semen warna C365 kg 1.980 68,002.00 134,643.96
JUMLAH HARGA BAHAN 1,088,803.98
C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 1,229,203.98
E Overhead & Profit 10% 122,920.40
F Harga Satuan Pekerjaan (D+E) 1,352,124.38

Memasang 1 M2 Tegel Homogenous Tile Ukuran 60x60


Kode AHSP = 4.4.3.T7
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Homogenous Tile 60x60 cm C244 Buah 3.000 80,000.00 240,000.00
Semen Portland C363 kg 9.700 1,300.00 12,610.00
Pasir Pasang C99 m3 0.050 100,000.00 5,000.00
Semen warna C365 kg 1.550 20,700.00 32,085.00
JUMLAH HARGA BAHAN 289,695.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 330,255.00
E Overhead & Profit 10% 33,025.50
F Harga Satuan Pekerjaan (D+E) 363,280.50

Memasang 1 M2 Tegel Homogenous Tile Ukuran 30x60


Kode AHSP = 4.4.3.T8
A TENAGA
Pekerja C9 OH 0.260 80,000.00 20,800.00
Tukang batu C18 OH 0.130 125,000.00 16,250.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 40,560.00
B BAHAN
Keramik 30x60 cm C286 Buah 6.000 50,000.00 300,000.00
Semen Portland C363 kg 9.700 1,300.00 12,610.00
Pasir Pasang C99 m3 0.050 100,000.00 5,000.00

JUMLAH HARGA BAHAN 317,610.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 358,170.00
E Overhead & Profit 10% 35,817.00
F Harga Satuan Pekerjaan (D+E) 393,987.00

Memasang 1 m' Plint Homogenous Tile ukuran (10 x 60) cm


Kode AHSP = 4.4.3.T9
A TENAGA
Pekerja C9 OH 0.060 80,000.00 4,800.00
Tukang batu C18 OH 0.030 125,000.00 3,750.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 9,360.00
B BAHAN
Homogenous Tile 60x60 cm C244 Buah 0.620 80,000.00 49,600.00
Semen Portland C363 kg 2.400 1,300.00 3,120.00
Pasir Pasang C99 m3 0.011 100,000.00 1,125.00
Semen warna C365 kg 0.375 20,700.00 7,762.50
JUMLAH HARGA BAHAN 61,607.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 70,967.50
E Overhead & Profit 10% 7,096.75
F Harga Satuan Pekerjaan (D+E) 78,064.25
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Memasang 1 m2 lantai keramik ukuran (50 x 50) cm
Kode AHSP = 4.4.3.T10
A TENAGA
Pekerja C9 OH 0.240 80,000.00 19,200.00
Tukang batu C18 OH 0.120 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.012 120,000.00 1,440.00
JUMLAH TENAGA KERJA 37,440.00
B BAHAN
keramik 50x50 cm C275 Buah 4.000 47,075.00 188,300.00
Semen Portland C363 kg 9.600 1,300.00 12,480.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
Semen warna C365 kg 1.500 20,700.00 31,050.00
JUMLAH HARGA BAHAN 236,330.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 273,770.00
E Overhead & Profit 10% 27,377.00
F Harga Satuan Pekerjaan (D+E) 301,147.00

Memasang 1 m2 lantai keramik ukuran (40 x 40) cm


Kode AHSP = 4.4.3.T11
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
keramik 40x40 cm C276 Buah 6.630 18,666.67 123,760.00
Semen Portland C363 kg 9.800 1,300.00 12,740.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
Semen warna C365 kg 1.300 20,700.00 26,910.00
JUMLAH HARGA BAHAN 167,910.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 207,045.00
E Overhead & Profit 10% 20,704.50
F Harga Satuan Pekerjaan (D+E) 227,749.50

Pemasangan 1 m2 Batu Sikat


Kode AHSP = 4.4.3.T12
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 159,200.00
B BAHAN
Batu Sikat C147 m2 1.100 73,333.33 80,666.67
Semen Portland C363 kg 23.500 1,300.00 30,550.00
Pasir Pasang C99 m3 0.035 100,000.00 3,500.00

JUMLAH HARGA BAHAN 114,716.67


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 273,916.67
E Overhead & Profit 10% 27,391.67
F Harga Satuan Pekerjaan (D+E) 301,308.33

1 m2 Pekerjaan Screed 1Pc:5PP


Kode AHSP = 4.4.3.T13
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 kg 5.184 1,300.00 6,739.20
Pasir Pasang C99 m3 0.026 100,000.00 2,600.00

JUMLAH HARGA BAHAN 9,339.20


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56,139.20
E Overhead & Profit 10% 5,613.92
F Harga Satuan Pekerjaan (D+E) 61,753.12

Pemasangan 1 m2 lantai Epoxy


Kode AHSP = 4.4.3.T14
A TENAGA

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA -


B BAHAN
Maxifloor MFT 323 SL C479 m2 1.100 192,000.00 211,200.00

JUMLAH HARGA BAHAN 211,200.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 211,200.00
E Overhead & Profit 10% 21,120.00
F Harga Satuan Pekerjaan (D+E) 232,320.00

Pemasangan 1 m2 lantai vynil Forbo


Kode AHSP = 4.4.3.T14
A TENAGA
Tenaga include bahan -
-
-
-
JUMLAH TENAGA KERJA -
B BAHAN
Vynil Merk Forbo Sarlon (Include lem dan pemasangan) C469 M2 1.080 815,000.00 880,200.00

JUMLAH HARGA BAHAN 880,200.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 880,200.00
E Overhead & Profit 10% 88,020.00
F Harga Satuan Pekerjaan (D+E) 968,220.00

Pemasangan 1 m2 lantai Karpet Tile Forbo Flotex


Kode AHSP = 4.4.3.T15
A TENAGA
Tenaga Include material -
-
-
-
JUMLAH TENAGA KERJA -
B BAHAN
Karpet Tile Merk Forbo Flotex (Include Pemasangan) C470 m2 1.050 750,000.00 787,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA BAHAN 787,500.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 787,500.00
E Overhead & Profit 10% 78,750.00
F Harga Satuan Pekerjaan (D+E) 866,250.00

Pemasangan 1m2 Langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm


Kode AHSP = 4.5.1.1
A TENAGA
Pekerja C9 OH 0.03 80,000.00 2,400.00
Tukang kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 12,680.00
B BAHAN
Asbes semen C129 m2 1.1 1.00 1.10
Paku tripleks C322 kg 0.01 22,100.00 221.00
JUMLAH HARGA BAHAN 222.10
C PERALATAN
% 10.000
Bahan
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 12,902.10
E Overhead & Profit 10% 1,290.21
F Harga Satuan Pekerjaan (D+E) 14,192.31

Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm


Kode AHSP = 4.5.1.2
A TENAGA
Pekerja C9 OH 0.12 80,000.00 9,600.00
Tukang kayu C19 OH 0.12 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,120.00
B BAHAN
Akustik C121 Lembar 12 - -
Paku tripleks C322 kg 0.05 22,100.00 1,105.00
JUMLAH HARGA BAHAN 1,105.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 28,225.00
E Overhead & Profit 10% 2,822.50
F Harga Satuan Pekerjaan (D+E) 31,047.50

Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm


Kode AHSP = 4.5.1.3
A TENAGA
Pekerja C9 OH 0.12 80,000.00 9,600.00
Tukang kayu C19 OH 0.12 125,000.00 15,000.00
Kepala tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,120.00
B BAHAN
Akustik C121 Lembar 5.8 - -
Paku tripleks C322 kg 0.05 22,100.00 1,105.00
JUMLAH HARGA BAHAN 1,105.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 28,225.00
E Overhead & Profit 10% 2,822.50
F Harga Satuan Pekerjaan (D+E) 31,047.50

Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm


Kode AHSP = 4.5.1.4
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang kayu C19 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Akustik C121 Lembar 1.5 - -
Paku tripleks C322 kg 0.05 22,100.00 1,105.00
JUMLAH HARGA BAHAN 1,105.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,705.00
E Overhead & Profit 10% 2,370.50
F Harga Satuan Pekerjaan (D+E) 26,075.50

Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm
Kode AHSP = 4.5.1.5
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang kayu C19 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Tripleks 3 mm C410 Lembar 0.375 63,701.00 23,887.88
Paku tripleks C322 kg 0.03 22,100.00 663.00
JUMLAH HARGA BAHAN 24,550.88
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 47,150.88
E Overhead & Profit 10% 4,715.09
F Harga Satuan Pekerjaan (D+E) 51,865.96

Pemasangan 1 m2 langit-langit lambrisering kayu, tebal 9 mm


Kode AHSP = 4.5.1.6
A TENAGA
Pekerja C9 OH 0.8 80,000.00 64,000.00
Tukang kayu C19 OH 0.8 125,000.00 100,000.00
Kepala tukang C39 OH 0.08 150,000.00 12,000.00
Mandor C47 OH 0.04 120,000.00 4,800.00
JUMLAH TENAGA KERJA 180,800.00
B BAHAN
Kayu papan 3/20 Kelas III m3 0,015 0.015 1,600,000.00 24,000.00
Paku tripleks kg 0,010 0.01 22,100.00 221.00
JUMLAH HARGA BAHAN 24,221.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 205,021.00
E Overhead & Profit 10% 20,502.10
F Harga Satuan Pekerjaan (D+E) 225,523.10

Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


Kode AHSP = 4.5.1.7
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang kayu C19 OH 0.05 125,000.00 6,250.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala tukang C39 OH 0.005 150,000.00 750.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 15,600.00
B BAHAN
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 0.364 65,000.00 23,660.00
Paku skrup C323 kg 0.11 114,700.00 12,617.00
JUMLAH HARGA BAHAN 36,277.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 51,877.00
E Overhead & Profit 10% 5,187.70
F Harga Satuan Pekerjaan (D+E) 57,064.70

Pemasangan 1 m’ list langit-langit kayu profil


Kode AHSP = 4.5.1.10
A TENAGA
Pekerja C9 OH 0.05 80,000.00 4,000.00
Tukang Kayu C19 OH 0.05 125,000.00 6,250.00
Kepala tukang C39 OH 0.005 150,000.00 750.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 11,360.00
B BAHAN
List kayu profil C293 m 1.05 25,000.00 26,250.00
Paku Biasa C318 kg 0.01 21,000.00 210.00
JUMLAH HARGA BAHAN 26,460.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 37,820.00
E Overhead & Profit 10% 3,782.00
F Harga Satuan Pekerjaan (D+E) 41,602.00

Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium


Kode AHSP = 4.5.1.12
A TENAGA
Pekerja C9 OH 0.5 80,000.00 40,000.00
Tukang Besi C20 OH 0.5 125,000.00 62,500.00
Kepala tukang C39 OH 0.05 150,000.00 7,500.00
Mandor C47 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 113,000.00
B BAHAN
Profil alluminium "T" C600 m 3.6 42,666.67 153,600.00
Kawat Diameter 4 mm C268 kg 0.15 32,400.00 4,860.00
Ramset C637 Buah 1.05 3,500.00 3,675.00
Akustik 60 x 120 C122 Lembar 1.5 - -
JUMLAH HARGA BAHAN 162,135.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 275,135.00
E Overhead & Profit 10% 27,513.50
F Harga Satuan Pekerjaan (D+E) 302,648.50

Pemasangan 1 m2 Rangka langit-langit besi hollow 40.40


Kode AHSP = 4.5.1.14
A TENAGA
Pekerja C9 OH 0.35 80,000.00 28,000.00
Tukang Besi C20 OH 0.35 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 79,160.00
B BAHAN
Besi Hollow 4x4 cm C171 m1 4 17,000.00 68,000.00
Assesoris perkuatan, las dll C131 Ls 4 12,000.00 48,000.00
JUMLAH HARGA BAHAN 116,000.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 195,160.00
E Overhead & Profit 10% 19,516.00
F Harga Satuan Pekerjaan (D+E) 214,676.00

Pemasangan 1 m2 langit-langit gypsum + rangka metal hollow


Kode AHSP = 4.5.1.T1
A TENAGA
Pekerja plafond C13 OH 0.4 80,000.00 32,000.00
Tukang plafond C25 OH 0.5 125,000.00 62,500.00
Mandor plafond C42 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 100,500.00
B BAHAN
Rangka Metal Hollow 2x4 C638 m’ 2.1 4,000.00 8,400.00
Rangka Metal Hollow 4x4 C639 m’ 1.6 5,500.00 8,800.00
Kawat Diameter 4 mm C268 Kg 0.15 32,400.00 4,860.00
Ramset C637 Bh 1.05 3,500.00 3,675.00
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 0.364 65,000.00 23,660.00
Screw Bremick C649 kg 0.11 120.00 13.20
JUMLAH HARGA BAHAN 49,408.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 149,908.20
E Overhead & Profit 10% 14,990.82
F Harga Satuan Pekerjaan (D+E) 164,899.02

Pemasangan 1 m2 langit-langit gypsum + rangka metal hollow (Type Drop Celling)


Kode AHSP = 4.5.1.T1
A TENAGA
Pekerja plafond C13 OH 0.021 80,000.00 1,680.00
Tukang plafond C25 OH 0.021 125,000.00 2,625.00
Mandor plafond C42 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 5,505.00
B BAHAN
Rangka Metal Hollow 2x4 C638 m’ 2.1 4,000.00 8,400.00
Rangka Metal Hollow 4x4 C639 m’ 1.6 5,500.00 8,800.00
Kawat Diameter 4 mm C268 Kg 0.15 32,400.00 4,860.00
Ramset C637 Bh 1.05 3,500.00 3,675.00
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 1.05 65,000.00 68,250.00
Screw Bremick C649 kg 0.11 120.00 13.20
JUMLAH HARGA BAHAN 93,998.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 99,503.20
E Overhead & Profit 10% 9,950.32
F Harga Satuan Pekerjaan (D+E) 109,453.52

Pemasangan 1 m2 langit-langit kalsiboard + rangka metal hollow


Kode AHSP = 4.5.1.T2
A TENAGA
Pekerja plafond C13 OH 0.5 80,000.00 40,000.00
Tukang plafond C25 OH 0.5 125,000.00 62,500.00
Mandor plafond C42 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 111,500.00
B BAHAN
Rangka Metal Hollow 2x4 C638 m’ 2.1 4,000.00 8,400.00
Rangka Metal Hollow 4x4 C639 m’ 1.6 5,500.00 8,800.00
Kawat Diameter 4 mm C268 Kg 0.15 32,400.00 4,860.00
Ramset C637 Bh 1.05 3,500.00 3,675.00
Kalsiboard 3,5 mm C260 Lembar 0.364 19,097.22 6,951.39
Self Drilling Screw dia-10x16mm (truss screw) C650 kg 11 180.00 1,980.00
JUMLAH HARGA BAHAN 34,666.39
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 146,166.39
E Overhead & Profit 10% 14,616.64
F Harga Satuan Pekerjaan (D+E) 160,783.03

Pemasangan 1 Bh Manhole
Kode AHSP = 4.5.1.T3
A TENAGA
Pekerja plafond C13 OH 0.05 80,000.00 4,000.00
Tukang plafond C25 OH 0.05 125,000.00 6,250.00
Mandor plafond C42 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 11,210.00
B BAHAN
Allumunium Siku C490 m’ 1.05 7,500.00 7,875.00

JUMLAH HARGA BAHAN 7,875.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 19,085.00
E Overhead & Profit 10% 1,908.50
F Harga Satuan Pekerjaan (D+E) 20,993.50

Pemasangan 1 m2 Dinding kalsiboard + rangka besi hollow


Kode AHSP = 4.5.1.T4
A TENAGA
Pekerja plafond C13 OH 0.5 80,000.00 40,000.00
Tukang plafond C25 OH 0.5 125,000.00 62,500.00
Mandor plafond C42 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 111,500.00
B BAHAN
Besi Hollow 4x4 cm C171 m’ 2.1 17,000.00 35,700.00
Kalsiboard 3,5 mm C260 Lembar 0.364 19,097.22 6,951.39
Cat Penutup 2 C215 Kg 0.25 72,500.00 18,125.00
Self Drilling Screw dia-10x16mm (truss screw) C650 Bh 11 180.00 1,980.00

JUMLAH HARGA BAHAN 62,756.39


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 174,256.39
E Overhead & Profit 10% 17,425.64
F Harga Satuan Pekerjaan (D+E) 191,682.03

Pemasangan 1 m pasang list gypsum langit-langit


Kode AHSP = 4.5.1.T5
A TENAGA
Pekerja plafond C13 OH 0.06 80,000.00 4,800.00
Tukang plafond C25 OH 0.06 125,000.00 7,500.00
Mandor plafond C42 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 13,380.00
B BAHAN
List Profil Gypsum C294 m’ 1.05 20,000.00 21,000.00
Tepung Gypsum C403 Lembar 0.15 4,000.00 600.00

JUMLAH HARGA BAHAN 21,600.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 34,980.00
E Overhead & Profit 10% 3,498.00
F Harga Satuan Pekerjaan (D+E) 38,478.00

Pemasangan 1 m atap genteng palentong kecil


Kode AHSP = 4.5.2.1
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12000
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Kayu C19 OH 0.075 125,000.00 9,375.00
Kepala tukang C39 OH 0.0075 150,000.00 1,125.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,460.00
B BAHAN
Genteng palentong C225 Bh 25 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,460.00
E Overhead & Profit 10% 2,346.00
F Harga Satuan Pekerjaan (D+E) 25,806.00

Pemasangan 1 m2 atap genteng kodok glazuur


Kode AHSP = 4.5.2.2
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Tukang Kayu C19 OH 0.075 125,000.00 9,375.00
Kepala tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,535.00
B BAHAN
Genteng kodok C226 Bh 25 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,535.00
E Overhead & Profit 10% 2,353.50
F Harga Satuan Pekerjaan (D+E) 25,888.50

Pemasangan 1 m2 atap genteng palentong besar/morando


Kode AHSP = 4.5.2.3
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Tukang Kayu C19 OH 0.075 125,000.00 9,375.00
Kepala tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,535.00
B BAHAN
Genteng kodok C226 Bh 12 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,535.00
E Overhead & Profit 10% 2,353.50
F Harga Satuan Pekerjaan (D+E) 25,888.50

Pemasangan 1 m’ bubung genteng palentong kecil


Kode AHSP = 4.5.2.4
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang Kayu C19 OH 0.2 125,000.00 25,000.00
Kepala tukang C39 OH 0.02 150,000.00 3,000.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 60,240.00
B BAHAN
Genteng bubung C227 Bh 5 - -
Semen Portland C363 Kg 8 1,300.00 10,400.00
Pasir pasang C99 M3 0.032 100,000.00 3,200.00
JUMLAH HARGA BAHAN 13,600.00
C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 73,840.00
E Overhead & Profit 10% 7,384.00
F Harga Satuan Pekerjaan (D+E) 81,224.00

Pemasangan 1 m’ bubung genteng kodok glazuur


Kode AHSP = 4.5.2.5
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang Kayu C19 OH 0.2 125,000.00 25,000.00
Kepala tukang C39 OH 0.02 150,000.00 3,000.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 60,240.00
B BAHAN
Genteng bubung C227 Bh 5 - -
Semen Portland C363 Kg 8 1,300.00 10,400.00
Pasir pasang C99 M3 0.032 100,000.00 3,200.00
JUMLAH HARGA BAHAN 13,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 73,840.00
E Overhead & Profit 10% 7,384.00
F Harga Satuan Pekerjaan (D+E) 81,224.00

Pemasangan 1 m’ bubung genteng palentong besar


Kode AHSP = 4.5.2.6
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang Kayu C19 OH 0.2 125,000.00 25,000.00
Kepala tukang C39 OH 0.02 150,000.00 3,000.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 60,240.00
B BAHAN
Genteng bubung m3 Bh 4 - -
Semen Portland kg Kg 8 1,300.00 10,400.00
Pasir pasang kg M3 0.032 100,000.00 3,200.00
JUMLAH HARGA BAHAN 13,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 73,840.00
E Overhead & Profit 10% 7,384.00
F Harga Satuan Pekerjaan (D+E) 81,224.00

Pemasangan 1 m2 roof light fibreglass 90 cm x180 cm


Kode AHSP = 4.5.2.7
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.067 125,000.00 8,375.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,465.00
B BAHAN
Rooflight 90x180 C231 Lbr 0.6 - -
Paku biasa ½”-1” C320 Kg 0.05 21,000.00 1,050.00
JUMLAH HARGA BAHAN 1,050.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 22,515.00
E Overhead & Profit 10% 2,251.50
F Harga Satuan Pekerjaan (D+E) 24,766.50

Pemasangan 1 m2 atap serat semen gelombang 92cm x 250cm x 5mm


Kode AHSP = 4.5.2.8
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Kayu C19 OH 0.075 125,000.00 9,375.00
Kepala tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 22,735.00
B BAHAN
Serat semen gel 92x250 C373 Lbr 0.5 1.00 0.50
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.62
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 22,735.62
E Overhead & Profit 10% 2,273.56
F Harga Satuan Pekerjaan (D+E) 25,009.18

Pemasangan 1 m2 atap serat semen gelombang 92cm x 225cm x 5mm


Kode AHSP = 4.5.2.9
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.075 125,000.00 9,375.00
Kepala tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 22,735.00
B BAHAN
Serat semen gel 92x250 C373 Lbr 0.6 1.00 0.60
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.72
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 22,735.72
E Overhead & Profit 10% 2,273.57
F Harga Satuan Pekerjaan (D+E) 25,009.29

Pemasangan 1 m2 atap serat semen gelombang 92cm x 200cm x 5mm


Kode AHSP = 4.5.2.10
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 92x200 C374 m3 70 1.00 70.00
Paku pancing 6x23 C326 Kg 9.68 1.00 9.68
JUMLAH HARGA BAHAN 79.68
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,919.68
E Overhead & Profit 10% 2,191.97
F Harga Satuan Pekerjaan (D+E) 24,111.65

Pemasangan 1 m2 atap serat semen gelombang 92cm x 180cm x 5mm


Kode AHSP = 4.5.2.11
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 92x180 C375 Lbr 0.75 1.00 0.75
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.87
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.87
E Overhead & Profit 10% 2,184.09
F Harga Satuan Pekerjaan (D+E) 24,024.96

Pemasangan 1 m2 atap serat semen gelombang 105cm x 300cm x 5mm


Kode AHSP = 4.5.2.12
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 105x300 C376 Lbr 0.35 1.00 0.35
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.47
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.47
E Overhead & Profit 10% 2,184.05
F Harga Satuan Pekerjaan (D+E) 24,024.52

Pemasangan 1 m2 atap serat semen gelombang 105cm x 270cm x 5mm


Kode AHSP = 4.5.2.15
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 105x270 C379 Lbr 0.4 1.00 0.40
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.52
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.52
E Overhead & Profit 10% 2,184.05
F Harga Satuan Pekerjaan (D+E) 24,024.57

Pemasangan 1 m2 atap serat semen gelombang 105cm x 240cm x 5mm


Kode AHSP = 4.5.2.16
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 105x240 C377 Lbr 0.44 1.00 0.44
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.56
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.56
E Overhead & Profit 10% 2,184.06
F Harga Satuan Pekerjaan (D+E) 24,024.62

Pemasangan 1 m2 atap serat semen gelombang 105cm x 210cm x 5mm


Kode AHSP = 4.5.2.17
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 105x210 C380 Lbr 0.51 1.00 0.51
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.63
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.63
E Overhead & Profit 10% 2,184.06
F Harga Satuan Pekerjaan (D+E) 24,024.69

Pemasangan 1 m2 atap serat semen gelombang 105cm x 150cm x 5mm


Kode AHSP = 4.5.2.18
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 105x150 C381 Lbr 0.8 1.00 0.80
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.92
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.92
E Overhead & Profit 10% 2,184.09
F Harga Satuan Pekerjaan (D+E) 24,025.01

Pemasangan 1 m2 atap serat semen gelombang 108cm x 300cm x 6mm


Kode AHSP = 4.5.2.19
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 108x300 C382 Lbr 0.37 1.00 0.37
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.49
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.49
E Overhead & Profit 10% 2,184.05
F Harga Satuan Pekerjaan (D+E) 24,024.54

Pemasangan 1 m2 atap serat semen gelombang 108cm x 270cm x 6mm


Kode AHSP = 4.5.2.20
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 108x270 C383 Lbr 0.38 1.00 0.38
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.50
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.50
E Overhead & Profit 10% 2,184.05
F Harga Satuan Pekerjaan (D+E) 24,024.55

Pemasangan 1 m2 atap serat semen gelombang 108cm x 240cm x 6mm


Kode AHSP = 4.5.2.21
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 108x240 C384 Lbr 0.46 1.00 0.46
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.58
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.58
E Overhead & Profit 10% 2,184.06
F Harga Satuan Pekerjaan (D+E) 24,024.64

Pemasangan 1 m2 atap serat semen gelombang 108cm x 210cm x 6mm


Kode AHSP = 4.5.2.22
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 108x210 C385 Lbr 0.49 1.00 0.49
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.61
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.61
E Overhead & Profit 10% 2,184.06
F Harga Satuan Pekerjaan (D+E) 24,024.67

Pemasangan 1 m2 atap serat semen gelombang 108cm x 180cm x 6mm


Kode AHSP = 4.5.2.23
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 108x180 C386 Lbr 0.57 1.00 0.57
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.69
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.69
E Overhead & Profit 10% 2,184.07
F Harga Satuan Pekerjaan (D+E) 24,024.76

Pemasangan 1 m’ Nok/Bubung stel gelombang 92cm


Kode AHSP = 4.5.2.24
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Bubung stel gel. C230 Lbr 2.4 - -
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 6.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,781.00
E Overhead & Profit 10% 2,478.10
F Harga Satuan Pekerjaan (D+E) 27,259.10

Pemasangan 1 m’ Nok/Bubung stel gelombang 105cm


Kode AHSP = 4.5.2.25
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Bubung stel gel. C230 Lbr 2.1 - -
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 6.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,781.00
E Overhead & Profit 10% 2,478.10
F Harga Satuan Pekerjaan (D+E) 27,259.10

Pemasangan 1 m’ Nok/Bubung stel gelombang 108cm


Kode AHSP = 4.5.2.26
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Bubung stel gel. C230 Lbr 2 - -
Paku skrup 3,5” C325 Kg 8 1.00 8.00
JUMLAH HARGA BAHAN 8.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,783.00
E Overhead & Profit 10% 2,478.30
F Harga Satuan Pekerjaan (D+E) 27,261.30

Pemasangan 1 m’ Nok/Bubung paten (Permanen) 92cm


Kode AHSP = 4.5.2.27
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Nok paten 92cm C308 Lbr 1.1 1.00 1.10
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 7.10
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,782.10
E Overhead & Profit 10% 2,478.21
F Harga Satuan Pekerjaan (D+E) 27,260.31

Pemasangan 1 m’ Nok/Bubung paten (Permanen) 105cm


Kode AHSP = 4.5.2.28
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Nok paten 105cm C309 Lbr 1.2 1.00 1.20
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 7.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,782.20
E Overhead & Profit 10% 2,478.22
F Harga Satuan Pekerjaan (D+E) 27,260.42

Pemasangan 1 m’ Nok/Bubung paten (Permanen)108cm


Kode AHSP = 4.5.2.29
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Nok paten 108cm C310 Lbr 1.2 1.00 1.20
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 7.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,782.20
E Overhead & Profit 10% 2,478.22
F Harga Satuan Pekerjaan (D+E) 27,260.42

Pemasangan 1 m’ nok/bubung stel rata 92cm


Kode AHSP = 4.5.2.30
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang Kayu C19 OH 0.15 125,000.00 18,750.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 29,180.00
B BAHAN
Nok setel rata 92cm C312 Lbr 1.1 1.00 1.10
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 7.10
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 29,187.10
E Overhead & Profit 10% 2,918.71
F Harga Satuan Pekerjaan (D+E) 32,105.81

Pemasangan 1 m’ nok/bubung stel rata 105cm


Kode AHSP = 4.5.2.31
A TENAGA
Pekerja C9 OH 0.084 80,000.00 6,720.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang Kayu C19 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 24,775.00
B BAHAN
Nok setel rata 105cm C314 Lbr 1.1 1.00 1.10
Paku skrup 3,5” C325 Bh 6 1.00 6.00
JUMLAH HARGA BAHAN 7.10
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24,782.10
E Overhead & Profit 10% 2,478.21
F Harga Satuan Pekerjaan (D+E) 27,260.31

Pemasangan 1 m2 atap genteng beton


Kode AHSP = 4.5.2.32
A TENAGA
Pekerja C9 OH 0.2 80,000.00 16,000.00
Tukang Kayu C19 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Genteng beton C228 Bh 11 - -
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.03 21,000.00 630.00
JUMLAH HARGA BAHAN 630.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 31,830.00
E Overhead & Profit 10% 3,183.00
F Harga Satuan Pekerjaan (D+E) 35,013.00

Pemasangan 1 m2 atap genteng aspal 80x100cm


Kode AHSP = 4.5.2.33
A TENAGA
Pekerja C9 OH 0.2 80,000.00 16,000.00
Tukang Kayu C19 OH 0.3 125,000.00 37,500.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 55,150.00
B BAHAN
Genteng aspal C229 Lbr 1.5 - -
Plywood 6 mm C349 Kg 0.3 1.00 0.30
Paku biasa ½”-1” C320 Lbr 0.03 21,000.00 630.00
Plastic aerator C341 Kg 0.5 1.00 0.50
JUMLAH HARGA BAHAN 630.80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 55,780.80
E Overhead & Profit 10% 5,578.08
F Harga Satuan Pekerjaan (D+E) 61,358.88

Pemasangan 1 m2 atap genteng metal


Kode AHSP = 4.5.2.34
A TENAGA
Pekerja C9 OH 0.2 80,000.00 16,000.00
Tukang Kayu C19 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 30,120.00
B BAHAN
Genteng metal C136 Bh 1.02 60,000.00 61,200.00
Paku biasa ½”-1” C320 Kg 0.2 21,000.00 4,200.00
JUMLAH HARGA BAHAN 65,400.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 95,520.00
E Overhead & Profit 10% 9,552.00
F Harga Satuan Pekerjaan (D+E) 105,072.00

Pemasangan 1 m2 atap sirap kayu


Kode AHSP = 4.5.2.35
A TENAGA
Pekerja C9 OH 0.166 80,000.00 13,280.00
Tukang Kayu C19 OH 0.25 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 49,240.00
B BAHAN
Atap Sirap kayu C132 Bh 30 12,000.00 360,000.00
Paku biasa ½”-1” C320 Kg 0.2 21,000.00 4,200.00
JUMLAH HARGA BAHAN 364,200.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 413,440.00
E Overhead & Profit 10% 41,344.00
F Harga Satuan Pekerjaan (D+E) 454,784.00

Pemasangan 1 m’ nok/bubung genteng beton


Kode AHSP = 4.5.2.36
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang Kayu C19 OH 0.2 125,000.00 25,000.00
Kepala tukang C39 OH 0.02 150,000.00 3,000.00
Mandor C47 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 62,400.00
B BAHAN
Nok genteng beton C311 Bh 3.5 1.00 3.50
Paku biasa ½”-1” C320 Kg 0.05 21,000.00 1,050.00
Semen Portland C363 Kg 10.8 1,300.00 14,040.00
Pasir pasang C99 M3 0.032 100,000.00 3,200.00
Semen warna C365 Kg 1 20,700.00 20,700.00
JUMLAH HARGA BAHAN 38,993.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 101,393.50
E Overhead & Profit 10% 10,139.35
F Harga Satuan Pekerjaan (D+E) 111,532.85

Pemasangan 1 m’ nok/bubung genteng aspal


Kode AHSP = 4.5.2.37
A TENAGA
Pekerja C9 OH 0.125 80,000.00 10,000.00
Tukang Kayu C19 OH 0.25 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 45,720.00
B BAHAN
Nok genteng aspal C313 Bh 2 1.00 2.00
Paku biasa ½”-1” C320 Kg 0.05 21,000.00 1,050.00
Kayu balok borneo C79 M3 0.0035 1,900,000.00 6,650.00
JUMLAH HARGA BAHAN 7,702.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 53,422.00
E Overhead & Profit 10% 5,342.20
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 58,764.20

Pemasangan 1 m’ nok/bubung genteng metal


Kode AHSP = 4.5.2.38
A TENAGA
Pekerja C9 OH 0.25 80,000.00 20,000.00
Tukang Kayu C19 OH 0.15 125,000.00 18,750.00
Kepala tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 42,560.00
B BAHAN
Nok genteng metal C307 Bh 1.1 34,200.00 37,620.00
Paku biasa ½”-1” C320 Kg 0.05 21,000.00 1,050.00
JUMLAH HARGA BAHAN 38,670.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 81,230.00
E Overhead & Profit 10% 8,123.00
F Harga Satuan Pekerjaan (D+E) 89,353.00

Pemasangan 1 m’ nok/bubung atap sirap


Kode AHSP = 4.5.2.39
A TENAGA
Pekerja C9 OH 0.125 80,000.00 10,000.00
Tukang Kayu C19 OH 0.25 125,000.00 31,250.00
Kepala tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 45,720.00
B BAHAN
Seng plat 3 x 6” C371 Lbr 0.4 1.00 0.40
Paku biasa ½”-1” C320 Kg 0.05 21,000.00 1,050.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.05 21,000.00 1,050.00
JUMLAH HARGA BAHAN 2,100.40
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 47,820.40
E Overhead & Profit 10% 4,782.04
F Harga Satuan Pekerjaan (D+E) 52,602.44

Pemasangan 1 m2 atap seng gelombang 105x180 cm


Kode AHSP = 4.5.2.40
A TENAGA
Pekerja C9 OH 0.12 80,000.00 9,600.00
Tukang Kayu C19 OH 0.06 125,000.00 7,500.00
Kepala tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 18,720.00
B BAHAN
Seng gel 3”x6” C369 Lbr 0.7 1.00 0.70
Paku biasa ½”-1” C320 Kg 0.02 21,000.00 420.00
JUMLAH HARGA BAHAN 420.70
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 19,140.70
E Overhead & Profit 10% 1,914.07
F Harga Satuan Pekerjaan (D+E) 21,054.77

Pemasangan 1 m’nok/bubung atap seng


Kode AHSP = 4.5.2.41
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.006 120,000.00 720.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 22,520.00
B BAHAN
Seng plat 3”x6”bjls28 C372 Lbr 0.3 1.00 0.30
Paku biasa ½”-1” C320 Kg 0.04 21,000.00 840.00
JUMLAH HARGA BAHAN 840.30
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,360.30
E Overhead & Profit 10% 2,336.03
F Harga Satuan Pekerjaan (D+E) 25,696.33

Pemasangan 1 m2 atap alumunium gelombang 95x180cm


Kode AHSP = 4.5.2.42
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 22,520.00
B BAHAN
Almn gel tbl0,55 C485 Lbr 0.75 - -
Paku hak panj 15cm C321 Kg 0.02 21,000.00 420.00
JUMLAH HARGA BAHAN 420.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 22,940.00
E Overhead & Profit 10% 2,294.00
F Harga Satuan Pekerjaan (D+E) 25,234.00

Pemasangan 1 m’ nok/bubung atap alumunium gelombang


Kode AHSP = 4.5.2.43
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang Kayu C19 OH 1 125,000.00 125,000.00
Kepala tukang C39 OH 0.1 150,000.00 15,000.00
Mandor C47 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 154,000.00
B BAHAN
Nok standar 40x18 C315 Lbr 1.2 1.00 1.20
Paku hak panj 15cm C321 Kg 0.04 21,000.00 840.00
JUMLAH HARGA BAHAN 841.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 154,841.20
E Overhead & Profit 10% 15,484.12
F Harga Satuan Pekerjaan (D+E) 170,325.32

Pemasangan 1 m2 lapisan alumunium foil


Kode AHSP = 4.5.2.44
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Tukang Kayu C19 OH 0.05 125,000.00 6,250.00
Kepala tukang C39 OH 0.005 150,000.00 750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 19,960.00
B BAHAN
Allumunium Foil C486 m2 1.05 - -

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 19,960.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 1,996.00
F Harga Satuan Pekerjaan (D+E) 21,956.00

Pemasangan 1 m2 atap serat semen gelombang 105cm x 270cm x 4mm


Kode AHSP = 4.5.2.45
A TENAGA
Pekerja C9 OH 0.14 80,000.00 11,200.00
Tukang Kayu C19 OH 0.07 125,000.00 8,750.00
Kepala tukang C39 OH 0.007 150,000.00 1,050.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 21,840.00
B BAHAN
Serat semen gel 105x270 C379 Lbr 0.42 1.00 0.42
Paku pancing 6x23 C326 Kg 0.12 1.00 0.12
JUMLAH HARGA BAHAN 0.12
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 21,840.12
E Overhead & Profit 10% 2,184.01
F Harga Satuan Pekerjaan (D+E) 24,024.13
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 Atap Genteng Metal + Rangka Baja Ringan
Kode AHSP = 4.5.2.T1
A TENAGA
Pekerja Atap C14 OH 0.247 80,000.00 19,760.00
Tukang Atap C23 OH 0.176 125,000.00 22,000.00
Mandor Atap C43 OH 0.1287 125,000.00 16,087.50
JUMLAH TENAGA KERJA 57,847.50
B BAHAN
Smartruss C 75.100 C653 M2 2.1 22,500.00 47,250.00
Reng R 32-0,45 C644 M2 3.5 11,283.33 39,491.67
Self Drilling Screw dia-10x16mm (truss screw) C650 M2 15 180.00 2,700.00
Self Drilling Screw dia-10x40mm (Roof Button Screw) C652 M2 25 420.00 10,500.00
Genteng Metal Soka C223 M2 1 62,279.41 62,279.41
JUMLAH HARGA BAHAN 162,221.08
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 220,068.58
E Overhead & Profit 10% 22,006.86
F Harga Satuan Pekerjaan (D+E) 242,075.44

1 m2 Pasang Rangka kuda-kuda baja Ringan (C75.100) + Reng


Kode AHSP = 4.5.2.T2
A TENAGA
Pekerja Atap C14 OH 0.247 80,000.00 19,760.00
Tukang Atap C23 OH 0.176 125,000.00 22,000.00
Mandor Atap C43 OH 0.117 125,000.00 14,625.00
JUMLAH TENAGA KERJA 56,385.00
B BAHAN
Smartruss C 75.100 C653 M 2.8 22,500.00 63,000.00
Reng R 32-0,45 C644 M 5.1 11,283.33 57,545.00
Self Drilling Screw dia-10x40mm (Roof Button Screw) C652 M 25 420.00 10,500.00
Atap Bitumen (Onduline) C135 M 168,000.00 -
JUMLAH HARGA BAHAN 131,045.00
C PERALATAN
Alat Bantu Mesin Bor Listrik (2% nilai material) Ls 1.000 2,620.90 2,620.90

JUMLAH HARGA ALAT 2,620.90


D Jumlah (A+B+C) 190,050.90
E Overhead & Profit 10% 19,005.09
F Harga Satuan Pekerjaan (D+E) 209,055.99

1 m2 Pasang Penutup Atap Bitumen (Onduline)


Kode AHSP = 4.5.2.T3
A TENAGA
Pekerja Atap C14 OH 0.14 80,000.00 11,200.00
Tukang Atap C23 OH 0.07 125,000.00 8,750.00
Kepala Tukang C39 OH 0.007 150,000.00 1,050.00
Mandor Atap C43 OH 0.007 125,000.00 875.00
JUMLAH TENAGA KERJA 21,875.00
B BAHAN
Self Drilling Screw dia-10x16mm (roof screw) Bitumen C651 Bh 11.465 1,200.00 13,758.00
Atap Bitumen (Onduline) C135 Lbr 0.732 168,000.00 122,976.00
JUMLAH HARGA BAHAN 136,734.00
C PERALATAN
Alat Bantu Mesin Bor Listrik (2% nilai material) Ls 1.000 2,734.68 2,734.68

JUMLAH HARGA ALAT 2,734.68


D Jumlah (A+B+C) 161,343.68
E Overhead & Profit 10% 16,134.37
F Harga Satuan Pekerjaan (D+E) 177,478.05

1 m2 Pasang Penutup Atap Genteng Metal


Kode AHSP = 4.5.2.T4
A TENAGA
Pekerja Atap C14 OH 0.14 80,000.00 11,200.00
Tukang Atap C23 OH 0.07 125,000.00 8,750.00
Kepala Tukang C39 OH 0.007 150,000.00 1,050.00
Mandor Atap C43 OH 0.007 125,000.00 875.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 21,875.00
B BAHAN
Self Drilling Screw dia-10x16mm (roof screw) Bitumen C651 Bh 11.465 1,200.00 13,758.00
Genteng Metal C136 Lbr 0.732 60,000.00 43,920.00
Smartruss C 75.100 C653 M 2.8 22,500.00 63,000.00
Reng R 32-0,45 C644 M 5.1 11,283.33 57,545.00
Self Drilling Screw dia-10x40mm (Roof Button Screw) C652 M 25 420.00 10,500.00
JUMLAH HARGA BAHAN 188,723.00
C PERALATAN
Alat Bantu Mesin Bor Listrik (2% nilai material) Ls 1.000 1,153.56 1,153.56

JUMLAH HARGA ALAT 1,153.56


D Jumlah (A+B+C) 211,751.56
E Overhead & Profit 10% 21,175.16
F Harga Satuan Pekerjaan (D+E) 232,926.72

Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Kode AHSP = 4.6.1.1
A TENAGA
Pekerja C9 OH 7.000 80,000.00 560,000.00
Tukang Kayu C19 OH 21.000 125,000.00 2,625,000.00
Kepala Tukang C39 OH 2.100 150,000.00 315,000.00
Mandor C47 OH 0.350 120,000.00 42,000.00
JUMLAH TENAGA KERJA 3,542,000.00
B BAHAN
Balok Kayu Kelas I C66 M3 1.100 4,000,000.00 4,400,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 1.250 21,000.00 26,250.00
Lem kayu C292 Kg 1.000 32,500.00 32,500.00

JUMLAH HARGA BAHAN 4,458,750.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,000,750.00
E Overhead & Profit 10% 800,075.00
F Harga Satuan Pekerjaan (D+E) 8,800,825.00

Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Kode AHSP = 4.6.1.2
A TENAGA
Pekerja C9 OH 6.000 80,000.00 480,000.00
Tukang Kayu C19 OH 18.000 125,000.00 2,250,000.00
Kepala Tukang C39 OH 1.800 150,000.00 270,000.00
Mandor C47 OH 0.300 120,000.00 36,000.00
JUMLAH TENAGA KERJA 3,036,000.00
B BAHAN
Balok Kayu Kelas II C67 M3 1.200 2,250,000.00 2,700,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 1.250 21,000.00 26,250.00
Lem kayu C292 Kg 1.000 32,500.00 32,500.00

JUMLAH HARGA BAHAN 2,758,750.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,794,750.00
E Overhead & Profit 10% 579,475.00
F Harga Satuan Pekerjaan (D+E) 6,374,225.00

Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II


Kode AHSP = 4.6.1.3
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang Kayu C19 OH 1.050 125,000.00 131,250.00
Kepala Tukang C39 OH 0.105 150,000.00 15,750.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 177,160.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Papan kayu kelas II C95 M3 0.040 2,100,000.00 84,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.050 21,000.00 1,050.00

JUMLAH HARGA BAHAN 85,050.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 262,210.00
E Overhead & Profit 10% 26,221.00
F Harga Satuan Pekerjaan (D+E) 288,431.00

Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III


Kode AHSP = 4.6.1.4
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang Kayu C19 OH 1.050 125,000.00 131,250.00
Kepala Tukang C39 OH 0.105 150,000.00 15,750.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 177,160.00
B BAHAN
Papan kayu kelas III C96 M3 0.040 1,600,000.00 64,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.050 21,000.00 1,050.00

JUMLAH HARGA BAHAN 65,050.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 242,210.00
E Overhead & Profit 10% 24,221.00
F Harga Satuan Pekerjaan (D+E) 266,431.00

Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II


Kode AHSP = 4.6.1.5
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 3.000 125,000.00 375,000.00
Kepala Tukang C39 OH 0.300 150,000.00 45,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 506,000.00
B BAHAN
Papan kayu kelas I C94 M3 0.040 4,000,000.00 160,000.00
Lem kayu C292 Kg 0.500 32,500.00 16,250.00

JUMLAH HARGA BAHAN 176,250.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 682,250.00
E Overhead & Profit 10% 68,225.00
F Harga Satuan Pekerjaan (D+E) 750,475.00

Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
Kode AHSP = 4.6.1.6
A TENAGA
Pekerja C9 OH 0.800 80,000.00 64,000.00
Tukang Kayu C19 OH 2.400 125,000.00 300,000.00
Kepala Tukang C39 OH 0.240 150,000.00 36,000.00
Mandor C47 OH 0.040 120,000.00 4,800.00
JUMLAH TENAGA KERJA 404,800.00
B BAHAN
Papan kayu kelas I C94 M3 0.024 4,000,000.00 96,000.00
Lem kayu C292 Kg 0.300 32,500.00 9,750.00

JUMLAH HARGA BAHAN 105,750.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 510,550.00
E Overhead & Profit 10% 51,055.00
F Harga Satuan Pekerjaan (D+E) 561,605.00

Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
Kode AHSP = 4.6.1.7
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 3.000 125,000.00 375,000.00
Kepala Tukang C39 OH 0.300 150,000.00 45,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 506,000.00
B BAHAN
Papan kayu kelas I C94 M3 0.064 4,000,000.00 256,000.00
Lem kayu C292 Kg 0.500 32,500.00 16,250.00

JUMLAH HARGA BAHAN 272,250.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 778,250.00
E Overhead & Profit 10% 77,825.00
F Harga Satuan Pekerjaan (D+E) 856,075.00

Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
Kode AHSP = 4.6.1.8
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Kayu C19 OH 2.100 125,000.00 262,500.00
Kepala Tukang C39 OH 0.210 150,000.00 31,500.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 354,200.00
B BAHAN
Papan kayu kelas II C95 m3 0.025 2,100,000.00 52,500.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.030 24,000.00 720.00
Lem kayu C292 Kg 0.500 32,500.00 16,250.00
Plywood tebal 4 mm (90 x 220cm) C436 Lembar 1.000 84,000.00 84,000.00

JUMLAH HARGA BAHAN 153,470.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 507,670.00
E Overhead & Profit 10% 50,767.00
F Harga Satuan Pekerjaan (D+E) 558,437.00

Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II


Kode AHSP = 4.6.1.9
A TENAGA
Pekerja C9 OH 0.800 80,000.00 64,000.00
Tukang Kayu C19 OH 2.400 125,000.00 300,000.00
Kepala Tukang C39 OH 0.240 150,000.00 36,000.00
Mandor C47 OH 0.040 120,000.00 4,800.00
JUMLAH TENAGA KERJA 404,800.00
B BAHAN
Papan kayu kelas I C94 m3 0.026 4,000,000.00 102,400.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.030 24,000.00 720.00
Lem kayu C292 Kg 0.500 32,500.00 16,250.00
Plywood tebal 4 mm (90 x 220cm) C436 Lembar 1.000 84,000.00 84,000.00

JUMLAH HARGA BAHAN 203,370.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 608,170.00
E Overhead & Profit 10% 60,817.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 668,987.00

Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II


Kode AHSP = 4.6.1.10
A TENAGA
Pekerja C9 OH 0.670 80,000.00 53,600.00
Tukang Kayu C19 OH 2.000 125,000.00 250,000.00
Kepala Tukang C39 OH 0.200 150,000.00 30,000.00
Mandor C47 OH 0.335 120,000.00 40,200.00
JUMLAH TENAGA KERJA 373,800.00
B BAHAN
Papan kayu kelas I C94 m3 0.060 4,000,000.00 240,000.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.150 24,000.00 3,600.00

JUMLAH HARGA BAHAN 243,600.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 617,400.00
E Overhead & Profit 10% 61,740.00
F Harga Satuan Pekerjaan (D+E) 679,140.00

Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I


Kode AHSP = 4.6.1.11
A TENAGA
Pekerja C9 OH 0.800 80,000.00 64,000.00
Tukang Kayu C19 OH 2.400 125,000.00 300,000.00
Kepala Tukang C39 OH 0.240 150,000.00 36,000.00
Mandor C47 OH 0.040 120,000.00 4,800.00
JUMLAH TENAGA KERJA 404,800.00
B BAHAN
Papan kayu kelas I C94 m3 0.025 4,000,000.00 100,000.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.030 24,000.00 720.00
Lem kayu C292 Kg 0.300 32,500.00 9,750.00
Teakwood 4 mm (90 x 220 cm) C438 Lembar 1.000 108,000.00 108,000.00

JUMLAH HARGA BAHAN 218,470.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 623,270.00
E Overhead & Profit 10% 62,327.00
F Harga Satuan Pekerjaan (D+E) 685,597.00

Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II


Kode AHSP = 4.6.1.12
A TENAGA
Pekerja C9 OH 0.850 80,000.00 68,000.00
Tukang Kayu C19 OH 2.550 125,000.00 318,750.00
Kepala Tukang C39 OH 0.255 150,000.00 38,250.00
Mandor C47 OH 0.043 120,000.00 5,160.00
JUMLAH TENAGA KERJA 430,160.00
B BAHAN
Papan kayu kelas II C95 m3 0.025 2,100,000.00 52,500.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.030 24,000.00 720.00
Lem kayu C292 Kg 0.800 32,500.00 26,000.00
Teakwood 4 mm (90 x 220 cm) C438 Lembar 1.000 108,000.00 108,000.00
High Laminate Pressure (HPL) C255 Lembar 0.500 85,382.51 42,691.26

JUMLAH HARGA BAHAN 229,911.26


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 660,071.26
E Overhead & Profit 10% 66,007.13
F Harga Satuan Pekerjaan (D+E) 726,078.38

Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = 4.6.1.13
A TENAGA
Pekerja C9 OH 4.000 80,000.00 320,000.00
Tukang Kayu C19 OH 12.000 125,000.00 1,500,000.00
Kepala Tukang C39 OH 1.200 150,000.00 180,000.00
Mandor C47 OH 0.200 120,000.00 24,000.00
JUMLAH TENAGA KERJA 2,024,000.00
B BAHAN
Balok Kayu Kelas I C66 m3 1.100 4,000,000.00 4,400,000.00
Besi Strip Tebal 5 mm C430 Kg 15.000 12,000.00 180,000.00
Paku biasa 12cm C435 Kg 5.600 30,000.00 168,000.00

JUMLAH HARGA BAHAN 4,748,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 6,772,000.00
E Overhead & Profit 10% 677,200.00
F Harga Satuan Pekerjaan (D+E) 7,449,200.00

Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I


Kode AHSP = 4.6.1.14
A TENAGA
Pekerja C9 OH 6.700 80,000.00 536,000.00
Tukang Kayu C19 OH 20.100 125,000.00 2,512,500.00
Kepala Tukang C39 OH 2.010 150,000.00 301,500.00
Mandor C47 OH 0.335 120,000.00 40,200.00
JUMLAH TENAGA KERJA 3,390,200.00
B BAHAN
Balok Kayu Kelas I C66 m3 1.200 4,000,000.00 4,800,000.00
Besi Strip Tebal 5 mm C430 Kg 15.000 12,000.00 180,000.00
Paku biasa 12cm C435 Kg 5.600 30,000.00 168,000.00

JUMLAH HARGA BAHAN 5,148,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,538,200.00
E Overhead & Profit 10% 853,820.00
F Harga Satuan Pekerjaan (D+E) 9,392,020.00

Pemasangan 1 m3 konstruksi gordeng, kayu kelas II


Kode AHSP = 4.6.1.15
A TENAGA
Pekerja C9 OH 2.400 80,000.00 192,000.00
Tukang Kayu C19 OH 7.200 125,000.00 900,000.00
Kepala Tukang C39 OH 0.720 150,000.00 108,000.00
Mandor C47 OH 0.120 120,000.00 14,400.00
JUMLAH TENAGA KERJA 1,214,400.00
B BAHAN
Balok Kayu Kelas II C67 m3 1.100 2,250,000.00 2,475,000.00
Besi Strip Tebal 5 mm C430 Kg 15.000 12,000.00 180,000.00
Paku biasa 12cm C435 Kg 3.000 30,000.00 90,000.00

JUMLAH HARGA BAHAN 2,745,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,959,400.00
E Overhead & Profit 10% 395,940.00
F Harga Satuan Pekerjaan (D+E) 4,355,340.00

Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II


Kode AHSP = 4.6.1.16
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Kayu Kaso 5/7 Kelas II C83 m3 0.014 2,100,000.00 29,400.00
Kayu Reng 2/3 Kelas II C84 m3 0.004 2,100,000.00 7,560.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.250 21,000.00 5,250.00

JUMLAH HARGA BAHAN 42,210.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 64,810.00
E Overhead & Profit 10% 6,481.00
F Harga Satuan Pekerjaan (D+E) 71,291.00

Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II


Kode AHSP = 4.6.1.17
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Kayu Kaso 5/7 Kelas II C83 m3 0.014 2,100,000.00 29,400.00
Kayu Reng 3/4 Kelas II C85 m3 0.006 2,100,000.00 11,970.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.250 21,000.00 5,250.00

JUMLAH HARGA BAHAN 46,620.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 69,220.00
E Overhead & Profit 10% 6,922.00
F Harga Satuan Pekerjaan (D+E) 76,142.00

Pemasangan 1 m2 rangka atap sirap, kayu kelas II


Kode AHSP = 4.6.1.18
A TENAGA
Pekerja C9 OH 0.120 80,000.00 9,600.00
Tukang Kayu C19 OH 0.120 125,000.00 15,000.00
Kepala Tukang C39 OH 0.012 150,000.00 1,800.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 27,120.00
B BAHAN
Kayu kelas II C81 m3 0.165 2,100,000.00 346,500.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.200 21,000.00 4,200.00

JUMLAH HARGA BAHAN 350,700.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 377,820.00
E Overhead & Profit 10% 37,782.00
F Harga Satuan Pekerjaan (D+E) 415,602.00

Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
Kode AHSP = 4.6.1.19
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Kayu C19 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.030 150,000.00 4,500.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 63,000.00
B BAHAN
Kayu Kaso 5/7 Kelas II C83 m3 0.015 2,100,000.00 32,340.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.200 21,000.00 4,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 36,540.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 99,540.00
E Overhead & Profit 10% 9,954.00
F Harga Satuan Pekerjaan (D+E) 109,494.00

Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Kode AHSP = 4.6.1.20
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Kayu C19 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.030 150,000.00 4,500.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 59,200.00
B BAHAN
Kayu Kaso 5/7 Kelas II C83 m3 0.016 2,100,000.00 34,230.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.250 21,000.00 5,250.00

JUMLAH HARGA BAHAN 39,480.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 98,680.00
E Overhead & Profit 10% 9,868.00
F Harga Satuan Pekerjaan (D+E) 108,548.00

Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II


Kode AHSP = 4.6.1.21
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 36,600.00
B BAHAN
Papan kayu kelas I C94 m3 0.011 4,000,000.00 43,200.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.100 21,000.00 2,100.00

JUMLAH HARGA BAHAN 45,300.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 81,900.00
E Overhead & Profit 10% 8,190.00
F Harga Satuan Pekerjaan (D+E) 90,090.00

Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II


Kode AHSP = 4.6.1.22
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 36,600.00
B BAHAN
Papan kayu kelas I C94 m3 0.011 4,000,000.00 44,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.050 21,000.00 1,050.00

JUMLAH HARGA BAHAN 45,050.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 81,650.00
E Overhead & Profit 10% 8,165.00
F Harga Satuan Pekerjaan (D+E) 89,815.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III
Kode AHSP = 4.6.1.23
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Kayu C19 OH 0.450 125,000.00 56,250.00
Kepala Tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 75,960.00
B BAHAN
Balok Kayu Kelas II C67 m3 0.028 2,250,000.00 63,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.150 21,000.00 3,150.00

JUMLAH HARGA BAHAN 66,150.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 142,110.00
E Overhead & Profit 10% 14,211.00
F Harga Satuan Pekerjaan (D+E) 156,321.00

Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II


Kode AHSP = 4.6.1.24
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Kayu C19 OH 0.450 125,000.00 56,250.00
Kepala Tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 75,960.00
B BAHAN
Balok Kayu 6x12 Kelas II C82 m3 0.028 2,100,000.00 58,800.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.150 21,000.00 3,150.00
Teakwood 4 mm (120 x 240 cm) C439 Lembar 0.860 108,000.00 92,880.00
Lem Kayu C292 Kg 0.560 32,500.00 18,200.00

JUMLAH HARGA BAHAN 173,030.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 248,990.00
E Overhead & Profit 10% 24,899.00
F Harga Satuan Pekerjaan (D+E) 273,889.00

Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II


Kode AHSP = 4.6.1.25
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Kayu C19 OH 0.450 125,000.00 56,250.00
Kepala Tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 75,960.00
B BAHAN
Balok Kayu 6x12 Kelas II C82 m3 0.028 2,100,000.00 58,800.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.150 21,000.00 3,150.00
Plywood tebal 4 mm (120 x 240cm) C437 Lembar 0.860 84,000.00 72,240.00
Lem Kayu C292 Kg 0.560 32,500.00 18,200.00

JUMLAH HARGA BAHAN 152,390.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 228,350.00
E Overhead & Profit 10% 22,835.00
F Harga Satuan Pekerjaan (D+E) 251,185.00

Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I


Kode AHSP = 4.6.1.26
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Kayu C19 OH 1.800 125,000.00 225,000.00
Kepala Tukang C39 OH 0.180 150,000.00 27,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 303,600.00
B BAHAN
Papan kayu kelas I C94 m3 0.007 4,000,000.00 28,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.100 21,000.00 2,100.00
Paku Skrup C323 Kg 0.150 114,700.00 17,205.00

JUMLAH HARGA BAHAN 47,305.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 350,905.00
E Overhead & Profit 10% 35,090.50
F Harga Satuan Pekerjaan (D+E) 385,995.50

Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm


Kode AHSP = 4.6.1.27
A TENAGA
Pekerja C9 OH 0.025 80,000.00 2,000.00
Tukang Kayu C19 OH 0.075 125,000.00 9,375.00
Kepala Tukang C39 OH 0.008 150,000.00 1,200.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 12,695.00
B BAHAN
Plywood tebal 4 mm (120 x 240cm) C437 m3 0.400 84,000.00 33,600.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.050 24,000.00 1,200.00

JUMLAH HARGA BAHAN 34,800.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 47,495.00
E Overhead & Profit 10% 4,749.50
F Harga Satuan Pekerjaan (D+E) 52,244.50

Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV


Kode AHSP = 4.6.1.28
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.050 125,000.00 6,250.00
Kepala Tukang C39 OH 0.005 150,000.00 750.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 15,600.00
B BAHAN
Bilik Bambu C71 m2 1.500 135,000.00 202,500.00
Kayu Kaso 5/7 Kelas III C88 m3 0.014 1,600,000.00 22,400.00
Paku Biasa C318 Kg 0.012 21,000.00 252.00
List Kayu 2/4 C431 m3 0.003 3,300,000.00 9,900.00

JUMLAH HARGA BAHAN 235,052.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 250,652.00
E Overhead & Profit 10% 25,065.20
F Harga Satuan Pekerjaan (D+E) 275,717.20

Pemasangan 1 buah kunci tanam antik


Kode AHSP = 4.6.2.1
A TENAGA
Pekerja C9 OH 0.060 80,000.00 4,800.00
Tukang Kayu C19 OH 0.600 125,000.00 75,000.00
Kepala Tukang C39 OH 0.060 150,000.00 9,000.00
Mandor C47 OH 0.003 120,000.00 360.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 89,160.00
B BAHAN
Kunci Tanam Antik C574 Bh 1.000 230,000.00 230,000.00

JUMLAH HARGA BAHAN 230,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 319,160.00
E Overhead & Profit 10% 31,916.00
F Harga Satuan Pekerjaan (D+E) 351,076.00

Pemasangan 1 buah kunci tanam biasa


Kode AHSP = 4.6.2.2
A TENAGA
Pekerja C9 OH 0.010 80,000.00 800.00
Tukang Kayu C19 OH 0.500 125,000.00 62,500.00
Kepala Tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 71,400.00
B BAHAN
Kunci Tanam Biasa C677 Bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 71,401.00
E Overhead & Profit 10% 7,140.10
F Harga Satuan Pekerjaan (D+E) 78,541.10

Pemasangan 1 buah kunci kamar mandi


Kode AHSP = 4.6.2.3
A TENAGA
Pekerja C9 OH 0.005 80,000.00 400.00
Tukang Kayu C19 OH 0.500 125,000.00 62,500.00
Kepala Tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 70,760.00
B BAHAN
Kunci Tanam Kamar Mandi (Silinder) C576 Bh 1.000 185,000.00 185,000.00

JUMLAH HARGA BAHAN 185,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 255,760.00
E Overhead & Profit 10% 25,576.00
F Harga Satuan Pekerjaan (D+E) 281,336.00

Pemasangan 1 buah kunci silinder


Kode AHSP = 4.6.2.4
A TENAGA
Pekerja C9 OH 0.005 80,000.00 400.00
Tukang Kayu C19 OH 0.500 125,000.00 62,500.00
Kepala Tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 70,760.00
B BAHAN
Kunci Silinder C678 Bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 70,761.00
E Overhead & Profit 10% 7,076.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 77,837.10

Pemasangan 1 buah engsel pintu


Kode AHSP = 4.6.2.5
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.001 120,000.00 96.00
JUMLAH TENAGA KERJA 22,296.00
B BAHAN
Engsel Pintu Kupu-kupu C513 Bh 1.000 82,550.00 82,550.00

JUMLAH HARGA BAHAN 82,550.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 104,846.00
E Overhead & Profit 10% 10,484.60
F Harga Satuan Pekerjaan (D+E) 115,330.60

Pemasangan 1 buah engsel jendela kupu-kupu


Kode AHSP = 4.6.2.6
A TENAGA
Pekerja C9 OH 0.010 80,000.00 800.00
Tukang Kayu C19 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.001 120,000.00 60.00
JUMLAH TENAGA KERJA 14,860.00
B BAHAN
Engsel Jendela Kupu-kupu C512 Bh 1.000 15,800.00 15,800.00

JUMLAH HARGA BAHAN 15,800.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 30,660.00
E Overhead & Profit 10% 3,066.00
F Harga Satuan Pekerjaan (D+E) 33,726.00

Pemasangan 1 buah engsel angin


Kode AHSP = 4.6.2.7
A TENAGA
Pekerja C9 OH 0.100 80,000.00 8,000.00
Tukang Kayu C19 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.001 120,000.00 60.00
JUMLAH TENAGA KERJA 36,060.00
B BAHAN
Engsel Angin C679 Bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 36,061.00
E Overhead & Profit 10% 3,606.10
F Harga Satuan Pekerjaan (D+E) 39,667.10

Pemasangan 1 buah spring knip


Kode AHSP = 4.6.2.8
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,160.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Grandel Jendela/ Pintu (Spring Knip ) C533 Bh 1.000 35,400.00 35,400.00

JUMLAH HARGA BAHAN 35,400.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 58,560.00
E Overhead & Profit 10% 5,856.00
F Harga Satuan Pekerjaan (D+E) 64,416.00

Pemasangan 1 buah kait angin


Kode AHSP = 4.6.2.9
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,160.00
B BAHAN
Kait Angin Jendela C571 Bh 1.000 36,800.00 36,800.00

JUMLAH HARGA BAHAN 36,800.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 59,960.00
E Overhead & Profit 10% 5,996.00
F Harga Satuan Pekerjaan (D+E) 65,956.00

Pemasangan 1 buah door closer


Kode AHSP = 4.6.2.10
A TENAGA
Pekerja C9 OH 0.050 80,000.00 4,000.00
Tukang Kayu C19 OH 0.500 125,000.00 62,500.00
Kepala Tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 74,360.00
B BAHAN
Door Closer #N/A Set 1.000 #N/A #N/A

JUMLAH HARGA BAHAN #N/A


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

Pemasangan 1 buah kunci slot


Kode AHSP = 4.6.2.11
A TENAGA
Pekerja C9 OH 0.020 80,000.00 1,600.00
Tukang Kayu C19 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 29,720.00
B BAHAN
Kunci Slot C680 Bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 29,721.00
E Overhead & Profit 10% 2,972.10
F Harga Satuan Pekerjaan (D+E) 32,693.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 buah Door holder
Kode AHSP = 4.6.2.12
A TENAGA
Pekerja C9 OH 0.050 80,000.00 4,000.00
Tukang Kayu C19 OH 0.500 125,000.00 62,500.00
Kepala Tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 74,360.00
B BAHAN
Door Holder C681 Bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 74,361.00
E Overhead & Profit 10% 7,436.10
F Harga Satuan Pekerjaan (D+E) 81,797.10

Pemasangan 1 buah door stop


Kode AHSP = 4.6.2.13
A TENAGA
Pekerja C9 OH 0.010 80,000.00 800.00
Tukang Kayu C19 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 15,400.00
B BAHAN
Door Stop C507 Bh 1.000 2,500.00 2,500.00

JUMLAH HARGA BAHAN 2,500.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 17,900.00
E Overhead & Profit 10% 1,790.00
F Harga Satuan Pekerjaan (D+E) 19,690.00

Pemasangan 1 buah Rrel pintu sorong


Kode AHSP = 4.6.2.14
A TENAGA
Pekerja C9 OH 0.060 80,000.00 4,800.00
Tukang Kayu C19 OH 0.600 125,000.00 75,000.00
Kepala Tukang C39 OH 0.060 150,000.00 9,000.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 89,160.00
B BAHAN
Rel Pintu Sorong C682 Set 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 89,161.00
E Overhead & Profit 10% 8,916.10
F Harga Satuan Pekerjaan (D+E) 98,077.10

Pemasangan 1 buah kunci lemari


Kode AHSP = 4.6.2.15
A TENAGA
Pekerja C9 OH 0.025 80,000.00 2,000.00
Tukang Kayu C19 OH 0.250 125,000.00 31,250.00
Kepala Tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.001 120,000.00 156.00
JUMLAH TENAGA KERJA 37,156.00
B BAHAN
Kunci Lemari C683 Set 1.000 1.00 1.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 1.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 37,157.00
E Overhead & Profit 10% 3,715.70
F Harga Satuan Pekerjaan (D+E) 40,872.70

Pemasangan 1 m2 kaca tebal 3 mm


Kode AHSP = 4.6.2.16
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.001 120,000.00 96.00
JUMLAH TENAGA KERJA 22,296.00
B BAHAN
Kaca bening 3 mm C684 m2 1.100 1.00 1.10
Sealant C656 Kg 0.050 6,000.00 300.00

JUMLAH HARGA BAHAN 301.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 22,597.10
E Overhead & Profit 10% 2,259.71
F Harga Satuan Pekerjaan (D+E) 24,856.81

Pemasangan 1 m2 kaca tebal 5 mm


Kode AHSP = 4.6.2.17
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.001 120,000.00 96.00
JUMLAH TENAGA KERJA 22,296.00
B BAHAN
Kaca bening 5 mm C544 m2 1.100 128,000.00 140,800.00
Sealant C656 Kg 0.050 6,000.00 300.00

JUMLAH HARGA BAHAN 141,100.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 163,396.00
E Overhead & Profit 10% 16,339.60
F Harga Satuan Pekerjaan (D+E) 179,735.60

Pemasangan 1 m2 kaca tebal 8 mm


Kode AHSP = 4.6.2.18
A TENAGA
Pekerja C9 OH 0.017 80,000.00 1,360.00
Tukang Kayu C19 OH 0.170 125,000.00 21,250.00
Kepala Tukang C39 OH 0.017 150,000.00 2,550.00
Mandor C47 OH 0.001 120,000.00 108.00
JUMLAH TENAGA KERJA 25,268.00
B BAHAN
Kaca bening 8 mm C546 m2 1.100 275,000.00 302,500.00
Sealant C656 Kg 0.070 6,000.00 420.00

JUMLAH HARGA BAHAN 302,920.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 328,188.00
E Overhead & Profit 10% 32,818.80
F Harga Satuan Pekerjaan (D+E) 361,006.80
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m2 kaca buram tebal 12 mm


Kode AHSP = 4.6.2.19
A TENAGA
Pekerja C9 OH 0.025 80,000.00 2,000.00
Tukang Kayu C19 OH 0.250 125,000.00 31,250.00
Kepala Tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.001 120,000.00 156.00
JUMLAH TENAGA KERJA 37,156.00
B BAHAN
Kaca Buram 12 mm C685 m2 1.100 1.00 1.10
Sealant C656 Kg 0.070 6,000.00 420.00

JUMLAH HARGA BAHAN 421.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 37,577.10
E Overhead & Profit 10% 3,757.71
F Harga Satuan Pekerjaan (D+E) 41,334.81

Pemasangan 1 m2 kaca cermin tebal 5 mm


Kode AHSP = 4.6.2.20
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,160.00
B BAHAN
Kaca Cermin 5 mm C686 m2 1.100 1.00 1.10

JUMLAH HARGA BAHAN 1.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,161.10
E Overhead & Profit 10% 2,316.11
F Harga Satuan Pekerjaan (D+E) 25,477.21

Pemasangan 1 m2 kaca cermin tebal 8 mm


Kode AHSP = 4.6.2.21
A TENAGA
Pekerja C9 OH 0.017 80,000.00 1,360.00
Tukang Kayu C19 OH 0.170 125,000.00 21,250.00
Kepala Tukang C39 OH 0.017 150,000.00 2,550.00
Mandor C47 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 26,240.00
B BAHAN
Kaca Cermin 8 mm C687 m2 1.100 1.00 1.10

JUMLAH HARGA BAHAN 1.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 26,241.10
E Overhead & Profit 10% 2,624.11
F Harga Satuan Pekerjaan (D+E) 28,865.21

Pemasangan 1 m2 kaca wireglassed tebal 5 mm


Kode AHSP = 4.6.2.22
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 23,160.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kaca Wireglass 5 mm C543 m2 1.100 175,000.00 192,500.00

JUMLAH HARGA BAHAN 192,500.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 215,660.00
E Overhead & Profit 10% 21,566.00
F Harga Satuan Pekerjaan (D+E) 237,226.00

Pemasangan 1 m2 kaca patri tebal 5 mm


Kode AHSP = 4.6.2.23
A TENAGA
Pekerja C9 OH 0.075 80,000.00 6,000.00
Tukang Kayu C19 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 27,480.00
B BAHAN
Kaca Patri 5mm C688 m2 1.100 1.00 1.10
Sealant C656 Kg 0.050 6,000.00 300.00

JUMLAH HARGA BAHAN 301.10


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 27,781.10
E Overhead & Profit 10% 2,778.11
F Harga Satuan Pekerjaan (D+E) 30,559.21

Pemasangan 1 m2 kaca Acrylic 5mm


Kode AHSP = 4.6.2.24
A TENAGA
Pekerja C9 OH 0.015 80,000.00 1,200.00
Tukang Allumunium C26 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 22,320.00
B BAHAN
Kaca Mika/Acrylic 5mm C564 m2 1.100 520,833.33 572,916.67
Sealant C656 Kg 0.050 6,000.00 300.00

JUMLAH HARGA BAHAN 573,216.67


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 595,536.67
E Overhead & Profit 10% 59,553.67
F Harga Satuan Pekerjaan (D+E) 655,090.33

HARGA SATUAN PEKERJAAN PENGECATAN Kode AHSP = 4.7.1.


1 m2 Pengikisan/pengerokan permukaan cat lama
Kode AHSP = 4.7.1.1
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 12,960.00
B BAHAN
Sabun C361 Kg 0.05 7,500.00 375.00
JUMLAH HARGA BAHAN 375.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 13,335.00
E Overhead & Profit 10% 1,333.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 14,668.50

1 m2 Pencucian bidang permukaan tembok yang pernah dicat


Kode AHSP = 4.7.1.2
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 12,360.00
B BAHAN
Sabun C361 Kg 0.05 7,500.00 375.00
JUMLAH HARGA BAHAN 375.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 12,735.00
E Overhead & Profit 10% 1,273.50
F Harga Satuan Pekerjaan (D+E) 14,008.50

1 m2 Pengerokan karat pada permukaan baja cara manual


Kode AHSP = 4.7.1.3
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 12,960.00
B BAHAN
Sabun C361 Kg 0.05 7,500.00 375.00
JUMLAH HARGA BAHAN 375.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 13,335.00
E Overhead & Profit 10% 1,333.50
F Harga Satuan Pekerjaan (D+E) 14,668.50

1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Kode AHSP = 4.7.1.4
A TENAGA
Pekerja C9 OH 0.07 80,000.00 5,600.00
Tukang cat C27 OH 0.009 125,000.00 1,125.00
Kepala tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 7,985.00
B BAHAN
Cat Meni C209 Kg 0.2 46,800.00 9,360.00
Plamir C339 Kg 0.15 14,200.00 2,130.00
Cat dasar C205 Kg 0.17 22,500.00 3,825.00
Cat penutup C213 Kg 0.26 30,000.00 7,800.00
Kuas 2,5 " C291 Bh 0.01 19,500.00 195.00
Thinner C405 Kg 0.03 51,300.00 1,539.00
Amplas C124 Lbr 0.2 6,900.00 1,380.00
JUMLAH HARGA BAHAN 26,229.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 34,214.00
E Overhead & Profit 10% 3,421.40
F Harga Satuan Pekerjaan (D+E) 37,635.40

Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
Kode AHSP = 4.7.1.5
A TENAGA
Pekerja C9 OH 0.07 80,000.00 5,600.00
Tukang Kayu C19 OH 0.105 125,000.00 13,125.00
Kepala tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 19,685.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Cat Meni C209 Kg 0.2 46,800.00 9,360.00
Plamir C339 Kg 0.15 14,200.00 2,130.00
Cat dasar C205 Kg 0.17 22,500.00 3,825.00
Cat penutup C213 Kg 0.35 30,000.00 10,500.00
Kuas 2,5 " C291 Bh 0.01 19,500.00 195.00
Thinner C405 Kg 0.03 51,300.00 1,539.00
Amplas C124 Lbr 0.2 6,900.00 1,380.00
JUMLAH HARGA BAHAN 28,929.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 48,614.00
E Overhead & Profit 10% 4,861.40
F Harga Satuan Pekerjaan (D+E) 53,475.40

Pelaburan 1 m2 bidang kayu dengan teak oil


Kode AHSP = 4.7.1.6
A TENAGA
Pekerja C9 OH 0.04 80,000.00 3,200.00
Tukang cat C27 OH 0.063 125,000.00 7,875.00
Kepala tukang C39 OH 0.063 150,000.00 9,450.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 20,885.00
B BAHAN
Teak oil C404 L 0.36 1.00 0.36
JUMLAH HARGA BAHAN 0.36
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 20,885.36
E Overhead & Profit 10% 2,088.54
F Harga Satuan Pekerjaan (D+E) 22,973.90

Pelaburan 1 m2 bidang kayu dengan politur


Kode AHSP = 4.7.1.7
A TENAGA
Pekerja C9 OH 0.04 80,000.00 3,200.00
Tukang cat C27 OH 0.06 125,000.00 7,500.00
Kepala tukang C39 OH 0.016 150,000.00 2,400.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 13,460.00
B BAHAN
Politur C352 L 0.15 1.00 0.15
Politur jadi C353 L 0.372 1.00 0.37
Amplas C124 Lbr 2 6,900.00 13,800.00
JUMLAH HARGA BAHAN 13,800.52
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 27,260.52
E Overhead & Profit 10% 2,726.05
F Harga Satuan Pekerjaan (D+E) 29,986.57

Pelaburan 1 m2 bidang kayu dengan cat residu dan ter


Kode AHSP = 4.7.1.8
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 8,720.00
B BAHAN
Residu C356 Ltr 0.35 15,000.00 5,250.00
JUMLAH HARGA BAHAN 5,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 13,970.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 1,397.00
F Harga Satuan Pekerjaan (D+E) 15,367.00

Pelaburan 1 m2 bidang kayu dengan vernis


Kode AHSP = 4.7.1.9
A TENAGA
Pekerja C9 OH 0.16 80,000.00 12,800.00
Tukang cat C27 OH 0.16 125,000.00 20,000.00
Kepala tukang C39 OH 0.016 150,000.00 2,400.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 35,560.00
B BAHAN
Cat Vernis C216 L 0.15 72,500.00 10,875.00
Dempul C218 Kg 0.05 39,900.00 1,995.00
Amplas C124 Lbr 0.1 6,900.00 690.00
JUMLAH HARGA BAHAN 13,560.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 49,120.00
E Overhead & Profit 10% 4,912.00
F Harga Satuan Pekerjaan (D+E) 54,032.00

Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Kode AHSP = 4.7.1.10
A TENAGA
Pekerja C9 OH 0.02 80,000.00 1,600.00
Tukang cat C27 OH 0.063 125,000.00 7,875.00
Kepala tukang C39 OH 0.0063 150,000.00 945.00
Mandor C47 OH 0.0025 120,000.00 300.00
JUMLAH TENAGA KERJA 10,720.00
B BAHAN
Plamir C339 Kg 0.1 14,200.00 1,420.00
Cat dasar C205 Kg 0.1 22,500.00 2,250.00
Cat penutup C213 Kg 0.26 30,000.00 7,800.00
JUMLAH HARGA BAHAN 11,470.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 22,190.00
E Overhead & Profit 10% 2,219.00
F Harga Satuan Pekerjaan (D+E) 24,409.00

Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)


Kode AHSP = 4.7.1.11
A TENAGA
Pekerja C9 OH 0.028 80,000.00 2,240.00
Tukang cat C27 OH 0.042 125,000.00 5,250.00
Kepala tukang C39 OH 0.0042 150,000.00 630.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 8,480.00
B BAHAN
Cat dasar C205 Kg 0.12 22,500.00 2,700.00
Cat penutup C213 Kg 0.18 30,000.00 5,400.00
JUMLAH HARGA BAHAN 8,100.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 16,580.00
E Overhead & Profit 10% 1,658.00
F Harga Satuan Pekerjaan (D+E) 18,238.00

Pengecatan 1 m2 Langit Langit ( 1 lapis cat dasar, 2 lapis cat penutup)


Kode AHSP = 4.7.1.15
A TENAGA
Pekerja Cat C15 OH 0.028 80,000.00 2,240.00
Tukang cat C27 OH 0.042 125,000.00 5,250.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala tukang C39 OH 0.0042 150,000.00 630.00
Mandor Cat C44 OH 0.0025 120,000.00 300.00
JUMLAH TENAGA KERJA 8,420.00
B BAHAN
Cat penutup C213 Kg 0.26 30,000.00 7,800.00
JUMLAH HARGA BAHAN 7,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 16,220.00
E Overhead & Profit 10% 1,622.00
F Harga Satuan Pekerjaan (D+E) 17,842.00

Pelaburan 1 m2 tembok dengan kalkarium


Kode AHSP = 4.7.1.12
A TENAGA
Pekerja C9 OH 0.028 80,000.00 2,240.00
Tukang cat C27 OH 0.042 125,000.00 5,250.00
Kepala tukang C39 OH 0.0042 150,000.00 630.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 8,480.00
B BAHAN
Kalkarium C261 Kg 0.1 1.00 0.10
JUMLAH HARGA BAHAN 0.10
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,480.10
E Overhead & Profit 10% 848.01
F Harga Satuan Pekerjaan (D+E) 9,328.11

Pelaburan 1 m2 tembok dengan kapur sirih


Kode AHSP = 4.7.1.13
A TENAGA
Pekerja C9 OH 0.15 80,000.00 12,000.00
Tukang cat C27 OH 0.001 125,000.00 125.00
Kepala tukang C39 OH 0.0001 150,000.00 15.00
Mandor C47 OH 0.0025 120,000.00 300.00
JUMLAH TENAGA KERJA 12,440.00
B BAHAN
Kapur sirih C263 Kg 0.15 1.00 0.15
Amplas C124 Lbr 0.1 6,900.00 690.00
Alang-alang C123 Ikat 0.25 - -
JUMLAH HARGA BAHAN 690.15
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 13,130.15
E Overhead & Profit 10% 1,313.02
F Harga Satuan Pekerjaan (D+E) 14,443.17

Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan)


Kode AHSP = 4.7.1.14
A TENAGA
Pekerja C9 OH 0.04 80,000.00 3,200.00
Tukang cat C27 OH 0.005 125,000.00 625.00
Kepala tukang C39 OH 0.0005 150,000.00 75.00
Mandor C47 OH 0.0025 120,000.00 300.00
JUMLAH TENAGA KERJA 4,200.00
B BAHAN
Kapur sirih C263 Kg 0.3 1.00 0.30
Amplas C124 Lbr 0.2 6,900.00 1,380.00
Alang-alang C123 Ikat 0.25 - -
JUMLAH HARGA BAHAN 1,380.30
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 5,580.30
E Overhead & Profit 10% 558.03
F Harga Satuan Pekerjaan (D+E) 6,138.33

Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis cat terakhir
Kode AHSP = 4.7.1.22
A TENAGA
Pekerja C9 OH 0.04 80,000.00 3,200.00
Tukang cat C27 OH 0.7 125,000.00 87,500.00
Kepala tukang C39 OH 0.07 150,000.00 10,500.00
Mandor C47 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 103,600.00
B BAHAN
Cat dasar C205 Kg 0.3 22,500.00 6,750.00
Thinner C405 Lbr 0.01 51,300.00 513.00
JUMLAH HARGA BAHAN 7,263.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 110,863.00
E Overhead & Profit 10% 11,086.30
F Harga Satuan Pekerjaan (D+E) 121,949.30

Pemasangan 1 buah closet duduk/monoblock


Kode AHSP = 5.1.1.1
A TENAGA
Pekerja C9 OH 3.3 80,000.00 264,000.00
Tukang batu C18 OH 1.1 125,000.00 137,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.16 120,000.00 19,200.00
JUMLAH TENAGA KERJA 422,200.00
B BAHAN
Kloset Duduk (Toto Type CW 660 NJ) C1289 Unit 1 3,400,000.00 3,400,000.00
Perlengkapan C1314 Ls 1 204,000.00 204,000.00
JUMLAH HARGA BAHAN 3,604,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,026,200.00
E Overhead & Profit 10% 402,620.00
F Harga Satuan Pekerjaan (D+E) 4,428,820.00

Pemasangan 1 buah closet duduk/monoblock Type 2


Kode AHSP = 5.1.1.1
A TENAGA
Pekerja C9 OH 3.3 80,000.00 264,000.00
Tukang batu C18 OH 1.1 125,000.00 137,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.16 120,000.00 19,200.00
JUMLAH TENAGA KERJA 422,200.00
B BAHAN
Kloset Duduk Type 2 (Toto Type C436N) C1290 Unit 1 8,200,000.00 8,200,000.00
JUMLAH HARGA BAHAN 8,200,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,622,200.00
E Overhead & Profit 10% 862,220.00
F Harga Satuan Pekerjaan (D+E) 9,484,420.00

Pemasangan 1 buah closet jongkok porslen


Kode AHSP = 5.1.1.2
A TENAGA
Pekerja C9 OH 1 80,000.00 80,000.00
Tukang batu C18 OH 1.5 125,000.00 187,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala tukang C39 OH 0.15 150,000.00 22,500.00
Mandor C47 OH 0.16 120,000.00 19,200.00
JUMLAH TENAGA KERJA 309,200.00
B BAHAN
Kloset Jongkok C1291 Unit 1 510,050.00 510,050.00
Semen Portland C363 Kg 6 1,300.00 7,800.00
Pasir pasang C99 M3 0.01 100,000.00 1,000.00
JUMLAH HARGA BAHAN 518,850.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 828,050.00
E Overhead & Profit 10% 82,805.00
F Harga Satuan Pekerjaan (D+E) 910,855.00

Pemasangan 1 buah closet jongkok teraso


Kode AHSP = 5.1.1.3
A TENAGA
Pekerja C9 OH 1 80,000.00 80,000.00
Tukang batu C18 OH 1.5 125,000.00 187,500.00
Kepala tukang C39 OH 0.15 150,000.00 22,500.00
Mandor C47 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 296,000.00
B BAHAN
Kloset Jongkok C1291 Unit 1 510,050.00 510,050.00
Semen Portland C363 Kg 6 1,300.00 7,800.00
Pasir pasang C99 M3 0.01 100,000.00 1,000.00
Bata merah C142 Bh 7 1,000.00 7,000.00
JUMLAH HARGA BAHAN 525,850.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 821,850.00
E Overhead & Profit 10% 82,185.00
F Harga Satuan Pekerjaan (D+E) 904,035.00

Pemasangan 1 buah urinoir


Kode AHSP = 5.1.1.4
A TENAGA
Pekerja C9 OH 1 80,000.00 80,000.00
Tukang batu C18 OH 1 125,000.00 125,000.00
Kepala tukang C39 OH 0.1 150,000.00 15,000.00
Mandor C47 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 226,000.00
B BAHAN
Urinoir #N/A Unit 1 #N/A #N/A
Semen Portland C363 Kg 6 1,300.00 7,800.00
Pasir pasang C99 M3 0.01 100,000.00 1,000.00
Perlengkapan C1314 % 30 1.00 30.00
JUMLAH HARGA BAHAN #N/A
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

Pemasangan 1 buah wastafel


Kode AHSP = 5.1.1.5
A TENAGA
Pekerja C9 OH 1.2 80,000.00 96,000.00
Tukang batu C18 OH 1.45 125,000.00 181,250.00
Kepala tukang C39 OH 0.15 150,000.00 22,500.00
Mandor C47 OH 0.06 120,000.00 7,200.00
JUMLAH TENAGA KERJA 306,950.00
B BAHAN
Wastafel 1 #N/A Unit 1.2 #N/A #N/A
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Semen Portland C363 Kg 6 1,300.00 7,800.00
Pasir pasang C99 M3 0.01 100,000.00 1,000.00
Perlengkapan C1314 % 12 1.00 12.00
JUMLAH HARGA BAHAN #N/A
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

Pemasangan 1 buah bathcuip porselen


Kode AHSP = 5.1.1.6
A TENAGA
Pekerja C9 OH 0.075 80,000.00 6,000.00
Tukang batu C18 OH 0.75 125,000.00 93,750.00
Kepala tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 111,360.00
B BAHAN
Bathcuip C1494 Unit 1 1.00 1.00
Perlengkapan C1314 % 20 1.00 20.00
JUMLAH HARGA BAHAN 21.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 111,381.00
E Overhead & Profit 10% 11,138.10
F Harga Satuan Pekerjaan (D+E) 122,519.10

Pemasangan 1 buah bak fibreglass vol 1 m3


Kode AHSP = 5.1.1.7
A TENAGA
Pekerja C9 OH 3 80,000.00 240,000.00
Tukang batu C18 OH 4.5 125,000.00 562,500.00
Kepala tukang C39 OH 0.05 150,000.00 7,500.00
Mandor C47 OH 0.9 120,000.00 108,000.00
JUMLAH TENAGA KERJA 918,000.00
B BAHAN
Bak fibreglass C1495 Unit 1 1.00 1.00
Perlengkapan C1314 Ls 0.12 1.00 0.12
JUMLAH HARGA BAHAN 1.12
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 918,001.12
E Overhead & Profit 10% 91,800.11
F Harga Satuan Pekerjaan (D+E) 1,009,801.23

Pemasangan 1 buah bak mandi batu bata vol 0,30 m3


Kode AHSP = 5.1.1.8
A TENAGA
Pekerja C9 OH 6 80,000.00 480,000.00
Tukang batu C18 OH 3 125,000.00 375,000.00
Kepala tukang C39 OH 0.3 150,000.00 45,000.00
Mandor C47 OH 0.03 120,000.00 3,600.00
JUMLAH TENAGA KERJA 903,600.00
B BAHAN
Bata merah C142 M3 150 1,000.00 150,000.00
Semen portland C363 Kg 120 1,300.00 156,000.00
Pasir pasang C99 M3 0.3 100,000.00 30,000.00
Porselen ( 11 x 11 ) cm C355 bh 360 1,987.95 715,662.65
Semen warna C365 Kg 6 20,700.00 124,200.00
JUMLAH HARGA BAHAN 1,175,862.65
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2,079,462.65
E Overhead & Profit 10% 207,946.27
F Harga Satuan Pekerjaan (D+E) 2,287,408.92

Pemasangan 1 buah bak mandi teraso vol 0,30 m3


Kode AHSP = 5.1.1.9
A TENAGA
Pekerja C9 OH 3 80,000.00 240,000.00
Tukang batu C18 OH 4.5 125,000.00 562,500.00
Kepala tukang C39 OH 0.05 150,000.00 7,500.00
Mandor C47 OH 0.9 120,000.00 108,000.00
JUMLAH TENAGA KERJA 918,000.00
B BAHAN
Bak fibreglass C1495 Unit 1 1.00 1.00
Perlengkapan C1314 Ls 0.12 1.00 0.12
JUMLAH HARGA BAHAN 1.12
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 918,001.12
E Overhead & Profit 10% 91,800.11
F Harga Satuan Pekerjaan (D+E) 1,009,801.23

Pemasangan 1 buah bak air fibreglass vol 1 m3


Kode AHSP = 5.1.1.10
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang batu C18 OH 0.45 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 88,800.00
B BAHAN
Bak air fibreglass C1496 Unit 1 1.00 1.00
Perlengkapan C1314 % 12 1.00 12.00
JUMLAH HARGA BAHAN 13.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 88,813.00
E Overhead & Profit 10% 8,881.30
F Harga Satuan Pekerjaan (D+E) 97,694.30

Pemasangan 1 buah bak beton volume 1 m3


Kode AHSP = 5.1.1.11
A TENAGA
Pekerja C9 OH 0.14 3,50 0.49
Tukang batu C18 OH 0.07 4,50 0.32
Kepala tukang C39 OH 0.007 0,05 0.00
Mandor C47 OH 0.007 0,018 0.00
JUMLAH TENAGA KERJA 0.81
B BAHAN
Beton 1:2:3 C473 M3 0.9 1.00 0.90
Besi Beton (Polos/ulir) C161 Kg 180 12,000.00 2,160,000.00
Kayu bekisting C90 M2 8 1,955,000.00 15,640,000.00
Porselen ( 11 x 11 ) cm C355 Bh 500 1,987.95 993,975.90
Perlengkapan C1314 % 10 1.00 10.00
JUMLAH HARGA BAHAN 18,793,986.80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 18,793,987.61
E Overhead & Profit 10% 1,879,398.76
F Harga Satuan Pekerjaan (D+E) 20,673,386.37

Pemasangan 1 buah bak cuci piring stainlessteel


Kode AHSP = 5.1.1.12
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja C9 OH 0.03 80,000.00 2,400.00
Tukang batu C18 OH 0.3 125,000.00 37,500.00
Kepala tukang C39 OH 0.03 150,000.00 4,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,200.00
B BAHAN
Bak cuci piring C477 Unit 1 1.00 1.00
Waterdrain C478 Bh 1 1.00 1.00
JUMLAH HARGA BAHAN 1.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 46,201.00
E Overhead & Profit 10% 4,620.10
F Harga Satuan Pekerjaan (D+E) 50,821.10

Pemasangan 1 buah bak cuci piring teraso


Kode AHSP = 5.1.1.13
A TENAGA
Pekerja C9 OH 0.05 80,000.00 4,000.00
Tukang batu C18 OH 0.5 125,000.00 62,500.00
Kepala tukang C39 OH 0.05 150,000.00 7,500.00
Mandor C47 OH 0.025 120,000.00 3,000.00
JUMLAH TENAGA KERJA 77,000.00
B BAHAN
Bak cuci piring C477 Unit 1 1.00 1.00
Waterdrain C478 Bh 1 1.00 1.00
Semen portland C363 Kg 20 1,300.00 26,000.00
Pasir pasang C99 M3 0.05 100,000.00 5,000.00
JUMLAH HARGA BAHAN 5,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 82,000.00
E Overhead & Profit 10% 8,200.00
F Harga Satuan Pekerjaan (D+E) 90,200.00

Pemasangan 1 buah floor drain


Kode AHSP = 5.1.1.14
A TENAGA
Pekerja C9 OH 0.01 80,000.00 800.00
Tukang batu C18 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 15,400.00
B BAHAN
Floor drain C1248 Unit 1 176,750.00 176,750.00
seal tape C657 bh 0.025 7,500.00 187.50
JUMLAH HARGA BAHAN 176,937.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 192,337.50
E Overhead & Profit 10% 19,233.75
F Harga Satuan Pekerjaan (D+E) 211,571.25

Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm


Kode AHSP = 5.1.1.15
A TENAGA
Pekerja C9 OH 2.16 80,000.00 172,800.00
Tukang batu C18 OH 0.72 125,000.00 90,000.00
Kepala tukang C39 OH 0.072 150,000.00 10,800.00
Mandor C47 OH 0.011 120,000.00 1,320.00
JUMLAH TENAGA KERJA 274,920.00
B BAHAN
Bata merah C142 bh 30 1,000.00 30,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Semen portland C363 Kg 20 1,300.00 26,000.00
Pasir pasang C99 m3 0.16 100,000.00 16,000.00
JUMLAH HARGA BAHAN 72,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 346,920.00
E Overhead & Profit 10% 34,692.00
F Harga Satuan Pekerjaan (D+E) 381,612.00

Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm


Kode AHSP = 5.1.1.16
A TENAGA
Pekerja C9 OH 3.2 80,000.00 256,000.00
Tukang batu C18 OH 1.15 125,000.00 143,750.00
Kepala tukang C39 OH 0.011 150,000.00 1,650.00
Mandor C47 OH 0.016 120,000.00 1,920.00
JUMLAH TENAGA KERJA 403,320.00
B BAHAN
Bata merah C142 bh 70 1,000.00 70,000.00
Semen portland C363 Kg 77 1,300.00 100,100.00
Pasir pasang C99 M3 0.13 100,000.00 13,000.00
Pasir beton C97 M3 0.09 100,000.00 9,000.00
batu Kerikil C74 M3 0.02 400,000.00 8,000.00
Besi Beton (Polos/ulir) C161 Kg 2.6 12,000.00 31,200.00
JUMLAH HARGA BAHAN 231,300.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 634,620.00
E Overhead & Profit 10% 63,462.00
F Harga Satuan Pekerjaan (D+E) 698,082.00

Pemasangan 1 buah bak kontrol pasangan bata 60cm x60cm tinggi 65 cm


Kode AHSP = 5.1.1.17
A TENAGA
Pekerja C9 OH 3.2 80,000.00 256,000.00
Tukang batu C18 OH 1.15 125,000.00 143,750.00
Kepala tukang C39 OH 0.011 150,000.00 1,650.00
Mandor C47 OH 0.016 120,000.00 1,920.00
JUMLAH TENAGA KERJA 403,320.00
B BAHAN
Bata merah C142 bh 123 1,000.00 123,000.00
Semen portland C363 Kg 114 1,300.00 148,200.00
Pasir pasang C99 M3 0.184 100,000.00 18,400.00
Pasir beton C97 M3 0.12 100,000.00 12,000.00
batu Kerikil C74 M3 0.033 400,000.00 13,200.00
Besi Beton (Polos/ulir) C161 Kg 4.85 12,000.00 58,200.00
JUMLAH HARGA BAHAN 373,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 776,320.00
E Overhead & Profit 10% 77,632.00
F Harga Satuan Pekerjaan (D+E) 853,952.00

Pemasangan 1 m’ pipa galvanis diameter ½”


Kode AHSP = 5.1.1.18
A TENAGA
Pekerja C9 OH 0.054 80,000.00 4,320.00
Tukang batu C18 OH 0.09 125,000.00 11,250.00
Kepala tukang C39 OH 0.009 150,000.00 1,350.00
Mandor C47 OH 0.027 120,000.00 3,240.00
JUMLAH TENAGA KERJA 20,160.00
B BAHAN
Pipa Galvanis 1/2" C1328 M 1.2 16,833.33 20,200.00
Perlengkapan C1314 Ls 0.42 1.00 0.42
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 20,200.42
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 40,360.42
E Overhead & Profit 10% 4,036.04
F Harga Satuan Pekerjaan (D+E) 44,396.46

pemasangan 1 Bh Staight Way Valve Diameter 25mm PPR


Kode AHSP = 5.1.1.T1
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,000.00
Tukang Pipa C24 OH 0.14 125,000.00 17,500.00
Mandor Pipa C41 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 25,900.00
B BAHAN
Staight Way Valve Ø 25mm PPR C1469 bh 1.00 195,233.00 195,233.00
JUMLAH HARGA BAHAN 195,233.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 221,133.00
E Overhead & Profit 10% 22,113.30
F Harga Satuan Pekerjaan (D+E) 243,246.30

pemasangan 1 Bh Valve Dia. 1"


Kode AHSP = 5.1.1.T2
A TENAGA
Pekerja Pipa C12 OH 0.07 80,000.00 5,600.00
Tukang Pipa C24 OH 0.10 125,000.00 12,500.00
Mandor Pipa C41 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 20,500.00
B BAHAN
Valve Ø 1" C1488 bh 1.00 95,950.00 95,950.00
JUMLAH HARGA BAHAN 95,950.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 116,450.00
E Overhead & Profit 10% 11,645.00
F Harga Satuan Pekerjaan (D+E) 128,095.00

pemasangan 1 bh Strainer Dia. 65mm


Kode AHSP = 5.1.1.T3
A TENAGA
Pekerja Pipa C12 OH 0.10 80,000.00 8,000.00
Tukang Pipa C24 OH 0.25 125,000.00 31,250.00
Mandor Pipa C41 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 45,250.00
B BAHAN
Strainer Dia. 65mm 10 K C1471 bh 1.00 1,683,670.00 1,683,670.00
JUMLAH HARGA BAHAN 1,683,670.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,728,920.00
E Overhead & Profit 10% 172,892.00
F Harga Satuan Pekerjaan (D+E) 1,901,812.00

pemasangan 1 Bh Flexible Joint Dia. 65mm


Kode AHSP = 5.1.1.T4
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,666.67
Tukang Pipa C24 OH 0.08 125,000.00 10,416.67
Mandor Pipa C41 OH 0.04 120,000.00 5,000.00
JUMLAH TENAGA KERJA 22,083.33
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Flexible Joint Dia. 65mm C1253 bh 1.00 313,100.00 313,100.00
JUMLAH HARGA BAHAN 313,100.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 335,183.33
E Overhead & Profit 10% 33,518.33
F Harga Satuan Pekerjaan (D+E) 368,701.67

Pemasangan 1 Bh Check Valve Diameter 65mm / 10 K


Kode AHSP = 5.1.1.T5
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,666.67
Tukang Pipa C24 OH 0.08 125,000.00 10,416.67
Mandor Pipa C41 OH 0.04 120,000.00 5,000.00
JUMLAH TENAGA KERJA 22,083.33
B BAHAN
Check Valve Ø 65mm C1229 bh 1.00 1,061,207.00 1,061,207.00
JUMLAH HARGA BAHAN 1,061,207.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,083,290.33
E Overhead & Profit 10% 108,329.03
F Harga Satuan Pekerjaan (D+E) 1,191,619.37

Pemasangan 1 Bh Check Valve Diameter 40mm


Kode AHSP = 5.1.1.T6
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,666.67
Tukang Pipa C24 OH 0.08 125,000.00 10,416.67
Mandor Pipa C41 OH 0.04 120,000.00 5,000.00
JUMLAH TENAGA KERJA 22,083.33
B BAHAN
Check Valve Ø 40mm C1231 bh 1.00 618,120.00 618,120.00
JUMLAH HARGA BAHAN 618,120.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 640,203.33
E Overhead & Profit 10% 64,020.33
F Harga Satuan Pekerjaan (D+E) 704,223.67

Pemasangan 1 Bh Check Valve Diameter 32mm


Kode AHSP = 5.1.1.T6
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,666.67
Tukang Pipa C24 OH 0.08 125,000.00 10,416.67
Mandor Pipa C41 OH 0.04 120,000.00 5,000.00
JUMLAH TENAGA KERJA 22,083.33
B BAHAN
Check Valve Ø 32mm C1232 bh 1.00 585,000.00 585,000.00
JUMLAH HARGA BAHAN 585,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 607,083.33
E Overhead & Profit 10% 60,708.33
F Harga Satuan Pekerjaan (D+E) 667,791.67

Pemasangan 1 Buah Pressure Gauge


Kode AHSP = 5.1.1.T6
A TENAGA
Pekerja Pipa C12 OH 0.33 80,000.00 26,666.67
Tukang Pipa C24 OH 0.33 125,000.00 41,666.67
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor Pipa C41 OH 0.17 120,000.00 20,000.00
JUMLAH TENAGA KERJA 88,333.33
B BAHAN
Pressure Gauge C1445 bh 1.00 560,550.00 560,550.00
JUMLAH HARGA BAHAN 560,550.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 648,883.33
E Overhead & Profit 10% 64,888.33
F Harga Satuan Pekerjaan (D+E) 713,771.67

pemasangan 1 Bh Gate Valve Diameter 50mm / 10 Kg


Kode AHSP = 5.1.1.T7
A TENAGA
Pekerja Pipa C12 OH 0.17 80,000.00 13,333.33
Tukang Pipa C24 OH 0.17 125,000.00 20,833.33
Mandor Pipa C41 OH 0.08 120,000.00 10,000.00
JUMLAH TENAGA KERJA 44,166.67
B BAHAN
Gate Valve Ø 50mm / 10 Kg C1276 bh 1.00 660,944.00 660,944.00
JUMLAH HARGA BAHAN 660,944.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 705,110.67
E Overhead & Profit 10% 70,511.07
F Harga Satuan Pekerjaan (D+E) 775,621.73

Pemasangan 1 Buah Pressure Switch


Kode AHSP = 5.1.1.T8
A TENAGA
Pekerja Pipa C12 OH 0.33 80,000.00 26,666.67
Tukang Pipa C24 OH 0.33 125,000.00 41,666.67
Mandor Pipa C41 OH 0.17 120,000.00 20,000.00
JUMLAH TENAGA KERJA 88,333.33
B BAHAN
Pressure Switch C1446 bh 1.00 636,300.00 636,300.00
JUMLAH HARGA BAHAN 636,300.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 724,633.33
E Overhead & Profit 10% 72,463.33
F Harga Satuan Pekerjaan (D+E) 797,096.67

Pemasangan 1 m pipa PVC Ø 63 mm


Kode AHSP = 8.4.1.1
A TENAGA
Pekerja C9 OH 0.081 80,000.00 6,480.00
Tukang pipa C24 OH 0.041 125,000.00 5,125.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 12,565.00
B BAHAN
Pipa PVC Ø 63 mm C1347 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.006 1.00 0.01

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 12,566.01
E Overhead & Profit 10% 1,256.60
F Harga Satuan Pekerjaan (D+E) 13,822.61
Catatan:
Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang tercantum pada tabel. Apabila ada tambahan peralatan yang digunakan, harus
disesuaikan dengan spesifikasi dan gambar kerja.
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m pipa PVC Ø 90 mm


Kode AHSP = 8.4.1.2
A TENAGA
Pekerja C9 OH 0.094 80,000.00 7,520.00
Tukang pipa C24 OH 0.047 125,000.00 5,875.00
Mandor C47 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 14,475.00
B BAHAN
Pipa PVC Ø 90 mm C1348 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.008 1.00 0.01

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 14,476.01
E Overhead & Profit 10% 1,447.60
F Harga Satuan Pekerjaan (D+E) 15,923.61

Pemasangan 1 m pipa PVC Ø 110 mm


Kode AHSP = 8.4.1.3
A TENAGA
Pekerja C9 OH 0.105 80,000.00 8,400.00
Tukang pipa C24 OH 0.053 125,000.00 6,625.00
Mandor C47 OH 0.011 120,000.00 1,320.00
JUMLAH TENAGA KERJA 16,345.00
B BAHAN
Pipa PVC Ø 110 mm C1349 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.01 1.00 0.01

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 16,346.01
E Overhead & Profit 10% 1,634.60
F Harga Satuan Pekerjaan (D+E) 17,980.61

Pemasangan 1 m pipa PVC Ø 150 mm


Kode AHSP = 8.4.1.4
A TENAGA
Pekerja C9 OH 0.118 80,000.00 9,440.00
Tukang pipa C24 OH 0.059 125,000.00 7,375.00
Mandor C47 OH 0.012 120,000.00 1,440.00
JUMLAH TENAGA KERJA 18,255.00
B BAHAN
Pipa PVC Ø 150 mm C1350 m 1 1.00 1.00
-
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.012 1.00 0.01

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 18,256.01
E Overhead & Profit 10% 1,825.60
F Harga Satuan Pekerjaan (D+E) 20,081.61

Pemasngan 1 m pipa PVC Ø 200 mm


Kode AHSP = 8.4.1.5
A TENAGA
Pekerja C9 OH 0.189 80,000.00 15,120.00
Tukang pipa C24 OH 0.095 125,000.00 11,875.00
Mandor C47 OH 0.019 120,000.00 2,280.00
JUMLAH TENAGA KERJA 29,275.00
B BAHAN
Pipa PVC Ø 200 mm C1351 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.024 1.00 0.02

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 29,276.02
E Overhead & Profit 10% 2,927.60
F Harga Satuan Pekerjaan (D+E) 32,203.63

Pemasangan 1 m pipa PVC Ø 250 mm


Kode AHSP = 8.4.1.6
A TENAGA
Pekerja C9 OH 0.256 80,000.00 20,480.00
Tukang pipa C24 OH 0.128 125,000.00 16,000.00
Mandor C47 OH 0.026 120,000.00 3,120.00
JUMLAH TENAGA KERJA 39,600.00
B BAHAN
Pipa PVC Ø 250 mm C1352 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.034 1.00 0.03

JUMLAH HARGA ALAT 0.03


D Jumlah (A+B+C) 39,601.03
E Overhead & Profit 10% 3,960.10
F Harga Satuan Pekerjaan (D+E) 43,561.14

Pemasangan 1 m pipa PVC Ø 300 mm


Kode AHSP = 8.4.1.7
A TENAGA
Pekerja C9 OH 0.294 80,000.00 23,520.00
Tukang pipa C24 OH 0.147 125,000.00 18,375.00
Mandor C47 OH 0.029 120,000.00 3,480.00
JUMLAH TENAGA KERJA 45,375.00
B BAHAN
Pipa PVC Ø 300 mm C1353 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.04 1.00 0.04

JUMLAH HARGA ALAT 0.04


D Jumlah (A+B+C) 45,376.04
E Overhead & Profit 10% 4,537.60
F Harga Satuan Pekerjaan (D+E) 49,913.64

Pemasangan 1 m pipa PVC Ø 400 mm


Kode AHSP = 8.4.1.8
A TENAGA
Pekerja C9 OH 0.544 80,000.00 43,520.00
Tukang pipa C24 OH 0.272 125,000.00 34,000.00
Mandor C47 OH 0.054 120,000.00 6,480.00
JUMLAH TENAGA KERJA 84,000.00
B BAHAN
Pipa PVC Ø 400 mm C1354 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.08 1.00 0.08

JUMLAH HARGA ALAT 0.08


D Jumlah (A+B+C) 84,001.08
E Overhead & Profit 10% 8,400.11
F Harga Satuan Pekerjaan (D+E) 92,401.19

Pemasangan 1 m pipa PVC Ø 450 mm


Kode AHSP = 8.4.1.9
A TENAGA
Pekerja C9 OH 0.669 80,000.00 53,520.00
Tukang pipa C24 OH 0.335 125,000.00 41,875.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.067 120,000.00 8,040.00
JUMLAH TENAGA KERJA 103,435.00
B BAHAN
Pipa PVC Ø 450 mm C1355 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.1 1.00 0.10

JUMLAH HARGA ALAT 0.10


D Jumlah (A+B+C) 103,436.10
E Overhead & Profit 10% 10,343.61
F Harga Satuan Pekerjaan (D+E) 113,779.71

Pemasangan 1 m pipa PVC Ø 500 mm


Kode AHSP = 8.4.1.10
A TENAGA
Pekerja C9 OH 0.809 80,000.00 64,720.00
Tukang pipa C24 OH 0.405 125,000.00 50,625.00
Mandor C47 OH 0.081 120,000.00 9,720.00
JUMLAH TENAGA KERJA 125,065.00
B BAHAN
Pipa PVC Ø 500 mm C1356 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.122 1.00 0.12

JUMLAH HARGA ALAT 0.12


D Jumlah (A+B+C) 125,066.12
E Overhead & Profit 10% 12,506.61
F Harga Satuan Pekerjaan (D+E) 137,572.73

Pemasangan 1 m pipa PVC Ø 600 mm


Kode AHSP = 8.4.1.11
A TENAGA
Pekerja C9 OH 0.957 80,000.00 76,560.00
Tukang pipa C24 OH 0.479 125,000.00 59,875.00
Mandor C47 OH 0.096 120,000.00 11,520.00
JUMLAH TENAGA KERJA 147,955.00
B BAHAN
Pipa PVC Ø 600 mm C1357 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.145 1.00 0.15

JUMLAH HARGA ALAT 0.15


D Jumlah (A+B+C) 147,956.15
E Overhead & Profit 10% 14,795.61
F Harga Satuan Pekerjaan (D+E) 162,751.76

Pemasangan 1 m pipa PVC Ø 800 mm


Kode AHSP = 8.4.1.12
A TENAGA
Pekerja C9 OH 1.618 80,000.00 129,440.00
Tukang pipa C24 OH 0.809 125,000.00 101,125.00
Mandor C47 OH 0.162 120,000.00 19,440.00
JUMLAH TENAGA KERJA 250,005.00
B BAHAN
Pipa PVC Ø 800 mm C1358 m 1 1.00 1.00

JUMLAH HARGA BAHAN -


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.25 1.00 0.25

JUMLAH HARGA ALAT 0.25


D Jumlah (A+B+C) 250,005.25
E Overhead & Profit 10% 25,000.53
F Harga Satuan Pekerjaan (D+E) 275,005.78
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m pipa PVC Ø 900 mm


Kode AHSP = 8.4.1.13
A TENAGA
Pekerja C9 OH 1.691 80,000.00 135,280.00
Tukang pipa C24 OH 0.846 125,000.00 105,750.00
Mandor C47 OH 0.169 120,000.00 20,280.00
JUMLAH TENAGA KERJA 261,310.00
B BAHAN
Pipa PVC Ø 900 mm C1359 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.262 1.00 0.26

JUMLAH HARGA ALAT 0.26


D Jumlah (A+B+C) 261,311.26
E Overhead & Profit 10% 26,131.13
F Harga Satuan Pekerjaan (D+E) 287,442.39

Pemasangan 1 m pipa PVC Ø 1000 mm


Kode AHSP = 8.4.1.14
A TENAGA
Pekerja C9 OH 1.895 80,000.00 151,600.00
Tukang pipa C24 OH 0.948 125,000.00 118,500.00
Mandor C47 OH 0.19 120,000.00 22,800.00
JUMLAH TENAGA KERJA 292,900.00
B BAHAN
Pipa PVC Ø 1000 mm C1360 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.294 1.00 0.29

JUMLAH HARGA ALAT 0.29


D Jumlah (A+B+C) 292,901.29
E Overhead & Profit 10% 29,290.13
F Harga Satuan Pekerjaan (D+E) 322,191.42

Pemasangan 1 m pipa PVC Ø 1100 mm


Kode AHSP = 8.4.1.15
A TENAGA
Pekerja C9 OH 2.099 80,000.00 167,920.00
Tukang pipa C24 OH 1.05 125,000.00 131,250.00
Mandor C47 OH 0.21 120,000.00 25,200.00
JUMLAH TENAGA KERJA 324,370.00
B BAHAN
Pipa PVC Ø 1100 mm C1361 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.327 1.00 0.33

JUMLAH HARGA ALAT 0.33


D Jumlah (A+B+C) 324,371.33
E Overhead & Profit 10% 32,437.13
F Harga Satuan Pekerjaan (D+E) 356,808.46

Pemasangan 1 m pipa PVC Ø 1200 mm


Kode AHSP = 8.4.1.16
A TENAGA
Pekerja C9 OH 2.303 80,000.00 184,240.00
Tukang pipa C24 OH 1.152 125,000.00 144,000.00
Mandor C47 OH 0.23 120,000.00 27,600.00
JUMLAH TENAGA KERJA 355,840.00
B BAHAN
Pipa PVC Ø 1200 mm C1362 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.327 1.00 0.33

JUMLAH HARGA ALAT 0.33


D Jumlah (A+B+C) 355,841.33
E Overhead & Profit 10% 35,584.13
F Harga Satuan Pekerjaan (D+E) 391,425.46

Pemasangan 1 m pipa HDPE Ø 63 mm


Kode AHSP = 8.4.1.17
A TENAGA
Pekerja C9 OH 0.035 80,000.00 2,800.00
Tukang pipa C24 OH 0.017 125,000.00 2,125.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 5,285.00
B BAHAN
Pipa HDPE Ø 63 mm C1363 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.019 1.00 0.02

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 5,286.02
E Overhead & Profit 10% 528.60
F Harga Satuan Pekerjaan (D+E) 5,814.62

Pemasangan 1 m pipa HDPE Ø 100 mm


Kode AHSP = 8.4.1.18
A TENAGA
Pekerja C9 OH 0.04 80,000.00 3,200.00
Tukang pipa C24 OH 0.02 125,000.00 2,500.00
Mandor C47 OH 0.004 120,000.00 480.00
JUMLAH TENAGA KERJA 6,180.00
B BAHAN
Pipa HDPE Ø 100 mm C1364 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.019 1.00 0.02

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 6,181.02
E Overhead & Profit 10% 618.10
F Harga Satuan Pekerjaan (D+E) 6,799.12

Pemasangan 1 m pipa HDPE Ø 125 mm


Kode AHSP = 8.4.1.19
A TENAGA
Pekerja C9 OH 0.045 80,000.00 3,600.00
Tukang pipa C24 OH 0.023 125,000.00 2,875.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 7,075.00
B BAHAN
Pipa HDPE Ø 125 mm C1365 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 m 1 1.00 1.00

JUMLAH HARGA ALAT 1.00


D Jumlah (A+B+C) 7,077.00
E Overhead & Profit 10% 707.70
F Harga Satuan Pekerjaan (D+E) 7,784.70

Pemasangan 1 m pipa HDPE Ø 150 mm


Kode AHSP = 8.4.1.20
A TENAGA
Pekerja C9 OH 0.062 80,000.00 4,960.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang pipa C24 OH 0.031 125,000.00 3,875.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 9,555.00
B BAHAN
Pipa HDPE Ø 150 mm C1366 m 1 1.00 1.00
-
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.019 1.00 0.02

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 9,556.02
E Overhead & Profit 10% 955.60
F Harga Satuan Pekerjaan (D+E) 10,511.62

Pemasangan 1 m pipa HDPE Ø 200 mm


Kode AHSP = 8.4.1.21
A TENAGA
Pekerja C9 OH 0.102 80,000.00 8,160.00
Tukang pipa C24 OH 0.051 125,000.00 6,375.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 15,735.00
B BAHAN
Pipa HDPE Ø 200 mm C1367 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.019 1.00 0.02

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 15,736.02
E Overhead & Profit 10% 1,573.60
F Harga Satuan Pekerjaan (D+E) 17,309.62

Pemasangan 1 m pipa HDPE Ø 250 mm


Kode AHSP = 8.4.1.22
A TENAGA
Pekerja C9 OH 0.133 80,000.00 10,640.00
Tukang pipa C24 OH 0.067 125,000.00 8,375.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 20,575.00
B BAHAN
Pipa HDPE Ø 250 mm C1368 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.042 1.00 0.04

JUMLAH HARGA ALAT 0.04


D Jumlah (A+B+C) 20,576.04
E Overhead & Profit 10% 2,057.60
F Harga Satuan Pekerjaan (D+E) 22,633.65

Pemasangan 1 m pipa HDPE Ø 300 mm


Kode AHSP = 8.4.1.23
A TENAGA
Pekerja C9 OH 0.17 80,000.00 13,600.00
Tukang pipa C24 OH 0.085 125,000.00 10,625.00
Mandor C47 OH 0.017 120,000.00 2,040.00
JUMLAH TENAGA KERJA 26,265.00
B BAHAN
Pipa HDPE Ø 300 mm C1369 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.065 1.00 0.07

JUMLAH HARGA ALAT 0.07


D Jumlah (A+B+C) 26,266.07
E Overhead & Profit 10% 2,626.61
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 28,892.67

Pemasangan 1 m pipa HDPE Ø 400 mm


Kode AHSP = 8.4.1.24
A TENAGA
Pekerja C9 OH 0.29 80,000.00 23,200.00
Tukang pipa C24 OH 0.145 125,000.00 18,125.00
Mandor C47 OH 0.029 120,000.00 3,480.00
JUMLAH TENAGA KERJA 44,805.00
B BAHAN
Pipa HDPE Ø 400 mm C1370 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.152 1.00 0.15

JUMLAH HARGA ALAT 0.15


D Jumlah (A+B+C) 44,806.15
E Overhead & Profit 10% 4,480.62
F Harga Satuan Pekerjaan (D+E) 49,286.77

Pemasangan 1 m pipa HDPE Ø 450 mm


Kode AHSP = 8.4.1.25
A TENAGA
Pekerja C9 OH 0.359 80,000.00 28,720.00
Tukang pipa C24 OH 0.18 125,000.00 22,500.00
Mandor C47 OH 0.036 120,000.00 4,320.00
JUMLAH TENAGA KERJA 55,540.00
B BAHAN
Pipa HDPE Ø 450 mm C1371 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.2 1.00 0.20

JUMLAH HARGA ALAT 0.20


D Jumlah (A+B+C) 55,541.20
E Overhead & Profit 10% 5,554.12
F Harga Satuan Pekerjaan (D+E) 61,095.32

Pemasangan 1 m pipa HDPE Ø 500 mm


Kode AHSP = 8.4.1.26
A TENAGA
Pekerja C9 OH 0.433 80,000.00 34,640.00
Tukang pipa C24 OH 0.216 125,000.00 27,000.00
Mandor C47 OH 0.043 120,000.00 5,160.00
JUMLAH TENAGA KERJA 66,800.00
B BAHAN
Pipa HDPE Ø 500 mm C1372 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.251 1.00 0.25

JUMLAH HARGA ALAT 0.25


D Jumlah (A+B+C) 66,801.25
E Overhead & Profit 10% 6,680.13
F Harga Satuan Pekerjaan (D+E) 73,481.38

Pemasangan 1 m pipa HDPE Ø 600 mm


Kode AHSP = 8.4.1.27
A TENAGA
Pekerja C9 OH 0.512 80,000.00 40,960.00
Tukang pipa C24 OH 0.256 125,000.00 32,000.00
Mandor C47 OH 0.051 120,000.00 6,120.00
JUMLAH TENAGA KERJA 79,080.00
B BAHAN
Pipa HDPE Ø 600 mm C1373 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.307 1.00 0.31

JUMLAH HARGA ALAT 0.31


D Jumlah (A+B+C) 79,081.31
E Overhead & Profit 10% 7,908.13
F Harga Satuan Pekerjaan (D+E) 86,989.44

Pemasangan 1 m pipa HDPE Ø 800 mm


Kode AHSP = 8.4.1.28
A TENAGA
Pekerja C9 OH 0.893 80,000.00 71,440.00
Tukang pipa C24 OH 0.446 125,000.00 55,750.00
Mandor C47 OH 0.089 120,000.00 10,680.00
JUMLAH TENAGA KERJA 137,870.00
B BAHAN
Pipa HDPE Ø 800 mm C1374 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.573 1.00 0.57

JUMLAH HARGA ALAT 0.57


D Jumlah (A+B+C) 137,871.57
E Overhead & Profit 10% 13,787.16
F Harga Satuan Pekerjaan (D+E) 151,658.73

Pemasangan 1 m pipa HDPE Ø 900 mm


Kode AHSP = 8.4.1.29
A TENAGA
Pekerja C9 OH 1.353 80,000.00 108,240.00
Tukang pipa C24 OH 0.677 125,000.00 84,625.00
Mandor C47 OH 0.135 120,000.00 16,200.00
JUMLAH TENAGA KERJA 209,065.00
B BAHAN
Pipa HDPE Ø 900 mm C1375 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.883 1.00 0.88

JUMLAH HARGA ALAT 0.88


D Jumlah (A+B+C) 209,066.88
E Overhead & Profit 10% 20,906.69
F Harga Satuan Pekerjaan (D+E) 229,973.57

Pemasangan 1 m pipa HDPE Ø 1000 mm


Kode AHSP = 8.4.1.30
A TENAGA
Pekerja C9 OH 1.659 80,000.00 132,720.00
Tukang pipa C24 OH 0.83 125,000.00 103,750.00
Mandor C47 OH 0.166 120,000.00 19,920.00
JUMLAH TENAGA KERJA 256,390.00
B BAHAN
Pipa HDPE Ø 1000 mm C1376 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.093 1.00 1.09

JUMLAH HARGA ALAT 1.09


D Jumlah (A+B+C) 256,392.09
E Overhead & Profit 10% 25,639.21
F Harga Satuan Pekerjaan (D+E) 282,031.30

Pemasangan 1 m pipa HDPE Ø 1100 mm


Kode AHSP = 8.4.1.31
A TENAGA
Pekerja C9 OH 1.818 80,000.00 145,440.00
Tukang pipa C24 OH 0.909 125,000.00 113,625.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.182 120,000.00 21,840.00
JUMLAH TENAGA KERJA 280,905.00
B BAHAN
Pipa HDPE Ø 1100 mm C1377 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.205 1.00 1.21

JUMLAH HARGA ALAT 1.21


D Jumlah (A+B+C) 280,907.21
E Overhead & Profit 10% 28,090.72
F Harga Satuan Pekerjaan (D+E) 308,997.93

Pemasangan 1 m pipa HDPE Ø 1200 mm


Kode AHSP = 8.4.1.32
A TENAGA
Pekerja C9 OH 2.37 80,000.00 189,600.00
Tukang pipa C24 OH 1.185 125,000.00 148,125.00
Mandor C47 OH 0.237 120,000.00 28,440.00
JUMLAH TENAGA KERJA 366,165.00
B BAHAN
Pipa HDPE Ø 1200 mm C1378 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.584 1.00 1.58

JUMLAH HARGA ALAT 1.58


D Jumlah (A+B+C) 366,167.58
E Overhead & Profit 10% 36,616.76
F Harga Satuan Pekerjaan (D+E) 402,784.34

Pemasangan 1 m pipa GIP Ø 63 mm


Kode AHSP = 8.4.1.33
A TENAGA
Pekerja C9 OH 0.345 80,000.00 27,600.00
Tukang pipa C24 OH 0.172 125,000.00 21,500.00
Mandor C47 OH 0.034 120,000.00 4,080.00
JUMLAH TENAGA KERJA 53,180.00
B BAHAN
Pipa GIP Ø 63 mm C1379 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 53,181.00
E Overhead & Profit 10% 5,318.10
F Harga Satuan Pekerjaan (D+E) 58,499.10

Pemasangan 1 m pipa GIP Ø 100 mm


Kode AHSP = 8.4.1.34
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang pipa C24 OH 0.2 125,000.00 25,000.00
Mandor C47 OH 0.04 120,000.00 4,800.00
JUMLAH TENAGA KERJA 61,800.00
B BAHAN
Pipa PVC Ø 90 mm C1348 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 61,801.00
E Overhead & Profit 10% 6,180.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 67,981.10

Pemasangan 1 m pipa GIP Ø 125 mm


Kode AHSP = 8.4.1.35
A TENAGA
Pekerja C9 OH 0.448 80,000.00 35,840.00
Tukang pipa C24 OH 0.224 125,000.00 28,000.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 69,240.00
B BAHAN
Pipa GIP Ø 125 mm C1381 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 69,241.00
E Overhead & Profit 10% 6,924.10
F Harga Satuan Pekerjaan (D+E) 76,165.10

Pemasangan 1 m pipa GIP Ø 150 mm


Kode AHSP = 8.4.1.36
A TENAGA
Pekerja C9 OH 0.506 80,000.00 40,480.00
Tukang pipa C24 OH 0.253 125,000.00 31,625.00
Mandor C47 OH 0.051 120,000.00 6,120.00
JUMLAH TENAGA KERJA 78,225.00
B BAHAN
Pipa GIP Ø 150 mm C1382 m 1 1.00 1.00
-
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 78,226.00
E Overhead & Profit 10% 7,822.60
F Harga Satuan Pekerjaan (D+E) 86,048.60

Pemasangan 1 m pipa GIP Ø 200 mm


Kode AHSP = 8.4.1.37
A TENAGA
Pekerja C9 OH 0.796 80,000.00 63,680.00
Tukang pipa C24 OH 0.398 125,000.00 49,750.00
Mandor C47 OH 0.08 120,000.00 9,600.00
JUMLAH TENAGA KERJA 123,030.00
B BAHAN
Pipa GIP Ø 200 mm C1383 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 123,031.00
E Overhead & Profit 10% 12,303.10
F Harga Satuan Pekerjaan (D+E) 135,334.10

Pemasangan 1 m pipa GIP Ø 250 mm


Kode AHSP = 8.4.1.38
A TENAGA
Pekerja C9 OH 0.949 80,000.00 75,920.00
Tukang pipa C24 OH 0.475 125,000.00 59,375.00
Mandor C47 OH 0.095 120,000.00 11,400.00
JUMLAH TENAGA KERJA 146,695.00
B BAHAN
Pipa GIP Ø 250 mm C1384 m 1 759,000.00 759,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 759,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 905,695.00
E Overhead & Profit 10% 90,569.50
F Harga Satuan Pekerjaan (D+E) 996,264.50

Pemasangan 1 m pipa GIP Ø 300 mm


Kode AHSP = 8.4.1.39
A TENAGA
Pekerja C9 OH 0.958 80,000.00 76,640.00
Tukang pipa C24 OH 0.479 125,000.00 59,875.00
Mandor C47 OH 0.096 120,000.00 11,520.00
JUMLAH TENAGA KERJA 148,035.00
B BAHAN
Pipa GIP Ø 300 mm C1385 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 148,036.00
E Overhead & Profit 10% 14,803.60
F Harga Satuan Pekerjaan (D+E) 162,839.60

Pemasangan 1 m pipa GIP Ø 400 mm


Kode AHSP = 8.4.1.40
A TENAGA
Pekerja C9 OH 1.212 80,000.00 96,960.00
Tukang pipa C24 OH 0.606 125,000.00 75,750.00
Mandor C47 OH 0.121 120,000.00 14,520.00
JUMLAH TENAGA KERJA 187,230.00
B BAHAN
Pipa GIP Ø 400 mm C1386 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 187,231.00
E Overhead & Profit 10% 18,723.10
F Harga Satuan Pekerjaan (D+E) 205,954.10

Pemasangan 1 m pipa GIP Ø 450 mm


Kode AHSP = 8.4.1.41
A TENAGA
Pekerja C9 OH 1.353 80,000.00 108,240.00
Tukang pipa C24 OH 0.676 125,000.00 84,500.00
Mandor C47 OH 0.135 120,000.00 16,200.00
JUMLAH TENAGA KERJA 208,940.00
B BAHAN
Pipa GIP Ø 450 mm C1387 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 208,941.00
E Overhead & Profit 10% 20,894.10
F Harga Satuan Pekerjaan (D+E) 229,835.10

Pemasangan 1 m pipa GIP Ø 500 mm


Kode AHSP = 8.4.1.42
A TENAGA
Pekerja C9 OH 1.469 80,000.00 117,520.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang pipa C24 OH 0.735 125,000.00 91,875.00
Mandor C47 OH 0.147 120,000.00 17,640.00
JUMLAH TENAGA KERJA 227,035.00
B BAHAN
Pipa GIP Ø 500 mm C1388 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 227,036.00
E Overhead & Profit 10% 22,703.60
F Harga Satuan Pekerjaan (D+E) 249,739.60

Pemasangan 1 m pipa GIP Ø 600 mm


Kode AHSP = 8.4.1.43
A TENAGA
Pekerja C9 OH 1.327 80,000.00 106,160.00
Tukang pipa C24 OH 0.664 125,000.00 83,000.00
Mandor C47 OH 0.133 120,000.00 15,960.00
JUMLAH TENAGA KERJA 205,120.00
B BAHAN
Pipa GIP Ø 600 mm C1389 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 205,121.00
E Overhead & Profit 10% 20,512.10
F Harga Satuan Pekerjaan (D+E) 225,633.10

Pemasangan 1 m pipa GIP Ø 800 mm


Kode AHSP = 8.4.1.44
A TENAGA
Pekerja C9 OH 2.327 80,000.00 186,160.00
Tukang pipa C24 OH 1.163 125,000.00 145,375.00
Mandor C47 OH 0.233 120,000.00 27,960.00
JUMLAH TENAGA KERJA 359,495.00
B BAHAN
Pipa GIP Ø 800 mm C1390 m 1 1.00 1.00

JUMLAH HARGA BAHAN -


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.25 1.00 0.25

JUMLAH HARGA ALAT 0.25


D Jumlah (A+B+C) 359,495.25
E Overhead & Profit 10% 35,949.53
F Harga Satuan Pekerjaan (D+E) 395,444.78

Pemasangan 1 m pipa GIP Ø 900 mm


Kode AHSP = 8.4.1.45
A TENAGA
Pekerja C9 OH 2.623 80,000.00 209,840.00
Tukang pipa C24 OH 1.312 125,000.00 164,000.00
Mandor C47 OH 0.262 120,000.00 31,440.00
JUMLAH TENAGA KERJA 405,280.00
B BAHAN
Pipa GIP Ø 900 mm C1391 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 405,281.00
E Overhead & Profit 10% 40,528.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 445,809.10

Pemasangan 1 m pipa GIP Ø 1000 mm


Kode AHSP = 8.4.1.46
A TENAGA
Pekerja C9 OH 2.911 80,000.00 232,880.00
Tukang pipa C24 OH 1.456 125,000.00 182,000.00
Mandor C47 OH 0.291 120,000.00 34,920.00
JUMLAH TENAGA KERJA 449,800.00
B BAHAN
Pipa GIP Ø 1000 mm C1392 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 449,801.00
E Overhead & Profit 10% 44,980.10
F Harga Satuan Pekerjaan (D+E) 494,781.10

Pemasangan 1 m pipa GIP Ø 1100 mm


Kode AHSP = 8.4.1.47
A TENAGA
Pekerja C9 OH 3.2 80,000.00 256,000.00
Tukang pipa C24 OH 1.6 125,000.00 200,000.00
Mandor C47 OH 0.32 120,000.00 38,400.00
JUMLAH TENAGA KERJA 494,400.00
B BAHAN
Pipa GIP Ø 1100 mm C1393 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.327 1.00 0.33

JUMLAH HARGA ALAT 0.33


D Jumlah (A+B+C) 494,401.33
E Overhead & Profit 10% 49,440.13
F Harga Satuan Pekerjaan (D+E) 543,841.46

Pemasangan 1 m pipa GIP Ø 1200 mm


Kode AHSP = 8.4.1.48
A TENAGA
Pekerja C9 OH 3.488 80,000.00 279,040.00
Tukang pipa C24 OH 1.744 125,000.00 218,000.00
Mandor C47 OH 0.349 120,000.00 41,880.00
JUMLAH TENAGA KERJA 538,920.00
B BAHAN
Pipa GIP Ø 1200 mm C1394 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0 1.00 -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 538,921.00
E Overhead & Profit 10% 53,892.10
F Harga Satuan Pekerjaan (D+E) 592,813.10

Pemasangan 1 m pipa DCI Ø 100 mm


Kode AHSP = 8.4.1.49
A TENAGA
Pekerja C9 OH 0.489 80,000.00 39,120.00
Tukang pipa C24 OH 0.098 125,000.00 12,250.00
Mandor C47 OH 0.049 120,000.00 5,880.00
JUMLAH TENAGA KERJA 57,250.00
B BAHAN
Pipa DCI Ø 100 mm C1395 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.38 1.00 0.38

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 57,251.38
E Overhead & Profit 10% 5,725.14
F Harga Satuan Pekerjaan (D+E) 62,976.52

Pemasangan 1 m pipa DCI Ø 125 mm


Kode AHSP = 8.4.1.50
A TENAGA
Pekerja C9 OH 0.547 80,000.00 43,760.00
Tukang pipa C24 OH 0.109 125,000.00 13,625.00
Mandor C47 OH 0.055 120,000.00 6,600.00
JUMLAH TENAGA KERJA 63,985.00
B BAHAN
Pipa DCI Ø 125 mm C1396 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.38 1.00 0.38

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 63,986.38
E Overhead & Profit 10% 6,398.64
F Harga Satuan Pekerjaan (D+E) 70,385.02

Pemasangan 1 m pipa DCI Ø 150 mm


Kode AHSP = 8.4.1.51
A TENAGA
Pekerja C9 OH 0.613 80,000.00 49,040.00
Tukang pipa C24 OH 0.123 125,000.00 15,375.00
Mandor C47 OH 0.061 120,000.00 7,320.00
JUMLAH TENAGA KERJA 71,735.00
B BAHAN
Pipa DCI Ø 150 mm C1397 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.38 1.00 0.38

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 71,736.38
E Overhead & Profit 10% 7,173.64
F Harga Satuan Pekerjaan (D+E) 78,910.02

Pemasangan 1 m pipa DCI Ø 200 mm


Kode AHSP = 8.4.1.52
A TENAGA
Pekerja C9 OH 0.855 80,000.00 68,400.00
Tukang pipa C24 OH 0.171 125,000.00 21,375.00
Mandor C47 OH 0.085 120,000.00 10,200.00
JUMLAH TENAGA KERJA 99,975.00
B BAHAN
Pipa DCI Ø 200 mm C1398 m 1 1.00 1.00
-
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.38 1.00 0.38

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 99,976.38
E Overhead & Profit 10% 9,997.64
F Harga Satuan Pekerjaan (D+E) 109,974.02

Pemasangan 1 m pipa DCI Ø 250 mm


Kode AHSP = 8.4.1.53
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.951 80,000.00 76,080.00
Tukang pipa C24 OH 0.19 125,000.00 23,750.00
Mandor C47 OH 0.095 120,000.00 11,400.00
JUMLAH TENAGA KERJA 111,230.00
B BAHAN
Pipa DCI Ø 250 mm C1399 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.05 1.00 0.05

JUMLAH HARGA ALAT 0.05


D Jumlah (A+B+C) 111,231.05
E Overhead & Profit 10% 11,123.11
F Harga Satuan Pekerjaan (D+E) 122,354.16

Pemasangan 1 m pipa DCI Ø 300 mm


Kode AHSP = 8.4.1.54
A TENAGA
Pekerja C9 OH 0.973 80,000.00 77,840.00
Tukang pipa C24 OH 0.195 125,000.00 24,375.00
Mandor C47 OH 0.097 120,000.00 11,640.00
JUMLAH TENAGA KERJA 113,855.00
B BAHAN
Pipa DCI Ø 300 mm C1400 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.071 1.00 0.07

JUMLAH HARGA ALAT 0.07


D Jumlah (A+B+C) 113,856.07
E Overhead & Profit 10% 11,385.61
F Harga Satuan Pekerjaan (D+E) 125,241.68

Pemasangan 1 m pipa DCI Ø 400 mm


Kode AHSP = 8.4.1.55
A TENAGA
Pekerja C9 OH 1.545 80,000.00 123,600.00
Tukang pipa C24 OH 0.309 125,000.00 38,625.00
Operator alat berat C31 OH 0.093 200,000.00 18,600.00
Mandor C47 OH 0.154 120,000.00 18,480.00
JUMLAH TENAGA KERJA 199,305.00
B BAHAN
Pipa DCI Ø 400 mm C1401 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.023 450,000.00 10,350.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.031 1.00 0.03

JUMLAH HARGA ALAT 10,350.03


D Jumlah (A+B+C) 209,656.03
E Overhead & Profit 10% 20,965.60
F Harga Satuan Pekerjaan (D+E) 230,621.63

Pemasangan 1 m pipa DCI Ø 450 mm


Kode AHSP = 8.4.1.56
A TENAGA
Pekerja C9 OH 1.813 80,000.00 145,040.00
Tukang pipa C24 OH 0.363 125,000.00 45,375.00
Operator alat berat C31 OH 0.143 200,000.00 28,600.00
Mandor C47 OH 0.181 120,000.00 21,720.00
JUMLAH TENAGA KERJA 240,735.00
B BAHAN
Pipa DCI Ø 450 mm C1402 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.029 450,000.00 13,050.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.039 1.00 0.04

JUMLAH HARGA ALAT 13,050.04


D Jumlah (A+B+C) 253,786.04
E Overhead & Profit 10% 25,378.60
F Harga Satuan Pekerjaan (D+E) 279,164.64

Pemasangan 1 m pipa DCI Ø 500 mm


Kode AHSP = 8.4.1.57
A TENAGA
Pekerja C9 OH 2.047 80,000.00 163,760.00
Tukang pipa C24 OH 0.409 125,000.00 51,125.00
Operator alat berat C31 OH 0.193 200,000.00 38,600.00
Mandor C47 OH 0.205 120,000.00 24,600.00
JUMLAH TENAGA KERJA 278,085.00
B BAHAN
Pipa DCI Ø 500 mm C1403 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.034 450,000.00 15,300.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.045 1.00 0.05

JUMLAH HARGA ALAT 15,300.05


D Jumlah (A+B+C) 293,386.05
E Overhead & Profit 10% 29,338.60
F Harga Satuan Pekerjaan (D+E) 322,724.65

Pemasangan pipa 1 m DCI Ø 600 mm


Kode AHSP = 8.4.1.58
A TENAGA
Pekerja C9 OH 2.011 80,000.00 160,880.00
Tukang pipa C24 OH 0.402 125,000.00 50,250.00
Operator alat berat C31 OH 0.293 200,000.00 58,600.00
Mandor C47 OH 0.201 120,000.00 24,120.00
JUMLAH TENAGA KERJA 293,850.00
B BAHAN
Pipa DCI Ø 600 mm C1404 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.058 450,000.00 26,100.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.077 1.00 0.08

JUMLAH HARGA ALAT 26,100.08


D Jumlah (A+B+C) 319,951.08
E Overhead & Profit 10% 31,995.11
F Harga Satuan Pekerjaan (D+E) 351,946.18

Pemasangan 1 m pipa DCI Ø800 mm


Kode AHSP = 8.4.1.59
A TENAGA
Pekerja C9 OH 3.859 80,000.00 308,720.00
Tukang pipa C24 OH 0.772 125,000.00 96,500.00
Operator alat berat C31 OH 0.493 200,000.00 98,600.00
Mandor C47 OH 0.386 120,000.00 46,320.00
JUMLAH TENAGA KERJA 550,140.00
B BAHAN
Pipa DCI Ø 800 mm C1405 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.084 450,000.00 37,800.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.225 1.00 0.23

JUMLAH HARGA ALAT 37,800.23


D Jumlah (A+B+C) 587,941.23
E Overhead & Profit 10% 58,794.12
F Harga Satuan Pekerjaan (D+E) 646,735.35
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m pipa DCI Ø900 mm
Kode AHSP = 8.4.1.60
A TENAGA
Pekerja C9 OH 4.995 80,000.00 399,600.00
Tukang pipa C24 OH 0.999 125,000.00 124,875.00
Operator alat berat C31 OH 0.593 200,000.00 118,600.00
Mandor C47 OH 0.499 120,000.00 59,880.00
JUMLAH TENAGA KERJA 702,955.00
B BAHAN
Pipa DCI Ø 900 mm C1406 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.093 450,000.00 41,850.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.248 1.00 0.25

JUMLAH HARGA ALAT 41,850.25


D Jumlah (A+B+C) 744,806.25
E Overhead & Profit 10% 74,480.62
F Harga Satuan Pekerjaan (D+E) 819,286.87

Pemasangan 1 m pipa DCI Ø1000 mm


Kode AHSP = 8.4.1.61
A TENAGA
Pekerja C9 OH 5.931 80,000.00 474,480.00
Tukang pipa C24 OH 1.186 125,000.00 148,250.00
Operator alat berat C31 OH 0.793 200,000.00 158,600.00
Mandor C47 OH 0.693 120,000.00 83,160.00
JUMLAH TENAGA KERJA 864,490.00
B BAHAN
Pipa DCI Ø 1000 mm C1407 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.112 450,000.00 50,400.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.298 1.00 0.30

JUMLAH HARGA ALAT 50,400.30


D Jumlah (A+B+C) 914,891.30
E Overhead & Profit 10% 91,489.13
F Harga Satuan Pekerjaan (D+E) 1,006,380.43

Pemasangan 1 m pipa DCI Ø1100 mm


Kode AHSP = 8.4.1.62
A TENAGA
Pekerja C9 OH 6.949 80,000.00 555,920.00
Tukang pipa C24 OH 1.39 125,000.00 173,750.00
Operator alat berat C31 OH 0.793 200,000.00 158,600.00
Mandor C47 OH 0.695 120,000.00 83,400.00
JUMLAH TENAGA KERJA 971,670.00
B BAHAN
Pipa DCI Ø 1100 mm C1408 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.152 450,000.00 68,400.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.304 1.00 0.30

JUMLAH HARGA ALAT 68,400.30


D Jumlah (A+B+C) 1,040,071.30
E Overhead & Profit 10% 104,007.13
F Harga Satuan Pekerjaan (D+E) 1,144,078.43

Pemasangan 1 m pipa DCI Ø1200 mm


Kode AHSP = 8.4.1.63
A TENAGA
Pekerja C9 OH 8.056 80,000.00 644,480.00
Tukang pipa C24 OH 1.611 125,000.00 201,375.00
Operator alat berat C31 OH 0.893 200,000.00 178,600.00
Mandor C47 OH 0.806 120,000.00 96,720.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 1,121,175.00
B BAHAN
Pipa DCI Ø 1200 mm C1409 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.18 450,000.00 81,000.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.36 1.00 0.36

JUMLAH HARGA ALAT 81,000.36


D Jumlah (A+B+C) 1,202,176.36
E Overhead & Profit 10% 120,217.64
F Harga Satuan Pekerjaan (D+E) 1,322,394.00

Pemasangan 1 m pipa baja Ø 63 mm


Kode AHSP = 8.4.1.64
A TENAGA
Pekerja C9 OH 0.499 80,000.00 39,920.00
Tukang pipa C24 OH 0.1 125,000.00 12,500.00
Mandor C47 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 58,420.00
B BAHAN
Pipa Baja Ø 63 mm C1410 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 58,421.00
E Overhead & Profit 10% 5,842.10
F Harga Satuan Pekerjaan (D+E) 64,263.10

Pemasangan 1 m pipa baja Ø 100 mm


Kode AHSP = 8.4.1.65
A TENAGA
Pekerja C9 OH 0.579 80,000.00 46,320.00
Tukang pipa C24 OH 0.116 125,000.00 14,500.00
Mandor C47 OH 0.058 120,000.00 6,960.00
JUMLAH TENAGA KERJA 67,780.00
B BAHAN
Pipa Baja Ø 100 mm C1411 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 67,781.00
E Overhead & Profit 10% 6,778.10
F Harga Satuan Pekerjaan (D+E) 74,559.10

Pemasangan 1 m pipa baja Ø 125 mm


Kode AHSP = 8.4.1.66
A TENAGA
Pekerja C9 OH 0.648 80,000.00 51,840.00
Tukang pipa C24 OH 0.13 125,000.00 16,250.00
Mandor C47 OH 0.065 120,000.00 7,800.00
JUMLAH TENAGA KERJA 75,890.00
B BAHAN
Pipa Baja Ø 125 mm C1412 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 75,891.00
E Overhead & Profit 10% 7,589.10
F Harga Satuan Pekerjaan (D+E) 83,480.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 m pipa baja Ø 150 mm


Kode AHSP = 8.4.1.67
A TENAGA
Pekerja C9 OH 0.708 80,000.00 56,640.00
Tukang pipa C24 OH 0.142 125,000.00 17,750.00
Mandor C47 OH 0.071 120,000.00 8,520.00
JUMLAH TENAGA KERJA 82,910.00
B BAHAN
Pipa Baja Ø 150 mm C1413 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 82,911.00
E Overhead & Profit 10% 8,291.10
F Harga Satuan Pekerjaan (D+E) 91,202.10

Pemasangan 1 m pipa baja Ø 200 mm


Kode AHSP = 8.4.1.68
A TENAGA
Pekerja C9 OH 1.113 80,000.00 89,040.00
Tukang pipa C24 OH 0.223 125,000.00 27,875.00
Mandor C47 OH 0.111 120,000.00 13,320.00
JUMLAH TENAGA KERJA 130,235.00
B BAHAN
Pipa Baja Ø 200 mm C1414 m 1 1.00 1.00

JUMLAH HARGA BAHAN -


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 130,235.00
E Overhead & Profit 10% 13,023.50
F Harga Satuan Pekerjaan (D+E) 143,258.50

Pemasangan pipa baja Ø 250 mm


Kode AHSP = 8.4.1.69
A TENAGA
Pekerja C9 OH 1.325 80,000.00 106,000.00
Tukang pipa C24 OH 0.265 125,000.00 33,125.00
Mandor C47 OH 0.133 120,000.00 15,960.00
JUMLAH TENAGA KERJA 155,085.00
B BAHAN
Pipa Baja Ø 250 mm C1415 Unit 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 155,086.00
E Overhead & Profit 10% 15,508.60
F Harga Satuan Pekerjaan (D+E) 170,594.60

Pemasangan 1 m pipa baja Ø 300 mm


Kode AHSP = 8.4.1.70
A TENAGA
Pekerja C9 OH 1.415 80,000.00 113,200.00
Tukang pipa C24 OH 0.283 125,000.00 35,375.00
Mandor C47 OH 0.141 120,000.00 16,920.00
JUMLAH TENAGA KERJA 165,495.00
B BAHAN
Pipa Baja Ø 300 mm C1416 Unit 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.004 1.00 0.00

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 165,496.00
E Overhead & Profit 10% 16,549.60
F Harga Satuan Pekerjaan (D+E) 182,045.60

Pemasangan 1 m pipa baja Ø 400 mm


Kode AHSP = 8.4.1.71
A TENAGA
Pekerja C9 OH 2.366 80,000.00 189,280.00
Tukang pipa C24 OH 0.473 125,000.00 59,125.00
Mandor C47 OH 0.237 120,000.00 28,440.00
JUMLAH TENAGA KERJA 276,845.00
B BAHAN
Pipa Baja Ø 400 mm C1417 Lbr 0.51 1.00 0.51

JUMLAH HARGA BAHAN 0.51


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.027 1.00 0.03

JUMLAH HARGA ALAT 0.03


D Jumlah (A+B+C) 276,845.54
E Overhead & Profit 10% 27,684.55
F Harga Satuan Pekerjaan (D+E) 304,530.09

Pemasangan 1 m pipa baja Ø 450 mm


Kode AHSP = 8.4.1.72
A TENAGA
Pekerja C9 OH 2.231 80,000.00 178,480.00
Tukang pipa C24 OH 0.446 125,000.00 55,750.00
Mandor C47 OH 0.223 120,000.00 26,760.00
JUMLAH TENAGA KERJA 260,990.00
B BAHAN
Pipa Baja Ø 450 mm C1418 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.026 450,000.00 11,700.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.037 1.00 0.04

JUMLAH HARGA ALAT 11,700.04


D Jumlah (A+B+C) 272,691.04
E Overhead & Profit 10% 27,269.10
F Harga Satuan Pekerjaan (D+E) 299,960.14

Pemasangan 1 m pipa baja Ø 500 mm


Kode AHSP = 8.4.1.73
A TENAGA
Pekerja C9 OH 2.432 80,000.00 194,560.00
Tukang pipa C24 OH 0.486 125,000.00 60,750.00
Mandor C47 OH 0.243 120,000.00 29,160.00
JUMLAH TENAGA KERJA 284,470.00
B BAHAN
Pipa Baja Ø 500 mm C1419 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.029 450,000.00 13,050.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.045 1.00 0.05

JUMLAH HARGA ALAT 13,050.05


D Jumlah (A+B+C) 297,521.05
E Overhead & Profit 10% 29,752.10
F Harga Satuan Pekerjaan (D+E) 327,273.15

Pemasangan 1 m pipa baja Ø 600 mm


Kode AHSP = 8.4.1.74
A TENAGA
Pekerja C9 OH 2.208 80,000.00 176,640.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Tukang pipa C24 OH 0.442 125,000.00 55,250.00
Mandor C47 OH 0.221 120,000.00 26,520.00
JUMLAH TENAGA KERJA 258,410.00
B BAHAN
Pipa Baja Ø 450 mm C1418 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.027 450,000.00 12,150.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.039 1.00 0.04

JUMLAH HARGA ALAT 12,150.04


D Jumlah (A+B+C) 270,561.04
E Overhead & Profit 10% 27,056.10
F Harga Satuan Pekerjaan (D+E) 297,617.14

Pemasangan 1 m pipa baja Ø 800 mm


Kode AHSP = 8.4.1.75
A TENAGA
Pekerja C9 OH 3.897 80,000.00 311,760.00
Tukang pipa C24 OH 0.779 125,000.00 97,375.00
Mandor C47 OH 0.39 120,000.00 46,800.00
JUMLAH TENAGA KERJA 455,935.00
B BAHAN
Pipa Baja Ø 800 mm C1421 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.046 450,000.00 20,700.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.098 1.00 0.10

JUMLAH HARGA ALAT 20,700.10


D Jumlah (A+B+C) 476,636.10
E Overhead & Profit 10% 47,663.61
F Harga Satuan Pekerjaan (D+E) 524,299.71

Pemasangan 1 m pipa baja Ø 900 mm


Kode AHSP = 8.4.1.76
A TENAGA
Pekerja C9 OH 4.403 80,000.00 352,240.00
Tukang pipa C24 OH 0.081 125,000.00 10,125.00
Mandor C47 OH 0.44 120,000.00 52,800.00
JUMLAH TENAGA KERJA 415,165.00
B BAHAN
Pipa Baja Ø 900 mm C1422 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.052 450,000.00 23,400.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.115 1.00 0.12

JUMLAH HARGA ALAT 23,400.12


D Jumlah (A+B+C) 438,566.12
E Overhead & Profit 10% 43,856.61
F Harga Satuan Pekerjaan (D+E) 482,422.73

Pemasangan 1 m pipa baja Ø 1000 mm


Kode AHSP = 8.4.1.77
A TENAGA
Pekerja C9 OH 4.895 80,000.00 391,600.00
Tukang pipa C24 OH 0.979 125,000.00 122,375.00
Mandor C47 OH 0.489 120,000.00 58,680.00
JUMLAH TENAGA KERJA 572,655.00
B BAHAN
Pipa Baja Ø 1000 mm C1423 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.058 450,000.00 26,100.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.133 1.00 0.13
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT 26,100.13


D Jumlah (A+B+C) 598,756.13
E Overhead & Profit 10% 59,875.61
F Harga Satuan Pekerjaan (D+E) 658,631.75

Pemasangan 1 m pipa baja Ø 1100 mm


Kode AHSP = 8.4.1.78
A TENAGA
Pekerja C9 OH 5.387 80,000.00 430,960.00
Tukang pipa C24 OH 1.077 125,000.00 134,625.00
Mandor C47 OH 0.539 120,000.00 64,680.00
JUMLAH TENAGA KERJA 630,265.00
B BAHAN
Pipa Baja Ø 450 mm C1418 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.064 450,000.00 28,800.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.15 1.00 0.15

JUMLAH HARGA ALAT 28,800.15


D Jumlah (A+B+C) 659,066.15
E Overhead & Profit 10% 65,906.62
F Harga Satuan Pekerjaan (D+E) 724,972.77

Pemasangan 1 m pipa baja Ø 1200 mm


Kode AHSP = 8.4.1.79
A TENAGA
Pekerja C9 OH 5.897 80,000.00 471,760.00
Tukang pipa C24 OH 1.176 125,000.00 147,000.00
Mandor C47 OH 0.588 120,000.00 70,560.00
JUMLAH TENAGA KERJA 689,320.00
B BAHAN
Pipa Baja Ø 450 mm C1418 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Exavator C1587 hari 0.07 450,000.00 31,500.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.167 1.00 0.17

JUMLAH HARGA ALAT 31,500.17


D Jumlah (A+B+C) 720,821.17
E Overhead & Profit 10% 72,082.12
F Harga Satuan Pekerjaan (D+E) 792,903.28

Pemotongan 1 buah pipa PVC Ø 63 mm


Kode AHSP = 8.4.2.1
A TENAGA
Pekerja C9 OH 0.005 80,000.00 400.00
Tukang Pipa C24 OH 0.002 125,000.00 250.00
Mandor C47 OH 0.001 120,000.00 60.00
JUMLAH TENAGA KERJA 710.00
B BAHAN
Pipa PVC Ø 63 mm C1347 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.003 1.00 0.00
/saw

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 711.00
E Overhead & Profit 10% 71.10
F Harga Satuan Pekerjaan (D+E) 782.10

Pemotongan 1 m pipa PVC Ø 90 mm


Kode AHSP = 8.4.2.2
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.014 80,000.00 1,120.00
Tukang Pipa C24 OH 0.007 125,000.00 875.00
Mandor C47 OH 0.001 120,000.00 120.00
JUMLAH TENAGA KERJA 2,115.00
B BAHAN
Pipa PVC Ø 90 mm C1348 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.003 1.00 0.00
/saw

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 2,116.00
E Overhead & Profit 10% 211.60
F Harga Satuan Pekerjaan (D+E) 2,327.60

Pemotongan 1 buah pipa PVC Ø 110 mm


Kode AHSP = 8.4.2.3
A TENAGA
Pekerja C9 OH 0.022 80,000.00 1,760.00
Tukang Pipa C24 OH 0.011 125,000.00 1,375.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 3,375.00
B BAHAN
Pipa PVC Ø 110 mm C1349 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.003 1.00 0.00
/saw

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 3,376.00
E Overhead & Profit 10% 337.60
F Harga Satuan Pekerjaan (D+E) 3,713.60

Pemotongan 1 buah pipa PVC Ø 150 mm


Kode AHSP = 8.4.2.4
A TENAGA
Pekerja C9 OH 0.031 80,000.00 2,480.00
Tukang Pipa C24 OH 0.015 125,000.00 1,875.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 4,715.00
B BAHAN
Pipa PVC Ø 150 mm C1350 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.003 1.00 0.00
/saw

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 4,716.00
E Overhead & Profit 10% 471.60
F Harga Satuan Pekerjaan (D+E) 5,187.60

Pemotongan 1 buah pipa PVC Ø 200 mm


Kode AHSP = 8.4.2.5
A TENAGA
Pekerja C9 OH 0.081 80,000.00 6,480.00
Tukang Pipa C24 OH 0.040 125,000.00 5,000.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 12,440.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pipa PVC Ø 200 mm C1351 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.017 1.00 0.02
/saw

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 12,441.02
E Overhead & Profit 10% 1,244.10
F Harga Satuan Pekerjaan (D+E) 13,685.12

Pemotongan 1 buah pipa PVC Ø 250 mm


Kode AHSP = 8.4.2.6
A TENAGA
Pekerja C9 OH 0.128 80,000.00 10,240.00
Tukang Pipa C24 OH 0.064 125,000.00 8,000.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 19,800.00
B BAHAN
Pipa PVC Ø 250 mm C1352 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.030 1.00 0.03
/saw

JUMLAH HARGA ALAT 0.03


D Jumlah (A+B+C) 19,801.03
E Overhead & Profit 10% 1,980.10
F Harga Satuan Pekerjaan (D+E) 21,781.13

Pemotongan 1 buah pipa PVC Ø 300 mm


Kode AHSP = 8.4.2.7
A TENAGA
Pekerja C9 OH 0.155 80,000.00 12,400.00
Tukang Pipa C24 OH 0.077 125,000.00 9,625.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 23,825.00
B BAHAN
Pipa PVC Ø 300 mm C1353 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.037 1.00 0.04
/saw

JUMLAH HARGA ALAT 0.04


D Jumlah (A+B+C) 23,826.04
E Overhead & Profit 10% 2,382.60
F Harga Satuan Pekerjaan (D+E) 26,208.64

Pemotongan 1 buah pipa PVC Ø 400 mm


Kode AHSP = 8.4.2.8
A TENAGA
Pekerja C9 OH 0.331 80,000.00 26,480.00
Tukang Pipa C24 OH 0.166 125,000.00 20,750.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 51,190.00
B BAHAN
Pipa PVC Ø 400 mm C1354 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Peralatan potong pipa
T1/manual (gergaji) C1312 Hari 0.086 1.00 0.09
/saw

JUMLAH HARGA ALAT 0.09


D Jumlah (A+B+C) 51,191.09
E Overhead & Profit 10% 5,119.11
F Harga Satuan Pekerjaan (D+E) 56,310.19

Pemotongan 1 buah pipa PVC Ø 450 mm


Kode AHSP = 8.4.2.9
A TENAGA
Pekerja C9 OH 0.420 80,000.00 33,600.00
Tukang Pipa C24 OH 0.210 125,000.00 26,250.00
Mandor C47 OH 0.042 120,000.00 5,040.00
JUMLAH TENAGA KERJA 64,890.00
B BAHAN
Pipa PVC Ø 450 mm C1355 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.054 2.00 0.11
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.11


D Jumlah (A+B+C) 64,891.11
E Overhead & Profit 10% 6,489.11
F Harga Satuan Pekerjaan (D+E) 71,380.22

Pemotongan 1 buah pipa PVC Ø 500 mm


Kode AHSP = 8.4.2.10
A TENAGA
Pekerja C9 OH 0.518 80,000.00 41,440.00
Tukang Pipa C24 OH 0.259 125,000.00 32,375.00
Mandor C47 OH 0.052 120,000.00 6,240.00
JUMLAH TENAGA KERJA 80,055.00
B BAHAN
Pipa PVC Ø 500 mm C1356 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.069 2.00 0.14
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.14


D Jumlah (A+B+C) 80,056.14
E Overhead & Profit 10% 8,005.61
F Harga Satuan Pekerjaan (D+E) 88,061.75

Pemotongan 1 buah pipa PVC Ø 600 mm


Kode AHSP = 8.4.2.11
A TENAGA
Pekerja C9 OH 0.623 80,000.00 49,840.00
Tukang Pipa C24 OH 0.311 125,000.00 38,875.00
Mandor C47 OH 0.062 120,000.00 7,440.00
JUMLAH TENAGA KERJA 96,155.00
B BAHAN
Pipa PVC Ø 600 mm C1357 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.086 2.00 0.17
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.17


D Jumlah (A+B+C) 96,156.17
E Overhead & Profit 10% 9,615.62
F Harga Satuan Pekerjaan (D+E) 105,771.79
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemotongan 1 buah pipa PVC Ø 800 mm


Kode AHSP = 8.4.2.12
A TENAGA
Pekerja C9 OH 1.089 80,000.00 87,120.00
Tukang Pipa C24 OH 0.545 125,000.00 68,125.00
Mandor C47 OH 0.109 120,000.00 13,080.00
JUMLAH TENAGA KERJA 168,325.00
B BAHAN
Pipa PVC Ø 800 mm C1358 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.160 2.00 0.32
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.32


D Jumlah (A+B+C) 168,326.32
E Overhead & Profit 10% 16,832.63
F Harga Satuan Pekerjaan (D+E) 185,158.95

Pemotongan 1 buah pipa PVC Ø 900 mm


Kode AHSP = 8.4.2.13
A TENAGA
Pekerja C9 OH 1.141 80,000.00 91,280.00
Tukang Pipa C24 OH 0.571 125,000.00 71,375.00
Mandor C47 OH 0.114 120,000.00 13,680.00
JUMLAH TENAGA KERJA 176,335.00
B BAHAN
Pipa PVC Ø 900 mm C1359 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.168 2.00 0.34
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.34


D Jumlah (A+B+C) 176,336.34
E Overhead & Profit 10% 17,633.63
F Harga Satuan Pekerjaan (D+E) 193,969.97

Pemotongan 1 buah pipa PVC Ø 1000 mm


Kode AHSP = 8.4.2.14
A TENAGA
Pekerja C9 OH 1.285 80,000.00 102,800.00
Tukang Pipa C24 OH 0.643 125,000.00 80,375.00
Mandor C47 OH 0.129 120,000.00 15,480.00
JUMLAH TENAGA KERJA 198,655.00
B BAHAN
Pipa PVC Ø 1000 mm C1360 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.191 2.00 0.38
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 198,656.38
E Overhead & Profit 10% 19,865.64
F Harga Satuan Pekerjaan (D+E) 218,522.02

Pemotongan 1 buah pipa PVC Ø 1100 mm


Kode AHSP = 8.4.2.15
A TENAGA
Pekerja C9 OH 1.429 80,000.00 114,320.00
Tukang Pipa C24 OH 0.715 125,000.00 89,375.00
Mandor C47 OH 0.143 120,000.00 17,160.00
JUMLAH TENAGA KERJA 220,855.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Pipa PVC Ø 1100 mm C1361 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.213 2.00 0.43
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.43


D Jumlah (A+B+C) 220,856.43
E Overhead & Profit 10% 22,085.64
F Harga Satuan Pekerjaan (D+E) 242,942.07

Pemotongan 1 buah pipa PVC Ø 1200 mm


Kode AHSP = 8.4.2.16
A TENAGA
Pekerja C9 OH 1.573 80,000.00 125,840.00
Tukang Pipa C24 OH 0.787 125,000.00 98,375.00
Mandor C47 OH 0.157 120,000.00 18,840.00
JUMLAH TENAGA KERJA 243,055.00
B BAHAN
Pipa PVC Ø 1200 mm C1362 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.236 2.00 0.47
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.47


D Jumlah (A+B+C) 243,056.47
E Overhead & Profit 10% 24,305.65
F Harga Satuan Pekerjaan (D+E) 267,362.12

Pemotongan 1 buah pipa HDPE Ø 63 mm


Kode AHSP = 8.4.2.17
A TENAGA
Pekerja C9 OH 0.002 80,000.00 160.00
Tukang Pipa C24 OH 0.001 125,000.00 125.00
Mandor C47 OH 0.000 120,000.00 24.00
Operator C32 OH 0.034 200,000.00 6,800.00
JUMLAH TENAGA KERJA 309.00
B BAHAN
Pipa HDPE Ø 63 mm C1363 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.004 2.00 0.01
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 310.01
E Overhead & Profit 10% 31.00
F Harga Satuan Pekerjaan (D+E) 341.01

Pemotongan 1 buah pipa HDPE Ø 100 mm


Kode AHSP = 8.4.2.18
A TENAGA
Pekerja C9 OH 0.006 80,000.00 480.00
Tukang Pipa C24 OH 0.003 125,000.00 375.00
Mandor C47 OH 0.001 120,000.00 120.00
Operator C32 OH 0.071 200,000.00 14,200.00
JUMLAH TENAGA KERJA 975.00
B BAHAN
Pipa HDPE Ø 100 mm C1364 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Peralatan potong pipa
C1313 Hari 0.005 2.00 0.01
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 976.01
E Overhead & Profit 10% 97.60
F Harga Satuan Pekerjaan (D+E) 1,073.61

Pemotongan 1 buah pipa HDPE Ø 125 mm


Kode AHSP = 8.4.2.19
A TENAGA
Pekerja C9 OH 0.009 80,000.00 720.00
Tukang Pipa C24 OH 0.005 125,000.00 625.00
Mandor C47 OH 0.001 120,000.00 120.00
Operator C32 OH 0.096 200,000.00 19,200.00
JUMLAH TENAGA KERJA 1,465.00
B BAHAN
Pipa HDPE Ø 125 mm C1365 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.006 2.00 0.01
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 1,466.01
E Overhead & Profit 10% 146.60
F Harga Satuan Pekerjaan (D+E) 1,612.61

Pemotongan 1 buah pipa HDPE Ø 150 mm


Kode AHSP = 8.4.2.20
A TENAGA
Pekerja C9 OH 0.016 80,000.00 1,280.00
Tukang Pipa C24 OH 0.008 125,000.00 1,000.00
Mandor C47 OH 0.002 120,000.00 240.00
Operator C32 OH 0.121 200,000.00 24,200.00
JUMLAH TENAGA KERJA 2,520.00
B BAHAN
Pipa HDPE Ø 150 mm C1366 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.009 2.00 0.02
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.02


D Jumlah (A+B+C) 2,521.02
E Overhead & Profit 10% 252.10
F Harga Satuan Pekerjaan (D+E) 2,773.12

Pemotongan 1 buah pipa HDPE Ø 200 mm


Kode AHSP = 8.4.2.21
A TENAGA
Pekerja C9 OH 0.044 80,000.00 3,520.00
Tukang Pipa C24 OH 0.022 125,000.00 2,750.00
Mandor C47 OH 0.004 120,000.00 480.00
Operator C32 OH 0.171 200,000.00 34,200.00
JUMLAH TENAGA KERJA 6,750.00
B BAHAN
Pipa HDPE Ø 200 mm C1367 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.017 2.00 0.03
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.03


D Jumlah (A+B+C) 6,751.03
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 675.10
F Harga Satuan Pekerjaan (D+E) 7,426.14

Pemotongan 1 buah pipaHDPE Ø 250 mm


Kode AHSP = 8.4.2.22
A TENAGA
Pekerja C9 OH 0.067 80,000.00 5,360.00
Tukang Pipa C24 OH 0.033 125,000.00 4,125.00
Mandor C47 OH 0.007 120,000.00 840.00
Operator C32 OH 0.221 200,000.00 44,200.00
JUMLAH TENAGA KERJA 10,325.00
B BAHAN
Pipa HDPE Ø 250 mm C1368 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.023 2.00 0.05
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.05


D Jumlah (A+B+C) 10,326.05
E Overhead & Profit 10% 1,032.60
F Harga Satuan Pekerjaan (D+E) 11,358.65

Pemotongan 1 buah pipa HDPE Ø 300 mm


Kode AHSP = 8.4.2.23
A TENAGA
Pekerja C9 OH 0.090 80,000.00 7,200.00
Tukang Pipa C24 OH 0.045 125,000.00 5,625.00
Mandor C47 OH 0.009 120,000.00 1,080.00
Operator C32 OH 0.271 200,000.00 54,200.00
JUMLAH TENAGA KERJA 13,905.00
B BAHAN
Pipa HDPE Ø 300 mm C1369 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.030 2.00 0.06
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.06


D Jumlah (A+B+C) 13,906.06
E Overhead & Profit 10% 1,390.61
F Harga Satuan Pekerjaan (D+E) 15,296.67

Pemotongan 1 buah pipa HDPE Ø 400 mm


Kode AHSP = 8.4.2.24
A TENAGA
Pekerja C9 OH 0.177 80,000.00 14,160.00
Tukang Pipa C24 OH 0.088 125,000.00 11,000.00
Mandor C47 OH 0.018 120,000.00 2,160.00
Operator C32 OH 0.371 200,000.00 74,200.00
JUMLAH TENAGA KERJA 27,320.00
B BAHAN
Pipa HDPE Ø 400 mm C1370 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.055 2.00 0.11
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.11


D Jumlah (A+B+C) 27,321.11
E Overhead & Profit 10% 2,732.11
F Harga Satuan Pekerjaan (D+E) 30,053.22

Pemotongan 1 buah pipa HDPE Ø 450 mm


Kode AHSP = 8.4.2.25
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja C9 OH 0.225 80,000.00 18,000.00
Tukang Pipa C24 OH 0.113 125,000.00 14,125.00
Mandor C47 OH 0.023 120,000.00 2,760.00
Operator C32 OH 0.421 200,000.00 84,200.00
JUMLAH TENAGA KERJA 34,885.00
B BAHAN
Pipa HDPE Ø 400 mm C1370 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.070 2.00 0.14
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.14


D Jumlah (A+B+C) 34,886.14
E Overhead & Profit 10% 3,488.61
F Harga Satuan Pekerjaan (D+E) 38,374.75

Pemotongan 1 buah pipa HDPE Ø 500 mm


Kode AHSP = 8.4.2.26
A TENAGA
Pekerja C9 OH 0.277 80,000.00 22,160.00
Tukang Pipa C24 OH 0.139 125,000.00 17,375.00
Mandor C47 OH 0.028 120,000.00 3,360.00
Operator C32 OH 0.471 200,000.00 94,200.00
JUMLAH TENAGA KERJA 42,895.00
B BAHAN
Pipa HDPE Ø 500 mm C1372 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.085 2.00 0.17
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.17


D Jumlah (A+B+C) 42,896.17
E Overhead & Profit 10% 4,289.62
F Harga Satuan Pekerjaan (D+E) 47,185.79

Pemotongan 1 buah pipa HDPE Ø 600 mm


Kode AHSP = 8.4.2.27
A TENAGA
Pekerja C9 OH 0.333 80,000.00 26,640.00
Tukang Pipa C24 OH 0.167 125,000.00 20,875.00
Mandor C47 OH 0.033 120,000.00 3,960.00
Operator C32 OH 0.571 200,000.00 114,200.00
JUMLAH TENAGA KERJA 51,475.00
B BAHAN
Pipa HDPE Ø 600 mm C1373 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.101 2.00 0.20
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.20


D Jumlah (A+B+C) 51,476.20
E Overhead & Profit 10% 5,147.62
F Harga Satuan Pekerjaan (D+E) 56,623.82

Pemotongan 1 buah pipa HDPE Ø 800 mm


Kode AHSP = 8.4.2.28
A TENAGA
Pekerja C9 OH 0.601 80,000.00 48,080.00
Tukang Pipa C24 OH 0.301 125,000.00 37,625.00
Mandor C47 OH 0.060 120,000.00 7,200.00
Operator C32 OH 0.771 200,000.00 154,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 92,905.00
B BAHAN
Pipa HDPE Ø 800 mm C1374 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.179 2.00 0.36
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.36


D Jumlah (A+B+C) 92,906.36
E Overhead & Profit 10% 9,290.64
F Harga Satuan Pekerjaan (D+E) 102,196.99

Pemotongan 1 buah pipa HDPE Ø 900 mm


Kode AHSP = 8.4.2.29
A TENAGA
Pekerja C9 OH 0.913 80,000.00 73,040.00
Tukang Pipa C24 OH 0.456 125,000.00 57,000.00
Mandor C47 OH 0.091 120,000.00 10,920.00
Operator C32 OH 0.871 200,000.00 174,200.00
JUMLAH TENAGA KERJA 140,960.00
B BAHAN
Pipa HDPE Ø 900 mm C1375 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.270 2.00 0.54
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.54


D Jumlah (A+B+C) 140,961.54
E Overhead & Profit 10% 14,096.15
F Harga Satuan Pekerjaan (D+E) 155,057.69

Pemotongan 1 buah pipa HDPE Ø 1000 mm


Kode AHSP = 8.4.2.30
A TENAGA
Pekerja C9 OH 1.125 80,000.00 90,000.00
Tukang Pipa C24 OH 0.562 125,000.00 70,250.00
Mandor C47 OH 0.112 120,000.00 13,440.00
Operator C32 OH 0.971 200,000.00 194,200.00
JUMLAH TENAGA KERJA 173,690.00
B BAHAN
Pipa HDPE Ø 1000 mm C1376 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.332 2.00 0.66
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.66


D Jumlah (A+B+C) 173,691.66
E Overhead & Profit 10% 17,369.17
F Harga Satuan Pekerjaan (D+E) 191,060.83

Pemotongan 1 buah pipa HDPE Ø 1100 mm


Kode AHSP = 8.4.2.31
A TENAGA
Pekerja C9 OH 1.238 80,000.00 99,040.00
Tukang Pipa C24 OH 0.619 125,000.00 77,375.00
Mandor C47 OH 0.124 120,000.00 14,880.00
Operator C32 OH 1.071 200,000.00 214,200.00
JUMLAH TENAGA KERJA 191,295.00
B BAHAN
Pipa HDPE Ø 1100 mm C1377 bh 1.000 1.00 1.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Peralatan potong pipa
C1313 Hari 0.365 2.00 0.73
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.73


D Jumlah (A+B+C) 191,296.73
E Overhead & Profit 10% 19,129.67
F Harga Satuan Pekerjaan (D+E) 210,426.40

Pemotongan 1 buah pipa HDPE Ø 1200 mm


Kode AHSP = 8.4.2.32
A TENAGA
Pekerja C9 OH 1.619 80,000.00 129,520.00
Tukang Pipa C24 OH 0.809 125,000.00 101,125.00
Mandor C47 OH 0.162 120,000.00 19,440.00
Operator C32 OH 1.171 200,000.00 234,200.00
JUMLAH TENAGA KERJA 250,085.00
B BAHAN
Pipa HDPE Ø 1200 mm C1378 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.477 2.00 0.95
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.95


D Jumlah (A+B+C) 250,086.95
E Overhead & Profit 10% 25,008.70
F Harga Satuan Pekerjaan (D+E) 275,095.65

Pemotongan 1 buah pipa GIP Ø 63 mm


Kode AHSP = 8.4.2.33
A TENAGA
Pekerja C9 OH 0.019 80,000.00 1,520.00
Tukang Pipa C24 OH 0.010 125,000.00 1,250.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 3,010.00
B BAHAN
Pipa GIP Ø 63 mm C1379 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,011.00
E Overhead & Profit 10% 301.10
F Harga Satuan Pekerjaan (D+E) 3,312.10

Pemotongan 1 buah pipa GIP Ø 100 mm


Kode AHSP = 8.4.2.34
A TENAGA
Pekerja C9 OH 0.058 80,000.00 4,640.00
Tukang Pipa C24 OH 0.029 125,000.00 3,625.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 8,985.00
B BAHAN
Pipa GIP Ø 100 mm C1380 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,986.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 898.60
F Harga Satuan Pekerjaan (D+E) 9,884.60

Pemotongan 1 buah pipa GIP Ø 125 mm


Kode AHSP = 8.4.2.35
A TENAGA
Pekerja C9 OH 0.092 80,000.00 7,360.00
Tukang Pipa C24 OH 0.046 125,000.00 5,750.00
Mandor C47 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 14,190.00
B BAHAN
Pipa GIP Ø 125 mm C1381 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 14,191.00
E Overhead & Profit 10% 1,419.10
F Harga Satuan Pekerjaan (D+E) 15,610.10

Pemotongan 1 buah pipa GIP Ø 150 mm


Kode AHSP = 8.4.2.36
A TENAGA
Pekerja C9 OH 0.131 80,000.00 10,480.00
Tukang Pipa C24 OH 0.066 125,000.00 8,250.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 20,290.00
B BAHAN
Pipa GIP Ø 150 mm C1382 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 20,291.00
E Overhead & Profit 10% 2,029.10
F Harga Satuan Pekerjaan (D+E) 22,320.10

Pemotongan 1 buah pipa GIP Ø 200 mm


Kode AHSP = 8.4.2.37
A TENAGA
Pekerja C9 OH 0.340 80,000.00 27,200.00
Tukang Pipa C24 OH 0.170 125,000.00 21,250.00
Mandor C47 OH 0.034 120,000.00 4,080.00
JUMLAH TENAGA KERJA 52,530.00
B BAHAN
Pipa GIP Ø 200 mm C1383 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 52,531.00
E Overhead & Profit 10% 5,253.10
F Harga Satuan Pekerjaan (D+E) 57,784.10

Pemotongan 1 buah pipa GIP Ø 250 mm


Kode AHSP = 8.4.2.38
A TENAGA
Pekerja C9 OH 0.475 80,000.00 38,000.00
Tukang Pipa C24 OH 0.237 125,000.00 29,625.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.047 120,000.00 5,640.00
JUMLAH TENAGA KERJA 73,265.00
B BAHAN
Pipa GIP Ø 250 mm C1384 bh 1.000 759,000.00 759,000.00

JUMLAH HARGA BAHAN 759,000.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 832,265.00
E Overhead & Profit 10% 83,226.50
F Harga Satuan Pekerjaan (D+E) 915,491.50

Pemotongan 1 buah pipa GIP Ø 300 mm


Kode AHSP = 8.4.2.39
A TENAGA
Pekerja C9 OH 0.504 80,000.00 40,320.00
Tukang Pipa C24 OH 0.252 125,000.00 31,500.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 77,820.00
B BAHAN
Pipa GIP Ø 300 mm C1385 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 77,821.00
E Overhead & Profit 10% 7,782.10
F Harga Satuan Pekerjaan (D+E) 85,603.10

Pemotongan 1 buah pipa GIP Ø 400 mm


Kode AHSP = 8.4.2.40
A TENAGA
Pekerja C9 OH 0.738 80,000.00 59,040.00
Tukang Pipa C24 OH 0.369 125,000.00 46,125.00
Mandor C47 OH 0.074 120,000.00 8,880.00
JUMLAH TENAGA KERJA 114,045.00
B BAHAN
Pipa GIP Ø 400 mm C1386 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 114,046.00
E Overhead & Profit 10% 11,404.60
F Harga Satuan Pekerjaan (D+E) 125,450.60

Pemotongan 1 buah pipa GIP Ø 450 mm


Kode AHSP = 8.4.2.41
A TENAGA
Pekerja C9 OH 0.848 80,000.00 67,840.00
Tukang Pipa C24 OH 0.424 125,000.00 53,000.00
Mandor C47 OH 0.085 120,000.00 10,200.00
JUMLAH TENAGA KERJA 131,040.00
B BAHAN
Pipa GIP Ø 450 mm C1387 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 131,041.00
E Overhead & Profit 10% 13,104.10
F Harga Satuan Pekerjaan (D+E) 144,145.10

Pemotongan 1 buah pipa GIP Ø 500 mm


Kode AHSP = 8.4.2.42
A TENAGA
Pekerja C9 OH 0.941 80,000.00 75,280.00
Tukang Pipa C24 OH 0.471 125,000.00 58,875.00
Mandor C47 OH 0.094 120,000.00 11,280.00
JUMLAH TENAGA KERJA 145,435.00
B BAHAN
Pipa GIP Ø 500 mm C1388 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 145,436.00
E Overhead & Profit 10% 14,543.60
F Harga Satuan Pekerjaan (D+E) 159,979.60

Pemotongan1 buah pipa GIP Ø 600 mm


Kode AHSP = 8.4.2.43
A TENAGA
Pekerja C9 OH 0.864 80,000.00 69,120.00
Tukang Pipa C24 OH 0.432 125,000.00 54,000.00
Mandor C47 OH 0.086 120,000.00 10,320.00
JUMLAH TENAGA KERJA 133,440.00
B BAHAN
Pipa GIP Ø 600 mm C1389 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 133,441.00
E Overhead & Profit 10% 13,344.10
F Harga Satuan Pekerjaan (D+E) 146,785.10

Pemotongan 1 buah pipa GIP Ø 800 mm


Kode AHSP = 8.4.2.44
A TENAGA
Pekerja C9 OH 1.567 80,000.00 125,360.00
Tukang Pipa C24 OH 0.783 125,000.00 97,875.00
Mandor C47 OH 0.157 120,000.00 18,840.00
JUMLAH TENAGA KERJA 242,075.00
B BAHAN
Pipa GIP Ø 800 mm C1390 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 242,076.00
E Overhead & Profit 10% 24,207.60
F Harga Satuan Pekerjaan (D+E) 266,283.60
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemotongan 1 buah pipa GIP Ø 900 mm
Kode AHSP = 8.4.2.45
A TENAGA
Pekerja C9 OH 1.770 80,000.00 141,600.00
Tukang Pipa C24 OH 0.885 125,000.00 110,625.00
Mandor C47 OH 0.177 120,000.00 21,240.00
JUMLAH TENAGA KERJA 273,465.00
B BAHAN
Pipa GIP Ø 900 mm C1391 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 273,466.00
E Overhead & Profit 10% 27,346.60
F Harga Satuan Pekerjaan (D+E) 300,812.60

Pemotongan 1 buah pipa GIP Ø 1000 mm


Kode AHSP = 8.4.2.46
A TENAGA
Pekerja C9 OH 1.974 80,000.00 157,920.00
Tukang Pipa C24 OH 0.987 125,000.00 123,375.00
Mandor C47 OH 0.197 120,000.00 23,640.00
JUMLAH TENAGA KERJA 304,935.00
B BAHAN
Pipa GIP Ø 1000 mm C1392 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 304,936.00
E Overhead & Profit 10% 30,493.60
F Harga Satuan Pekerjaan (D+E) 335,429.60

Pemotongan 1 buah pipa GIP Ø 1100 mm


Kode AHSP = 8.4.2.47
A TENAGA
Pekerja C9 OH 2.178 80,000.00 174,240.00
Tukang Pipa C24 OH 1.089 125,000.00 136,125.00
Mandor C47 OH 0.218 120,000.00 26,160.00
JUMLAH TENAGA KERJA 336,525.00
B BAHAN
Pipa GIP Ø 1100 mm C1393 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 336,526.00
E Overhead & Profit 10% 33,652.60
F Harga Satuan Pekerjaan (D+E) 370,178.60

Pemotongan 1 buah pipa GIP Ø 1200 mm


Kode AHSP = 8.4.2.48
A TENAGA
Pekerja C9 OH 2.382 80,000.00 190,560.00
Tukang Pipa C24 OH 1.191 125,000.00 148,875.00
Mandor C47 OH 0.238 120,000.00 28,560.00
JUMLAH TENAGA KERJA 367,995.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pipa GIP Ø 1200 mm C1394 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari - 2.00 -
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 367,996.00
E Overhead & Profit 10% 36,799.60
F Harga Satuan Pekerjaan (D+E) 404,795.60

Pemotongan 1 buah pipa DCI Ø 100 mm


Kode AHSP = 8.4.2.49
A TENAGA
Pekerja C9 OH 0.071 80,000.00 5,680.00
Tukang Pipa C24 OH 0.014 125,000.00 1,750.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 8,270.00
B BAHAN
Pipa DCI Ø 100 mm C1395 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel &
C1603 Hari 0.003 1.00 0.00
handle crane 2 T

JUMLAH HARGA ALAT 0.00


D Jumlah (A+B+C) 8,271.00
E Overhead & Profit 10% 827.10
F Harga Satuan Pekerjaan (D+E) 9,098.10

Pemotongan 1 buah pipa DCI Ø 125 mm


Kode AHSP = 8.4.2.50
A TENAGA
Pekerja C9 OH 0.112 80,000.00 8,960.00
Tukang Pipa C24 OH 0.022 125,000.00 2,750.00
Mandor C47 OH 0.011 120,000.00 1,320.00
JUMLAH TENAGA KERJA 13,030.00
B BAHAN
Pipa DCI Ø 125 mm C1396 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel &
C1603 Hari 0.010 1.00 0.01
handle crane 2 T

JUMLAH HARGA ALAT 0.01


D Jumlah (A+B+C) 13,031.01
E Overhead & Profit 10% 1,303.10
F Harga Satuan Pekerjaan (D+E) 14,334.11

Pemotongan 1 buah pipa DCI Ø 150 mm


Kode AHSP = 8.4.2.51
A TENAGA
Pekerja C9 OH 0.159 80,000.00 12,720.00
Tukang Pipa C24 OH 0.032 125,000.00 4,000.00
Mandor C47 OH 0.016 120,000.00 1,920.00
JUMLAH TENAGA KERJA 18,640.00
B BAHAN
Pipa DCI Ø 150 mm C1397 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel &
C1603 Hari 0.018 1.00 0.02
handle crane 2 T
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT 0.02
D Jumlah (A+B+C) 18,641.02
E Overhead & Profit 10% 1,864.10
F Harga Satuan Pekerjaan (D+E) 20,505.12

Pemotongan 1 buah pipa DCI Ø 200 mm


Kode AHSP = 8.4.2.52
A TENAGA
Pekerja C9 OH 0.366 80,000.00 29,280.00
Tukang Pipa C24 OH 0.073 125,000.00 9,125.00
Mandor C47 OH 0.037 120,000.00 4,440.00
JUMLAH TENAGA KERJA 42,845.00
B BAHAN
Pipa DCI Ø 200 mm C1398 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel &
C1603 Hari 0.054 1.00 0.05
handle crane 2 T

JUMLAH HARGA ALAT 0.05


D Jumlah (A+B+C) 42,846.05
E Overhead & Profit 10% 4,284.61
F Harga Satuan Pekerjaan (D+E) 47,130.66

Pemotongan 1 buah pipa DCI Ø 250 mm


Kode AHSP = 8.4.2.53
A TENAGA
Pekerja C9 OH 0.476 80,000.00 38,080.00
Tukang Pipa C24 OH 0.095 125,000.00 11,875.00
Mandor C47 OH 0.048 120,000.00 5,760.00
JUMLAH TENAGA KERJA 55,715.00
B BAHAN
Pipa DCI Ø 250 mm C1399 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel &
C1603 Hari 0.073 1.00 0.07
handle crane 2 T

JUMLAH HARGA ALAT 0.07


D Jumlah (A+B+C) 55,716.07
E Overhead & Profit 10% 5,571.61
F Harga Satuan Pekerjaan (D+E) 61,287.68

Pemotongan 1 buah pipa DCI Ø 300 mm


Kode AHSP = 8.4.2.54
A TENAGA
Pekerja C9 OH 0.512 80,000.00 40,960.00
Tukang Pipa C24 OH 0.102 125,000.00 12,750.00
Mandor C47 OH 0.051 120,000.00 6,120.00
JUMLAH TENAGA KERJA 59,830.00
B BAHAN
Pipa DCI Ø 300 mm C1400 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel &
C1603 Hari 0.079 1.00 0.08
handle crane 2 T

JUMLAH HARGA ALAT 0.08


D Jumlah (A+B+C) 59,831.08
E Overhead & Profit 10% 5,983.11
F Harga Satuan Pekerjaan (D+E) 65,814.19

Pemotongan 1 buah pipa DCI Ø 400 mm


Kode AHSP = 8.4.2.55
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pekerja C9 OH 0.941 80,000.00 75,280.00
Tukang Pipa C24 OH 0.188 125,000.00 23,500.00
Mandor C47 OH 0.094 120,000.00 11,280.00
JUMLAH TENAGA KERJA 110,060.00
B BAHAN
Pipa DCI Ø 400 mm C1401 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.158 2.00 0.32
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.32


D Jumlah (A+B+C) 110,061.32
E Overhead & Profit 10% 11,006.13
F Harga Satuan Pekerjaan (D+E) 121,067.45

Pemotongan 1 buah pipa DCI Ø 450 mm


Kode AHSP = 8.4.2.56
A TENAGA
Pekerja C9 OH 1.137 80,000.00 90,960.00
Tukang Pipa C24 OH 0.227 125,000.00 28,375.00
Mandor C47 OH 0.114 120,000.00 13,680.00
JUMLAH TENAGA KERJA 133,015.00
B BAHAN
Pipa DCI Ø 450 mm C1402 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.176 2.00 0.35
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.35


D Jumlah (A+B+C) 133,016.35
E Overhead & Profit 10% 13,301.64
F Harga Satuan Pekerjaan (D+E) 146,317.99

Pemotongan 1 buah pipa DCI Ø 500 mm


Kode AHSP = 8.4.2.57
A TENAGA
Pekerja C9 OH 1.312 80,000.00 104,960.00
Tukang Pipa C24 OH 0.262 125,000.00 32,750.00
Mandor C47 OH 0.131 120,000.00 15,720.00
JUMLAH TENAGA KERJA 153,430.00
B BAHAN
Pipa DCI Ø 500 mm C1403 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.192 2.00 0.38
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 153,431.38
E Overhead & Profit 10% 15,343.14
F Harga Satuan Pekerjaan (D+E) 168,774.52

Pemotongan 1 buah pipa DCI Ø 600 mm


Kode AHSP = 8.4.2.58
A TENAGA
Pekerja C9 OH 1.309 80,000.00 104,720.00
Tukang Pipa C24 OH 0.262 125,000.00 32,750.00
Mandor C47 OH 0.131 120,000.00 15,720.00
JUMLAH TENAGA KERJA 153,190.00
B BAHAN
Pipa DCI Ø 600 mm C1404 bh 1.000 1.00 1.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Peralatan potong pipa
C1313 Hari 0.192 2.00 0.38
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.38


D Jumlah (A+B+C) 153,191.38
E Overhead & Profit 10% 15,319.14
F Harga Satuan Pekerjaan (D+E) 168,510.52

Pemotongan 1 buah pipa DCI Ø 800 mm


Kode AHSP = 8.4.2.59
A TENAGA
Pekerja C9 OH 2.598 80,000.00 207,840.00
Tukang Pipa C24 OH 0.520 125,000.00 65,000.00
Mandor C47 OH 0.260 120,000.00 31,200.00
JUMLAH TENAGA KERJA 304,040.00
B BAHAN
Pipa DCI Ø 800 mm C1405 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.310 2.00 0.62
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.62


D Jumlah (A+B+C) 304,041.62
E Overhead & Profit 10% 30,404.16
F Harga Satuan Pekerjaan (D+E) 334,445.78

Pemotongan 1 buah pipa DCI Ø 900 mm


Kode AHSP = 8.4.2.60
A TENAGA
Pekerja C9 OH 3.370 80,000.00 269,600.00
Tukang Pipa C24 OH 0.674 125,000.00 84,250.00
Mandor C47 OH 0.337 120,000.00 40,440.00
JUMLAH TENAGA KERJA 394,290.00
B BAHAN
Pipa DCI Ø 900 mm C1406 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.381 2.00 0.76
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.76


D Jumlah (A+B+C) 394,291.76
E Overhead & Profit 10% 39,429.18
F Harga Satuan Pekerjaan (D+E) 433,720.94

Pemotongan 1 buah pipa DCI Ø 1000 mm


Kode AHSP = 8.4.2.61
A TENAGA
Pekerja C9 OH 4.021 80,000.00 321,680.00
Tukang Pipa C24 OH 0.804 125,000.00 100,500.00
Mandor C47 OH 0.402 120,000.00 48,240.00
JUMLAH TENAGA KERJA 470,420.00
B BAHAN
Pipa DCI Ø 1000 mm C1407 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.441 2.00 0.88
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.88


D Jumlah (A+B+C) 470,421.88
E Overhead & Profit 10% 47,042.19
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 517,464.07

Pemotongan 1 buah pipa DCI Ø 1100 mm


Kode AHSP = 8.4.2.62
A TENAGA
Pekerja C9 OH 4.731 80,000.00 378,480.00
Tukang Pipa C24 OH 0.946 125,000.00 118,250.00
Mandor C47 OH 0.473 120,000.00 56,760.00
JUMLAH TENAGA KERJA 553,490.00
B BAHAN
Pipa DCI Ø 1100 mm C1408 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.506 2.00 1.01
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 1.01


D Jumlah (A+B+C) 553,492.01
E Overhead & Profit 10% 55,349.20
F Harga Satuan Pekerjaan (D+E) 608,841.21

Pemotongan 1 buah pipa DCI Ø 1200 mm


Kode AHSP = 8.4.2.63
A TENAGA
Pekerja C9 OH 5.502 80,000.00 440,160.00
Tukang Pipa C24 OH 1.100 125,000.00 137,500.00
Mandor C47 OH 0.550 120,000.00 66,000.00
JUMLAH TENAGA KERJA 643,660.00
B BAHAN
Pipa DCI Ø 1200 mm C1409 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.576 2.00 1.15
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 1.15


D Jumlah (A+B+C) 643,662.15
E Overhead & Profit 10% 64,366.22
F Harga Satuan Pekerjaan (D+E) 708,028.37

Pemotongan 1 buah pipa baja Ø 63 mm


Kode AHSP = 8.4.2.64
A TENAGA
Pekerja C9 OH 0.028 80,000.00 2,240.00
Tukang Pipa C24 OH 0.006 125,000.00 750.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 3,350.00
B BAHAN
Pipa Baja Ø 63 mm C1410 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.037 2.00 0.07
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.07


D Jumlah (A+B+C) 3,351.07
E Overhead & Profit 10% 335.11
F Harga Satuan Pekerjaan (D+E) 3,686.18

Pemotongan 1 buah pipa baja Ø 100 mm


Kode AHSP = 8.4.2.65
A TENAGA
Pekerja C9 OH 0.085 80,000.00 6,800.00
Tukang Pipa C24 OH 0.017 125,000.00 2,125.00
Mandor C47 OH 0.008 120,000.00 960.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 9,885.00
B BAHAN
Pipa Baja Ø 100 mm C1411 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.040 2.00 0.08
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.08


D Jumlah (A+B+C) 9,886.08
E Overhead & Profit 10% 988.61
F Harga Satuan Pekerjaan (D+E) 10,874.69

Pemotongan 1 buah pipa baja Ø 125 mm


Kode AHSP = 8.4.2.66
A TENAGA
Pekerja C9 OH 0.133 80,000.00 10,640.00
Tukang Pipa C24 OH 0.027 125,000.00 3,375.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 15,575.00
B BAHAN
Pipa Baja Ø 125 mm C1412 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.042 2.00 0.08
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.08


D Jumlah (A+B+C) 15,576.08
E Overhead & Profit 10% 1,557.61
F Harga Satuan Pekerjaan (D+E) 17,133.69

Pemotongan 1 buah pipa baja Ø 150 mm


Kode AHSP = 8.4.2.67
A TENAGA
Pekerja C9 OH 0.184 80,000.00 14,720.00
Tukang Pipa C24 OH 0.037 125,000.00 4,625.00
Mandor C47 OH 0.018 120,000.00 2,160.00
JUMLAH TENAGA KERJA 21,505.00
B BAHAN
Pipa Baja Ø 150 mm C1413 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.045 2.00 0.09
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.09


D Jumlah (A+B+C) 21,506.09
E Overhead & Profit 10% 2,150.61
F Harga Satuan Pekerjaan (D+E) 23,656.70

Pemotongan 1 buah pipa baja Ø 200 mm


Kode AHSP = 8.4.2.68
A TENAGA
Pekerja C9 OH 0.476 80,000.00 38,080.00
Tukang Pipa C24 OH 0.095 125,000.00 11,875.00
Mandor C47 OH 0.048 120,000.00 5,760.00
JUMLAH TENAGA KERJA 55,715.00
B BAHAN
Pipa Baja Ø 200 mm C1414 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Peralatan potong pipa
C1313 Hari 0.060 2.00 0.12
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.12


D Jumlah (A+B+C) 55,716.12
E Overhead & Profit 10% 5,571.61
F Harga Satuan Pekerjaan (D+E) 61,287.73

Pemotongan 1 buah pipa baja Ø 250 mm


Kode AHSP = 8.4.2.69
A TENAGA
Pekerja C9 OH 0.663 80,000.00 53,040.00
Tukang Pipa C24 OH 0.133 125,000.00 16,625.00
Mandor C47 OH 0.066 120,000.00 7,920.00
JUMLAH TENAGA KERJA 77,585.00
B BAHAN
Pipa Baja Ø 250 mm C1415 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.068 2.00 0.14
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.14


D Jumlah (A+B+C) 77,586.14
E Overhead & Profit 10% 7,758.61
F Harga Satuan Pekerjaan (D+E) 85,344.75

Pemotongan 1 buah pipa baja Ø 300 mm


Kode AHSP = 8.4.2.70
A TENAGA
Pekerja C9 OH 0.745 80,000.00 59,600.00
Tukang Pipa C24 OH 0.149 125,000.00 18,625.00
Mandor C47 OH 0.074 120,000.00 8,880.00
JUMLAH TENAGA KERJA 87,105.00
B BAHAN
Pipa Baja Ø 300 mm C1416 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.072 2.00 0.14
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.14


D Jumlah (A+B+C) 87,106.14
E Overhead & Profit 10% 8,710.61
F Harga Satuan Pekerjaan (D+E) 95,816.76

Pemotongan 1 buah pipa baja Ø 400 mm


Kode AHSP = 8.4.2.71
A TENAGA
Pekerja C9 OH 1.440 80,000.00 115,200.00
Tukang Pipa C24 OH 0.288 125,000.00 36,000.00
Mandor C47 OH 0.144 120,000.00 17,280.00
JUMLAH TENAGA KERJA 168,480.00
B BAHAN
Pipa Baja Ø 400 mm C1417 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.105 2.00 0.21
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.21


D Jumlah (A+B+C) 168,481.21
E Overhead & Profit 10% 16,848.12
F Harga Satuan Pekerjaan (D+E) 185,329.33
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemotongan 1 buah pipa baja Ø 450 mm
Kode AHSP = 8.4.2.72
A TENAGA
Pekerja C9 OH 1.399 80,000.00 111,920.00
Tukang Pipa C24 OH 0.280 125,000.00 35,000.00
Mandor C47 OH 0.140 120,000.00 16,800.00
JUMLAH TENAGA KERJA 163,720.00
B BAHAN
Pipa Baja Ø 450 mm C1418 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.107 2.00 0.21
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.21


D Jumlah (A+B+C) 163,721.21
E Overhead & Profit 10% 16,372.12
F Harga Satuan Pekerjaan (D+E) 180,093.34

Pemotongan 1 buah pipa baja Ø 500 mm


Kode AHSP = 8.4.2.73
A TENAGA
Pekerja C9 OH 1.558 80,000.00 124,640.00
Tukang Pipa C24 OH 0.312 125,000.00 39,000.00
Mandor C47 OH 0.156 120,000.00 18,720.00
JUMLAH TENAGA KERJA 182,360.00
B BAHAN
Pipa Baja Ø 500 mm C1419 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.107 2.00 0.21
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.21


D Jumlah (A+B+C) 182,361.21
E Overhead & Profit 10% 18,236.12
F Harga Satuan Pekerjaan (D+E) 200,597.34

Pemotongan 1 buah pipa baja Ø 600 mm


Kode AHSP = 8.4.2.74
A TENAGA
Pekerja C9 OH 1.437 80,000.00 114,960.00
Tukang Pipa C24 OH 0.287 125,000.00 35,875.00
Mandor C47 OH 0.144 120,000.00 17,280.00
JUMLAH TENAGA KERJA 168,115.00
B BAHAN
Pipa Baja Ø 600 mm C1420 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.113 2.00 0.23
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.23


D Jumlah (A+B+C) 168,116.23
E Overhead & Profit 10% 16,811.62
F Harga Satuan Pekerjaan (D+E) 184,927.85

Pemotongan 1 buah pipa baja Ø 800 mm


Kode AHSP = 8.4.2.75
A TENAGA
Pekerja C9 OH 2.624 80,000.00 209,920.00
Tukang Pipa C24 OH 0.525 125,000.00 65,625.00
Mandor C47 OH 0.262 120,000.00 31,440.00
JUMLAH TENAGA KERJA 306,985.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pipa Baja Ø 800 mm C1421 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.166 2.00 0.33
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.33


D Jumlah (A+B+C) 306,986.33
E Overhead & Profit 10% 30,698.63
F Harga Satuan Pekerjaan (D+E) 337,684.97

Pemotongan 1 buah pipa baja Ø 900 mm


Kode AHSP = 8.4.2.76
A TENAGA
Pekerja C9 OH 2.971 80,000.00 237,680.00
Tukang Pipa C24 OH 0.594 125,000.00 74,250.00
Mandor C47 OH 0.297 120,000.00 35,640.00
JUMLAH TENAGA KERJA 347,570.00
B BAHAN
Pipa Baja Ø 900 mm C1422 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.183 2.00 0.37
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.37


D Jumlah (A+B+C) 347,571.37
E Overhead & Profit 10% 34,757.14
F Harga Satuan Pekerjaan (D+E) 382,328.50

Pemotongan 1 buah pipa baja Ø 1000 mm


Kode AHSP = 8.4.2.77
A TENAGA
Pekerja C9 OH 3.319 80,000.00 265,520.00
Tukang Pipa C24 OH 0.664 125,000.00 83,000.00
Mandor C47 OH 0.332 120,000.00 39,840.00
JUMLAH TENAGA KERJA 388,360.00
B BAHAN
Pipa Baja Ø 1000 mm C1423 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.201 2.00 0.40
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.40


D Jumlah (A+B+C) 388,361.40
E Overhead & Profit 10% 38,836.14
F Harga Satuan Pekerjaan (D+E) 427,197.54

Pemotongan 1 buah pipa baja Ø 1100 mm


Kode AHSP = 8.4.2.78
A TENAGA
Pekerja C9 OH 3.667 80,000.00 293,360.00
Tukang Pipa C24 OH 0.733 125,000.00 91,625.00
Mandor C47 OH 0.367 120,000.00 44,040.00
JUMLAH TENAGA KERJA 429,025.00
B BAHAN
Pipa Baja Ø 1100 mm C1424 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.218 2.00 0.44
T2/mekanik / cilinder saw
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT 0.44
D Jumlah (A+B+C) 429,026.44
E Overhead & Profit 10% 42,902.64
F Harga Satuan Pekerjaan (D+E) 471,929.08

Pemotongan 1 buah pipa baja Ø 1200 mm


Kode AHSP = 8.4.2.79
A TENAGA
Pekerja C9 OH 4.015 80,000.00 321,200.00
Tukang Pipa C24 OH 0.803 125,000.00 100,375.00
Mandor C47 OH 0.402 120,000.00 48,240.00
JUMLAH TENAGA KERJA 469,815.00
B BAHAN
Pipa Baja Ø 1200 mm C1425 bh 1.000 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa
C1313 Hari 0.236 2.00 0.47
T2/mekanik / cilinder saw

JUMLAH HARGA ALAT 0.47


D Jumlah (A+B+C) 469,816.47
E Overhead & Profit 10% 46,981.65
F Harga Satuan Pekerjaan (D+E) 516,798.12

Pemasangan 1 buah Valve Ø 150 mm


Kode AHSP = 8.4.3.1
A TENAGA
Pekerja C9 OH 1.429 80,000.00 114,320.00
Tukang pipa C24 OH 0.715 125,000.00 89,375.00
Mandor C47 OH 0.143 120,000.00 17,160.00
JUMLAH TENAGA KERJA 220,855.00
B BAHAN
Valve Ø 150 mm C1523 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.1 1.00 0.10

JUMLAH HARGA ALAT 0.10


D Jumlah (A+B+C) 220,856.10
E Overhead & Profit 10% 22,085.61
F Harga Satuan Pekerjaan (D+E) 242,941.71

Pemasangan 1 buah Valve Ø 200 mm


Kode AHSP = 8.4.3.2
A TENAGA
Pekerja C9 OH 1.714 80,000.00 137,120.00
Tukang pipa C24 OH 0.857 125,000.00 107,125.00
Mandor C47 OH 0.171 120,000.00 20,520.00
JUMLAH TENAGA KERJA 264,765.00
B BAHAN
Valve Ø 200 mm C1524 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.3 1.00 0.30

JUMLAH HARGA ALAT 0.30


D Jumlah (A+B+C) 264,766.30
E Overhead & Profit 10% 26,476.63
F Harga Satuan Pekerjaan (D+E) 291,242.93

Pemasangan 1 buah Valve Ø 250 mm


Kode AHSP = 8.4.3.3
A TENAGA
Pekerja C9 OH 1.714 80,000.00 137,120.00
Tukang pipa C24 OH 0.857 125,000.00 107,125.00
Mandor C47 OH 0.171 120,000.00 20,520.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 264,765.00
B BAHAN
Valve Ø 250 mm C1525 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.4 1.00 0.40

JUMLAH HARGA ALAT 0.40


D Jumlah (A+B+C) 264,766.40
E Overhead & Profit 10% 26,476.64
F Harga Satuan Pekerjaan (D+E) 291,243.04

Pemasangan 1 buah Valve Ø 300 mm


Kode AHSP = 8.4.3.4
A TENAGA
Pekerja C9 OH 2 80,000.00 160,000.00
Tukang pipa C24 OH 1 125,000.00 125,000.00
Mandor C47 OH 0.2 120,000.00 24,000.00
JUMLAH TENAGA KERJA 309,000.00
B BAHAN
Valve Ø 300 mm C1526 bh 1 1.00 1.00
-
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.5 1.00 0.50

JUMLAH HARGA ALAT 0.50


D Jumlah (A+B+C) 309,001.50
E Overhead & Profit 10% 30,900.15
F Harga Satuan Pekerjaan (D+E) 339,901.65

Pemasangan 1 buah Valve Ø 400 mm


Kode AHSP = 8.4.3.5
A TENAGA
Pekerja C9 OH 3.429 80,000.00 274,320.00
Tukang pipa C24 OH 1.715 125,000.00 214,375.00
Mandor C47 OH 0.343 120,000.00 41,160.00
JUMLAH TENAGA KERJA 529,855.00
B BAHAN
Valve Ø 400 mm C1527 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1 1.00 1.00

JUMLAH HARGA ALAT 1.00


D Jumlah (A+B+C) 529,857.00
E Overhead & Profit 10% 52,985.70
F Harga Satuan Pekerjaan (D+E) 582,842.70

Pemasangan 1 buah Valve Ø 450 mm


Kode AHSP = 8.4.3.6
A TENAGA
Pekerja C9 OH 3.429 80,000.00 274,320.00
Tukang pipa C24 OH 1.715 125,000.00 214,375.00
Mandor C47 OH 0.343 120,000.00 41,160.00
JUMLAH TENAGA KERJA 529,855.00
B BAHAN
Valve Ø 450 mm C1528 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1 1.00 1.00

JUMLAH HARGA ALAT 1.00


D Jumlah (A+B+C) 529,857.00
E Overhead & Profit 10% 52,985.70
F Harga Satuan Pekerjaan (D+E) 582,842.70
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 buah Valve Ø 500 mm


Kode AHSP = 8.4.3.7
A TENAGA
Pekerja C9 OH 4 80,000.00 320,000.00
Tukang pipa C24 OH 2 125,000.00 250,000.00
Mandor C47 OH 0.4 120,000.00 48,000.00
JUMLAH TENAGA KERJA 618,000.00
B BAHAN
Valve Ø 500 mm C1529 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1 1.00 1.00

JUMLAH HARGA ALAT 1.00


D Jumlah (A+B+C) 618,002.00
E Overhead & Profit 10% 61,800.20
F Harga Satuan Pekerjaan (D+E) 679,802.20

Pemasangan 1 buah Valve Ø 600 mm


Kode AHSP = 8.4.3.8
A TENAGA
Pekerja C9 OH 1.421 80,000.00 113,680.00
Tukang pipa C24 OH 0.711 125,000.00 88,875.00
Mandor C47 OH 0.142 120,000.00 17,040.00
JUMLAH TENAGA KERJA 219,595.00
B BAHAN
Valve Ø 600 mm C1530 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.6 1.00 0.60
Mobile crane =< 3 ton C1607 hari 0.3 1.00 0.30

JUMLAH HARGA ALAT 0.90


D Jumlah (A+B+C) 219,596.90
E Overhead & Profit 10% 21,959.69
F Harga Satuan Pekerjaan (D+E) 241,556.59

Pemasangan 1 buah Valve Ø 700 mm


Kode AHSP = 8.4.3.9
A TENAGA
Pekerja C9 OH 1.429 80,000.00 114,320.00
Tukang pipa C24 OH 0.715 125,000.00 89,375.00
Mandor C47 OH 0.143 120,000.00 17,160.00
JUMLAH TENAGA KERJA 220,855.00
B BAHAN
Valve Ø 700 mm C1531 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.5 1.00 0.50
Mobile crane =< 3 ton C1607 hari 0.5 1.00 0.50

JUMLAH HARGA ALAT 1.00


D Jumlah (A+B+C) 220,857.00
E Overhead & Profit 10% 22,085.70
F Harga Satuan Pekerjaan (D+E) 242,942.70

Pemasangan 1 buah Valve Ø 800 mm


Kode AHSP = 8.4.3.10
A TENAGA
Pekerja C9 OH 1.786 80,000.00 142,880.00
Tukang pipa C24 OH 0.893 125,000.00 111,625.00
Mandor C47 OH 0.179 120,000.00 21,480.00
JUMLAH TENAGA KERJA 275,985.00
B BAHAN
Valve Ø 800 mm C1532 bh 1 1.00 1.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 1.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.5 1.00 0.50
Mobile crane =< 3 ton C1607 hari 0.5 1.00 0.50

JUMLAH HARGA ALAT 1.00


D Jumlah (A+B+C) 275,987.00
E Overhead & Profit 10% 27,598.70
F Harga Satuan Pekerjaan (D+E) 303,585.70

Pemasangan 1 buah Valve Ø 900 mm


Kode AHSP = 8.4.3.11
A TENAGA
Pekerja C9 OH 1.714 80,000.00 137,120.00
Tukang pipa C24 OH 0.857 125,000.00 107,125.00
Mandor C47 OH 0.171 120,000.00 20,520.00
JUMLAH TENAGA KERJA 264,765.00
B BAHAN
Valve Ø 900 mm C1533 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.75 1.00 0.75
Mobile crane =< 3 ton C1607 hari 0.75 1.00 0.75

JUMLAH HARGA ALAT 1.50


D Jumlah (A+B+C) 264,767.50
E Overhead & Profit 10% 26,476.75
F Harga Satuan Pekerjaan (D+E) 291,244.25

Pemasangan 1 buah Valve Ø 1000 mm


Kode AHSP = 8.4.3.12
A TENAGA
Pekerja C9 OH 2.571 80,000.00 205,680.00
Tukang pipa C24 OH 1.286 125,000.00 160,750.00
Mandor C47 OH 0.257 120,000.00 30,840.00
JUMLAH TENAGA KERJA 397,270.00
B BAHAN
Valve Ø 1000 mm C1534 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1 1.00 1.00
Mobile crane =< 3 ton C1607 hari 1 1.00 1.00

JUMLAH HARGA ALAT 2.00


D Jumlah (A+B+C) 397,273.00
E Overhead & Profit 10% 39,727.30
F Harga Satuan Pekerjaan (D+E) 437,000.30

Pemasangan 1 buah Valve Ø 1100 mm


Kode AHSP = 8.4.3.13
A TENAGA
Pekerja C9 OH 3 80,000.00 240,000.00
Tukang pipa C24 OH 1.5 125,000.00 187,500.00
Mandor C47 OH 0.3 120,000.00 36,000.00
JUMLAH TENAGA KERJA 463,500.00
B BAHAN
Valve Ø 1100 mm C1535 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1 1.00 1.00
Mobile crane =< 3 ton C1607 hari 1 1.00 1.00

JUMLAH HARGA ALAT 2.00


D Jumlah (A+B+C) 463,503.00
E Overhead & Profit 10% 46,350.30
F Harga Satuan Pekerjaan (D+E) 509,853.30
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 buah Valve Ø 1200 mm
Kode AHSP = 8.4.3.14
A TENAGA
Pekerja C9 OH 3 80,000.00 240,000.00
Tukang pipa C24 OH 1.5 125,000.00 187,500.00
Mandor C47 OH 0.3 120,000.00 36,000.00
JUMLAH TENAGA KERJA 463,500.00
B BAHAN
Valve Ø 1200 mm C1536 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.1 1.00 0.10
Mobile crane =< 3 ton C1607 hari 0.1 1.00 0.10

JUMLAH HARGA ALAT 0.20


D Jumlah (A+B+C) 463,501.20
E Overhead & Profit 10% 46,350.12
F Harga Satuan Pekerjaan (D+E) 509,851.32

Pemasangan 1 buah Tee Ø 150 mm


Kode AHSP = 8.4.3.15
A TENAGA
Pekerja C9 OH 0.106 80,000.00 8,480.00
Tukang pipa C24 OH 0.053 125,000.00 6,625.00
Mandor C47 OH 0.011 120,000.00 1,320.00
JUMLAH TENAGA KERJA 16,425.00
B BAHAN
Tee Ø 150 mm C1509 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.028 1.00 0.03

JUMLAH HARGA ALAT 0.03


D Jumlah (A+B+C) 16,426.03
E Overhead & Profit 10% 1,642.60
F Harga Satuan Pekerjaan (D+E) 18,068.63

Pemasangan 1 buah Tee Ø 200 mm


Kode AHSP = 8.4.3.16
A TENAGA
Pekerja C9 OH 0.216 80,000.00 17,280.00
Tukang pipa C24 OH 0.108 125,000.00 13,500.00
Mandor C47 OH 0.022 120,000.00 2,640.00
JUMLAH TENAGA KERJA 33,420.00
B BAHAN
Tee Ø 200 mm C1510 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.029 1.00 0.03

JUMLAH HARGA ALAT 0.03


D Jumlah (A+B+C) 33,421.03
E Overhead & Profit 10% 3,342.10
F Harga Satuan Pekerjaan (D+E) 36,763.13

Pemasangan 1 buah Tee Ø 250 mm


Kode AHSP = 8.4.3.17
A TENAGA
Pekerja C9 OH 0.326 80,000.00 26,080.00
Tukang pipa C24 OH 0.163 125,000.00 20,375.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 50,415.00
B BAHAN
Tee Ø 250 mm C1511 bh 1 1.00 1.00

JUMLAH HARGA BAHAN -


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.039 1.00 0.04

JUMLAH HARGA ALAT 0.04


D Jumlah (A+B+C) 50,415.04
E Overhead & Profit 10% 5,041.50
F Harga Satuan Pekerjaan (D+E) 55,456.54

Pemasangan 1 buah Tee Ø 300 mm


Kode AHSP = 8.4.3.18
A TENAGA
Pekerja C9 OH 0.436 80,000.00 34,880.00
Tukang pipa C24 OH 0.218 125,000.00 27,250.00
Mandor C47 OH 0.044 120,000.00 5,280.00
JUMLAH TENAGA KERJA 67,410.00
B BAHAN
Tee Ø 300 mm C1512 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.5 1.00 0.50

JUMLAH HARGA ALAT 0.50


D Jumlah (A+B+C) 67,411.50
E Overhead & Profit 10% 6,741.15
F Harga Satuan Pekerjaan (D+E) 74,152.65

Pemasangan 1 buah Tee Ø 400 mm


Kode AHSP = 8.4.3.19
A TENAGA
Pekerja C9 OH 0.656 80,000.00 52,480.00
Tukang pipa C24 OH 0.328 125,000.00 41,000.00
Mandor C47 OH 0.066 120,000.00 7,920.00
JUMLAH TENAGA KERJA 101,400.00
B BAHAN
Tee Ø 400 mm C1513 m 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.5 1.00 0.50

JUMLAH HARGA ALAT 0.50


D Jumlah (A+B+C) 101,401.50
E Overhead & Profit 10% 10,140.15
F Harga Satuan Pekerjaan (D+E) 111,541.65

Pemasangan 1 buah Tee Ø 450 mm


Kode AHSP = 8.4.3.20
A TENAGA
Pekerja C9 OH 0.766 80,000.00 61,280.00
Tukang pipa C24 OH 0.383 125,000.00 47,875.00
Mandor C47 OH 0.077 120,000.00 9,240.00
JUMLAH TENAGA KERJA 118,395.00
B BAHAN
Tee Ø 450 mm C1514 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.5 1.00 0.50

JUMLAH HARGA ALAT 0.50


D Jumlah (A+B+C) 118,396.50
E Overhead & Profit 10% 11,839.65
F Harga Satuan Pekerjaan (D+E) 130,236.15

Pemasangan 1 buah Tee Ø 500 mm


Kode AHSP = 8.4.3.21
A TENAGA
Pekerja C9 OH 0.876 80,000.00 70,080.00
Tukang pipa C24 OH 0.438 125,000.00 54,750.00
Mandor C47 OH 0.088 120,000.00 10,560.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 135,390.00
B BAHAN
Tee Ø 500 mm C1515 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.6 1.00 0.60

JUMLAH HARGA ALAT 0.60


D Jumlah (A+B+C) 135,391.60
E Overhead & Profit 10% 13,539.16
F Harga Satuan Pekerjaan (D+E) 148,930.76

Pemasangan 1 buah Tee Ø 600 mm


Kode AHSP = 8.4.3.22
A TENAGA
Pekerja C9 OH 1.096 80,000.00 87,680.00
Tukang pipa C24 OH 0.548 125,000.00 68,500.00
Mandor C47 OH 0.11 120,000.00 13,200.00
JUMLAH TENAGA KERJA 169,380.00
B BAHAN
Tee Ø 600 mm C1516 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.193 1.00 0.19
Mobile crane =< 3 ton C1607 hari 0.096 1.00 0.10

JUMLAH HARGA ALAT 0.29


D Jumlah (A+B+C) 169,381.29
E Overhead & Profit 10% 16,938.13
F Harga Satuan Pekerjaan (D+E) 186,319.42

Pemasangan 1 buah Tee Ø 700 mm


Kode AHSP = 8.4.3.23
A TENAGA
Pekerja C9 OH 1.316 80,000.00 105,280.00
Tukang pipa C24 OH 0.658 125,000.00 82,250.00
Mandor C47 OH 0.132 120,000.00 15,840.00
JUMLAH TENAGA KERJA 203,370.00
B BAHAN
Tee Ø 700 mm C1517 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.225 1.00 0.23
Mobile crane =< 3 ton C1607 hari 0.113 1.00 0.11

JUMLAH HARGA ALAT 0.34


D Jumlah (A+B+C) 203,371.34
E Overhead & Profit 10% 20,337.13
F Harga Satuan Pekerjaan (D+E) 223,708.47

Pemasangan 1 buah Tee Ø 800 mm


Kode AHSP = 8.4.3.24
A TENAGA
Pekerja C9 OH 1.536 80,000.00 122,880.00
Tukang pipa C24 OH 0.768 125,000.00 96,000.00
Mandor C47 OH 0.154 120,000.00 18,480.00
JUMLAH TENAGA KERJA 237,360.00
B BAHAN
Tee Ø 800 mm C1518 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.257 1.00 0.26
Mobile crane =< 3 ton C1607 hari 0.129 1.00 0.13

JUMLAH HARGA ALAT 0.39


D Jumlah (A+B+C) 237,361.39
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
E Overhead & Profit 10% 23,736.14
F Harga Satuan Pekerjaan (D+E) 261,097.52

Pemasangan 1 buah Tee Ø 900 mm


Kode AHSP = 8.4.3.25
A TENAGA
Pekerja C9 OH 1.756 80,000.00 140,480.00
Tukang pipa C24 OH 0.878 125,000.00 109,750.00
Mandor C47 OH 0.176 120,000.00 21,120.00
JUMLAH TENAGA KERJA 271,350.00
B BAHAN
Tee Ø 900 mm C1519 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.321 1.00 0.32
Mobile crane =< 3 ton C1607 hari 0.161 1.00 0.16

JUMLAH HARGA ALAT 0.48


D Jumlah (A+B+C) 271,351.48
E Overhead & Profit 10% 27,135.15
F Harga Satuan Pekerjaan (D+E) 298,486.63

Pemasangan 1 buah Tee Ø 1000 mm


Kode AHSP = 8.4.3.26
A TENAGA
Pekerja C9 OH 1.976 80,000.00 158,080.00
Tukang pipa C24 OH 0.988 125,000.00 123,500.00
Mandor C47 OH 0.198 120,000.00 23,760.00
JUMLAH TENAGA KERJA 305,340.00
B BAHAN
Tee Ø 1000 mm C1520 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.366 1.00 0.37
Mobile crane =< 3 ton C1607 hari 0.183 1.00 0.18

JUMLAH HARGA ALAT 0.55


D Jumlah (A+B+C) 305,341.55
E Overhead & Profit 10% 30,534.15
F Harga Satuan Pekerjaan (D+E) 335,875.70

Pemasangan 1 buah Tee Ø 1100 mm


Kode AHSP = 8.4.3.27
A TENAGA
Pekerja C9 OH 2.196 80,000.00 175,680.00
Tukang pipa C24 OH 1.098 125,000.00 137,250.00
Mandor C47 OH 0.22 120,000.00 26,400.00
JUMLAH TENAGA KERJA 339,330.00
B BAHAN
Tee Ø 1100 mm C1521 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.386 1.00 0.39
Mobile crane =< 3 ton C1607 hari 0.193 1.00 0.19

JUMLAH HARGA ALAT 0.58


D Jumlah (A+B+C) 339,331.58
E Overhead & Profit 10% 33,933.16
F Harga Satuan Pekerjaan (D+E) 373,264.74

Pemasangan 1 buah Tee Ø 1200 mm


Kode AHSP = 8.4.3.28
A TENAGA
Pekerja C9 OH 2.416 80,000.00 193,280.00
Tukang pipa C24 OH 1.208 125,000.00 151,000.00
Mandor C47 OH 0.242 120,000.00 29,040.00
JUMLAH TENAGA KERJA 373,320.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Tee Ø 1200 mm C1522 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.45 1.00 0.45
Mobile crane =< 3 ton C1607 hari 0.225 1.00 0.23

JUMLAH HARGA ALAT 0.68


D Jumlah (A+B+C) 373,321.68
E Overhead & Profit 10% 37,332.17
F Harga Satuan Pekerjaan (D+E) 410,653.84

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 80 mm


Kode AHSP = 8.4.4.1
A TENAGA
Pekerja C9 OH 1.466 80,000.00 117,280.00
Tukang pipa C24 OH 0.733 125,000.00 91,625.00
Mandor C47 OH 0.147 120,000.00 17,640.00
JUMLAH TENAGA KERJA 226,545.00
B BAHAN
Pipa Ø 80 mm C1497 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 0.606 1.00 0.61
Sewa Genset 1500watt C1605 hari 0.075 1.00 0.08
Sewa Pompa Submersible 3m3/h C1606 hari 0.968 1.00 0.97
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.865 1.00 0.87

JUMLAH HARGA ALAT 2.51


D Jumlah (A+B+C) 226,548.51
E Overhead & Profit 10% 22,654.85
F Harga Satuan Pekerjaan (D+E) 249,203.37

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm


Kode AHSP = 8.4.4.2
A TENAGA
Pekerja C9 OH 1.646 80,000.00 131,680.00
Tukang pipa C24 OH 0.823 125,000.00 102,875.00
Mandor C47 OH 0.165 120,000.00 19,800.00
JUMLAH TENAGA KERJA 254,355.00
B BAHAN
Pipa Ø 100 mm C1498 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 0.65 1.00 0.65
Sewa Genset 1500watt C1605 hari 0.159 1.00 0.16
Sewa Pompa Submersible 3m3/h C1606 hari 1.078 1.00 1.08
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 0.911 1.00 0.91

JUMLAH HARGA ALAT 2.80


D Jumlah (A+B+C) 254,358.80
E Overhead & Profit 10% 25,435.88
F Harga Satuan Pekerjaan (D+E) 279,794.68

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm


Kode AHSP = 8.4.4.3
A TENAGA
Pekerja C9 OH 2.096 80,000.00 167,680.00
Tukang pipa C24 OH 1.048 125,000.00 131,000.00
Mandor C47 OH 0.21 120,000.00 25,200.00
JUMLAH TENAGA KERJA 323,880.00
B BAHAN
Pipa Ø 150 mm C1499 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 0.76 1.00 0.76
Sewa Genset 1500watt C1605 hari 0.369 1.00 0.37
Sewa Pompa Submersible 3m3/h C1606 hari 1.353 1.00 1.35
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.026 1.00 1.03

JUMLAH HARGA ALAT 3.51


D Jumlah (A+B+C) 323,884.51
E Overhead & Profit 10% 32,388.45
F Harga Satuan Pekerjaan (D+E) 356,272.96

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 200 mm


Kode AHSP = 8.4.4.4
A TENAGA
Pekerja C9 OH 2.546 80,000.00 203,680.00
Tukang pipa C24 OH 1.273 125,000.00 159,125.00
Mandor C47 OH 0.255 120,000.00 30,600.00
JUMLAH TENAGA KERJA 393,405.00
B BAHAN
Pipa Ø 200 mm C1500 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 0.87 1.00 0.87
Sewa Genset 1500watt C1605 hari 0.579 1.00 0.58
Sewa Pompa Submersible 3m3/h C1606 hari 1.628 1.00 1.63
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.141 1.00 1.14

JUMLAH HARGA ALAT 4.22


D Jumlah (A+B+C) 393,410.22
E Overhead & Profit 10% 39,341.02
F Harga Satuan Pekerjaan (D+E) 432,751.24

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 250 mm


Kode AHSP = 8.4.4.5
A TENAGA
Pekerja C9 OH 2.996 80,000.00 239,680.00
Tukang pipa C24 OH 1.498 125,000.00 187,250.00
Mandor C47 OH 0.3 120,000.00 36,000.00
JUMLAH TENAGA KERJA 462,930.00
B BAHAN
Pipa Ø 250 mm C1501 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 0.98 1.00 0.98
Sewa Genset 1500watt C1605 hari 0.789 1.00 0.79
Sewa Pompa Submersible 3m3/h C1606 hari 1.903 1.00 1.90
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.256 1.00 1.26

JUMLAH HARGA ALAT 4.93


D Jumlah (A+B+C) 462,935.93
E Overhead & Profit 10% 46,293.59
F Harga Satuan Pekerjaan (D+E) 509,229.52

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 300 mm


Kode AHSP = 8.4.4.6
A TENAGA
Pekerja C9 OH 3.446 80,000.00 275,680.00
Tukang pipa C24 OH 1.723 125,000.00 215,375.00
Mandor C47 OH 0.345 120,000.00 41,400.00
JUMLAH TENAGA KERJA 532,455.00
B BAHAN
Pipa Ø 300 mm C1502 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 1.09 1.00 1.09
Sewa Genset 1500watt C1605 hari 0.999 1.00 1.00
Sewa Pompa Submersible 3m3/h C1606 hari 2.178 1.00 2.18
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.371 1.00 1.37

JUMLAH HARGA ALAT 5.64


D Jumlah (A+B+C) 532,461.64
E Overhead & Profit 10% 53,246.16
F Harga Satuan Pekerjaan (D+E) 585,707.80

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 400 mm


Kode AHSP = 8.4.4.7
A TENAGA
Pekerja C9 OH 4.346 80,000.00 347,680.00
Tukang pipa C24 OH 2.173 125,000.00 271,625.00
Mandor C47 OH 0.435 120,000.00 52,200.00
JUMLAH TENAGA KERJA 671,505.00
B BAHAN
Pipa Ø 400 mm C1503 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 1.31 1.00 1.31
Sewa Genset 1500watt C1605 hari 1.419 1.00 1.42
Sewa Pompa Submersible 3m3/h C1606 hari 2.728 1.00 2.73
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.601 1.00 1.60

JUMLAH HARGA ALAT 7.06


D Jumlah (A+B+C) 671,513.06
E Overhead & Profit 10% 67,151.31
F Harga Satuan Pekerjaan (D+E) 738,664.36

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 450 mm


Kode AHSP = 8.4.4.8
A TENAGA
Pekerja C9 OH 4.796 80,000.00 383,680.00
Tukang pipa C24 OH 2.398 125,000.00 299,750.00
Mandor C47 OH 0.48 120,000.00 57,600.00
JUMLAH TENAGA KERJA 741,030.00
B BAHAN
Pipa Ø 450 mm C1504 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 1.42 1.00 1.42
Sewa Genset 1500watt C1605 hari 1.629 1.00 1.63
Sewa Pompa Submersible 3m3/h C1606 hari 3.003 1.00 3.00
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.716 1.00 1.72

JUMLAH HARGA ALAT 7.77


D Jumlah (A+B+C) 741,038.77
E Overhead & Profit 10% 74,103.88
F Harga Satuan Pekerjaan (D+E) 815,142.64

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 500 mm


Kode AHSP = 8.4.4.9
A TENAGA
Pekerja C9 OH 5.246 80,000.00 419,680.00
Tukang pipa C24 OH 2.623 125,000.00 327,875.00
Mandor C47 OH 0.525 120,000.00 63,000.00
JUMLAH TENAGA KERJA 810,555.00
B BAHAN
Pipa Ø 500 mm C1505 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 1.53 1.00 1.53
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sewa Genset 1500watt C1605 hari 1.839 1.00 1.84
Sewa Pompa Submersible 3m3/h C1606 hari 3.278 1.00 3.28
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 1.831 1.00 1.83

JUMLAH HARGA ALAT 8.48


D Jumlah (A+B+C) 810,564.48
E Overhead & Profit 10% 81,056.45
F Harga Satuan Pekerjaan (D+E) 891,620.93

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 600 mm


Kode AHSP = 8.4.4.10
A TENAGA
Pekerja C9 OH 6.146 80,000.00 491,680.00
Tukang pipa C24 OH 3.073 125,000.00 384,125.00
Mandor C47 OH 0.615 120,000.00 73,800.00
JUMLAH TENAGA KERJA 949,605.00
B BAHAN
Pipa Ø 600 mm C1506 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 1.75 1.00 1.75
Sewa Genset 1500watt C1605 hari 2.259 1.00 2.26
Sewa Pompa Submersible 3m3/h C1606 hari 3.828 1.00 3.83
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 2.061 1.00 2.06

JUMLAH HARGA ALAT 9.90


D Jumlah (A+B+C) 949,615.90
E Overhead & Profit 10% 94,961.59
F Harga Satuan Pekerjaan (D+E) 1,044,577.49

Penyambungan 1 buah pipa baru ke pipa yang ada Ø 700 mm


Kode AHSP = 8.4.4.11
A TENAGA
Pekerja C9 OH 7.046 80,000.00 563,680.00
Tukang pipa C24 OH 3.523 125,000.00 440,375.00
Mandor C47 OH 0.705 120,000.00 84,600.00
JUMLAH TENAGA KERJA 1,088,655.00
B BAHAN
Pipa Ø 700 mm C1507 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 1.97 1.00 1.97
Sewa Genset 1500watt C1605 hari 2.679 1.00 2.68
Sewa Pompa Submersible 3m3/h C1606 hari 4.378 1.00 4.38
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 2.291 1.00 2.29

JUMLAH HARGA ALAT 11.32


D Jumlah (A+B+C) 1,088,667.32
E Overhead & Profit 10% 108,866.73
F Harga Satuan Pekerjaan (D+E) 1,197,534.05

Penyambungan 1 buah 1 buah pipa baru ke pipa yang ada Ø 800 mm


Kode AHSP = 8.4.4.12
A TENAGA
Pekerja C9 OH 7.946 80,000.00 635,680.00
Tukang pipa C24 OH 3.973 125,000.00 496,625.00
Mandor C47 OH 0.795 120,000.00 95,400.00
JUMLAH TENAGA KERJA 1,227,705.00
B BAHAN
Pipa Ø 800 mm C1508 bh 1 1.00 1.00

JUMLAH HARGA BAHAN 1.00


C PERALATAN
Peralatan potong pipa T2/mekanik / cilinder saw C1608 hari 2.19 1.00 2.19
Sewa Genset 1500watt C1605 hari 3.099 1.00 3.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Sewa Pompa Submersible 3m3/h C1606 hari 4.928 1.00 4.93
Sewa Tripot/Tackel & handle crane 2 T C1603 hari 2.521 1.00 2.52

JUMLAH HARGA ALAT 12.74


D Jumlah (A+B+C) 1,227,718.74
E Overhead & Profit 10% 122,771.87
F Harga Satuan Pekerjaan (D+E) 1,350,490.61

Pengetesan 1 m pipa Ø 50 mm
Kode AHSP = 8.4.5.1
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.002 100.00 0.20
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 0.26
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 736.26
E Overhead & Profit 10% 73.63
F Harga Satuan Pekerjaan (D+E) 809.89

Pengetesan 1 m pipa Ø 75 mm
Kode AHSP = 8.4.5.2
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.004 100.00 0.40
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 0.46
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 736.46
E Overhead & Profit 10% 73.65
F Harga Satuan Pekerjaan (D+E) 810.11

Pengetesan 1 m pipa Ø 100 mm


Kode AHSP = 8.4.5.3
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.008 100.00 0.80
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 0.86
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 736.86
E Overhead & Profit 10% 73.69
F Harga Satuan Pekerjaan (D+E) 810.55

Pengetesan 1 m pipa Ø 150 mm


Kode AHSP = 8.4.5.4
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.018 100.00 1.80
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 1.86
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 737.86
E Overhead & Profit 10% 73.79
F Harga Satuan Pekerjaan (D+E) 811.65

Pengetesan 1 m pipa Ø 200 mm


Kode AHSP = 8.4.5.5
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.031 100.00 3.10
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 3.16
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 739.16
E Overhead & Profit 10% 73.92
F Harga Satuan Pekerjaan (D+E) 813.08

Pengetesan 1 m pipa Ø 250 mm


Kode AHSP = 8.4.5.6
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.049 100.00 4.90
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 4.96
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 740.96
E Overhead & Profit 10% 74.10
F Harga Satuan Pekerjaan (D+E) 815.06

Pengetesan 1 m pipa Ø 300 mm


Kode AHSP = 8.4.5.7
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.071 100.00 7.10
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 7.16
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 743.16
E Overhead & Profit 10% 74.32
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 817.48

Pengetesan 1 m pipa Ø 400 mm


Kode AHSP = 8.4.5.8
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.126 100.00 12.60
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 12.66
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 748.66
E Overhead & Profit 10% 74.87
F Harga Satuan Pekerjaan (D+E) 823.53

Pengetesan 1 m pipa Ø 500 mm


Kode AHSP = 8.4.5.9
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.158 100.00 15.80
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 15.86
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 751.86
E Overhead & Profit 10% 75.19
F Harga Satuan Pekerjaan (D+E) 827.05

Pengetesan 1 m pipa Ø 600 mm


Kode AHSP = 8.4.5.10
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.283 100.00 28.30
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 28.36
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 764.36
E Overhead & Profit 10% 76.44
F Harga Satuan Pekerjaan (D+E) 840.80

Pemasangan 1 m2 Allumunium Composit + Rangka Besi Hollow


Kode AHSP = T1
A TENAGA
Pekerja C9 OH 0.6 80,000.00 48,000.00
Tukang Las Konstruksi C28 OH 1 125,000.00 125,000.00
Mandor C47 OH 0.3 120,000.00 36,000.00
JUMLAH TENAGA KERJA 209,000.00
B BAHAN
Allumunium Composite Panel Type PVDF C488 m2 1.1 365,000.00 401,500.00
Besi Hollow 4x4 cm C171 m' 14.2 17,000.00 241,400.00
Pengelasan C334 Ls 1 15,000.00 15,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 657,900.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 866,900.00
E Overhead & Profit 10% 86,690.00
F Harga Satuan Pekerjaan (D+E) 953,590.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 Allumunium Composit + Rangka Besi Hollow (Motif Cutting)
Kode AHSP = T1
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang Las Konstruksi C28 OH 0.8 125,000.00 100,000.00
Mandor C47 OH 0.3 120,000.00 36,000.00
JUMLAH TENAGA KERJA 168,000.00
B BAHAN
Allumunium Composite Panel Type PVDF C488 m2 1.1 365,000.00 401,500.00
Besi Hollow 4x4 cm C171 m' 14.2 17,000.00 241,400.00
Pengelasan C334 Ls 1 15,000.00 15,000.00
JUMLAH HARGA BAHAN 657,900.00
C PERALATAN
Biaya Cutting M2 1.000 600,000.00 600,000.00

JUMLAH HARGA ALAT 600,000.00


D Jumlah (A+B+C) 1,425,900.00
E Overhead & Profit 10% 142,590.00
F Harga Satuan Pekerjaan (D+E) 1,568,490.00

Pemasangan 1 m2 Allumunium Composit Type PE + Rangka Besi Hollow


Kode AHSP = T2
A TENAGA
Pekerja C9 OH 0.4 80,000.00 32,000.00
Tukang Las Konstruksi C28 OH 0.8 125,000.00 100,000.00
Mandor C47 OH 0.3 120,000.00 36,000.00
JUMLAH TENAGA KERJA 168,000.00
B BAHAN
Allumunium Composite Panel Type PE C489 m2 1.1 230,000.00 253,000.00
Besi Hollow 4x4 cm C171 m' 14.1 17,000.00 239,700.00
JUMLAH HARGA BAHAN 492,700.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 660,700.00
E Overhead & Profit 10% 66,070.00
F Harga Satuan Pekerjaan (D+E) 726,770.00

Pemasangan 1 Unit Dudukan Lampu LED Strip (Material Acrylic)


Kode AHSP = T3
A TENAGA
Pabrikasi dan Pemasangan Ls 1 2,500,000.00 2,500,000.00

JUMLAH TENAGA KERJA 2,500,000.00


B BAHAN
Kaca Mika/Acrylic 5mm (Colour) C567 m2 4.1448 520,833.33 2,158,750.00
Stainless Steel Besi Pipe Profil C667 m' 5.28 47,500.00 250,800.00
Sticker Scotlight C480 m' 1 757,500.00 757,500.00
JUMLAH HARGA BAHAN 3,167,050.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,667,050.00
E Overhead & Profit 10% 566,705.00
F Harga Satuan Pekerjaan (D+E) 6,233,755.00

Pemasangan 1 Set Backdrop Type 2


Kode AHSP = T5
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 6,000,000.00 6,000,000.00

JUMLAH TENAGA KERJA 6,000,000.00


B BAHAN
Kayu kelas II C81 M3 0.22638 2,100,000.00 475,398.00
Plywood 18 mm C351 M' 54.34 180,000.00 9,781,200.00
Cat Dasar Kayu C206 Kg 2 59,400.00 118,800.00
Cat Kayu C208 Kg 5 85,000.00 425,000.00
WPC Kisi-kisi C425 M2 19.228 865,000.00 16,632,220.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Material Bantu Ls 1 150,000.00 150,000.00
JUMLAH HARGA BAHAN 27,582,618.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 33,582,618.00
E Overhead & Profit 10% 3,358,261.80
F Harga Satuan Pekerjaan (D+E) 36,940,879.80

Pemasangan 1 Set Backdrop + WPC Kisi kisi


Kode AHSP = T6
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 6,000,000.00 6,000,000.00

JUMLAH TENAGA KERJA 6,000,000.00


B BAHAN
Plywood 18 mm C351 Lbr 3.965 180,000.00 713,699.27
High Laminate Pressure (HPL) C255 m2 10.73 85,382.51 916,154.37
Cat Dasar Kayu C206 Kg 2 59,400.00 118,800.00
Cat Kayu C208 Kg 5 85,000.00 425,000.00
WPC Kisi-kisi C425 M2 17.54 865,000.00 15,172,100.00
Material Bantu Ls 1 150,000.00 150,000.00
JUMLAH HARGA BAHAN 17,495,753.65
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 23,495,753.65
E Overhead & Profit 10% 2,349,575.36
F Harga Satuan Pekerjaan (D+E) 25,845,329.01

Pemasangan 1 m2 Secondary Skin (Material ACP)


Kode AHSP = T6
A TENAGA
Pekerja Las Kontruksi C16 OH 0.4 80,000.00 32,000.00
Tukang C17 OH 0.8 125,000.00 100,000.00
Mandor Las Kontruksi C46 OH 0.275 125,000.00 34,375.00
JUMLAH TENAGA KERJA 166,375.00
B BAHAN
Allumunium Composite Panel Type PVDF C488 m2 1.1 365,000.00 401,500.00
Besi Hollow 4x4 cm C171 m' 14.2 17,000.00 241,400.00
Pengelasan C334 Ls 1 15,000.00 15,000.00

JUMLAH HARGA BAHAN 657,900.00


C PERALATAN
Laser Cutting M2 1 250,000.00 250,000.00

JUMLAH HARGA ALAT 250,000.00


D Jumlah (A+B+C) 1,074,275.00
E Overhead & Profit 10% 107,427.50
F Harga Satuan Pekerjaan (D+E) 1,181,702.50

Mengerjakan 1m2 Cover Kolom Finish HPL


Kode AHSP = T8
A TENAGA
Pekerja C9 OH 0.350 80,000.00 28,000.00
Tukang C17 OH 0.175 125,000.00 21,875.00
Mandor C47 OH 0.002 120,000.00 240.00
JUMLAH TENAGA KERJA 50,115.00
B BAHAN
Tripleks 9 mm C413 m2 1.1 48,611.11 53,472.22
High Laminate Pressure (HPL) C255 M2 1.1 85,382.51 93,920.77
Lem Kayu C292 Kg 0.5 32,500.00 16,250.00

JUMLAH HARGA BAHAN 163,642.99


C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 213,757.99
E Overhead & Profit 10% 21,375.80
F Harga Satuan Pekerjaan (D+E) 235,133.79

Pemasangan 1 m2 Partisi Pembatas Tangga


Kode AHSP = T10
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang C17 OH 0.4 125,000.00 50,000.00
Mandor C47 OH 0.04 120,000.00 4,800.00
JUMLAH TENAGA KERJA 62,800.00
B BAHAN
Profil alluminium Openbek "Profil C" C604 m 7.7 35,333.33 272,066.67
Material Bantu Ls 1 54,413.33 54,413.33
JUMLAH HARGA BAHAN 326,480.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 389,280.00
E Overhead & Profit 10% 38,928.00
F Harga Satuan Pekerjaan (D+E) 428,208.00

Pemasangan 1 M2 Raised Floor


Kode AHSP = T10
A TENAGA
Pekerja Las Kontruksi C16 OH 0.25 80,000.00 20,000.00
Tukang Las Konstruksi C28 OH 0.5 125,000.00 62,500.00
Mandor Las Kontruksi C46 OH 0.175 125,000.00 21,875.00
JUMLAH TENAGA KERJA 104,375.00
B BAHAN
Raised Floor C1542 m2 1 985,000.00 985,000.00
Material Bantu Ls 1 500,000.00 500,000.00
JUMLAH HARGA BAHAN 1,485,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,589,375.00
E Overhead & Profit 10% 158,937.50
F Harga Satuan Pekerjaan (D+E) 1,748,312.50

Pemasangan 1 Unit Kunci Finger Print


Kode AHSP = T11
A TENAGA
Pemasangan Ls 1 1,000,000.00 1,000,000.00
JUMLAH TENAGA KERJA 1,000,000.00
B BAHAN
Kunci Finger Print C1543 m2 1.1 10,130,300.00 11,143,330.00
Material Bantu Ls 1 557,166.50 557,166.50
JUMLAH HARGA BAHAN 11,700,496.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 12,700,496.50
E Overhead & Profit 10% 1,270,049.65
F Harga Satuan Pekerjaan (D+E) 13,970,546.15

Pemasangan 1 Set Kamuflase Tandon


Kode AHSP = T12
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 3,500,000.00 3,500,000.00
JUMLAH TENAGA KERJA 3,500,000.00
B BAHAN
Besi Hollow 4x4 cm C171 M' 49.28 17,000.00 837,760.00
Besi Hollow 2x4 cm C170 M' 316.8 15,500.00 4,910,400.00
Allumunium Composite Panel Type PVDF C488 M2 13.5 365,000.00 4,922,614.84
Pengelasan Ls 1 500.00 500.00
Cat Besi C203 Kg 1 100.00 100.00
JUMLAH HARGA BAHAN 10,671,374.84
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 14,171,374.84
E Overhead & Profit 10% 1,417,137.48
F Harga Satuan Pekerjaan (D+E) 15,588,512.32

Pemasangan 1 Set Folding Door


Kode AHSP = T13
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 15,000,000.00 15,000,000.00
JUMLAH TENAGA KERJA 15,000,000.00
B BAHAN
Folding Door C1544 M' 53.2 3,535,000.00 188,062,000.00
Besi Baja WF C156 M' 414.4 21,086.31 8,738,166.67
Material Bantu Ls 1 1,880,620.00 1,880,620.00
JUMLAH HARGA BAHAN 198,680,786.67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 213,680,786.67
E Overhead & Profit 10% 21,368,078.67
F Harga Satuan Pekerjaan (D+E) 235,048,865.33

Pemasangan 1 Set Backdrop + Panggung


Kode AHSP = T14
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 20,000,000.00 20,000,000.00
JUMLAH TENAGA KERJA 20,000,000.00
B BAHAN
Kayu kelas II C81 M' 4.67 2,100,000.00 9,809,553.60
Plywood 18 mm C351 M' 122.14 180,000.00 21,985,023.06
High Laminate Pressure (HPL) C255 M' 122.14 85,382.51 10,428,536.29
Karpet Tile (Merk Forbo) C299 m2 75.26 182,327.35 13,722,527.55
Lampu LED Strip C883 M' 11.00 295,344.20 3,248,786.20
Material Bantu Ls 1.00 500,000.00 500,000.00
JUMLAH HARGA BAHAN 59,694,426.69
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 79,694,426.69
E Overhead & Profit 10% 7,969,442.67
F Harga Satuan Pekerjaan (D+E) 87,663,869.36

Pemasangan 1 Set Backdrop Lobby


Kode AHSP = T15
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 4,000,000.00 4,000,000.00
JUMLAH TENAGA KERJA 4,000,000.00
B BAHAN
Plywood 9 mm C350 lbr 5.45 85,000.00 463,291.12
High Laminate Pressure (HPL) C255 m2 16.23 85,382.51 1,385,331.28
Allumunium Composite Panel Type PE C489 m2 11.66 230,000.00 2,681,800.00
Profil Allumunium List U C622 m 38.28 6,334.25 242,475.09
Lampu LED Strip C883 M' 8.80 295,344.20 2,599,028.96
Plat Stainlees C1557 cm 315.00 20,000.00 6,300,000.00
Material Bantu Ls 1.00 750,000.00 750,000.00
JUMLAH HARGA BAHAN 14,421,926.45
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 18,421,926.45
E Overhead & Profit 10% 1,842,192.65
F Harga Satuan Pekerjaan (D+E) 20,264,119.10

Pemasangan 1 Set Backdrop Rg. Mushola


Kode AHSP = T16
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 3,000,000.00 3,000,000.00
JUMLAH TENAGA KERJA 3,000,000.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Plywood 9 mm C350 lbr 5.07 85,000.00 430,710.83
High Laminate Pressure (HPL) C255 m2 13.83 85,382.51 1,180,584.02
Wallpaper C419 m2 8.84 48,076.92 425,192.31
Material Bantu Ls 1.00 500,000.00 500,000.00
JUMLAH HARGA BAHAN 2,536,487.15
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,536,487.15
E Overhead & Profit 10% 553,648.72
F Harga Satuan Pekerjaan (D+E) 6,090,135.87

Pemasangan 1 Set Backdrop Ruang Rapat


Kode AHSP = T16
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 2,500,000.00 2,500,000.00
JUMLAH TENAGA KERJA 2,500,000.00
B BAHAN
Plywood 18 mm C351 lbr 9.95 180,000.00 1,791,232.20
High Laminate Pressure (HPL) C255 m2 19.15 85,382.51 1,635,160.52
Material Bantu Ls 1.00 500,000.00 500,000.00
JUMLAH HARGA BAHAN 3,926,392.71
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 6,426,392.71
E Overhead & Profit 10% 642,639.27
F Harga Satuan Pekerjaan (D+E) 7,069,031.99

Memasang 1 M2 Logo dan Tulisan Material Acrylic


Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 2,000,000.00 2,000,000.00
JUMLAH TENAGA KERJA 2,000,000.00
B BAHAN
Kaca Mika/Acrylic 5mm C564 lbr 1.10 520,833.33 572,916.67
Rangka Metal Hollow 4x4 C639 m2 4.40 5,500.00 24,200.00
Material Bantu Ls 1.00 200,000.00 200,000.00
JUMLAH HARGA BAHAN 797,116.67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2,797,116.67
E Overhead & Profit 10% 279,711.67
F Harga Satuan Pekerjaan (D+E) 3,076,828.33

Memasang 1 M2 Logo dan Tulisan Material Acrylic Interior Balai Bahasa


Kode AHSP = T29
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 1,000,000.00 1,000,000.00
JUMLAH TENAGA KERJA 1,000,000.00
B BAHAN
Kaca Mika/Acrylic 5mm C564 M2 1.10 520,833.33 572,916.67
Material Bantu Ls 1.00 200,000.00 200,000.00
JUMLAH HARGA BAHAN 772,916.67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,772,916.67
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 1,772,916.67

Memasang 1 Set Logo dan Tulisan Material Acrylic Rutan Umum


Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 247,916.67 247,916.67
JUMLAH TENAGA KERJA 247,916.67
B BAHAN
Kaca Mika/Acrylic 5mm C564 M2 1.52 520,833.33 791,666.67
Material Bantu Ls 1.00 200,000.00 200,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 991,666.67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,239,583.33
E Overhead & Profit 10% 123,958.33
F Harga Satuan Pekerjaan (D+E) 1,363,541.67

Mengerjakan 1 Set Deep Well


Kode AHSP = T15
JASA PENGEBORAN
A Persiapan Lapangan
Mob, Demob Peralatan Ls 1 1,500,000.00 1,500,000.00
Pembuatan Spull bak / Bak sirkulasi Unit 1 500,000.00 500,000.00
Transportasi Tenaga Kerja Ls 1 1,000,000.00 1,000,000.00
Tenda Kerja Ls 1 200,000.00 200,000.00
JUMLAH TENAGA KERJA 3,200,000.00
B Jasa Konstruksi
Jasa Bor pilot hole M' 75.00 350,000.00 26,250,000.00
Reaming Bor Hole M' 75.00 200,000.00 15,000,000.00
Sewa / Explotasi alat kerja Hari 10.00 150,000.00 1,500,000.00
Solar/olie/bensin/bahan las Ls 1.00 2,500,000.00 2,500,000.00
Buang Lumpur Bor Ls 1.00 500,000.00 500,000.00
Electrical Logging Ls 1.00 500,000.00 500,000.00
Air Kerja Ls 1.00 500,000.00 500,000.00
Spolling ( Pembersihan sumur ) Ls 1.00 2,000,000.00 2,000,000.00
JUMLAH HARGA BAHAN 48,750,000.00
C Lain-Lain
Pumping Test Hari 3.00 500,000.00 1,500,000.00
Analisa Air Bersih Ls 1.00 1,500,000.00 1,500,000.00
Foto dan Laporan Ls 1.00 250,000.00 250,000.00
Pemasangan pompa Ls 1.00 300,000.00 300,000.00
JUMLAH HARGA BAHAN 3,550,000.00
D MATERIAL
Pompa Deepwell Unit 1.00 10,000,000.00 10,000,000.00
Daya : 3 HP
Pipa PVC Medium,dia. 4 " M' 80.00 87,500.00 7,000,000.00
Pipa PVC Medium,dia. 3 " M' 70.00 62,500.00 4,375,000.00
Screen, dia. 3 " M' 5.00 500,000.00 2,500,000.00
Dop dia. 3 " Bh 1.00 150,000.00 150,000.00
Reducer 6 " x 3 " Bh 1.00 150,000.00 150,000.00
Tutup Sumur Bh 1.00 250,000.00 250,000.00
Koral Beton C92 M3 1.50 275,000.00 412,500.00
Pasir beton C97 M3 1.00 100,000.00 100,000.00
Semen Portland C363 Kg 100.00 1,300.00 130,000.00
JUMLAH HARGA ALAT 25,067,500.00
E AKSESORIS POMPA
Panel dan Aksesoris Unit 1.00 6,000,000.00 6,000,000.00
Kabel NYY 3 x 4 mm C835 M' 100.00 23,230.00 2,323,000.00
Dari DW Ke Panel
Kabel NYMHY 3 x 1,5 mm C850 M' 100.00 12,625.00 1,262,500.00
Kabel WLC, Dari DW Ke Panel
Electroda Bh 5.00 150,000.00 750,000.00
Sock / Connector Ls 1.00 300,000.00 300,000.00
Pipa Hisap GIP Medium dia. 2 " M' 10.00 200,000.00 2,000,000.00
Bak Kontrol Unit 1.00 400,000.00 400,000.00
Aksesoris Bak Control ( Manometer, Check valve ) Ls 1.00 2,000,000.00 2,000,000.00
JUMLAH HARGA ALAT 15,035,500.00
F PERIZINAN
Meter Air 2 " + Tera & segel Ls 1.00 Include
D Jumlah (A+B+C+D+E+F) 95,603,000.00
E Overhead & Profit 10% 9,560,300.00
F Harga Satuan Pekerjaan (D+E) 105,344,680.00

Mengerjakan 1m2 Waterproofing Coating


Kode AHSP = T16
A TENAGA
Pekerja C9 OH 0.02 80,000.00 1,600.00
Tukang C17 OH 0.03 125,000.00 3,750.00
Mandor C47 OH 0.006 120,000.00 720.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 6,070.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Waterproofing (Aquaproof) C420 Kg 0.5 168,700.00 84,350.00

JUMLAH HARGA BAHAN 84,350.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 90,420.00
E Overhead & Profit 10% 9,042.00
F Harga Satuan Pekerjaan (D+E) 99,462.00

Mengerjakan 1m2 Waterproofing Fiberglass


Kode AHSP = T17
A TENAGA
Pekerja C9 OH 0.02 80,000.00 1,600.00
Tukang C17 OH 0.03 125,000.00 3,750.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 6,070.00
B BAHAN
Waterproofing Fibreglass C421 Kg 0.5 350,000.00 175,000.00

JUMLAH HARGA BAHAN 175,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 181,070.00
E Overhead & Profit 10% 18,107.00
F Harga Satuan Pekerjaan (D+E) 199,177.00

Memasang 1 m2 Paving Blok 6 cm K-300


Kode AHSP = T17
A TENAGA
Pekerja C9 OH 0.248 80,000.00 19,840.00
Tukang batu C18 OH 0.2 125,000.00 25,000.00
Kepala tukang C39 OH 0.02 150,000.00 3,000.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 49,040.00
B BAHAN
Paving Blok 6 cm K-300 C331 Bh 46 80,000.00 3,680,000.00
Pasir Urug C100 Kg 0.121 75,000.00 9,075.00

JUMLAH HARGA BAHAN 3,689,075.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3,738,115.00
E Overhead & Profit 10% 373,811.50
F Harga Satuan Pekerjaan (D+E) 4,111,926.50

Memasang 1 m2 Rumput Gajah Mini


Kode AHSP = T19
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 25,200.00
B BAHAN
Rumput Gajah Mini C1548 m2 1.1 50,000.00 55,000.00

JUMLAH HARGA BAHAN 55,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 80,200.00
E Overhead & Profit 10% 8,020.00
F Harga Satuan Pekerjaan (D+E) 88,220.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Memasang 1 M Saluran Keliling pas 1/2 Bata Ukuran 0,3x0,4x0,6 m
Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Pas Dinding 1/2 Bata M2 1.22 142,175.00 173,453.50
Plesteran M2 1.32 61,753.12 81,514.12
Acian M2 1.62 38,967.50 63,127.35
Pasir Urug M3 0.01 126,720.00 1,267.20
Lantai Kerja M3 0.01 795,508.36 7,955.08
JUMLAH HARGA BAHAN 327,317.25
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 327,317.25
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 327,317.25

Memasang 1 M Saluran Keliling pas 1/2 Bata Ukuran 0,8x0,9


Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Pas Dinding 1/2 Bata M2 1.81 125,516.00 227,183.96
Plesteran M2 1.91 56,139.20 107,225.87
Acian M2 1.91 35,425.00 67,661.75
Pasir Urug M3 0.03 244,000.00 7,320.00
Lantai Kerja M3 0.09 889,731.83 80,075.86
JUMLAH HARGA BAHAN 489,467.45
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 489,467.45
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 489,467.45

Memasang 1 M Saluran Keliling pas Batu Kali


Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Galian Tanah M2 0.60 63,000.00 37,800.00
Pas Batu Kali M2 0.45 639,200.00 287,640.00
Plesteran M2 2.85 55,240.80 157,436.28
Acian M2 2.85 4,420.00 12,597.00
Pasir Urug M3 0.03 115,200.00 3,456.00
Lantai Kerja M3 0.09 723,189.42 65,087.05
JUMLAH HARGA BAHAN 564,016.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 564,016.33
E Overhead & Profit 10% 56,401.63
F Harga Satuan Pekerjaan (D+E) 620,417.96

Memasang 1 M Buis Beton


Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 168,750.00 168,750.00
JUMLAH TENAGA KERJA 168,750.00
B BAHAN
Galian Tanah M3 1.00 63,000.00 63,000.00
Buis Beton Ø 80 cm x 50 cm C481 Bh 2.00 306,000.00 612,000.00
JUMLAH HARGA BAHAN 675,000.00
C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 843,750.00
E Overhead & Profit 10% 84,375.00
F Harga Satuan Pekerjaan (D+E) 928,125.00

Memasang 1 Bh Bak Kontrol 0,6x0,6x0.6


Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Pas Dinding 1/2 Bata M2 1.30 125,516.00 163,170.80
Plesteran M2 1.17 55,240.80 64,631.74
Acian M2 1.53 4,420.00 6,762.60
Pasir Urug M3 0.02 244,000.00 4,880.00
Lantai Kerja M3 0.02 889,731.83 17,794.64
JUMLAH HARGA BAHAN 257,239.77
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 257,239.77
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 257,239.77

Memasang 1 M Kawat Silet, Include Tiang Pipa GIP 2"


Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 40,459.38 40,459.38
JUMLAH TENAGA KERJA 40,459.38
B BAHAN
Kawat Silet BTO 22 M 1.10 43,125.00 47,437.50
Pipa Galvanis 2" M2 1.10 104,000.00 114,400.00
JUMLAH HARGA BAHAN 161,837.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 202,296.88
E Overhead & Profit 10% 20,229.69
F Harga Satuan Pekerjaan (D+E) 222,526.56

Memasang 1 set Gril Penutup Saluran Type A


Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 200,700.00 200,700.00
JUMLAH TENAGA KERJA 200,700.00
B BAHAN
Besi Siku 5x5 M 9.60 38,250.00 367,200.00
Besi Strip Tebal 5 mm M2 36.30 12,000.00 435,600.00
JUMLAH HARGA BAHAN 802,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,003,500.00
E Overhead & Profit 10% 100,350.00
F Harga Satuan Pekerjaan (D+E) 1,103,850.00

Memasang 1 set Gril Penutup Saluran Type B


Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 261,838.13 261,838.13
JUMLAH TENAGA KERJA 261,838.13
B BAHAN
Besi Siku 5x5 M 12.37 38,250.00 473,152.50
Besi Strip Tebal 5 mm M2 47.85 12,000.00 574,200.00
JUMLAH HARGA BAHAN 1,047,352.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,309,190.63
E Overhead & Profit 10% 130,919.06
F Harga Satuan Pekerjaan (D+E) 1,440,109.69
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Memasang 1 Liter Lapis Resap pengikat (Prime Coat)


Kode AHSP = T31
A TENAGA
Pekerja OH 0.02 80,000.00 1,600.00
Mandor OH 0.00427 120,000.00 512.40
JUMLAH TENAGA KERJA 2,112.40
B BAHAN
Aspal Kg 0.68 14,800.00 10,048.84
Kerosene Kg 0.37 14,800.00 5,487.84
JUMLAH HARGA BAHAN 15,536.68
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 17,649.08
E Overhead & Profit 10% 1,764.91
F Harga Satuan Pekerjaan (D+E) 19,413.99

Memasang 1 M3 Lapis Penetrasi Maccadam


Kode AHSP = T32
A TENAGA
Pekerja OH 0.69 80,000.00 55,200.00
Mandor Oh 0.09 120,000.00 10,800.00
JUMLAH TENAGA KERJA 66,000.00
B BAHAN
Agregat Pokok M3 1.55 275,000.00 426,800.00
Agregat Pengunci M3 0.37 275,000.00 101,475.00
Agregat Penutup M3 0.21 275,000.00 56,925.00
Aspal Kg 107.12 14,800.00 1,585,376.00
Kayu Bakar M3 0.45 500,000.00 225,000.00
JUMLAH HARGA BAHAN 2,395,576.00
C PERALATAN
Sewa Tandem Roller + Operator OH 0.11 708,225.30 75,780.11
Alat bantu Ls 1.00 10,000.00 10,000.00

JUMLAH HARGA ALAT 85,780.11


D Jumlah (A+B+C) 2,547,356.11
E Overhead & Profit 10% 254,735.61
F Harga Satuan Pekerjaan (D+E) 2,802,091.72

Memasang 1 Liter Lapis Perekat


Kode AHSP = T32
A TENAGA
Pekerja OH 0.02 80,000.00 1,600.00
Mandor OH 0.01 120,000.00 648.00
JUMLAH TENAGA KERJA 2,248.00
B BAHAN
Aspal Kg 0.85 14,800.00 12,580.00
Kerosene Ltr 0.21 14,800.00 3,108.00
JUMLAH HARGA BAHAN 15,688.00
C PERALATAN
Alat bantu Ls 1.00 10,000.00 10,000.00

JUMLAH HARGA ALAT 10,000.00


D Jumlah (A+B+C) 27,936.00
E Overhead & Profit 10% 2,793.60
F Harga Satuan Pekerjaan (D+E) 30,729.60

Memasang 1 M2 Latasir Kelas SS-B


Kode AHSP = T31
A TENAGA
Pekerja OH 0.33 80,000.00 26,400.00
Mandor OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 32,400.00
B BAHAN
Pasir Halus Kg 0.63 75,000.00 47,250.00
Filler Ltr 31.50 1,300.00 40,950.00
Aspal Kg 92.70 14,800.00 1,371,960.00
Kayu Bakar Ltr 0.45 500,000.00 225,000.00
JUMLAH HARGA BAHAN 1,685,160.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
Sewa Tandem Roller + Operator Jam 0.02 708,225.30 16,625.91
Alat bantu Ls 1.00 10,000.00 10,000.00

JUMLAH HARGA ALAT 26,625.91


D Jumlah (A+B+C) 1,744,185.91
E Overhead & Profit 10% 174,418.59
F Harga Satuan Pekerjaan (D+E) 1,918,604.51
F Harga Satuan Pekerjaan (Ton) 1,918,604.51
F Harga Satuan Pekerjaan (M3) 4,412,790.36
F Harga Satuan Pekerjaan (M2) 88,255.81

Memasang 1 m' Kansteen uk. 20x30x60


Kode AHSP = T25
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.001 120,000.00 156.00
JUMLAH TENAGA KERJA 90,156.00
B BAHAN
Kansteen uk. 20x30x60 C1553 M2 1.667 25,000.00 41,666.67
pasir beton C97 m3 0.015 100,000.00 1,500.00
Semen Portland C363 Kg 0.200 1,300.00 260.00
Pengecatan m2 0.300 11,470.00 3,441.00

JUMLAH HARGA BAHAN 46,867.67


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 137,023.67
E Overhead & Profit 10% 13,702.37
F Harga Satuan Pekerjaan (D+E) 150,726.03

Pemasangan 1 Unit Panel PP-Pompa


Kode AHSP = T1
A TENAGA
Pekerja Listrik #N/A OH 2 80,000.00 160,000.00
Tukang Listrik C21 OH 4 125,000.00 500,000.00
Mandor Listrik C40 OH 1 120,000.00 120,000.00
JUMLAH TENAGA KERJA 780,000.00
B BAHAN
MCCB 15 A/3 Phasa C956 m2 1 548,430.00 548,430.00
MCB 16 A/3 Phasa C960 m' 3 295,930.00 887,790.00
Kontaktor 3 Phase C876 m' 1 234,825.00 234,825.00
Over Load C994 m' 1 319,968.00 319,968.00
Switch Auto Manual C1059 m' 1 101,000.00 101,000.00
Push Button C1019 m' 1 151,500.00 151,500.00
Pilot Lamp C1016 m' 4 25,250.00 101,000.00
Fuse Kubur C771 m' 3 120,000.00 360,000.00
Box Panel ( 30x40x20 ) cm C713 m' 1 338,350.00 338,350.00
Material Bantu Ls 1 430,866.00 430,866.00
- CU Bars set
- Sepatu Kabel set
- Roll Isolator set
- Spiral Duck Kabel set
- Duck Kabel set
- Mur Baut set
JUMLAH HARGA BAHAN 3,473,729.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,253,729.00
E Overhead & Profit 10% 425,372.90
F Harga Satuan Pekerjaan (D+E) 4,679,101.90

Pemasangan 1 m Kabel NYY 4 x 4 mm2


Kode AHSP = T2
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
A TENAGA
Pekerja Listrik #N/A OH 0.025 80,000.00 2,000.00
Tukang Listrik C21 OH 0.1 125,000.00 12,500.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 15,700.00
B BAHAN
Kabel NYY 4 x 4 mm C831 m' 1.1 34,340.00 37,774.00
JUMLAH HARGA BAHAN 37,774.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 53,474.00
E Overhead & Profit 10% 5,347.40
F Harga Satuan Pekerjaan (D+E) 58,821.40

Pemasangan 1 m Kabel NYM 3 x 2,5 mm


Kode AHSP = T3
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYM 3 x 2,5 mm C842 m' 1.1 12,000.00 13,200.00
Pipa Conduit 20mm C1017 m' 1.1 3,766.67 4,143.33
JUMLAH HARGA BAHAN 17,343.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYA 2 x 1,5 mm2


Kode AHSP = T4
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYA 2 x 1,5 mm C814 m' 1.1 2,020.00 2,222.00
Pipa Conduit 20mm C1017 m' 1.1 3,766.67 4,143.33
JUMLAH HARGA BAHAN 6,365.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYFGbY 4x2,5mm2


Kode AHSP = T5
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYFGbY 4x2,5mm2 C813 m' 1.1 35,350.00 38,885.00
JUMLAH HARGA BAHAN 38,885.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 240 mm


Kode AHSP = T4
A TENAGA
Pekerja Listrik #N/A OH 0.11 #N/A #N/A
Tukang Listrik C21 OH 0.25 125,000.00 31,250.00
Mandor Listrik C40 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 240 mm C818 m' 1.1 1,778,149.25 1,955,964.18
JUMLAH HARGA BAHAN 1,955,964.18
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 185 mm


Kode AHSP = T5
A TENAGA
Pekerja Listrik #N/A OH 0.11 #N/A #N/A
Tukang Listrik C21 OH 0.25 125,000.00 31,250.00
Mandor Listrik C40 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 185 mm C819 m' 1.1 1,318,000.00 1,449,800.00
JUMLAH HARGA BAHAN 1,449,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 120 mm


Kode AHSP = T6
A TENAGA
Pekerja Listrik #N/A OH 0.11 #N/A #N/A
Tukang Listrik C21 OH 0.25 125,000.00 31,250.00
Mandor Listrik C40 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 120 mm C821 m' 1.1 860,000.00 946,000.00
JUMLAH HARGA BAHAN 946,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 95 mm


Kode AHSP = T6
A TENAGA
Pekerja Listrik #N/A OH 0.11 #N/A #N/A
Tukang Listrik C21 OH 0.25 125,000.00 31,250.00
Mandor Listrik C40 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 95 mm C823 m' 1.1 682,000.00 750,200.00
JUMLAH HARGA BAHAN 750,200.00
C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 50 mm


Kode AHSP = T6
A TENAGA
Pekerja Listrik #N/A OH 0.11 #N/A #N/A
Tukang Listrik C21 OH 0.25 125,000.00 31,250.00
Mandor Listrik C40 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 50 mm C825 m' 1.1 346,766.67 381,443.33
JUMLAH HARGA BAHAN 381,443.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 25 mm


Kode AHSP = T6
A TENAGA
Pekerja Listrik #N/A OH 0.05 #N/A #N/A
Tukang Listrik C21 OH 0.115 125,000.00 14,375.00
Mandor Listrik C40 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 25 mm C827 m' 1.1 223,000.00 245,300.00
JUMLAH HARGA BAHAN 245,300.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 16 mm


Kode AHSP = T7
A TENAGA
Pekerja Listrik #N/A OH 0.05 #N/A #N/A
Tukang Listrik C21 OH 0.115 125,000.00 14,375.00
Mandor Listrik C40 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 16 mm C828 m' 1.1 143,000.00 157,300.00
JUMLAH HARGA BAHAN 157,300.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 10 mm


Kode AHSP = T8
A TENAGA
Pekerja Listrik #N/A OH 0.05 #N/A #N/A
Tukang Listrik C21 OH 0.115 125,000.00 14,375.00
Mandor Listrik C40 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 10 mm C829 m' 1.1 112,000.00 123,200.00
JUMLAH HARGA BAHAN 123,200.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 6 mm


Kode AHSP = T9
A TENAGA
Pekerja Listrik #N/A OH 0.025 #N/A #N/A
Tukang Listrik C21 OH 0.1 125,000.00 12,500.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 6 mm C830 m' 1.1 44,440.00 48,884.00
JUMLAH HARGA BAHAN 48,884.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 2,5 mm2


Kode AHSP = T10
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 2,5 mm C832 m' 1.1 21,210.00 23,331.00
JUMLAH HARGA BAHAN 23,331.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 3 x 2,5 mm


Kode AHSP = T8
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 3 x 2,5 mm C836 m' 1.1 20,200.00 22,220.00
JUMLAH HARGA BAHAN 22,220.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel NYY 4 x 16 mm + BC16


Kode AHSP = T9
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel NYY 4 x 16 mm C828 m' 1.1 143,000.00 157,300.00
Kabel BC 16 mm C855 m' 1.1 19,183.00 21,101.30
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 21,101.30
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel Cat 6


Kode AHSP = T11
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel Cat 6 C810 m' 1.1 21,614.00 23,775.40
Pipa Conduit 20mm C1017 m' 1.1 3,766.67 4,143.33
JUMLAH HARGA BAHAN 27,918.73
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kable Tray Uk 20x10


Kode AHSP = T12
A TENAGA
Pekerja Listrik #N/A OH 0.15 #N/A #N/A
Tukang Listrik C21 OH 0.4 125,000.00 50,000.00
Mandor Listrik C40 OH 0.1 120,000.00 12,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kable Tray Uk 20x10 C868 m' 1.1 93,750.00 103,125.00
JUMLAH HARGA BAHAN 103,125.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kable Tray Uk 40x10


Kode AHSP = T13
A TENAGA
Pekerja Listrik #N/A OH 0.15 #N/A #N/A
Tukang Listrik C21 OH 0.4 125,000.00 50,000.00
Mandor Listrik C40 OH 0.1 120,000.00 12,000.00
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kable Tray Uk 40x10 C870 m' 1.1 303,000.00 333,300.00
JUMLAH HARGA BAHAN 333,300.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) #N/A
E Overhead & Profit 10% #N/A
F Harga Satuan Pekerjaan (D+E) #N/A

pemasangan 1 m Kabel ITC 2x2x0,6


Kode AHSP = T14
A TENAGA
Pekerja Listrik #N/A OH 0.02 #N/A #N/A
Tukang Listrik C21 OH 0.04 125,000.00 5,000.00
Mandor Listrik C40 OH 0.01 120,000.00 1,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA #N/A
B BAHAN
Kabel ITC 2x2x0,6 C862 m' 1.1 3,535.00 3,888.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Biaya Manajemen Keselamatan Dan Kesehatan Kerja
Kode AHSP = 1.1.2.1
A TENAGA
OH -
OH -
OH -
JUMLAH TENAGA KERJA -
B BAHAN
Liter -
Liter -
JUMLAH HARGA BAHAN -
C PERALATAN
Helm C109 Bh 10.000 65,100.00 651,000.00
Sepatu C110 Psg 10.000 90,000.00 900,000.00
Sarung Tangan C111 Psg 10.000 50,000.00 500,000.00
Kacamata Pelindung C112 Bh 3.000 60,600.00 181,800.00
Rompi K3 C113 Bh 10.000 115,000.00 1,150,000.00
Kotak P3K C114 Bh 1.000 200,500.00 200,500.00
APAR 3kg C115 Bh 1.000 1,013,000.00 1,013,000.00
Rambu-Rambu Keselamatan C117 Bh 1.000 202,000.00 202,000.00
Penanganan Covid 19 Ls 1.000 750,000.00 750,000.00
- Masker 500 buah
- Wastafel Cuci Tangah
- Sabun cuci tangan dan Hand sanitizer
JUMLAH HARGA ALAT 5,548,300.00
D Jumlah (A+B+C) 5,548,300.00
E Overhead & Profit 10% 554,830.00
F Harga Satuan Pekerjaan (D+E) 6,103,130.00

Pembuatan 1 m2 kantor sementara lantai plesteran


Kode AHSP = 1.1.1.5
A TENAGA
Pekerja C9 OH 2.000 80,000.00 160,000.00
Tukang Kayu C19 OH 2.000 125,000.00 250,000.00
Tukang Batu C18 OH 1.000 125,000.00 125,000.00
Kepala Tukang C39 OH 0.300 150,000.00 45,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 586,000.00
B BAHAN
Dolken kayu, φ8-10/400 cm C77 m3 1.250 20,900.00 26,125.00
Kayu kelas III C86 m3 0.180 1,600,000.00 288,000.00
Paku biasa C318 Kg 0.080 21,000.00 1,680.00
Besi strip C198 Kg 1.100 11,250.00 12,375.00
Semen Portland C363 Kg 35.000 1,300.00 45,500.00
Pasir pasang C99 m3 0.150 100,000.00 15,000.00
Pasir beton C97 m3 0.100 100,000.00 10,000.00
Koral beton C92 m3 0.150 275,000.00 41,250.00
Bata merah C142 Bh 30.000 1,000.00 30,000.00
Seng Plat BJLS 20 C370 Lbr 0.250 56,600.00 14,150.00
Jendela naco C258 Bh 0.200 185,000.00 37,000.00
Kaca Bening 5 mm C544 m2 0.080 128,000.00 10,240.00
Kunci Tanam Pintu 2 Slaag C573 Bh 0.150 450,000.00 67,500.00
Plywood 4 mm C347 Lbr 0.060 111,800.00 6,708.00
JUMLAH HARGA BAHAN 605,528.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,191,528.00
E Overhead & Profit 10% 119,152.80
F Harga Satuan Pekerjaan (D+E) 1,310,680.80
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

HARGA SATUAN PEKERJAAN TANAH Kode AHSP = 1.5.1.


Penggalian 1 m3 tanah biasa sedalam 1 m
Kode AHSP = 1.5.1.1
A TENAGA
Pekerja C9 OH 0.750 80,000.00 60,000.00
Mandor C47 OH 0.025 120,000.00 3,000.00

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 63,000.00


B BAHAN

JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN -


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 63,000.00
E Overhead & Profit 10% 6,300.00
F Harga Satuan Pekerjaan (D+E) 69,300.00

Pengurugan 1 m3 dengan pasir urug


Kode AHSP = 1.5.1.10
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 25,200.00


B BAHAN
Pasir urug C100 m3 1.200 75,000.00 90,000.00

JUMLAH HARGA BAHAN 90,000.00


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 115,200.00
E Overhead & Profit 10% 11,520.00
F Harga Satuan Pekerjaan (D+E) 126,720.00

Pengurugan 1 m3 sirtu padat


Kode AHSP = 1.5.1.14
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Mandor C47 OH 0.025 120,000.00 3,000.00

JUMLAH TENAGA KERJA 23,000.00


B BAHAN
Sirtu C103 m3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 83,000.00
E Overhead & Profit 10% 8,300.00
F Harga Satuan Pekerjaan (D+E) 91,300.00

Pembentukan 1 m3 Badan Jalan Menggunakan Sirtu


Kode AHSP = 1.5.1.15
A TENAGA
Pekerja C9 OH 0.040 80,000.00 3,200.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 4,400.00


B BAHAN
Sirtu C103 m3 1.250 50,000.00 62,500.00

JUMLAH HARGA BAHAN 62,500.00


C PERALATAN - -
Sewa Tandem Roller + Operator - 0.013 708,225.30 9,490.22
Sewa Water Tanker + Operator - 0.070 363,391.19 25,437.38
Alat bantu - 1.000 10,000.00 10,000.00
JUMLAH HARGA ALAT 44,927.60
D Jumlah (A+B+C) 111,827.60
E Overhead & Profit 10% 11,182.76
F Harga Satuan Pekerjaan (D+E) 123,010.36

Pengurugan 1 m3 Tanah Urug


Kode AHSP = 1.5.1.T1
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 25,200.00


B BAHAN
Tanah Urug C105 m3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 85,200.00
E Overhead & Profit 10% 8,520.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 93,720.00

Mengurug 1 m3 tanah subur


Kode AHSP = 1.5.1.T6
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Mandor C47 OH 0.010 120,000.00 1,200.00

JUMLAH TENAGA KERJA 25,200.00


B BAHAN
Tanah Subur C107 M3 1.200 50,000.00 60,000.00

JUMLAH HARGA BAHAN 60,000.00


C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 85,200.00
E Overhead & Profit 10% 8,520.00
F Harga Satuan Pekerjaan (D+E) 93,720.00

Pemasangan 1 m3 pondasi batu belah campuran 1PC : 5PP


Kode AHSP = 3.1.1.3
A TENAGA
Pekerja C9 OH 1.500 80,000.00 120,000.00
Tukang Batu C18 OH 0.750 125,000.00 93,750.00
Kepala Tukang C39 OH 0.075 150,000.00 11,250.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 234,000.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Semen Portland C363 Kg 136.000 1,300.00 176,800.00
Pasir Pasang C99 m3 0.544 100,000.00 54,400.00
JUMLAH HARGA BAHAN 405,200.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 639,200.00
E Overhead & Profit 10% 63,920.00
F Harga Satuan Pekerjaan (D+E) 703,120.00

Pemasangan 1 m3 batu kosong (aanstamping) untuk pondasi gedung


Kode AHSP = 3.1.1.9
A TENAGA
Pekerja C9 OH 0.780 80,000.00 62,400.00
Tukang Batu C18 OH 0.390 125,000.00 48,750.00
Kepala Tukang C39 OH 0.039 150,000.00 5,850.00
Mandor C47 OH 0.039 120,000.00 4,680.00
JUMLAH TENAGA KERJA 121,680.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 1.200 145,000.00 174,000.00
Pasir urug C100 m3 0.432 75,000.00 32,400.00

JUMLAH HARGA BAHAN 206,400.00


C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 328,080.00
E Overhead & Profit 10% 32,808.00
F Harga Satuan Pekerjaan (D+E) 360,888.00

HARGA SATUAN PEKERJAAN BETON Kode AHSP = 4.1.1.


Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),slump (3-6) cm, w/c = 0,87
Kode AHSP = 4.1.1.4
A TENAGA
Pekerja C9 OH 1.200 80,000.00 96,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.060 120,000.00 7,200.00
JUMLAH TENAGA KERJA 131,200.00
B BAHAN
Semen Portland C363 Kg 230.000 1,300.00 299,000.00
Pasir beton (Kg) C98 Kg 893.000 71.43 63,785.71
Koral Beton (Kg) C93 Kg 1027.000 203.70 209,203.70
Air C120 Ltr 200.000 100.00 20,000.00
JUMLAH HARGA BAHAN 591,989.42
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 723,189.42
E Overhead & Profit 10% 72,318.94
F Harga Satuan Pekerjaan (D+E) 795,508.36

Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Kode AHSP = 4.1.1.8
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 384.000 1,300.00 499,200.00
Pasir beton (Kg) C98 Kg 692.000 71.43 49,428.57
Koral Beton (Kg) C93 Kg 1039.000 203.70 211,648.15
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 781,776.72
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 962,311.72
E Overhead & Profit 10% 96,231.17
F Harga Satuan Pekerjaan (D+E) 1,058,542.89
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pembesian 1 Kg dengan besi polos atau ulir
Kode AHSP = 4.1.1.15
A TENAGA
Pekerja C9 OH 0.007 80,000.00 560.00
Tukang Batu C18 OH 0.007 125,000.00 875.00
Kepala Tukang C39 OH 0.001 150,000.00 105.00
Mandor C47 OH 0.000 120,000.00 48.00
JUMLAH TENAGA KERJA 1,588.00
B BAHAN
Besi beton (polos/ulir) C161 Kg 1.050 12,000.00 12,600.00
Kawat beton C267 Kg 0.015 29,900.00 448.50
JUMLAH HARGA BAHAN 13,048.50
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 14,636.50
E Overhead & Profit 10% 1,463.65
F Harga Satuan Pekerjaan (D+E) 16,100.15

Pemasangan 1 m2 bekisting untuk pondasi (2x)


Kode AHSP = 4.1.1.18a
A TENAGA
Pekerja C9 OH 0.520 80,000.00 41,600.00
Tukang Batu C18 OH 0.260 125,000.00 32,500.00
Kepala Tukang C39 OH 0.026 150,000.00 3,900.00
Mandor C47 OH 0.0260 120,000.00 3,120.00
JUMLAH TENAGA KERJA 81,120.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 24,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.300 21,000.00 6,300.00
Minyak bekisting C302 Liter 0.100 5,100.00 510.00
JUMLAH HARGA BAHAN 30,300.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 111,420.00
E Overhead & Profit 10% 11,142.00
F Harga Satuan Pekerjaan (D+E) 122,562.00

Pemasangan 1 m2 bekisting untuk kolom (2x)


Kode AHSP = 4.1.1.20a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.011 2,250,000.00 25,312.50
Plywood 9 mm C350 Lbr 0.263 85,000.00 22,312.50
Dolken kayu, φ8-10/400 cm C77 Batang 1.500 20,900.00 31,350.00
JUMLAH HARGA BAHAN 136,395.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 239,355.00
E Overhead & Profit 10% 23,935.50
F Harga Satuan Pekerjaan (D+E) 263,290.50

Pemasangan 1 m2 bekisting untuk balok (2x)


Kode AHSP = 4.1.1.21a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.014 2,250,000.00 30,375.00
Tripleks 9 mm C413 Lbr 0.263 48,611.11 12,760.42
Dolken kayu, φ8-10/400 cm C77 Batang 1.500 20,900.00 31,350.00
JUMLAH HARGA BAHAN 131,905.42
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 234,865.42
E Overhead & Profit 10% 23,486.54
F Harga Satuan Pekerjaan (D+E) 258,351.96

Pemasangan 1 m2 bekisting untuk plat lantai beton bangunan gedung (2x)


Kode AHSP = 4.1.1.22a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.030 1,600,000.00 48,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.011 2,250,000.00 25,312.50
Tripleks 9 mm C413 Lbr 0.263 48,611.11 12,760.42
Dolken kayu, φ8-10/400 cm C77 Batang 4.500 20,900.00 94,050.00
JUMLAH HARGA BAHAN 189,542.92
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 292,502.92
E Overhead & Profit 10% 29,250.29
F Harga Satuan Pekerjaan (D+E) 321,753.21

Pemasangan 1 m2 bekisting untuk dinding sheerwall (2x)


Kode AHSP = 4.1.1.23a
A TENAGA
Pekerja C9 OH 0.660 80,000.00 52,800.00
Tukang Batu C18 OH 0.330 125,000.00 41,250.00
Kepala Tukang C39 OH 0.033 150,000.00 4,950.00
Mandor C47 OH 0.033 120,000.00 3,960.00
JUMLAH TENAGA KERJA 102,960.00
B BAHAN
Kayu kelas III C86 m3 0.023 1,600,000.00 36,000.00
Paku biasa 2” – 5” (5-10 cm) C317 kg 0.400 21,000.00 8,400.00
Minyak bekisting C302 Liter 0.200 5,100.00 1,020.00
Balok kayu kelas II C67 m3 0.015 2,250,000.00 33,750.00
Plywood 9 mm C350 Lbr 0.263 85,000.00 22,312.50
Dolken kayu, φ8-10/400 cm C77 Batang 2.250 20,900.00 47,025.00
Penjaga jarak bekisting/spacer C335 Buah 3.000 25,000.00 75,000.00
JUMLAH HARGA BAHAN 223,507.50
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 326,467.50
E Overhead & Profit 10% 32,646.75
F Harga Satuan Pekerjaan (D+E) 359,114.25

Pembuatan 1 m' kolom praktis beton bertulang (11x11)


Kode AHSP = 4.1.1.26
A TENAGA
Pekerja C9 OH 0.180 80,000.00 14,400.00
Tukang batu C18 OH 0.020 125,000.00 2,500.00
Tukang kayu C19 OH 0.020 125,000.00 2,500.00
Tukang besi C20 OH 0.020 125,000.00 2,500.00
Kepala tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 23,880.00
B BAHAN
Kayu kelas III C86 m3 0.002 1,600,000.00 3,200.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.010 21,000.00 210.00
Minyak bekisting C302 Ltr 5,100.00 -
Besi Beton (Polos/ulir) C161 Kg 3.000 12,000.00 36,000.00
Kawat beton C267 Kg 0.450 29,900.00 13,455.00
Semen Portland C363 Kg 4.000 1,300.00 5,200.00
Pasir Beton C97 M3 0.006 100,000.00 600.00
koral beton C92 M3 0.009 275,000.00 2,475.00
JUMLAH HARGA BAHAN 61,140.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 85,020.00
E Overhead & Profit 10% 8,502.00
F Harga Satuan Pekerjaan (D+E) 93,522.00

Pembuatan 1 m' ring balok beton bertulang (10x15)


Kode AHSP = 4.1.1.27
A TENAGA
Pekerja C9 OH 0.297 80,000.00 23,760.00
Tukang batu C18 OH 0.033 125,000.00 4,125.00
Tukang kayu C19 OH 0.033 125,000.00 4,125.00
Tukang besi C20 OH 0.033 125,000.00 4,125.00
Kepala tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH TENAGA KERJA 39,435.00
B BAHAN
Kayu kelas III C86 m3 0.003 1,600,000.00 4,800.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.020 21,000.00 420.00
Minyak bekisting C302 Ltr 5,100.00 -
Besi Beton (Polos/ulir) C161 Kg 3.600 12,000.00 43,200.00
Kawat beton C267 Kg 0.050 29,900.00 1,495.00
Semen Portland C363 Kg 5.500 1,300.00 7,150.00
Pasir Beton C97 M3 0.009 100,000.00 900.00
Batu Kerikil C74 M3 0.015 400,000.00 6,000.00
JUMLAH HARGA BAHAN 63,965.00
C PERALATAN - - -
- - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 103,400.00
E Overhead & Profit 10% 10,340.00
F Harga Satuan Pekerjaan (D+E) 113,740.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

Pemasangan 1 Set Pintu P1 Rutan Teroris


Kode AHSP = 4.2.1.T83
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,512,730.13 1,512,730.13

JUMLAH TENAGA KERJA 1,512,730.13


B BAHAN
Besi Baja UNP C158 Kg 63.941 28,000.00 1,790,342.40
Besi Beton (Polos/ulir) C161 Kg 24.593 12,000.00 295,111.75
Besi Plat C183 Kg 50.461 28,000.00 1,412,894.56
Kawat Ornamesh C264 Kg 8.672 26,966.80 233,866.88
Pengelasan C334 m 0.400 15,000.00 6,000.00
Amplas C124 Lbr 30.000 6,900.00 207,000.00
Cat Besi C203 Kg 3.945 74,200.00 292,719.00
Thinner C405 Kg 0.132 51,300.00 6,745.95

JUMLAH HARGA BAHAN 4,244,680.54


C Aksesoris
Engsel Pintu Besi C515 bh 6.000 126,000.00 756,000.00
Grandel Pintu Besi C534 bh 1.000 150,000.00 150,000.00
Pull Handle Stainless 32x300 C633 psg 2.000 450,120.00 900,240.00

JUMLAH HARGA ALAT 1,806,240.00


D Jumlah (A+B+C) 7,563,650.67
E Overhead & Profit 10% 756,365.07
F Harga Satuan Pekerjaan (D+E) 8,320,015.74

Pemasangan 1 Set Pintu P2 Rutan Teroris


Kode AHSP = 4.2.1.T83
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,093,153.25 1,093,153.25

JUMLAH TENAGA KERJA 1,093,153.25


B BAHAN
Besi Baja UNP C158 Kg 51.762 28,000.00 1,449,324.80
Besi Plat C183 Kg 53.917 28,000.00 1,509,668.16
Besi Kotak 4x4 cm tebal 3mm C174 m 7.590 33,333.33 253,000.00
Kaca Mika/Acrylic 5mm C564 m 0.440 520,833.33 229,166.67
Pengelasan C334 m 0.800 15,000.00 12,000.00
Amplas C124 Lbr 15.000 6,900.00 103,500.00
Cat Besi C203 Kg 2.229 74,200.00 165,391.80
Thinner C405 Kg 0.074 51,300.00 3,811.59

JUMLAH HARGA BAHAN 3,725,863.02


C Aksesoris
Engsel Pintu Besi C515 bh 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 bh 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 5,465,766.27
E Overhead & Profit 10% 546,576.63
F Harga Satuan Pekerjaan (D+E) 6,012,342.90

Pemasangan 1 Set Pintu P3 Rutan Teroris


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,008,845.65 1,008,845.65

JUMLAH TENAGA KERJA 1,008,845.65


B BAHAN
Besi Baja UNP C158 Kg 98.956 28,000.00 2,770,768.00
Besi Beton (Polos/ulir) C161 Kg 76.225 12,000.00 914,699.62
Besi Plat C183 Kg 7.776 28,000.00 217,740.60
Besi Siku 5x5 C179 m 7.271 38,250.00 278,115.75
Pengelasan C334 m 2.690 15,000.00 40,350.00
Amplas C124 Lbr 15.000 6,900.00 103,500.00
Cat Besi C203 Kg 0.953 74,200.00 70,675.50
Thinner C405 Kg 0.032 51,300.00 1,628.78
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA BAHAN 4,397,478.24


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 6,053,073.89
E Overhead & Profit 10% 605,307.39
F Harga Satuan Pekerjaan (D+E) 6,658,381.28

Pemasangan 1 Set Pintu P4 Rutan Teroris


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,533,686.61 1,533,686.61

JUMLAH TENAGA KERJA 1,533,686.61


B BAHAN
Besi Baja UNP C158 Kg 42.247 28,000.00 1,182,904.80
Besi Beton (Polos/ulir) C161 Kg 79.577 12,000.00 954,928.78
Besi Plat C183 Kg 50.115 28,000.00 1,403,217.20
Besi Kotak 4x4 cm tebal 3mm C174 m 13.057 33,333.33 435,233.33
Besi Siku 5x5 C179 m 11.253 38,250.00 430,427.25
Pengelasan C334 m 5.500 15,000.00 82,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 3.771 74,200.00 279,836.03
Thinner C405 Kg 0.126 51,300.00 6,449.05

JUMLAH HARGA BAHAN 4,809,996.44


C Aksesoris
Engsel Pintu Besi C515 Kg 6.000 126,000.00 756,000.00
Grandel Pintu Besi C534 Kg 3.000 150,000.00 450,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 1,324,750.00


D Jumlah (A+B+C) 7,668,433.05
E Overhead & Profit 10% 766,843.31
F Harga Satuan Pekerjaan (D+E) 8,435,276.36

Pemasangan 1 Set Pintu P5 Rutan Teroris


Kode AHSP = 4.2.1.T84
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,303,881.31 1,303,881.31

JUMLAH TENAGA KERJA 1,303,881.31


B BAHAN
Besi Baja UNP C158 Kg 107.405 28,000.00 3,007,348.96
Besi Beton (Polos/ulir) C161 Kg 177.532 12,000.00 2,130,383.86
Besi Plat C183 Kg 13.998 28,000.00 391,933.08
Besi Siku 5x5 C179 m 4.598 38,250.00 175,873.50
Pengelasan C334 m 2.500 15,000.00 37,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 1.253 74,200.00 92,974.46
Thinner C405 Kg 0.042 51,300.00 2,142.67

JUMLAH HARGA BAHAN 5,872,656.53


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 7,823,287.83
E Overhead & Profit 10% 782,328.78
F Harga Satuan Pekerjaan (D+E) 8,605,616.62

Pemasangan 1 Set Pintu P6 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pengerjaan Dan Pemasangan Ls 1.000 253,617.50 253,617.50

JUMLAH TENAGA KERJA 253,617.50


B BAHAN
Profil alluminium "Profil C" C599 Kg 5.588 35,333.33 197,442.67
Profil alluminium "Ambang Datar Atas" C609 Kg 1.078 28,855.83 31,106.59
Profil alluminium "Ambang Datar Bawah" C610 Kg 1.078 44,574.00 48,050.77
Profil alluminium "Ambang Datar Tegak" C611 m 2.200 37,770.67 83,095.47
Profil Alluminium Strip C619 m 26.070 13,683.33 356,724.50

JUMLAH HARGA BAHAN 716,419.99


C Aksesoris
Engsel Pintu Kupu-kupu C513 Kg 3.000 82,550.00 247,650.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Kg 1.000 35,400.00 35,400.00
Handle Pintu Aluminium C536 Kg 1.000 15,000.00 15,000.00

JUMLAH HARGA ALAT 298,050.00


D Jumlah (A+B+C) 1,268,087.49
E Overhead & Profit 10% 126,808.75
F Harga Satuan Pekerjaan (D+E) 1,394,896.24

Pemasangan 1 Set Pintu P7 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 217,775.67 217,775.67

JUMLAH TENAGA KERJA 217,775.67


B BAHAN
Profil alluminium "Profil C" C599 Kg 5.291 35,333.33 186,948.67
Profil alluminium "Ambang Datar Atas" C609 Kg 0.627 28,855.83 18,092.61
Profil alluminium "Ambang Datar Bawah" C610 Kg 0.627 44,574.00 27,947.90
Profil alluminium "Ambang Datar Tegak" C611 m 2.189 37,770.67 82,679.99
Profil Alluminium Strip C619 m 18.810 13,683.33 257,383.50

JUMLAH HARGA BAHAN 573,052.66


C Aksesoris
Engsel Pintu Kupu-kupu C513 Kg 3.000 82,550.00 247,650.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Kg 1.000 35,400.00 35,400.00
Handle Pintu Aluminium C536 Kg 1.000 15,000.00 15,000.00

JUMLAH HARGA ALAT 298,050.00


D Jumlah (A+B+C) 1,088,878.33
E Overhead & Profit 10% 108,887.83
F Harga Satuan Pekerjaan (D+E) 1,197,766.16

Pemasangan 1 Set Pintu P8 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,424,307.71 1,424,307.71

JUMLAH TENAGA KERJA 1,424,307.71


B BAHAN
Besi Baja UNP C158 Kg 51.762 28,000.00 1,449,324.80
Besi Plat C183 Kg 107.833 28,000.00 3,019,336.32
Besi Kotak 4x4 cm tebal 3mm C174 m 7.590 33,333.33 253,000.00
Besi Beton (Polos/ulir) C161 Kg 9.176 12,000.00 110,116.33
Pengelasan C334 m 1.000 15,000.00 15,000.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 2.229 74,200.00 165,391.80
Thinner C405 Kg 0.074 51,300.00 3,811.59

JUMLAH HARGA BAHAN 5,050,480.84


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Lever Handle Plate C580 psg 1.000 118,750.00 118,750.00

JUMLAH HARGA ALAT 646,750.00


D Jumlah (A+B+C) 7,121,538.55
E Overhead & Profit 10% 712,153.85
F Harga Satuan Pekerjaan (D+E) 7,833,692.40

Pemasangan 1 Set Pintu P9 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 673,447.50 673,447.50

JUMLAH TENAGA KERJA 673,447.50


B BAHAN
Besi Baja UNP C158 Kg 37.299 28,000.00 1,044,366.40
Besi Plat C183 Kg 27.650 28,000.00 774,188.80
Besi Kotak 4x4 cm tebal 3mm C174 m 6.160 33,333.33 205,333.33
Pengelasan C334 m 1.000 15,000.00 15,000.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 1.217 74,200.00 90,319.95
Thinner C405 Kg 0.041 51,300.00 2,081.50

JUMLAH HARGA BAHAN 2,165,789.98


C Aksesoris
Engsel Pintu Besi C515 Kg 3.000 126,000.00 378,000.00
Grandel Pintu Besi C534 Kg 1.000 150,000.00 150,000.00

JUMLAH HARGA ALAT 528,000.00


D Jumlah (A+B+C) 3,367,237.48
E Overhead & Profit 10% 336,723.75
F Harga Satuan Pekerjaan (D+E) 3,703,961.22

Pemasangan 1 Set Jendela J1 Rutan Teroris


Kode AHSP = 4.2.1.T85
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 596,076.80 596,076.80

JUMLAH TENAGA KERJA 596,076.80


B BAHAN
Besi Baja UNP C158 Kg 49.935 28,000.00 1,398,172.16
Besi Beton (Polos/ulir) C161 Kg 41.135 12,000.00 493,614.79
Kawat Ornamesh C264 Kg 12.366 26,966.80 333,476.84
Pengelasan C334 m 6.560 15,000.00 98,400.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.344 74,200.00 25,554.48
Thinner C405 Kg 0.011 51,300.00 588.92

JUMLAH HARGA BAHAN 2,384,307.19


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2,980,383.99
E Overhead & Profit 10% 298,038.40
F Harga Satuan Pekerjaan (D+E) 3,278,422.39

Pemasangan 1 Set Jendela J2 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,155,226.06 1,155,226.06

JUMLAH TENAGA KERJA 1,155,226.06


B BAHAN
Besi Baja UNP C158 Kg 99.717 28,000.00 2,792,081.60
Besi Beton (Polos/ulir) C161 Kg 85.157 12,000.00 1,021,879.51
Kawat Ornamesh C264 Kg 24.893 26,966.80 671,284.55
Pengelasan C334 m 3.290 15,000.00 49,350.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.683 74,200.00 50,641.50
Thinner C405 Kg 0.023 51,300.00 1,167.08
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA BAHAN 4,620,904.23
C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,776,130.29
E Overhead & Profit 10% 577,613.03
F Harga Satuan Pekerjaan (D+E) 6,353,743.32

Pemasangan 1 Set Ventilasi V1 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 269,502.70 269,502.70

JUMLAH TENAGA KERJA 269,502.70


B BAHAN
Besi Baja UNP C158 Kg 25.043 28,000.00 701,217.44
Besi Beton (Polos/ulir) C161 Kg 13.214 12,000.00 158,567.51
Kawat Ornamesh C264 Kg 4.497 26,966.80 121,264.31
Pengelasan C334 m 3.290 15,000.00 49,350.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.173 74,200.00 12,816.20
Thinner C405 Kg 0.006 51,300.00 295.36

JUMLAH HARGA BAHAN 1,078,010.81


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,347,513.51
E Overhead & Profit 10% 134,751.35
F Harga Satuan Pekerjaan (D+E) 1,482,264.86

Pemasangan 1 Set Ventilasi V2 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 269,559.90 269,559.90

JUMLAH TENAGA KERJA 269,559.90


B BAHAN
Besi Baja UNP C158 Kg 24.663 28,000.00 690,560.64
Kaca Mika/Acrylic 5mm C564 m 0.560 520,833.33 291,666.67
Pengelasan C334 m 3.240 15,000.00 48,600.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.170 74,200.00 12,621.42
Thinner C405 Kg 0.006 51,300.00 290.87

JUMLAH HARGA BAHAN 1,078,239.60


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,347,799.50
E Overhead & Profit 10% 134,779.95
F Harga Satuan Pekerjaan (D+E) 1,482,579.45

Pemasangan 1 Set Ventilasi V3 Rutan Teroris


Kode AHSP = 4.2.1.T86
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 164,622.52 164,622.52

JUMLAH TENAGA KERJA 164,622.52


B BAHAN
Besi Baja UNP C158 Kg 19.030 28,000.00 532,840.00
Besi Beton (Polos/ulir) C161 Kg 3.303 12,000.00 39,641.88
Kawat Ornamesh C264 Kg 0.150 26,966.80 4,045.02
Pengelasan C334 m 2.500 15,000.00 37,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.131 74,200.00 9,738.75
Thinner C405 Kg 0.004 51,300.00 224.44

JUMLAH HARGA BAHAN 658,490.08


C Aksesoris
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 823,112.61
E Overhead & Profit 10% 82,311.26
F Harga Satuan Pekerjaan (D+E) 905,423.87

Pemasangan 1 Set Ventilasi V4 Rutan Teroris


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 430,845.23 430,845.23

JUMLAH TENAGA KERJA 430,845.23


B BAHAN
Besi Baja UNP C158 Kg 61.657 28,000.00 1,726,401.60
Besi Beton (Polos/ulir) C161 Kg 18.108 12,000.00 217,296.22
Kawat Ornamesh C264 Kg 0.825 26,966.80 22,247.61
Pengelasan C334 m 8.100 15,000.00 121,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.425 74,200.00 31,553.55
Thinner C405 Kg 0.014 51,300.00 727.18

JUMLAH HARGA BAHAN 2,154,226.15


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2,585,071.39
E Overhead & Profit 10% 258,507.14
F Harga Satuan Pekerjaan (D+E) 2,843,578.52

Pemasangan 1 Set Ventilasi V5 Rutan Teroris


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 247,659.36 247,659.36

JUMLAH TENAGA KERJA 247,659.36


B BAHAN
Besi Baja UNP C158 Kg 28.164 28,000.00 788,603.20
Besi Beton (Polos/ulir) C161 Kg 7.341 12,000.00 88,093.06
Kawat Ornamesh C264 Kg 0.341 26,966.80 9,195.68
Pengelasan C334 m 3.700 15,000.00 55,500.00
Amplas C124 Lbr 5.000 6,900.00 34,500.00
Cat Besi C203 Kg 0.194 74,200.00 14,413.35
Thinner C405 Kg 0.006 51,300.00 332.17

JUMLAH HARGA BAHAN 990,637.46


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,238,296.82
E Overhead & Profit 10% 123,829.68
F Harga Satuan Pekerjaan (D+E) 1,362,126.50

Pemasangan 1 Set Trali Rutan Teroris


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,024,211.11 1,024,211.11

JUMLAH TENAGA KERJA 1,024,211.11


B BAHAN
Besi Beton (Polos/ulir) C161 Kg 255.131 12,000.00 3,061,571.44
Pengelasan C334 m 67.500 15,000.00 1,012,500.00
Cat Besi C203 Kg 0.300 74,200.00 22,260.00
Thinner C405 Kg 0.010 51,300.00 513.00

JUMLAH HARGA BAHAN 4,096,844.44


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,121,055.55
E Overhead & Profit 10% 512,105.56
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
F Harga Satuan Pekerjaan (D+E) 5,633,161.11

Pemasangan 1 Set Penutup Atap Acrylic


Kode AHSP = 4.2.1.T88
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 9,429,862.75 9,429,862.75

JUMLAH TENAGA KERJA 9,429,862.75


B BAHAN
Besi Kotak 4x4 cm tebal 3mm C174 m 114.906 33,333.33 3,830,200.00
Kaca Mika/Acrylic 5mm C564 m 74.943 520,833.33 39,032,812.50

JUMLAH HARGA BAHAN 42,863,012.50


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 52,292,875.25
E Overhead & Profit 10% 5,229,287.53
F Harga Satuan Pekerjaan (D+E) 57,522,162.78

Pemasangan 1 Set Partisi Ruang Pembesuk


Kode AHSP = 4.2.1.T87
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 1,608,611.54 1,608,611.54

JUMLAH TENAGA KERJA 1,608,611.54


B BAHAN
Tripleks 18 mm C414 m2 8.270 86,805.56 717,881.94
Kaca Mika/Acrylic 12mm C570 m2 3.720 1,145,833.33 4,262,500.00
High Laminate Pressure (HPL) C255 m2 17.030 85,382.51 1,454,064.21

JUMLAH HARGA BAHAN 6,434,446.15


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,043,057.69
E Overhead & Profit 10% 804,305.77
F Harga Satuan Pekerjaan (D+E) 8,847,363.46

Pemasangan 1 Finishing Meja Jaga


Kode AHSP = 4.2.1.T88
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 150,158.24 150,158.24

JUMLAH TENAGA KERJA 150,158.24


B BAHAN
Tripleks 9 mm C413 m2 4.240 48,611.11 206,111.11
High Laminate Pressure (HPL) C255 m2 4.240 85,382.51 362,021.86
Lem Kayu C292 Kg 1.000 32,500.00 32,500.00

JUMLAH HARGA BAHAN 600,632.97


C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 750,791.21
E Overhead & Profit 10% 75,079.12
F Harga Satuan Pekerjaan (D+E) 825,870.33

Pemasangan 1 Set Penutup Manhole


Kode AHSP = 4.2.1.T81
A TENAGA
Pengerjaan Dan Pemasangan Ls 1.000 39,905.36 39,905.36

JUMLAH TENAGA KERJA 39,905.36


B BAHAN
Besi Siku 4x4 C180 m 1.600 20,250.00 32,400.00
Besi Plat 3 mm C185 m 0.230 541,666.67 124,583.33
Pengecatan m2 0.230 11,470.00 2,638.10

JUMLAH HARGA BAHAN 159,621.43


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C Aksesoris

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 199,526.79
E Overhead & Profit 10% 19,952.68
F Harga Satuan Pekerjaan (D+E) 219,479.47

Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP:5PP
Kode AHSP = 4.4.1.10
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 11.5 1,300.00 14,950.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 89,450.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 129,250.00
E Overhead & Profit 10% 12,925.00
F Harga Satuan Pekerjaan (D+E) 142,175.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm
Kode AHSP = 4.4.2.5
A TENAGA
Pekerja C9 OH 0.300 80,000.00 24,000.00
Tukang Batu C18 OH 0.150 125,000.00 18,750.00
Kepala Tukang C39 OH 0.015 150,000.00 2,250.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 46,800.00
B BAHAN
Semen Portland C363 Kg 5.184 1,300.00 6,739.20
Pasir pasang C99 m3 0.026 100,000.00 2,600.00

JUMLAH HARGA BAHAN 9,339.20


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56,139.20
E Overhead & Profit 10% 5,613.92
F Harga Satuan Pekerjaan (D+E) 61,753.12

Pemasangan 1 m2 acian
Kode AHSP = 4.4.2.27
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Batu C18 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Semen Portland C363 Kg 3.250 1,300.00 4,225.00

JUMLAH HARGA BAHAN 4,225.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 35,425.00
E Overhead & Profit 10% 3,542.50
F Harga Satuan Pekerjaan (D+E) 38,967.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 dinding keramik 20cm x 40cm
Kode AHSP = 4.4.3.55
A TENAGA
Pekerja C9 OH 0.900 80,000.00 72,000.00
Tukang Batu C18 OH 0.450 125,000.00 56,250.00
Kepala tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.045 120,000.00 5,400.00
JUMLAH TENAGA KERJA 140,400.00
B BAHAN
Keramik 20x40 cm C283 buah 10.000 8,076.92 80,769.23
Semen Portland C363 Kg 9.300 1,300.00 12,090.00
Pasir pasang C99 M3 0.018 100,000.00 1,800.00
Semen warna C365 Kg 1.940 20,700.00 40,158.00
JUMLAH HARGA BAHAN 134,817.23
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 275,217.23
E Overhead & Profit 10% 27,521.72
F Harga Satuan Pekerjaan (D+E) 302,738.95

Pemasangan 1 m paving block (blok beton) natural tebal 6cm


Kode AHSP = 4.4.3.63
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.001 120,000.00 156.00
JUMLAH TENAGA KERJA 90,156.00
B BAHAN
Paving Blok 6 cm K-300 C331 M2 1.010 80,000.00 80,800.00
pasir beton C97 m3 0.050 100,000.00 5,000.00

JUMLAH HARGA BAHAN 85,800.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 175,956.00
E Overhead & Profit 10% 17,595.60
F Harga Satuan Pekerjaan (D+E) 193,551.60

Memasang 1 m2 lantai keramik ukuran (40 x 40) cm


Kode AHSP = 4.4.3.T11
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang batu C18 OH 0.125 125,000.00 15,625.00
Kepala tukang C39 OH 0.013 150,000.00 1,950.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 39,135.00
B BAHAN
keramik 40x40 cm C276 Buah 6.630 18,666.67 123,760.00
Semen Portland C363 kg 9.800 1,300.00 12,740.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
Semen warna C365 kg 1.300 20,700.00 26,910.00
JUMLAH HARGA BAHAN 167,910.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 207,045.00
E Overhead & Profit 10% 20,704.50
F Harga Satuan Pekerjaan (D+E) 227,749.50

Pemasangan 1 m2 lantai Epoxy


Kode AHSP = 4.4.3.T14
A TENAGA

JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Maxifloor MFT 323 SL C479 m2 1.100 192,000.00 211,200.00

JUMLAH HARGA BAHAN 211,200.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 211,200.00
E Overhead & Profit 10% 21,120.00
F Harga Satuan Pekerjaan (D+E) 232,320.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 m2 langit-langit gypsum + rangka metal hollow
Kode AHSP = 4.5.1.T1
A TENAGA
Pekerja plafond C13 OH 0.4 80,000.00 32,000.00
Tukang plafond C25 OH 0.5 125,000.00 62,500.00
Mandor plafond C42 OH 0.05 120,000.00 6,000.00
JUMLAH TENAGA KERJA 100,500.00
B BAHAN
Rangka Metal Hollow 2x4 C638 m’ 2.1 4,000.00 8,400.00
Rangka Metal Hollow 4x4 C639 m’ 1.6 5,500.00 8,800.00
Kawat Diameter 4 mm C268 Kg 0.15 32,400.00 4,860.00
Ramset C637 Bh 1.05 3,500.00 3,675.00
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 0.364 65,000.00 23,660.00
Screw Bremick C649 kg 0.11 120.00 13.20
JUMLAH HARGA BAHAN 49,408.20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 149,908.20
E Overhead & Profit 10% 14,990.82
F Harga Satuan Pekerjaan (D+E) 164,899.02

Pemasangan 1 m2 langit-langit kalsiboard + rangka metal hollow


Kode AHSP = 4.5.1.T2
A TENAGA
Pekerja plafond C13 OH 0.5 80,000.00 40,000.00
Tukang plafond C25 OH 0.5 125,000.00 62,500.00
Mandor plafond C42 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 111,500.00
B BAHAN
Rangka Metal Hollow 2x4 C638 m’ 2.1 4,000.00 8,400.00
Rangka Metal Hollow 4x4 C639 m’ 1.6 5,500.00 8,800.00
Kawat Diameter 4 mm C268 Kg 0.15 32,400.00 4,860.00
Ramset C637 Bh 1.05 3,500.00 3,675.00
Kalsiboard 3,5 mm C260 Lembar 0.364 19,097.22 6,951.39
Self Drilling Screw dia-10x16mm (truss screw) C650 kg 11 180.00 1,980.00
JUMLAH HARGA BAHAN 34,666.39
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 146,166.39
E Overhead & Profit 10% 14,616.64
F Harga Satuan Pekerjaan (D+E) 160,783.03

Pemasangan 1 m pasang list gypsum langit-langit


Kode AHSP = 4.5.1.T5
A TENAGA
Pekerja plafond C13 OH 0.06 80,000.00 4,800.00
Tukang plafond C25 OH 0.06 125,000.00 7,500.00
Mandor plafond C42 OH 0.009 120,000.00 1,080.00
JUMLAH TENAGA KERJA 13,380.00
B BAHAN
List Profil Gypsum C294 m’ 1.05 20,000.00 21,000.00
Tepung Gypsum C403 Lembar 0.15 4,000.00 600.00

JUMLAH HARGA BAHAN 21,600.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 34,980.00
E Overhead & Profit 10% 3,498.00
F Harga Satuan Pekerjaan (D+E) 38,478.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Pemasangan 1 buah floor drain
Kode AHSP = 5.1.1.14
A TENAGA
Pekerja C9 OH 0.01 80,000.00 800.00
Tukang batu C18 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 15,400.00
B BAHAN
Floor drain C1248 Unit 1 176,750.00 176,750.00
seal tape C657 bh 0.025 7,500.00 187.50
JUMLAH HARGA BAHAN 176,937.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 192,337.50
E Overhead & Profit 10% 19,233.75
F Harga Satuan Pekerjaan (D+E) 211,571.25

pemasangan 1 Bh Valve Dia. 1"


Kode AHSP = 5.1.1.T2
A TENAGA
Pekerja Pipa C12 OH 0.07 80,000.00 5,600.00
Tukang Pipa C24 OH 0.10 125,000.00 12,500.00
Mandor Pipa C41 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 20,500.00
B BAHAN
Valve Ø 1" C1488 bh 1.00 95,950.00 95,950.00
JUMLAH HARGA BAHAN 95,950.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 116,450.00
E Overhead & Profit 10% 11,645.00
F Harga Satuan Pekerjaan (D+E) 128,095.00

Pemasangan 1 Bh Check Valve Diameter 40mm


Kode AHSP = 5.1.1.T6
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,666.67
Tukang Pipa C24 OH 0.08 125,000.00 10,416.67
Mandor Pipa C41 OH 0.04 120,000.00 5,000.00
JUMLAH TENAGA KERJA 22,083.33
B BAHAN
Check Valve Ø 40mm C1231 bh 1.00 618,120.00 618,120.00
JUMLAH HARGA BAHAN 618,120.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 640,203.33
E Overhead & Profit 10% 64,020.33
F Harga Satuan Pekerjaan (D+E) 704,223.67

Pemasangan 1 Bh Check Valve Diameter 32mm


Kode AHSP = 5.1.1.T6
A TENAGA
Pekerja Pipa C12 OH 0.08 80,000.00 6,666.67
Tukang Pipa C24 OH 0.08 125,000.00 10,416.67
Mandor Pipa C41 OH 0.04 120,000.00 5,000.00
JUMLAH TENAGA KERJA 22,083.33
B BAHAN
Check Valve Ø 32mm C1232 bh 1.00 585,000.00 585,000.00
JUMLAH HARGA BAHAN 585,000.00
C PERALATAN

JUMLAH HARGA ALAT -


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
D Jumlah (A+B+C) 607,083.33
E Overhead & Profit 10% 60,708.33
F Harga Satuan Pekerjaan (D+E) 667,791.67

Pemasangan 1 Buah Pressure Gauge


Kode AHSP = 5.1.1.T6
A TENAGA
Pekerja Pipa C12 OH 0.33 80,000.00 26,666.67
Tukang Pipa C24 OH 0.33 125,000.00 41,666.67
Mandor Pipa C41 OH 0.17 120,000.00 20,000.00
JUMLAH TENAGA KERJA 88,333.33
B BAHAN
Pressure Gauge C1445 bh 1.00 560,550.00 560,550.00
JUMLAH HARGA BAHAN 560,550.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 648,883.33
E Overhead & Profit 10% 64,888.33
F Harga Satuan Pekerjaan (D+E) 713,771.67

pemasangan 1 Bh Gate Valve Diameter 50mm / 10 Kg


Kode AHSP = 5.1.1.T7
A TENAGA
Pekerja Pipa C12 OH 0.17 80,000.00 13,333.33
Tukang Pipa C24 OH 0.17 125,000.00 20,833.33
Mandor Pipa C41 OH 0.08 120,000.00 10,000.00
JUMLAH TENAGA KERJA 44,166.67
B BAHAN
Gate Valve Ø 50mm / 10 Kg C1276 bh 1.00 660,944.00 660,944.00
JUMLAH HARGA BAHAN 660,944.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 705,110.67
E Overhead & Profit 10% 70,511.07
F Harga Satuan Pekerjaan (D+E) 775,621.73
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Memasang 1 Set Logo dan Tulisan Material Acrylic Rutan Umum
Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 247,916.67 247,916.67
JUMLAH TENAGA KERJA 247,916.67
B BAHAN
Kaca Mika/Acrylic 5mm C564 M2 1.52 520,833.33 791,666.67
Material Bantu Ls 1.00 200,000.00 200,000.00
JUMLAH HARGA BAHAN 991,666.67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,239,583.33
E Overhead & Profit 10% 123,958.33
F Harga Satuan Pekerjaan (D+E) 1,363,541.67

Mengerjakan 1m2 Waterproofing Coating


Kode AHSP = T16
A TENAGA
Pekerja C9 OH 0.02 80,000.00 1,600.00
Tukang C17 OH 0.03 125,000.00 3,750.00
Mandor C47 OH 0.006 120,000.00 720.00
JUMLAH TENAGA KERJA 6,070.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
Waterproofing (Aquaproof) C420 Kg 0.5 168,700.00 84,350.00

JUMLAH HARGA BAHAN 84,350.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 90,420.00
E Overhead & Profit 10% 9,042.00
F Harga Satuan Pekerjaan (D+E) 99,462.00

Memasang 1 m2 Rumput Gajah Mini


Kode AHSP = T19
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Mandor C47 OH 0.01 120,000.00 1,200.00
JUMLAH TENAGA KERJA 25,200.00
B BAHAN
Rumput Gajah Mini C1548 m2 1.1 50,000.00 55,000.00

JUMLAH HARGA BAHAN 55,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 80,200.00
E Overhead & Profit 10% 8,020.00
F Harga Satuan Pekerjaan (D+E) 88,220.00

Memasang 1 M Saluran Keliling pas 1/2 Bata Ukuran 0,3x0,4x0,6 m


Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Pas Dinding 1/2 Bata M2 1.22 142,175.00 173,453.50
Plesteran M2 1.32 61,753.12 81,514.12
Acian M2 1.62 38,967.50 63,127.35
Pasir Urug M3 0.01 126,720.00 1,267.20
Lantai Kerja M3 0.01 795,508.36 7,955.08
JUMLAH HARGA BAHAN 327,317.25
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 327,317.25
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 327,317.25

Memasang 1 M Saluran Keliling pas Batu Kali


Kode AHSP = T30
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Galian Tanah M2 0.60 63,000.00 37,800.00
Pas Batu Kali M2 0.45 639,200.00 287,640.00
Plesteran M2 2.85 55,240.80 157,436.28
Acian M2 2.85 4,420.00 12,597.00
Pasir Urug M3 0.03 115,200.00 3,456.00
Lantai Kerja M3 0.09 723,189.42 65,087.05
JUMLAH HARGA BAHAN 564,016.33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 564,016.33
E Overhead & Profit 10% 56,401.63
F Harga Satuan Pekerjaan (D+E) 620,417.96

Memasang 1 Bh Bak Kontrol 0,6x0,6x0.6


ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 -
JUMLAH TENAGA KERJA -
B BAHAN
Pas Dinding 1/2 Bata M2 1.30 125,516.00 163,170.80
Plesteran M2 1.17 55,240.80 64,631.74
Acian M2 1.53 4,420.00 6,762.60
Pasir Urug M3 0.02 244,000.00 4,880.00
Lantai Kerja M3 0.02 889,731.83 17,794.64
JUMLAH HARGA BAHAN 257,239.77
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 257,239.77
E Overhead & Profit 10%
F Harga Satuan Pekerjaan (D+E) 257,239.77

Memasang 1 M Kawat Silet, Include Tiang Pipa GIP 2"


Kode AHSP = T31
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1 40,459.38 40,459.38
JUMLAH TENAGA KERJA 40,459.38
B BAHAN
Kawat Silet BTO 22 M 1.10 43,125.00 47,437.50
Pipa Galvanis 2" M2 1.10 104,000.00 114,400.00
JUMLAH HARGA BAHAN 161,837.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 202,296.88
E Overhead & Profit 10% 20,229.69
F Harga Satuan Pekerjaan (D+E) 222,526.56

Memasang 1 m' Kansteen uk. 20x30x60


Kode AHSP = T25
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Batu C18 OH 0.500 125,000.00 62,500.00
Kepala tukang C39 OH 0.050 150,000.00 7,500.00
Mandor C47 OH 0.001 120,000.00 156.00
JUMLAH TENAGA KERJA 90,156.00
B BAHAN
Kansteen uk. 20x30x60 C1553 M2 1.667 25,000.00 41,666.67
pasir beton C97 m3 0.015 100,000.00 1,500.00
Semen Portland C363 Kg 0.200 1,300.00 260.00
Pengecatan m2 0.300 11,470.00 3,441.00

JUMLAH HARGA BAHAN 46,867.67


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 137,023.67
E Overhead & Profit 10% 13,702.37
F Harga Satuan Pekerjaan (D+E) 150,726.03

Pemasangan 1 Unit Panel PP-Pompa


Kode AHSP = T1
A TENAGA
Pekerja Listrik #N/A OH 2 80,000.00 160,000.00
Tukang Listrik C21 OH 4 125,000.00 500,000.00
Mandor Listrik C40 OH 1 120,000.00 120,000.00
JUMLAH TENAGA KERJA 780,000.00
B BAHAN
MCCB 15 A/3 Phasa C956 m2 1 548,430.00 548,430.00
MCB 16 A/3 Phasa C960 m' 3 295,930.00 887,790.00
Kontaktor 3 Phase C876 m' 1 234,825.00 234,825.00
Over Load C994 m' 1 319,968.00 319,968.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)

HARGA SATUAN JUMLAH HARGA


No. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
Switch Auto Manual C1059 m' 1 101,000.00 101,000.00
Push Button C1019 m' 1 151,500.00 151,500.00
Pilot Lamp C1016 m' 4 25,250.00 101,000.00
Fuse Kubur C771 m' 3 120,000.00 360,000.00
Box Panel ( 30x40x20 ) cm C713 m' 1 338,350.00 338,350.00
Material Bantu Ls 1 430,866.00 430,866.00
- CU Bars set
- Sepatu Kabel set
- Roll Isolator set
- Spiral Duck Kabel set
- Duck Kabel set
- Mur Baut set
JUMLAH HARGA BAHAN 3,473,729.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,253,729.00
E Overhead & Profit 10% 425,372.90
F Harga Satuan Pekerjaan (D+E) 4,679,101.90
DAFTAR HARGA SATUAN UPAH
HARGA SATUAN
URAIAN KODE SATUAN
(Rp.)

Pekerja C11 OH 80,000.00


Pekerja Pipa C12 OH 80,000.00
Pekerja Plafond C13 OH 80,000.00
Pekerja Cat C15 OH 80,000.00
Tukang C17 OH 125,000.00
Tukang Batu C18 OH 125,000.00
Tukang Kayu C19 OH 125,000.00
Tukang Besi C20 OH 125,000.00
Tukang Listrik C21 OH 125,000.00
Tukang Pipa C24 OH 125,000.00
Tukang Plafond C25 OH 125,000.00
Tukang Cat C27 OH 125,000.00
Kepala tukang C39 OH 150,000.00
Mandor Listrik C40 OH 120,000.00
Mandor Pipa C41 OH 120,000.00
Mandor Plafond C42 OH 120,000.00
Mandor Cat C44 OH 120,000.00
Mandor C47 OH 120,000.00
DAFTAR HARGA SATUAN MATERIAL
KODE HARGA SATUAN
URAIAN SATUAN
MATERIAL (Rp.)

A. AGREGAT, BATU & KAYU


Balok Kayu Kelas II C67 m3 2,250,000.00
Bilik Bambu C71 m2 135,000.00
Batu belah 15 cm/20 cm C73 m3 145,000.00
Batu Kerikil C74 m3 400,000.00
Dolken kayu, φ8-10/400 cm C77 Btg 20,900.00
Balok Kayu 6x12 Kelas II C82 m3 2,100,000.00
Kayu Kaso 5/7 Kelas II C83 m3 2,100,000.00
Kayu Reng 2/3 Kelas II C84 m3 2,100,000.00
Kayu Reng 3/4 Kelas II C85 m3 2,100,000.00
Kayu kelas III C86 m3 1,600,000.00
Kayu Kaso 5/7 Kelas III C88 m3 1,600,000.00
Koral Beton C92 m3 275,000.00
Koral Beton (Kg) C93 Kg 203.70
Pasir beton C97 m3 100,000.00
Pasir beton (Kg) C98 kg 71.43
Pasir pasang C99 m3 100,000.00
Pasir urug C100 m3 75,000.00
Sirtu C103 m3 50,000.00
Tanah Urug C105 m3 50,000.00
Tanah subur C107 m3 50,000.00
Helm C109 bh 65,100.00
Sepatu C110 psg 90,000.00
Sarung Tangan C111 psg 50,000.00
Kacamata Pelindung C112 bh 60,600.00
Rompi K3 C113 bh 115,000.00
Kotak P3K C114 bh 200,500.00
APAR 3kg C115 bh 1,013,000.00
Rambu-Rambu Keselamatan C117 bh 202,000.00
C. BAHAN BANGUNAN (STRUKTUR)
Amplas C124 Lbr 6,900.00
Bata merah C142 Bh 1,000.00
Batu Alam C146 Bh 3,000.00
Besi Baja UNP C158 Kg 28,000.00
Besi Beton (Polos/ulir) C161 Kg 12,000.00
Besi Kotak 4x4 cm tebal 3mm C174 m 33,333.33
Besi Siku 5x5 C179 m 38,250.00
Besi Strip C198 m 11,250.00
C. BAHAN BANGUNAN (ARSITEK)
KODE HARGA SATUAN
URAIAN SATUAN
MATERIAL (Rp.)

Cat Besi C203 Kg 74,200.00


Cat Dasar C205 Kg 22,500.00
Cat Penutup C213 Kg 30,000.00
Gypsum board 120x240 cm, tebal 9mm C232 Lbr 65,000.00
Jendela Naco C258 Bh 185,000.00
Kalsiboard 3,5 mm C260 M2 19,097.22
Kawat Ornamesh C264 kg 26,966.80
Kawat beton C267 kg 29,900.00
Kawat Diameter 4 mm C268 kg 32,400.00
List profil Gypsum C294 m’ 20,000.00
Minyak bekisting C302 Ltr 5,100.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 21,000.00
Paving Blok 6 cm K-300 C331 m2 80,000.00
Pengelasan C334 cm 15,000.00
Penjaga jarak bekisting/spacer C335 Bh 25,000.00
Plamir C339 Kg 14,200.00
Plywood 4 mm C347 Lbr 111,800.00
Plywood 9 mm C350 Lbr 85,000.00
Semen Portland C363 Kg 1,300.00
Seng Plat BJLS 20 C370 M2 56,600.00
Tepung Gypsum C403 Kg 4,000.00
Thinner C405 Ltr 51,300.00
Tripleks 9 mm C413 M2 48,611.11
Waterproofing (Aquaproof) C420 Kg 168,700.00
Engsel Pintu Kupu-kupu C513 Bh 82,550.00
Engsel Pintu Besi C515 Bh 126,000.00
Grandel Jendela/ Pintu (Spring Knip ) C533 Bh 35,400.00
Grandel Pintu Besi C534 Bh 150,000.00
Handle Pintu Aluminium C536 m 15,000.00
Kaca Bening 5 mm C544 m2 128,000.00
Kaca Mika/Acrylic 5mm C564 m2 520,833.33
Kunci Tanam Pintu 2 Slaag C573 Bh 450,000.00
Lever Handle Plate C580 psg 118,750.00
Profil alluminium "Profil C" C599 m’ 35,333.33
Profil alluminium "Ambang Datar Atas" C609 m’ 28,855.83
Profil alluminium "Ambang Datar Bawah" C610 m’ 44,574.00
Profil alluminium "Ambang Datar Tegak" C611 m’ 37,770.67
Profil Alluminium Strip C619 m' 13,683.33
Ramset C637 bh 3,500.00
Rangka Metal Hollow 2x4 C638 m’ 4,000.00
Rangka Metal Hollow 4x4 C639 m’ 5,500.00
Screw Bremick C649 bh 120.00
Self Drilling Screw dia-10x16mm (truss screw) C650 Bh 180.00
Kansteen uk. 20x30x60 C1553 bh 25,000.00

I. SEWA PERALATAN & JASA


Sewa Tandem Roller + Operator C1596 Jam 708,225.30
Sewa Water Tanker + Operator C1601 Jam 363,391.19