REKAP
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM POLDA SULAWESI TENGAH
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022
REKAPITULASI
No URAIAN PEKERJAAN JUMLAH BIAYA PPN (11%) JUMLAH HARGA
A PEKERJAAN KONSTRUKSI GEDUNG :
1 PERSIAPAN Rp 11,103,130.00 Rp 1,221,344.30 Rp 12,324,474.30
2 PEKERJAAN TANAH Rp 34,065,788.68 Rp 3,747,236.75 Rp 37,813,025.43
3 PEKERJAAN STRUKTUR Rp 1,023,240,071.01 Rp 112,556,407.81 Rp 1,135,796,478.82
4 PEKERJAAN ARSITEKTUR Rp 1,095,213,595.45 Rp 120,473,495.50 Rp 1,215,687,090.95
5 PEKERJAAN MEKANIKAL / PLUMBING Rp 341,733,964.70 Rp 37,590,736.12 Rp 379,324,700.81
6 PEKERJAAN ELEKTRKAL Rp 158,761,062.76 Rp 17,463,716.90 Rp 176,224,779.66
SUB JUMLAH A Rp 2,664,117,612.60 Rp 293,052,937.39 Rp 2,957,170,549.99
B PEKERJAAN FASILITAS UMUM (FASUM)
1 PEKERJAAN JALAN DAN LANDSCAPE Rp 33,580,598.88 Rp 3,693,865.88 Rp 37,274,464.75
2 PEKERJAAN SALURAN Rp 212,615,593.87 Rp 23,387,715.33 Rp 236,003,309.20
SUB JUMLAH B Rp 246,196,192.75 Rp 27,081,581.20 Rp 273,277,773.95
SYANNE RAWUNG
Direktur
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022
RINCIAN
Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
PERSIAPAN
I PEKERJAAN PERSIAPAN
1 Standar Biaya Manajemen Kesehatan Dan Keselamatan Kerja Set 1.00 6,103,130.00 6,103,130.00
2 Standar Pek. Direksi Keet luas 12 m2 (Rangka kayu lokal + multipleks 6 mm + Atap seng) lS 1.00 5,000,000.00 5,000,000.00
JUMLAHPEKERJAAN PERSIAPAN 11,103,130.00
TOTAL BIAYA SITE WORK 11,103,130.00
PEKERJAAN TANAH
II.1 PEKERJAAN TANAH
A Pondasi Poer Plat
1 1.5.1.1 Standar Pek. Galian Tanah M3 57.53 69,300.00 3,986,829.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 38.35 23,100.00 885,885.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 2.84 126,720.00 359,884.80
B Pondasi Batu Kali -
1 1.5.1.1 Standar Pek. Galian Tanah M3 23.71 69,300.00 1,643,103.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 6.02 23,100.00 139,062.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 3.53 126,720.00 447,321.60
C Plat lantai 1 -
1 1.5.1.14 Standar Pek. Timbunan Peninggi Lantai M3 215.31 91,300.00 19,657,803.00
2 1.5.1.10 Standar Pek. Urugan Pasir M3 25.53 126,720.00 3,235,161.60
3 1.5.1.10 Standar Pek. Urugan Pasir Rabat Keliling M3 2.97 126,720.00 376,231.68
C Sloof -
1 1.5.1.10 Standar Pek. Urugan Pasir M3 3.30 126,720.00 418,176.00
D Pot Bunga -
1 1.5.1.T6 Standar Pek. Tanah Subur M3 12.15 93,720.00 1,138,698.00
2 T19 Standar Pek. Rumput Gajah Mini M2 20.15 88,220.00 1,777,633.00
JUMLAH PEKERJAAN TANAH 34,065,788.68
PEKERJAAN STRUKTUR
III.1 PEKERJAAN STRUKTUR BAWAH
A Pekerjaan Pondasi Batu Kali
1 3.1.1.3 Standar Pek. Pondasi Batu Kali M3 23.80 703,120.00 16,734,256.00
2 3.1.1.9 Standar Pek. Batu Kosong (Aanstamping) M3 7.10 360,888.00 2,562,304.80
B Pekerjaan Pondasi Poer pLat -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 2.84 795,508.36 2,259,243.74
2 4.1.1.8 Standar Pek. Beton K 250 M3 11.75 1,058,542.89 12,437,878.98
3 4.1.1.15 Standar Pek. Pembesian KG 1340.96 16,100.15 21,589,592.83
4 4.1.1.18a Standar Pek. Bekisting M2 47.00 122,562.00 5,760,414.00
C Pekerjaan Kolom Pedestal 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 3.23 1,058,542.89 3,419,093.54
2 4.1.1.15 Standar Pek. Pembesian KG 1110.49 16,100.15 17,879,047.76
3 4.1.1.18a Standar Pek. Bekisting M2 51.70 122,562.00 6,336,455.40
D Pekerjaan Sloof 25x35 -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 3.30 795,508.36 2,625,177.59
1 4.1.1.8 Standar Pek. Beton K 250 M3 23.78 1,058,542.89 25,172,149.96
2 4.1.1.15 Standar Pek. Pembesian KG 4106.22 16,100.15 66,110,723.79
3 4.1.1.18a Standar Pek. Bekisting M2 190.24 122,562.00 23,316,194.88
JUMLAH PEKERJAAN STRUKTUR BAWAH 206,202,533.26
III.2 PEKERJAAN STRUKTUR LANTAI 1
A Pekerjaan Plat Lantai 1
1 4.1.1.4 Standar Pek. Lantai Kerja M3 26.12 795,508.36 20,778,678.36
2 4.1.1.8 Standar Pek. Beton K 250 M3 37.37 1,058,542.89 39,557,747.86
3 4.1.1.15 Standar Pek. Pembesian KG 1374.20 16,100.15 22,124,813.48
4 4.1.1.4 Standar Pek. Rabat Keliling M3 2.97 795,508.36 2,361,864.32
B Pekerjaan Kolom 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 11.70 1,058,542.89 12,384,951.83
2 4.1.1.15 Standar Pek. Pembesian KG 2323.52 16,100.15 37,409,018.06
3 4.1.1.20a Standar Pek. Bekisting M2 188.00 263,290.50 49,498,614.00
C Pekerjaan Kolom 10x40 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.19 1,058,542.89 201,123.15
2 4.1.1.15 Standar Pek. Pembesian KG 27.53 16,100.15 443,275.72
3 4.1.1.20a Standar Pek. Bekisting M2 3.20 263,290.50 842,529.60
D Pekerjaan Dinding Beton -
1 4.1.1.8 Standar Pek. Beton K 250 M3 27.77 1,058,542.89 29,395,736.10
2 4.1.1.15 Standar Pek. Pembesian KG 2487.93 16,100.15 40,056,104.00
3 4.1.1.23a Standar Pek. Bekisting M2 337.20 359,114.25 121,093,325.10
E Pekerjaan Kolom Praktis dan Balok Praktis -
1 4.1.1.26 Standar Pek. Kolom (Termasuk Bekisting Dan Pembesian) M 135.56 93,522.00 12,677,426.67
2 4.1.1.27 Standar Pek. Balok (Termasuk Bekisting Dan Pembesian) M 118.22 113,740.00 13,446,595.56
F Pekerjaan Meja Beton Ruang Besuk -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.33 1,058,542.89 349,319.15
2 4.1.1.15 Standar Pek. Pembesian KG 32.04 16,100.15 515,820.98
3 4.1.1.22a Standar Pek. Bekisting M2 4.15 321,753.21 1,335,275.81
4 4.4.3.T11 Standar Pek. Keramik Ukuran 40x40 M2 4.15 227,749.50 945,160.43
JUMLAH PEKERJAAN STRUKTUR LANTAI 1 405,417,380.17
III.3 PEKERJAAN STRUKTUR ATAS
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022
RINCIAN
Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
B Pekerjaan Ring Balok 25x25
1 4.1.1.8 Standar Pek. Beton K 250 M3 16.99 1,058,542.89 17,984,643.73
2 4.1.1.15 Standar Pek. Pembesian KG 3744.64 16,100.15 60,289,275.83
3 4.1.1.21a Standar Pek. Bekisting M2 135.92 258,351.96 35,115,198.18
B Pekerjaan Ring Balok 15x20 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 3.14 1,058,542.89 3,323,824.68
2 4.1.1.15 Standar Pek. Pembesian KG 947.02 16,100.15 15,247,202.20
3 4.1.1.21a Standar Pek. Bekisting M2 41.87 258,351.96 10,816,335.32
E Pekerjaan Plat Kanopi -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.51 1,058,542.89 539,856.87
2 4.1.1.15 Standar Pek. Pembesian KG 43.13 16,100.15 694,325.54
3 4.1.1.22a Standar Pek. Bekisting M2 5.95 321,753.21 1,914,431.59
E Pekerjaan Listplank Beton -
1 4.1.1.8 Standar Pek. Beton K 250 M3 1.37 1,058,542.89 1,450,203.76
2 4.1.1.15 Standar Pek. Pembesian KG 447.54 16,100.15 7,205,485.55
3 4.1.1.22a Standar Pek. Bekisting M2 56.68 321,753.21 18,236,971.85
A Pekerjaan Plat Atap -
1 4.1.1.8 Standar Pek. Beton K 250 M3 37.40 1,058,542.89 39,589,504.14
2 4.1.1.15 Standar Pek. Pembesian KG 2950.71 16,100.15 47,506,858.61
3 4.1.1.22a Standar Pek. Bekisting M2 338.80 321,753.21 109,009,986.98
4 T16 Standar Pek. Waterproofing M2 429.27 99,462.00 42,696,052.74
JUMLAH PEKERJAAN STRUKTUR ATAS 411,620,157.58
JUMLAH PEKERJAAN STRUKTUR 1,023,240,071.01
PEKERJAAN ARSITEKTUR
IV,1 PEKERJAAN FINISHING DINDING
A PEKERJAAN FINISHING DINDING LANTAI 1
1 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps M2 875.96 142,175.00 124,539,613.00
2 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps (Area Pot Bunga) M2 23.74 142,175.00 3,375,234.50
3 4.4.2.5 Standar Pek. Plesteran Dinding M2 1514.14 61,753.12 93,502,869.12
4 4.4.2.5 Standar Pek. Plesteran Pondasi Batu Kali M2 14.92 61,753.12 921,356.55
5 4.4.2.27 Standar Pek. Acian M2 1818.22 38,967.50 70,851,487.85
6 4.4.3.55 Standar Pek. Keramik Dinding 20x40 (Km/Wc) M2 34.72 302,738.95 10,511,096.48
7 4.4.1.25a Standar Pek. Keramik Dinding Batu alam Type Palimanan M2 14.85 274,422.50 4,075,174.13
8 4.4.1.25a Standar Pek. Keramik Dinding Batu alam Type Andesit M2 17.05 274,422.50 4,678,903.63
9 T30 Standar Pek. Logo Set 1.00 1,363,541.67 1,363,541.67
JUMLAH PEKERJAAN FINISHING DINDING 313,819,276.91
IV,2 PEKERJAAN FINISHING LANTAI
A PEKERJAAN FINISHING LANTAI 1
1 4.4.3.T11 Standar Pek. Keramik Ukuran 40x40 M2 138.07 227,749.50 31,445,373.47
2 4.4.3.T11 Standar Pek. Keramik Ukuran 40x40 M2 14.43 227,749.50 3,286,425.29
3 4.4.3.T11 Standar Pek. Keramik Unpolished Ukuran 40x40 (Km/Wc) M2 6.87 227,749.50 1,564,639.07
4 4.4.3.T14 Standar Pek. Lantai Epoxy M2 297.40 232,320.00 69,091,968.00
5 4.4.3.63 Standar Pek. Paving Blok M2 335.17 193,551.60 64,872,689.77
6 4.1.1.4 Standar Pek. Lantai Kerja Pengancing Tepi Paving M3 1.51 795,508.36 1,198,512.89
JUMLAH PEKERJAAN FINISHING LANTAI 171,459,608.48
IV,3 PEKERJAAN PINTU DAN JENDELA ALLUMUNIUM
A PEKERJAAN PINTU DAN JENDELA ALLUMUNIUM LANTAI 1
1 4.2.1.T83 Standar Pekerjaan Pintu Utama (P1) Set 1.00 8,320,015.74 8,320,015.74
2 4.2.1.T83 Standar Pekerjaan Pintu (P2) Set 3.00 6,012,342.90 18,037,028.69
3 4.2.1.T84 Standar Pekerjaan Pintu (P3) Set 5.00 6,658,381.28 33,291,906.40
4 4.2.1.T84 Standar Pekerjaan Pintu (P4) Set 1.00 8,435,276.36 8,435,276.36
5 4.2.1.T84 Standar Pekerjaan Pintu (P5) Set 10.00 8,605,616.62 86,056,166.18
6 4.2.1.T85 Standar Pekerjaan Pintu (P6) Set 1.00 1,394,896.24 1,394,896.24
7 4.2.1.T85 Standar Pekerjaan Pintu (P7) Set 1.00 1,197,766.16 1,197,766.16
8 4.2.1.T85 Standar Pekerjaan Pintu (P8) Set 2.00 7,833,692.40 15,667,384.80
9 4.2.1.T86 Standar Pekerjaan Pintu (P9) Set 2.00 3,703,961.22 7,407,922.45
8 4.2.1.T85 Standar Pekerjaan Jendela (J1) Set 1.00 3,278,422.39 3,278,422.39
9 4.2.1.T86 Standar Pekerjaan Jendela (J2) Set 1.00 6,353,743.32 6,353,743.32
9 4.2.1.T86 Standar Pekerjaan Ventilasi (V1) Set 5.00 1,482,264.86 7,411,324.32
10 4.2.1.T86 Standar Pekerjaan Ventilasi (V2) Set 1.00 1,482,579.45 1,482,579.45
11 4.2.1.T86 Standar Pekerjaan Ventilasi (V3) Set 10.00 905,423.87 9,054,238.67
12 4.2.1.T87 Standar Pekerjaan Ventilasi (V4) Set 12.00 2,843,578.52 34,122,942.29
13 4.2.1.T87 Standar Pekerjaan Ventilasi (V5) Set 4.00 1,362,126.50 5,448,506.02
14 4.2.1.T87 Standar Pekerjaan Trali Void Koridor Set 1.00 5,633,161.11 5,633,161.11
15 4.2.1.T88 Standar Pekerjaan Penutup Atap Acrylic Set 1.00 57,522,162.78 57,522,162.78
16 4.2.1.T87 Standar Pekerjaan Partisi Ruang Besuk (PR) Set 2.00 8,847,363.46 17,694,726.92
17 4.2.1.T88 Standar Pekerjaan Finishing Meja Ruang Jaga Set 1.00 825,870.33 825,870.33
JUMLAH PEKERJAAN PINTU DAN JENDELA ALLUMUNIUM LANTAI 1 328,636,040.60
IV,4 PEKERJAAN ATAP DAN LANGIT-LANGIT
A PEKERJAAN LANGIT-LANGIT LANTAI 1
1 4.5.1.T1 Standar Pek. Langit-Langit Gypsum + Rangka Hollow M2 83.75 164,899.02 13,810,292.93
2 4.5.1.T5 Standar Pek. List Gypsum M 122.92 38,478.00 4,729,715.76
3 4.5.1.T2 Standar Pek. Langit-Langit Kalsiboard + Rangka Hollow M2 8.43 160,783.03 1,355,400.92
JUMLAH PEKERJAAN ATAP DAN LANGIT-LANGIT 19,895,409.61
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022
RINCIAN
Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
IV,5 PEKERJAAN PENGECATAN
A PEKERJAAN PENGECATAN LANTAI 1
1 4.7.1.10 Standar Pek. Cat Dinding M2 2249.84 24,409.00 54,916,344.56
2 4.7.1.15 Standar Pek. Cat Langit Langit M2 92.18 17,842.00 1,644,675.56
JUMLAH PEKERJAAN PENGECATAN 56,561,020.12
I.1 PEKERJAAN PAGAR ANTAR GEDUNG
I.1,1 PEKERJAAN TANAH
A Pondasi Poer Plat (P1)
1 1.5.1.1 Standar Pek. Galian Tanah M3 5.76 69,300.00 399,168.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 4.29 23,100.00 99,099.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 0.36 126,720.00 45,619.20
B Pondasi Poer Plat (P2) -
1 1.5.1.1 Standar Pek. Galian Tanah M3 2.88 69,300.00 199,584.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 2.56 23,100.00 59,136.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 0.12 126,720.00 15,206.40
C Pondasi Batu Kali -
1 1.5.1.1 Standar Pek. Galian Tanah M3 6.55 69,300.00 453,915.00
2 1.5.1.T1 Standar Pek. Urugan Kembali M3 2.18 23,100.00 50,435.00
3 1.5.1.10 Standar Pek. Urugan Pasir M3 0.82 126,720.00 103,910.40
JUMLAH PEKERJAAN TANAH 1,426,073.00
I.1,2 PEKERJAAN STRUKTUR
A Pekerjaan Pondasi Batu Kali
1 3.1.1.3 Standar Pek. Pondasi Batu Kali M3 7.21 703,120.00 5,069,495.20
2 3.1.1.9 Standar Pek. Batu Kosong (Aanstamping) M3 1.63 360,888.00 588,247.44
B Pekerjaan Pondasi Poer Plat (P1) -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 0.36 795,508.36 286,383.01
2 4.1.1.8 Standar Pek. Beton K 250 M3 1.00 1,058,542.89 1,058,542.89
3 4.1.1.15 Standar Pek. Pembesian KG 110.62 16,100.15 1,781,049.82
4 4.1.1.18a Standar Pek. Bekisting M2 4.00 122,562.00 490,248.00
C Pekerjaan Pondasi Poer Plat (P2) -
1 4.1.1.4 Standar Pek. Lantai Kerja M3 0.12 795,508.36 95,461.00
2 4.1.1.8 Standar Pek. Beton K 250 M3 0.32 1,058,542.89 338,733.73
3 4.1.1.15 Standar Pek. Pembesian KG 37.76 16,100.15 607,908.05
4 4.1.1.18a Standar Pek. Bekisting M2 0.80 122,562.00 98,049.60
D Pekerjaan Kolom Pedestal 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.47 1,058,542.89 497,515.16
2 4.1.1.15 Standar Pek. Pembesian KG 89.78 16,100.15 1,445,391.38
3 4.1.1.18a Standar Pek. Bekisting M2 0.47 122,562.00 57,604.14
E Pekerjaan Sloof 25x35 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 1.51 1,058,542.89 1,598,399.77
2 4.1.1.15 Standar Pek. Pembesian KG 205.29 16,100.15 3,305,207.13
3 4.1.1.18a Standar Pek. Bekisting M2 12.21 122,562.00 1,496,482.02
F Pekerjaan Kolom 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 2.86 1,058,542.89 3,027,432.67
2 4.1.1.15 Standar Pek. Pembesian KG 395.49 16,100.15 6,367,492.44
3 4.1.1.20a Standar Pek. Bekisting M2 45.98 263,290.50 12,106,097.19
G Pekerjaan Ring Balok 25x25 -
1 4.1.1.8 Standar Pek. Beton K 250 M3 1.51 1,058,542.89 1,598,399.77
2 4.1.1.15 Standar Pek. Pembesian KG 205.29 16,100.15 3,305,207.13
3 4.1.1.21a Standar Pek. Bekisting M2 12.21 258,351.96 3,154,477.41
JUMLAH PEKERJAAN STRUKTUR 48,373,824.95
I.1,3 PEKERJAAN FINISHING DINDING
1 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps M2 129.20 142,175.00 18,369,010.00
2 4.4.2.5 Standar Pek. Plesteran Dinding M2 258.40 61,753.12 15,957,006.21
3 4.4.2.5 Standar Pek. Plesteran Pondasi Batu Kali M2 13.50 61,753.12 833,667.12
4 4.4.2.27 Standar Pek. Acian M2 271.90 38,967.50 10,595,263.25
5 T31 Standar Pek. Kawat Silet Include Tiang M 17.60 222,526.56 3,916,467.50
JUMLAH PEKERJAAN FINISHING DINDING 49,671,414.08
I.1,4 PEKERJAAN PENGECATAN
1 4.7.1.10 Standar Pek. Cat Dinding M2 271.90 24,409.00 6,636,807.10
JUMLAH PEKERJAAN PENGECATAN 6,636,807.10
JUMLAH PEKERJAAN PAGAR ANTAR GEDUNG 106,108,119.12
II.2 PEKERJAAN SALURAN KELILING GEDUNG
A Pekerjaan Saluran Keliling
1 T30 Standar Pek. Saluran Keliling Bangunan Pas 1/2 Bata M 92.50 327,317.25 30,276,845.81
2 T31 Standar Pek.Bak Kontrol Bh 6.00 257,239.77 1,543,438.64
B Pekerjaan Plat Penutup Saluran Depan Bangunan
1 4.1.1.8 Standar Pek. Beton K 250 M3 0.18 1,058,542.89 190,537.72
2 4.1.1.15 Standar Pek. Pembesian KG 16.24 16,100.15 261,543.31
3 4.1.1.22a Standar Pek. Bekisting M2 1.79 321,753.21 575,938.24
JUMLAH PEKERJAAN SALURAN KELILING GEDUNG 32,848,303.72
II.3 PEKERJAAN SALURAN LINGKUNGAN
A Pekerjaan Saluran
1 T30 Standar Pek. Saluran Keliling Pas Batu Kali M 51.85 620,417.96 32,168,671.25
B Pekerjaan Plat Penutup Saluran Jalan -
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022
RINCIAN
Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
1 4.1.1.8 Standar Pek. Beton K 250 M3 2.08 1,058,542.89 2,201,769.21
2 4.1.1.15 Standar Pek. Pembesian KG 1465.12 16,100.15 23,588,709.63
3 4.1.1.22a Standar Pek. Bekisting M2 13.87 321,753.21 4,461,644.49
A Pekerjaan Saluran -
1 T30 Standar Pek. Saluran Pas Batu Kali Satu Sisi Area Dinding Penahan Tanah M 2.70 620,417.96 1,675,128.49
2 4.1.1.4 Standar Pek. Lantai Kerja M3 2.25 795,508.36 1,789,893.81
JUMLAH PEKERJAAN SALURAN LINGKUNGAN 65,885,816.88
JUMLAH PEKERJAAN ARSITEKTUR 1,095,213,595.45
PEKERJAAN MEKANIKAL / PLUMBING
V.1 PEKERJAAN MEKANIKAL
A PEKERJAAN SISTEM TATA UDARA
1 T11 Standar AC Split Wall Mounted 1PK Bh 4.00 5,150,000.00 20,600,000.00
1 T38 Standar Instalasi Pipa Refrigerant 1/4''x3/8' dan Kabel Kontrol NYM 3x2.5mm M' 18.00 105,000.00 1,890,000.00
2 T39 Standar Instalasi Pipa Drain AC, PVC AW Ø 3/4'' M' 12.00 23,250.00 279,000.00
3 Standar Test and Commisioning Ls 1.00 600,000.00 600,000.00
JUMLAH PEKERJAAN SISTEM TATA UDARA 23,369,000.00
V.2 PEKERJAAN PLUMBING
A PEKERJAAN INSTALASI AIR HUJAN
1 8.4.1.T5 Standar Pipa PVC Type AW Diameter 3" M' 92.40 95,150.00 8,791,860.00
2 5.1.1.T33 Standar Roof Drain Unit 12.00 290,000.00 3,480,000.00
3 Standar Aksessories dan Material Bantu Ls 1.00 1,840,779.00 1,840,779.00
JUMLAH PEKERJAAN INSTALASI AIR HUJAN 14,112,639.00
V.3 PEKERJAAN SUMBER AIR BERSIH DAN PERPOMPAAN
A Pek. Sumber Air Bersih
1 T16 Standar Pek. Sumur Dalam Unit 1.00 95,650,000.00 95,650,000.00
Standar Pengadaan dan pemasangan Pompa Sumur Dalam
Standar Type : Submersible Pump
Standar Daya : 3 HP
Standar Lengkap Dengan Screen, proteksi, instalasi kabel daya/pemipaan (casing), dll
Standar Kabel jenis waterproof, lengkap Panel Kontrol, dll
Standar Pemipaan sampai ke Ground Water Tank (GWT)
Standar Peralatan penunjang, Gate Valve, Check Valve, Meter air, Bak Kontrol, dan accessories lainnya.
Standar Pengeboran dalam sampai mendapatkan Kapasitas air Min. 2liter/Detik (Jernih)
Standar Pekerjaan harus mengikuti/memenuhi Standard DepKes-RI
2 5.1.1.T26 Standar Check Valve dia 40 mm Unit 1.00 700,000.00 700,000.00
3 5.1.1.T18 Standar Gate Valve dia 1 1/2 mm Bh 1.00 2,650,000.00 2,650,000.00
B Pek. Mesin Pompa Transfer
1 5.1.1.T12 Standar Pompa Transfer, Semi Jet Pump Unit 3.00 11,000,000.00 33,000,000.00
Kapasitas 120 Lpm, Head 62 m
Include dengan WLC
2 5.1.1.T22 Standar Gate Valve dia 1" Bh 3.00 265,000.00 795,000.00
3 5.1.1.T26 Standar Check Valve Dia. 1'' Unit 3.00 670,000.00 2,010,000.00
4 5.1.1.T26 Standar Foot Valve Dia. 1 1/4'' Unit 3.00 513,500.00 1,540,500.00
4 5.1.1.T26 Standar Pressure Gauge Bh 3.00 718,600.00 2,155,800.00
5 T1 Standar Panel Control - Pompa Transfer Unit 1.00 5,000,000.00 5,000,000.00
C PEKERJAAN RUMAH POMPA
1 4.4.1.10 Standar Pek. Pasangan Batu Camp. 1 Pc : 5 Ps M2 4.25 142,175.00 604,243.75
2 4.4.2.5 Standar Pek. Plesteran Dinding M2 10.45 61,753.12 645,320.10
3 4.4.2.27 Standar Pek. Acian M2 10.45 38,967.50 407,210.38
4 4.1.1.26 Standar Pek. Kolom (Termasuk Bekisting Dan Pembesian) M 4.00 93,522.00 374,088.00
5 4.1.1.27 Standar Pek. Balok (Termasuk Bekisting Dan Pembesian) M 5.00 113,740.00 568,700.00
6 4.2.1.T81 Standar Pek. Plat Penutup Set 1.00 219,479.47 219,479.47
JUMLAH PEKERJAAN SUMBER AIR BERSIH DAN PERPOMPAAN 146,320,341.70
V.4 INSTALASI PIPA UTAMA AIR BERSIH
1 8.4.1.T9 Standar Pipa transfer dari GWT ke Tandon, Pipa PVC AW Ø 1'' M' 66.00 170,000.00 11,220,000.00
2 8.4.1.T9 Standar Pipa Pembagi dari Tandon ke Tandon, Pipa PVC AW Ø 1/2'' M' 19.80 75,000.00 1,485,000.00
3 8.4.1.T5 Standar Pipa Balancing Air Tandon, Pipa PVC AW Ø 2'' M' 11.00 55,000.00 605,000.00
4 5.1.1.T23 Standar Gate Valve 1/2'' M' 4.00 220,000.00 880,000.00
6 5.1.1.T27 Standar Valve 2'' M' 6.00 750,000.00 4,500,000.00
7 Aksessories dan Material Bantu Ls 1.00 3,444,507.00 3,444,507.00
8 GWT Kap. 25 m³ Ls 1.00 25,800,000.00 25,800,000.00
9 5.1.1.T29 Standar Water Tank Stainless Steel Kapasitas 1500 L + Dudukan, berikut pelampung Unit 4.00 5,500,000.00 22,000,000.00
JUMLAH INSTALASI PIPA UTAMA AIR BERSIH 69,934,507.00
V.5 INSTALASI AIR BERSIH
1 8.4.1.T5 Standar Pipa PVC AW Ø 2'' M' 93.50 56,974.50 5,327,115.75
2 8.4.1.T1 Standar Pipa PVC AW Ø 1/2'' M' 77.00 23,487.75 1,808,556.75
3 5.1.1.T27 Standar Gate Valve 2'' Bh 2.00 760,950.67 1,521,901.33
4 Standar Aksessories dan Material Bantu Ls 1.00 1,427,134.50 1,427,134.50
JUMLAH INSTALASI AIR BERSIH 10,084,708.33
V.6 INSTALASI AIR KOTOR DAN BEKAS
1 8.4.1.T5 Standar Pipa PVC Type AW Diameter 3" M' 97.90 56,974.50 5,577,803.55
2 8.4.1.T6 Standar Pipa PVC Type AW Diameter 4" M' 73.70 155,787.50 11,481,538.75
3 8.4.1.T6 Standar Pipa PVC Type AW Diameter 4" (Outlet Ke Saluran) M' 44.00 155,787.50 6,854,650.00
4 5.1.1.T31 Standar CO 2'' Set 8.00 187,742.50 1,501,940.00
5 5.1.1.T30 Standar CO 4'' Set 6.00 283,167.50 1,699,005.00
BILL OF QUANTITY
PROGRAM : PENINGKATAN SARANA DAN PRASARANA APARATUR POLRI
KEGIATAN : PENGEMBANGAN FASILITAS DAN KONSTRUKSI POLRI
PEKERJAAN : PEMBANGUNAN GEDUNG TAHANAN UMUM DITTAHTI POLDA SULTENG
LOKASI : JALAN SOEKARNO HATTA, PALU, PROVINSI SULAWESI TENGAH
TAHUN ANGGARAN : 2022
RINCIAN
Kode Type
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
ANALISA Pekerjaan
a b c d e f g h=fxg
6 5.1.1.T30 Standar Septictank 20 m³ + Sumur Resapan Unit 3.00 10,375,000.00 31,125,000.00
JUMLAH INSTALASI AIR KOTOR DAN BEKAS 58,239,937.30
V.7 PEKERJAAN SANITAIR
1 5.1.1.3 Standar Kloset Duduk Unit 2.00 3,343,725.00 6,687,450.00
2 5.1.1.T1 Standar Jet Washer Toilet Unit 2.00 297,398.75 594,797.50
3 5.1.1.T4 Standar Wastafel Type Meja Unit 3.00 952,875.00 2,858,625.00
4 5.1.1.18 Standar Floor Drain (Toto/Amstad) Unit 12.00 211,598.75 2,539,185.00
5 5.1.1.6 Standar Closet Jongkok Unit 10.00 502,488.80 5,024,888.00
6 5.1.1.T7 Standar Kran Unit 10.00 143,673.75 1,436,737.50
7 Aksessories dan Material Bantu Ls 1.00 531,148.37 531,148.37
JUMLAH PEKERJAAN SANITAIR 19,672,831.37
JUMLAH PEKERJAAN MEKANIKAL 341,733,964.70
PEKERJAAN ELEKTRKAL
VI.1 PEKERJAAN INSTALASI DAYA DAN ARMATUR PENERANGAN
1 Standar Sambung Daya Listrik PLN 35 KVA berikut SLO + UJL Ls 1.00 61,820,000.00 61,820,000.00
2 T38 Standar Panel Listrik Utama Type Outdoor Set 1.00 20,000,000.00 20,000,000.00
3 T39 Standar Panel PP Pompa Type Outdoor Set 1.00 7,850,000.00 7,850,000.00
4 T39 Standar Panel Listrik Rutan Umum Set 1.00 3,612,400.92 3,612,400.92
5 T11 Standar Kabel Power dari Panel Utama ke KWH PLN, Kabel NYY 4x25mm M' 10.00 370,837.50 3,708,375.00
6 T15 Standar Kabel Power dari Panel Utama ke Panel Rutan Teroris, Kabel NYY 4x2.5mm M' 19.80 52,421.88 1,037,953.13
7 T15 Standar Kabel Power dari Panel Utama ke Panel Rutan Umum, Kabel NYY 4x2.5mm M' 41.80 52,421.88 2,191,234.38
8 T14 Standar Kabel Power dari Panel Utama ke Panel Pompa, Kabel NYY 4x6mm M' 28.60 106,260.00 3,039,036.00
9 T91 Standar Lampu Downlight LED 13 W Bh 22.00 169,262.50 3,723,775.00
10 T92 Standar Lampu Downlight LED 7 W Bh 2.00 158,125.00 316,250.00
11 T86 Standar Lampu TKO LED 2x18 Watt Bh 6.00 387,420.00 2,324,520.00
12 T68 Standar Saklar Tunggal Bh 6.00 77,742.50 466,455.00
13 T69 Standar Saklar Ganda Bh 4.00 77,187.00 308,748.00
14 T75 Standar Stop Kontak Bh 5.00 102,740.00 513,700.00
15 T76 Standar Stop Kontak Pompa + Waterproof Bh 3.00 251,377.50 754,132.50
16 T76 Standar Stop Kontak AC Bh 2.00 112,739.00 225,478.00
17 T30 Standar Instalasi penerangan, NYM 3 x 2,5 mm2 + Pipa Conduit Titik 24.00 337,457.02 8,098,968.56
18 T23a Standar Instalasi stop kontak, Kabel NYM 3 x 2,5 mm2 + Pipa Conduit Titik 8.00 382,144.20 3,057,153.58
19 T29 Standar Instalasi stop kontak AC, Kabel NYM 3 x 2,5 mm2 + Pipa Conduit Titik 2.00 440,027.50 880,055.00
20 Standar Test and Commisioning Ls 1.00 3,500,000.00 3,500,000.00
JUMLAH PEKERJAAN INSTALASI DAYA DAN ARMATUR PENERANGAN 127,428,235.06
VI.2 PEKERJAAN INSTALASI FIRE ALARM
A Pekerjaan Instalasi dan Armature Fire Alarm
1 T130 Standar TB-FA Set 1.00 2,000,000.00 2,000,000.00
2 T126 Standar Smoke Detector Unit 10.00 845,020.00 8,450,200.00
3 T137 Standar Manual Breack Glass Unit 1.00 229,102.50 229,102.50
4 T139 Standar Bell Alarm Unit 1.00 850,000.00 850,000.00
5 T125 Standar Indicator Lamp Unit 1.00 309,650.00 309,650.00
6 T36 Standar Instalasi Fire Alarm, Kabel NYA 2(1x 1,5) mm didalam Pipa Conduit PVC 20mm Titik 13.00 300,238.20 3,903,096.57
JUMLAH PEKERJAAN INSTALASI FIRE ALARM 15,742,049.07
VI.3 PEKERJAAN INSTALASI CCTV
A Instalasi beserta Armatur CCTV
1 T122 Standar Pemasangan Monitor TV LED 32" + Bracket Full Motion Unit 1.00 5,600,000.00 5,600,000.00
2 T124 Standar Pemasangan Fixed Camera Unit 6.00 553,000.00 3,318,000.00
3 T123 Standar Pemasangan Dome Camera Unit 4.00 675,000.00 2,700,000.00
4 T35 Standar Instalasi kabel CCTV, Kabel UTP Cat.6 dalam Pipa Conduit PVC 20mm Unit 10.00 350,000.00 3,500,000.00
5 Standar Test and Commisioning Ls 1.00 472,778.63 472,778.63
JUMLAH PEKERJAAN INSTALASI CCTV 15,590,778.63
JUMLAH PEKERJAAN ELEKTRKAL 158,761,062.76
PEKERJAAN FASILITAS UMUM (FASUM)
PEKERJAAN JALAN DAN LANDSCAPE
I.1 PEKERJAAN JALAN DAN LANDSCAPE
A Pekerjaan Jalan
1 1.5.1.15 Standar Pek. Timbunan Pilihan M3 272.99 123,010.36 33,580,598.88
JUMLAH PEKERJAAN JALAN DAN LANDSCAPE 33,580,598.88
PEKERJAAN SALURAN
II.1 PEKERJAAN SALURAN LINGKUNGAN
A Pekerjaan Saluran
1 T30 Standar Pek. Saluran Keliling Pas Batu Kali M 205.40 620,417.96 127,433,849.06
2 T25 Standar Pek. Kansteen M 426.21 150,726.03 64,240,942.67
B Pekerjaan Plat Penutup Saluran Jalan
1 4.1.1.8 Standar Pek. Beton K 250 M3 2.40 1,058,542.89 2,540,502.94
2 4.1.1.15 Standar Pek. Pembesian KG 823.11 16,100.15 13,252,247.87
3 4.1.1.22a Standar Pek. Bekisting M2 16.00 321,753.21 5,148,051.33
JUMLAH PEKERJAAN SALURAN LINGKUNGAN 212,615,593.87
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pembongkaran 1 m3 Plesteran
Kode AHSP = 1.1.1.13
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1 m3 pondasi siklop. 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
Kode AHSP = 3.1.1.10
A TENAGA
Pekerja C9 OH 3.400 80,000.00 272,000.00
Tukang Batu C18 OH 0.850 125,000.00 106,250.00
Kepala Tukang C39 OH 0.085 150,000.00 12,750.00
Mandor C47 OH 0.170 120,000.00 20,400.00
JUMLAH TENAGA KERJA 411,400.00
B BAHAN
Batu belah 15 cm/20 cm C73 m3 0.480 145,000.00 69,600.00
Semen Portland C363 Kg 194.000 1,300.00 252,200.00
Pasir Beton C97 m3 0.312 100,000.00 31,200.00
Batu Kerikil C74 m3 0.468 400,000.00 187,200.00
Besi Beton (Polos/ulir) C161 Kg 126.000 12,000.00 1,512,000.00
Kawat beton C267 Kg 1.800 29,900.00 53,820.00
JUMLAH HARGA BAHAN 2,106,020.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 2,517,420.00
E Overhead & Profit 10% 251,742.00
F Harga Satuan Pekerjaan (D+E) 2,769,162.00
Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Kode AHSP = 4.1.1.2
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 276.000 1,300.00 358,800.00
Pasir beton (Kg) C98 Kg 828.000 71.43 59,142.86
Koral Beton (Kg) C93 Kg 1012.000 203.70 206,148.15
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 645,591.01
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 826,126.01
E Overhead & Profit 10% 82,612.60
F Harga Satuan Pekerjaan (D+E) 908,738.61
Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Kode AHSP = 4.1.1.3
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 299.000 1,300.00 388,700.00
Pasir beton (Kg) C98 Kg 799.000 71.43 57,071.43
Koral Beton (Kg) C93 Kg 1017.000 203.70 207,166.67
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 674,438.10
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 854,973.10
E Overhead & Profit 10% 85,497.31
F Harga Satuan Pekerjaan (D+E) 940,470.40
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),slump (3-6) cm, w/c = 0,87
Kode AHSP = 4.1.1.4
A TENAGA
Pekerja C9 OH 1.200 80,000.00 96,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.060 120,000.00 7,200.00
JUMLAH TENAGA KERJA 131,200.00
B BAHAN
Semen Portland C363 Kg 230.000 1,300.00 299,000.00
Pasir beton (Kg) C98 Kg 893.000 71.43 63,785.71
Koral Beton (Kg) C93 Kg 1027.000 203.70 209,203.70
Air C120 Ltr 200.000 100.00 20,000.00
JUMLAH HARGA BAHAN 591,989.42
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 723,189.42
E Overhead & Profit 10% 72,318.94
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Kode AHSP = 4.1.1.5
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 326.000 1,300.00 423,800.00
Pasir beton (Kg) C98 Kg 760.000 71.43 54,285.71
Koral Beton (Kg) C93 Kg 1029.000 203.70 209,611.11
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 709,196.83
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 889,731.83
E Overhead & Profit 10% 88,973.18
F Harga Satuan Pekerjaan (D+E) 978,705.01
Membuat 1 m3 beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Kode AHSP = 4.1.1.6
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 352.000 1,300.00 457,600.00
Pasir beton (Kg) C98 Kg 731.000 71.43 52,214.29
Koral Beton (Kg) C93 Kg 1031.000 203.70 210,018.52
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 741,332.80
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 921,867.80
E Overhead & Profit 10% 92,186.78
F Harga Satuan Pekerjaan (D+E) 1,014,054.58
Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,5
Kode AHSP = 4.1.1.7
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 371.000 1,300.00 482,300.00
Pasir beton (Kg) C98 Kg 698.000 71.43 49,857.14
Koral Beton (Kg) C93 Kg 1047.000 203.70 213,277.78
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 766,934.92
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 947,469.92
E Overhead & Profit 10% 94,746.99
F Harga Satuan Pekerjaan (D+E) 1,042,216.91
Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Kode AHSP = 4.1.1.8
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Membuat 1 m3 beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Kode AHSP = 4.1.1.9
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Kode AHSP = 4.1.1.10
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 413.000 1,300.00 536,900.00
Pasir beton (Kg) C98 Kg 681.000 71.43 48,642.86
Koral Beton (Kg) C93 Kg 1021.000 203.70 207,981.48
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 815,024.34
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 995,559.34
E Overhead & Profit 10% 99,555.93
F Harga Satuan Pekerjaan (D+E) 1,095,115.27
Membuat 1 m3 beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Membuat 1 m3 beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Kode AHSP =
A TENAGA
Pekerja C9 OH 2.100 80,000.00 168,000.00
Tukang Batu C18 OH 0.350 125,000.00 43,750.00
Kepala Tukang C39 OH 0.035 150,000.00 5,250.00
Mandor C47 OH 0.105 120,000.00 12,600.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 229,600.00
B BAHAN
Semen Portland C363 Kg 448.000 1,300.00 582,400.00
Pasir pasang C99 Kg 667.000 100,000.00 66,700,000.00
Papan kayu kelas I C94 Kg 1000.000 4,000,000.00 4,000,000,000.00
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN JUMLAH HARGA BAHAN 4,067,303,900.00
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,067,533,500.00
E Overhead & Profit 10% 406,753,350.00
F Harga Satuan Pekerjaan (D+E) 4,474,286,850.00
Pembuatan 1 m2 lahan produksi tebal 8cm beton f’c 14.5 Mpa (K 175) slump (12 ± 2)
Kode AHSP = 4.1.2.1
A TENAGA
Pekerja C9 OH 0.132 80,000.00 10,560.00
Tukang batu C18 OH 0.022 125,000.00 2,750.00
Kepala tukang C39 OH 0.002 150,000.00 300.00
Mandor C47 OH 0.007 120,000.00 840.00
JUMLAH TENAGA KERJA 14,450.00
B BAHAN
Semen Portland C363 Kg 26.080 1,300.00 33,904.00
Pasir beton (Kg) C98 Kg 60.8000 71.43 4,342.86
Koral Beton (Kg) C93 Kg 82.320 203.70 16,768.89
Air C120 Ltr 17.200 100.00 1,720.00
JUMLAH HARGA BAHAN 56,735.75
C PERALATAN
Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14.5 Mpa (K 175) slump (12 ±2) cm
Kode AHSP = 4.1.2.2
A TENAGA
Pekerja C9 OH 0.165 80,000.00 13,200.00
Tukang batu C18 OH 0.028 125,000.00 3,500.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14.5 Mpa (K 175) slump (12 ±2) cm
Kode AHSP = 4.1.2.3
A TENAGA
Pekerja C9 OH 0.198 80,000.00 15,840.00
Tukang batu C18 OH 0.033 125,000.00 4,125.00
Kepala tukang C39 OH 0.003 150,000.00 450.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 21,615.00
B BAHAN
Semen Portland C363 Kg 32.120 1,300.00 41,756.00
Pasir beton (Kg) C98 Kg 91.2000 71.43 6,514.29
Koral Beton (Kg) C93 Kg 123.480 203.70 25,153.33
Air C120 Ltr 25.800 100.00 2,580.00
JUMLAH HARGA BAHAN 76,003.62
C PERALATAN
Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14.5 Mpa (K 175) slump (12 ±2) cm
Kode AHSP = 4.1.2.4
A TENAGA
Pekerja C9 OH 0.248 80,000.00 19,840.00
Tukang batu C18 OH 0.041 125,000.00 5,125.00
Kepala tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 27,125.00
B BAHAN
Semen Portland C363 Kg 48.900 1,300.00 63,570.00
Pasir beton (Kg) C98 Kg 114.0000 71.43 8,142.86
Koral Beton (Kg) C93 Kg 154.350 203.70 31,441.67
Air C120 Ltr 32.250 100.00 3,225.00
JUMLAH HARGA BAHAN 106,379.52
C PERALATAN
Mendirikan 1 buah komponen plat pracetak beserta indeks kenaikan lantai ereksi plat hingga 24 lantai
Kode AHSP = 4.1.2.14
A TENAGA
Pekerja C9 OH 0.067 80,000.00 5,360.00
Tukang batu C18 OH 0.067 125,000.00 8,375.00
Tukang erection C29 OH 0.134 125,000.00 16,750.00
Operator crane C33 OH 0.067 200,000.00 13,400.00
Operator Crane (Pembantu) C34 OH 0.067 75,000.00 5,025.00
Kepala Tukang C39 OH 0.067 150,000.00 10,050.00
Mandor C47 OH 0.067 120,000.00 8,040.00
JUMLAH TENAGA KERJA 48,910.00
B BAHAN
Solar C389 ltr 6.676 16,200.00 108,151.20
-
-
JUMLAH HARGA BAHAN 108,151.20
C PERALATAN
Sewa Crane C1585 UH 0.067 1,608,257.14 107,753.23
Sewa Skafolding 1 Set (Hari) C1595 UH 1.100 5,050.00 5,555.00
JUMLAH HARGA ALAT 113,308.23
D Jumlah (A+B+C) 270,369.43
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Mendirikan 1 buah komponen balok pracetak beserta indeks kenaikan lantai ereksi balok hingga 24 lantai
Kode AHSP = 4.1.2.15
A TENAGA
Pekerja C9 OH 0.061 80,000.00 4,880.00
Tukang batu C18 OH 0.061 125,000.00 7,625.00
Tukang erection C29 OH 0.122 125,000.00 15,250.00
Operator crane C33 OH 0.061 200,000.00 12,200.00
Operator Crane (Pembantu) C34 OH 0.061 75,000.00 4,575.00
Kepala Tukang C39 OH 0.061 150,000.00 9,150.00
Mandor C47 OH 0.061 120,000.00 7,320.00
JUMLAH TENAGA KERJA 61,000.00
B BAHAN
Solar C389 ltr 6.110 16,200.00 98,982.00
-
-
JUMLAH HARGA BAHAN 98,982.00
C PERALATAN
Sewa Crane C1585 UH 0.061 1,608,257.14 98,103.69
Sewa Skafolding 1 Set (Hari) C1595 UH 1.100 5,050.00 5,555.00
JUMLAH HARGA ALAT 103,658.69
D Jumlah (A+B+C) 263,640.69
E Overhead & Profit 10% 26,364.07
F Harga Satuan Pekerjaan (D+E) 290,004.75
Mendirikan 1 buah komponen kolom pracetak beserta indeks kenaikan lantai ereksi kolom hingga 24 lantai
Kode AHSP = 4.1.2.16
A TENAGA
Pekerja C9 OH 0.083 80,000.00 6,640.00
Tukang batu C18 OH 0.083 125,000.00 10,375.00
Tukang erection C29 OH 0.166 125,000.00 20,750.00
Operator crane C33 OH 0.083 200,000.00 16,600.00
Operator Crane (Pembantu) C34 OH 0.083 75,000.00 6,225.00
Kepala Tukang C39 OH 0.083 150,000.00 12,450.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 83,000.00
B BAHAN
Solar C389 ltr 8.277 16,200.00 134,087.40
-
-
JUMLAH HARGA BAHAN 134,087.40
C PERALATAN
Sewa Crane C1585 UH 0.083 1,608,257.14 133,485.34
Sewa pipe support C1592 UH 2.200 75,000.00 165,000.00
JUMLAH HARGA ALAT 298,485.34
D Jumlah (A+B+C) 515,572.74
E Overhead & Profit 10% 51,557.27
F Harga Satuan Pekerjaan (D+E) 567,130.02
Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap. rangka baja siku
Kode AHSP = 4.2.1.4
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Tukang Las Konstruksi C28 OH 1.050 125,000.00 131,250.00
Kepala Tukang C39 OH 0.105 150,000.00 15,750.00
Mandor C47 OH 0.052 120,000.00 6,240.00
JUMLAH TENAGA KERJA JUMLAH TENAGA KERJA 237,240.00
B BAHAN
Besi Siku L 30.30.3 C179 Kg 15.000 1.00 15.00
Besi Plat C183 Kg 32.800 28,000.00 918,400.00
Kawat Las C272 Kg 0.050 3,250.00 162.50
Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm. modul 60 x 120 cm. dinding partisi
Kode AHSP = 4.2.1.20
A TENAGA
Pekerja C9 OH 0.250 80,000.00 20,000.00
Tukang Besi C20 OH 0.250 125,000.00 31,250.00
Kepala Tukang C39 OH 0.025 150,000.00 3,750.00
Mandor C47 OH 0.013 120,000.00 1,560.00
JUMLAH TENAGA KERJA 56,560.00
B BAHAN
Besi Hollow 4x4 cm C171 m1 3.500 17,000.00 59,500.00
Assesoris perkuatan, las dll C131 Ls 3.500 12,000.00 42,000.00
JUMLAH HARGA BAHAN 101,500.00
C PERALATAN
Pemasangan 1 m2 Arap pelana rangka atap baja ringan (canai dingin) profil C75
Kode AHSP = 4.2.1.22
A TENAGA
Pekerja C9 OH 0.734 80,000.00 58,720.00
Tukang Besi C20 OH 0.734 125,000.00 91,750.00
Kepala Tukang C39 OH 0.073 150,000.00 10,950.00
Mandor C47 OH 0.037 120,000.00 4,440.00
JUMLAH TENAGA KERJA 165,860.00
B BAHAN
Smartruss C 75.75 C654 btg 0.873 21,000.00 18,333.00
Assesoris perkuatan, las dll C131 Ls 0.873 12,000.00 10,476.00
Pemasangan 1 m2 atap jurai / limasan rangka atap baja ringan (canai dingin) profil C75
Kode AHSP = 4.2.1.23
A TENAGA
Pekerja C9 OH 0.760 80,000.00 60,832.00
Tukang Besi C20 OH 0.760 125,000.00 95,050.00
Kepala Tukang C39 OH 0.076 150,000.00 11,400.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1 m2 Partisi
Kode AHSP = 4.2.1.T6
A TENAGA
Pekerja Plafond C13 OH 0.300 80,000.00 24,000.00
Tukang Plafond C25 OH 0.600 125,000.00 75,000.00
Mandor Plafond C42 OH 0.375 120,000.00 45,000.00
JUMLAH TENAGA KERJA 144,000.00
B BAHAN
Smartruss C 75.65 C655 m’ 4.180 19,500.00 81,510.00
Dynabolt dia- 10 x 50 mm C509 Bh 6.000 3,500.00 21,000.00
Perban Gypsum C336 Roll 0.200 10,000.00 2,000.00
Tepung Gypsum C403 kg 0.150 4,000.00 600.00
Gypsum board 120x240 cm, tebal 9mm C232 Lembar 0.728 65,000.00 47,320.00
Screw Bremick C649 Bh 6.000 120.00 720.00
Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 1) Kaca Abu-abu
Kode AHSP = 4.2.1.T52
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 19,795,295.00 19,795,295.00
Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 2) Kaca Abu-Abu
Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 2) Kaca Abu-Abu
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 12,906,000.00 12,906,000.00
Pemasangan 1 Set Curtain Wall Balai Bahasa (CW Type 3) Kaca Abu-Abu
Pemasangan 1 Set Ventilasi Balai Bahasa (V1)
A TENAGA
Perakitan, Pemasangan Dan Perapian Ls 1.000 6,443,200.00 6,443,200.00
Pemasangan 1m dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :2PP
Kode AHSP = 4.4.1.1
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 43.5 1,300.00 56,550.00
Pasir Pasang C99 m3 0.08 100,000.00 8,000.00
JUMLAH HARGA BAHAN 204,550.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP
Kode AHSP = 4.4.1.2
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 32.95 1,300.00 42,835.00
Pasir Pasang C99 m3 0.091 100,000.00 9,100.00
JUMLAH HARGA BAHAN 191,935.00
C PERALATAN
Pemasangan 1m dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :4PP
Kode AHSP = 4.4.1.3
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 26.55 1,300.00 34,515.00
Pasir Pasang C99 m3 0.093 100,000.00 9,300.00
JUMLAH HARGA BAHAN 183,815.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP
Kode AHSP = 4.4.1.4
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 Kg 140.000 1,000.00 140,000.00
Semen Portland C363 Kg 22.200 1,300.00 28,860.00
Pasir Pasang C99 Kg 0.102 100,000.00 10,200.00
JUMLAH HARGA BAHAN 179,060.00
C PERALATAN
Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1SP :6PP
Kode AHSP = 4.4.1.5
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP :3KP : 10PP
Kode AHSP = 4.4.1.6
A TENAGA
Pekerja C9 OH 0.600 80,000.00 48,000.00
Tukang Batu C18 OH 0.200 125,000.00 25,000.00
Kepala Tukang C39 OH 0.020 150,000.00 3,000.00
Mandor C47 OH 0.030 120,000.00 3,600.00
JUMLAH TENAGA KERJA 79,600.00
B BAHAN
Bata merah C142 m3 140 1,000.00 140,000.00
Semen Portland C363 Kg 10.08 1,300.00 13,104.00
Kapur Padam C262 m3 0.0275 200,000.00 5,500.00
Pasir Pasang C99 m3 0.0925 100,000.00 9,250.00
JUMLAH HARGA BAHAN 167,854.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :2PP
Kode AHSP = 4.4.1.7
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 18.95 1,300.00 24,635.00
Pasir Pasang C99 m3 0.038 100,000.00 3,800.00
JUMLAH HARGA BAHAN 98,435.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :3PP
Kode AHSP = 4.4.1.8
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
Kode AHSP = 4.4.1.9
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 11.5 1,300.00 14,950.00
Pasir Pasang C99 m3 0.043 100,000.00 4,300.00
JUMLAH HARGA BAHAN 89,250.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP:5PP
Kode AHSP = 4.4.1.10
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 11.5 1,300.00 14,950.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 89,450.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :6PP
Kode AHSP = 4.4.1.11
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 8.32 1,300.00 10,816.00
Pasir Pasang C99 m3 0.049 100,000.00 4,900.00
JUMLAH HARGA BAHAN 85,716.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP:8PP
Kode AHSP = 4.4.1.12
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 6.5 1,300.00 8,450.00
Pasir Pasang C99 m3 0.05 100,000.00 5,000.00
JUMLAH HARGA BAHAN 83,450.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :3KP :10PP
Kode AHSP = 4.4.1.13
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 4.5 1,300.00 5,850.00
Kapur Padam C262 m3 0.015 200,000.00 3,000.00
Pasir Pasang C99 m3 0.05 100,000.00 5,000.00
JUMLAH HARGA BAHAN 83,850.00
C PERALATAN
Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SM :1KP :1PP
Kode AHSP = 4.4.1.14
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM :1KP :2PP
Kode AHSP = 4.4.1.15
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Merah C366 Kg 0.014 20,700.00 289.80
Kapur Padam C262 m3 0.014 200,000.00 2,800.00
Pasir Pasang C99 m3 0.028 100,000.00 2,800.00
JUMLAH HARGA BAHAN 75,889.80
C PERALATAN
Pemasangan 1 m2 acian
Kode AHSP = 4.4.2.27
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1m2 lantai keramik ukuran 30 s.d < <40 cm untuk variasi/border
Kode AHSP = 4.4.3.37
A TENAGA
Pekerja C9 OH 1.050 80,000.00 84,000.00
Tukang Batu C18 OH 0.525 125,000.00 65,625.00
Kepala tukang C39 OH 0.053 150,000.00 7,950.00
Mandor C47 OH 0.053 120,000.00 6,360.00
JUMLAH TENAGA KERJA 163,935.00
B BAHAN
Keramik 33x33 cm C471 Bh 33.000 8,500.00 280,500.00
Semen Portland C363 Kg 9.800 1,300.00 12,740.00
Pasir pasang C99 M3 0.045 100,000.00 4,500.00
Semen warna C365 Kg 4.370 20,700.00 90,459.00
JUMLAH HARGA BAHAN 388,199.00
C PERALATAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm
Kode AHSP = 4.5.1.5
A TENAGA
Pekerja C9 OH 0.1 80,000.00 8,000.00
Tukang kayu C19 OH 0.1 125,000.00 12,500.00
Kepala tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.005 120,000.00 600.00
JUMLAH TENAGA KERJA 22,600.00
B BAHAN
Tripleks 3 mm C410 Lembar 0.375 63,701.00 23,887.88
Paku tripleks C322 kg 0.03 22,100.00 663.00
JUMLAH HARGA BAHAN 24,550.88
C PERALATAN
Pemasangan 1 Bh Manhole
Kode AHSP = 4.5.1.T3
A TENAGA
Pekerja plafond C13 OH 0.05 80,000.00 4,000.00
Tukang plafond C25 OH 0.05 125,000.00 6,250.00
Mandor plafond C42 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 11,210.00
B BAHAN
Allumunium Siku C490 m’ 1.05 7,500.00 7,875.00
Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Kode AHSP = 4.6.1.1
A TENAGA
Pekerja C9 OH 7.000 80,000.00 560,000.00
Tukang Kayu C19 OH 21.000 125,000.00 2,625,000.00
Kepala Tukang C39 OH 2.100 150,000.00 315,000.00
Mandor C47 OH 0.350 120,000.00 42,000.00
JUMLAH TENAGA KERJA 3,542,000.00
B BAHAN
Balok Kayu Kelas I C66 M3 1.100 4,000,000.00 4,400,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 1.250 21,000.00 26,250.00
Lem kayu C292 Kg 1.000 32,500.00 32,500.00
Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Kode AHSP = 4.6.1.2
A TENAGA
Pekerja C9 OH 6.000 80,000.00 480,000.00
Tukang Kayu C19 OH 18.000 125,000.00 2,250,000.00
Kepala Tukang C39 OH 1.800 150,000.00 270,000.00
Mandor C47 OH 0.300 120,000.00 36,000.00
JUMLAH TENAGA KERJA 3,036,000.00
B BAHAN
Balok Kayu Kelas II C67 M3 1.200 2,250,000.00 2,700,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 1.250 21,000.00 26,250.00
Lem kayu C292 Kg 1.000 32,500.00 32,500.00
Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
Kode AHSP = 4.6.1.6
A TENAGA
Pekerja C9 OH 0.800 80,000.00 64,000.00
Tukang Kayu C19 OH 2.400 125,000.00 300,000.00
Kepala Tukang C39 OH 0.240 150,000.00 36,000.00
Mandor C47 OH 0.040 120,000.00 4,800.00
JUMLAH TENAGA KERJA 404,800.00
B BAHAN
Papan kayu kelas I C94 M3 0.024 4,000,000.00 96,000.00
Lem kayu C292 Kg 0.300 32,500.00 9,750.00
Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
Kode AHSP = 4.6.1.7
A TENAGA
Pekerja C9 OH 1.000 80,000.00 80,000.00
Tukang Kayu C19 OH 3.000 125,000.00 375,000.00
Kepala Tukang C39 OH 0.300 150,000.00 45,000.00
Mandor C47 OH 0.050 120,000.00 6,000.00
JUMLAH TENAGA KERJA 506,000.00
B BAHAN
Papan kayu kelas I C94 M3 0.064 4,000,000.00 256,000.00
Lem kayu C292 Kg 0.500 32,500.00 16,250.00
Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
Kode AHSP = 4.6.1.8
A TENAGA
Pekerja C9 OH 0.700 80,000.00 56,000.00
Tukang Kayu C19 OH 2.100 125,000.00 262,500.00
Kepala Tukang C39 OH 0.210 150,000.00 31,500.00
Mandor C47 OH 0.035 120,000.00 4,200.00
JUMLAH TENAGA KERJA 354,200.00
B BAHAN
Papan kayu kelas II C95 m3 0.025 2,100,000.00 52,500.00
Paku biasa 3/8” – 1” (1-2.5 cm) C433 Kg 0.030 24,000.00 720.00
Lem kayu C292 Kg 0.500 32,500.00 16,250.00
Plywood tebal 4 mm (90 x 220cm) C436 Lembar 1.000 84,000.00 84,000.00
Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
Kode AHSP = 4.6.1.19
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Kayu C19 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.030 150,000.00 4,500.00
Mandor C47 OH 0.075 120,000.00 9,000.00
JUMLAH TENAGA KERJA 63,000.00
B BAHAN
Kayu Kaso 5/7 Kelas II C83 m3 0.015 2,100,000.00 32,340.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.200 21,000.00 4,200.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Kode AHSP = 4.6.1.20
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Kayu C19 OH 0.300 125,000.00 37,500.00
Kepala Tukang C39 OH 0.030 150,000.00 4,500.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 59,200.00
B BAHAN
Kayu Kaso 5/7 Kelas II C83 m3 0.016 2,100,000.00 34,230.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.250 21,000.00 5,250.00
Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III
Kode AHSP = 4.6.1.23
A TENAGA
Pekerja C9 OH 0.150 80,000.00 12,000.00
Tukang Kayu C19 OH 0.450 125,000.00 56,250.00
Kepala Tukang C39 OH 0.045 150,000.00 6,750.00
Mandor C47 OH 0.008 120,000.00 960.00
JUMLAH TENAGA KERJA 75,960.00
B BAHAN
Balok Kayu Kelas II C67 m3 0.028 2,250,000.00 63,000.00
Paku biasa 2” – 5” (5-10 cm) C317 Kg 0.150 21,000.00 3,150.00
1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Kode AHSP = 4.7.1.4
A TENAGA
Pekerja C9 OH 0.07 80,000.00 5,600.00
Tukang cat C27 OH 0.009 125,000.00 1,125.00
Kepala tukang C39 OH 0.006 150,000.00 900.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 7,985.00
B BAHAN
Cat Meni C209 Kg 0.2 46,800.00 9,360.00
Plamir C339 Kg 0.15 14,200.00 2,130.00
Cat dasar C205 Kg 0.17 22,500.00 3,825.00
Cat penutup C213 Kg 0.26 30,000.00 7,800.00
Kuas 2,5 " C291 Bh 0.01 19,500.00 195.00
Thinner C405 Kg 0.03 51,300.00 1,539.00
Amplas C124 Lbr 0.2 6,900.00 1,380.00
JUMLAH HARGA BAHAN 26,229.00
C PERALATAN
Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
Kode AHSP = 4.7.1.5
A TENAGA
Pekerja C9 OH 0.07 80,000.00 5,600.00
Tukang Kayu C19 OH 0.105 125,000.00 13,125.00
Kepala tukang C39 OH 0.004 150,000.00 600.00
Mandor C47 OH 0.003 120,000.00 360.00
JUMLAH TENAGA KERJA 19,685.00
B BAHAN
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Kode AHSP = 4.7.1.10
A TENAGA
Pekerja C9 OH 0.02 80,000.00 1,600.00
Tukang cat C27 OH 0.063 125,000.00 7,875.00
Kepala tukang C39 OH 0.0063 150,000.00 945.00
Mandor C47 OH 0.0025 120,000.00 300.00
JUMLAH TENAGA KERJA 10,720.00
B BAHAN
Plamir C339 Kg 0.1 14,200.00 1,420.00
Cat dasar C205 Kg 0.1 22,500.00 2,250.00
Cat penutup C213 Kg 0.26 30,000.00 7,800.00
JUMLAH HARGA BAHAN 11,470.00
C PERALATAN
Pengecatan 1 m2 Permukaan Baja Galvanis Secara Semprot Sistem 3 Lapis cat terakhir
Kode AHSP = 4.7.1.22
A TENAGA
Pekerja C9 OH 0.04 80,000.00 3,200.00
Tukang cat C27 OH 0.7 125,000.00 87,500.00
Kepala tukang C39 OH 0.07 150,000.00 10,500.00
Mandor C47 OH 0.02 120,000.00 2,400.00
JUMLAH TENAGA KERJA 103,600.00
B BAHAN
Cat dasar C205 Kg 0.3 22,500.00 6,750.00
Thinner C405 Lbr 0.01 51,300.00 513.00
JUMLAH HARGA BAHAN 7,263.00
C PERALATAN
Pengetesan 1 m pipa Ø 50 mm
Kode AHSP = 8.4.5.1
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.002 100.00 0.20
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 0.26
C PERALATAN
Pengetesan 1 m pipa Ø 75 mm
Kode AHSP = 8.4.5.2
A TENAGA
Pekerja C9 OH 0.008 80,000.00 640.00
Mandor C47 OH 0.0008 120,000.00 96.00
JUMLAH TENAGA KERJA 736.00
B BAHAN
Air C120 m3 0.004 100.00 0.40
Bahan bakar C475 liter 0.06 1.00 0.06
Oli C474 liter 0.002 1.00 0.00
JUMLAH HARGA BAHAN 0.46
C PERALATAN
Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Kode AHSP = 4.1.1.8
A TENAGA
Pekerja C9 OH 1.650 80,000.00 132,000.00
Tukang Batu C18 OH 0.275 125,000.00 34,375.00
Kepala Tukang C39 OH 0.028 150,000.00 4,200.00
Mandor C47 OH 0.083 120,000.00 9,960.00
JUMLAH TENAGA KERJA 180,535.00
B BAHAN
Semen Portland C363 Kg 384.000 1,300.00 499,200.00
Pasir beton (Kg) C98 Kg 692.000 71.43 49,428.57
Koral Beton (Kg) C93 Kg 1039.000 203.70 211,648.15
Air C120 Ltr 215.000 100.00 21,500.00
JUMLAH HARGA BAHAN 781,776.72
C PERALATAN - - -
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 962,311.72
E Overhead & Profit 10% 96,231.17
F Harga Satuan Pekerjaan (D+E) 1,058,542.89
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP:5PP
Kode AHSP = 4.4.1.10
A TENAGA
Pekerja C9 OH 0.3 80,000.00 24,000.00
Tukang Batu C18 OH 0.1 125,000.00 12,500.00
Kepala Tukang C39 OH 0.01 150,000.00 1,500.00
Mandor C47 OH 0.015 120,000.00 1,800.00
JUMLAH TENAGA KERJA 39,800.00
B BAHAN
Bata merah C142 m3 70 1,000.00 70,000.00
Semen Portland C363 Kg 11.5 1,300.00 14,950.00
Pasir Pasang C99 m3 0.045 100,000.00 4,500.00
JUMLAH HARGA BAHAN 89,450.00
C PERALATAN
Pemasangan 1 m2 acian
Kode AHSP = 4.4.2.27
A TENAGA
Pekerja C9 OH 0.200 80,000.00 16,000.00
Tukang Batu C18 OH 0.100 125,000.00 12,500.00
Kepala Tukang C39 OH 0.010 150,000.00 1,500.00
Mandor C47 OH 0.010 120,000.00 1,200.00
JUMLAH TENAGA KERJA 31,200.00
B BAHAN
Semen Portland C363 Kg 3.250 1,300.00 4,225.00