Laporan Trial STC 01 Agustus 2022
Laporan Trial STC 01 Agustus 2022
TANGGAL : 01 AGS 2022 REKAPITULASI STOK MATERIAL DAN HASIL PRODUKSI HARIAN STONE CRUSHER (STC)
LOKASI PRODUKSI : STC MALUK
START PRODUKSI I JAM : 10.00 PENGGUNAAN SOLAR UNTUK PERALATAN YANG DIPAKAI PRODUKSI MENYETUJUI :
STOP PRODUKSI I JAM : 12.00 START : 15.00 VOLUME SOLAR : 210 LITER HM PENGISIAN : JAM : PELAKSANA PRODUKSI KA. PLANT
GENSET
ISTIRAHAT JAM : 12.00-13.00 FINISH : 16.30 WAKTU KERJA : 4 JAM 30 MNT PEMAKAIAN SOLAR : 100 LITER RING SOLAR : L/M3
START PRODUKSI II JAM : 14.30 HM AWAL : 145.5 VOLUME SOLAR : 204 LITER HM PENGISIAN : 143.2 JAM : (……………………………………..)
WHEEL LOADER
STOP PRODUKSI II JAM : 17.00 HM AKHIR : 145.5 WAKTU KERJA : 3 JAM PEMAKAIAN SOLAR : 0 LITER RING SOLAR : L/M3 DIREKAP PELAKSANA LOGISTIK
TOTAL JAM PRODUKSI : 4 JAM 30 MENIT HM AWAL : 318.0 VOLUME SOLAR : 100 LITER HM PENGISIAN : JAM : PRODUKSI PLANT
EXCAVATOR 01
TOTAL PEMAKAIAN SOLAR HM AKHIR : 324.5 WAKTU KERJA : 6 JAM PEMAKAIAN SOLAR : 76.8 LITER RING SOLAR : 0.1 L/M3
: 218.3 LITER
UNTUK PRODUKSI STC HM AWAL : 131.2 VOLUME SOLAR : 100.1 LITER HM PENGISIAN : JAM : (……………………………………..)
EXCAVATOR 02
TOTAL HASIL HOULING DT HM AKHIR : 136.0 WAKTU KERJA : 5 JAM PEMAKAIAN SOLAR : 41.5 LITER RING SOLAR : L/M3 DI VERIFIKASI :
: 112.5 M3
DARI QUARY KE STC TYPE : KM AWAL : VOLUME KEPALA SUPPORTING MALUK
1 : LITER KM PENGISIAN : JAM :
STOCK AWAL : KM AKHIR
MATERIAL
W : 8644 DY : SOLAR
RAW
TOTAL PRODUKSI :
KETERANGAN PRODUKSI :
Sabtu, 30 Juli 2022 Trial STC yang ke Tiga