REKAPITULASI

Rencana Anggaran Biaya

No. Jenis Barang/Jasa Jumlah Harga (Rp.) Total Harga (Rp.)

I. BIAYA LANGSUNG PERSONIL


A. Biaya Tenaga Ahli 286,670,000.00

B. Biaya Tenaga Pendukung 47,960,000.00

Total Harga Biaya Langsung Personil 334,630,000.00

II. BIAYA LANGSUNG NON PERSONIL

A.Biaya Survey 12,000,000.00

B. Biaya Rapat 173,000,000.00

C. Biaya Laporan 12,625,000.00

Total Harga Biaya Langsung Non Personil 197,625,000.00


TOTAL HARGA 532,255,000.00
PPN 10% 53,225,500.00
GRAND TOTAL 585,480,500.00

Jogjakarta, 10 Juli 2020


Penawar,

Direktur
No Jenis barang/jasa Satuan Volume Harga satuan (Rp.) Jumlah harga (Rp.)
I. BIAYA PERSONIL
A. BIAYA TENAGA AHLI
1) Ahli Lingkungan Orang/ Bulan 5 22,018,000.00 110,090,000.00
2) Ahli Hidrologi Orang/ Bulan 3 19,620,000.00 58,860,000.00
3) Ahli Pertanian Orang/ Bulan 3 19,620,000.00 58,860,000.00
4) Ahli Sosial Ekonomi Orang/ Bulan 3 19,620,000.00 58,860,000.00
Jumlah Harga I.A 286,670,000.00

B. BIAYA TENAGA PENUNJANG


1) Jasa Survey Pemetaan Orang/ Bulan 6 4,360,000.00 26,160,000.00
2) Tenaga Administrasi dan Operator
Orang/ Bulan 5 4,360,000.00 21,800,000.00
Komputer
Jumlah Harga I.B 47,960,000.00
No Jenis barang/jasa Satuan Volume Harga satuan (Rp.) Jumlah harga (Rp.)
II. BIAYA NON PERSONIL
A. BIAYA SURVEY

1) Biaya Pengambilan Sampel dan Labor Udara Ambien titik 2 2,000,000.00 4,000,000.00

2) Biaya Pengambilan Sampel Kebisingan titik 2 1,000,000.00 2,000,000.00


3) Biaya Pengambilan Sampel dan Labor Tanah titik 2 1,500,000.00 3,000,000.00
4) Biaya Pengambilan Sampel dan Labor Air titik 2 1,500,000.00 3,000,000.00
Jumlah Harga II.A 12,000,000.00
B. BIAYA RAPAT
1) Biaya Rapat Penilaian tim teknis AMDAL Pusat Kali 1 60,000,000.00 60,000,000.00
2) Biaya Rapat Penilaian tim Komisi AMDAL Pusat Kali 1 35,000,000.00 35,000,000.00
3) Sewa Ruang Rapat Penilaian Dokumen Kali 2 3,000,000.00 6,000,000.00
4) Biaya Transport Akomodasi dan Uang Harian
Orang 4 6,500,000.00 26,000,000.00
Masyarakat ke Jakarta

5) Biaya Transportasi, Akomodasi dan Uang Harian


OK 4 6,500,000.00 26,000,000.00
dalam rangka Assistensi ke Jakarta
6) Biaya Rapat Draft ANDAL RKL RPL Ls 1 10,000,000.00 10,000,000.00
7) Biaya Rapat Finalisasi Draft ANDAL RKL RPL Ls 1 10,000,000.00 10,000,000.00
Jumlah Harga II.B 173,000,000.00
C. BIAYA LAPORAN
1) Laporan Pendahuluan Buku 5 125,000.00 625,000.00
2) Laporan ANDAL RKL RPL Buku 50 150,000.00 7,500,000.00
3) Biaya Dokumentasi Ls 1 3,000,000.00 3,000,000.00
4) Hardisk Eksternal Ls 1 1,500,000.00 1,500,000.00
Jumlah Harga II.D 12,625,000.00
Jumlah Harga II.(A + B + C) 197,625,000.00
DAFTAR ANALISA HARGA SATUAN DAN TENAGA

Personil : Ahli Teknik Lingkungan (S1)


Pengalaman : 5 Tahun

KOEFISIEN BILLING RATE HARGA SATUAN


No. KOMPONEN BLP KOEFISIEN NASIONAL
DIAMBIL (Rp.) (Rp.)
1 2 3 4 5 6 = (4*5)
a Gaji Dasar (GD) 1,00 x GD 1.00 10,100,000 10,100,000
b Beban Biaya Sosial (BBS) (0,3 - 0,4 ) x GD 0.30 10,100,000 3,030,000
c Beban Biaya Umum (BBU) (0,5 - 1,3 ) x GD 0.50 10,100,000 5,050,000
d Tunjangan Penugasan (TP) (0,1- 0,3) x GD 0.20 10,100,000 2,020,000
e Keuntungan 0,1 x (GD + BBS + BBU) 0.10 1,818,000
f Jumlah Total 22,018,000

Personil : Ahli Hidrologi (S1 Teknik Sipil/Lingkungan/Sumber Daya Air)


Pengalaman : 3 Tahun

KOEFISIEN BILLING RATE HARGA SATUAN


No. KOMPONEN BLP KOEFISIEN NASIONAL
DIAMBIL (Rp.) (Rp.)
1 2 3 4 5 6 = (4*5)
a Gaji Dasar (GD) 1,00 x GD 1.00 9,000,000 9,000,000
b Beban Biaya Sosial (BBS) (0,3 - 0,4 ) x GD 0.30 9,000,000 2,700,000
c Beban Biaya Umum (BBU) (0,5 - 1,3 ) x GD 0.50 9,000,000 4,500,000
d Tunjangan Penugasan (TP) (0,1- 0,3) x GD 0.20 9,000,000 1,800,000
e Keuntungan 0,1 x (GD + BBS + BBU) 0.10 1,620,000
f Jumlah Total 19,620,000

Personil : Ahli Pertanian (S1 Pertanian)


Pengalaman : 3 Tahun

KOEFISIEN BILLING RATE HARGA SATUAN


No. KOMPONEN BLP KOEFISIEN NASIONAL
DIAMBIL (Rp.) (Rp.)

1 2 3 4 5 6 = (4*5)
a Gaji Dasar (GD) 1,00 x GD 1.00 9,000,000 9,000,000
b Beban Biaya Sosial (BBS) (0,3 - 0,4 ) x GD 0.30 9,000,000 2,700,000
c Beban Biaya Umum (BBU) (0,5 - 1,3 ) x GD 0.50 9,000,000 4,500,000
d Tunjangan Penugasan (TP) (0,1- 0,3) x GD 0.20 9,000,000 1,800,000
e Keuntungan 0,1 x (GD + BBS + BBU) 0.10 1,620,000
f Jumlah Total 19,620,000
Personil : Ahli Sosial Ekonomi (S1 Sosiologi/Antropologi/Ekonomi/Ilmu Sosial
Pengalaman : 3 Tahun

KOEFISIEN BILLING RATE HARGA SATUAN


No. KOMPONEN BLP KOEFISIEN NASIONAL
DIAMBIL (Rp.) (Rp.)
1 2 3 4 5 6 = (4*5)
a Gaji Dasar (GD) 1,00 x GD 1.00 9,000,000 9,000,000
b Beban Biaya Sosial (BBS) (0,3 - 0,4 ) x GD 0.30 9,000,000 2,700,000
c Beban Biaya Umum (BBU) (0,5 - 1,3 ) x GD 0.50 9,000,000 4,500,000
d Tunjangan Penugasan (TP) (0,1- 0,3) x GD 0.20 9,000,000 1,800,000
e Keuntungan 0,1 x (GD + BBS + BBU) 0.10 1,620,000
f Jumlah Total 19,620,000

Personil : Survey dan Pemetaan (D3 Sipil/S1 Sipil)


Pengalaman : 3 Tahun/2 Tahun

KOEFISIEN BILLING RATE HARGA SATUAN


No. KOMPONEN BLP KOEFISIEN NASIONAL
DIAMBIL (Rp.) (Rp.)

1 2 3 4 5 6 = (4*5)
a Gaji Dasar (GD) 1,00 x GD 1.00 2,000,000 2,000,000
b Beban Biaya Sosial (BBS) (0,3 - 0,4 ) x GD 0.30 2,000,000 600,000
c Beban Biaya Umum (BBU) (0,5 - 1,3 ) x GD 0.50 2,000,000 1,000,000
d Tunjangan Penugasan (TP) (0,1- 0,3) x GD 0.20 2,000,000 400,000
e Keuntungan 0,1 x (GD + BBS + BBU) 0.10 360,000
f Jumlah Total 4,360,000

Personil : Administrasi dan Operator Komputer


Pengalaman :-

KOEFISIEN BILLING RATE HARGA SATUAN


No. KOMPONEN BLP KOEFISIEN NASIONAL
DIAMBIL (Rp.) (Rp.)

1 2 3 4 5 6 = (4*5)
a Gaji Dasar (GD) 1,00 x GD 1.00 2,000,000 2,000,000
b Beban Biaya Sosial (BBS) (0,3 - 0,4 ) x GD 0.30 2,000,000 600,000
c Beban Biaya Umum (BBU) (0,5 - 1,3 ) x GD 0.50 2,000,000 1,000,000
d Tunjangan Penugasan (TP) (0,1- 0,3) x GD 0.20 2,000,000 400,000
e Keuntungan 0,1 x (GD + BBS + BBU) 0.10 360,000
f Jumlah Total 4,360,000