M35_Konstruksi Lainnya

ID Task Name Duration Start Finish Predecessors


Dec '21 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22
12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02
1 Jasa Perencanaan dan Pembangunan Jalan at 255 days Mon Wed 99%
Grade serta Pematangan Lahan Kawasan Bank 20/12/21 31/08/22
Indonesia di Kabupaten Karawang Menggunakan
Metode Design and Build
2 Mulai 0 days Mon 20/12/21Mon 20/12/21 20/12
3 PERSIAPAN 255 days Mon 20/12/21 Wed 31/08/22 100%
4 Mobilisasi 255 days Mon 20/12/21Wed 31/08/222SS 100%
5 Manajemen dan Keselamatan Lalu Lintas 255 days Mon 20/12/21Wed 31/08/222SS 100%
6 Pengujian Lingkungan Hidup 255 days Mon 20/12/21Wed 31/08/222 100%
7 Keselamatan dan Kesehatan Kerja 255 days Mon 20/12/21Wed 31/08/222SS 100%
8 Manajemen Mutu 255 days Mon 20/12/21Wed 31/08/222SS 100%
9 PEMATANGAN LAHAN KAWASAN BANK 255 days Mon Wed 100%
INDONESIA 20/12/21 31/08/22
10 Pembersihan Lahan (Stripping & Clearing) 56 days Mon 20/12/21Sun 13/02/22 100%
11 Pembersihan dan Pengupasan Lahan 35 days Mon 20/12/21Sun 23/01/224SS 100%
12 Pemotongan Pohon Pilihan diameter 15 - 30 cm56 days Mon 20/12/21 Sun 13/02/224SS 100%
13 Pekerjaan Cut & Fill (Pematangan Lahan) 196 days Mon 07/02/22 Sun 21/08/22 100%
14 Galian Biasa 196 days Mon 07/02/22 Sun 21/08/22 100%
15 Zona 1 196 days Mon 07/02/22Sun 21/08/2211SS+49 days 100%
16 Zona 2 184 days Mon 07/02/22Tue 09/08/2211SS+49 days 100%
17 Timbunan Biasa dari hasil galian 196 days Mon 07/02/22 Sun 21/08/22 100%
18 Zona 1 196 days Mon 07/02/22Sun 21/08/2211SS+49 days 100%
19 Zona 2 196 days Mon 07/02/22Sun 21/08/2211SS+49 days 100%
20 Pekerjaan Soil Improvement 167 days Fri 18/03/22 Wed 31/08/22 100%
21 Timbunan Limestone dari sumber galian 157 days Fri 18/03/22Sun 21/08/2218FS-98 days;19FS-98 days;15FS-112 days;16FS-112 days 100%
22 Solid Sodding 59 days Mon 04/07/22Wed 31/08/2217FS-28 days 100%
23 PEKERJAAN DINDING PENAHAN TANAH CI 84 days Mon Sun 98%
SUBAH 23/05/22 14/08/22
24 Pekerjaan Dinding Penahan Tanah Sungai 77 days Mon Sun 98%
Cisubah 23/05/22 07/08/22
25 Penyediaan CCSP (W 450 B) Sisi Sungai Cisubah42 days Mon 23/05/22 Sun 03/07/22 100%
26 Pemancangan CCSP (W 450 B) Sisi Sungai Cisubah42 days Mon 23/05/22Sun 03/07/2225SS 85%
27 Bored Pile Dia. 60 cm Sisi Sungai Cisubah 42 days Mon 30/05/22Sun 10/07/2217SS+112 days 100%
28 Beton struktur Capping Beam CCSP, FC' 30 Mpa22 days Sun 26/06/22 Sun 17/07/2229SS+7 days;26SS+28 days 100%
29 Baja Tulangan Sirip - BjTS 420A 42 days Mon 20/06/22Sun 31/07/2226SS+21 days;27SS+21 days 100%
30 Beton struktur Capping Beam Soldier Pile, 8 days Sun Sun 27FS+14 100%
FC' 30 Mpa 24/07/22 31/07/22 days;29FS-14
31 Beton Struktur Capping Bored Pile, FC' 30 Mpa 35 days Mon 27/06/22 days
Sun 31/07/2227SS+28 days;29SS+7 days 100%
32 Beton Struktur DPT Kantilever, FC' 30 Mpa 28 days Mon 04/07/22Sun 31/07/2231SS+7 days;29SS+14 days 100%
33 Beton Struktur Capping Beam dengan Pondasi Strauss
7 daysPile
Mon 01/08/22Sun 07/08/2229SS+56 days 100%
34 Gabion sisi cisubah 21 days Mon 25/07/22Sun 14/08/22 100%
35 Gabion sisi cisubah 21 days Mon 25/07/22Sun 14/08/2217FS-80 days 100%
36 PHO 14 days Thu 18/08/22Wed 31/08/225;7;8;21;22;35;4;30;31 0%
37 Selesai 0 days Wed 31/08/22Wed 31/08/2236 31/08