Progress M33.

mpp
ID Task Name Actual Start Actual Finish Half 1, 2022 Half 2, 2022 Half 1, 2023
N D J F M A M J J A S O N D J F
1 Pekerjaan Pengadaan Jasa Perencanaan dan Pembangunan 20/12/21 NA 80%
Jalan at Grade serta Pematangan Lahan Kawasan Bank
Indonesia di Kabupaten Karawang Menggunakan Metode
Design and Build
2 Mulai NA NA 20/12
3 PEKERJAAN PERANCANGAN 20/12/21 NA 99%
4 Survei Topografi 03/01/22 30/01/22 100%
5 Survei Penyelidikan Tanah 03/01/22 13/03/22 100%
6 Survei Hidrologi dan Hidrodinamika 10/01/22 30/01/22 100%
7 Penyusunan Kriteria Desain 20/12/21 09/01/22 100%
8 Analisis Pematangan Lahan/Land Grading 24/01/22 10/04/22 100%
9 Analisis Perkerasan Jalan Jalan Akses 10/01/22 05/06/22 100%
10 Analisis Dinding Penahan Tanah dan Pagar Pembatas 17/01/22 26/06/22 100%
11 Analisis Penerangan Jalan Umum 10/01/22 10/04/22 100%
12 Analisis Jaringan Air Bersih/Air Baku 10/01/22 05/06/22 100%
13 Analisis Jaringan Irigasi Lanskap dan Infrastruktur Rumah 17/01/22 10/04/22 100%
Pompa
14 Analisis Hidrologi Kawasan 24/01/22 13/02/22 100%
15 Analisis Duct Infrastruktur (Trenching) 17/01/22 05/06/22 100%
16 Analisis Danau/Pond 10/01/22 10/04/22 100%
17 Analisis Jaringan Pemadam Kebakaran/Fire Fighting 17/01/22 10/04/22 100%
18 Analisis Drainase Kawasan dan Jalan Akses 17/01/22 26/06/22 100%
19 Penggambaran Detail 17/01/22 NA 97%
20 Penyusunan Rencana Kerja dan Syarat-Syarat 24/01/22 NA 90%
21 PERSIAPAN 20/12/21 NA 80%
22 Mobilisasi 20/12/21 NA 81%
23 Manajemen dan Keselamatan Lalu Lintas 20/12/21 NA 89%
24 Pengujian Lingkungan Hidup 20/12/21 NA 50%
25 Keselamatan dan Kesehatan Kerja 20/12/21 NA 89%
26 Manajemen Mutu 20/12/21 NA 89%
27 PEMATANGAN LAHAN KAWASAN BANK INDONESIA 21/12/21 NA 88%
28 Pembersihan Lahan (Stripping & Clearing) 21/12/21 13/02/22 100%
29 Pembersihan dan Pengupasan Lahan 21/12/21 23/01/22 100%
30 Pemotongan Pohon Pilihan diameter 15 - 30 cm 21/12/21 13/02/22 100%
31 Pekerjaan Cut & Fill (Pematangan Lahan) 14/02/22 NA 96%
32 Galian Biasa 14/02/22 NA 97%
33 Zona 1 14/02/22 NA 96%
34 Zona 2 14/02/22 NA 98%
35 Timbunan Biasa dari hasil galian 14/02/22 NA 96%
36 Zona 1 14/02/22 NA 94%
37 Zona 2 14/02/22 NA 97%
38 Pekerjaan Soil Improvement 18/03/22 NA 53%
39 Timbunan Limestone dari sumber galian 18/03/22 NA 64%
40 Solid Sodding 04/07/22 NA 24%
41 PEKERJAAN JALAN AT GRADE 20/12/21 NA 63%

Page 1
Progress M33.mpp
ID Task Name Actual Start Actual Finish Half 1, 2022 Half 2, 2022 Half 1, 2023
N D J F M A M J J A S O N D J F
42 Pembangunan Jalan at Grade Right Of Way = 22m, 2 20/12/21 NA 43%
Jalur 2 Lajur dan 2 arah, Lebar Jalan SPU 8m, Lebar
Jalan Residensial 6,5m
43 Pembersihan dan Pengupasan Lahan 20/12/21 09/01/22 100%
44 Pemotongan Pohon Pilihan diameter 15 - 30 cm 20/12/21 10/01/22 100%
45 Galian Biasa 07/03/22 27/03/22 100%
46 Timbunan Biasa dari hasil galian 07/03/22 NA 99%
47 Timbunan Limestone dari sumber galian 28/03/22 NA 81%
48 Penyiapan Badan Jalan 02/05/22 NA 63%
49 Lapis Pondasi Agregat Kelas A 22/05/22 NA 29%
50 Perkerasan Beton Semen NA NA 0%
51 Lapis Pondasi bawah Beton Kurus 04/06/22 NA 23%
52 Marka Jalan Termoplastik NA NA 0%
53 Rambu Jalan Tunggal dengan Permukaan Pemantul NA NA 0%
Engineering Grade
54 Unit Lampu Penerangan Jalan Lengan Tunggal, Tipe NA NA 0%
LED
55 Unit Lampu Penerangan Jalan Lengan Ganda, Tipe LED NA NA 0%

56 Solid Sodding NA NA 0%
57 Paving Blok Trotoar NA NA 0%
58 Kerb Pracetak Jenis 2 (Penghalang/Barrier) NA NA 0%
59 Canopy untuk Pedestrian NA NA 0%
60 Pekerjaan Dinding Penahan Tanah 31/01/22 NA 99%
61 Beton Struktur Capping Beam CCSP, FC' 30 MPa 09/05/22 26/06/22 100%
62 Baja Tulangan Sirip - BjTS 420A 22/02/22 17/07/22 100%
63 Penyediaan CCSP (W 450 B) Sisi Sungai Cikirinjing 13/03/22 03/07/22 100%
64 Pemancangan CCSP (W 450 B) Sisi Sungai Cikirinjing 25/05/22 03/07/22 100%

65 Bored Pile Dia. 60 cm Sisi Sungai Cikirinjing 21/02/22 12/06/22 100%


66 Dinding SRW Sisi Peruri 07/04/22 NA 98%
67 Dinding Penahan Tanah Sisi Sungai Cikirinjing 14/03/22 17/07/22 100%
68 Bored Pile Dia. 60 cm 31/01/22 24/04/22 100%
69 Beton Struktur Capping Bored Pile, FC' 30 Mpa 06/03/22 05/06/22 100%
70 Pagar NA NA 0%
74 Pembangunan Jalan Area PERURI (Lokasi POND PERURI 09/01/22 NA 95%
sebagai jalan akses ke Proyek BI)
75 Pembersihan dan Pengupasan Lahan 10/01/22 13/01/22 100%
76 Pemotongan Pohon Pilihan diameter 15 - 30 cm 09/01/22 11/01/22 100%
77 Galian Biasa 14/01/22 01/02/22 100%
78 Timbunan Biasa dari hasil galian 14/01/22 01/02/22 100%
79 Penyiapan Badan Jalan 30/01/22 05/02/22 100%
80 Lapis Pondasi Agregat Kelas A 03/02/22 NA 82%
81 Perkerasan Beton Semen 16/02/22 NA 82%
82 Lapis Pondasi Bawah Beton Kurus 11/02/22 NA 82%

Page 2
Progress M33.mpp
ID Task Name Actual Start Actual Finish Half 1, 2022 Half 2, 2022 Half 1, 2023
N D J F M A M J J A S O N D J F
83 Saluran Drainase menggunakan U-Ditch / Box Culvert 06/03/22 NA 83%
yang dibuang ke sungai Ci Kirinjing
84 Saluran U-Ditch 60x60 (dengan penutup beton) 22/05/22 NA 31%
85 Saluran U-Ditch 120x120 30/06/22 17/07/22 100%
86 Saluran Box Culvert 100x100 20/03/22 03/07/22 100%
87 Saluran Box Culvert 150x150 06/03/22 24/04/22 100%
88 Catchbasin NA NA 0%
89 Jaringan Distribusi Air Bersih dan air baku 24/07/22 NA 12%
90 Pipa Conveyance / Transmisi Ø 12 (300 mm) 24/07/22 NA 24%
91 Fitting dan Aksesoris NA NA 0%
92 Jaringan Irigasi 14/06/22 NA 60%
93 Pipa Tranmisi HDPE Ø 2 24/07/22 NA 19%
94 Ground Tank Kapasitas 50 m³ 14/06/22 NA 79%
95 Pekerjaan Ducting Infrastruktur 12/04/22 NA 90%
96 Ducting Utilitas Pipa Air Bersih dan Air Baku 12/04/22 NA 93%
97 Ducting Utilitas Kabel 12/04/22 NA 87%
98 Jaringan Fire Fighthing 29/06/22 NA 74%
99 Pipa Tranmisi Black Steel Ø 8 NA NA 0%
100 Ground Tank Kapasitas 50 m³ 29/06/22 07/08/22 100%
101 Gabion (Perlindungan Sungai Cikirinjing dengan Bronjong)10/06/22 NA 33%
102 Gabion (Perlindungan Sungai Cikirinjing dengan Bronjong)
10/06/22 NA 33%
103 PEKERJAAN DINDING PENAHAN TANAH CI SUBAH 21/03/22 NA 96%
104 Pekerjaan Dinding Penahan Tanah Sungai Cisubah 21/03/22 07/01/23 100%
105 Beton struktur Capping Beam CCSP, FC' 30 Mpa 17/07/22 26/08/22 26/08
106 Baja Tulangan Sirip - BjTS 420A 11/06/22 31/07/22 100%
107 Penyediaan CCSP (W 450 B) Sisi Sungai Cisubah 04/05/22 03/07/22 100%
108 Pemancangan CCSP (W 450 B) Sisi Sungai Cisubah 03/07/22 07/01/23 07/01
109 Bored Pile Dia. 60 cm 03/07/22 08/07/22 08/07
110 Beton Struktur Capping Beam Bored Pile, FC' 30 Mpa 21/03/22 31/07/22 100%
111 Gabion sisi cisubah 12/07/22 NA 68%
112 Gabion sisi cisubah 12/07/22 NA 68%
113 PEKERJAAN POND 04/02/22 NA 78%
114 Pond 1 07/03/22 NA 44%
115 Galian Biasa 07/03/22 NA 90%
116 Geomembran untuk Pond NA NA 0%
117 Timbunan Limestone dari sumber galian NA NA 0%
118 Pond 2 01/03/22 NA 51%
119 Galian Biasa 01/03/22 NA 90%
120 Geomembran untuk Pond NA NA 0%
121 Timbunan Limestone dari sumber galian NA NA 0%
122 Pond 3 04/04/22 NA 98%
123 Galian Biasa 04/04/22 03/07/22 100%
124 Geomembran untuk Pond 11/07/22 NA 90%
125 Timbunan Limestone dari sumber galian 04/07/22 NA 90%
126 Pond 4 04/02/22 26/06/22 100%

Page 3
Progress M33.mpp
ID Task Name Actual Start Actual Finish Half 1, 2022 Half 2, 2022 Half 1, 2023
N D J F M A M J J A S O N D J F
127 Galian Biasa 04/02/22 15/05/22 100%
128 Geomembran untuk Pond 16/05/22 26/06/22 100%
129 Timbunan Limestone dari sumber galian 16/05/22 26/06/22 100%
130 Pekerjaan saluran drainase finish B0 area kawasan 50HaNA NA 0%
134 PHO NA NA 0%
135 Selesai NA NA 31/08