WAKTU PELAKSANAAN

NO JENIS PEKERJAAN BOBOT (%) MINGGU KE


1 2 3 4 5 6 7 8

1 PEK. PONDASI 14.46 6.7 5.2 2.56

2 PEK. BETON 24.69 7.55 6.5 5.9 4.74

3 PEK. DINDING 6.62 2.30 3.14 1.18

4 PEK. ATAP 4.24 2.00 2.24

5 PEK. PLAFOND 14.27 7.00 5.27 2.00

6 PEK. PLASTERAN 17.36 7.12 7.10

7 PEK. LANTAI 4.8 4.80

8 PEK. PINTU 6.94 3.47 3.47

9 PEK. PENGECETAN 3.46 0.46

10 PEK. INSTALASI 3.16

100

RENCANA FISIK PER MINGGU 6.7 12.75 11.36 16.04 11.19 8.8 12.83 11.03

RENCANA FISIK KOMULATIF 6.7 19.45 30.81 46.85 58.04 66.84 79.67 90.7
9 10

14.46 0

24.69 0

6.62 0

4.24 0

14.27 0

3.14 17.36 0

4.8 0

6.94 0

3.00 3.46 0

2.6 0.56 3.16 0

8.74 0.56

99.44 100