Matrix Pengadaan Item Arsitektur CHI

Update : 28 Maret 2022


Durasi Selesai Start
Stasiun Skup by Supplier Aplikator Target PO Cutting List Status Ket. Spek
Produksi produksi Instalasi
KP Rambutan
ACP CHI/ABS Trianda Trianda 31-Mar sudah PO blm DP Biru & Grey 7 7-Apr-22 19-Apr-22

Solar Tuff ADHI Alderon 31-Mar Bronze & Clear 7 7-Apr-22 22-Apr-22

Marmer CHI/ABS Kota Marmer Kota Marmer 31-Mar sudah PO blm DP Marmer + Step Nosing 30 30-Apr-22 20-Apr-22

Guiding Block ADHI WSI/WID 31-Mar Line & Dot 45 15-May-22 20-Apr-22

HT ADHI 31-Mar 20-Apr-22

Bondek + Wiremesh 31-Mar 19-Mar-22

Durasi Selesai Start


Stasiun Skup by Supplier Aplikator Target PO Cutting List Status Ket. Spek
Produksi produksi Instalasi
Pancoran
ACP CHI/ABS Trianda Trianda 31-Mar sudah PO blm DP Biru & Grey 7 7-Apr-22 19-Apr-22

Solar Tuff ADHI Alderon 31-Mar Bronze & Clear 7 7-Apr-22 22-Apr-22

Marmer CHI/ABS Kota Marmer Kota Marmer 31-Mar sudah PO blm DP Marmer + Step Nosing 30 30-Apr-22 20-Apr-22

Guiding Block ADHI WSI/VID 31-Mar Line & Dot 45 15-May-22 20-Apr-22

HT ADHI 31-Mar 20-Apr-22

Bondek + Wiremesh 31-Mar sudah PO 19-Mar-22

Durasi Selesai Start


Stasiun Skup by Supplier Aplikator Target PO Cutting List Status Ket. Spek
Produksi produksi Instalasi
Ciliwung
ACP ADHI Alderon/Dekson Sub ADHI 14-Apr Biru & Grey 7 21-Apr-22 14-May-22

Solar Tuff ADHI Alderon 14-Apr Bronze & Clear 7 21-Apr-22 17-May-22

Marmer ADHI Kota Marmer Kota Marmer 31-Mar Marmer + Step Nosing 30 30-Apr-22 27-Apr-22

Guiding Block ADHI WSI/VID 31-Mar Line & Dot 45 15-May-22 27-Apr-22

HT ADHI 14-Apr 27-Apr-22

Bondek + Wiremesh ADHI 14-Apr 18-Apr-22


Durasi Selesai Start
Stasiun Skup by Supplier Aplikator Target PO Cutting List Status Ket. Spek
Produksi produksi Instalasi
Kuningan
ACP ADHI Alderon/Dekson Sub ADHI 14-Apr Biru & Grey 7 21-Apr-22 14-May-22

Solar Tuff ADHI Alderon 14-Apr Bronze & Clear 7 21-Apr-22 17-May-22

Marmer ADHI Kota Marmer Kota Marmer 31-Mar Marmer + Step Nosing 45 15-May-22 7-May-22

Guiding Block ADHI WSI/VID 31-Mar Line & Dot 45 15-May-22 7-May-22

HT ADHI 14-Apr 7-May-22

Bondek + Wiremesh 14-Apr 1-May-22

Durasi Selesai Start


Stasiun Skup by Supplier Aplikator Target PO Cutting List Status Ket. Spek
Produksi produksi Instalasi
Dukuh Atas
ACP ADHI Alderon/Dekson Sub ADHI 14-Apr Biru & Grey 7 21-Apr-22 14-May-22

Solar Tuff ADHI Alderon 14-Apr Bronze & Clear 7 21-Apr-22 17-May-22

Marmer ADHI Kota Marmer Kota Marmer 31-Mar Marmer + Step Nosing 45 15-May-22 7-May-22

Guiding Block ADHI WSI/VID 31-Mar Line & Dot 45 15-May-22 7-May-22

HT ADHI 14-Apr 7-May-22

Bondek + Wiremesh 14-Apr 1-May-22