RENCANA ANGGARAN BIAYA (RAB)

BANTUAN PEMBANGUNAN RUANG BELAJAR PMDT

No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah (Rp)


(Rp)

I PEKERJAAN PERSIAPAN
Penyediaan listrik, air, selama
pelaksanaan 1 Is. 1,000,000.00 1,000,000.00
SUB TOTAL PEKERJAAN I 1,000,000.00
II PEKERJAAN DINDING DAN PLESTERAN
Bata Merah 5000 Buah 450.00 2,250,000.00
Pasir 18 m3 250,000.00 4,500,000.00
Semen 100 Sak 55,000.00 5,500,000.00
SUB TOTAL PEKERJAAN II 12,250,000.00
III PEKERJAAN ATAP DAN PLAFON
Genteng 1000 Buah 4,000.00 4,000,000.00
Lisplank 80 m2 51,600.00 4,128,000.00
Papan Gypsum 80 Lembar 65,000.00 5,200,000.00
Hollow 2x4 150 Batang 15,000.00 2,250,000.00
SUB TOTAL PEKERJAAN III 15,578,000.00
IV PEKERJAAN KUSEN PINTU DAN JENDELA
Kusen dan Pintu 8 Pasang 1,700,000.00 13,600,000.00
Kusen dan Jendela 6 Pasang 1,300,000.00 7,800,000.00
Engsel 16 Pasang 35,000.00 560,000.00
Kunci 8 Pasang 150,000.00 1,200,000.00
SUB TOTAL PEKERJAAN IV 23,160,000.00
V PEKERJAAN LANTAI
Keramik Lantai 100 m2 60,000.00 5,400,000.00
Pasir 6 m3 250,000.00 1,500,000.00
Semen 30 sak 55,000.00 1,650,000.00
SUB TOTAL PEKERJAAN V 8,550,000.00
VI PEKERJAAN PENGECATAN
Cat Tembok 4 Pel 800,000.00 2,400,000.00
Cat Kayu 13 Kg 50,000.00 650,000.00
SUB TOTAL PEKERJAAN VI 3,050,000,00
VII BELANJA PEGAWAI
Belanja Upah Tukang 60 hari 100,000.00 6,000,000.00
Belanja Upah kuli 60 hari 75,000.00 4,500,000.00
SUB TOTAL PEKERJAAN VII 10,500,000.00
TOTAL PEKERJAAN 74,888,000.00
DIBULATKAN 75,000,000.00

Tuban, 05 Juni 2022

Kepala MDTW SUNAN BONANG Ketua UPK2B

SOLEH MUHIBBUDIN