A PEKERJAAN PERSIAPAN
1 PEMBERSIHAN LAHAN ls 1,0 12.500.000,00 12.500.000,00
(termasuk penebangan pohon)
2 MARKING DAN PENGUKURAN KEMBALI m1 95,0 20.000,00 1.900.000,00
(BOWPLANK)
3 BEDENG PEKERJA / DIREKSI KEET / ls 1,0 15.000.000,00 15.000.000,00
(termasuk Bahan)
SUB TOTAL 29.400.000,00

B PEKERJAAN GALIAN DAN URUGAN TANAH


1 Galian Tanah Pondasi Cakar Ayam m3 36,0 110.000,00 3.960.000,00
2 Galian Tanah Pondasi Batu Kali m3 83,7 110.000,00 9.207.000,00
(Dinding Penahan Tanah)
3 Galian Dan Urugan (Cut & Fill) Tanah
Existing dan Lantai by Owner
SUB TOTAL 13.167.000,00

C PEKERJAAN BETON STRUKTUR & PONDASI


1 Pas. Pondasi Batu Kali m1 139,5 95.000,00 13.252.500,00
(untuk Dinding Penahan Tanah max = 1m)
2 Pekerjaan Pondasi Cakar Ayam m3 18,0 750.000,00 13.500.000,00
(termasuk pembesian, bekisting dan cor)
3 Pekerjaan Beton Sloof / Tie Beam
(0,3/0,4m) m3 20,6 750.000,00 15.480.000,00
(termasuk pembesian, bekisting dan cor)
5 Pekerjaan Beton Ring Balk/ Tie Beam m3 6,5 750.000,00 4.896.000,00
(termasuk pembesian, bekisting dan cor)
6 Pekerjaan Kolom Praktis m3 5,0 750.000,00 3.750.000,00
(termasuk pembesian, bekisting dan cor)
7 Pekerjaan Beton Composite Kolom Baja m3 11,0 750.000,00 8.250.000,00
SUB TOTAL 59.128.500,00
D PEKERJAAN LANTAI
1 Pekerjaan Pemadatan Tanah m2 687,0 25.000,00 17.175.000,00
2 Pekerjaan Floor Screed m2 687,0 40.000,00 27.480.000,00
3 Pekerjaan Pas. Keramik Lantai m2 687,0 65.000,00 44.655.000,00
4 Pekerjaan Pas. Plinth Lantai m1 322,0 25.000,00 8.050.000,00
SUB TOTAL 97.360.000,00
E PEKERJAAN DINDING
1 Pasang Dinding Bata Merah m2 585,2 75.000,00 43.890.000,00
2 Plester Dinding dan Acian m2 1.170,4 55.000,00 64.372.000,00
3 Pekerjaan Cat Dinding m2 1.170,4 17.500,00 20.482.000,00
4 Pasang Keramik Dinding Kamar Mandi m2 85,0 65.000,00 5.525.000,00
SUB TOTAL 134.269.000,00
F PEKERJAAN PASANG PINTU DAN JENDELA
NO URAIAN PEKERJAAN UNIT VOLUME HARGA SATUAN HARGA (Rp)
(Rp)
F PEKERJAAN PLAFOND

G PEKERJAAN INSTALASI LISTRIK


1 Instalasi Titik Lampu ttk 40,0 125.000,00 5.000.000,00
2 Instalasi Stop Kontak ttk 10,0 125.000,00 1.250.000,00
3 Instalasi Saklar ttk 10,0 125.000,00 1.250.000,00
4 Instalasi Box MCB Listrik ttk 5,0 250.000,00 1.250.000,00
SUB TOTAL 8.750.000,00
H PEKERJAAN SANITAIR
1 Pas. Closed Duduk unit 10,0 350.000,00 3.500.000,00
2 Pas. Urinoir unit 4,0 350.000,00 1.400.000,00
3 Pas. Washtafel unit 4,0 350.000,00 1.400.000,00
4 Pas. Hand Dryer unit 2,0 125.000,00 250.000,00
SUB TOTAL 6.550.000,00
I PEKERJAAN INSTALASI AIR BERSIH DAN AIR
KOTOR
1 Pekerjaan Septic Tank ls 1,0 3.000.000,00 3.000.000,00
2 Instalasi Air Bersih ttk 28,0 75.000,00 2.100.000,00
3 Instalasi Air Kotor ttk 13,0 90.000,00 1.170.000,00
SUB TOTAL 6.270.000,00

GRAND TOTAL 354.894.500,00