PERENCANAAN
PEKERJAAN
PEMBANGUNAN SALURAN DRAINASE DUSUN AJUN GUCI GAMPONG JEUMPET AJUN KEC. DARUL IMARAH
KAB. ACEH BESAR
LOKASI
KABUPATEN ACEH BESAR
GAMBAR BESTEK
PERENCANAAN PEMBANGUNAN SALURAN
DRAINASE DUSUN AJUN GUCI GAMPONG
JEUMPET AJUN KEC. DARUL IMARAH KAB. ACEH
BESAR
GAMPONG JEUMPET AJUN
KEC. DARUL IMARAH KAB. ACEH BESAR
TAHUN 2022
LEMBAR PENGESAHAN DOKUMEN
GAMBAR PERENCANAAN
PEKERJAAN :
PEMBANGUNAN SALURAN DRAINASE DUSUN AJUN GUCI GAMPONG JEUMPET AJUN
KEC. DARUL IMARAH KAB. ACEH BESAR
(TAHUN ANGGARAN 2022)
LOKASI :
KEC. DARUL IMARAH KAB. ACEH BESAR
KE
SI
M
PA PEMERINTAH ACEH
N
G N DINAS PERUMAHAN RAKYAT DAN
AJ
U KAWASAN PERMUKIMAN ACEH
14.223
14.153
N
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
as as
15.035
sal
15.030
sal
14.120
14.387
as
sendimen
15.029
sal
A-4 14.198
15.187
p
14.136
14.991
sal
14.069
as
p
cr
14.980
sal
15.220
pb3
A-3
15.065
pb2
14.320
cr
14.474
15.296
cr
slop
W E
14.228
cr
14.47014.526
14.480 15.359
cr
cr
cr pndasi
14.664
pb1
A-2 13.843
cr
13.777
cr
B-6
14.217
cr
14.442
cr
14.829
cr
A-1
14.837
cr
14.100
cr
GAMBAR BESTEK
14.193
cr 14.552
14.473
cr
14.670cr
cr
B-5
14.459
p
14.315
cr
14.070
cr
S
13.972
cr
A-0
14.070
cr
14.420
CATATAN :
cr
C-2
14.594
X= 753 500
X= 753 600
X= 753 700
X= 753 800
X= 753 900
14.576
p
cr
14.568
cr
15.544
pndasi
B-4
14.763
14.623
p
p
14.665as
14.805
15.035 cr bnang14.501
cr
14.721
14.648
C-1
cr
p
14.810
cr
14.767
Renc. Plat Saluran = 4 m
cr
15.182
14.655 cr
15.000
B-3
cr
cr
p
14.727
sit
14.814
14.404
14.836
14.726
cr
as
14.783 sal
sal
14.380
14.793
as
sal
B-1B-2
14.465
as
B-0 15.007
cr
15.061
cr 14.67714.721
cr
15.068 p
14.617
cr
cr
15.016
14.478
D-2
14.978
sal assal
14.812
r
15.085
cr
14.897
14.909 cr 15.092
14.471
cr
14.888 14.481
cr
as 14.403 sal
14.446 cr
14.548
14.902
as cr
14.413
as
sal 14.901
14.458 14.839
as
15.237
cr
cr14.509 cr
t
as 14.428
15.089 14.439
cr 14.550 14.433
as
plat cr cr
15.070 14.385
plat
as
14.966
15.067 cr
t
15.000
Start
15.036
p
14.999
p
14.405
D-1
sal
MENGETAHUI :
15.055
14.393
plat
as
14.820
14.363
15.049
p
KUASA PENGGUNA ANGGARAN
D-0
as
sal
14.952
14.834
14.405
sal as
sal
PROGRAM PENINGKATAN PRASARANA, SARANA DAN
14.425
as
DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.483
as
PERMUKIMAN ACEH
X= 753 500
X= 753 600
X= 753 700
X= 753 800
X= 753 900
MENGETAHUI / MENYETUJUI :
Y= 611 000 Y= 611 000 Y= 611 000 Y= 611 000 Y= 611 000
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
KONSULTAN PERENCANA:
X= 753 500
X= 753 600
X= 753 700
X= 753 800
X= 753 900
E-0
Y= 610 900 Y= 610 900 Y= 610 900 Y= 610 900 Y= 610 900
E-1
E-2
E-3
TIM PERENCANA:
TANDA
PERSONIL NAMA
TANGAN
TEAM LEADER
CAD OPERATOR
E-4 SKALA :
X= 753 500
X= 753 600
X= 753 700
X= 753 800
X= 753 900
NAMA GAMBAR :
Ruas - A
Awal Pekerjaan STA. 0+000
Koordinat : Ruas - B
GAMBAR BESTEK
5°31'28.09"N, 95°17'21.20"E Akhir Pekerjaan STA. 0+091.5
CATATAN :
Koordinat :
5°31'28.87"N, 95°17'23.55"E
Ruas - C
Akhir Pekerjaan STA. 0+030.7
Koordinat : Ruas - D
5°31'28.09"N, 95°17'21.20"E Akhir Pekerjaan STA. 0+035
Koordinat :
5°31'26.94"N, 95°17'23.95"E
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
TIM PERENCANA:
TANDA
PERSONIL NAMA
TANGAN
TEAM LEADER
AHLI STRUKTUR
Ruas - E
Akhir Pekerjaan STA. 0+216
LAYOUT 1 : 1500
Koordinat :
5°31'17.24"N, 95°17'19.49"E
2022 -
KE
PEMERINTAH ACEH
SI
M N DINAS PERUMAHAN RAKYAT DAN
PA KAWASAN PERMUKIMAN ACEH
Akhir Pekerjaan N
G JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
0+110.5 15.030
sal
14.223
as
sal
14.153
as
15.035
N
A-5 15.018
sal
14.100
as14.358
sendimen
W E
15.003
sal
A-4 15.220
pb3
14.198
cr15.187
p
14.136
14.991
psal 14.069
as
14.980
sal
A-3
15.065
pb2
14.320
cr
14.474
cr
15.296
slop
GAMBAR BESTEK
14.228
cr
14.526
14.470
14.480cr 15.359
cr
cr pndasi
14.664
pb1
S
A-2 13.843
cr
B-6
13.777
cr
Awal Pekerjaan
14.217
cr
14.442
cr
14.829
cr
CATATAN :
A-1
14.837
cr
0+000
14.100
cr
14.193
cr 14.552
14.473
cr
14.670cr
cr
B-5
14.459
p
14.315
cr
14.070
cr
13.972
cr
Akhir Pekerjaan
A-0 0+091.5
14.070
cr
14.420
cr
C-2
14.594
X= 753 600
X= 753 700
X= 753 800
14.576 cr
14.568 p
cr
15.544
14.763
pndasi
B-4
14.50114.623
p
14.805 as
14.665 p
15.035 cr bnang
cr
14.810
14.721
p
14.648
cr
C-1
PEMBERI TUGAS
cr
0+000 B-3
15.182
cr
15.000cr14.655
cr
p
14.727
sit
14.814
14.404
as
14.836
sal
14.726
cr
C-0 Y= 611 100 Y= 611 100 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
B-2
14.465
as
B-0 14.812
r
15.007
cr
15.085
cr B-1
15.061
cr 14.677
cr 14.721
15.068
cr cr
15.016
14.478
14.617
p
sal as 14.978
sal
15.000
Start
PERMUKIMAN ACEH
15.036
p
14.999
p
14.405
D-1
sal
15.049
14.363 p
14.820
D-0
sal as
14.952 14.834
14.405
sal sal as
NAMA PEKERJAAN :
19.00 19.00
PEMBANGUNAN SALURAN DRAINASE
DUSUN AJUN GUCI GAMPONG JEUMPET AJUN
KEC. DARUL IMARAH KAB. ACEH BESAR
18.00 18.00
LOKASI PEKERJAAN :
Rencana Top Saluran Rencana Top Saluran
17.00 Rencana Dasar Saluran 17.00
Awal Pekerjaan Rencana Dasar Saluran KEC. DARUL IMARAH KAB. ACEH BESAR
Elevasi Tanah Asli Awal Pekerjaan Elevasi Tanah Asli
16.00 16.00 KONSULTAN PERENCANA:
Akhir Pekerjaan Akhir Pekerjaan
15.00 15.00
14.00 14.00
13.00 13.00
12.00 12.00
TIM PERENCANA:
11.00 11.00
TANDA
PERSONIL NAMA
TANGAN
10.00 10.00 TEAM LEADER
Station A.0 A.1 A.2 A.3 A.4 A.5 Station B.0 B.1 B.2 B.3 B.4 B.5 B.6 CAD OPERATOR
14.385
14.655
14.501
14.473
14.480
14.576
14.315
14.442
14.228
14.320
14.069
Tanah Tanah
Asli Asli SITUASI DAN
PENAMPANG MEMANJANG 1 : 1000
Rencana Rencana
14.270
14.230
14.213
14.194
14.179
14.162
14.400
14.342
14.315
14.301
14.256
14.219
14.194
Dasar Dasar TAHUN NO GAMBAR : JLH GAMBAR
Saluran Saluran 2022 -
A-1
14.100
cr
14.193
cr 14.552
14.473
cr
14.670cr
B-5
cr
14.459
p
PEMERINTAH ACEH
14.315
cr14.070
cr
13.972
cr
14.420
cr
C-2
14.594
X= 753 700
X= 753 800
cr
42882 Fax : (0651) 41130 Banda Aceh 23236
14.568 p
cr
Akhir Pekerjaan
B-4
15.544
pndasi
14.763
p
14.50114.623
as
14.665
14.805 p
15.035 cr bnang
cr
0+030.7
W E
C-1
14.810
cr
14.721
p
14.648
cr
S
GAMBAR BESTEK
Awal Pekerjaan Renc. Plat Saluran = 4 m
14.767
0+000 CATATAN :
B-3
cr
15.182
14.655 cr
15.000cr
cr
p
14.727
sit
14.814
14.404
as
14.836
sal
14.726
cr
B-0 r
14.812
15.007
cr
15.085
cr
15.061
cr cr14.67714.721
cr cr15.068
14.617
p
14.478
15.016 14.978
sal as sal
D-2
14.897
14.909 cr 15.092
14.471 cr cr
14.888 14.481
as 14.403 14.446
sal cr
as as 14.548
14.902 14.413 cr
sal as 14.901
15.237 14.458 14.839 cr
t cr 14.509 cr
as 14.428
15.089 cr
14.439 14.550 14.433
plat as cr cr
15.070 14.385
plat as
14.966
15.067 cr
t
15.000
Start
Akhir Pekerjaan
15.036
0+039
p
14.999
p
14.405
D-1
sal
PEMBERI TUGAS
Awal Pekerjaan 0+000 MENGETAHUI :
15.055
14.393
plat
as
15.049
p
14.820
14.363
D-0
sal as
MENGETAHUI / MENYETUJUI :
NAMA PEKERJAAN :
19.00 19.00
PEMBANGUNAN SALURAN DRAINASE
Rencana Top Saluran DUSUN AJUN GUCI GAMPONG JEUMPET AJUN
KEC. DARUL IMARAH KAB. ACEH BESAR
18.00 18.00 Rencana Dasar Saluran
LOKASI PEKERJAAN :
Awal Pekerjaan Elevasi Tanah Asli
17.00 17.00 Awal Pekerjaan
Rencana Top Saluran KEC. DARUL IMARAH KAB. ACEH BESAR
14.00 14.00
13.00 13.00
12.00 12.00
TIM PERENCANA:
11.00 11.00
TANDA
PERSONIL NAMA
TANGAN
10.00 10.00 TEAM LEADER
Station C.0 C.1 C.2 Station D.0 D.1 D.2 CAD OPERATOR
4.00
14.405
14.478
14.814
14.721
14.576
Tanah Tanah
Asli Asli SITUASI DAN
PENAMPANG MEMANJANG 1 : 1000
Rencana Rencana
14.320
14.299
14.270
14.363
14.334
14.315
E
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
S
N
E-1
E-0
W
GAMBAR BESTEK
E-2
CATATAN :
Y= 611 000
Y= 610 900
Y= 610 800
Y= 610 700
Akhir Pekerjaan
Pasangan Batu
dan Plesteran
0+134
PEMBERI TUGAS
MENGETAHUI :
E-5
E-3
X= 753 600 X= 753 600 X= 753 600 KUASA PENGGUNA ANGGARAN
E-6
PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
E-4
DINAS PERUMAHAN RAKYAT DAN KAWASAN
PERMUKIMAN ACEH
SAWAH
MENGETAHUI / MENYETUJUI :
NAMA PEKERJAAN :
19.00
PEMBANGUNAN SALURAN DRAINASE
DUSUN AJUN GUCI GAMPONG JEUMPET AJUN
KEC. DARUL IMARAH KAB. ACEH BESAR
18.00
LOKASI PEKERJAAN :
17.00
Rencana Top Saluran KEC. DARUL IMARAH KAB. ACEH BESAR
14.00
13.00
12.00
TIM PERENCANA:
11.00
TANDA
PERSONIL NAMA
TANGAN
10.00 TEAM LEADER
Station E.0 E.1 E.2 E.3 E.4 E.5 E.6 CAD OPERATOR
14.855
14.905
14.806
14.669
14.663
14.460
Tanah
Asli SITUASI DAN
PENAMPANG MEMANJANG 1 : 1000
Rencana
14.370
14.316
14.245
14.169
14.118
14.063
13.860
CATATAN :
14.153
14.223
sal
as
15.035
as
sal
as
15.030
14.120
14.387
sal
sendimen
15.029
15.018
as
sal
sendimen
14.358
14.100
15.003
sal
14.136
cr
14.198
15.187
sal
as
p
p
14.991
14.069
14.980
15.220
pb3
sal
A-3
pb2
15.065
14.320
cr
14.474
cr
slop
15.296
14.228
cr
14.526
15.359
pndasi
cr
cr
14.470
14.480
cr
14.664
pb1
B-6
cr
13.843
13.777
cr
cr
14.217
14.442
cr
cr
14.829
14.837
cr
14.100
cr
14.670
14.552
cr
14.193
cr
14.473
cr
14.459
cr
14.315
p
14.070
13.972
S
cr
cr
14.070
14.420
cr 14.594
14.568
14.576
cr
p
cr
B-4
14.623
pndasi
14.501
p
15.544
4.763
as
15.035
14.665
bnang
cr
cr
14.805
C-1
cr
14.810
p
14.721
cr
14.648
cr
14.767
15.182
14.655
cr
B-3
15.000
cr
cr
14.726
sit
14.809
sit
14.727
14.814
14.783
14.404
sal
14.836
as
p
14.380
sal
as
14.793
B-0 B-2
as
14.465
15.007
15.061
14.721
cr
14.677
p
14.617
cr
15.068
14.978
14.478
D-2
sal
sal
cr
cr
15.016 as
r
14.812
15.092
cr
15.085
cr
14.897 cr
14.909
14.403
14.481
14.413
as
14.471
as
sal
as
14.446
14.902
14.888
cr
cr
14.548
as
14.901
14.509
15.089
14.428
14.439
14.433
plat
15.237 cr
14.458
as
as
cr
cr
14.839 cr
cr
t
14.550
15.070
14.966
plat
as
cr
14.385
15.067
cr
t
Start
15.000
p
15.036
14.999
MENGETAHUI / MENYETUJUI :
14.405
sal
MENGETAHUI :
14.378
plat
as
15.115
15.055
plat
as
14.393
14.820
15.049
14.363
p
as
sal
D-0
sal
sal
14.952
as
14.834
14.405
as
14.425
14.483
as
MENGETAHUI / MENYETUJUI : KEC. DARUL IMARAH KAB. ACEH BESAR
PPTK JASA KONSULTASI PERENCANAAN I ACEH
NAMA PEKERJAAN :
TIM PERENCANA:
Y= 610 900 Y= 610 900 Y= 610 900 Y= 610 900 Y= 610 900
LAYOUT 1 : 1500
TIM PERENCANA:
-
E-4
1 : 1500
Y= 610 800 Y= 610 800 Y= 610 800 Y= 610 800 Y= 610 800
-
X= 753 800
X= 753 900
X= 753 800
X= 753 900
as
14.223
sal
15.035
as
14.153
sal
15.030
14.120
sendimen
14.387
as
sal
15.029
14.358
15.018
sendimen sal
as
14.100
15.003
sal
14.069
sal
cr
p
14.198
15.187
p
14.991
14.136
as
15.220
14.980
pb3
sal
A-3
pb2
15.065
cr
14.320
14.474
15.296
cr
slop
14.228
cr
14.470
15.359
pndasi
cr
14.480
cr
14.526
14.664
pb1
A-2 B-5
13.843
cr
13.777
14.217
cr
cr
14.442
A-1
cr
14.829
14.837
cr
A-1
cr
14.100
14.552
cr
14.193 14.473
cr
cr
14.459
14.670
14.100
p
B-4
cr
cr
14.315
14.070
cr
cr
14.193
cr
14.552
13.972
14.473
cr
p
14.459
B-5
cr
14.670
cr
PEMERINTAH ACEH PEMERINTAH ACEH PEMERINTAH ACEH
cr
14.070
14.315
cr
13.972
N N
E
14.070
cr
cr
14.420
14.594
14.070
X= 753 800
X= 753 900
cr
14.568
p
14.576
cr
cr
14.420
cr
14.568
X= 753 700
cr
p
cr
14.576
14.594
42882 Fax : (0651) 41130 Banda Aceh 23236 42882 Fax : (0651) 41130 Banda Aceh 23236 42882 Fax : (0651) 41130 Banda Aceh 23236 42882 Fax : (0651) 41130 Banda Aceh 23236
14.223
14.153
sal
as
as
15.035
sendimen
15.029
14.387 15.030
sal
14.120
15.544
14.763
pndasi
sal
as
p14.623
14.501
15.035
14.805
cr
cr
bnang
14.665
as
p
15.544
B-4
pndasi
14.763
14.665
bnang
14.623
N
cr
15.035
cr
14.805
as
14.501
S
14.100
sal
as
15.018
sendimen
14.358
sal
15.003
E-1
14.198
15.187
14.991
14.136
sal
as
cr
p
p
14.069
sal
pb3
15.220 14.980
15.065
pb2
14.474
14.320
cr
slop
cr
15.296
cr
14.810
p
14.721
cr
14.648
W
GAMBAR BESTEK GAMBAR BESTEK GAMBAR BESTEK GAMBAR BESTEK
cr
14.228
14.480
14.526
14.721
14.648
cr
14.470
pndasi
15.359
cr
cr
14.810
pb1
14.664
cr
S S S
13.843
13.777
cr
cr
14.767
cr
14.217
14.655
cr
cr
14.829
cr
14.837
cr
14.767
B-3
14.655
15.182
C-0
cr
15.000
cr
cr
14.809
14.100
sit
sit
14.727 cr
cr
14.404
14.814
sal
14.836
as
p
cr
14.193
cr
14.552
14.473
cr
14.727
sal
as
14.783
14.793
14.380
p
14.459
B-5
cr
14.670
sit
14.809
sit
cr
14.726
14.315
14.814
as
14.465
cr
14.070
as
p
14.404
13.972
14.836
15.061
14.721
14.783
14.793
14.380
sal
cr
cr
as
sal
14.677
14.617
15.007
14.478
14.465
sal
cr
cr
cr
15.068 sal
15.016
as
as
B-2
p
14.978
15.061
14.677
15.068
14.617
r
14.812
cr
15.007 cr
cr
14.721
cr
sal
as
sal
14.978
14.478
15.016
p
cr
15.085
14.897
14.471
14.548
15.092
14.812
as
as
14.403 as
14.446
sal
14.888
cr
14.481 cr
14.909
cr
cr
cr
14.902
14.413
r
15.237
14.458
14.509
14.428
14.901
15.085
sal
tas
as
cr
cr
14.839
cr
cr
cr
15.089
14.439
15.070
14.966
14.433
14.446
14.888
14.909
14.897
plat
plat
as
sal
as
cr
14.550
14.385
cr
as
14.471 as
14.403 cr
14.481
cr
cr
cr
15.092
as
14.548
14.902
14.839
sal
15.067
cr
14.413
15.237
as
as
cr
14.458
14.509
cr
cr
14.901
t
14.428
14.550
14.385
plat
15.089
as
cr
14.439
plat
15.070
as
cr
cr
14.433
14.966
15.067
cr
t
Start
15.000
14.070
15.000
Start
cr
14.420
p
15.036
cr
14.568
14.576
X= 753 600
cr
cr
p
14.594
p
14.999
p
15.036
14.405
sal
p
14.999
sal
14.405
D-1
15.544
14.763
pndasi
B-4
14.501
p 14.623
14.665
bnang
cr
15.035
cr
14.805
as
p
as
14.378
plat
15.115
14.810
14.721
14.648
14.378
15.115
plat
cr
as
p
cr
PEMBERI TUGAS PEMBERI TUGAS PEMBERI TUGAS PEMBERI TUGAS
plat
15.055
as
14.393
15.055
14.393
plat
as
E-5
p
15.049
14.363
14.820
14.405
D-0
sal
sal
14.952 14.834
as
cr
14.767
B-3
15.182
14.655
15.049
cr
15.000
cr
cr
p
14.952
14.834
14.363
14.820
sal
sal
sal
as
14.405
14.726
14.727
E-6
sit
14.809
sit
cr
14.814
sal
as
p
14.404
14.836
14.783
14.793
14.380
sal
as
14.465
as
as
14.425
B-2 cr
15.061 14.721
14.677
14.617
15.068
sal
cr
15.007
cr
cr
cr
as
sal
14.978
14.478
15.016
as
14.425
15.085
cr
14.897
14.446
as
14.471 as
14.403
sal
as
14.888 cr
14.481
cr
14.909
14.548
cr
cr
15.092
14.902
14.413
14.839
sal
as
15.237
as
cr
14.458
14.509 cr
14.428
cr
cr
14.901
14.550
14.385
plat
15.089
as
14.439
plat
15.070
as
cr
cr
14.433
14.966
15.067
PERMUKIMAN ACEH PERMUKIMAN ACEH PERMUKIMAN ACEH PERMUKIMAN ACEH
cr
t
15.000
Start
14.483
as
p
15.036
p
14.999
14.483
as
sal
14.405
D-1
14.378
15.115
plat
as
X= 753 800
X= 753 900
15.055
14.393
plat
as
15.049
p
14.363
14.820
14.952
14.834
sal
sal
as
14.405
X= 753 900
TEAM LEADER 10.00 10.00 TEAM LEADER 10.00 10.00 TEAM LEADER 10.00 TEAM LEADER
NAMA GAMBAR : SKALA : NAMA GAMBAR : SKALA : NAMA GAMBAR : SKALA : NAMA GAMBAR : SKALA :
40.70 18.00 18.70 16.10 17.00 23.00 11.00 6.50 21.80 17.50 11.70 12.70 18.00 23.00 12.00 33.00 44.00 47.00 21.00 34.00 27.00
14.385
14.721
14.655
14.576
14.228
14.814
14.363
14.669
SITUASI DAN SITUASI DAN SITUASI DAN
E-1
14.270
14.194
14.342
14.320
14.363
14.118
2022 - 2022 - 2022 - 2022 -
E-4
X= 753 800
X= 753 900
E-5
SAWAH
X= 753 800
X= 753 900
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - I 0.25 0.90 0.25 Type - I GAMBAR BESTEK
15 15 CATATAN :
0.80
1.30
0.20
14 0.30 14
0.35 0.70 0.35
1.40
1.00
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.131
14.070
14.420
14.594
14.650
14.017
14.100
14.193
14.315
14.070
13.972
13.852
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
0.85
0.21
0.53
JARAK (m) 1.95 1.05 0.80 2.20 JARAK (m) 1.13 1.02 2.26
MENGETAHUI / MENYETUJUI :
14.270
14.230
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
A+000 A+040.7
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14 14
13 13
12 12
13.843
13.777
14.217
14.442
14.829
14.837
14.856
14.047
14.099
14.228
14.526
15.359
15.496
15.532
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
TEAM LEADER
0.66
0.59
0.78
0.75
0.80
0.56
1.75 0.67 1.60 1.12 1.24 1.32 AHLI STRUKTUR
JARAK (m) JARAK (m)
NAMA GAMBAR : SKALA :
14.213
14.194
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
14.812 DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.481
14.446
15.237
14.897
14.839
14.550
14.385
15.067
14.860
15.299
15.237
14.949
15.088
15.004
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
0.34
0.32
0.98
0.55
0.27
0.43
JARAK (m) 1.44 1.22 1.44 1.24 JARAK (m) 1.20 1.36 1.21
14.400 MENGETAHUI / MENYETUJUI :
14.342
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
B+000 B+023
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14 14
13 13
12 12
14.897
14.839
14.550
14.385
15.067
15.088
15.004
15.216
15.061
14.677
14.721
15.068
15.148
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
TEAM LEADER
0.98
0.55
0.27
0.43
0.30
0.35
0.20
1.20 1.36 1.21 1.35 1.80 AHLI STRUKTUR
JARAK (m) JARAK (m)
NAMA GAMBAR : SKALA :
14.342
14.315
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
B+023' B+034
TAHUN NO GAMBAR : JLH GAMBAR
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - IV Type - III
GAMBAR BESTEK
15 15 CATATAN :
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
15.000
14.655
15.182
15.035
14.805
14.665
14.501
14.623
15.544
15.296
15.251
15.149
15.278
15.369
15.381
15.206
15.163
15.709
15.613
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
0.43
0.39
0.54
0.34
0.66
0.28
0.36
0.37
0.12
JARAK (m) 1.34 0.84 0.92 1.20 JARAK (m) 0.99 0.71 1.27 1.24
14.301 MENGETAHUI / MENYETUJUI :
14.256
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
B+040.5 B+062.3
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14 14
13 13
12 12
14.480
14.470
15.359
15.284
15.166
14.916
15.627
15.539
15.252
15.088
14.880
15.529
15.456
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
TEAM LEADER
0.44
0.45
0.24
0.55
0.40
0.11
1.14 0.96 1.44 1.32 1.53 0.67 1.29 1.45 AHLI STRUKTUR
JARAK (m) JARAK (m)
NAMA GAMBAR : SKALA :
14.219
14.194
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
B+079.8 B+091.5
TAHUN NO GAMBAR : JLH GAMBAR
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - II Type - II GAMBAR BESTEK
15 15 CATATAN :
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.171
14.211
14.320
14.474
15.296
15.475
15.440
14.232
14.136
14.069
14.980
14.990
14.961
14.193
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
0.65
0.25
0.29
0.41
JARAK (m) 1.49 1.06 1.23 1.32 JARAK (m) 1.41 1.30 1.28 1.31
14.179 MENGETAHUI / MENYETUJUI :
14.162
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
A+093.5 A+110.5
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
KONSULTAN PERENCANA:
TIM PERENCANA:
TANDA
PERSONIL NAMA
TANGAN
TEAM LEADER
AHLI STRUKTUR
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - IV Type - IV GAMBAR BESTEK
15 15 CATATAN :
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.809
14.814
14.726
14.810
14.721
14.648
14.824
14.882
14.610
14.505
14.843
14.878
14.522
14.447
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
0.52
0.83
0.63
0.70
JARAK (m) 1.35 1.13 0.78 1.39 JARAK (m) 1.29 1.08 0.99 1.31
14.320 MENGETAHUI / MENYETUJUI :
14.299
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
C+000 C+012.7
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14
13
12
Bidang persamaan
11
Reference level
10.00 TIM PERENCANA:
TANDA
14.568
14.576
14.594
14.555
14.615
14.457
14.315
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI
TEAM LEADER
0.72
0.47
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - V Type - V
GAMBAR BESTEK
15 15 CATATAN :
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.867
14.856
14.820
14.363
15.049
14.910
14.899
14.863
14.405
14.863
14.897
14.911
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
0.25
0.50
0.40
0.35
JARAK (m) 4.00 0.55 JARAK (m) 4.00 0.55 1.00
MENGETAHUI / MENYETUJUI :
14.363
14.334
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
D+000 D+023
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14
13
12
Bidang persamaan
11
Reference level
10.00 TIM PERENCANA:
TANDA
15.121
15.091
15.016
14.478
14.978
14.651
14.610
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI
TEAM LEADER
0.35
0.35
0.35
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - V Type - V GAMBAR BESTEK
15 15 CATATAN :
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
15.031
15.005
14.970
14.979
14.967
14.879
14.832
14.855
14.874
14.902
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
JARAK (m) 1.50 1.00 1.00 1.50 JARAK (m) 1.50 1.20 0.80 1.30
MENGETAHUI / MENYETUJUI :
14.370
14.316
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
E+000 E+033
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14 14
13 13
12 12
14.879
14.905
14.937
14.958
14.777
14.830
14.806
14.818
14.883
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
TEAM LEADER
0.91 1.30 1.00 1.38 1.35 1.00 0.77 1.16 AHLI STRUKTUR
JARAK (m) JARAK (m)
NAMA GAMBAR : SKALA :
14.245
14.169
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
E+077 E+124
TAHUN NO GAMBAR : JLH GAMBAR
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
16 16
Type - V Type - V
GAMBAR BESTEK
15 15 CATATAN :
14 14
13 13
12 12
PEMBERI TUGAS
Bidang persamaan Bidang persamaan MENGETAHUI :
11 11
Reference level Reference level KUASA PENGGUNA ANGGARAN
10.00 10.00 PROGRAM PENINGKATAN PRASARANA, SARANA DAN
UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
14.677
14.647
14.669
14.699
14.720
14.703
14.720
14.663
14.619
14.602
ELEVASI TANAH ASLI ELEVASI TANAH ASLI PERMUKIMAN ACEH
JARAK (m) 1.30 1.25 1.25 1.30 JARAK (m) 1.75 0.88 1.26 1.35
MENGETAHUI / MENYETUJUI :
14.118
14.063
PPTK JASA KONSULTASI PERENCANAAN I ACEH
ELEVASI RENCANA SALURAN ELEVASI RENCANA SALURAN
E+155 E+189
NAMA PEKERJAAN :
LOKASI PEKERJAAN :
14
13
12
Bidang persamaan
11
Reference level
10.00 TIM PERENCANA:
TANDA
14.447
14.460
14.492
14.496
14.375
PERSONIL NAMA
TANGAN
ELEVASI TANAH ASLI
TEAM LEADER
E+216
TAHUN NO GAMBAR : JLH GAMBAR
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
GAMBAR BESTEK
30 25 90 25 30 30 25 90 CATATAN :
Timbunan
Plesteran Plesteran
80
80
PEMBERI TUGAS
1.30 MENGETAHUI :
Pipa PVC 3/4"
KUASA PENGGUNA ANGGARAN
Pipa PVC 3/4" Jarak 2 m PROGRAM PENINGKATAN PRASARANA, SARANA DAN
20
20
Jarak 2 m UTILITAS UMUM (PSU)
DINAS PERUMAHAN RAKYAT DAN KAWASAN
PERMUKIMAN ACEH
30
30
MENGETAHUI / MENYETUJUI :
100
Ceurucuk Ø 10 cm
P = 1 m, Jarak 1 m
Ceurucuk Ø 10 cm
P = 1 m, Jarak 1 m
NAMA PEKERJAAN :
KONSULTAN PERENCANA:
25 65 25 70 25
Plesteran
Plesteran
Pas. Batu
Pas. Batu
80
80
10 20
TANDA
PERSONIL NAMA
TANGAN
TEAM LEADER
AHLI STRUKTUR
30 60 30 60 30 SKALA :
NAMA GAMBAR :
2022 -
PEMERINTAH ACEH
DINAS PERUMAHAN RAKYAT DAN
KAWASAN PERMUKIMAN ACEH
JL. Pemancar No. 5 Simpang Tiga Telp : (0651)
42882 Fax : (0651) 41130 Banda Aceh 23236
GAMBAR BESTEK
CATATAN :
PEMBERI TUGAS
MENGETAHUI :
Ø12-150
25 60 25
MENGETAHUI / MENYETUJUI :
20
Plesteran PPTK JASA KONSULTASI PERENCANAAN I ACEH
60
Pipa PVC 3/4"
NAMA PEKERJAAN :
Jarak 2 m
10 20
10 20
PEMBANGUNAN SALURAN DRAINASE
DUSUN AJUN GUCI GAMPONG JEUMPET AJUN
KEC. DARUL IMARAH KAB. ACEH BESAR
LOKASI PEKERJAAN :
30 50 30 30 50 30
KEC. DARUL IMARAH KAB. ACEH BESAR
KONSULTAN PERENCANA:
DETAIL TYPE - V DETAIL PLAT SALURAN
SKALA 1 : 25 SKALA 1 : 25
TIM PERENCANA:
TANDA
PERSONIL NAMA
TANGAN
TEAM LEADER
AHLI STRUKTUR
DETAIL 1 : 25
2022 -