HARGA
NO URAIAN PEKERJAAN
UPAH BAHAN JUMLAH
PEKERJAAN PERSIAPAN
1 m2 membersihkan lapangan
Tenaga
0.1 OH Pekerja @ Rp. 110,000.00 11,000.00
0.05 OH mandor @ Rp. 135,000.00 6,750.00
JUMLAH 17,750.00
Tenaga
0.100 org Tukang kayu @ Rp. 135,000.00 13,500.000
0.010 org Kepala tukang kayu @ Rp. 150,000.00 1,500.000
0.100 org Pekerja @ Rp. 110,000.00 11,000.000
0.005 org Mandor @ Rp. 135,000.00 675.000
@ Rp. 380,000.00
JUMLAH 39,250.00 39,250.00
PEKERJAAN PONDASI
Tenaga
0.780 OH pekerja @ Rp. 110,000.00 85,800.000
0.390 OH tukang batu @ Rp. 135,000.00 52,650.000
0.040 OH kepala tukang @ Rp. 150,000.00 6,000.000
0.040 OH mandor @ Rp. 135,000.00 5,400.000
JUMLAH 149,850.000 270,000.00 419,850.000
Bahan
1.200 m3 batu belah 15-20 cm @ Rp. 225,000.00 270,000.00
202.00 kg portland semen @ Rp. 20,000.00 4,040,000.00
0.485 m3 pasir pasang @ Rp. 160,000.00 77,600.00
tenaga
1.500 OH pekerja @ Rp. 110,000.00 165,000.00
0.600 OH tukang batu @ Rp. 135,000.00 81,000.00
0.060 OH kepala tukang @ Rp. 150,000.00 9,000.00
0.075 OH mandor @ Rp. 135,000.00 10,125.00
PEKERJAAN BETON
Bahan
276.00 kg portland semen @ Rp. 20,000.00 5,520,000.00
0.59143 m3 pasir pasang @ Rp. 160,000.00 94,628.80
0.74963 m3 batu pecah 2-3 cm @ Rp. 265,000.00 198,651.95
Tenaga
1.65 OH pekerja @ Rp. 110,000.00 181,500.00
0.275 OH tukang batu @ Rp. 135,000.00 37,125.00
0.028 OH kepala tukang @ Rp. 150,000.00 4,200.00
0.083 OH mandor @ Rp. 135,000.00 11,205.00
Bahan
10.50 kg besi beton @ Rp. 17,500.00 183,750.00
0.150 kg kawat beton @ Rp. 20,610.00 3,091.50
tenaga
0.070 OH pekerja @ Rp. 110,000.00 7,700.000
0.070 OH tukang besi @ Rp. 135,000.00 9,450.000
0.007 OH kepala tukang @ Rp. 150,000.00 1,050.000
0.004 OH mandor @ Rp. 135,000.00 540.000
Bahan
0.040 m3 kayu kelas III @ Rp. 3,850,000.00 154,000.000
0.300 kg paku biasa @ Rp. 24,000.00 7,200.000
0.100 liter minyak begisting @ Rp. 29,000.00 2,900.000
Tenaga
0.300 OH pekerja @ Rp. 110,000.00 33,000.000
0.260 OH tukang kayu @ Rp. 135,000.00 35,100.000
0.026 OH kepala tukang @ Rp. 150,000.00 3,900.000
0.005 OH mandor @ Rp. 135,000.00 675.000
Bahan
0.27 m3 kayu kelas III @ Rp. 3,850,000.00 1,039,500.00
0.200 kg paku biasa @ Rp. 24,000.00 4,800.00
0.600 liter minyak begisting @ Rp. 29,000.00 17,400.00
157.500 kg besi beton polos @ Rp. 17,500.00 2,756,250.00
2.260 kg kawat beton @ Rp. 20,610.00 46,578.60
336.000 kg portland semen @ Rp. 20,000.00 6,720,000.00
3.500 lbr tripleks @ Rp. 170,000.00 595,000.00
0.540 m3 pasir pasang @ Rp. 160,000.00 86,400.00
0.810 m3 kerikil beton @ Rp. 180,000.00 145,800.00
Tenaga
4.850 OH pekerja @ Rp. 110,000.00 533,500.000
0.350 OH tukang batu @ Rp. 135,000.00 47,250.000
1.560 OH tukang kayu @ Rp. 135,000.00 210,600.000
1.400 OH tukang besi @ Rp. 135,000.00 189,000.000
0.331 OH kepala tukang @ Rp. 150,000.00 49,650.000
0.17 OH mandor @ Rp. 135,000.00 22,950.000
Bahan
0.320 m3 kayu kelas III @ Rp. 3,850,000.00 1,232,000.000
3.200 kg paku biasa @ Rp. 24,000.00 76,800.000
1.600 liter minyak bekisting @ Rp. 29,000.00 46,400.000
157.500 besi beton polos @ Rp. 17,500.00 2,756,250.000
2.250 kawat beton @ Rp. 20,610.00 46,372.500
336.000 portland cement @ Rp. 20,000.00 6,720,000.000
0.540 pasir pasang @ Rp. 160,000.00 86,400.000
0.810 kerikil beton @ Rp. 180,000.00 145,800.000
0.120 kayu kelas III balok @ Rp. 3,850,000.00 462,000.000
2.800 tripleks @ Rp. 170,000.00 476,000.000
Tenaga
5.300 OH pekerja @ Rp. 110,000.00 583,000.000
0.275 OH tukang batu @ Rp. 135,000.00 37,125.000
1.300 OH tukang kayu @ Rp. 135,000.00 175,500.000
1.050 OH tukang besi @ Rp. 135,000.00 141,750.000
0.265 OH kepala tukang @ Rp. 150,000.00 39,750.000
0.265 OH mandor @ Rp. 135,000.00 35,775.000
JUMLAH 1,012,900.000 12,048,022.500 13,060,922.500
Bahan
0.320 m3 papan kayu kelas III @ Rp. 3,850,000.00 1,232,000.00
3.200 kg paku biasa @ Rp. 24,000.00 76,800.00
1.600 liter minyak bekisting @ Rp. 29,000.00 46,400.00
105.000 kg besi beton polos @ Rp. 17,500.00 1,837,500.00
1.500 kg kawat beton @ Rp. 20,610.00 30,915.00
336.000 kg portland cement @ Rp. 20,000.00 6,720,000.00
0.540 m3 pasir pasang @ Rp. 160,000.00 86,400.00
0.810 m3 kerikil beton @ Rp. 180,000.00 145,800.00
0.140 m3 kayu kelas III balok @ Rp. 3,850,000.00 539,000.00
2.800 lbr tripleks @ Rp. 170,000.00 476,000.00
Tenaga
5.650 OH pekerja @ Rp. 110,000.00 621,500.000
0.275 OH tukang batu @ Rp. 135,000.00 37,125.000
1.560 OH tukang kayu @ Rp. 135,000.00 210,600.000
1.400 OH tukang besi @ Rp. 135,000.00 189,000.000
0.323 OH kepala tukang @ Rp. 150,000.00 48,450.000
0.283 OH mandor @ Rp. 135,000.00 38,205.000
PEKERJAAN DINDING
Bahan
70.000 buah bata merah @ Rp. 900.00 63,000.000
14.370 kg portland cement @ Rp. 20,000.00 287,400.000
0.040 m3 pasir pasang @ Rp. 160,000.00 6,400.000
Tenaga
0.300 OH pekerja @ Rp. 110,000.00 33,000.000
0.100 OH tukang batu @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.015 OH mandor @ Rp. 135,000.00 2,025.000
PEKERJAAN PLESTERAN
Bahan
10.224 kg portland cement @ Rp. 20,000.00 204,480.00
0.020 m3 pasir pasang @ Rp. 160,000.00 3,200.00
Tenaga
0.300 OH pekerja @ Rp. 110,000.00 33,000.00
0.150 OH tukang batu @ Rp. 135,000.00 20,250.00
0.015 OH kepala tukang @ Rp. 150,000.00 2,250.00
0.015 OH mandor @ Rp. 135,000.00 2,025.00
PEKERJAAN KAYU
membuat dan memasang 1 m3 kusen pintu dan kusen jendela ,kayu kelas II
Bahan
1.200 m3 balok kayu kelas II @ Rp. 3,850,000.00 4,620,000.000
1.250 kg paku 10 cm @ Rp. 20,000.00 25,000.000
1.000 kg lem kayu @ Rp. 18,000.00 18,000.000
Tenaga
6.000 OH pekerja @ Rp. 110,000.00 660,000.000
18.000 OH tukang kayu @ Rp. 135,000.00 2,430,000.000
1.800 OH kepala tukang @ Rp. 150,000.00 270,000.000
0.300 OH mandor @ Rp. 135,000.00 40,500.000
Bahan
0.0154 m3 kaso-kaso (5 x 7)cm @ Rp. 7,800,000.00 120,120.00
0.200 kg paku biasa @ Rp. 240,000.00 48,000.00
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.200 OH tukang kayu @ Rp. 135,000.00 27,000.000
0.020 OH kepala tukang @ Rp. 150,000.00 3,000.000
0.005 OH mandor @ Rp. 135,000.00 675.000
Tenaga
0.620 OH pekerja @ Rp. 110,000.00 68,200.000
0.350 OH tukang batu @ Rp. 135,000.00 47,250.000
0.035 OH kepala tukang @ Rp. 150,000.00 5,250.000
0.030 OH mandor @ Rp. 135,000.00 4,050.000
Bahan
25.000 buah lantai keramik @ Rp. 7,280.00 182,000.000
10.400 kg portland cement @ Rp. 20,000.00 208,000.000
0.045 m3 pasir pasang @ Rp. 160,000.00 7,200.000
11.620 kg semen warna @ Rp. 62,000.00 720,440.000
Tenaga
0.620 OH pekerja @ Rp. 110,000.00 68,200.000
0.350 OH tukang batu @ Rp. 135,000.00 47,250.000
0.035 OH kepala tukang @ Rp. 150,000.00 5,250.000
0.030 OH mandor @ Rp. 135,000.00 4,050.000
Bahan
20.000 buah lantai keramik @ Rp. 7,280.00 145,600.000
10.400 kg portland cement @ Rp. 20,000.00 208,000.000
0.045 m3 pasir pasang @ Rp. 160,000.00 7,200.000
1.620 kg semen warna @ Rp. 62,000.00 100,440.000
Tenaga
0.620 OH pekerja @ Rp. 110,000.00 68,200.000
0.350 OH tukang batu @ Rp. 135,000.00 47,250.000
0.035 OH kepala tukang @ Rp. 150,000.00 5,250.000
0.030 OH mandor @ Rp. 135,000.00 4,050.000
PEKERJAAN LANGIT-LANGIT
Bahan
0.364 m3 kayu papan kelas III @ Rp. 3,850,000.00 1,401,400.00
0.110 kg papan tripleks @ Rp. 170,000.00 18,700.00
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.00
0.050 OH tukang batu @ Rp. 135,000.00 6,750.00
0.005 OH kepala tukang @ Rp. 150,000.00 750.00
0.005 OH mandor @ Rp. 135,000.00 675.00
PEKERJAAN ATAP
Bahan
0.014 m3 kayu jati balok @ Rp. 3,850,000.00 53,900.00
0.036 m3 reng (2 x3 ) cm @ Rp. 3,500,000.00 126,000.00
0.25 kg paku biasa @ Rp. 24,000.00 6,000.00
Tenaga
0.060 OH pekerja @ Rp. 110,000.00 6,600.000
0.006 OH tukang kayu @ Rp. 135,000.00 810.000
0.006 OH kepala tukang @ Rp. 150,000.00 900.000
0.003 OH mandor @ Rp. 135,000.00 405.000
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.2 OH tukang kayu @ Rp. 135,000.00 27,000.000
0.02 OH kepala tukang @ Rp. 150,000.00 3,000.000
0.005 OH mandor @ Rp. 135,000.00 675.000
pasang 1 titik instalasi penerangan dan stop kontak dengan kabelnya 3 x 2.5 m
Bahan
9.000 m' kabel NYA 3 X 2.5 mm2 @ Rp. 33,000.00 297,000.000
3.000 btg condult @ Rp. 9,350.00 28,050.000
1.000 ls alat bantu @ Rp. 25,000.00 25,000.000
Tenaga
0.250 OH pekerja @ Rp. 110,000.00 27,500.000
0.250 OH tukang listrik @ Rp. 135,000.00 33,750.000
0.025 OH kepala tukang @ Rp. 150,000.00 3,750.000
0.025 OH mandor @ Rp. 135,000.00 3,375.000
Bahan
1.000 bh lampu pijar 25 watt @ Rp. 143,000.00 143,000.000
1.000 Ls alat bantu @ Rp. 25,000.00 25,000.000
tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.100 OH tukang listrik @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.001 OH mandor @ Rp. 135,000.00 135.000
Bahan
1.000 bh lampu TL @ Rp. 143,000.00 143,000.000
1.000 ls alat bantu @ Rp. 25,000.00 25,000.000
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.100 OH tukang listrik @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.001 OH mandor @ Rp. 135,000.00 135.000
Bahan
1.000 bh stop kontak @ Rp. 181,500.00 181,500.000
1.000 Ls alat bantu @ Rp. 25,000.00 25,000.000
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.100 OH tukang listrik @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.001 OH mandor @ Rp. 135,000.00 135.000
Bahan
1.000 bh saklar tunggal @ Rp. 22,000.00 22,000.000
1.000 Ls alat bantu @ Rp. 25,000.00 25,000.000
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.100 OH tukang listrik @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.001 OH mandor @ Rp. 135,000.00 135.000
Bahan
1.000 bh saklar ganda @ Rp. 187,000.00 187,000.000
1.000 Ls alat bantu @ Rp. 25,000.00 25,000.000
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.100 OH tukang listrik @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.001 OH mandor @ Rp. 135,000.00 135.000
PEKERJAAN SANITASI
Bahan
1.000 bh kloset jongkok setara TOTO @ Rp. 170,000.00 170,000.00
6.000 kg semen portland @ Rp. 20,000.00 120,000.000
0.010 m3 pasir pasang @ Rp. 160,000.00 1,600.000
Tenaga
0.100 OH pekerja @ Rp. 110,000.00 11,000.000
0.100 OH tukang listrik @ Rp. 135,000.00 13,500.000
0.010 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.001 OH mandor @ Rp. 135,000.00 135.000
Tenaga
1.200 OH pekerja @ Rp. 110,000.00 132,000.000
1.450 OH tukang batu @ Rp. 135,000.00 195,750.000
0.150 OH kepala tukang @ Rp. 150,000.00 22,500.000
0.100 OH mandor @ Rp. 135,000.00 13,500.000
Bahan
1.000 bak fiberglass @ Rp. 480,000.00 480,000.000
20% dari harga bak perlengkapan @ Rp. 96,000.00 96,000.00
Tenaga
1.800 OH pekerja @ Rp. 110,000.00 198,000.000
0.540 OH tukang batu @ Rp. 135,000.00 72,900.000
0.054 OH kepala tukang @ Rp. 150,000.00 8,100.000
0.110 OH mandor @ Rp. 135,000.00 14,850.000
Tenaga
1.800 OH pekerja @ Rp. 110,000.00 198,000.000
0.540 OH tukang @ Rp. 135,000.00 72,900.000
0.054 OH kepala tukang @ Rp. 150,000.00 8,100.000
0.110 OH mandor @ Rp. 135,000.00 14,850.000
Bahan
1.200 m2 pipa PVC tipe AW Ø3" @ Rp. 25,000.00 30,000.00
Tenaga
0.081 OH pekerja @ Rp. 110,000.00 8,910.00
0.135 OH tukang batu @ Rp. 135,000.00 18,225.00
0.0135 OH kepala tukang @ Rp. 150,000.00 2,025.00
0.041 OH mandor @ Rp. 135,000.00 5,535.00
Bahan
1.200 m2 pipa PVC tipe AW Ø4" @ Rp. 11,000.00 13,200.000
Tenaga
0.081 OH pekerja @ Rp. 110,000.00 8,910.00
0.135 OH tukang batu @ Rp. 135,000.00 18,225.00
0.0135 OH kepala tukang @ Rp. 150,000.00 2,025.00
0.041 OH mandor @ Rp. 135,000.00 5,535.00
PEKERJAAN PINTU
Bahan
1.000 bh kunci tanam @ Rp. 9,900.00 9,900.00
Tenaga
0.010 OH pekerja @ Rp. 110,000.00 1,100.000
0.500 OH tukang kayu @ Rp. 135,000.00 67,500.000
0.0100 OH kepala tukang @ Rp. 150,000.00 1,500.000
0.005 OH mandor @ Rp. 135,000.00 675.000
Bahan
1.000 bh engsel pintu @ Rp. 16,000.00 16,000.000
Tenaga
0.015 OH pekerja @ Rp. 110,000.00 1,650.00
0.150 OH tukang kayu @ Rp. 135,000.00 20,250.00
0.0150 OH kepala tukang @ Rp. 150,000.00 2,250.00
0.001 OH mandor @ Rp. 135,000.00 101.25
Bahan
1.000 psg engsel jendela @ Rp. 12,500.00 12,500.000
Tenaga
0.010 OH pekerja @ Rp. 110,000.00 1,100.00
0.100 OH tukang kayu @ Rp. 135,000.00 13,500.00
0.0100 OH kepala tukang @ Rp. 150,000.00 1,500.00
0.0005 OH mandor @ Rp. 135,000.00 67.50
PENGERJAAN PENGECATAN
bahan
0.15 kg cat kayu kilat @ Rp. 75,000.00 11,250.00
0.05 kg cat kayu dasar @ Rp. 37,000.00 1,850.00
0.100 lbr amplas @ Rp. 3,960.00 396.00
0.010 Bh kuas @ Rp. 24,750.00 247.50
Tenaga
0.180 OH pekerja @ Rp. 110,000.00 19,800.00
0.160 OH tukang cat @ Rp. 135,000.00 21,600.00
0.0160 OH kepala tukang @ Rp. 150,000.00 2,400.00
0.0025 OH mandor @ Rp. 135,000.00 337.50
bahan
0.1 kg plamir @ Rp. 17,500.00 1,750.00
0.11 kg cat dasar @ Rp. 37,000.00 4,070.00
0.26 kg cat tembok @ Rp. 90,000.00 23,400.00
Tenaga
0.180 OH pekerja @ Rp. 110,000.00 19,800.00
0.160 OH tukang cat @ Rp. 135,000.00 21,600.00
0.0160 OH kepala tukang @ Rp. 150,000.00 2,400.00
0.0025 OH mandor @ Rp. 135,000.00 337.50