RAB PEKERJAAN KRIS ( Kelas Rawat Inap Standart ) RUANG PINANG
RUMAH SAKIT UMUM SRI PAMELA
No Uraian Pekerjaan Vol Satuan Harga Satuan Jumlah Harga
I Pekerjaan Pendahuluan Bongkaran Plaster Dinding 1 m³ 245,000 245,000
Sub Total 245,000
II Pekerjaan Sentral Oksigen dan Nurse Call Sentral Oksigen 1 lot 11,725,000 11,725,000 Sistem Alarm Oksigen 1 lot 13,860,000 13,860,000 Outlet Oksigen + Flow Meter + Stop Kontak dan Wall duck 17 set 5,119,000 87,023,000 Regulator Oksigen 17 set 825,000 14,025,000 NC Sistem 30 Gates 1 set 8,000,000 8,000,000 Nurse Call + Instalasi 17 set 421,000 7,157,000 Bell Kamar Mandi + Instalasi 4 set 280,000 1,120,000 Hallway Display 2 set 4,500,000 9,000,000
Sub Total 151,910,000
III Pekerjaan Instalasi Listrik dan AC Bola Lampu XL 45W 17 bh 67,000 1,139,000 Sakelar Tunggal ( Voltama ) 3 set 23,000 69,000 Fitting Lampu 6 bh 16,700 100,200 Kabel NYM 2 x 1,5 mm ( Lestari ) 3 roll 420,000 1,260,000 Kabel NYA 2,5 mm ( Praba ) 1 roll 621,000 621,000 Pipa 17 mm P. 5 Meter 12 btg 13,000 156,000 MCB Schneider 32 Ampere + Box 4 bh 148,000 592,000 AC Split 1 PK AUX 6 unit 4,325,000 25,950,000
Sub Total 29,887,200
IV Pekerjaan Pengecatan Dinding Cat Air Danabryte Cream 50 kg 44,000 2,200,000 Kuas 4" 4 bh 37,500 150,000 Pasir 1 m³ 167,000 167,000 Semen @40 kg 6 zak 67,000 402,000 Cat Minyak 6 kg 64,000 384,000 Thinner 3 ltr 22,500 67,500 Semen Putih 10 kg 7,500 75,000
Sub Total 3,445,500
IV Pekerjaan Lain - Lain Hygrometer Thermoter HTC - 1 4 bh 316,000 1,264,000 Pegangan Kamar mandi Stainless 40 cm 4 bh 128,000 512,000
Sub Total 1,776,000
TOTAL 187,018,700 UPAH KERJA 28,297,805 TOTAL + UPAH KERJA 215,316,505 PPN ( 11% ) 23,684,816 TOTAL BIAYA 239,001,321