RAB PEKERJAAN RENOVASI POLI GIGI MENJADI RUANG TUNGGU

DAN RENOVASI FARMASI KRONIS MENJADI POLI GIGI


RUMAH SAKIT UMUM SRI PAMELA

No Uraian Pekerjaan Vol Satuan Harga Satuan Jumlah Harga

I Pekerjaan Pendahuluan
Bongkaran Dinding Tembok 22 mtr² 30,000 660,000
Bongkaran Kosen Pintu dan Kosen Jendela 9 mtr² 30,000 270,000
Bongkaran Lantai 2 mtr³ 152,000 304,000
Bongkar pasang out door AC 1 unit 150,000 150,000

Sub Total 1,384,000


II Pekerjaan Dinding, Lantai & Kamar Mandi
Granit 60 x 60 cm 34 ktk 21,500 731,000
Batu Bata 600 bh 575 345,000
Semen @40 kg Tiga Roda 14 zak 60,950 853,300
Pintu Kamar Mandi Aluminium 70 x 200 cm 1 set 852,000 852,000
Semen Putih 2 kg 9,350 18,700
Tepung Dempul Keramik 4 bks 9,350 37,400
Kramik 30 x 60 cm 2 ktk 97,000 194,000
Kramik 30 x 30 cm 7 ktk 72,000 504,000
Tanah timbun 2 mtr³ 130,000 260,000
Cat air Danabrite Cream 5 kg 44,000 220,000
Cat air Paragon Putih 5 kg 37,000 185,000
Kosen jendela kamar mandi uk 50 x 50 cm 1 set 127,000 127,000
Kuas 4 inch 1 bh 36,800 36,800
-
Sub Total 4,364,200
III Pekerjaan Pemasangan Kaca, Pintu HPL dan pagar stainless
Dinding Kaca 5 mm + Rangka Aluminium 6 mtr² 520,000 3,120,000
Kaca Tempered 10 mm 6 mtr² 1,200,000 7,200,000
Sekat Partisi + Pintu ( HPL ) uk. 3 x 1,5 mtr 1 set 1,950,000 1,950,000
Pintu Stainless Stell uk 94 x 60 cm 2 bh 425,000 850,000
Pagar Stainless Stell uk 94 cm 4 mtr 480,000 1,920,000

Sub Total 15,040,000


IV Pekerjaan Wallpaper Ruang Tunggu dan Poli Gigi
Wallpaper ( dynasti ) 22 roll 197,000 4,334,000

Sub Total 4,334,000


V Pekerjaan Pemipaan Saluran Air dan Wastafel
Pipa PVC 1/2" Rucika 15 btg 48,000 720,000
Elbow PVC 1/2 '' Rucika 20 bh 4,000 80,000
Pipa PVC 1 1/4" Rucika 2 btg 52,000 104,000
Tandon Air Pinguin 1050 L 1 bh 2,185,000 2,185,000
Lem pipa PVC 4 bh 7,000 28,000
Tee PVC 1/2 inch 5 bh 4,000 20,000

Sub Total 3,137,000


VI Pekerjaan Instalasi Listrik
Bola lampu xl 23 watt 1 bh 31,000 31,000
Fiting lampu voltama 1 bh 15,000 15,000
Lampu led hannoch 20 watt 6 '' 4 bh 92,000 368,000
Kabel NYA 1,5 mm 1 rol 385,000 385,000
Pipa 17 mm 6 btg 14,000 84,000
Saklar Panasonic 3 set 25,000 75,000

Sub Total 958,000


TOTAL 27,833,200
UPAH KERJA 5,558,980
TOTAL + UPAH KERJA 33,392,180
PPN ( 11% ) 3,673,140
TOTAL BIAYA 37,065,320

Tebing Tinggi, 2022

Diperiksa Oleh : Dibuat Oleh :

Agnes Delvina Tarigan M. Ilham, Nst


Kasi Keuangan / Teknik / Umum Kepala ISPRS
Di Setujui Oleh :

Dr. dr. Sake Juli Martina, Sp. FK


Kepala RSU Sri Pamela