Anda di halaman 1dari 3

RAB PEKERJAAN PEMBUATAN KAMAR MANDI RUANG PINUS

RUMAH SAKIT UMUM SRI PAMELA

No Uraian Pekerjaan Vol Satuan Harga Satuan Jumlah Harga

I Pekerjaan Pendahuluan
Pek. Pembongkaran Jendela Nako 2.5 m3 25,000 62,500
Pek. Pembongkaran Dinding Tembok 2 m3 216,000 432,000

Sub Total 494,500


II Pekerjaan Pembuatan Kamar Mandi (P:2 L:1,80 T :3,40)
Batu Bata 1000 bh 770 770,000
Semen @40 kg 13 zak 63,000 819,000
Pasir Kali 3 m3 132,000 396,000
Batu Bunga 15 x 40 cm 6 bh 35,000 210,000
Besi Beton 10 mm 2 btg 60,000 120,000
Besi Beton 6 mm 2 btg 50,000 100,000
Keramik Dinding 20 x 25 cm ( merk IKAD setara ) 2 ktk 72,000 144,000
Keramik Dinding 25 x 40 cm ( merk IKAD setara ) 13 ktk 62,000 806,000
Keramik Lantai uk. 25 x 25 cm ( merk IKAD setara ) 5 ktk 72,000 360,000
Bon - bon Keramik uk. 10 cm 15 bh 770 11,550
Kloset Duduk American Standart ( non Tabung ) 1 set 700,000 700,000
Bak Air Fiber 60 x 60 cm 1 bh 198,000 198,000
Saringan Air Kamar Mandi 1 bh 27,500 27,500
Pipa PVC 4" Wavin 3 btg 250,000 750,000
Elbow PVC 4" Wavin 3 bh 59,400 178,200
Lem PVC 2 bh 5,500 11,000
Pipa PVC 1/2" 1 btg 40,425 40,425
Elbow PVC 1/2" 3 bh 5,500 16,500
Soket Drat PVC 1/2" 1 bh 5,500 5,500
Pipa PVC 1 1/4'' 2 bh 15,000 30,000
Keran Air merk ONDA 1 bh 21,000 21,000
Dempul Keramik 1 kg 18,150 18,150
Pintu Alumunium 0,7 x 2 m 1 bh 977,500 977,500
Wastaple American Standart 1 set 500,000 500,000
Cat Air Danabrite Cream 5 Kg 44,000 220,000
Kuas 5'' 1 bh 40,480 40,480

Sub Total 7,470,805


TOTAL 7,470,805
UPAH KERJA 1,988,661
TOTAL + UPAH KERJA 9,459,466
PPN ( 10% ) 945,947
TOTAL BIAYA 10,405,413

Tebing Tinggi, 2020

Diperiksa Oleh : Dibuat Oleh :

Agnes Delvina Tarigan M. Ilham, Nst


Kasi Keuangan / Teknik / Umum Kepala ISPRS
Di Setujui Oleh :
dr. Syahrizal Siregar, M.Kes
Kepala RSU Sri Pamela
KONSEP

RAB PEKERJAAN PEMASANGAN BATU KESING TAMAN


RUMAH SAKIT UMUM SRI PAMELA

No Uraian Pekerjaan Vol Satuan Harga Satuan Jumlah Harga

A Pekerjaan Batu Kesing Taman


- Bahan
Batu Bata 400 bh 770 308,000
Semen @ 40 Kg 6 zak 63,657 381,942
Pasir Kali 1.5 m³ 150,000 225,000
Cat Minyak ( Putih ) 18 Kg 64,400 1,159,200
Cat Minyak ( Biru ) 17 Kg 64,400 1,094,800
Cat Minyak ( Hitam ) 5 Kg 64,400 322,000
Thinner 20 Ltr 13,333 266,660
Kuas 2" 7 bh 14,700 102,900
TOTAL 3,860,502
Terbilang " Tiga Juta Delapan Ratus Enam Puluh Ribu Lima Ratus Dua "

Tebing Tinggi, 2018

Diperiksa Oleh : Dibuat Oleh :

R.M. Nainggolan M. Ilham, Nst


Kasi Keuangan / Teknik / Umum Kepala ISPRS
Di Setujui Oleh :

dr. Syahrizal.Srg, M.Kes


Kepala RSU Sri Pamela

Anda mungkin juga menyukai