RAB PEKERJAAN PEMBUATAN SEKAT RUANGAN SWAB TEST DI RUANG PINUS

RUMAH SAKIT UMUM SRI PAMELA

No Uraian Pekerjaan Vol Satuan Harga Satuan Jumlah Harga

I Pekerjaan Pendahuluan
Pek. Pembongkaran Jendela Nako + Dinding Tembok 5 m3 25,000 125,000

Sub Total 125,000


II Pekerjaan Pembuatan Sekat Ruangan dan Dinding
Kaca 8 mm + Rangka + Sarung Tangan 1 set 800,000 800,000
Kaca 5 mm + Rangka + Pintu 1 x 2 m ( 3 x 3.4 m ) 1 set 3,250,000 3,250,000
Batu Bata 150 bh 770 115,500
Semen @40 kg 1 zak 63,000 63,000
Cat Air Paragon Putih 10 kg 35,000 350,000
Cat Minyak 1 kg 52,000 52,000
Thinner 1 ltr 20,000 20,000
Broti 2 x 2 x 16 7 btg 54,500 381,500
Triplek 6 mm 4 lbr 127,765 511,060
Paku 2" 0.5 kg 18,975 9,488
Paku 1" 0.5 kg 18,975 9,488
Paku Beton 4" 1 ktk 25,300 25,300
Kuas 2'' 1 bh 40,480 40,480

Sub Total 5,627,815


TOTAL 5,627,815
UPAH KERJA 1,250,563
TOTAL + UPAH KERJA 6,878,378
PPN ( 10% ) 687,838
TOTAL BIAYA 7,566,216

Tebing Tinggi, 2020

Diperiksa Oleh : Dibuat Oleh :

Agnes Delvina Tarigan M. Ilham, Nst


Kasi Keuangan / Teknik / Umum Kepala ISPRS
Di Setujui Oleh :

dr. Syahrizal Siregar, M.Kes


Kepala RSU Sri Pamela
KONSEP

RAB PEKERJAAN PEMASANGAN BATU KESING TAMAN


RUMAH SAKIT UMUM SRI PAMELA

No Uraian Pekerjaan Vol Satuan Harga Satuan Jumlah Harga

A Pekerjaan Batu Kesing Taman


- Bahan
Batu Bata 400 bh 770 308,000
Semen @ 40 Kg 6 zak 63,657 381,942
Pasir Kali 1.5 m³ 150,000 225,000
Cat Minyak ( Putih ) 18 Kg 64,400 1,159,200
Cat Minyak ( Biru ) 17 Kg 64,400 1,094,800
Cat Minyak ( Hitam ) 5 Kg 64,400 322,000
Thinner 20 Ltr 13,333 266,660
Kuas 2" 7 bh 14,700 102,900
TOTAL 3,860,502
Terbilang " Tiga Juta Delapan Ratus Enam Puluh Ribu Lima Ratus Dua "

Tebing Tinggi, 2018

Diperiksa Oleh : Dibuat Oleh :

R.M. Nainggolan M. Ilham, Nst


Kasi Keuangan / Teknik / Umum Kepala ISPRS
Di Setujui Oleh :

dr. Syahrizal.Srg, M.Kes


Kepala RSU Sri Pamela