TERBILANG : ( # DUA RATUS TUJUH JUTA LIMA RATUS ENAM PULUH RIBU RUPIAH # )
WENSELINA PAREIRA
Direktris
RENCANA ANGGARAN DAN BIAYA (RAB)
HARGA JUMLAH
NO Jenis Barang/Jasa VOL SAT SATUAN HARGA
(Rp) (Rp)
1 Pasir Pasang 30.00 M3 150,500.00 4,515,000.00
2 Batu Merah 18,000.00 Bh 795.00 14,310,000.00
3 Balok Kls II 6/12 - 4 M 20.00 Btg 138,875.00 2,777,500.00
4 Papan Kls II 3/25 - 4 M 24.00 Lbr 149,875.00 3,597,000.00
5 Balok Kelapa 4/6 - 4 M 21.00 Btg 34,375.00 721,875.00
6 Balok Kelapa 5/7 - 4 M 80.00 Btg 43,500.00 3,480,000.00
7 Balok Kelapa 6/8 - 4 M 28.00 Btg 61,500.00 1,722,000.00
8 Balok Kelapa 10/10 - 3 M 12.00 Btg 109,500.00 1,314,000.00
9 Pelupuh 2.5 M 6.00 Ikat 73,500.00 441,000.00
10 Semen 40 Kg 756.00 Zak 54,600.00 41,277,600.00
11 Besi Beton 10 mm SNI No.1 385.00 Btg 66,600.00 25,641,000.00
12 Besi Beton 6 mm SNI No.1 257.00 Btg 36,600.00 9,406,200.00
13 Kawat Ikat 18.348 Kg 24,120.00 442,553.76
14 Teakwood 46.00 Lbr 150,180.00 6,908,280.00
15 Seng Gelombang Bjls 02 1,151.00 Lbr 55,980.00 64,432,980.00
16 Seng Plat Bjls 0.3Lebar 40 Cm 210.00 M 24,030.00 5,046,300.00
17 Paku Biasa 5-15 Cm 82.31 Kg 18,030.00 1,484,049.30
18 Paku Beton 5-15 Cm 1.00 Kg 24,030.00 24,030.00
19 Paku Seng 53.50 Kg 42,030.00 2,248,605.00
JUMLAH 189,789,973.06
WENSELINA PAREIRA
Direktris
HARGA SATUAN BAHAN
WENSLINA PAREIRA
Direktris
JADWAL WAKTU PENYERAHAN / PENGIRIMAN BARANG
1 PEKERJAAN PERSIAPAN
2 PEMESANAN BARANG
3 PENGEPAKAN
4 PENGIRIMAN
5 PEMERIKSAAN
6 SERAH TERIMA BARANG
WENSELINA PAREIRA
Direktris