RENCANA BIAYA PORTACAMP LOKASI SALAWATI

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH


A PEKERJAAN BONGKARAN EXITING
1 Pekerjaan bongkaran dan bukaan dinding, Plafon dan Lantai
a. Bongkaran Rangka & Penutup dinding 36.96 M2 110,000 4,065,600
2
b. Bongkaran Rangka & penutup Plafon 14.4 M 110,000 1,584,000
c. Bongkaran kusen dan daun Pintu 2 Bh 50,000 100,000
d. Bongkaran Rangka dan Penutup Lantai 14.4 M2 80,000 1,152,000

2 PEKERJAAN PENGELUPASAN
a. Pekerjaan Grinding amplas dinding luar dan Tralis jendela
36.96 M2 60,000 2,217,600

B PEKERJAAN PASANG KEMBALI RANGKA DAN PENUTUP


1 Pekerjaan Rangka Dan Penutup Dinding 36.96 M2 110,000 4,065,600
2
2 pekerjaan rangka dan penutup plafon 14.4 M 110,000 1,584,000
3 pekerjaan list plafon 16.80 𝑚^1 50,000 840,000
4 Pekerjaan Kusen Dan Pintu 1𝑚^1 210,000 210,000

C PEKERJAAN ELECTRICAL
1 Pekerjaan Pasangan Kabel NYM 2 X 2,5m 35 M1 50,000 1,750,000
2 Pekerjaan Pasangan Fitting Lampu 2 TITIK 50,000 100,000
3 Pekerjaan Pasangan Saklar 2 TITIK 30,000 60,000
4 Pekerjaan Pasangan MCB & box 1 TITIK 200,000 200,000
4 Pekerjaan Pasangan stop kontak 6 TITIK 30,000 180,000
E PEKERJAAN FINISHING
1 Pekerjaan Pengecetan Dan Kompon
a. dinding dan Plafon (Dalam) 36.96 M2 50,000 1,848,000
b. Dinding (Luar) 40.02 M2 50,000 2,001,000
1
c. List Plafon 16.80 M 20,000 336,000

TOTAL Rp 22,293,800
1. Pekerjaan Bongkar Dinding Dalam UK 15,20 X 2
2. Pekerjaan Bongkar Lantai Uk 5,50 X 2,50
3. Pekerjaan Bongkar Plafon UK 5,50 X 2,50
REKAPITULASI LIST MATRIAL PEKERJAAN RENOVASI PORTACAMP

NO JENIS MATRIAL VOLUME SATUAN HARGA TOTAL


1 Papan kayu Besi 20, X 2 X 4 31 Lbr 110,000 3,410,000
2 Triplex 9 mm (Dinding) 17 Lbr 165,000 2,805,000
3 Triplex 6 mm (Plafon) 6 Lbr 98,500 591,000
4 Paku 7 Cm 2 KG 35,000 70,000
5 Paku 5 Cm 1 KG 35,000 35,000
6 Kompon Gypsum (cornis) 5 KG 25,000 125,000
7 Sekrup Gypsum (isi 300 pcs) 1 DOS 350,000 350,000
8 Kasa Gypsum (ada Lem) 1 ROLL 40,000 40,000
9 Cat Minyak alfian 5 Kg 2 KLG 310,000 620,000
10 Cat Plafon & dinding Superwhite Uk 5 Ltr. 20 KG 1,250,000 25,000,000
11 Kuas Ganggang Kayu 2 3 PCS 20,000 60,000
12 list Plafon (kembar sari) 5 cm X 4 m 5 BTG 45,000 225,000
13 Paku Triplex 0.5 KG 35,000 17,500
14 Isolasi listrik 1 ROLL 30,000 30,000
15 Saklar ganda tanam 1 BH 30,000 30,000
16 Stop kontak tanam 6 BH 30,000 180,000
17 Kabel Nym eterna Uk 2x 2,5 m 38 Meter 50,000 1,900,000
18 Kapi Plastik 2 BH 10,000 20,000
19 Kapi besi (Pisau ) 1 BH 15,000 15,000
20 Box mcb isi 3 1 BH 68,000 68,000
21 MCb 30 ampare 3 BH 95,000 285,000
22 Balok 5X10X4 (K. Besi) 8 BRG 100,000 800,000
23 Hollow Galvalum 4X4X4 15 BRG 40,000 600,000
24 cat Avcat coklat 1 kg 1 klg 65,000 65,000
25 Transportasi Via Laut 2,000,000
TOTAL IDR 39,341,500
MANPOWER PROJECT PORTACAMP

FEBRUARI
NO NAMA MANPOWER
10-Feb-22 11-Feb-22 12-Feb-22 13-Feb-22 14-Feb-22
1 ANDARIAS 1 1 1 1 1
2 ROGGER 1 1 1 1 1
3 BAYU 1 1 1 1 1
4 BOYKE 1 1 1 1 1
5 ANDRE 1 1 1 1 1
6 SAMUEL 1 1 1 1 1
7 JAN REMON 1
8
9
10
HADIR
TIDAK HADIR

FEBRUARI
TOTAL
15-Feb-22 16-Feb-22 17-Feb-22 18-Feb-22 19-Feb-22 20-Feb-22
1 1 1 1 1 1 11
1 1 1 1 1 1 11
1 1 1 1 1 1 11
1 1 1 1 1 1 11
1 1 1 1 1 1 11
1 1 1 1 1 1 11
1 2