LAPANGAN JATIASRI
LOKASI : SP JATIASRI
TABEL REVISI
DAFTAR ISI
1. COVER…………………………………………………..………..…….…….……..……………………. 1
2. TABEL REVISI…………………………………………….……..…….……..……..……………………. 2
3. DAFTAR ISI……………………..……………………………………….…………..……………………. 3
4. WEEKLY PROGRESS REPORT NO.019……………………..……..…………..……………………. 4
WEEKLY PROGRESS REPORT NO.019 - INSTRUMENT & UTILITY AIR RECEIVER JAS-EPC-DJA-IUR-00-G0-WPR-019
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 REV.A
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Hal 4 dari 17
Status
Submission date Approved date (Under preparation
No. Doc. Title
/CPPHK review/under
Plan Actual Plan Actual revise/or approved)
1 MDR INDEX 7-Sep-22 5-Sep-22 12-Sep-22 10-Jan-23 AAN
2 VENDOR 18-Aug-22 22-Aug-22 29-Aug-22 10-Jan-23 AAN
DOCUMENT
REGISTER LIST
3 PROJECT PLAN / 25-Aug-22 29-Aug-22 5-Sep-22 6-Okt-22 AAN
SCHEDULE
4 MECHANICAL 13-Okt-22 11-Okt-22 20-Okt-22 17-Okt-22 APP
DESIGN
CALCULATION
5 GENERAL ASSY 18-Aug-22 29-Aug-22 25-Aug-22 6-Okt-22 AAN
6 GENERAL 13-Okt-22 11-Okt-22 20-Okt-22 17-Okt-22 APP
ARRANGEMENT
7 SUPORT DETAIL 23-Aug-22 29-Aug-22 30-Aug-22 6-Okt-22 AAN
DRAWING
8 NOZZLE DETAIL 23-Aug-22 29-Aug-22 30-Aug-22 6-Okt-22 AAN
DRAWING
9 MANHOLE DETAIL 23-Aug-22 29-Aug-22 30-Aug-22 6-Okt-22 AAN
DRAWING
10 WELDING MAP & 24-Aug-22 29-Aug-22 31-Aug-22 6-Okt-22 AAN
NDE DRAWING
11 NAME PLATE DETAIL 23-Aug-22 28-Sept-2230-Aug-22 6-Okt-22 AAN
12 MECHANICAL 18-Aug-22 29-Aug-22 25-Aug-22 6-Okt-22 AAN
DATA SHEET
13 LINE LIST PIPING 19-Aug-22 29-Aug-22 26-Aug-22 1-Nov-22 AAN
14 MTO PIPING 22-Aug-22 29-Aug-22 29-Aug-22 2-Nov-22 AAN
15 MANUAL VALVE LIST 19-Aug-22 29-Aug-22 26-Aug-22 1-Nov-22 AAN
16 PIPING 22-Aug-22 30-Aug-22 29-Aug-22 2-Nov-22 AAN
CALCULATION
ASME B31.3
17 PIPING ISOMETRIC 25-Aug-22 29-Aug-22 1-Sep-22 1-Nov-22 AAN
18 PIPING SUPPORT 25-Aug-22 30-Aug-22 1-Sep-22 1-Nov-22 AAN
19 SKID STRUCTURAL 25-Aug-22 6-Sep-22 1-Sep-22 6-Okt-22 AAN
ANALYSIS DESIGN
CALCULATION
20 RIGGING ANALYSIS 25-Aug-22 6-Sep-22 1-Sep-22 6-Okt-22 AAN
21 LIFTING 26-Aug-22 2-Sep-22 Under Preparation
PROCEDURE
22 SKID 25-Aug-22 30-Aug-22 1-Sep-22 27-Okt-22 APP
CONSTRUCTION
DETAILS
23 LADDER & 25-Aug-22 30-Aug-22 1-Sep-22 27-Okt-22 APP
PLATFORM DETAILS
24 INSTRUMENT INDEX 22-Aug-22 29-Aug-22 29-Aug-22 19-Okt-22 AAN
25 UTILITY 22-Aug-22 29-Aug-22 Under Preparation
CONSUMPTION
WEEKLY PROGRESS REPORT NO.019 - INSTRUMENT & UTILITY AIR RECEIVER JAS-EPC-DJA-IUR-00-G0-WPR-019
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 REV.A
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Hal 6 dari 17
Summary of status:
Material arrived in
PO issued
No. PO name/Raw material Factory
Plan Actual Plan Actual
PLATE 12 X 6' X 20' A516GR70+N 17-Sep-2022 5-Sep-2022 3-Oct-2022 14-Sept-22
PLATE 10 X 6' X 20' A516GR70+N 17-Sep-2022 5-Sep-2022 3-Oct-2022 14-Sept-22
PLATE 8 X 6' X 20' A516GR70+N 17-Sep-2022 5-Sep-2022 3-Oct-2022 14-Sept-22
PLATE 8 X 6' X 20' A283GRC 17-Sep-2022 5-Sep-2022 3-Oct-2022 14-Sept-22
H BEAM 150 X 150 X 7 X 10 X 12M 17-Sep-2022 5-Sep-2022 3-Oct-2022 12-Sept-22
H BEAM 200 X 200 X 8 X 12 X 12M 17-Sep-2022 5-Sep-2022 3-Oct-2022 12-Sept-22
SIKU 75 X 75 X 6 X 6M 17-Sep-2022 5-Sep-2022 3-Oct-2022 12-Sept-22
PIPE & FITTINGS 4-Oct-2022 20-Oct-2022 7-Oct-2022 08-Nov-22
BALL Valve size 2" & Larger 4-Oct-2022 06-Jan-2023 10-Oct-2022
BALL Valve, Size 1.1/2" & Smaller 4-Oct-2022 06-Jan-2023 10-Oct-2022
GATE Valve Size 2" & larger 4-Oct-2022 06-Jan-2023 10-Oct-2022
GLOBE Valve Size 2" & larger 4-Oct-2022 06-Jan-2023 10-Oct-2022
Globe Valve, Size 1.1/2" & Smaller 4-Oct-2022 06-Jan-2023 10-Oct-2022
Automatic Drain 4-Oct-2022 10-Oct-2022
Pressure Regulator Valve (PCV 511, 4-Oct-2022 2-Dec-2022 10-Oct-2022
411)
Pressure Safety Valve (PSV 051, 041) 4-Oct-2022 2-Dec-2022 10-Oct-2022
Pressure Indicator (PI 511, 512, 412) 4-Oct-2022 2-Dec-2022 10-Oct-2022
Level Gauge (LG 511, 411) 4-Oct-2022 2-Dec-2022 10-Oct-2022
Pressure Transmitter (PT 411) 1-Dec-2022 2-Dec-2022 7-Dec-2022 15-Dec-2022
Summary of status:
WEEKLY PROGRESS REPORT NO.019 - INSTRUMENT & UTILITY AIR RECEIVER JAS-EPC-DJA-IUR-00-G0-WPR-019
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 REV.A
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Hal 8 dari 17
3. Monthly progress
Issues need to be solved or may cause delay: Review & Approval Drawing, Calculation, Data Sheet &
Procedure from Aldaberta
Delay already confirmed: (if has, the reason, impact and mitigation plan need to be listed)
4. Inspection status
Summary of status:
Catatan/Punchlist
1.
5. Delivery Status
Summary of status:
WEEKLY PROGRESS REPORT NO.019 - INSTRUMENT & UTILITY AIR RECEIVER JAS-EPC-DJA-IUR-00-G0-WPR-019
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 REV.A
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Hal 9 dari 17
Progress
No. Description Weight Deviation Remarks
Plan Actual
1 ENGINEERING 5.00% 100.00% 81.72% -18.28%
2 PROCUREMENT 50.00% 100.00% 100.00% 00.00%
3 FABRICATION STAGE 40.00% 100.00% 90.74% -9.26%
4 SHIPMENT 5.00% 100.00% 0.00% -100.00%
TOTAL 100.00% 100.00% 90.65% -9.35%
INSTRUMENT & UTILITY AIR RECEIVER PACKAGE
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRIWP1-ENGINEERING
PO. No : 07/06/22/AI-PEP/JAS/021
07/06/22/AI-PEP/JAS/022 WP1 - ENGINEERING VDRL
Material : INSTRUMENT AIR RECEIVER PACKAGE (2-13-PK-51)
UTILITY AIR RECEIVER PACKAGE (2-13-PK-41)
Vendor : PT. DWITUNGGAL JAYA AGUNG
Project : PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI
Prepared : HABIB
Reviewed :
Cut Of Date : 13-Jan-2023
6-Jan-23 13-Jan-23
PROGRESS
PROGRESS
WP3 - FABRICATION
PO. No : 07/06/22/AI-PEP/JAS/021
07/06/22/AI-PEP/JAS/022
Material : INSTRUMENT AIR RECEIVER PACKAGE (2-13-PK-51)
UTILITY AIR RECEIVER PACKAGE (2-13-PK-41)
Vendor : PT. DWITUNGGAL JAYA AGUNG
Project : PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI
Prepared : HABIB
Reviewed :
Cut Of Date : 13-Jan-2023
6-Jan-2023 13-Jan-2023
PROGRESS
REMARKS
NO. FABRICATION QTY WF Prev This Acc
Plan Actual Plan Actual Plan Actual
40.00% 40.00% 24.37% 0.00% 11.93% 40.00% 36.30%
A HEAD 3 11.11%
1 Marking, Cutting Development Head 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
2 Fit-up & Welding Plate To Plate 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
3 Forming Head 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
B SHELL 4 14.81%
1 Marking, Cutting, Bevel Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
2 Roll Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
3 Fit-up Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
4 Welding Longseam Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
C NOZZLE 3 11.11%
1 Marking, Cutting 1 3.70% 3.70% 0.56% 0.00% 3.15% 3.70% 3.70%
2 Fit Up 1 3.70% 3.70% 0.56% 0.00% 3.15% 3.70% 3.70%
3 Welding Neck To Flange 1 3.70% 3.70% 0.56% 0.00% 3.15% 3.70% 3.70%
D SKIRT And ACC 3 11.11%
1 Marking, Cutting 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
2 Fit Up 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
3 Welding 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
E INSTALLATON 6 22.22%
1 Shell To Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
2 Head To Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
3 Bottom To Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
4 Nozzle To Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
5 External Accessories To Shell 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
6 Skirt To Bottom Head 1 3.70% 3.70% 3.70% 0.00% 0.00% 3.70% 3.70%
F INSPECTION AND TEST 5 18.52%
1 Final Dimensional Inspection Internal 1 3.70% 3.70% 0.00% 0.00% 3.70% 3.70% 3.70%
2 Radiography Test 1 3.70% 3.70% 0.00% 0.00% 3.70% 3.70% 3.70%
3 Penetrant Test 1 3.70% 3.70% 0.00% 0.00% 3.70% 3.70% 3.70%
4 Final Dimensional Inspection User 1 3.70% 3.70% 0.00% 0.00% 3.70% 3.70% 3.70%
5 Pre-Test & Hydrostatic Test 1 3.70% 3.70% 0.00% 0.00% 3.70% 3.70% 3.70%
G FINISHING 3 11.11%
1 Surface Preparation 1 3.70% 3.70% 0.00% 0.00% 1.85% 3.70% 1.85%
2 Sandblasting 1 3.70% 3.70% 0.00% 0.00% 0.00% 3.70% 0.00%
3 Painting (Primer Coat-Finish Coat ) 1 3.70% 3.70% 0.00% 0.00% 0.00% 3.70% 0.00%
TOTAL PROGRESS WP3 27 100.00% 100.00% 60.93% 0.00% 29.81% 100.00% 90.74%
INSTRUMENT & UTILITY AIR RECEIVER PACKAGE
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI
WP4 - SHIPMENT
PO. No : 07/06/22/AI-PEP/JAS/021
07/06/22/AI-PEP/JAS/022
Material : INSTRUMENT AIR RECEIVER PACKAGE (2-13-PK-51)
UTILITY AIR RECEIVER PACKAGE (2-13-PK-41)
Vendor : PT. DWITUNGGAL JAYA AGUNG
Project : PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI
Prepared : HABIB
Reviewed :
Cut Of Date : 13-Jan-2023
6-Jan-2023 13-Jan-2023
Progress
NO. FABRICATION WF Prev This Acc
Plan Actual Plan Actual Plan Actual
5.00% 5.00% 0.00% 0.00% 0.00% 5.00% 0.00%
A INSTRUMENT & UTILITY AIR RECEIVER PACKAGE 100.00%
1 Packing 50.00% 50.00% 0.00% 0.00% 50.00%
2 Delivery 50.00% 50.00% 0.00% 0.00% 50.00%
TOTAL PROGRESS WP3 100.00% 100.00% 0.00% 0.00% 0.00% 100.00% 0.00%
INSTRUMENT & UTILITY AIR RECEIVER PACKAGE
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI
S-CURVE
13 January 2023
PO. No : 07/06/22/AI-PEP/JAS/021
07/06/22/AI-PEP/JAS/022
Vendor : PT. DWITUNGGAL JAYA AGUNG