TIME SCHEDULE

PROYEK : FIRE HYDRANT DAN SPRINKLER


PEKERJAAN : PEMBUATAN GROUND WATER TANK DAN RUMAH POMPA
PEMILIK / LOKASI : PT HERLINA INDA - KAWASAN INDUSTRI PULO GADUNG ( JIEP )
NOMOR KONTRAK : 0258//PP/RENUS-I-CIVIL/0919/101
ANGKA WAKTU PELAKSANAAN : 115 HK ( 23 SEPTEMBER 2019 s/d 15 JANUARI 2020
Bobot Pek. JANGKA WAKTU PELAKSANAAN PEKERJAAN
No. Jenis Pekerjaan Keterangan
(%) Sep-19 Okt -19 Nov-19 Des-19 Jan-20
100,00
I PEKERJAAN STRUKTUR

1,518 1,518
A. Pekerjaan Bongkaran Beton 3,036

2,978 2,978 2,978


B. Pekerjaan Tanah 8,934

6,118 6,118 6,117 6,117 6,117 6,117 6,117 6,117 6,117 6,117 6,117 6,117
C. Pekerjaan Beton 73,406

0,653 0,653 0,653 0,652


D. Pekerjaan Lain-lain 2,611

2,403 2,403 2,403 2,402 2,402


II. PEEEKERAAN ARSITEKTUR 12,013

Bobot Prestasi Komulatif 100,000 - - - 1,518 5,149 9,749 9,749 6,769 6,117 6,117 6,117 6,117 6,117 8,520 8,520 8,520 8,519 2,402

Bobot Prestasi Rencana 1,518 32,934 57,402


89,079 100,000

Bobot Prestasi Aktual

Selisih Bobot Prestasi / Deviasi

Mengetahui / menyetujui : Jakarta, 19 September 2019


PT. REKA ENERGI NUSANTARA

( ) ( Ir. Kirno Arryanto )


STRUKTUR ORGANISASI LAPANGAN
SUB KONTRAKTOR

PROJECT MANAGER
IR.. HARYANTO

SITE MANAGGER
Ir.. KIRNO ARRYANTO

PELAKSANA ADMIN/KEU/LOGISTIK
ROSIDIN KRISTANTO

MANDOR
RASDI

DIVISI PEMBESIAN DIVISI BATU / KAYU DIVISI ALAT BERAT

UNTUNG RIKI JULPIKAR BY APPLIKATOR


SAEPULOH ARIS IRAWAN
ABDUL HARIS

Jakarta, 19 September 20119