NAMA PROYEK : PEMBANGUNAN NEW CONSTRUCTION JETTY & TEMPORARY ACCESS ROAD
0 0
LEMBAR RESPON
DOKUMEN REF. : -
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 3 of 11
Dokumen / Hal.
No. Komen Inisial Respon Inisial Keterangan
Ref.
DAFTAR ISI
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 4 of 11
1. FLOWCHART .........................................................................................................................................
2. PERSIAPAN PEKERJAAN ........................................................................................................................
a. Alat dan Bahan .....................................................................................................................................
b. Fabrikasi Besi dan Bbekisting ...............................................................................................................
3. METODE PELAKSANAAN .......................................................................................................................
3.1 Pekerjaan Isian Tiang Pancang .......................................................................................................
a. Pembesian ....................................................................................................................................
b. Pengecoran ..................................................................................................................................
3.2 Pekerjaan Joint Pile Cap – Beam ....................................................................................................
a. Pembesian ....................................................................................................................................
b. Pekerjaan Bekisting ......................................................................................................................
c. Pengecoran ..................................................................................................................................
d. Pembongkaran Bekisting ..............................................................................................................
e. Perawatan Beton ..........................................................................................................................
3.3 Pekerjaan Topping Off ...................................................................................................................
a. Pembesian ....................................................................................................................................
b. Pekerjaan Bekisting ......................................................................................................................
c. Pengecoran ..................................................................................................................................
3.4 Pekerjaan Plank Fender .................................................................................................................
a. Pembesian ....................................................................................................................................
b. Pekerjaan Bekisting ......................................................................................................................
c. Pengecoran ..................................................................................................................................
1. FLOWCHART
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 5 of 11
2. PERSIAPAN PEKERJAAN
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 6 of 11
Bahan
- Besi Tulangan :
D32, D25, D19,
D16, D12
- Beton K-500
3. METODE PELAKSANAAN
3.1 Pekerjaan Isian Tiang Pancang
a. Pembesian
1) Pada proses pekerjaan awal untuk pekerjaan tulangan utama atau rebars pipa baja
dimulai dengan cara pembuatan kerangka tulangan utama pipa baja yang sesuai dengan
spesifikasi gambar rencana kerja.
2) Setelah selesai kemudian dibaringkan secara horizontal dan kemudian diberi begel pada
area sengkang yang telah dibengkokkan dengan alat bernama bar bender secara spiral
3) kemudian ikat dengan kawat bendrat sehingga sengkang tidak bergeser dari jarak aman
yang telah direcanakan. Ilustrasi dapat dilihat pada Gambar 3.1 berikut.