WORK METHOD

Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0


U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 1 of 11

PEMBERI KERJA : PT PERTAMINA (PERSERO) RU-VI BALONGAN

KONTRAKTOR : PT NINDYA KARYA (PERSERO)

NAMA PROYEK : PEMBANGUNAN NEW CONSTRUCTION JETTY & TEMPORARY ACCESS ROAD

PROYEK REVITALISASI RCC RU VI - BALONGAN

LOKASI : PT PERTAMINA (PERSERO) RU-VI BALONGAN, INDRAMAYU – JAWA BARAT

NO. KONTRAK : SP-19168

0 04/04/2021 All Issued For Review DAM RA SS


Prepared Checked Approved Approved
Rev. Date Page Description
PT Nindya Karya PT Pertamina
REVISI TABULASI
HAL. REVISI KETERANGAN HAL. LAMPIRAN KETERANGAN
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 2 of 11

0 0

LEMBAR RESPON

DOKUMEN REF. : -
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 3 of 11

Dokumen / Hal.
No. Komen Inisial Respon Inisial Keterangan
Ref.

DAFTAR ISI
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 4 of 11

1. FLOWCHART .........................................................................................................................................
2. PERSIAPAN PEKERJAAN ........................................................................................................................
a. Alat dan Bahan .....................................................................................................................................
b. Fabrikasi Besi dan Bbekisting ...............................................................................................................
3. METODE PELAKSANAAN .......................................................................................................................
3.1 Pekerjaan Isian Tiang Pancang .......................................................................................................
a. Pembesian ....................................................................................................................................
b. Pengecoran ..................................................................................................................................
3.2 Pekerjaan Joint Pile Cap – Beam ....................................................................................................
a. Pembesian ....................................................................................................................................
b. Pekerjaan Bekisting ......................................................................................................................
c. Pengecoran ..................................................................................................................................
d. Pembongkaran Bekisting ..............................................................................................................
e. Perawatan Beton ..........................................................................................................................
3.3 Pekerjaan Topping Off ...................................................................................................................
a. Pembesian ....................................................................................................................................
b. Pekerjaan Bekisting ......................................................................................................................
c. Pengecoran ..................................................................................................................................
3.4 Pekerjaan Plank Fender .................................................................................................................
a. Pembesian ....................................................................................................................................
b. Pekerjaan Bekisting ......................................................................................................................
c. Pengecoran ..................................................................................................................................

1. FLOWCHART
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 5 of 11

2. PERSIAPAN PEKERJAAN
WORK METHOD
Nomor Dokumen PEKERJAAN INSITU PADA Rev. 0
U2003-004-DAP-C07-NK0006 KONSTRUKSI JETTY Page 6 of 11

a. Alat dan Bahan


 Alat

- Concrete Mixer - Concrete Vibrator


- Concrete Pump - Jidar
- Bar Bender -
- Bar Cutter
- Crane
- Alat Survey

 Bahan

- Besi Tulangan :
D32, D25, D19,
D16, D12
- Beton K-500

b. Fabrikasi Besi Tulangan dan Bekisting


1) Cek setiap diameter tulangan yang akan di fabrikasi berdasarkan gambar kerja
2) Lakukan pembengkokan dan pemotongan besi sesuai dengan gambar kerja
3) Untuk pemotongan besi tulangan digunakan Bar Cutter, sedangkan untuk pembengkokan
digunakan mesin Bar Bender.
4) Perhatikan panjang dan jumlah tulangan yang dibutuhkan
5) Cek kembali besi - besi yang telah di fabrikasi sesuai dengan kebutuhan
6) Setelah fabrikasi tulangan selesai, maka dilanjutkan fabrikasi bekisting untuk pekerjaan Insitu
Jetty
7) Tentukan ukuran bekisting yang diperlukan
8) Potong multiplek/plywood sesuai ukuran yang telah ditentukan

3. METODE PELAKSANAAN
3.1 Pekerjaan Isian Tiang Pancang
a. Pembesian
1) Pada proses pekerjaan awal untuk pekerjaan tulangan utama atau rebars pipa baja
dimulai dengan cara pembuatan kerangka tulangan utama pipa baja yang sesuai dengan
spesifikasi gambar rencana kerja.
2) Setelah selesai kemudian dibaringkan secara horizontal dan kemudian diberi begel pada
area sengkang yang telah dibengkokkan dengan alat bernama bar bender secara spiral
3) kemudian ikat dengan kawat bendrat sehingga sengkang tidak bergeser dari jarak aman
yang telah direcanakan. Ilustrasi dapat dilihat pada Gambar 3.1 berikut.

Gambar 3.1 Fabrikasi Besi Isian Tiang Pancang