ANALISA HARGA SATUAN

KABUPATEN : BEKASI
KODE ANALISA : D7.23
JENIS PEKERJAAN : Pekerjaan Beton K.350 NFA (Jalan)
SATUAN PEMBAYARAN : M3
P A. PEKERJA Kemampuan Tenaga / Jam / M3 Kode Kuantitas Upah / Jam Biaya Sub Total
E Penghamparan Plastik + Beton + Sealant + Curing
K Mandor
1,0000 Org L3 0,1167 18.408,62 2.148,29
E
Pekerja 3,0000 Org L1 0,9333 17.844,83 16.654,58
R
J Tukang 2,0000 Org L2 0,4667 18.110,02 8.451,94
A JUMLAH PEKERJA 27.254,81
B. MATERIAL Kuantitas Satuan Kode Harga Biaya Sub Total
M
Beton Batching Plant K.350 1,1000 m3 M 80 1.000.735,35 1.100.808,88
A
T Sealant 0,3350 kg M 73 30.157,03 10.102,60
E Air 84,0000 ltr M 23 142,50 11.970,00
R Karung 6,6670 bh M 20 4.914,48 32.764,86
I Plastik 4,0000 m2 M 22 2.028,71 8.114,82
A
-
L
JUMLAH MATERIAL 1.163.761,17
C. PERALATAN Kuantitas Satuan Kode Harga Biaya Sub Total
A Alat Bantu (Set @3 alat) - ls E 26 4.695,30 -
L Alat Penggetar Beton 4 HP 0,11667 Jam E 17 68.516,38 7.993,81
A Concrette Cutter (Mesin Pemotong Beton) 0,11667 Jam E 25 79.761,10 9.305,73
T -
JUMLAH PERALATAN 17.299,53
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 1.208.315,51
E. OVERHEAD & PROFIT 10% X D 120.831,55
F. HARGA SATUAN PEKERJAAN (D + E) 1.329.147,07
G. HARGA SATUAN PEKERJAAN / M3 1.329.147,07
Note: 1 SATUAN dapat berdasarkan atas jam operasional untuk Tenaga Kerja dan Peralatan, volume dan atau ukuran berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan terdapat Penyesuaian Harga (Eskalasi/Deskalasi)
sesuai ketentuan dalam Instruksi kepada Peserta Lelang.
3 Biaya satuan peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang dibayar dari kontrak) dan biaya-biaya lainnya.