1 2 3 4 5
HARGA UPAH TENAGA KERJA
1 Pekerja Rp. 110,000.00 /Oh Terlatih
2 Tukang Gali, Batu, Kayu, Besi, Plumbing dan Cat Rp. 150,000.00 /Oh Terlatih
3 Kepala Tukang Rp. 155,000.00 /Oh Terlatih
4 Mandor Rp. 165,000.00 /Oh Terlatih
1 2 3 4 5
###
L BAHAN KUSEN ###
1 Kusen Alluminium Warna Original 3" Rp. 121,000.00 /M1 Setara Hape
2 Bingkai profil alluminium Warna Coklat + Karet Sielent Rp. 176,000.00 /M1 ###
3 Bingkai Casement Profil Alluminium Warna Coklat + Karet Sielent Rp. 220,000.00 /M1 ###
4 Alumunium Strip Rp. 44,000.00 /M1 ###
5 Daun Pintu Tempered 80 x 210 x 12 mm Rp. 3,850,000.00 /M2 ###
6 Skrup fixer Rp. 8,250.00 /Bh ###
7 Karet Sielent Rp. 4,500.00 /M1 ###
8 Sielent Rp. 60,000.00 /tube ###
9 Kaca Rayben 5 mm Rp. 110,000.00 /M2 Setara Asahi
10 Kaca Bening Screen Glass 5 mm Rp. 115,000.00 /M2 Setara Asahi
###
DAFTAR ANALISA
STANDART NASIONAL INDONESIA (SNI) EDISI TAHUN 2016
PEKERJAAN PERSIAPAN
PEKERJAAN BETON
Cat: Bobot isi Pasir = 1400 kg/m3, Bobot isi Kerikil = 1350 kg/m3, >> Buckling factor pasir = 20%
A.4.1.1.4.43.b : 1 m3 Pek. Pembuatan Beton Lantai kerja mutu f'c = 7,4 MPa Kode
Harga Jumlah
No. Uraian Kode Satuan Koefisien
Satuan (Rp) Harga (Rp)
A. TENAGA :
1 Pekerja L.01 OH 1.6500 110,000.00 181,500.00
2 Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
3 Kepala Tukang L.03 OH 0.0280 155,000.00 4,340.00
4 Mandor L.04 OH 0.0830 165,000.00 13,695.00
Jumlah Tenaga Kerja............ 240,785.00
B. BAHAN :
1 Semen Kg 247.0000 1,400.00 345,800.00
2 pasir beton Kg 869.0000 164.29 142,764.29
3 Batu Pecah 1/2 Kg 999.0000 296.30 296,000.00
3 Kawat Mesh m2 6.6667 13,333.3333 88,888.89
4 air liter 200.0000 550.00 110,000.00
Jumlah harga bahan............ 983,453.17
C. PERALATAN:
1 Molen unit -
2 Alat bantu Set - -
PEKERJAAN CAT
3.3.10.(c) : 1 m2 Pek. Cat Atap Kode
Harga Jumlah
No. Uraian Kode Satuan Koefisien
Satuan (Rp) Harga (Rp)
A. TENAGA :
1 Pekerja L.01 OH 0.0200 110,000.00 2,200.00
2 Tukang cat L.02 OH 0.0630 150,000.00 9,450.00
3 Kepala tukang L.03 OH 0.0063 155,000.00 976.50
4 Mandor L.04 OH 0.0030 165,000.00 495.00
Jumlah Tenaga Kerja............ 13,121.50
B. BAHAN :
1 Cat Dasar kg 0.1000 35,000.00 3,500.00
1 Cat Penutup kg 0.2600 70,000.00 18,200.00
3.3.11.(d) : 1 m2 Pek. Pengecatan Permukaan tembok dengan cat anti jamur Kode
Harga Jumlah
No. Uraian Kode Satuan Koefisien
Satuan (Rp) Harga (Rp)
A. TENAGA :
1 Pekerja L.01 OH 0.0200 110,000.00 2,200.00
2 Tukang cat L.02 OH 0.0630 150,000.00 9,450.00
3 Kepala tukang L.03 OH 0.0063 155,000.00 976.50
4 Mandor L.04 OH 0.0030 165,000.00 495.00
Jumlah Tenaga Kerja............ 13,121.50
B. BAHAN :
2 Cat Dasar kg 0.1000 35,000.00 3,500.00
3 Cat Penutup anti jamur kg 0.2600 75,000.00 19,500.00
Jumlah harga bahan............ 23,000.00
C. PERALATAN:
1 Alat bantu Set - - -
PEKERJAAN PLASTERAN
A.4.4.2.4 : 1 m2 Pek. Pemasangan plesteran 1SP : 4 PP tebal 15 mm Kode
Harga Jumlah
No. Uraian Kode Satuan Koefisien
Satuan (Rp) Harga (Rp)
A. TENAGA :
1 Pekerja L.01 OH 0.3000 110,000.00 33,000.00
2 Tukang batu L.02 OH 0.1500 150,000.00 22,500.00
3 Kepala tukang L.03 OH 0.0150 155,000.00 2,325.00
4 Mandor L.04 OH 0.0150 165,000.00 2,475.00
Jumlah Tenaga Kerja............ 60,300.00
B. BAHAN :
1 semen kg 6.2400 1,400.00 8,736.00
2 pasir pasang M³ 0.0240 230,000.00 5,520.00
Jumlah harga bahan............ 14,256.00
C. PERALATAN:
2 Alat bantu Set - - -
A Pek. pembesian dengan besi polos atau ulir A.4.1.1.17 Kg 0.2027 14,000.00 2,837.84
B Pek. Beton Mutu f'c= 9,8 Mpa A.4.1.1.4.43.b m3 1.0000 1,407,873.90 1,407,873.90
D Harga satuan pekerjaan ( A + B + C)............... 1,410,711.74
A.5.1.1.31 : 1 M Pemasangan 1 m pipa 3" Kode
Harga Jumlah
No. Uraian Kode Satuan Koefisien
Satuan (Rp) Harga (Rp)
A. TENAGA :
1 Pekerja L.01 OH 0.0810 110,000.00 8,910.00
2 Tukang batu L.02 OH 0.1350 150,000.00 20,250.00
3 Kepala tukang L.03 OH 0.0135 155,000.00 2,092.50
3 Mandor L.04 OH 0.0400 165,000.00 6,600.00
Jumlah Tenaga Kerja............ 37,852.50
B. BAHAN :
1 Pipa 3 " m 1.2000 152,000.00 182,400.00
Jumlah harga bahan............ 182,400.00
C. PERALATAN:
2 Alat bantu Set 35 % harga pipa 22,800.00 22,800.00
JUMLAH
NO URAIAN PEKERJAAN
(Rp)
1 2 2
1 PEKERJAAN PERSIAPAN 2,800,000.00
2 SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK) 1,750,000.00
3 PEKERJAAN BONGKARAN 748,535.91
4 PEKERJAAN PASANGAN 46,361,433.64
5 PEKERJAAN PENGECATAN 70,158,920.82
6 PEKERJAAN ALUMUNIUM 17,928,043.60
7 PEKERJAAN LAIN-LAIN 1,605,100.00
SUB JUMLAH FISIK Rp. 141,352,033.96
PPN 11% Rp. 15,548,723.74
TOTAL JUMLAH FISIK + PPN 11% Rp. 156,900,757.70
TOTAL JUMLAH FISIK + PPN 11% DIBULATKAN Rp. 156,900,000.00
Terbilang : Seratus Lima Puluh Enam Juta Sembilan Ratus 0 0 Ribu 0 0 0 Rupiah
Bengkulu, 2022
Kontraktor Pelaksana
Cv. Pangestu jaya
Direktur