Anda di halaman 1dari 1

TIME SCHEDULE

Kontrak
Kontrak Adendum :
Nilai : Rp. 100.000.000,00.
Waktu : 60 Hari Kalender

JADWAL WAKTU PELAKSANAAN 60 HARI KALENDER


NO URAIAN KEGIATAN VOL SAT. BOBOT (%) FEBRUARY MARET APRIL
W1 W2 W3 W4 W5 W6 W7 W8
1 2 3 4 5 21/02 S/D 27/02 28/02 S/D 06/03 07/03 S/D 13/03 14/03 S/D 20/03 21/03 S/D 27/03 28/03 S/D 03/04 04/04 S/D 10/04 11/04 S/D 17/04
A PEKERJAAN BANGUNAN RUMAH TINGGAL
I PEKERJAAN PERSIAPAN DAN BONGKARAN
7,0900 4,1900 2,9000
II PEKERJAAN TANAH
2,1500 1,0900 0,7100 0,3500
III PEKERJAAN PONDASI
8,2200 0,1400 8,0800
IV PEKERJAAN BETON BERTULANG
14,2400 2,4600 8,3600 0,8200 2,3400 0,2600
V PEKERJAAN PASANGAN
38,7100 3,2100 18,2300 8,3700 8,9000
VI PEKERJAAN PELAPIS LANTAI
10,1500 1,0900 7,2900 1,7700
VII PEKERJAAN PLUMBING & SANITASI
4,9600 3,1300 1,8300
VIII PEKERJAAN KUSEN, PINTU, JENDELA DAN KACA
4,1100 4,1100
IX PEKERJAAN PLAFON (Rangka Hollow 33x33/ 13x33 Galvanize t.0,35mm)
2,7300 2,7300
X PEKERJAAN LISTRIK (Pipa listrik didinding saja)
4,6400 4,0800 0,5600
XI PEKERJAAN PENGECATAN
3,0000 3,0000

RENCANA FISIK MINGGUAN 4,19 4,13 10,54 13,37 26,29 25,16 2,33 13,99 100
RENCANA FISIK KOMULATIF MINGGUAN 4,19 8,32 18,86 32,23 58,52 83,68 86,01 100
REALISASI FISIK MINGGUAN 0 0 0 0 0 0 0 0
REALISASI FISIK KOMULATIF MINGGUAN 0 0 0 0 0 0 0 0
MAJU / LAMBAT -4,19 -8,32 -18,86 -32,23 -58,52 -83,68 -86,01 -100