SCHEDULE PEMBANGUNAN JEMBATAN DK141

ID Task Name Duration Year 1


M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
1 Pembangunan Overpass DK141 pada Proyek KCIC 300 days

2 Start 0 days

3 Pekerjaan :Persiapan 21 days

9 Traffic Management dan SMK3L 290 days

10 Group 1 (A1 ~P8) 151 days

11 Pekerjaan Pemancangan 54 days

14 Pekerjaan Pilecap 70 days

15 Abutmen 1 14 days

23 Pier 1 14 days

31 Pier 2 14 days

39 Pier 3 14 days

47 Pier 4 14 days

55 Pier 5 14 days

63 Pier 6 14 days

71 Pier 7 14 days

79 Pier 8 14 days

87 Pekerjaan Kolom Pier dan Pier Head 88 days

88 Abutmen 1 35 days

106 Pier 1 15 days

115 Pier 2 17 days

124 Pier 3 17 days

133 Pier 4 15 days

142 Pier 5 15 days

151 Pier 6 16 days

160 Pier 7 30 days

169 Pier 8 30 days

178 Group 2 (P9 ~A2) 109 days

179 Pekerjaan Pemancangan 74 days

182 Pekerjaan Pilecap 70 days

183 Pier 9 14 days

191 Pier 10 14 days

199 Pier 11 14 days

207 Pier 12 14 days

215 Pier 13 14 days

223 Pier 14 14 days

231 Pier 15 14 days

239 Pier 16 14 days

247 Abutmen 2 14 days

255 Pekerjaan Kolom Pier dan Pier Head 74 days

256 Pier 9 27 days

265 Pier 10 27 days

274 Pier 11 23 days

283 Pier 12 18 days

292 Pier 13 18 days

301 Pier 14 18 days

310 Pier 15 18 days

319 Pier 16 18 days

328 Abutmen 2 24 days

344 Pekerjaan Stuktur Atas Group 1+2 211 days

349 Pekerjaan Beton Slab Group 1+2 36 days

353 Pekerjaan Lain-lain 39 days

363 Finish 0 days