Kelompok 12
SEPTEMBER OKTOBER
NO. Nama Kegiatan Bobot Minggu ke- Minggu ke-
III IV I II III IV
1 Pencarian Data Geologi 1 1
2 Pembuatan dan Evaluasi S-Curve 2 1 1
3 Evaluasi Petrofisik 12 2 6 3 1
4 Evaluasi Reservoir dan Produksi 12 1 4 3
5 Progress Report Tim FDP-UTS 10 5 5
6 Evaluasi Drilling dan Komplesi 13 5
7 Perencanaan Fasilitas Produksi 17
8 Perhitungan dan Perencanaan Skenario Produksi 10
9 Penentuan Skenario Produksi 10
10 Evaluasi Keseluruhan 9
11 Penulisan Laporan 2
12 Persiapan Presentasi 2
Total Progress 100
Planning Progress 1.00 1.00 3.00 7.00 12.00 14.00
Kumulatif Planning Progress 1 2 5 12 24 38
Actual Progress 1 1 2 5
Kumulatif Actual Progress 1 1 4 9
Minggu ke Kumulatif Planning Progress
1 1
2 2
3 5
4 12
5 24
6 38
7 52
8 66
9 81
10 94
11 98
12 100
November Desember
Minggu ke- Minggu ke
I II III IV I II III IV
4 3 1
6 6 1 4
5 4 1
5 5
4 3 2
2
2
20
00
80
60
40
20
0
0 2 4 6 8 10 12 14
NAMA
NIM
KEAHLIAN
September
No Nama Kegiatan Bobot (%)
Week 3 Week 4
1 Pengumpulan Data dan Study Geology 2 2
2 Pembuatan S-Curve 5 3
3 Menentukan Top Bottom 5
4 Menganalisa Peta Depth Structure & Isopach 4
5 Menentukan Net Pay & Cut Off 6
6 Progress Report Tim FDP-UTS 10
7 Diskusi, Evaluasi, Revisi, dan Pembuatan Draft 12
8 Menentukan Koordinat Titik Sumur 15
9 Pembuatan Skenario Lapangan 16
10 Evaluasi 18
11 Pembuatan Presentasi 4
12 Pembuatan dan penyerahan Draft Final 3
Total 100
Planning Progress (%) 2 3
Cummulative Planning Progress (%) 2 5
Actual Progress (%) 1 2
Cummulative Actual Progress (%) 1 3
Oktober November
Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
2
2 3
2 2
4 2
4 6
2 2 8
2 3 10
3 5
3
4 5 6 8 10 14 18
9 14 20 28 38 52 70
3 4
6 12
S-CURVE GEOLOGY
120
100
80
PROGRESS (%)
60
40
20
PROGRESS (%
60
40
20
0
0 2 4 6 8 10 12 14
WEEK
12 13 14
er Desember
Week 4 Week 1 Week 2 Week 3 Week 4
8
10 5
2 2
1 2
18 8 4
88 96 100
Pl anni ng
Actua l
Pl anni ng
Actua l
12 14
S-CURVE PETROPHYSICS
No Activity Bobot
2 4 4 7 8 10 11
2 6 10 17 25 35 46
2 4 4 6
2 6 10 16
16
120
14
12
100
10
8
80
6
4
60
2
0
400 2 4 6 8 10 12 14
8
80
6
4
60
2
0
400 2 4 6 8 10 12 14
20
0
0 2 4 6 8 10 12
November Desember
Minggu ke- Minggu ke
II III IV I II
5
2 5
5 5 5
2 8 5
1 2 3
4 2
12 12 14 11 5
58 70 84 95 100
12 14
12 14
10 12 14
S-C
Alvian Iac
710
SEPTEMBER OKTOBE
NO. Nama Kegiatan Bobot Minggu ke- Minggu
III IV I
1 Pembacaan Sejarah Lapangan 2 2
2 Pembuatan S-Curve 5 1 2
3 Analisa Data Reservoir 4 1 2
4 Menganalisa Jenis Reservoir, RF dan OOIP 3 1
5 Menyelaraskan data reservoir dan produksi 2
6 Progress Report Tim FDP-UTS 10
7 Pembuktian Cadangan Awal 14
8 Pembuktian Drive Mechanism, EUR, Nilai RF 17
9 Pembuatan skenario lapangan dan Plan of Development 15
10 Evaluasi 16
11 Pembuatan Presentasi 6
12 Pembuatan dan penyerahan Draft Final 6
71001500014
1
1
2
1 1
5 5
2 3 4 3 3
2 4 4 4 3
2 3 5 3 2
2 2 5 3 4
3 2 1
3 2 1
5 6 9 11 13 17 18 10 2
14 20 29 40 53 70 88 98 100
4
12
120
100
80
60
40
20
0
0 2 4 6 8 10 12 14
AFI MAULANA / 071001500006
KELOMPOK 12
SCHEDULE
KEGIATAN BOBOT SEPTEMBER
NO.
week I
1 Analisa Data Produksi 1
2 Analisa Sejarah Produksi Tiap Sumur 2
3 Menentukan Laju Produksi Tiap Sumur 12
4 Menentukan Kumulatif Produksi Tiap Sumur 12
5 Progress Report Tim FDP-UTS 10
6 Penyelarasan Kumulatif Produksi dengan Data Lapang 13
7 Penentuan Jumlah Produksi Tiap Lapisan 17
8 Perhitungan dan Perencanaan Skenario Produksi 10
9 Penentuan Skenario Produksi 10
10 Evaluasi dan Diskusi 9
11 Penulisan Laporan 2
12 Persiapan Presentasi 2
Total Bobot 100
Progress Planning (%) 0.00
Kumulatif Progress Planning (%) 0.00
Real Progress (%) 0.00
Kumulatif Real Progress (%) 0.00
4 12.00
5 24.00
6 38.00
7 52.00 100.00
8 66.00
9 81.00
KUMULATIF PROGRES
10 94.00
11 98.00
80.00
60.00
100.00
KUMULATIF PROGRES
80.00
12 100.00
12
0.00
0
SEPTEMBER OKTOBER
week II week III week IV week I week II week III week IV
1.00 UTS
1.00 1.00
2.00 5.00 5.00
2.00 2.00 8.00
5.00 5.00
1.00
100.00
KUMULATIF PROGRES
80.00
60.00
100.00
KUMULATIF PROGRES
80.00
60.00
40.00
20.00
0.00
0 2 4 6 8
MINGGU KE-
NOVEMBER DECEMBER
week I week II week III week IV week I week II
UAS
8.00 4.00
6.00 10.00 1.00
5.00 5.00
5.00 5.00
4.00 3.00 2.00
1.00 1.00
1.00 1.00
WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12
14.00 14.00 15.00 13.00 4.00 2.00
52.00 66.00 81.00 94.00 98.00 100.00
0.00 0.00 0.00 0.00 0.00 0.00
12.00 12.00 12.00 12.00 12.00 12.00
KELOMPOK 12
PLANNING
AKTUAL
PLANNING
AKTUAL
8 10 12 14
Minggu ke Kumulatif PlanKumulatif Real Progeres
1 1.00 0
2 2.00 1
3 5.00 5
4 12.00
5 24.00
6 38.00
7 52.00
8 66.00
9 81.00
10 94.00
11 98.00
12 100.00
NAMA : MARSHA SAUFIKA
NIM : 071001500077
120
100
80
KUMULATIF
60
40
20
-
1 2 3 4 5 6 7 8 9
MINGGU KE-
20
-
1 2 3 4 5 6 7 8 9
MINGGU KE-
TIME SCHEDULE PEMBORAN
1 3 2 5 7 14 15
1 4 6 11 18 32 47
1 2 2 3
1 3 5 8
S CURVE
KUMULATIF PLANNING
PROGRESS
KUMULATIF ACTUAL
PROGRESS
5 6 7 8 9 10 11 12
MINGGU KE-
5 6 7 8 9 10 11 12
MINGGU KE-
NOVEMBER DESEMBER
MINGGU II MINGGU III MINGGU IV MINGGU I MINGGU II MINGGU III MINGGU IV
4
4
5 3
3 4 4
3 4 3
3 3 2
2 2
2 2
16 13 13 9 2
63 76 89 98 100
3
5
8
12
12
12
11
11
10
8
4
4
100
NO.
1
2
3
4
5
6
7
8
9
10
11
12
S CURVE SURFACE FACILITIES
NAMA KEGIATAN
Total Progress
Planning Progress
Kumulatif Planning Progress
Actual Progress
Kumulatif Actual Progress
120
100
80
60
40
80
60
40
20
0
0 2
IMAM HASANI PRIHATMOJO
071001500058
WAKTU PELAKSAAN
OKTOBER
BOBOT Minggu ke-
III IV I II III IV
2 2
5 1 2 2
5 1 2 2
4 2 2
3 1 2
10 5 5
17 2
15 2
14
15
5
5
100
2 2 6 7 7 9
2 4 10 17 24 33
2 1 5 3
2 3 8 11
2 4 6 8 10 12 14
NOVEMBER DESEMBER
Minggu ke- Minggu ke-
I II III IV I II III
4 4 4 3
3 4 3 3
2 3 4 3 2
2 2 4 3 4
2 2 1
2 2 1
11 13 15 16 10 2
44 57 72 88 98 100
Pl anni ng
Actua l
Pl anni ng
Actua l
14
ER
ke-
IV
TIME SCHEDULE KEEKONOMIAN
NO
1
2
3
4
5
6
7
8
TOTAL
TIME SCHEDULE KEEKONOMIAN
KEGIATAN
120
100
80
60
40
60
40
20
0
0 2 4 6 8 10 12
100
80
60
40
20
0
0 2 4 6 8 10 12 14
40
20
0
0 2 4 6 8 10 12 14
Nama : Rahmat Valdi
NIM : 071.15.115
SEPTEMBER OKTOBER
BOBOT % Minggu ke
3 4 1 2 3 4
2 2
5 2 3
8 2 3 3
10 2 3 5
20 2
25 2
10
20
100
2 2 5 5 6 9
2 4 9 14 20 29
1 2 3 5
1 3 6 11
8 10 12 14
progress
10 12 14
12
10 12 14
NOVEMBER
1 2 3 4
4 5 5 4
6 4 4 5
1 2 2 2
5 5 5
11 16 16 16
40 56 72 88
SEPTEMBER
No Deskripsi Pekerjaan Bobot (%)
Week 1 Week 2 Week 3 Week 4
1 Pengambilan data lapangan 5 1 1
Menganalisa data serta
2 pengambilan peraturan-peraturan
7 perundangan 1
Pembuatan
3 studi lingkungan (amdal,ukl/upl)
10
4Report progres Tim FDP UTS12 1
Penentuan dan pembuatan
5 perencanaan HSE di setiap
15 bidang pekerjaan
perencanaan
6 abandontment lapangan
15
7 pembuatan CSR 21
8 Final Report 15
Total 100
Planning Progress % 0 0 1 3
Cummulative Planning Progress (%) 0 0 1 4
Actual Progress (%) 0 0 1 5
Cummulative Actual Progress (%) 0 0 1 6
120
100
80
60
40
20
0
0 2 4 6 8 10 12
40
20
0
0 2 4 6 8 10 12
5 6 7 8 9 10 11
TIME SCHEDULE HSE
OKTOBER NOVEMBER
Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week3
3
1 5
1 1 8
1 2 8
1 6 4 2 1
6 4 2 1
1 6 5 5 1
3 4 5
6 8 18 18 16 13 8
10 18 36 54 70 83 91
7 8
13 21
10 12 14
10 12 14
12 13 14 15 16
BER DESEMBER
Week4 Week 1 Week 2 Week3 Week4
1
1 1
1 1 1
1 1 1
4 3 2
95 98 100
spp