LAPORAN KEMAJUAN PEKERJAAN

Pengadaan dan Pemasangan Instalasi Listrik Pos Security


GI BOMASA JAYA ABADI - SIEMENS - MPE PERIODE : 02 Febuari 2022 s/d 07 Maret 2022

NO KEGIATAN Volume Satuan Total Bobot satuan Bobot Total (%) Vol. Mgg. Bobot Mgg. lalu Vol. Bobot Mgg. ini (%) Jumlah Jumlah Bobot (%)
Lalu (%) Mgg. ini Vol.

A. GEDUNG POS SECURITY 12.00 12.0 100.0000 100.0


I INSTALATION OF ELECTRICAL AND MECANICAL WORK

Installation of electric lighting to included for all neccesary (cabling plugs, fittings, lights, exhaust fans, etc.)

1 Downlight LED - 18 Watt 7.00 Rp 200,000 Rp 1,400,000 - - 7.00 100.00


2 Price for capacity electrical 1.00 Rp 3,250,000 Rp 3,250,000 - - - 1.00 100.00
3 Stop contact 2.00 Rp 250,000 Rp 500,000 - - - 2.00 100.00
4 Box Panel MCB 1.00 Rp 150,000 Rp 150,000 - - - 1.00 100.00
5 Exhaus fan ceiling 40 W/220 Volt (10") very low noice 1.00 Rp 1,400,000 Rp 1,400,000 - - - 1.00 100.00

C MOBILISASI & DEMOBILISASI - - 100.00 ©

1 Mob / Demob peralatan 1.00 ls

2 Mob / Demob Pekerja 1.00 ls

3 Pemasangan dan Margin Ankur 1.00 ttk

4 Biaya Erection 1.00 bh

TOTAL JUMLAH Rp 6,700,000 (A) + ( B

DIBULATKAN

BOBOT % 6,700,000 6,700,000

Popayato, 02 Febuari 2022

Dibuat Oleh Diperiksa Oleh Diperiksa Oeh Disetujui Oleh

Wawan Alfred Sroyer Berman T Hendrik Purba


MANDOR Site Manager SPV Project Manager