PERHITUNGAN BACK UP DATA

MC . 100 %
Balai Wilayah Sungai : Maluku Utara
SNVT : Pelaksanaan Jaringan Pemanfaatan Air Maluku, Provinsi Maluku Utara
Pelaksana Kegiatan : Pengembangan Dan Rehabilitasi, Jaringan Irigasi Permukaan,Rawa,dan Tambak
Paket Pekerjaan : Peningkatan D.I Tiley
Lokasi : Kab. Pulau Morotai
Sumber Dana : APBN
Item Pekerjaan Galian Tanah
TA : 2019 :

NO SKETSA GAMBAR

Rencana Sayap Hillir Rencana Sayap Hillir


+23.640 +23.640

Elev. Top Ensil


+ 21.630

Potongan a-a Rehab


Skala 1 : 125

KORDINAT A B
NO (A-B ) / 2
Kiri X Y X2 * Y1 X1 * Y2

1
317 6959.145 316.281 ###
2
6959.94 313.355 2,201,296.783 2180682.881475 10,306.95 ###
3
6960.94 313.355 2,181,245.354 2180931.9987 156.68 ###
316
4
6960.94 315.162 2,181,245.354 2193823.77228 (6,289.21) ###
5
6960.655 315.199 2,193,733.951 2194081.32706 (173.69) ###
315
6
6959.145 316.281 2,193,515.545 2201522.924055 (4,003.69) ###

314

at
Total Luas Kiri = 2.959 M2 at
313
at
KORDINAT A B
at
312 NO (A-B ) / 2
X Y X2 * Y1 X1 * Y2 at
1
6957.347 316.137 at
311
6959 6959.5 6960 6960.5 6961 6961.5
Kanan 2 2,199,327.489
6956.881 313.355 2180119.469185 9,604.01 at
316.5
3
6955.881 313.355 2,179,660.091 2179973.445755 (156.68) at
316 4 2,179,660.091
6955.881 314.549 2187965.412669 (4,152.66) at
315.5 5
6956.225 314.549 2,188,073.618 2187965.412669 54.10 at

315
6
6957.347 316.137 2,188,426.542 2199120.102825 (5,346.78)

314.5

314
Total Luas Kanan = 1.993 M2
313.5

313 Total Luas = 4.952 M2

312.5

312

311.5
.8

.2

.4

.6

.8

57
56

.2

.4

.6
55

56

56

56

56

57

57

57
69

69
69

69

69

69

69

69

69

69

Diketahui Oleh Diperiksa Oleh DIajukan OLeh


Direksi Teknik Pekerjaan Konsultan Supervisi PT. HALTIM MITRA SEJATI
CV. Della Concieta

Irwan Triyatmono Daryanto,ST.,MT Fardi Kalumata,SST


NIP.197403172014 01 001 Team Leader Pelaksana / Quantity
PERHITUNGAN BACK UP DATA
MC . 100 %
Balai Wilayah Sungai : Maluku Utara
SNVT : Pelaksanaan Jaringan Pemanfaatan Air Maluku, Provinsi Maluku Utara
Pelaksana Kegiatan : Pengembangan Dan Rehabilitasi, Jaringan Irigasi Permukaan,Rawa,dan Tambak
Paket Pekerjaan : Peningkatan D.I Tiley
Lokasi : Kab. Pulau Morotai
Sumber Dana : APBN
Item Pekerjaan Galian Tanah
TA : 2019 :

NO SKETSA GAMBAR

Rencana Sayap Hillir Rencana Sayap Hillir


+23.640 +23.640

Elev. Top Ensil


+ 21.630

Potongan b-b Rehab


Skala 1 : 125

KORDINAT A B
NO (A-B ) / 2
Kiri X Y X2 * Y1 X1 * Y2

297 1
6955.731 292.306 ###
2
6954.731 292.306 2,032,909.600 2033201.905686 (146.15) ###
296
3
6953.936 295.969 2,032,677.216 2058384.779339 (12,853.78) ###
4
6955.446 294.15 2,058,596.397 2045500.2744 6,548.06 ###
295
5
6955.731 294.113 2,046,028.274 2045687.089398 170.59 ###

294 6
6955.731 292.306 2,045,770.912 2033201.905686 6,284.50 ###

293
at
Total Luas Kiri = 3.222 M2 at
292

at

291 KORDINAT A B
at
NO (A-B ) / 2
X Y X2 * Y1 X1 * Y2 at
290
6953.5 6954 6954.5 6955 6955.5 6956 1
6957.261 293.442 at
Kanan 2
6957.261 292.306 2,041,552.582 2033649.133866 3,951.72 at
297
3
6958.261 292.306 2,033,941.440 2033649.133866 146.15 at
4
6959.545 295.73 2,034,316.761 2057766.52553 (11,724.88) at
296
5
6958.727 295.088 2,057,904.336 2053678.21496 2,113.06 at

295
6
6957.605 293.499 2,053,105.744 2042379.415773 5,363.16
7
6957.261 293.442 2,041,949.146 2041653.52641 147.81
294

293 Total Luas Kanan = 2.971 M2

292
Total Luas = 6.193 M2

291

290
6957 6957.5 6958 6958.5 6959 6959.5 6960

Diketahui Oleh Diperiksa Oleh DIajukan OLeh


Direksi Teknik Pekerjaan Konsultan Supervisi PT. HALTIM MITRA SEJATI
CV. Della Concieta

Irwan Triyatmono Daryanto,ST.,MT Fardi Kalumata,SST


NIP.197403172014 01 001 Team Leader Pelaksana / Quantity
PERHITUNGAN BACK UP DATA
MC . 100 %
Balai Wilayah Sungai : Maluku Utara
SNVT : Pelaksanaan Jaringan Pemanfaatan Air Maluku, Provinsi Maluku Utara
Pelaksana Kegiatan : Pengembangan Dan Rehabilitasi, Jaringan Irigasi Permukaan,Rawa,dan Tambak
Paket Pekerjaan : Peningkatan D.I Tiley
Lokasi : Kab. Pulau Morotai
Sumber Dana : APBN
Item Pekerjaan Timbunan Tanah
TA : 2019 :

NO SKETSA GAMBAR

Rencana Sayap Hillir Rencana Sayap Hillir


+23.640 +23.640

Elev. Top Ensil


+ 21.630

Potongan a-a Rehab


Skala 1 : 125

KORDINAT A B
NO (A-B ) / 2
Kiri X Y X2 * Y1 X1 * Y2
318
1
6899.44 317.475 ###
317.5
2
6899.74 317.525 2,190,494.957 2190744.686 (124.86) ###
317
3
6899.74 317.725 2,190,839.944 2192219.8915 (689.97) ###
316.5 4 2,191,266.717
6896.74 317.725 2192219.8915 (476.59) ###
316 5
6895.219 316.204 2,190,783.457 2180776.77496 5,003.34 ###
315.5 6
6898.346 316.281 2,181,284.599 2180826.760539 228.92 ###

315 6899.231 315.647 2,182,095.680 2177442.219862 2,326.73

314.5 6899.44 317.475 2,177,787.538 2190333.361725 (6,272.91) at


6894 6895 6896 6897 6898 6899 6900 6901
Total Luas Kiri = 5.348 M2 at

at
KORDINAT A B
at
NO (A-B ) / 2
X Y X2 * Y1 X1 * Y2 at
Kanan
1
318 6918.849 317.725 at

317.5
2
6915.76 317.725 2,197,309.846 2198291.298525 (490.73) at
3
6915.76 317.525 2,197,309.846 2195926.694 691.58 at
317
4
6916.06 317.475 2,196,021.952 2195580.906 220.52 at
316.5
5
6916.299 315.39 2,195,752.025 2181256.1634 7,247.93 at
316
6
6916.827 316.137 2,181,498.068 2186498.016963 (2,499.97)
315.5
7
6918.849 317.725 2,187,304.166 2197648.858575 (5,172.35)
315

314.5
Total Luas Kanan = 3.018 M2
314
6915.5 6916 6916.5 6917 6917.5 6918 6918.5 6919 6919.5

Total Luas = 8.366 M2

Diketahui Oleh Diperiksa Oleh DIajukan OLeh


Direksi Teknik Pekerjaan Konsultan Supervisi PT. HALTIM MITRA SEJATI
CV. Della Concieta

Irwan Triyatmono Daryanto,ST.,MT Fardi Kalumata,SST


NIP.197403172014 01 001 Team Leader Pelaksana / Quantity
PERHITUNGAN BACK UP DATA
MC . 100 %
Balai Wilayah Sungai : Maluku Utara
SNVT : Pelaksanaan Jaringan Pemanfaatan Air Maluku, Provinsi Maluku Utara
Pelaksana Kegiatan : Pengembangan Dan Rehabilitasi, Jaringan Irigasi Permukaan,Rawa,dan Tambak
Paket Pekerjaan : Peningkatan D.I Tiley
Lokasi : Kab. Pulau Morotai
Sumber Dana : APBN
Item Pekerjaan Timbunan Tanah
TA : 2019 :

NO SKETSA GAMBAR

Rencana Sayap Hillir Rencana Sayap Hillir


+23.640 + 23.640

Elev. Top Ensil


+ 21.630

Potongan b-b Rehab


Skala 1 : 125

KORDINAT A B
NO (A-B ) / 2
Kiri X Y X2 * Y1 X1 * Y2
297 1 6899.44 296.426 ###
296.5 2 6899.74 296.476 2,045,262.329 2045518.37344 (128.02) ###
296 3 6899.74 296.676 2,045,607.316 2046987.26424 (689.97) ###
295.5 4 6896.74 296.676 2,046,097.236 2046987.26424 (445.01) ###
295 5 6895.975 295.911 2,045,870.279 2040821.23014 2,524.52 ###
294.5 6 6898.346 295.969 2,041,296.463 2040994.824775 150.82 ###
294
7 6899.262 294.866 2,041,967.675 2034087.691636 3,939.99

293.5
8 6899.44 296.426 2,034,410.275 2045120.637612 (5,355.18) at
6895.5 6896 6896.5 6897 6897.5 6898 6898.5 6899 6899.5 6900
Total Luas Kiri = 2.856 M2 at
at
Tengah KORDINAT A B at
NO (A-B ) / 2
293.6 X Y X2 * Y1 X1 * Y2 at
293.4
293.2 1 6915.36 293.442 at
293
292.8
2 6915.36 293.514 2,029,257.069 2029754.97504 (248.95) at
292.6 3 6904.366 293.514 2,026,528.082 2029754.97504 (1,613.45) at
292.4
292.2 4 6910.298 292.595 2,028,269.207 2020182.96977 4,043.12 at
292
6902 6904 6906 6908 6910 6912 6914 6916 6918 5 6915.36 293.442 2,023,399.759 2027771.665716 (2,185.95) at

Total Luas Tengah = 5.234 M2


KORDINAT A B
NO (A-B ) / 2
Kanan X Y X2 * Y1 X1 * Y2
297 1 6918.849 296.676
296.5
296 2 6915.76 296.676 2,051,740.014 2052656.445924 (458.22)
295.5
3 6915.76 296.476 2,051,740.014 2050356.86176 691.58
295
294.5 4 6916.06 296.426 2,050,445.805 2050011.07376 217.37
294
293.5
5 6916.299 294.341 2,050,170.847 2035680.01646 7,245.42
293
6915.5 6916 6916.5 6917 6917.5 6918 6918.5 6919 6919.5
6 6916.827 295.088 2,035,905.776 2040916.839312 (2,505.53)
7 6917.644 295.73 2,041,313.733 2045513.24871 (2,099.76)
8 6918.849 296.676 2,046,111.215 2052298.951344 (3,093.87)
Total Luas Kanan = 3.017 M2

Total Luas = 11.12 m2

Diketahui Oleh Diperiksa Oleh DIajukan OLeh


Direksi Teknik Pekerjaan Konsultan Supervisi PT. HALTIM MITRA SEJATI
CV. Della Concieta

Irwan Triyatmono Daryanto,ST.,MT Fardi Kalumata,SST


NIP.197403172014 01 001 Team Leader Pelaksana / Quantity
PERHITUNGAN BACK UP DATA
MC . 0 %
Balai Wilayah Sungai : Maluku Utara
SNVT : Pelaksanaan Jaringan Pemanfaatan Air Maluku, Provinsi Maluku Utara
Pelaksana Kegiatan : Pengembangan Dan Rehabilitasi, Jaringan Irigasi Permukaan,Rawa,dan Tambak
Paket Pekerjaan : Peningkatan D.I Tiley
Lokasi : Kab. Pulau Morotai
Sumber Dana : APBN
TA : 2019
Item Pekerjaan : REKAPAN TIMBUNAN DAN GALIAN

LUAS TIMBUNAN LUAS GALIAN JARAK VOLUME VOLUME BORROW


PATOK
M2 M2 M GALIAN TIMBUNAN MATERIAL
PA 8.366 4.952
PB 11.120 6.193 5.000 27.863 48.715

5.000 27.86 48.72 -


Total Volume Galian 27.86 m3
Timbunan Biasa Dipadatkan 48.72 m3
Timbunan Biasa Dipadatkan ( Borrow Material ) - m3