Nama : Aldi Reza Febrian

Nim : 2017310007

Mata Kuliah : Kontruksi Kapal II

KEBUTUHAN PLAT DAN PROFILE KAPAL FERRY RO-RO 3200 GT


DIMENSI Total Volume Berat Pelat Harga Pelat
MATERIAL JUMLAH (Lembar)
TEBAL (m) X PANJANG (m) X LEBAR (m) (m3) (Kg) (Rp)
PELAT KAPAL 0.006 X 2.438 X 1.219 32 0.571 4479.281 44,792,808
PELAT KAPAL 0.006 X 12.192 X 3.353 30 7.358 57763.123 577,631,235
PELAT KAPAL 0.008 X 12.192 X 3.353 85 27.798 218216.244 2,182,162,443
PELAT KAPAL 0.008 X 12.192 X 1.829 26 4.638 36410.082 364,100,815
PELAT KAPAL 0.008 X 12.192 X 1.524 7 1.041 8168.035 81,680,353
PELAT KAPAL 0.009 X 12.192 X 2.438 4 1.070 8400.030 84,000,295
PELAT KAPAL 0.009 X 12.192 X 3.353 7 2.575 20217.093 202,170,932
PELAT KAPAL 0.010 X 12.192 X 3.353 19 7.767 60972.186 609,721,859
PELAT KAPAL 0.010 X 12.192 X 3.048 2 0.743 5834.311 58,343,109
PELAT KAPAL 0.010 X 12.192 X 1.524 7 1.301 10210.044 102,100,441

Total Panjang Las Total Hari Harga Pengelasan


Geladak Jumlah Welder
(m) 1 Hari 40 meter 1 Hari / 400 rb x jumlah welder
Bottom 327 8 5 Rp 16,337,400
Double bottom 327 8 5 Rp 16,367,800
Car Deck 445 11 6 Rp 26,700,840
Geladak Antara 218 5 5 Rp 10,881,500
Main Deck 445 11 6 Rp 26,700,840
Second Deck 355 9 5 Rp 17,739,600
Geladak anjungan 29 1 5 Rp 1,462,800
Compass Deck 29 1 5 Rp 1,462,800
Total Rp 117,653,580

Total (dus) Harga Elektroda Kecepatan Pengelasan (Jam) Harga Listrik (Kw)
elektroda terpakai (kg)
(5 Kg / Dus) ( 1 Dus / 80 Rb) Metode SMAW 5 m / Jam (Rp 1.646 /kwh)
163.374 33 Rp 2,613,984 65 Rp 107,565
163.678 33 Rp 2,618,848 65 Rp 107,766
222.507 45 Rp 3,560,112 89 Rp 146,499
108.815 22 Rp 1,741,040 44 Rp 71,644
222.507 45 Rp 3,560,112 89 Rp 146,499
177.396 35 Rp 2,838,336 71 Rp 116,798
14.628 3 Rp 234,048 6 Rp 9,631
14.628 3 Rp 234,048 6 Rp 9,631
DAFTAR KUANTITAS DAN HARGA SATUAN BAHAN/MATERIAL
TERMASUK UPAH DAN PERALATAN
PEMBANGUNAN 1 (SATU) UNIT KAPAL FERRY RO-RO 3200 GT

Harga Total
N Harga
o. Jenis Pekerjaan/Bahan Vol. Sat. Satuan (Rp.) Bobot
1 2 3 4 5 6 7

I LAMBUNG

1 Pelat baja & profil 219 Lembar 10,000,000 2,190,000,000

2 Las electrode 2 Ton 20,000,000 40,000,000

3 Oxygen 4,400 Btl 50,000 220,000,000

4 Sanblasted 10,500 M2 75,000 787,500,000

5 Gas LPG 548 Btl 400,000 219,200,000


Kaleng
6 Cat primer 15 (20kg) 1,200,000 18,000,000
Kaleng
7 Cat AC 16 (20kg) 1,400,000 22,400,000
Kaleng
8 Cat AF 8 (20kg) 1,850,000 14,800,000

9 Cat FP 8,756 Ltr 100,000 875,600,000

10 Cat Epoxy 4,063 Ltr 100,000 406,300,000

11 Cat BTP 200 Ltr 150,000 30,000,000


Kaleng
12 Deck Painting 8 (20kg) 2,500,000 20,000,000

13 Thinner 1,700 Ltr 35,000 59,500,000

14 Zink Anode 12 Kg 1 Shippset 200,000,000 200,000,000

Sub total I 5,103,300,000

II PERLENGKAPAN LAMBUNG

1 Pintu 1 Shippset 250,000,000 250,000,000

2 Seal trunk 1 Shippset 150,000,000 150,000,000

3 Jendela Alumunium persegi 88 Buah 1,550,000 136,400,000


4 Jendela Alumunium bulat 32 Buah 1,500,000 48,000,000

5 Exhaust Fan 10" WC/KM 1 Shippset 90,000,000 90,000,000

6 Double bollard 6 Buah 1,700,000 10,200,000


Lantai dek ABK/PNP dilapisi deck
7 komposit/Vynil 1 Shippset 420,000,000 420,000,000
Dinding isolasi disesuaikan dengan
8 aturan yang berlaku 1 Shippset 550,000,000 550,000,000

9 Langit-langit 1 Shippset 430,000,000 430,000,000

10 House pipe & Bellmouth 1 Shippset 75,000,000 75,000,000

11 WC/KM dengan pelengkap 1 Shippset 200,000,000 200,000,000

12 Cerobong asap 1 Shippset 130,000,000 130,000,000

13 Lifeboat 2 Unit 500,000,000 1,000,000,000


Alat lift/release untuk Lifeboat
14 (dewi-dewi) 2 Set 200,000,000 400,000,000

15 Chrismas Tree/tiang compass 1 Shippset 15,000,000 15,000,000

16 Natural ventilasi ruang pnp 8 Unit 10,000,000 80,000,000

17 Natural ventilasi ruang cargo 4 Unit 10,000,000 40,000,000

18 Mekanik ventilasi ruang pnp 4 Unit 12,000,000 48,000,000

19 Televisi ukuran 29" 14 Unit 3,500,000 49,000,000

20 VCD player 12 Unit 750,000 9,000,000

21 Tutup palka 1 Shippset 300,000,000 300,000,000

22 Lantai kamar mesin pelat kembang 1 Shippset 150,000,000 150,000,000

23 Deck covering material 1 Shipset 70,000,000 70,000,000

24 Tangga 1 Shippset 440,000,000 440,000,000

25 Railing 1 Shippset 220,000,000 220,000,000

26 Tangga Samping 2 Unit 100,000,000 200,000,000

27 Kabin Perwira dan ABK 1 Shippset 200,000,000 200,000,000


Kabin Penumpang dan
28 Perlengkapannya 1 Shippset 800,000,000 800,000,000

29 Kabin Kadet 1 Shippset 100,000,000 100,000,000


30 Tempat Tidur Kelas Ekonomi 400 Buah 2,000,000 800,000,000

31 Klinik, Mushola & Perlengkapannya 1 Set 150,000,000 150,000,000

32 Pendingin udara central 2 Set 200,000,000 400,000,000

33 Perlengkapan unit pendingin 1 Set 270,000,000 270,000,000

Sub total II 8,230,600,000

II GALLEY DAN PERLENGKAPAN


I MESS ROOM
Galley, Restaurant, Meeting
Room

1 Galley dan Perlengkapannya 1 Set 270,000,000 270,000,000


Ruang Pendingin (Store) dan
2 Perlengkapanan 3 Set 180,000,000 540,000,000

3 Restauran/Dinning Room 1 Set 70,000,000 70,000,000

4 Meeting Room 1 Set 70,000,000 70,000,000


Mess Room Perwira, ABK dan
perlengkapan

5 Meja makan + lemari + kursi 1 Lot 25,000,000 25,000,000

6 Lemari es 200 L 2 Unit 3,500,000 7,000,000

7 Perlengkapan makan 1 Lot 5,000,000 5,000,000

Sub total III 987,000,000