LOKASI : KAWASAN INDUSTRI KENDAL - JAWA TENGAH PEKERJAAN : BANGUNAN EXT. 37 M X 30 M ( 2 LANTAI )
Harga Sat. Total Harga
No. PEKERJAAN Sat. Volume Rp Rp I. PEKERJAAN PERSIAPAN 1 Pagar Sementara ( Depan Saja) m2 90.00 - 3 traspot pekerja Ls 1.00 -
II PEKERJAAAN TANAH & PONDASI
1 Pengukuran m2 1,110.00 - 2 Galian Tanah : (exavator,hanya perapian galian) - Galian Pile Cap m3 56.34 - - Galian Sloof m3 104.76 - - Pembuangan tanah m3 40.28 - 3 Urug Pasir T. 5 cm di bawah : - Pile Cap m2 77.31 - - Sloof ( Tie Beam ) m2 153.00 - - Lantai m2 1,038.00 - 4 Lantai Kerja t = 5 cm, di bawah : - Pile Cap m2 77.31 - - Sloof ( Tie Beam ) m2 153.00 - - Lantai m2 1,038.00 - 5 Pekerjaan Beton (incl. Tulangan and Bekisting) K-300 a. Pile cap (pembesian,bekisting,cor) m3 45.08 - b. Sloof 30/50 (pembesian,bekisting,cor) m3 54.00 - c. Sloof 25/40 (pembesian,bekisting,cor) m3 18.00 - d. Kolom Pedestal (pembesian,bekiting,cor) m3 21.00 - e. Dinding Beton Penahan Tanah T. 20 cm (pembesian,bekisting,cor) m3 42.00 - f. Lantai T = 15 cm, M6 - 2 layer (pembesian,beskiting,cor,trowel halus flat) m2 1,038.00 -
6 Lantai Beton (Lt. 02) t = 17cm (pembesian,bekiting,cor,trowel halus flat) m2 1,110.00 -
III PEKERJAAN ARSITEKTUR & FINISHING
III.A PEKERJAAN DINDING 1 Pas. Dinding bata ringan T. 10 mm (inc. Ring Balk & Kolom Praktis,bongkar psg.scapolding ) -Dinding Pabrik H. 300 cm m2 567.00 - 2 Plester & Acian Dinding m2 1,134.00 - 3 Plester & Acian Kolom Padestal m2 84.00 - 4 Plester & Acian Dinding Penahan Tanah m2 201.00 -
654758760.xlsx hal : 1/4
BILL OF QUANTITY PROYEK : GUDANG TOB -7 KIK LOKASI : KAWASAN INDUSTRI KENDAL - JAWA TENGAH PEKERJAAN : BANGUNAN EXT. 37 M X 30 M ( 2 LANTAI )
Harga Sat. Total Harga
No. PEKERJAAN Sat. Volume Rp Rp III.B PEKERJAAN OPENINGAN KUSEN 1 Kusen Alumunium uk. 3'' ex. Alexindo PC Putih m' 58.34 - 2 Daun Pintu Kaca 6mm , Rangka Alumunium ex. Alexindo PC Putih m' 28.16 - 3 Daun Jendela Kaca 6mm , Rangka Alumunium ex. Alexindo PC Putih m' 43.60 - 4 Daun KM/WC , Panel Alumunium ex. Alexindo PC Putih m' 5.00 - 5 Pintu Besi 100 x 220 cm Unit 10.00 - 6 Pintu Rolling Door -Pintu Rolling Door - Uk. @ 4 x 4 m 7 unit (kolom 30x30, Ring balok 30x40) m' 84.00 -
III.C PEKERJAAN FINISHING LANTAI DAN DINDING
2 Lt. Toilet Keramik 40 x 40 ex. Roman / Setara m2 8.00 - 3 Dinding Keramik Toilet 20x 40 ex. Roman / setara m2 38.40 -
IV PEKERJAAN MEKANIKAL, ELEKTRIKAL & PLUMBING
a PEKERJAAN SANITAIR 1 Closet duduk ex. TOTO, CW 420J/SW 420 JP unit 1.00 - 2 Wastafel LW 781 CJ ex. TOTO unit 2.00 - 3 Floor Drain ex. TOTO, TX 1 AN unit 2.00 - 4 Urinoir ex. TOTO unit 3.00 - 5 Jet Washer ex. San-Ei unit 1.00 - 6 Meja Wastafel (meja beton,keramik+wastafel) unit 2.00 -
654758760.xlsx hal : 2/4
BILL OF QUANTITY PROYEK : GUDANG TOB -7 KIK LOKASI : KAWASAN INDUSTRI KENDAL - JAWA TENGAH PEKERJAAN : BANGUNAN EXT. 37 M X 30 M ( 2 LANTAI )
Harga Sat. Total Harga
No. PEKERJAAN Sat. Volume Rp Rp b Pekerjaan Lain - lain Ground tank 1.5 x 1.5 x 2 (pembesian,bekisting,cor,pasang keramik,upah psg 1 unit 1.00 - waterprofing coating) 2 Septic tank & resapan (pembesian,bekisting,cor) unit 1.00 - 4 Saluran Buis Beton dia 40cm (incl. Bak Kontrol) m' 135.74 -
V PEKERJAAN HALAMAN , PAGAR & BETON DUIKER (JALAN MASUK)
a PEKERJAAN PAGAR PINTU PAGAR DEPAN 1 - Galian Tanah m3 2.00 - 2 - Urug Kembali m3 1.00 - 3 - Pondasi Tapak 80 x 80 (pembesian,bekisting,cor) m3 0.32 - 4 - Kolom 30 x 30 H. 300 cm (pembesian,bekisting,cor) m3 0.65 - b PEKERJAAN DUIKER BETON JALAN MASUK -Duiker Jalan Masuk 6m x 12 m 1 Pondasi Batu Kali - Galian Tanah m3 96.00 - - Urug Kembali m3 48.00 - - Pondasi Batu Kali m3 60.00 - 2 Beton Jalan Masuk (Duiker) - Balok Beton 25 x 50 (pembesian,bekisting,cor) m3 6.75 - - Beton K. 300-T. 20 cm (pembesian,bekisting,cor,trowel garis) m3 14.40 -
654758760.xlsx hal : 3/4
BILL OF QUANTITY PROYEK : GUDANG TOB -7 KIK LOKASI : KAWASAN INDUSTRI KENDAL - JAWA TENGAH PEKERJAAN : BANGUNAN EXT. 37 M X 30 M ( 2 LANTAI )
Harga Sat. Total Harga
No. PEKERJAAN Sat. Volume Rp Rp VI PEKERJAAN JEMBATAN CONNECTING a Pekerjaan Beton (incl. Tulangan and Bekisting) K-300 1 - Pile cap (pembesian,bekisting,cor) m3 0.43 - 2 - Kolom Padestal (pembesian,bekisting,cor) m3 1.75 -