Anda di halaman 1dari 11

rbukhori.blogspot.

com

Laporan Hasil uji pembetonan


Gedung Siliwangi Jakarta Pusat

Dites oleh: Ridwan Bukhori


f'c rencana: 22.5 Mpa
Kuat Tekan (Mpa)
Kode
Tanggal Jam Hasil Uji
No Benda Rata-rata 3
Pembuatan (WIB) Sil. A Sil. B Umur 28
Uji Hasil uji
Hari

1 3/22/2017 7:00 S1 23 27 22.5 24.17


2 3/22/2017 7:30 S2 25 22.5 24 23.83
3 3/22/2017 8:00 S3 22 24 23 23.00
4 3/22/2017 9:00 S4 23 23 22 22.67
5 3/23/2017 7:00 S5 22 22 24 22.67
6 3/23/2017 7:30 S6 23 25 25 24.33
7 3/23/2017 8:00 S7 22 21 25 22.67
8 3/23/2017 9:00 S8 21 23 24 22.67
9 3/23/2017 10:00 S9 25 27 27 26.33
10 3/24/2017 7:00 K1 21 22.5 25 22.83
11 3/24/2017 7:30 K2 22.5 25 22 23.17
12 3/24/2017 8:00 K3 24 23 22 23.00
13 3/24/2017 9:00 K4 23 24 22 23.00
14 3/25/2017 7:00 K5 22 25 22 23.00
15 3/25/2017 7:30 K6 23 22 22.5 22.50
16 3/25/2017 8:00 K7 22 23 26 23.67
17 3/25/2017 9:00 K8 21 22 25 22.67
18 3/25/2017 10:00 K9 25 23 21 23.00
19 3/26/2017 7:00 K10 26 25 22 24.33
20 3/26/2017 7:30 B1 21 24 23 22.67
21 3/26/2017 8:00 B2 25 25 25 25.00
22 3/26/2017 9:00 B3 26 26 22.5 24.83
23 3/26/2017 10:00 B4 21 22 25 22.67
24 3/26/2017 11:00 B5 22 25 23 23.33
25 3/26/2017 12:00 B6 23 25 21 23.00
26 3/26/2017 12:30 B7 24 19 25 22.67
27 3/27/2017 7:00 B8 26 25 22 24.33
28 3/27/2017 7:30 B9 21 23 26 23.33
29 3/27/2017 8:00 B10 21 28 22 23.67
30 3/27/2017 9:00 B11 22 23 24 23.00

Pengawas
rbukhori.blogspot.com

Ir. Sam Witwickiy


rbukhori.blogspot.com

rbukhori.blogspot.com

1 19
30 Kuat
19 tekan silinder dan hasil uji dari pengambilan
contoh beton
30.0

25.0

Hasil Uji 28 hari


Kuat Tekan (Mpa)

20.0 f'c-3,5
Sil. A
15.0 Sil. B

10.0

5.0
0 5 10 15 20 25 30
Nomor

1 22.5
Evaluasi kuat tekan produk beton
3030 22.5

25
Kuat Tekan (Mpa)

20
f'c
Hasil Uji 28 hari
15 Rata2

10

5
0 5 10 15 20 25 30
Nomor
rbukhori.blogspot.com

UJI PALU BETON (HAMMER TEST)


(SNI 03-4430-1997/ASTM C. 805-97)

Laporan :
Lokasi :
Pemberi Tugas : Arah pukuan Horizontal
Jumlah Lantai :
Proyek :

Elemen Struktur Kolom K6


Sudut Pukulan 90 90 90
Kode Bidang Uji k6-A K6-B K6-C
1 32 20 26
2 20 27 26
3 33 23 27
4 30 25 24
Nilai Lenting Palu Beton 5 30 28 26
(R) 6 29 23 27
7 31 29 29
8 30 28 26
9 27 25 28
10 27 24 22
R max 33 29 29
R min 20 20 22
R rata2 28.9 25.2 26.1
Simpangan Baku 3.6651512 2.82055944 1.9692074
Koef. Variasi 13.4333333 7.95555556 3.87777778
Terkoreksi (Kg/cm^2) 275 210 210

f'c rencana: 22.5 Mpa = 229.275 kg/cm^2


Rata-rata 3 benda uji = 231.666667 kg/cm^2 > 229.275
Sesuai rencana
rbukhori.blogspot.com

Pilih sesuai arah pukulan: Keatas, kebawah, atau horizontal diamter (d) =

No

1
2
3

maka f'cc =
rbukhori.blogspot.com

Pengujian Bor Inti


Gedung Siliwangi Jakarta Pusat

diamter (d) = 9.5 cm l/d = 1.25


I= 11.875 cm
C0 = 0.92 Arah pukuan Horizontal
C1 = 0.96
C2 = 1
Beban Kuat Tekan Kuat Tekan f'c terkoreksi
Kode sebelum sebelum f;cc(M,pa)
Max P A (cm^2)
Sample koreksi koreksi C0 C1 C2 C0XC1XC2
(Kn) (Kg/cm^2) (Mpa)
K6-A 185 70.882 260.996 26.100 24.01 25.06 26.10 23.0512
K6-B 155 70.882 218.673 21.867 20.12 20.99 21.87 19.3132
K6-C 165 70.882 232.781 23.278 21.42 22.35 23.28 20.5592
Rata-rata = 20.9745

maka f'cc = 20.9745 < f'c = 22.5 Tidak memenuhi

file excel ini masih banyak kekurangannya, bila ada kesalahan mohon koreksinya
Terima Kasih
rbukhori.blogspot.com

Sumber : Materi kuliah "Evaluasi Struktur Bangunan" Bapak Maris Setyo Nugroho, A.Md.T.,S.Pd.T.,cand M.Eng
rbukhori.blogspot.com
RBUKHORI.BLOGSPOT.COM

Anda mungkin juga menyukai