Anda di halaman 1dari 7

B 03

ARS 04 ARS 06

12

2.500
TAMAN TAMAN
5.000 GL -0.25 GL -0.25

11
J3 J4

R.SANTAI
2.500

FFL ±0.00
TERAS
FFL -0.05

P1

A 10
DAPUR A
ARS 03 BORDES 9 8 7 6 5 43 2 1 ARS 03
NAIK FFL ±0.00
FFL +1.75
2.000

10

P2
11 12 13 14
4.000

9
P3 KM/WC
FFL -0.05
2.000
17.000

TAMAN
GL -0.25 R.KELUARGA
J3 FFL ±0.00
R.MAKAN
8
FFL ±0.00
02
1.000

ARS 06 P2
7
1.000

6
4.500

R.TIDUR
J2 FFL ±0.00
2.000

5
R.TAMU
FFL ±0.00 J5
4
0.500

TERAS P1
3 FFL -0.05
J1 J1 J1
1.250

2
TAMAN
3.500

GL -0.25
TAMAN
2.250

GL -0.25
CARPORT
FFL -0.40
KEMIRINGAN 1,5%

1
1.750 3.250 1.400 2.600 1.000 2.000

2.000 7.000 3.000

12.000

A B D B E F G H
01 ARS 04

02 DENAH LANTAI 1 C
ARS 05

Ars 02 Skala 1:100

LOKASI PROYEK DETAIL ENGINEERING DESIGN (DED) PERENCANA


C:\Users\UNTUK GURU\Documents\logo ali.png

RUBBAYYI SHAFFIYYAH
NAMA PROYEK RUMAH 2 LT TYPE BOUGENVILE
TANGGAL REVISI TGL CATATAN
1.SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN MILILMETER (MM)
JUDUL GAMBAR MENGETAHUI 2.SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN METER (M)
3.TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
TENAGA AHLI 4.KEMIRINGNA ATAP 35°
DENAH LANTAI 1 DRAFTER
5.TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN ACIAN
NOTASI : FFL = FLOOR FINISHING LEVEL
GL = GROUND LEVEL = ARAH POTONGAN
SKALA GAMBAR KODE GAMBAR NO.GMB JML.GMB DEVELOPER FD = FLOOR DRAIN
Up = NAIK = ARAH TAMPAK
1 : 100 SMKN 1 NGANJUK Dn = TURUN
B
ARS 04

12

2.500
5.000

11
J3 J2
BALKON R.SANTAI
FFL +3.45
2.500

FFL +3.50

P1 R.TIDUR
FFL +3.50

A 10 A
ARS 03 9 8 7 6 5 43 2 1 ARS 03
BORDES
2.000

FFL +1.75
10
TURUN P2
11 12 13 14 15 16 17 18 19
4.000

9
P3 KM/WC
FFL +3.45
2.000
17.000

TAMAN J3
GL -0.25
VOID
R.DUDUK
8 FFL +3.50
02
1.000

P2
ARS 06
7
1.000

6
4.500

R.KERJA R.TIDUR
J2 FFL +3.50 FFL +3.50
2.000

P1 J2
4
0.500

J1 J1 J1
3 BALKON
FFL +3.45
1.250

2
3.500

2.250

1
1.750 3.250 1.400 2.600 1.000 2.000

2.000 7.000 3.000

12.000

A B D E F G H
01 B
03 DENAH LANTAI 2 C
ARS 05
ARS 04

Ars 03 Skala 1:100

LOKASI PROYEK DETAIL ENGINEERING DESIGN (DED) PERENCANA


C:\Users\UNTUK GURU\Documents\logo ali.png

RUBBAYYI SHAFFIYYAH
NAMA PROYEK RUMAH 2 LT TYPE BOUGENVILE
TANGGAL REVISI TGL CATATAN
1.SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN MILILMETER (MM)
JUDUL GAMBAR MENGETAHUI 2.SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN METER (M)
3.TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
TENAGA AHLI 4.KEMIRINGNA ATAP 35°
DENAH LANTAI 2 DRAFTER
5.TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN ACIAN
NOTASI : FFL = FLOOR FINISHING LEVEL
GL = GROUND LEVEL = ARAH POTONGAN
SKALA GAMBAR KODE GAMBAR NO.GMB JML.GMB DEVELOPER FD = FLOOR DRAIN
Up = NAIK = ARAH TAMPAK
1 : 100 SMKN 1 NGANJUK Dn = TURUN
BUBUNGAN EL+11.26

3.657
4.457

RING BALK 2 EL+7.60


1.100

RING BALK 1 EL+6.80


PLAFOND EL+6.50
0.500

HEAD EL+6.00
11.257

3.300
2.500

MUKA LANTAI 1 EL+3.50


0.400

PLAFOND EL+3.10
1.350
3.500

BORDES EL+1.75
1.750

MUKA L.DASAR EL±0.00


0.400

MUKA TANAH EL-0.40

2.000 3.000 4.000 3.000

5.000 7.000

12.000

A C D E G

06 TAMPAK DEPAN
Ars 06 Skala 1:120

LOKASI PROYEK DETAIL ENGINEERING DESIGN (DED) PERENCANA


C:\Users\UNTUK GURU\Documents\logo ali.png

RUBBAYYI SHAFFIYYAH
NAMA PROYEK RUMAH 2 LT TYPE BOUGENVILE
TANGGAL REVISI TGL CATATAN
1.SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN MILILMETER (MM)
JUDUL GAMBAR MENGETAHUI 2.SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN METER (M)
3.TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
TENAGA AHLI 4.KEMIRINGNA ATAP 35°
TAMPAK DEPAN DRAFTER
5.TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN ACIAN
NOTASI : FFL = FLOOR FINISHING LEVEL
GL = GROUND LEVEL = ARAH POTONGAN
SKALA GAMBAR KODE GAMBAR NO.GMB JML.GMB DEVELOPER FD = FLOOR DRAIN
Up = NAIK = ARAH TAMPAK
1 : 100 SMKN 1 NGANJUK Dn = TURUN
DEVELOPER
BUBUNGAN EL+11.26 SMKN 1 NGANJUK
DETAIL ENGINEERING DESIGN (DED)
NAMA PROYEK
3.657

RUMAH TINGGAL LANTAI 2


4.457

LOKASI PROYEK
TIRTASANI PR. II / 60
KARANG PLOSO KAB.MALANG 65152
RING BALK 2 EL+7.60
CATATAN
1.100

1. SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN


RING BALK 1 EL+6.80 MILILMETER (MM)
PLAFOND EL+6.50 2. SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN
0.500

METER (M)
HEAD EL+6.00 3. TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
4. KEMIRINGNA ATAP 35°
11.257

5. TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN


ACIAN
3.300

NOTASI :
2.500

FFL = FLOOR FINISHING LEVEL


GL = GROUND LEVEL
FD = FLOOR DRAIN
Up = NAIK
Dn = TURUN
KODE KUSEN :
MUKA LANTAI 1 EL+3.50
0.400

= ARAH POTONGAN P = PINNTU


PLAFOND EL+3.10 J = JENDELA
= ARAH TAMPAK
PJ = PINTU JENDELA
1.350

JUDUL GAMBAR SKALA


TAMPAK SAMPING KIRI 1:100
3.500

BORDES EL+1.75
1.750

REVISI TTD TGL


MUKA L.DASAR EL±0.00
0.400

MUKA TANAH EL-0.40


MENGETAHUI / MENYETUJUI TTD TGL
2.250 1.250 2.500 1.000 3.000 2.000 2.500 2.500
3.500 3.500 5.000 5.000 KONSULTAN / PERENCANA TTD TGL
17.000
TENAGA AHLI TTD TGL
1 2 3 5 6 8 9 10 11
DRAFTER TTD TGL
09 TAMPAK SAMPING KIRI ALI FAMALIL FADDLI
Ars 09 Skala 1:120
KODE GAMBAR NO.GAMBAR JML.LEMBAR
ARS
BUBUNGAN EL+11.26

3.657
4.457

RING BALK 2 EL+7.60


1.100

RING BALK 1 EL+6.80


PLAFOND EL+6.50
0.500

HEAD EL+6.00
11.257

3.300
2.500

MUKA LANTAI 1 EL+3.50


0.400

PLAFOND EL+3.10
1.350
3.500

BORDES EL+1.75
1.750

MUKA L.DASAR EL±0.00


0.400

MUKA TANAH EL-0.40

3.000 4.000 3.000 2.000

7.000 5.000

12.000

G E D C A

08 TAMPAK BELKANG
Ars 08 Skala 1:120

LOKASI PROYEK DETAIL ENGINEERING DESIGN (DED) PERENCANA


C:\Users\UNTUK GURU\Documents\logo ali.png

RUBBAYYI SHAFFIYYAH
NAMA PROYEK RUMAH 2 LT TYPE BOUGENVILE
TANGGAL REVISI TGL CATATAN
1.SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN MILILMETER (MM)
JUDUL GAMBAR MENGETAHUI 2.SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN METER (M)
3.TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
TENAGA AHLI 4.KEMIRINGNA ATAP 35°
TAMPAK BELAKANG DRAFTER
5.TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN ACIAN
NOTASI : FFL = FLOOR FINISHING LEVEL
GL = GROUND LEVEL = ARAH POTONGAN
SKALA GAMBAR KODE GAMBAR NO.GMB JML.GMB DEVELOPER FD = FLOOR DRAIN
Up = NAIK = ARAH TAMPAK
1 : 100 SMKN 1 NGANJUK Dn = TURUN
BUBUNGAN
PAPAN REUTER 2/20
BUBUNGAN EL+11.26 BALOK NOK 10/14
TIANG GANTUNG 10/14

SKOOR 10/14
GORDING 10/14
BALOK KUNCI 10/14
BALOK GAPIT 2 5/14
GENTENG KARANG PILANG
3.657

USUK 5/7
4.457

GORDING 10/14

BALOK KUNCI 10/14


KAKI KUDA-KUDA 10/14
MURPLAT 10/14
BALOK TARIK 10/14
LISTPLANK 2/20
RING BALK 2 EL+7.60
TALANG COR
1.100

RING BALK 1 EL+6.80


PLAFOND EL+6.50
0.500

PLAFOND GYPSUM PLAFOND GYPSUM


+6.50 +6.50
HEAD EL+6.00
11.657

J2
3.300

J3
2.500

B1 B1 B1

RALLING HOOLLOW 4/4


R.SANTAI R.IDUR
FFL +3.50 FFL +3.50 PAS.1/2 BATA 1PC:5PS
MUKA LANTAI 1 EL+3.50
0.400

BALOK 15/30
PLAFOND EL+3.10 BV
PLAFOND GYPSUM PLAFOND GYPSUM
PAS.1/2 BATA 1PC:5PS
+3.10 +3.10
1.350

KUSEN EL+2.50
BORDES B4
FFL +1.75
3.500

BORDER KERAMIK
BORDES EL+1.75
7/20
B2 J3 B2 J2 B3
B2
1.750

R.SANTAI DAPUR
TAMAN FFL ±0.00 TRASRAM 1PC:3PS
FFL ±0.00
MUKA L.DASAR EL±0.00 GL -0.25
0.400

SLOOF 15/30
MUKA TANAH EL-0.40
1.400

PAS.BATU KALI PAS.BATU KALI


0.800

TANAH URUG TANAH URUG


ANSTAMPING ANSTAMPING
DASAR PONDASI EL-1.40
3.60

0.750

FOOT PLAT 80/80


2.600

FOOT PLAT 80/80 FOOT PLAT 80/80 FOOT PLAT 80/80


FOOTPLAT EL-2.15
1.850

FOOTPLAT EL-4.00

2.000 3.000 4.000 3.000

5.000 7.000

12.000

A C D E G

04 POTONGAN A-A
Ars 04 Skala 1:120

LOKASI PROYEK DETAIL ENGINEERING DESIGN (DED) PERENCANA


C:\Users\UNTUK GURU\Documents\logo ali.png

RUBBAYYI SHAFFIYYAH
NAMA PROYEK RUMAH 2 LT TYPE BOUGENVILE
TANGGAL REVISI TGL CATATAN
1.SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN MILILMETER (MM)
JUDUL GAMBAR MENGETAHUI 2.SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN METER (M)
3.TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
TENAGA AHLI 4.KEMIRINGNA ATAP 35°
POTONGAN A-A DRAFTER
5.TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN ACIAN
NOTASI : FFL = FLOOR FINISHING LEVEL
GL = GROUND LEVEL = ARAH POTONGAN
SKALA GAMBAR KODE GAMBAR NO.GMB JML.GMB DEVELOPER FD = FLOOR DRAIN
Up = NAIK = ARAH TAMPAK
1 : 100 ARS SMKN 1 NGANJUK Dn = TURUN
BUBUNGAN
DEVELOPER
PAPAN REUTER 2/20
BUBUNGAN EL+11.26 BALOK NOK 10/14
TIANG GANTUNG 10/14
SMKN 1 NGANJUK
SKOOR 10/14 DETAIL ENGINEERING DESIGN (DED)
GORDING 10/14
BALOK KUNCI 10/14 NAMA PROYEK
BALOK GAPIT 2 5/14
GENTENG KARANG PILANG
3.657

USUK 5/7
RUMAH TINGGAL LANTAI 2
4.457

GORDING 10/14
LOKASI PROYEK
BALOK KUNCI 10/14
KAKI KUDA-KUDA 10/14
MURPLAT 10/14 TIRTASANI PR. II / 60
BALOK TARIK 10/14 KARANG PLOSO KAB.MALANG 65152
LISTPLANK 2/20
RING BALK 2 EL+7.60
CATATAN
1.100

+6.95
1. SEMUA SATUAN DIMENSI MENGGUNAKAN SATUAN
RING BALK 1 EL+6.80 MILILMETER (MM)
PLAFOND EL+6.50 2. SEMUA SATUAN ELVASI MENGGUNAKAN SATUAN
0.500

+6.15 +6.15 +6.15 METER (M)


PLAFOND GYPSUM PLAFOND GYPSUM PLAFOND GYPSUM
HEAD EL+6.00 +6.50 +6.50 +6.50 3. TITIK DUGA ±0.00 DI AMBIL DARI AS JALAN +0.35
11.257

4. KEMIRINGNA ATAP 35°


5. TEBAL DINDING 15 CM TERMASUK PLESTERAN DAN
ACIAN
3.300

B1 J3 NOTASI :
J3
2.500

RALLING HOOLLOW 4/4 B1 B1 FFL = FLOOR FINISHING LEVEL


GL = GROUND LEVEL
FD = FLOOR DRAIN
R.KERJA R.DUDUK R.SANTAI Up = NAIK
FFL +3.50 FFL +3.50 FFL +3.50 Dn = TURUN
MUKA LANTAI 1 EL+3.50 KODE KUSEN :
0.400

= ARAH POTONGAN P = PINNTU


PLAFOND EL+3.10 J = JENDELA
= ARAH TAMPAK
+2.65 PJ = PINTU JENDELA
PLAFOND GYPSUM PLAFOND GYPSUM PLAFOND GYPSUM
1.350

KUSEN EL+2.50 +3.10 +3.10 +3.10 JUDUL GAMBAR SKALA


B4
POTONGAN B-B 1:100
3.500

BORDES EL+1.75
B2 B2 B4
J3 J3
1.750

B5
R.TAMU R.MAKAN DAPUR REVISI TTD TGL
TAMAN FFL ±0.00 FFL ±0.00 FFL ±0.00 TAMAN
MUKA L.DASAR EL±0.00 GL -0.25 CARPORT GL -0.25
0.400

FFL -0.30
MUKA TANAH EL-0.40
1.400
0.800
2.150

DASAR PONDASI EL-1.40 MENGETAHUI / MENYETUJUI TTD TGL


0.750
1.430

1.430

FOOTPLAT EL-2.15
KONSULTAN / PERENCANA TTD TGL
0.680
FOOTPLAT EL-4.00
2.250 1.250 2.500 1.000 3.000 2.000 2.500 2.500
3.500 3.500 5.000 5.000
TENAGA AHLI TTD TGL
17.000
1 2 3 5 6 8 9 10 11 DRAFTER TTD TGL
05 POTONGAN B-B ALI FAMALIL FADDLI
Ars 05 Skala 1:120 KODE GAMBAR NO.GAMBAR JML.LEMBAR
ARS

Anda mungkin juga menyukai