Anda di halaman 1dari 1

DAFTAR HARGA SATUAN BAHAN BANGUNAN DAN UPAH KERJA

PEMERINTAH KOTA BLITAR TAHUN ANGGARAN 2022


Triwulan I Tahun 2022

B. DAFTAR UPAH KERJA HARIAN

HARGA
NO. JENIS BAHAN UKURAN SAT. KODE STANDAR
(Rp)
1 2 3 4 5 5

1 MANDOR 7 jam/hari Org/hr L.04 102,500.00


2 KEPALA TK. BATU 7 jam/hari Org/hr L.03 97,500.00
3 KEPALA TK. KAYU 7 jam/hari Org/hr L.03 97,500.00
4 KEPALA TK. BESI 7 jam/hari Org/hr L.03 97,500.00
5 KEPALA TK. CAT 7 jam/hari Org/hr L.03 97,500.00
6 KEPALA TK. LISTRIK 7 jam/hari Org/hr L.03 97,500.00
7 KEPALA TK. PIPA 7 jam/hari Org/hr L.03 97,500.00
8 TUKANG BATU 7 jam/hari Org/hr L.02 92,500.00
9 TUKANG KAYU 7 jam/hari Org/hr L.02 92,500.00
10 TUKANG BESI 7 jam/hari Org/hr L.02 92,500.00
11 TUKANG CAT 7 jam/hari Org/hr L.02 92,500.00
12 TUKANG PLITUR 7 jam/hari Org/hr L.02 92,500.00
13 TUKANG ASPAL 7 jam/hari Org/hr L.02 92,500.00
14 TUKANG PIPA 7 jam/hari Org/hr L.02 92,500.00
15 TUKANG LISTRIK 7 jam/hari Org/hr L.02 92,500.00
16 TUKANG GALI TANAH 7 jam/hari Org/hr L.02 92,500.00
17 PENJAGA MALAM/ PENJAGA 7 jam/hari Org/hr 81,600.00
18 MASINIS 7 jam/hari Org/hr 92,500.00
19 PEMBANTU MASINIS 7 jam/hari Org/hr 81,600.00
20 MEKANIK 7 jam/hari Org/hr 92,500.00
21 PEMBANTU MEKANIK 7 jam/hari Org/hr 81,600.00
22 OPERATOR (TERAMPIL) 7 jam/hari Org/hr 92,500.00
23 PENGEMUDI/SOPIR 7 jam/hari Org/hr 92,500.00
24 PENJAGA API/PENJAGA 7 jam/hari Org/hr 81,600.00
25 PEMBANTU TUKANG / PEKERJA/BURUH TERAMPIL 7 jam/hari Org/hr L.01 81,600.00
26 PEKERJA TIDAK TERLATIH/BURUH TAK TERAMPIL 7 jam/hari Org/hr 81,600.00
27 PEMBANTU SOPIR 7 jam/hari Org/hr 81,600.00
28 PEKERJA PENGISI BATU 7 jam/hari Org/hr 81,600.00
29 OPERATOR SEMI TERAMPIL/PEMBANTU OPERATOR 7 jam/hari Org/hr 81,600.00

Anda mungkin juga menyukai