A.4.2.1.11.

Pemasangan 1 m' kusen pintu/jendela alluminium


No Uraian Kode Satuan Koefisien H. Satuan (Rp) Jml. Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.0430 91,138.10 3,918.94
Tukang Aluminium L.02 OH 0.0430 139,745.09 6,009.04
Kepla Tukang L.03 OH 0.0043 162,023.30 696.70
Mandor L.04 OH 0.0021 101,264.56 212.66
Jumlah Tenaga Kerja 10,837.33
B BAHAN
Profil Aluminium M' 1.1000 135,000.00 148,500.00
Skrup Fexer Buah 3.0000 4,600.00 13,800.00
Sealant Tube 0.0500 100,000.00 5,000.00
aksesoris ls 1.0000 55,000.00 55,000.00
Jumlah Harga Bahan 222,300.00
C PERALATAN
- - -
Jumlah Harga Alat -

D Jumlah (A+B+C) 233,137.33


E Overhead & Profit 15% 15% x D 34,970.60
F Harga Satuan Pekerjaan (D+E) 268,107.93

A.4.2.1.14. Pemasangan 1 m 2 jendela almunium rangka aluminium


No Uraian Kode Satuan Koefisien H. Satuan (Rp) Jml. Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.085 91,138.10 7,746.74
Tukang Aluminium L.02 OH 0.085 139,745.09 11,878.33
Kepla Tukang L.03 OH 0.009 162,023.30 1,458.21
Mandor L.04 OH 0.005 101,264.56 506.32
Jumlah Tenaga Kerja 21,589.60
B BAHAN
Profil Aluminium M' 4.4000 135,000.00 594,000.00
spandrel M2 0.8500 204,400.00 173,740.00
Sealant Tube 0.2700 100,000.00 27,000.00
Skrup Fexer Buah 16.0000 4,600.00 73,600.00
aksesoris ls 1.0000 55,000.00 55,000.00
Jumlah Harga Bahan 923,340.00
C PERALATAN
- - -
Jumlah Harga Alat -

D Jumlah (A+B+C) 944,929.60


E Overhead & Profit 15% 15% x D 141,739.44
F Harga Satuan Pekerjaan (D+E) 1,086,669.04
Pemasangan 1 unit jendela aluminium
No Uraian Kode Satuan Koefisien H. Satuan (Rp) Jml. Harga (Rp)
A TENAGA
Pekerja L.01 OH 91,138.10 -
Tukang Aluminium L.02 OH 139,745.09 -
Kepla Tukang L.03 OH 162,023.30 -
Mandor L.04 OH 101,264.56 -
Jumlah Tenaga Kerja -
B BAHAN
A.4.2.1.11. Pemasangan 1 m' kusen pintu/jendela alluminium M' 4.5500 233,137.33 1,060,774.87
A.4.2.1.14. Pemasangan 1 m2 jendela almunium rangka aluminium M2 1.0075 944,929.60 952,016.58

Jumlah Harga Bahan 2,012,791.44


C PERALATAN
- - -
Jumlah Harga Alat -

D Jumlah (A+B+C) 2,012,791.44


E Overhead & Profit 15% 15% x D 301,918.72
F Harga Satuan Pekerjaan (D+E) 2,314,710.16
G Dibulatkan 2,314,700.00