Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
ANALISA HARGA SATUAN
Nama Pekerjaan : Membuat 1 m3 beton mutu f’= 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Satuan : M3
Analisa : A. 4.1.1.5
HARGA SATUAN JUMLAH HARGA
NO URAIAN KODE SAT. KOEF.
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 1,650 83.200,00 137.280,00
2 Tukang Batu L.02 OH 0,275 131.352,00 36.121,80
3 Kepala Tukang L.03 OH 0,028 157.872,00 4.420,42
4 Mandor L.04 OH 0,083 118.248,00 9.814,58
JUMLAH TENAGA KERJA 187.636,80
B BAHAN
1 Semen Portland Kg 326,00 1.631,50 531.869,00
2 Pasir Beton Kg 760,00 112,05 85.160,71
3 Kerikil (Maks. 30 mm) Kg 1.029,00 408,34 420.181,86
4 Air Liter 215,00 100,00 21.500,00
JUMLAH HARGA BAHAN 1.058.711,57
C PERALATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
ANALISA HARGA SATUAN
Nama Pekerjaan : Membuat 1 m3 beton mutu f’= 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Satuan : M3
Analisa : A. 4.1.1.7
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
ANALISA HARGA SATUAN
Nama Pekerjaan : Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87
Satuan : M3
Analisa : A .4.1.1.4
HARGA SATUAN JUMLAH HARGA
NO URAIAN KODE SAT. KOEF.
(Rp.) (Rp.)
A TENAGA
1 Pekerja L.01 OH 1,200 83.200,00 99.840,00
2 Tukang Batu L.02 OH 0,200 131.352,00 26.270,40
3 Kepala Tukang L.03 OH 0,020 157.872,00 3.157,44
4 Mandor L.04 OH 0,060 118.248,00 7.094,88
JUMLAH TENAGA KERJA 136.362,72
B BAHAN
1 Semen Portland Kg 230,00 1.631,50 375.245,00
2 Pasir Beton Kg 893,00 112,05 100.063,84
3 Kerikil (Maks. 30 mm) Kg 1.027,00 408,34 419.365,18
4 Air Liter 200,00 100,00 20.000,00
JUMLAH HARGA BAHAN 914.674,02
C PERALATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
ERFINDO MAISYAHPUTRA, ST
Wakil Direktur