HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp.)
(Rp.)
I PEKERJAAN PENDAHULUAN
1 Direksi Keet Ls 1.00 5,000,000.00 5,000,000.00
2 Papan Nama Proyek Ls 1.00 500,000.00 500,000.00
3 Pekerjaan Pengukuran m' 28.50 35,000.00 997,500.00
4 Membongkar Pasangan Batu Kali m3 107.80 22,146.38 2,387,379.44
5 Pengaturan Lalu Lintas Ls 1.00 5,000,000.00 5,000,000.00
6 Prasasti Ls 1.00 1,500,000.00 1,500,000.00
Sub Total I 15,384,879.44
II PEKERJAAN TANAH
1 m3 177.300 12,598.31 2,233,680.54
2 Pekerjaan timbunan dengan urugan pilihan. m3 125.40 194,599.36 24,402,759.87
Sub Total II 26,636,440.41
III PEKERJAAN BETON
1 Pekerjaan beton, Beton Mutu fc-20 Mpa, dengan perancah m3 60.67 3,679,590.45 223,256,390.86
2 Pekerjaan beton, Beton Mutu fc-20 Mpa, tanpa perancah m3
34.80 2,429,423.73 84,543,945.80
4 Pekerjaan Penulangan, Baja Tulangan BJ 32 Ulir kg 11,804.56 17,424.00 205,682,683.01
Sub Total IV 513,483,019.67
(A) Jumlah Harga Pekerjaan 555,504,339.52
(B) Pajak Pertambahan Nilai (PPN) = 10% x (A) 55,550,433.95
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 611,054,773.47
(D) DIBULATKAN 611,055,000.00
Terbilang : Enam Ratus Sebelas Juta Lima Puluh Lima Ribu Rupiah
STRUKTUR : ABUTMENT KANAN DAN KIRI
GAMBAR SKETSA
DATA :
F1 = 3.20
F2 = 0.50
F3 = 0.80
F7 F4 = 0.50
F6 F5 = 0.50
F6 = 0.30
F7 = 0.35
F5
PANJANG
L = 7.50
F4
PERHITUNGAN VOLUME :
1 Beton K-250 dengan peran
V =
=
F3 2 Beton K-250 dengan peran
V =
=
3 Lantai Kerja K-125
V =
=
4 Galian Tanah Menggunaka
V =
F2 =
5 Membongkar Pasangan Ba
V =
F1 =
6 Tulangan Ulir
V =
volume total =
4 Urugan Pilihan
V =
=
PERHITUNGAN
3.20 x 0.60
0.50 x ( 3.20 + 0.80 ) x 0.20
0.80 x 5.00
0.50 x ( 0.75 + 0.30 ) x 0.30
0.50 x ( 1.25 + 1.48 ) x 0.25
0.30 x 0.27
0.35 x 0.25
7.50 m L = 6.50 m
N VOLUME :
n K-250 dengan perancah, abutment
4.67 x 6.50 x 2.00
60.67 m3 193,618,865
n K-250 dengan perancah, footplate
2.32 x 7.50 x 2.00
34.80 m3 111,051,006
ai Kerja K-125
0.32 x 7.50 x 2.00
4.80 m3 5,527,373
an Tanah Menggunakan Alat Berat
11.82 x 7.50 x 2.00
177.30 m3 2,233,681
mbongkar Pasangan Batu (Abutment Eksisting)
15.40 x 3.50 x 2.00
107.80 m3 2,320,538
11804.56 kg 136,077,793
6.987 m2
DAFTAR HARGA SATUAN PEKERJAAN
DINAS PU BINA MARGA DAERAH KAB. NGANJUK
TAHUN 2017
Kecamatan Rejoso
m3 34,980.00
m3 12,232.58
m3 13,757.66
m3 618,050.81
m3 629,438.77
m' 14,446.45
m3 227,518.03
m3 194,551.03
m3 422,045.22
m3 371,093.22
m3 340,193.07
m3 21,950.00
m3 882,942.90
m3 818,972.62
m3 331,787.50
m2 54,199.95
m2 30,878.38
m3 21,526.33
m3 29,779.85
m2 57,618.08
m2 89,289.43
m2 39,519.52
m2 3,263.47
m2 77,511.31
m2 83,760.44
m3 577,246.02
m2 19,124.70
m2 17,158.90
m2 55,218.35
m3 614,817.50
Ltr 10,553.66
Ltr 10,043.79
ton 1,292,320.70
m3 246,007.47
m3 290,816.50
ton 1,229,614.67
m3 2,765,178.68
ton 1,206,010.96
ton 1,162,893.48
m3 1,926,393.91
m3 1,981,562.78
m3 1,999,945.63
m3 1,871,848.17
m3 1,917,416.22
m3 1,985,770.30
m3 1,489,286.98
m3 3,256,532.14
m3 2,224,925.73
m3 3,220,747.38
m3 3,191,120.86
m3 2,159,514.45
m3 1,960,335.03
m3 1,151,536.01
m3 922,949.29
kg 10,938.95
kg 11,527.56
kg 24,999.55
kg 1,163.57
m2 167,352.35
buah 223,339.29
buah 25,402.93
bh 6,892.46
cm 1,997.10
kg 10,125.00
kg 4,050.00
kg 40,018.75
m2 75,365.37
m' -
m' -
m' -
m2 -
m2 17,158.90
m' -
DAFTAR HARGA SATUAN PEKERJAAN
BIDANG BINA MARGA
TAHUN 2019
Kecamatan Rejoso
1 A01 35,992.00
2 EI311a 12,598.31
3 EI313 14,167.75
4 EI314 712,647.83
5 EI315 724,371.97
6 EI7619b 254,580.90
7 EI321a 227,566.36
8 EI321b 194,599.36
9 EI421 422,669.45
10 EI422a 371,717.45
11 EI512 196,095.55
12 A17b 22,580.00
13 EI791a 913,856.64
14 EI791b 842,378.86
15 LI7102 334,675.00
16 D02 56,052.70
17 D021 32,089.75
18 EI7151 22,146.38
19 EI7152 30,637.63
20 EI7155 59,320.43
21 EI7151a 89,289.43
22 EI621 40,008.35
23 EI622 58,918.00
24 EI341 3,358.81
25 RR6 77,885.25
26 EI661 81,511.24
27 EI551 588,259.18
28 EI426 19,281.05
29 A.4.7.19 27,103.89
30 A.4.7.18 60,920.75
31 LI7103a 647,955.00
32 EI611 11,385.15
33 EI612 10,872.55
34 EI633a 1,361,906.66
35 EI317 253,357.43
36 EI318 299,522.03
37 EI634a 3,370,730.96
38 EI815b 2,904,686.50
39 EI635c 1,267,923.06
40 EI636c 1,217,768.52
41 EI531a 1,524,647.39
42 EI531b
43 EI531c 1,643,520.52
44 EI532a 1,889,546.90
45 EI532b 1,958,130.46
46 EI532c 2,022,870.67
47 EI533 1,343,333.86
48 EI713a 3,752,393.73
49 EI713b 2,502,227.01
50 EI714a 3,679,590.45
51 EI715a 3,679,590.45
52 EI715b 2,429,423.73
53 EI716a 2,219,466.07
54 EI718a 1,243,933.64
55 EI718b 954,992.20
56 EI731 15,631.00
57 EI733 17,424.00
58 EI 741a 21,393.52
59 EI 742a 1,199.28
60 PV1 175,216.14
61 BC1 230,053.21
62 UD1 26,172.87
63 - 15,521.00
64 SNI-6.5 2,306.90
65 SNI-6.1 10,452.00
66 SNI-6.1a 4,180.80
67 RR17 37,300.00
68 EI841 77,199.89
69 EI531d 1,571,377.88
Nganjuk, 2019
Mengetahui :
Kepala Dinas PU Dan Penataan Ruang Pejabat Pembuat Komitmen Pejabat Pembuat Komitmen
Kabupaten Nganjuk Bidang Bina Marga Bidang Bina Marga