Anda di halaman 1dari 4

DAILY CHECKLIST ACTIVITY

SEA SHORE PROTECTION FOR JETTY 1 AREA PROJECT


PT ASAHIMAS CHEMICAL (ASC)
Hari/Tanggal : Kamis, 25 Mei 2023
Status
No Nama Dokumen Material & Alat Submited Approved Keterangan
Tanggal
Menunggu Sertifikat Asli
Unicrane NWA 04-Mei-23 (Operator sedang proses sertifikat
asli)

Truck Colt Diesel : B 9470 MV


1 Submit Perpanjangan Kendaraan
Dump Truck : A 8793 FF, A 8266 TY,
23-Mei-23 Review by userr
A 9221 S
Long Bed : B 9329 CYU, B 9262 JYT,
B 9325 CYU, B 9849 TYX

Method Statement of Instalation Tetrapod in


2 - 08-Mei-23 Masih in progress
STA 0 - STA 83.13
Follow up tgl 25 mei, masih in
3 Perpanjangan Hotwork - 16-Mei-23
progress di safety
Method Statement of Moving Tetrapod
4 - 23-Mei-23 Masih in progress
From Plant Area to Site

5 Submit Overtime Weekend : Sabtu-Minggu 24-Mei-23 Masih prosess approval

6 Submit ID Card Pak Raup 25-Mei-23 Review by security

7 Submit Carry Out Material Tabung Penyelam 25-Mei-23 Review ASC

Anda mungkin juga menyukai