f
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.2 Grit Chamber
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.3 Grease Trap
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
d
b
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.7 Bak Sedimentasi II
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
a
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
f
e
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp335,900 Rp335,900
Total Rp573,175
Over Head 15% Rp85,976
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.10 Sludge Drying Bed
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.11 Anaerobic Digester
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
2 Perpipaan dan Aksesoris
Pemasangan Pipa PVC
Pemasangan Pipa PVC Diameter 6"
Tenaga Kerja
Mandor org/hari 0.002 Rp175,000 Rp350
Tukang Pipa org/hari 0.06 Rp150,000 Rp9,000
Pekerja org/hari 0.036 Rp110,000 Rp3,960
a. Bahan
Pipa 4 1.2 Rp190,560 Rp228,672
Perlengkapan (35%) % 0.35 Rp190,560 Rp66,696
Total Rp308,678
Over Head 15% Rp46,302
Harga Satuan Pekerjaan
Pemasangan Pipa PVC Diameter 8"
Tenaga Kerja
b.
Mandor org/hari 0.002 Rp175,000 Rp350
Tukang Pipa org/hari 0.06 Rp150,000 Rp9,000
Pekerja org/hari 0.036 Rp110,000 Rp3,960
b. Bahan
Pipa 4m 1.2 Rp489,345 Rp587,214
Perlengkapan (35%) % 0.35 Rp489,345 Rp171,271
Total Rp771,795
Over Head 15% Rp115,769
Harga Satuan Pekerjaan
3 Pemasangan Pompa Sentrifugal (Lengkap dengan Aksesoris)
Tenaga Kerja
Pekerja org/hari 0.25 Rp110,000 Rp27,500
Mekanik org/hari 0.125 Rp180,000 Rp22,500
Bahan
Pompa buah 1 8,170,000 Rp8,170,000
Total Rp8,220,000
Over Head 15% Rp1,233,000
Harga Satuan Pekerjaan
Total Biaya
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp659,151
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp22,713
Rp83,331
Rp99,906
Rp73,313
Rp1,675,659
Rp168,545
Rp354,980
Rp887,564
Rp9,453,000
No. Uraian Pekerjaan Volume Pekerjaan
I Pekerjaan Sipil
I.1 Saluran Pembawa dan Bar Screen
Pembersihan Lapangan
Saluran Pembawa dan Bar Screen (satu bak)
Panjang di permukaan = 10 m
Lebar di permukaan = 0,32 m 14.52
Luas = (10+1) m x (0,32+1) m
= 14,52 m2
Pemasangan Bowplank
Keliling Saluran Pembawa dan Bar Screen (satu bak)
K = 2 x ((10+1) + (0,32+1)) 24.64
= 24,64 m
Penggalian tanah
Saluran Pembawa dan Bar Screen (satu bak)
Kedalaman = 0,25 m
Volume Galian Tangki Bawah 7.986
Volume = (10+1) m x (0,32+1) m x (0,25+0,3) m
= 7,986 m3
Stamp Beton Bertulang K-300
Saluran Pembawa
Panjang = 10 m Jumlah Bar = 8 Batang
Lebar = 0,32 m Panjang Batang = 0,444 m
Tinggi = 0,25 m
2.312
Tebal beton = 0,2 m
Volume beton dasar
V = [2 x (10 x 0,32 x 0,2) + (10 x 0,25 x 0,2) + (0,32 x 0,25 x 0,2)] m3
= 2,312 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 14,52 m2
0.726
= 14,52 m2 x 0,05 m
= 0,726 m3
Waterproof dinding dalam
(10 m x 0,32 m x 0,2 dinding) = 0,64 m2 0.64
I.2 Grit Chamber
Pembersihan Lapangan
Grit Chamber (satu bak)
Panjang di permukaan = 18 m
Lebar di permukaan = 0,8 m
68.4
Luas = (18+1) m x (0,8+1) m
= 34,2 m2
Luas A 2 Bak = 68,4 m2
Pemasangan Bowplank
Keliling Grit Chamber (satu bak)
K = 2 x ((18+1)+(0,8+1))
= 41,6 m 83.2
K 2 bak = 2 (41,6 m)
83.2
= 83,2 m
Penggalian tanah
Grit Chamber (satu bak)
Kedalaman = 1 m
Volume Galian Tangki Bawah
88.92
Volume = (18+1) m x (0,8+1) m x (1+0,3) m
= 44,46 m3
Vol 2 bak = 2 (44,46) m3 = 88,92
Stamp Beton Bertulang K-300
Grit Chamber Hopper
Panjang = 18 m Panjang = 5 m
Lebar = 0,8 m Lebar = 1 m
Tinggi = 1 m Tinggi = 0,5 m
Tebal beton = 0,2 m Panjang sisi miring = 0,5 m
Lebar sisi miring = 0,75 m
Volume beton
V = (2x(18 x 1 x 0,2)) + (2x(0,8 x 1 x 0,2)) m3
= 7,52 m3 26.12
Volume beton sisi miring
V = (18+5)/2 x 0,75 x 0,5) + ((0,8+1)/2 x 0,5 x 0,5) m3
= 4,54 m3
Volume beton dasar
V = (5 x 1 x 0,2) m3
= 1 m3
Volume beton total = 13,06 m3
Volume beton dua bak = 26,12 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 68,4m2
3.42
= 68,4 m2 x 0,05 m
= 3,42 m3
Waterproof dinding dalam
= (18 m x 1 m x 2 dinding) = 36 m2
= (0,8 m x 1 m x 2 dinding) = 1,6 m2
= (5 m x 0,5 m x 2 dinding) = 5 m2
= (18 + 5)/2 m x 0,75 x 2 dinding) = 17,25 m2 121.5
= (0,8 + 1)/2 m x 0,5 x 2 dinding) = 0,9 m
2
= 56,8 m3
Stamp Beton Bertulang K-300
Gravity Thickener
Diamter = 3,237 m
Tinggi = 1 m
Tebal beton = 0,2 m
84.84
Volume beton
84.84
m2
m3
m3
m3
m2
m2
m
m
m3
m3
m3
m2
m2
m
m3
m3
m3
m2
m2
m
m
m3
m3
m3
m2
m2
m
m3
m3
m3
m2
m2
m3
m3
m3
m3
m3
m2
m3
m3
m3
m2
m2
m3
m3
m3
m3
m2
m2
m3
m3
m3
m2
Buah
Buah
Buah
Buah
m
m
Buah
Buah
Buah
Buah
m
m
Buah
Buah
Buah
Buah
Buah
m
m
m
Buah
Buah
Buah
m
m
Buah
Buah
Buah
Buah
m
m
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Harga Satuan Jumlah Biaya
No Uraian Pekerjaan Volume Satuan
Pekerjaan (Rp) (Rp)
I. Pekerjaan Sipil
I.1 Saluran Pembawa dan Bar Screen
Pembersihan Lapangan 14.52 m2 Rp22,713 Rp329,786
Pemasangan Bouwplank 24.64 m2 Rp83,331 Rp2,053,269
Penggalian Tanah 7.986 m 2
Rp99,906 Rp797,851
Stamp Beton Bertulang K300 2.312 m 3
Rp73,313 Rp169,499
Pengurugan Tanah 0.726 m 3
Rp1,675,659 Rp1,216,528
Pemasangan Waterstop 200 mm 0.64 m 3
Rp168,545 Rp107,869
I.2 Grit Chamber
Pembersihan Lapangan 68.4 m2 Rp22,713 Rp1,553,535
Pemasangan Bouwplank 83.2 m 2
Rp83,331 Rp6,933,116
Penggalian Tanah 88.9 m2 Rp99,906 Rp8,883,664
Stamp Beton Bertulang K300 26.12 m3 Rp73,313 Rp1,914,923
Pengurugan Tanah 3.42 m3 Rp1,675,659 Rp5,730,754
Pemasangan Waterstop 200 mm 121.5 m3 Rp168,545 Rp20,478,236
I.3 Tangki Aliran Rata-Rata (TAR)
Pembersihan Lapangan 383.13 m2 Rp22,713 Rp8,701,840
Pemasangan Bouwplank 116.48 m2 Rp83,331 Rp9,706,363
Penggalian Tanah 1,455.88 m 2
Rp99,906 Rp145,451,511
Stamp Beton Bertulang K300 141.314 m 3
Rp73,313 Rp10,360,083
Pengurugan Tanah 19.157 m 3
Rp1,675,659 Rp32,100,600
Pemasangan Waterstop 200 mm 833.12 m 3
Rp168,545 Rp140,418,335
I.4 Bak Sedimentasi I
Pembersihan Lapangan 171.46 m2 Rp22,713 Rp3,894,285
Pemasangan Bouwplank 122.8 m 2
Rp83,331 Rp10,233,013
Penggalian Tanah 737.29 m 2
Rp99,906 Rp73,659,879
Stamp Beton Bertulang K300 78.844 m 3
Rp73,313 Rp5,780,251
Pengurugan Tanah 8.573 m 3
Rp1,675,659 Rp14,365,425
Pemasangan Waterstop 200 mm 285.156 m 3
Rp168,545 Rp48,061,661
I.5 Activated Sludge
Pembersihan Lapangan 420 m2 Rp22,713 Rp9,539,250
Pemasangan Bouwplank 101 m 2
Rp83,331 Rp8,416,403
Penggalian Tanah 1,596 m 2
Rp99,906 Rp159,450,375
Stamp Beton Bertulang K300 152 m 3
Rp73,313 Rp11,143,500
Pengurugan Tanah 21 m 3
Rp1,675,659 Rp35,188,840
Pemasangan Waterstop 200 mm 399 m 3
Rp168,545 Rp67,249,515
I.6 Bak Sedimentasi II
Pembersihan Lapangan 40.82 m2 Rp22,713 Rp927,124
Pemasangan Bouwplank 163.28 m 2
Rp83,331 Rp13,606,241
Penggalian Tanah 3,990.56 m 2
Rp99,906 Rp398,681,885
Stamp Beton Bertulang K300 637.896 m 3
Rp73,313 Rp46,765,751
Pengurugan Tanah 2.041 m 3
Rp1,675,659 Rp3,420,020
Pemasangan Waterstop 200 mm 78.5 m3 Rp168,545 Rp13,230,794
I.7 Desinfeksi
Pembersihan Lapangan 60.4 m2 Rp22,713 Rp1,371,835
Pemasangan Bouwplank 42.2 m 2
Rp83,331 Rp3,516,557
I.7