No.

Uraian Satuan Harga (Rp)


DAFTAR UPAH
Pekerja Hari 110,000
Mandor Hari 175,000
Tukang Batu, Kayu, Besi, Pipa dan Cat Hari 150,000
A
Pekerjaan Galian dan Urug Hari 110,000
Mekanik Hari 180,000
Pembantu Mekanik Hari 110,000
Tukang Besi/Las Hari 150,000
B DAFTAR MATERIAL
Pipa PVC Wavin Tipe AW (1 batang = 4 m)
Pipa PVC dia 4'' M 80,567
1 Pipa PVC dia 6'' M 190,560
Pipa PVC dia 8'' M 310,710
Pipa PVC dia 10'' M 489,345
Bend 90 Socket/ Spigot PVC AW
2 Bend 90 PVC dia 6" Unit 383,000
Bend 90 PVC dia 8" Unit 691,500
Bend 45 PVC Tipe D
3 Bend 45 PVC dia 6" Unit 335,900
Bend 45 PVC dia 8" Unit 592,000
Tee PVC Tipe AW
4 Tee PVC dia 6" Unit 86,500
Tee PVC dia 8" Unit 157,000
Gate Valve
5 Gate Valve dia 6" Unit 4,100,000
Gate Valve dia 8" Unit 6,400,000
Pompa
6
Pompa Sentrifugal Unit 8,170,000
Material lain-lain
Beton Ready Mix K-300 m3 1,219,820
Waterstop lebar 150 mm M 96,300
Waterstop lebar 200 mm M 125,900
Pasir Urug m3 107,500
Papan Kayu Merantih 3 x 20 m3 2,761,875
Kayu 2/3 Kelas IV m3 2,137,500
Kayu 5/7 Kelas IV m 3
2,520,000
Batu Bata Merah buah 900.00
7 Besi Baja H Beam 100 mm 12 m 3,536,402
Besi Penggantung Unit 54,000
Nylon M 3000
Pahat Beton Unit 33,700
Gergaji Besi Lengkap Unit 47,500
Palu Unit 52,700
Paku 5 cm - 7 cm Kg 19,200
Semen/pc (50 kg) Zak 76,000
Kawat beton kg 19,100
Papan Bekisting Kelas IV m2 1,800,000
No. Uraian Satuan Koefisien Harga Satuan Jumlah Biaya
1. Pekerjaan Sipil
1.1 Saluran Pembawa dan Bar Screen
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja

f
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.2 Grit Chamber
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.3 Grease Trap
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
d

Over Head 15% Rp9,563


Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.4 Tangki Aliran Rata-Rata (TAR)
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
c

Over Head 15% Rp13,031


Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.5 Bak Sedimentasi I
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.6 Activated Sludge
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875

b
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.7 Bak Sedimentasi II
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750

a
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
f

Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195


Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.8 Desinfeksi
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.9 Gravity Thickener
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525

e
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp335,900 Rp335,900
Total Rp573,175
Over Head 15% Rp85,976
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.10 Sludge Drying Bed
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
1.11 Anaerobic Digester
Pembersihan Lapangan
Mandor org/hari 0.05 Rp175,000 Rp8,750
Pekerja org/hari 0.1 Rp110,000 Rp11,000
a
Total Rp19,750
Over Head 15% Rp2,963
Harga Satuan Pekerjaan
Pemasangan Bouwplank/m
Tenaga Kerja
Mandor org/hr 0.005 Rp175,000 Rp875
Tukang Kayu org/hr 0.1 Rp150,000 Rp15,000
Pekerja org/hr 0.1 Rp110,000 Rp11,000
Material
b
Kayu 2/3 Kelas IV m³ 0.007 Rp2,137,500 Rp14,963
Kayu 5/7 Kelas IV m³ 0.012 Rp2,520,000 Rp30,240
Paku 5 cm - 7 cm kg 0.02 Rp19,200 Rp384
Total Rp72,462
Over Head 15% Rp10,869
Harga Satuan Pekerjaan
Galian Tanah Biasa/m³
Tenaga Kerja
Mandor org/hr 0.025 Rp175,000 Rp4,375
c
c Pekerja org/hr 0.75 Rp110,000 Rp82,500
Total Rp86,875
Over Head 15% Rp13,031
Harga Satuan Pekerjaan
Urugan Tanah/m³
Tenaga Kerja
Mandor org/hr 0.05 Rp175,000 Rp8,750
d Pekerja org/hr 0.5 Rp110,000 Rp55,000
Total Rp63,750
Over Head 15% Rp9,563
Harga Satuan Pekerjaan
Beton K-300
Tenaga Kerja
Mandor org/hari 0.083 Rp175,000 Rp14,525
Tukang Batu org/hari 0.275 Rp150,000 Rp41,250
Pekerja org/hari 1.65 Rp110,000 Rp181,500
e
Bahan
Beton Ready Mix K-300 m³ 1 Rp1,219,820 Rp1,219,820
Total Rp1,457,095
Over Head 15% Rp218,564
Harga Satuan Pekerjaan
Pemasangan Waterstop/m
Tenaga Kerja
Mandor org/hr 0.007 Rp175,000 Rp1,225
Tukang Batu org/hr 0.035 Rp150,000 Rp5,250
Pekerja org/hr 0.07 Rp110,000 Rp7,700
f Material
Kawat beton kg 0.01 Rp19,100 Rp191
Waterstop lebar 200 mm m 1.05 Rp125,900 Rp132,195
Total Rp146,561
Over Head 15% Rp21,984
Harga Satuan Pekerjaan
2 Perpipaan dan Aksesoris
Pemasangan Pipa PVC
Pemasangan Pipa PVC Diameter 6"
Tenaga Kerja
Mandor org/hari 0.002 Rp175,000 Rp350
Tukang Pipa org/hari 0.06 Rp150,000 Rp9,000
Pekerja org/hari 0.036 Rp110,000 Rp3,960
a. Bahan
Pipa 4 1.2 Rp190,560 Rp228,672
Perlengkapan (35%) % 0.35 Rp190,560 Rp66,696
Total Rp308,678
Over Head 15% Rp46,302
Harga Satuan Pekerjaan
Pemasangan Pipa PVC Diameter 8"
Tenaga Kerja

b.
Mandor org/hari 0.002 Rp175,000 Rp350
Tukang Pipa org/hari 0.06 Rp150,000 Rp9,000
Pekerja org/hari 0.036 Rp110,000 Rp3,960
b. Bahan
Pipa 4m 1.2 Rp489,345 Rp587,214
Perlengkapan (35%) % 0.35 Rp489,345 Rp171,271
Total Rp771,795
Over Head 15% Rp115,769
Harga Satuan Pekerjaan
3 Pemasangan Pompa Sentrifugal (Lengkap dengan Aksesoris)
Tenaga Kerja
Pekerja org/hari 0.25 Rp110,000 Rp27,500
Mekanik org/hari 0.125 Rp180,000 Rp22,500
Bahan
Pompa buah 1 8,170,000 Rp8,170,000
Total Rp8,220,000
Over Head 15% Rp1,233,000
Harga Satuan Pekerjaan
Total Biaya

Rp22,713

Rp83,331

Rp99,906

Rp73,313

Rp1,675,659
Rp168,545

Rp22,713

Rp83,331

Rp99,906

Rp73,313
Rp1,675,659

Rp168,545

Rp22,713

Rp83,331

Rp99,906
Rp73,313

Rp1,675,659

Rp168,545

Rp22,713

Rp83,331
Rp99,906

Rp73,313

Rp1,675,659

Rp168,545

Rp22,713
Rp83,331

Rp99,906

Rp73,313

Rp1,675,659

Rp168,545

Rp22,713
Rp83,331

Rp99,906

Rp73,313

Rp1,675,659

Rp168,545
Rp22,713

Rp83,331

Rp99,906

Rp73,313

Rp1,675,659
Rp168,545

Rp22,713

Rp83,331

Rp99,906

Rp73,313

Rp1,675,659
Rp168,545

Rp22,713

Rp83,331

Rp99,906

Rp73,313
Rp659,151

Rp168,545

Rp22,713

Rp83,331

Rp99,906
Rp73,313

Rp1,675,659

Rp168,545

Rp22,713

Rp83,331
Rp99,906

Rp73,313

Rp1,675,659

Rp168,545

Rp354,980
Rp887,564

Rp9,453,000
No. Uraian Pekerjaan Volume Pekerjaan
I Pekerjaan Sipil
I.1 Saluran Pembawa dan Bar Screen
Pembersihan Lapangan
Saluran Pembawa dan Bar Screen (satu bak)
Panjang di permukaan = 10 m
Lebar di permukaan = 0,32 m 14.52
Luas = (10+1) m x (0,32+1) m
= 14,52 m2
Pemasangan Bowplank
Keliling Saluran Pembawa dan Bar Screen (satu bak)
K = 2 x ((10+1) + (0,32+1)) 24.64
= 24,64 m
Penggalian tanah
Saluran Pembawa dan Bar Screen (satu bak)
Kedalaman = 0,25 m
Volume Galian Tangki Bawah 7.986
Volume = (10+1) m x (0,32+1) m x (0,25+0,3) m
= 7,986 m3
Stamp Beton Bertulang K-300
Saluran Pembawa
Panjang = 10 m Jumlah Bar = 8 Batang
Lebar = 0,32 m Panjang Batang = 0,444 m
Tinggi = 0,25 m
2.312
Tebal beton = 0,2 m
Volume beton dasar
V = [2 x (10 x 0,32 x 0,2) + (10 x 0,25 x 0,2) + (0,32 x 0,25 x 0,2)] m3
= 2,312 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 14,52 m2
0.726
= 14,52 m2 x 0,05 m
= 0,726 m3
Waterproof dinding dalam
(10 m x 0,32 m x 0,2 dinding) = 0,64 m2 0.64
I.2 Grit Chamber
Pembersihan Lapangan
Grit Chamber (satu bak)
Panjang di permukaan = 18 m
Lebar di permukaan = 0,8 m
68.4
Luas = (18+1) m x (0,8+1) m
= 34,2 m2
Luas A 2 Bak = 68,4 m2
Pemasangan Bowplank
Keliling Grit Chamber (satu bak)
K = 2 x ((18+1)+(0,8+1))
= 41,6 m 83.2
K 2 bak = 2 (41,6 m)
83.2

= 83,2 m
Penggalian tanah
Grit Chamber (satu bak)
Kedalaman = 1 m
Volume Galian Tangki Bawah
88.92
Volume = (18+1) m x (0,8+1) m x (1+0,3) m
= 44,46 m3
Vol 2 bak = 2 (44,46) m3 = 88,92
Stamp Beton Bertulang K-300
Grit Chamber Hopper
Panjang = 18 m Panjang = 5 m
Lebar = 0,8 m Lebar = 1 m
Tinggi = 1 m Tinggi = 0,5 m
Tebal beton = 0,2 m Panjang sisi miring = 0,5 m
Lebar sisi miring = 0,75 m
Volume beton
V = (2x(18 x 1 x 0,2)) + (2x(0,8 x 1 x 0,2)) m3
= 7,52 m3 26.12
Volume beton sisi miring
V = (18+5)/2 x 0,75 x 0,5) + ((0,8+1)/2 x 0,5 x 0,5) m3
= 4,54 m3
Volume beton dasar
V = (5 x 1 x 0,2) m3
= 1 m3
Volume beton total = 13,06 m3
Volume beton dua bak = 26,12 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 68,4m2
3.42
= 68,4 m2 x 0,05 m
= 3,42 m3
Waterproof dinding dalam
= (18 m x 1 m x 2 dinding) = 36 m2
= (0,8 m x 1 m x 2 dinding) = 1,6 m2
= (5 m x 0,5 m x 2 dinding) = 5 m2
= (18 + 5)/2 m x 0,75 x 2 dinding) = 17,25 m2 121.5
= (0,8 + 1)/2 m x 0,5 x 2 dinding) = 0,9 m
2

Total = 36 + 1,6 + 5 + 17,25 + 0,9 = 60,75 m2


2 bak = 60,75 m2 x 2 = 121,5 m2
I.3 Tangki Aliran Rata-Rata (TAR)
Pembersihan Lapangan
Tangki Aliran Rata-Rata (satu bak)
Panjang di permukaan = 18,08 m
Lebar di permukaan = 9,04 m
Luas = (18,08+1) m x (9,04+1) m 383.13
= 191,56 m2
Luas 2 bak = 2 (191,56 m2)
= 383,13 m2
Pemasangan Bowplank
Keliling Tangki Aliran Rata-Rata (satu bak)
K = 2 x ((18,08+1)+(9,04+1))
= 58,24 m 116.48
K 2 bak = 2 (58,24 m)
= 116,48 m
Penggalian tanah
Tangki Aliran Rata-Rata (satu bak)
Kedalaman = 3,5 m
Volume Galian Tangki Bawah
1,455.88
Volume = (18,08+1) m x (9,04+1)m x (3,5+0,3) m
= 727,945 m3
Vol 2 bak = 2 (727,945) m3 = 1.455,88 m3
Stamp Beton Bertulang K-300
Tangki Aliran Rata-Rata Impeller
Panjang = 18,08 m Panjang = 0,603 m
Lebar = 9,04 m Lebar = 0,603m
Tinggi = 3,5 m Diameter = 3,013 m
Tebal Beton - 0,2 m Tinggi = 0,875 m
Diameter central disk = 6,027 m
Volume beton
141.314
V = (2x(18,08 x 3,5 x 0,2) + (2x(9,04 x 3,5 x 0,2)) m3
= 37,968 m3
Volume beton dasar
V = (18,08 x 9,04 x 0,2) m3
= 32,689 m3
Volume beton total = 37,968 + 32,689 = 70,657 m3
Volume beton dua bak = 141,314 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 383,13 m2
19.157
= 383,13 m2 x 0,05 m
= 19,157 m3
Waterproof dinding dalam
= (18,08 x 3,5 x 4 dinding) = 253,12 m2
= (18,08 x 9,04 x 1 dinding) = 163,44 m2
833.12
Total = 253,12 + 163,44 = 416,56 m2
2 bak = 833,12 m2
I.4 Bak Sedimentasi I
Pembersihan Lapangan
Bak Sedimentasi I (satu bak)
Panjang di permukaan = 10,68 m
Lebar di permukaan = 2,67 m
Luas = (10,68+1) m x (2,67+1) m 171.46
= 42,87 m2
Luas 4 bak = 4 (42,87 m2)
= 171,46 m2
Pemasangan Bowplank
Keliling Bak Sedimentasi I (satu bak)
K = 2 x ((10,68 m+1)+(2,67 m+1))
122.8
= 30,7 m 122.8
K 4 bak = 4 (30,7m)
= 122,8 m
Penggalian tanah
Kolam Bak Sedimentasi I (satu bak)
Kedalaman = 4 m
Volume Galian Tangki Bawah
737.29
Volume = (10,68+1) m x (2,67+1)m x (4+0,3) m
= 184,32 m3
Vol 4 bak = 4 (184,32) m3 = 737,29 m3
Stamp Beton Bertulang K-300
Bak Sedimentasi I Zona lumpur
Panjang = 10,68 m Panjang = 2,67 m
Lebar = 2,67 m Lebar = 3 m
Tinggi = 4 m Tinggi = 2 m
Tebal Beton = 0,2 m zona inlet dan zona outlet
Panjang = 2,85 m
Volume beton
79.844
V = (2x(10,68 x 2,67 x 0,2)) + (2x(2,67 x 2,67 x 0,2) m3
= 14,258 m3
Volume beton dasar
V = (10,68 x 2,67 x 0,2) m3
= 5,703 m3
Volume beton total = 14,258 + 5,703 = 19,961 m3
Volume beton 4 bak = 79,844 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 171,46 m2
8.573
= 171,46 m2 x 0,05 m
= 8,573 m3
Waterproof dinding dalam
= (10,68 x 2,67 x 2 dinding) = 57,031 m2
= (2,67 x 2,67 x 2 dinding) = 14,258 m2
285.156
Total = 57,031 + 14,258 = 71,289 m2
4 bak = 285,156 m2
I.5 Activated Sludge
Pembersihan Lapangan
Activated Sludge (satu bak)
Panjang di permukaan = 19 m
Lebar di permukaan = 9,5 m
Luas = (19+1) m x (9,5+1) m 420
= 210 m2
Luas 2 bak = 2 (210 m2)
= 420 m2
Pemasangan Bowplank
Keliling Activated Sludge
K = 2 x ((19+1)+(9,5+1)) m
= 50,5 m 101
K 2 bak = 2 (50,5 m)
= 101 m
Penggalian Tanah
Activated Sludge (satu bak)
Kedalaman = 3,5 m
Volume Galian Tangki Bawah
1,596
Vol = (19+1) m x (9,5+1) m x (3,5+0,3) m
= 798 m3
Vol 2 bak = 2 (798) m3 = 1.596
Stamp Beton Bertulang K-300
Activated Sludge (satu bak)
Panjang = 19 m
Lebar = 9,5 m
Tinggi = 3,5 m
Tebal beton = 0,2 m
Volume Beton sisi miring
V = (2 x (19 x 3,5 x 0,2) + (2 x (9,5 x 3,5 x 0,2) m3
152
= 39,9 m3
Volume Beton dasar
V = (19 x 9,5 x 0,2) m3
= 36,1 m3
Volume beton total = 76 m3
Volume beton dua bak = 2 x 76
= 152 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 420 m2
21
= 420 m2 x 0,05 m
= 21 m3
Waterproofing dinding dalam
= (19 x 3,5 x 2 dinding) = 133
= (9,5 x 3,5 x 2 dinding) = 66,5
399
Total = 133 + 66,5 = 199,5
2 bak = 199,5 x 2 = 399
I.6 Bak Sedimentasi II
Pembersihan Lapangan
Bak Sedimentasi II (satu bak)
diameter = 25 m
Luas = 1/4 x π x (d+1) m
40.82
= 20,41m2
Luas = 2 (20,41 m2)
= 40,82 m2
Pemasangan Bowplank
Keliling Bak Sedimentasi II (satu bak)
K = 3,14 (26) m = 81,64 m 163.28
K 2 bak = 2 x 81,64 m = 163,28 m
Penggalian Tanah
Bak Sedimentasi II (satu bak)
Kedalaman = 3,46 m
Volume Galian Tangki Bawah
Vol = (0,25 x 3,14 x (25+1)2) m x (3,46+0,3) m 3,990.56
3,990.56
= 1.995,282 m 3

Vol 2 bak = 2 (1.995,282)


= 3.990,564 m3
Stamp Beton Bertulang K-300
Bak Sedimentasi II (satu bak)
Diamter = 25 m
Tinggi = 3,46 m
Tebal Beton = 0,2 m
Volume Beton
V = ((0,25 x 3,14 x (25+0,2)3,56) + ((0,25 x 3,14 x (25)3,46)) x 3,46 m3
637.896
= 305,367 m3
Volume beton dasar
V = (0,25 x 3,14 (25) 3,46) x 0,2 m3
= 13,581 m3
V = 305,367 + 13,581 = 318,948 m3
V 2 bak = 2 x 318,948 = 637,896 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 40,82 m2 2.041
= 40,82 m2 x 0,05 m = 2,041 m3
Waterproofing dinding dalam
= (3,14 x 25 x 1 dinding) = 78,5 m2
= ((0,25 x 3,14 (25)2) m x 1 dinding) = 39,25 m2
78.5
Luas 2 bak = 2 (39,25)
= 78,5 m2
I.7 Desinfeksi
Pembersihan Lapangan
Desinfeksi (satu bak)
Panjang di permukaan = 5,55 m
Lebar di permukaan = 3 m
Luas = (5,55+2) m x (3+1) m 60.4
= 30,2 m2
Luas = 2 (30,2 m2)
= 60,4 m2
Pemasangan Bowplank
Keliling Desinfeksi (satu bak)
K = 2 x (5,55+1) + (3+1) m
= 21,1 m 42.20
K 2 bak = 2 x (21,1) m
= 42,2 m
Penggalian Tanah
Desinfeksi (satu bak)
Kedalaman = 2 m
Volume Galian Tangki Bawah
Vol = (5,55+1) m x (3+1) m x (2+0,3) m 120.52
= 60,26 m3
Vol 2 bak = 2 (60,26)
= 120,52 m3
Stamp Beton Bertulang K-300
Desinfeksi (satu bak)
Panjang di permukaan = 5,55 baffle = 7
Lebar di permukaan = 3 m panjang = 5,55 m
Tinggi = 2 m
Tebal beton = 0,2 m
Volume Beton
V = (2 x (5,55 x 3 x 0,2) + (2 x (2 x 3 x 0,2))
= 9,06 m3
69.2
Volume beton dasar
V = (5,55 x 2 x 0,2)
= 2,22 m3
Volume baffle
V = 7 x (5,55 x 3 x 0,2)
= 23,31m3
Volume beton total = 34,6 m3
Volume beton 2 bak = 69,2 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 60,4 m2
3.02
= 60,4m2 x 0,05 m
= 3,02 m3
Waterproof dinding dalam
= (5,55 x 3 x 2 dinding) = 33,3 m2
= (2 x 3 x 2 dinding) = 12 m2
= (5,55 x 2 x 1 dinding) = 11,1 m2 2,220
= (5,55 x 2 x 100 dinding) = 1.110 m3
2 bak = 2.220 m3
I.8 Gravity Thickener
Pembersihan Lapangan
Gravity Thickener
Diameter = 3,237 m
3.326
Luas = (0,25 x 3,14 x (3,237+1)) m
= 3,326 m2
Pemasangan Bowplank
Keliling Gravity Thickener
K = 3,14 x (3,237+1) 13.304
= 13,304 m
Penggalian tanah
Gravity Thickener
Kedalaman = 4,03 m
Volume Galian Tangki Bawah 56.8
Vol = (0,25 x 3,14 x (3,237+1) ) m x 4,03 m
2

= 56,8 m3
Stamp Beton Bertulang K-300
Gravity Thickener
Diamter = 3,237 m
Tinggi = 1 m
Tebal beton = 0,2 m
84.84
Volume beton
84.84

Vol = (0,25 x 3,14 x (3,237+0,2)2)+ (0,25 x 3,14 (3,237x3,237) m x 4,03 m =


= 42,42 m3
Vol 2 bak = 2 (42,42) m3 = 84,84 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 3,326 m2
0.1663
= 3,326 m2 x 0,05 m
= 0,1663 m3
Waterproof dinding dalam
= (3,14 x 3,237 x 4,03) = 40,96 m2
33.15
= (3,14 x 0,25 x 3,237 x 3,237 x 4,03) = 33,15 m2
I.9 Sludge Drying Bed
Pembersihan Lapangan
Sludge Drying Bed (satu bak)
Panjang di permukaan = 14,56 m
Lebar di permukaan = 3,64 m
Luas = (14,56+1) m x (3,64+1) m 144.4
= 72,2 m2
Luas 2 bak = 2 (72,2 m2)
= 144,4 m2
Pemasangan Bowplank
Keliling Sludge Drying Bed (satu bak)
K = 2 x ((14,56+1)+(3,64+1))
= 40,4 m 80.8
K 2 bak = 2 (40,4 m)
= 80,8 m
Penggalian tanah
Sludge Drying Bed (satu bak)
Kedalaman = 1,105 m
Volume Galian Tangki Bawah
202.88
Volume = (14,56+1) m x (3,64+1) m x (1,105+0,3)
= 101,44 m3
Vol 2 bak = 2 (101,44) m3 = 202,88 m3
Stamp Beton Bertulang K-300
SDB
Panjang = 14,56 m
Lebar = 3,64 m
Tinggi = 1,105 m
Tebal beton = 0,2 m 29.244
Volume beton
= (14,56 x 3,64 x 0,2) + (14,56 x 1,105 x 0,2) + (3,64 x 1,105 x 0,2) m3
= 14,622 m3
Vol 2 bak = 2 (14,622) m3 = 29,244 m3
Urugan Tanah
Tebal = 0,05 m
Luas = 80,8 m2
4.04
= 80,8 m2 x 0,05 m
= 4,04 m3
Waterproof dinding dalam
= (14,56 x 1,105 x 2 dinding) = 32,178 m2
= (3,64 x 1 x 2 dinding) = 8,044 m2
= (14,56 x 3,64 x 2 dinding) = 106 m2 292.444
Total = 146,222
2 bak = 292,444
II. Perpipaan dan Aksesoris
II.1 Grit Chamber
Pipa
Pipa PVC Diameter 150 mm 1m
Bend 90
Bend 90 PVC Diameter 150 mm 4 Buah
Reducer
Reducer PVC 150/200 1 Buah
Gate Valve
Gate Valve Diameter 150 mm 2 Buah
Tee All
Tee All PVC Diameter 150 mm 2 Buah
II.2 Tangki Aliran Rata-Rata (TAR)
Pipa
Pipa PVC Diameter 200 mm 3m
Pipa PVC Diameter 150 mm 10 m
Bend 90
Bend 90 PVC Diameter 200 mm 4 Buah
Reducer
Reducer PVC 150/200 1 Buah
Gate Valve
Gate Valve Diameter 200 mm 2 Buah
Tee All
Tee All PVC Diameter 200 mm 2 Buah
II.3 Bak Sedimentasi I
Pipa
Pipa PVC Diameter 200 mm 1.5 m
Pipa PVC Diameter 100 mm 3m
Bend 90
Bend 90 PVC Diameter 200 mm 2 Buah
Reducer
Reducer PVC 200/300 2 Buah
Gate Valve
Gate Valve Diameter 200 mm 4 Buah
Tee All
Tee All PVC Diameter 200 mm 4 Buah
Pompa
Pompa Lumpur 1 Buah
II.4 Activated Sludge
Pipa
Pipa PVC Diameter 300 mm 3m
Pipa PVC Diameter 250 mm 5m
Pipa PVC Diameter 200 mm 29 m
Bend 90
Bend 90 PVC Diameter 300 mm 2 Buah
Gate Valve
Gate Valve Diameter 300 mm 1 Buah
Tee All
Tee All PVC Diameter 300 mm 1 Buah
II.5 Bak Sedimentasi II
Pipa
Pipa PVC Diameter 300 mm 3m
Pipa PVC Diameter 200 mm 29 m
Bend 90
Bend 90 PVC Diameter 300 mm 3 Buah
Gate Valve
Gate Valve Diameter 300 mm 2 Buah
Tee All
Tee All PVC Diameter 300 mm 2 Buah
Pompa
Pompa Lumpur 1 Buah
II.6 Desinfeksi
Pipa
Pipa PVC Diameter 300 mm 3m
Pipa PVC Diameter 200 mm 1.5 m
Bend 90
Bend 90 PVC Diameter 300 mm 2 Buah
Gate Valve
Gate Valve Diameter 300 mm 1 Buah
Tee All
Tee All PVC Diameter 300 mm 1 Buah
II.7 Gravity Thickener
Pipa
Pipa PVC Diameter 300 mm 40 m
Bend 90
Bend 90 PVC Diameter 300 mm 1 Buah
Gate Valve
Gate Valve Diameter 300 mm 2 Buah
Tee All
Tee All PVC Diameter 300 mm 2 Buah
Pompa
Pompa Lumpur 1 Buah
II.8 Sludge Drying Bed
Pipa
Pipa PVC Diameter 300 mm 5m
Bend 90
Bend 90 PVC Diameter 300 mm 1 Buah
Gate Valve
Gate Valve Diameter 300 mm 1 Buah
Tee All
Tee All PVC Diameter 300 mm 1 Buah
Satuan
saluran pembawa 1
p 10 2
l 0.32 0.2
h 0.25

m2

m3

m3

m3

m2

m2

m
m

m3

m3

m3

m2

m2
m

m3

m3

m3

m2

m2

m
m

m3

m3

m3

m2

m2

m
m3

m3

m3

m2

m2

m3
m3

m3

m3

m3

m2

m3
m3

m3

m2

m2

m3

m3
m3

m3

m2

m2

m3

m3

m3
m2

Buah

Buah

Buah

Buah

m
m

Buah

Buah

Buah

Buah

m
m

Buah

Buah

Buah

Buah

Buah

m
m
m

Buah
Buah

Buah

m
m

Buah

Buah

Buah

Buah

m
m

Buah

Buah

Buah

Buah

Buah

Buah

Buah

Buah

Buah

Buah
Harga Satuan Jumlah Biaya
No Uraian Pekerjaan Volume Satuan
Pekerjaan (Rp) (Rp)
I. Pekerjaan Sipil
I.1 Saluran Pembawa dan Bar Screen
Pembersihan Lapangan 14.52 m2 Rp22,713 Rp329,786
Pemasangan Bouwplank 24.64 m2 Rp83,331 Rp2,053,269
Penggalian Tanah 7.986 m 2
Rp99,906 Rp797,851
Stamp Beton Bertulang K300 2.312 m 3
Rp73,313 Rp169,499
Pengurugan Tanah 0.726 m 3
Rp1,675,659 Rp1,216,528
Pemasangan Waterstop 200 mm 0.64 m 3
Rp168,545 Rp107,869
I.2 Grit Chamber
Pembersihan Lapangan 68.4 m2 Rp22,713 Rp1,553,535
Pemasangan Bouwplank 83.2 m 2
Rp83,331 Rp6,933,116
Penggalian Tanah 88.9 m2 Rp99,906 Rp8,883,664
Stamp Beton Bertulang K300 26.12 m3 Rp73,313 Rp1,914,923
Pengurugan Tanah 3.42 m3 Rp1,675,659 Rp5,730,754
Pemasangan Waterstop 200 mm 121.5 m3 Rp168,545 Rp20,478,236
I.3 Tangki Aliran Rata-Rata (TAR)
Pembersihan Lapangan 383.13 m2 Rp22,713 Rp8,701,840
Pemasangan Bouwplank 116.48 m2 Rp83,331 Rp9,706,363
Penggalian Tanah 1,455.88 m 2
Rp99,906 Rp145,451,511
Stamp Beton Bertulang K300 141.314 m 3
Rp73,313 Rp10,360,083
Pengurugan Tanah 19.157 m 3
Rp1,675,659 Rp32,100,600
Pemasangan Waterstop 200 mm 833.12 m 3
Rp168,545 Rp140,418,335
I.4 Bak Sedimentasi I
Pembersihan Lapangan 171.46 m2 Rp22,713 Rp3,894,285
Pemasangan Bouwplank 122.8 m 2
Rp83,331 Rp10,233,013
Penggalian Tanah 737.29 m 2
Rp99,906 Rp73,659,879
Stamp Beton Bertulang K300 78.844 m 3
Rp73,313 Rp5,780,251
Pengurugan Tanah 8.573 m 3
Rp1,675,659 Rp14,365,425
Pemasangan Waterstop 200 mm 285.156 m 3
Rp168,545 Rp48,061,661
I.5 Activated Sludge
Pembersihan Lapangan 420 m2 Rp22,713 Rp9,539,250
Pemasangan Bouwplank 101 m 2
Rp83,331 Rp8,416,403
Penggalian Tanah 1,596 m 2
Rp99,906 Rp159,450,375
Stamp Beton Bertulang K300 152 m 3
Rp73,313 Rp11,143,500
Pengurugan Tanah 21 m 3
Rp1,675,659 Rp35,188,840
Pemasangan Waterstop 200 mm 399 m 3
Rp168,545 Rp67,249,515
I.6 Bak Sedimentasi II
Pembersihan Lapangan 40.82 m2 Rp22,713 Rp927,124
Pemasangan Bouwplank 163.28 m 2
Rp83,331 Rp13,606,241
Penggalian Tanah 3,990.56 m 2
Rp99,906 Rp398,681,885
Stamp Beton Bertulang K300 637.896 m 3
Rp73,313 Rp46,765,751
Pengurugan Tanah 2.041 m 3
Rp1,675,659 Rp3,420,020
Pemasangan Waterstop 200 mm 78.5 m3 Rp168,545 Rp13,230,794
I.7 Desinfeksi
Pembersihan Lapangan 60.4 m2 Rp22,713 Rp1,371,835
Pemasangan Bouwplank 42.2 m 2
Rp83,331 Rp3,516,557
I.7

Penggalian Tanah 120.52 m2 Rp99,906 Rp12,040,701


Stamp Beton Bertulang K300 69.2 m 3
Rp73,313 Rp5,073,225
Pengurugan Tanah 3.02 m 3
Rp1,675,659 Rp5,060,490
Pemasangan Waterstop 200 mm 2,220 m3 Rp168,545 Rp374,170,233
I.8 Gravity Thickener
Pembersihan Lapangan 3.326 m2 Rp22,713 Rp75,542
Pemasangan Bouwplank 13.304 m 2
Rp83,331 Rp1,108,632
Penggalian Tanah 56.80 m 2
Rp99,906 Rp5,674,675
Stamp Beton Bertulang K300 84.84 m3 Rp73,313 Rp6,219,833
Pengurugan Tanah 0.1663 m3 Rp1,675,659 Rp278,662
Pemasangan Waterstop 200 mm 33.15 m 3
Rp168,545 Rp5,587,272
I.9 Sludge Drying Bed
Pembersihan Lapangan 144.4 m2 Rp22,713 Rp3,279,685
Pemasangan Bouwplank 80.8 m 2
Rp83,331 Rp6,733,123
Penggalian Tanah 202.88 m2 Rp99,906 Rp20,268,980
Stamp Beton Bertulang K300 29.244 m3 Rp73,313 Rp2,143,951
Pengurugan Tanah 4.04 m 3
Rp1,675,659 Rp6,769,663
Pemasangan Waterstop 200 mm 292.444 m 3
Rp168,545 Rp49,290,018
Total Rp1,829,185,048
II Perpipaan dan Aksesoris
I.1 Grit Chamber
Pipa PVC Diameter 150 mm 1 m Rp190,560 Rp190,560
Bend 90 PVC Diameter 150 mm 4 Buah Rp383,000 Rp1,532,000
Reducer PVC 150/200 1 Buah Rp799,100 Rp799,100
Gate Valve Diameter 150 mm 2 Buah Rp6,400,000 Rp12,800,000
Tee All PVC Diameter 150 mm 2 Buah Rp86,500 Rp173,000
I.2 Tangki Aliran Rata-Rata (TAR)
Pipa PVC Diameter 200 mm 3 m Rp310,710 Rp932,130
Pipa PVC Diameter 150 mm 10 m Rp190,560 Rp1,905,600
Bend 90 PVC Diameter 200 mm 4 Buah Rp691,500 Rp2,766,000
Reducer PVC 150/200 1 Buah Rp799,100 Rp799,100
Gate Valve Diameter 200 mm 2 Buah Rp6,400,000 Rp12,800,000
Tee All PVC Diameter 200 mm 2 Buah Rp157,000 Rp314,000
I.3 Bak Sedimentasi I
Pipa PVC Diameter 200 mm 1.5 m2 Rp310,710 Rp466,065
Pipa PVC Diameter 100 mm 3 m Rp80,567 Rp241,701
Bend 90 PVC Diameter 200 mm 2 Buah Rp691,500 Rp1,383,000
Reducer PVC 200/300 2 Buah Rp1,115,550 Rp2,231,100
Gate Valve Diameter 200 mm 4 Buah Rp6,400,000 Rp25,600,000
Tee All PVC Diameter 200 mm 4 Buah Rp157,000 Rp628,000
Pompa Lumpur 1 Buah Rp8,170,000 Rp8,170,000
I.4 Activated Sludge
Pipa PVC Diameter 300 mm 3 m Rp489,345 Rp1,468,035
Pipa PVC Diameter 250 mm 5 m Rp396,703 Rp1,983,515
Pipa PVC Diameter 200 mm 29 m Rp310,710 Rp9,010,590
Bend 90 PVC Diameter 300 mm 2 Buah Rp871,500 Rp1,743,000
Gate Valve Diameter 300 mm 1 Buah Rp13,200,000 Rp13,200,000
Tee All PVC Diameter 300 mm 1 Buah Rp157,000 Rp157,000
I.5 Bak Sedimentasi II
I.5
Pipa PVC Diameter 300 mm 3 m Rp489,345 Rp1,468,035
Pipa PVC Diameter 200 mm 29 m Rp310,710 Rp9,010,590
Bend 90 PVC Diameter 300 mm 3 Buah Rp871,500 Rp2,614,500
Gate Valve Diameter 300 mm 2 Buah Rp13,200,000 Rp26,400,000
Tee All PVC Diameter 300 mm 2 Buah Rp157,000 Rp314,000
Pompa Lumpur 1 Buah Rp8,170,000 Rp8,170,000
I.6 Desinfeksi
Pipa PVC Diameter 300 mm 3 m Rp489,345 Rp1,468,035
Pipa PVC Diameter 200 mm 1.5 m Rp310,710 Rp466,065
Bend 90 PVC Diameter 300 mm 2 Buah Rp871,500 Rp1,743,000
Gate Valve Diameter 300 mm 1 Buah Rp13,200,000 Rp13,200,000
Tee All PVC Diameter 300 mm 1 Buah Rp157,000 Rp157,000
I.7 Gravity Thickener
Pipa PVC Diameter 300 mm 40 m Rp489,345 Rp19,573,800
Bend 90 PVC Diameter 300 mm 1 Buah Rp871,500 Rp871,500
Gate Valve Diameter 300 mm 2 Buah Rp13,200,000 Rp26,400,000
Tee All PVC Diameter 300 mm 2 Buah Rp157,000 Rp314,000
Pompa Lumpur 1 Buah Rp8,170,000 Rp8,170,000
I.8 Sludge Drying Bed
Pipa PVC Diameter 300 mm 5 m Rp489,345 Rp2,446,725
Bend 90 PVC Diameter 300 mm 1 Buah Rp871,500 Rp871,500
Gate Valve Diameter 300 mm 1 Buah Rp13,200,000 Rp13,200,000
Tee All PVC Diameter 300 mm 1 Buah Rp157,000 Rp157,000
Total Rp238,309,246
Total Biaya IPAL Rp2,305,803,540
Uraian Pekerjaan Jumlah Biaya (Rp)
Pekerjaan Sipil 1,829,185,048
Pemasangan Pipa dan Aksesoris 238,309,246
Jumlah 2,067,494,294
Jasa Pemborong 10% 206,749,429.4
Jumlah Total 2,274,243,724
Dibulatkan  2.270.000.000
Terbilang: Dua Milyar Dua Ratus Tujuh Puluh Juta Rupiah