A.2.3.1.1.

Penggalian 1 m3 tanah biasa sedalam 1 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.750 63,100.00 47,325.00
Mandor L.04 OH 0.025 74,100.00 1,852.50
JUMLAH TENAGA KERJA 49,177.50
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 49,177.50


D Overhead & Profit 7,376.63
E Harga Satuan Pekerjaan (C+D) 56,554.13

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.900 63,100.00 56,790.00
Mandor L.04 OH 0.045 74,100.00 3,334.50
JUMLAH TENAGA KERJA 60,124.50
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 60,124.50


D Overhead & Profit 9,018.68
E Harga Satuan Pekerjaan (C+D) 69,143.18

A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.050 63,100.00 66,255.00
Mandor L.04 OH 0.067 74,100.00 4,964.70
JUMLAH TENAGA KERJA 71,219.70
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 71,219.70


D Overhead & Profit 10,682.96
E Harga Satuan Pekerjaan (C+D) 81,902.66

A.2.3.1.14. Pengurugan 1 m3 sirtu SNI


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.250 63,100.00 15,775.00
Mandor L.04 OH 0.025 74,100.00 1,852.50
JUMLAH TENAGA KERJA 17,627.50
B BAHAN
Sirtu m³ 1.200 224,400.00 269,280.00
JUMLAH HARGA BAHAN 269,280.00

C JUMLAH (A+B) 286,907.50


D Overhead & Profit 43,036.13
E Harga Satuan Pekerjaan (C+D) 329,943.63
A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP SNI
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.500 63,100.00 94,650.00
Tukang L.02 OH 0.750 79,500.00 59,625.00
Kepala Tukang L.03 OH 0.075 79,500.00 5,962.50
Mandor L.04 OH 0.075 74,100.00 5,557.50
JUMLAH TENAGA KERJA 165,795.00
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Semen Portland kg 163.000 1,100.00 179,300.00
Pasir pasang m³ 0.520 243,100.00 126,412.00
JUMLAH HARGA BAHAN 618,432.00

C JUMLAH (A+B) 784,227.00


D Overhead & Profit 117,634.05
E Harga Satuan Pekerjaan (C+D) 901,861.05

A.4.1.1.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 SNI
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.600 63,100.00 100,960.00
Tukang L.02 OH 0.275 79,500.00 21,862.50
Kepala Tukang L.03 OH 0.028 79,500.00 2,226.00
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 131,198.80
B BAHAN
Semen portlan kg 326.000 1,100.00 358,600.00
Pasir beton kg 760.000 173.64 131,968.57
Kerikil Maks 30mm (Split 1-2 (pecah tangan) kg 1,029.000 308,500.00 317,446,500.00
Air liter 215.000 - -
JUMLAH HARGA BAHAN 317,937,068.57

C JUMLAH (A+B) 318,068,267.37


D Overhead & Profit 47,710,240.11
E Harga Satuan Pekerjaan (C+D) 365,778,507.48

A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir SNI


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.070 63,100.00 4,417.00
Tukang L.02 OH 0.070 79,500.00 5,565.00
Kepala Tukang L.03 OH 0.007 79,500.00 556.50
Mandor L.04 OH 0.004 74,100.00 296.40
JUMLAH TENAGA KERJA 10,834.90
B BAHAN
Besi beton (polos/ulir) kg 10.500 9,700.00 101,850.00
Kawat beton kg 0.150 19,800.00 2,970.00
JUMLAH HARGA BAHAN 104,820.00

C JUMLAH (A+B) 115,654.90


D Overhead & Profit 17,348.24
E Harga Satuan Pekerjaan (C+D) 133,003.14
A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton SNI
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.150 63,100.00 9,465.00
Tukang L.02 OH 0.050 79,500.00 3,975.00
Kepala Tukang L.03 OH 0.005 79,500.00 397.50
Mandor L.04 OH 0.008 74,100.00 592.80
JUMLAH TENAGA KERJA 14,430.30
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.0264 2,567,500.00 67,782.00
Paku 5 - 10 cm kg 0.600 14,200.00 8,520.00
Dolken kayu φ 8-10cm – panj. 4 m btg 0.500 48,000.00 24,000.00
JUMLAH HARGA BAHAN 100,302.00

C JUMLAH (A+B) 114,732.30


D Overhead & Profit 17,209.85
E Harga Satuan Pekerjaan (C+D) 131,942.15

A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP SNI
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 63,100.00 18,930.00
Tukang batu L.02 OH 0.100 79,500.00 7,950.00
Kepala tukang L.03 OH 0.010 79,500.00 795.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 28,786.50
B BAHAN
Bata merah buah 70.000 1,000.00 70,000.00
Semen portan kg 11.500 1,100.00 12,650.00
Pasir pasang m³ 0.043 243,100.00 10,453.30
JUMLAH HARGA BAHAN 93,103.30

C JUMLAH (A+B) 121,889.80


D Overhead & Profit 18,283.47
E Harga Satuan Pekerjaan (C+D) 140,173.27

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm (termasuk acian) SNI


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 63,100.00 18,930.00
Tukang batu L.02 OH 0.150 79,500.00 11,925.00
Kepala tukang L.03 OH 0.015 79,500.00 1,192.50
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 33,159.00
B BAHAN
Semen portland kg 6.240 1,100.00 6,864.00
Pasir pasang m³ 0.024 243,100.00 5,834.40
JUMLAH HARGA BAHAN 12,698.40

C JUMLAH (A+B) 45,857.40


D Overhead & Profit 6,878.61
E Harga Satuan Pekerjaan (C+D) 52,736.01
A.5.1.1.36. Pemasangan 1 m' pipa beton Ø 30 - Ø 100 cm SNI
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.380 63,100.00 23,978.00
Tukang Batu L.02 OH 0.190 79,500.00 15,105.00
Kepala Tukang L.03 OH 0.019 79,500.00 1,510.50
Mandor L.04 OH 0.019 74,100.00 1,407.90
JUMLAH TENAGA KERJA 42,001.40
B BAHAN
Pipa tanah Ø 30 cm (Pipa Beton ø 30 cm (Buis Beton)) bh 1.100 80,500.00 88,550.00
Bata merah m 3
0.550 1,000.00 550.00
Semen Portland kg 10.300 1,100.00 11,330.00
Pasir Pasang m3 0.061 243,100.00 14,829.10
Pasir Urug m 3
0.069 151,000.00 10,419.00
JUMLAH HARGA BAHAN 125,678.10

C JUMLAH (A+B) 167,679.50


D Overhead & Profit 25,151.93
E Harga Satuan Pekerjaan (C+D) 192,831.43

A.PV.1 1 m2 Pas. Paving Block Natural 6 cm HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.250 63,100.00 15,775.00
Tukang Batu L.02 OH 0.500 79,500.00 39,750.00
Kepala Tukang L.03 OH 0.050 79,500.00 3,975.00
Mandor L.04 OH 0.025 74,100.00 1,852.50
JUMLAH TENAGA KERJA 61,352.50
B BAHAN
Paving Block Natural 6 cm m2 1.010 85,200.00 86,052.00
Pasir Halus m3 0.100 194,300.00 19,430.00
JUMLAH HARGA BAHAN 105,482.00

C JUMLAH (A+B) 166,834.50


D Overhead & Profit 25,025.18
E Harga Satuan Pekerjaan (C+D) 191,859.68

A.WLS.1 Biaya Menggilas sebulan ( 25 hari x 5 jam kerja = 125 jam ) BOW
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Masinis OH 25.000 109,800.00 2,745,000.00
Pembantu Masinis OH 25.000 71,300.00 1,782,500.00
Penjaga Malam OH 30.000 57,600.00 1,728,000.00
Pekerja OH 150.000 63,100.00 9,465,000.00
JUMLAH TENAGA KERJA 15,720,500.00
B BAHAN
Solar liter 800.000 6,700.00 5,360,000.00
Olie Kaleng liter 30.000 - -
JUMLAH HARGA BAHAN 5,360,000.00
C PERALATAN
Sewa Wales hari 25.000 - -
JUMLAH HARGA ALAT -

D JUMLAH (A+B+C) 21,080,500.00


E Overhead & Profit 3,162,075.00
F Harga Satuan Pekerjaan (D+E) 24,242,575.00
A.WLS.2 Pemadatan 1 m3 Urugan dengan Wales HSPK
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Biaya Menggilas (sewa wales) = 3/7500 (A.WLS.1) OH 0.0004 24,242,575.00 9,697.03
JUMLAH TENAGA KERJA 9,697.03
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 9,697.03


D Overhead & Profit 1,454.55
E Harga Satuan Pekerjaan (C+D) 11,151.58

P. 01 Pasangan batu dengan mortar jenis PC-PP (1 m3)


c) Mortar tipe N (untuk mutu PP tertentu setara dengan campuran 1 PC:4 PP)
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 2.700 63,100.00 170,370.00
Tukang Batu L.02 OH 0.900 79,500.00 71,550.00
Kepala Tukang L.03 OH 0.090 79,500.00 7,155.00
Mandor L.04 OH 0.270 74,100.00 20,007.00
JUMLAH TENAGA KERJA 269,082.00
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Semen Portland kg 163.000 1,100.00 179,300.00
Pasir pasang m³ 0.520 243,100.00 126,412.00
JUMLAH HARGA BAHAN 618,432.00

C PERALATAN
Molen unit/hari 0.167 150,000.00 25,050.00
JUMLAH HARGA ALAT 25,050.00

D JUMLAH (A+B+C) 912,564.00


E Overhead & Profit 136,884.60
F Harga Satuan Pekerjaan (D+E) 1,049,448.60
HARGA SATUAN PEKERJAAN

NO

1
2
3
4
5
6
7
8

9
10
11
12
13
14
15
16
17
18
19
20
21
22

23
24
25
26
27
28
29

30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63

64
65
66
67
68
69
70
71
72
73
74
75
76
77

78
79
80
81
82
83
84

85
86
87
88
89
90
91
92
93
94

95
96
97
98

99
100
101
102
103
104
105
106
107
108
109
110

111
112
113
114
115
116
117
118
119
120

121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143

144
145
146
147
148

149
150
151
152
153
154

155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184

185
186
187
188
189
190
191
192
193
194
195
196
HARGA SATUAN PEKERJAAN

JENIS PEKERJAAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
Pengukuran dan pemasangan Bouwplank
Pembuatan kantor sementara lantai plesteran
Pembersihan lapangan dan perataan
Pembuatan steger/perancah dari bambu
Pembuatan jalan sementara
Pembongkaran beton bertulang
Pembongkaran dinding tembok bata

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


Penggalian tanah biasa sedalam 1 m
Penggalian tanah biasa sedalam 2 m
Penggalian tanah biasa sedalam 3 m
Menggali tanah keras sedalam 1 m
Menggali tanah cadas sedalam 1 m
Menggali tanah lumpur sedalam 1 m
Pengerjaan stripping tanah tebing setinggi 1 meter
Pembuangan tanah sejauh 30 meter
Pengurugan kembali galian tanah
Pemadatan tanah tanah ( per 20 cm)
Pengurugan dengan pasir urug
Pemasangan lapisan ijuk tebal 10 cm untuk bidang resapan
Pengurugan sirtu padat
Pengurugan 1 m3 tanah pilihan

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


Pemasangan pondasi batu belah campuran 1SP : 3PP
Pemasangan pondasi batu belah campuran 1SP : 4PP
Pemasangan pondasi batu belah campuran 1SP : 5PP
Pemasangan pondasi batu belah campuran 1SP : 6PP
Pemasangan batu kosong (anstamping)
Pemasangan pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
Pemasangan pondasi sumuran, diameter 100 cm

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Membuat beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Membuat beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Membuat beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Membuat lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Membuat beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Membuat beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Membuat beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Membuat beton mutu f’c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Membuat beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Membuat beton mutu f’c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
Membuat beton mutu f’c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Pembesian dengan besi polos atau besi ulir
Pemasangan jaring kawat baja (wiremesh)
Pemasangan bekisting untuk pondasi
Pemasangan bekisting untuk sloof
Pemasangan bekisting untuk kolom
Pemasangan bekisting untuk balok
Pemasangan bekisting untuk lantai
Pemasangan bekisting untuk dinding
Pemasangan bekisting untuk tangga
Pemasangan jembatan untuk pengecoran beton
Membuat pondasi beton bertulang (150 kg besi + bekisting)
Membuat sloof beton bertulang (200 kg besi + bekisting)
Membuat kolom beton bertulang (300 kg besi + bekisting)
Membuat balok beton bertulang (200 kg besi + bekisting)
Membuat kolom beton bertulang (150 kg besi + bekisting)
Membuat dinding beton bertulang (150 kg besi + bekisting)
Membuat dinding beton bertulang (200 kg besi + bekisting)
Membuat kolom praktis beton bertulang (11 x 11) cm
Membuat ring balok beton bertulang (10 x 15) cm
Membuat 1 m' sloof beton bertulang (15 x 20) cm
Membuat 1 m3 beton tumbuk 1PC : 3PS : 5KR
Membuat 1 m2 bekisting untuk permukaan beton biasa dengan papan ukuran 2/20 cm (tanpa perancah)

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM


Pemasangan besi profil
Pemasangan rangka kuda-kuda baja IWF
Pengerjaan pekerjaan perakitan
Pengerjaan pengelasan dengan las listrik
Pemasangan pintu rolling door besi
Pemasangan rolling door alluminium
Pemasangan kusen pintu alluminium
Pemasangan pintu alluminium strip lebar 8 cm
Pemasangan pintu kaca rangka alluminium
Pemasangan terali besi strip (2 x 3) mm
Pemasangan talang datar/ jurai seng bjls 28 lebar 90 cm
Pemasangan talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
Pemasangan rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, dinding partisi
Pemasangan rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP
Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 4PP
Pemasangan dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 5PP
Pemasangan dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 6PP
Pemasangan dinding terawang (rooster) 12x11x24 campuran 1SP : 4PP

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


Pemasangan plesteran 1SP : 2PP tebal 15 mm (termasuk acian)
Pemasangan plesteran 1SP : 3PP tebal 15mm (termasuk acian)
Pemasangan plesteran 1SP : 4PP tebal 15 mm (termasuk acian)
Pemasangan plesteran 1SP : 5PP tebal 15 mm (termasuk acian)
Pemasangan plesteran 1SP : 6PP tebal 15 mm (termasuk acian)
Pemasangan plesteran skoning 1SP : 3PP lebar 10 cm
Pemasangan plesteran ciprat 1SP : 2PP
Pemasangan finishing siar pasangan bata merah
Pemasangan finishing siar pasangan conblock ekspose
Pemasangan finishing siar pasangan batu kali, campuran 1SP : 2PP.

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


Pemasangan lantai keramik ukuran 30 cm x 30 cm
Pemasangan lantai keramik ukuran 20 cm x 20 cm
Pemasangan dinding keramik 20 cm x 20 cm
Pemasangan dinding batu tempel hitam

A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


Pemasangan langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
Pemasangan langit-langit tripleks ukuran ( 120 x 240 ) cm, tebal 3 mm, 4 mm & 6 mm
Pemasangan langit-langit gypsum board ukuran ( 120 x 240 x 9 ) mm, tebal 9 mm
Pemasangan langit-langit akuistik ukuran ( 60 x 120 ) mm berikut rangka alluminium
Pemasangan langit-langit kayu profil
Pemasangan Rangka langit-langit besi hollow 40.40
1 M2 PAS. PLAFOND TRIPLEK 6 MM BERIKUT RANGKA Ky. Meranti Batu
1 M2 PAS. RANGKA PLAFOND KAYU Meranti Batu DIMENI KAYU ( HANYA RANGKA )
1 M2 LANGIT - LANGIT ETERNIT 4 MM, RANGKA KAYU KEMPAS
1 M' List Langit-Langit Kayu Profil
1 M2 PAS. BAHAN PLAFOND HARDFLEX 5 MM PADA RANGKANYA
1 M2 PAS. LANGIT-LANGIT ASBES SEMEN, TEBAL 4,5,6 MM

A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


Pemasangan atap genteng palentong kecil
Pemasangan atap genteng palentong besar / super
Pemasangan bubung genteng palentong
Pemasangan bubung genteng palentong besar
Pemasangan atap asbes gelombang 1.05 m x 3.00 m x 4 mm
Pemasangan atap asbes gelombang 1.08 m x 1.80 m x 6 mm
Pemasangan bubung stel gelombang 1.05 m
Pemasangan bubung stel gelombang 1.08 m
Pemasangan genteng beton
Pemasangan nok genteng beton

A.4.6.1 HARGA SATUAN PEKERJAAN KAYU


Pembuatan dan pemasangan kusen pintu dan kusen jendela, kayu kelas I
Pembuatan dan pemasangan kusen pintu dan kusen jendela, kayu kelas II atau III
Pembuatan dan pemasangan pintu klamp standar, kayu kelas II
Pembuatan dan pemasangan pintu klamp sederhana, kayu kelas III
Pembuatan dan pemasangan daun pintu panel, kayu kelas I dan II
Pembuatan dan pemasangan pintu dan jendela kaca, kayu kelas I dan II
Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kelas I dan II
Pembuatan daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
Pembuatan daun pintu plywood rangkap, rangka expose kayu kelas I atau II
Pemasangan teakwood rangkap, rangka expose kayu kelas I
Pemasangan teakwood rangkap lapis formika, rangka expose kayu kelas II
Pemasangan konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 m
Pemasangan konstruksi kuda-kuda expose, kayu kelas I
Pemasangan konstruksi gording, kayu kelas II
Pemasangan rangka atap genteng keramik, kayu kelas II
Pemasangan rangka atap genteng beton, kayu kelas II
Pemasangan rangka atap sirap, kayu kelas II
Pemasangan rangka langit-langit (50 x 100) cm, kayu kelas II atau III
Pemasangan rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Pemasangan lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Pemasangan lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II
Pemasangan 1 m² dinding pemisah teakwood rangkap, rangka ky kelas II
Pemasangan 1 m² dinding pemisah plywood rangkap, rangka ky kelas II

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA


Pemasangan kunci tanam biasa
Pemasangan engsel pintu
Pemasangan engsel jendela kupu-kupu
Pemasangan kait angin
Pemasangan kaca tebal 5 mm

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


Pengecatan bidang kayu baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
Pelaburan bidang kayu dengan politur
Pengecatan tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
Pengecatan permukaan baja galvanis secara manual sistem 3 lapis
Pengecatan permukaan besi 3 x

A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


Pemasangan closet duduk / monoblock
Pemasangan closet jongkok porselen
Pemasangan closet jongkok teraso
Pemasangan urinoir
Pemasangan wastafel
Pemasangan bathtub porselen
Pemasangan bak fibreglass vol 1 m3
Pemasangan bak mandi batu bata vol 0.30 m 3
Pemasangan bak cuci piring stainlessteel
Pemasangan floor drain
Pemasangan bak kontrol pasangan bata 30 x 30 tinggi 35 cm
Pemasangan bak kontrol pasangan bata 45 x 45 tinggi 50 cm
Pemasangan bak kontrol pasangan bata 60 x 60 tinggi 65 cm
Pemasangan pipa galvanis diameter 1/2"
Pemasangan kran diameter 1/2" atau 3/4"
Pemasangan pipa galvanis diameter 3/4"
Pemasangan pipa galvanis diameter 1"
Pemasangan pipa galvanis diameter 1 1/2"
Pemasangan pipa galvanis diameter 3"
Pemasangan pipa galvanis diameter 4"
Pemasangan pipa PVC tipe AW diameter 1/2"
Pemasangan pipa PVC tipe AW diameter 3/4"
Pemasangan pipa PVC tipe AW diameter 1"
Pemasangan pipa PVC tipe AW diameter 1 1/2"
Pemasangan pipa PVC tipe AW diameter 2"
Pemasangan pipa PVC tipe AW diameter 2 1/2"
Pemasangan pipa PVC tipe AW diameter 3"
Pemasangan pipa PVC tipe AW diameter 4"
Pemasangan pipa beton Ø 15 - Ø 20 cm
Pemasangan pipa beton Ø 30 - Ø 100 cm

HARGA SATUAN PEKERJAAN JALAN


Pemadatan 1 m3 Urugan dengan Wales
1 M2 PAS. ONDERLAG BATU BELAH T. 20 CM
1 M2 PAS. ONDERLAG BATU BELAH T 15 CM
1 M2 AMPARAN BATU PECAH MESIN 2/3 T = 5 CM
1 M2 AMPARAN BATU PECAH MESIN 3/4, 2/3, 1/2 T = 5 CM
1 M2 PENGASPALAN MANUAL
1 M2 HOTMIX TANGAN T = 3 CM (JADI) UNTUK HAL & JLN KLS 6 TON KEBAWAH
1 M2 HOTMIX TANGAN T = 2 CM (JADI) UNTUK HAL & JLN KLS 6 TON KEBAWAH
1 M2 PAS. PAVING BLOCK NATURAL 6 CM
1 M2 PAS. PAVING BLOCK NATURAL 6 CM Lama
Bongkar Paving
BIAYA MENGGILAS SEBULAN ( 25 HARI x 5 JAM KERJA = 125 JAM )
KODE SATUAN HARGA SATUAN KETERANGAN

A. 2.2.1.2 m2 Rp 520,810.00
A. 2.2.1.4 m' Rp 584,594.00
A. 2.2.1.5 m2 Rp 1,680,631.00
A. 2.2.1.9 m2 Rp 66,805.00
A. 2.2.1.10 m2 Rp 288,275.00
A. 2.2.1.12 m2 Rp 131,550.00
A. 2.2.1.13 m3 Rp 890,726.00
A. 2.2.1.14 m3 Rp 66,744.00

A.2.3.1.1 m3 Rp 39,697.00 34,519.13


A.2.3.1.2 m3 Rp 47,594.00
A.2.3.1.3 m3 Rp 53,587.00
A.2.3.1.4 m3 Rp 65,471.00
A.2.3.1.5 m3 Rp 99,096.00
A.2.3.1.6 m3 Rp 58,712.00
A.2.3.1.7 m2 Rp 3,525.00
A.2.3.1.8 m3 Rp 21,564.00
A.2.3.1.9 m3 Rp 35,255.00
A.2.3.1.10 m3 Rp 35,255.00
A.2.3.1.11 m3 Rp 200,871.00
A.2.3.1.13 m2 Rp 314,895.00
A.2.3.1.14 m3 Rp 286,907.00
A.2.3.1.14.A m3 Rp 110,592.00

A.3.2.1.1 m3 Rp 818,618.00
A.3.2.1.2 m3 Rp 784,227.00
A.3.2.1.3 m3 Rp 760,361.00 661,183.48
A.3.2.1.4 m3 Rp 743,594.00
A.3.2.1.9 m3 Rp 464,165.00 403,621.74
A.3.2.1.10 m3 Rp 2,118,528.00
A.3.2.1.11 m3 Rp 781,113.00

A.4.1.1.1 m3 Rp 785,239.00
A.4.1.1.2 m3 Rp 812,990.00
A.4.1.1.3 m3 Rp 834,397.00
A.4.1.1.4 m3 Rp 740,407.00
A.4.1.1.5 m3 Rp 856,912.00
A.4.1.1.6 m3 Rp 884,089.00
A.4.1.1.7 m3 Rp 1,038,352.00
A.4.1.1.8 m3 Rp 1,051,497.00
A.4.1.1.9 m3 Rp 1,074,313.00
A.4.1.1.10 m3 Rp 1,081,255.00
A.4.1.1.11 m3 Rp 1,150,032.00
A.4.1.1.12 m3 Rp 1,159,241.00
A.4.1.1.17 kg Rp 11,565.00
A.4.1.1.19 kg Rp 774.00
A.4.1.1.20 m2 Rp 82,487.00
A.4.1.1.21 m2 Rp 88,979.00
A.4.1.1.22 m2 Rp 197,415.00
A.4.1.1.23 m2 Rp 204,294.00
A.4.1.1.24 m2 Rp 293,415.00
A.4.1.1.25 m2 Rp 253,049.00 Harga Spacer Belum Ada
A.4.1.1.26 m2 Rp 392,085.00
A.4.1.1.27 m2 Rp 65,971.00
A.4.1.1.28 m3 Rp 3,960,142.00
A.4.1.1.29 m3 Rp 4,841,828.00
A.4.1.1.30 m3 Rp 9,127,799.00
A.4.1.1.31 m3 Rp 6,885,007.00
A.4.1.1.32 m3 Rp 7,187,426.00
A.4.1.1.33 m3 Rp 6,720,289.00
A.4.1.1.34 m3 Rp 6,541,796.00
A.4.1.1.35 m' Rp 79,573.00 69,193.91
A.4.1.1.36 m' Rp 98,560.00
A026 I m' Rp 105,424.00 91,673.04
A024 m3 Rp 881,489.00
B.22 m2 Rp 170,226.00

A.4.2.1.1 kg Rp 26,773.00
A.4.2.1.2 kg Rp 29,418.00
A.4.2.1.3 kg Rp 240.00 Harga Sewa Alat Belum Ada
A.4.2.1.5 1 cm Rp 2,325.00 Harga Sewa Alat Belum Ada
A.4.2.1.7 m2 Rp 208,270.00 Harga Bahan Belum Ada
A.4.2.1.10 m2 Rp 177,393.00 Harga Bahan Belum Ada
A.4.2.1.11 m' #REF! Harga Bahan Belum Ada
A.4.2.1.12 m2 Rp 15,074.00 Harga Bahan Belum Ada
A.4.2.1.13 m2 #REF! Harga Bahan Belum Ada
A.4.2.1.15 m2 Rp 463,096.00
A.4.2.1.18 m' Rp 212,598.00
A.4.2.1.19 m' Rp 65,567.00
A.4.2.1.20 m2 Rp 44,390.00 Harga Bahan Belum Ada
A.4.2.1.21 m2 Rp 62,130.00 Harga Bahan Belum Ada

A. 4.4.1.3 m2 Rp 286,794.00
A. 4.4.1.7 m2 Rp 148,199.00 128,868.70
A. 4.4.1.8 m2 Rp 142,965.00
A. 4.4.1.9 m2 Rp 121,889.00
A. 4.4.1.10 m2 Rp 138,430.00
A. 4.4.1.11 m2 Rp 137,827.00
A. 4.4.1.23 cm2 Rp 1,517,308.00

A.4.4.2.2 m2 Rp 56,657.00
A.4.4.2.3 m2 Rp 54,399.00
A.4.4.2.4 m2 Rp 45,857.00 39,875.65
A.4.4.2.5 m2 Rp 51,769.00
A.4.4.2.6 m2 Rp 51,267.00
A.4.4.2.20 m' Rp 50,639.00
A.4.4.2.23 m2 Rp 36,451.00
A.4.4.2.24 m2 Rp 23,086.00
A.4.4.2.25 m2 Rp 11,009.00
A.4.4.2.26 m2 Rp 49,507.00

A.4.4.3.35 m2 Rp 147,535.00
A.4.4.3.36 m2 Rp 162,585.00
A.4.4.3.54 m2 Rp 171,777.00
A.4.4.3.58 m2 Rp 217,734.00

A.4.5.1.1 m2 Rp 29,065.00
A.4.5.1.5 m2 Rp 41,362.00
A.4.5.1.7 m2 Rp 38,976.00 Harga Paku Skrup Belum Ada
A.4.5.1.8 m2 #REF! Harga Bahan Belum Ada
A.4.5.1.9 m2 Rp 31,768.00
A.4.5.1.10 m2 #REF! Harga Bahan Belum Ada
A082 m2 Rp 221,345.00
A085 m2 Rp 138,229.00
A085 C m2 Rp 167,903.00
A085 D m Rp 31,768.00
A086 m2 Rp 46,429.00
A087 m2 Rp 30,445.00

A.4.5.2.1 m2 Rp 87,375.00
A.4.5.2.3 m2 Rp 57,398.00
A.4.5.2.4 m' Rp 92,689.00
A.4.5.2.6 m' Rp 89,489.00
A.4.5.2.12 m2 Rp 71,500.00
A.4.5.2.21 m2 Rp 61,957.00
A.4.5.2.23 m' Rp 19,941.00 Harga Bahan Belum Ada
A.4.5.2.24 m' Rp 19,941.00 Harga Bahan Belum Ada
A.4.5.2.30 m2 Rp 116,716.00
A.4.5.2.34 m2 Rp 146,525.00

A.4.6.1.1 m3 Rp 18,537,442.00
A.4.6.1.2 m3 Rp 11,979,642.00
A.4.6.1.3 m2 Rp 474,259.00
A.4.6.1.4 m2 Rp 477,626.00
A.4.6.1.5 m2 Rp 1,112,623.00
A.4.6.1.6 m2 Rp 747,530.00
A.4.6.1.7 m2 Rp 1,514,317.00
A.4.6.1.8 m2 Rp 611,119.00
A.4.6.1.9 m2 Rp 871,146.00
A.4.6.1.11 m2 Rp 872,052.00
A.4.6.1.12 m2 Rp 935,439.00
A.4.6.1.13 m3 Rp 17,551,852.00
A.4.6.1.14 m3 Rp 10,604,345.00
A.4.6.1.15 m3 Rp 11,641,294.00
A.4.6.1.16 m2 Rp 273,762.00
A.4.6.1.17 m2 Rp 374,929.00
A.4.6.1.18 m2 Rp 133,596.00
A.4.6.1.19 m2 Rp 161,773.00
A.4.6.1.20 m2 Rp 167,045.00
A.4.6.1.21 m' Rp 120,884.00
A.4.6.1.22 m' Rp 120,068.00
A.4.6.1.24 m2 Rp 444,423.00
A.4.6.1.25 m2 Rp 400,017.00

A.4.6.2.2 buah Rp 153,762.00


A.4.6.2.5 buah Rp 40,821.00
A.4.6.2.6 buah Rp 29,530.00
A.4.6.2.9 buah Rp 32,407.00
A.4.6.2.17 m2 Rp 193,139.00 Harga sealant dalam kg belum ada

A.4.7.1.4 m2 Rp 49,180.00
A.4.7.1.7 m2 Rp 18,846.00 Harga Politur Belum Ada
A.4.7.1.10 m2 Rp 19,309.00
A.4.7.1.11 m2 Rp 14,242.00
A.4.7.1.20 m2 Rp 118,160.00
A079 m2 Rp 72,286.00 HSPK

A.5.1.1.1 buah Rp 1,981,965.00


A.5.1.1.2 buah Rp 381,862.00
A.5.1.1.3 buah Rp 2,842,811.00
A.5.1.1.4 buah Rp 1,603,036.00
A.5.1.1.5 buah Rp 797,542.00
A.5.1.1.6 buah Rp 16,879.00 Harga Bathub Belum Ada
A.5.1.1.7 buah Rp 940,499.00
A.5.1.1.8 buah Rp 2,043,603.00
A.5.1.1.12 buah Rp 524,439.00
A.5.1.1.14 buah Rp 38,246.00
A.5.1.1.15 buah Rp 357,193.00
A.5.1.1.16 buah Rp 534,977.00
A.5.1.1.17 buah Rp 674,933.00
A.5.1.1.18 m' Rp 50,538.00
A.5.1.1.19 buah Rp 113,769.00
A.5.1.1.20 m' Rp 52,648.00
A.5.1.1.21 m' Rp 67,218.00
A.5.1.1.22 m' Rp 22,926.00 Harga Pipa Belum Ada
A.5.1.1.23 m' Rp 205,763.00
A.5.1.1.24 m' Rp 395,328.00
A.5.1.1.25 m' Rp 15,726.00
A.5.1.1.26 m' Rp 18,516.00
A.5.1.1.27 m' Rp 22,546.00
A.5.1.1.28 m' Rp 36,610.00
A.5.1.1.29 m' Rp 43,430.00
A.5.1.1.30 m' Rp 64,488.00
A.5.1.1.31 m' Rp 82,623.00
A.5.1.1.32 m' Rp 125,403.00
A.5.1.1.35 m' Rp 101,400.00
A.5.1.1.36 m' Rp 167,679.00

A020 A m3 4,646.00
A109 m2 116,727.00
A109 A m2 91,448.00
A111 m2 30,014.00
A111 A m2 63,428.00
A113 m2 42,478.00
A114 m2 62,250.00
A114 A m2 46,687.00
A121 m2 166,834.00
A121 A m2 85,662.00
A121 B m2 3,525.00
W4 Bulan 11,615,500.00
HARGA SATUAN PEKERJAAN

NO JENIS PEKERJAAN KODE SATUAN HARGA SATUAN

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


9 Penggalian tanah biasa sedalam 1 m A.2.3.1.1 m3 #REF!
17 Pengurugan kembali galian tanah A.2.3.1.9 m3 #REF!
19 Pengurugan dengan pasir urug A.2.3.1.11 m3 #REF!

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


24 Pemasangan pondasi batu belah campuran 1SP : 4PP A.3.2.1.2 m3 #REF!

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Err:520 Membuat beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 A.4.1.1.1 m3 #REF!
Err:520 Membuat beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 A.4.1.1.6 m3 #REF!
Err:520 Pembesian dengan besi polos atau besi ulir A.4.1.1.17 kg #REF!
Err:520 Pemasangan bekisting untuk pondasi A.4.1.1.20 m2 #REF!
Err:520 Pemasangan bekisting untuk sloof A.4.1.1.21 m2 #REF!
Err:520 Pemasangan bekisting untuk kolom A.4.1.1.22 m2 #REF!
Err:520 Pemasangan bekisting untuk balok A.4.1.1.23 m2 #REF!
Err:520 Membuat kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35 m' #REF!
Err:520 Membuat ring balok beton bertulang (10 x 15) cm A.4.1.1.36 m' #REF!
Err:520 Membuat 1 m' sloof beton bertulang (15 x 20) cm A026 I m' #REF!
Err:520 Membuat 1 m2 bekisting untuk permukaan beton biasa dengan papan ukuran 2/20 cm (tanpa perancah) B.22 m2 #REF!

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Err:520 Pemasangan dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 4PP A. 4.4.1.9 m2 #REF!

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


Err:520 Pemasangan plesteran 1SP : 4PP tebal 15 mm (termasuk acian) A.4.4.2.4 m2 #REF!

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


Err:520 Pengecatan tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) A.4.7.1.10 m2 #REF!
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN :
PEKERJAAN : REHABILITASI BALAI DESA BALAPULANG WETAN TAHAP I
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2015

HARGA JUMLAH JUMLAH


NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN. Rp HARGA . Rp SEMUA . Rp
1 2 3 4 5 6 7 8
I PEKERJAAN TANAH
1 Pek. Galian tanah A.2.3.1.1 31.45 M3 #REF! #REF!
2 Pek. Urugan kembali bekas galian A.2.3.1.9 7.86 M3 #REF! #REF!
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 1.60 M3 #REF! #REF!
Jumlah #REF!
II PEKERJAAN BETON
1 Pemasangan pondasi batu belah campuran 1SP : 4PP A.3.2.1.2 9.75 m3 #REF! #REF!
2 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.61 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 434.71 kg #REF! #REF!
Pemasangan bekisting untuk sloof A.4.1.1.21 20.07 m2 #REF! #REF!
3 Pondasi Plat Menerus (tidak Termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 4.14 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 699.19 kg #REF! #REF!
Pemasangan bekisting untuk pondasi A.4.1.1.20 19.68 m2 #REF! #REF!
4 Kolom (tidak termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 6.48 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,197.15 kg #REF! #REF!
Pemasangan bekisting untuk kolom A.4.1.1.22 20.25 m2 #REF! #REF!
5 Membuat ring balok beton bertulang (10 x 15) cm A.4.1.1.36 74.00 m' #REF! #REF!
Jumlah #REF!

Jumlah Total Rp. #REF!


PPN + PPH 11.5% Rp. #REF!
Jumlah #REF!
PERHITUNGAN VOLUME
KEGIATAN :
PEKERJAAN : REHABILITASI BALAI DESA BALAPULANG WETAN TAHAP I
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2015

NO GAMBAR DETAIL

8Ø12

+4.50 6Ø12
Ø8 - 15

+3.00 Ø8 - 15

8Ø12

Ø8 - 15

±0.00
-1.20
9.00
DETAIL
POTONGAN B-B DENAH PENULANGAN FOOT PLAT
1:10 DENAH PENULANGAN FOOT PLAT
1 : 100 1:10

URAIAN PEKERJAAN PERHITUNGAN

PEKERJAAN PERSIAPAN
1 Galian Tanah (1.2*1*1*16)+(0.5*49*0.5) = 31.45 m3
2 Urugan kembali bekas galian 1/4* (1.2*1*1*16)+(0.5*49*0.5) = 7.86 m3
PEKERJAAN BETON
Urugan Pasir Bawah Pondasi 0.1*1*1*16 = 1.60 m3
(0.2+0.4)*0.5/2*65
Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) 0.2*0.3*(65-(0.3*16)) = 3.61 m3
Pembesian 1 kg dengan besi polos atau besi ulir ((0.617*6*74)+(74*5*1.1*0.395 = 434.71
Bekisting 1*(65-(0.3*16))/3 = 20.07 m2
Pondasi Plat Menerus (tidak Termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) ((0.8*0.8*0.25)+(0.3*0.3*1.1))*16 = 4.14 m3
Pembesian 1 kg dengan besi polos atau besi ulir (42*0.888*16)+(1.2*8*0.667*16) = 699.19
Bekisting ((3.6*0.35)+(1*1.2))*8 = 19.68 kg
Kolom (tidak termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) (0.3*0.3*4.5*16) = 6.48 m3
Pembesian 1 kg dengan besi polos atau besi ulir (0.888*8*5.5*16)+(1.3*5*5.5*(1 = 1,197.15
Bekisting (0.9*4.5*5) = 20.25 m2
Ring balok = 74 m
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : LANJUTAN PENGEMBANGAN MASJID ATTOYBAH
PEKERJAAN : PEMBANGUNAN PAGAR MASJID
LOKASI : DESA TEMBOK KIDUL
TAHUN ANGGARAN : 2015

HARGA JUMLAH JUMLAH


NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN. Rp HARGA . Rp SEMUA . Rp
1 2 3 4 5 6 7 8
A LANTAI I
I PEK. PERSIAPAN
1 Pengadaan Air Kerja Taksir 1.00 Unit 500,000.00 500,000.00
5 Ukur Proyek / bouplank Taksir 1.00 Unit 300,000.00 300,000.00
Jumlah 800,000.00
II PEKERJAAN TANAH
1 Pek. Galian tanah A.2.3.1.1 4.14 M3 #REF! #REF!
2 Pek. Urugan kembali bekas galian A.2.3.1.9 1.04 M3 #REF! #REF!
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 0.74 M3 #REF! #REF!
Jumlah #REF!
III PEKERJAAN BETON
1 Pasang Sloof 15/20 A026 I 28.75 M' 94,487.00 2,716,501.25
2 Pasang Kolom struktur 30/40
Membuat beton mutu f’c = 24,0 MPa A.4.1.1.9 2.64 M3 1,074,313.00 2,836,186.32
Pembesian dengan besi polos atau besi ulir A.4.1.1.17 104.09 Kg #REF! #REF!
Pemasangan bekisting untuk kolom A.4.1.1.22 14.08 M2 #REF! #REF!
6 Pasang Kolom praktis 15/15 A.4.1.1.35 28.80 M' #REF! #REF!
7 Pasang Ring Balok lengkung (praktis) A.4.1.1.36 36.00 m' #REF! #REF!
11 Pasang Plat beton 12 cm
Membuat beton mutu f’c = 24,0 MPa A.4.1.1.20 0.44 M3 1,074,313.00 476,994.97
Pembesian dengan besi polos atau besi ulir A.4.1.1.24 22.829 Kg #REF! #REF!
Pemasangan Bekisting A.4.1.1.28 3.50 M2 #REF! #REF!

Jumlah #REF!
IV PEK. KAYU / PASANGAN
1 Pasang Batu kosong #REF! 1.18 M3 #REF! #REF!
2 Pasang Pondasi batu belah 1 : 4 A.3.2.1.2 2.59 M3 #REF! #REF!
3 Pasang Dinding batu bata 1 : 4 1 bata A. 4.4.1.3 28.80 M2 286,794.00 8,259,667.20
4 Pasang Dinding batu bata 1 : 4 1/2 bata A. 4.4.1.9 28.16 m2 #REF! #REF!
5 Pasang Plesteran 1:4 A.4.4.2.4 170.88 M2 #REF! #REF!
6 Pasang Plesteran skoning A.4.4.2.20 250.00 m' 50,639.00 12,659,750.00
7 Pasang batu candi A.4.4.3.58 8.80 M2 217,734.00 1,916,059.20
8 Pasang Ornamen GRC pada Gerbang Ls 10.00 m2 750,000.00 7,500,000.00
Jumlah #REF!
VI PEK. CAT
1 Cat Tembok Baru ( Metrolite ) N 03 200.00 M2 18,659.00 3,731,800.00

V PEK. STAINLESS STEEL


1 Pasang Teralis pada pagar ls 21.00 m2 1,500,000.00 31,500,000.00
2 Pasang Pintu Gerbang dari stainless steel ls 14.80 m2 1,750,000.00 25,900,000.00
Jumlah 57,400,000.00

BOW SOME Rp. #REF!


DIBULATKAN Rp. #REF!
TERBILANG : SERATUS DUA BELAS JUTA DUA RATUS SEMBILAN PULUH DUA RIBU RUPIAH
REKAPITULASI RAB
KEGIATAN : REHAB GEDUNG SMA/SMK
PEKERJAAN : PEMBANGUNAN RKB SMA NEGERI 5
LOKASI : SMA NEGERI 5 KOTA TEGAL
TAHUN ANGGARAN : 2015

JUMLAH
NO URAIAN PEKERJAAN
HARGA
1 2 3

A PEKERJAAN LANTAI I
I PEK. PERSIAPAN Rp 2,950,000.00
II PEK. TANAH Rp 16,139,402.99
III PEK. BETON Rp 390,542,555.55
IV PEK. KAYU / PASANGAN Rp 183,672,379.80
V PEK. PENUTUP / KAP Rp 52,420,141.46
VI 0 Rp 42,426,293.72
Jumlah
B PEKERJAAN LANTAI II
I PEK. BETON Rp 59,145,148.44
II PEK. KAYU / PASANGAN Rp 246,079,522.49
III PEK. PENUTUP / KAP Rp 27,033,861.00
IV PEK. CAT DLL Lt II Rp 36,969,319.99
V PEK. PENGHANTAR PETIR Rp 7,994,250.00
Jumlah

JUMLAH TOTAL
DIBULATKAN

TERBILANG : SATU MILYAR ENAM PULUH LIMA JUTA TIGA RATUS TUJUH PULUH DUA RIBU RUPIAH

Tegal, …………………………… 2015

SARANA DAN PRASARANA (SARPAS) Perencana


SMA NEGERI 5 KOTA TEGAL CV. SINAR KONSULTAN JAYA

SUWITNO, S.Pd Drs. KOMAR SOFIHUDIN


NIP. 19671208 200012 1 002 Direktur

Mengetahui,
KEPALA SMA NEGERI 5
KOTA TEGAL

MASDUKI, S.Pd., M.Pd.


NIP. 19661007 199003 1 009
JUMLAH
SEMUA
4

Rp 688,150,773.52

Rp 377,222,101.92

Rp 1,065,372,875.44
Rp 1,065,372,000.00

UH PULUH DUA RIBU RUPIAH

gal, …………………………… 2015

Perencana
. SINAR KONSULTAN JAYA

Drs. KOMAR SOFIHUDIN


Direktur
Galian tanah untuk gerbang
4.144
Pondasi batu belah
0.35 2.59
Batu Kosong
1.184
Kolom pembesian
65.1552
ring kolom
38.9312
104.0864
lengkung 1 pembesian
12.34
ring kolom lengkung 1
11.06
23.4
lengkung 2 pembesian
19.744
ring kolom lengkung 2
17.696 37.44
BACK UP PERHITUNGAN VOLUME
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016

NO GAMBAR DETAIL

URAIAN PEKERJAAN PERHITUNGAN

PEKERJAAN PASANGAN
Membuat ring balok (10X15) (16+9+16+9+9) = 59 m'
Pas. Bata 1/2 Bata 1 : 4 (1,3*59) = 76,7 m2
Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) 0,2*0,3*(59-(0,3*16)) = 3,25 m3
Pembesian 1 kg dengan besi polos atau besi ulir ((0,617*6*59)+(59*5*1,1*0,395)) = 346,59 kg
Begisting 1*(59-(0,3*16))/3 = 18,07 m2

Kolom (lanjutan)
Membuat beton mutu f’c = 16,9 MPa (K 200) 0,25*0,3*2,3*16 = 2,76m3
Pembesian 1 kg dengan besi polos atau besi ulir (1,578*8*2,3*16)+(1,3*5*0,395*(16)) = 505,64kg
Begisting Kolom (0.9*4.5*5) = 20,25m2

III PEKERJAAN BAJA


Pasang kuda-kuda IWF 5*2*6*21,32 = 1,279.20kg
Erection kuda-kuda baja 5*2*6*21,32 = 1,279.20kg
Pasang baut kuda-kuda 12*6 = 72.00bh
Pasang baut angkur 12*6 = 72.00bh
Pasang plat simpul 0,4*12*21,32/2 = 51.17kg
Pasang gording canal C 8*17*4,516 = 614.18kg
Pasang Jarum antar gording dia 12 mm 10*5*0,888 = 44.40kg
Ikatan Angin dia 16mm 1,578*10*2 = 31.56kg
Plat Landas 3*12 = 36.00kg
Pasang Penutup atap galvalum (5,8*2*20) = 232.00m2
Pekerjaan pengelasan 24*4,167 = 100 kg
Meni Besi(baja) 4,583*12 = 55.00 m2
Pengecatan permukaan baja secara manual sistem 3 lapis 4,583*12 = 55.00 m2
RINCIAN MATERIAL DAN UPAH TENAGA
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016

Harga Jumlah Jumlah


No Uraian Volume Satuan Material Harga Semua
(Rp) (Rp) (Rp)

A MATERIAL
1 Kayu lokal 3.503 m3 1,494,000.00 5,233,482.00
2 Paku 18.500 kg 18,800.00 347,800.00
3 Besi 1,830.000 kg 6,941.67 12,703,256.10
5 Bendrat 16.860 kg 16,000.00 269,760.00
6 Semen 3,300.000 kg 1,280.00 4,224,000.00
7 Pasir 8.000 m3 125,000.00 1,000,000.00
8 Split 6.000 m3 178,000.00 1,068,000.00
9 Olie Bekas 6.000 lt 20,000.00 120,000.00
10 Usuk 0.305 m3 1,170,500.00 357,002.50
11 Plywood 7.000 lbr 125,000.00 875,000.00
12 Dolken 40.500 bt 27,083.33 1,096,874.87
13 Baja IWF 200x100 1,471.080 kg 13,254.55 19,498,503.41
14 Lipped Channel (Kanal C) C 125x50x20 x 2.3 706.307 kg 11,000.00 7,769,377.00
15 Baut Kuda 72.00 bh 7,500.00 540,000.00
16 Baut Angkur 72.00 bh 20,000.00 1,440,000.00
17 Plat simpul 51.17 kg 11,500.00 588,455.00
18 Jarum antar gording 44.40 kg 15,000.00 666,000.00
19 Ikatan angin 31.65 kg 15,000.00 474,750.00
20 Plat landas 36.00 kg 15,000.00 540,000.00
21 Galvalum Gelombang Tebal 0,3 252.00 lbr 58,200.00 14,666,400.00
22 Paku Hak pj 15cm 6.00 kg 22,600.00 135,600.00
23 Kawat las 7.00 kg 30,000.00 210,000.00
24 Solar 5.50 lt 7,725.52 42,490.36
25 Olie 0.50 lt 30,000.00 15,000.00
26 Sewa Alat (welding Machine) 8.00 jam 28,385.31 227,082.48
27 Menie besi 9.00 kg 25,000.00 225,000.00
28 Kuas 3.00 bh 8,900.00 26,700.00
29 Cat baja 20.00 kg 52,000.00 1,040,000.00
30 Pengencer 1.00 lt 19,100.00 19,100.00
Jumlah I (a) 75,419,633.72
PPN + PPH (11,5%) (b) 8,673,257.88

Jumlah (a) + (b) 84,092,891.60


UPAH TENAGA
Hari ke-1 hari
Pekerja 8 org 46 70,000.00 25,760,000.00
Tukang Batu 2 org 46 90,000.00 8,280,000.00
Tukang Besi 3 org 46 90,000.00 12,420,000.00
Kepala Tukang 1 org 46 95,000.00 4,370,000.00
Mandor 1 org 46 95,000.00 4,370,000.00
JUMLAH II (c) 55,200,000.00
JUMLAH (a+b+c) 139,292,891.60
PEMBULATAN 139,292,800.00

TERBILANG : SERATUS TIGA PULUH SEMBILAN JUTA DUA RATUS SEMBILAN PULUH DUA RIBU DELAPAN RATUS RUPIAH

Balapulang, 2016

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan Pelaksana Kegiatan
H. GHAZIM BZ, SH Drs. Edy Pranoto MUCHAMMAD MUGIONO
RINCIAN MATERIAL DAN UPAH TENAGA
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALA
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016

Harga
No Uraian Volume Satuan Material
(Rp)

A MATERIAL
1 Kayu lokal 1.70 m3 1,494,000.00
2 Paku 18.50 kg 18,800.00
3 Besi 1,530.00 kg 6,941.67
5 Bendrat 16.86 kg 16,000.00
6 Semen 3,300.00 kg 1,280.00
7 Pasir 8.00 m3 125,000.00
8 Split 6.00 m3 178,000.00
10 Usuk 0.31 m3 1,170,500.00
11 Papan Kayu pinus 0.50 m3 2,200,000.00
12 bata 10,000.00 bt 1,000.00
13 Baja IWF 200x100 1,228.25 kg 13,254.55
14 Lipped Channel (Kanal C) C 125x50x20 x 2.3 614.18 kg 11,000.00
15 Baut Kuda 72.00 bh 7,500.00
16 Baut Angkur 72.00 bh 20,000.00
17 Plat simpul 51.17 kg 11,500.00
18 Jarum antar gording 44.40 kg 15,000.00
19 Ikatan angin 31.65 kg 15,000.00
20 Plat landas 36.00 kg 15,000.00
21 Galvalum Gelombang Tebal 0,3 252.00 lbr 58,200.00
22 Paku Hak pj 15cm 6.00 kg 22,600.00
23 Kawat las 7.00 kg 30,000.00
24 Solar 5.50 lt 7,725.52
25 Olie 0.50 lt 30,000.00
26 Sewa Alat (welding Machine) 8.00 jam 28,385.31
27 Menie besi 9.00 kg 25,000.00
28 Kuas 3.00 bh 8,900.00
29 Cat baja 20.00 kg 52,000.00
30 Pengencer 1.00 lt 19,100.00
Jumlah I (a)
PPN + PPH (11,5%) (b
Jumlah (a) + (b)
UPAH TENAGA
Hari ke-1 hari
Pekerja 8 org 46 70,000.00
Tukang Batu 2 org 46 90,000.00
Tukang Besi 3 org 46 90,000.00
Kepala Tukang 1 org 46 95,000.00
Mandor 1 org 46 95,000.00
JUMLAH II (c)
JUMLAH (a+b+c)
PEMBULATAN

TERBILANG : SERATUS TIGA PULUH SEMBILAN JUTA DUA RATUS SEMBILAN PULUH DUA RIBU DELAPAN

Balapulang

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan

H. GHAZIM BZ, SH Drs. Edy Pranoto


TENAGA

TASI GEDUNG BALAI DESA TAHAP II

Jumlah Jumlah
Harga Semua
(Rp) (Rp)

2,539,800.00
347,800.00
10,620,755.10
269,760.00
4,224,000.00
1,000,000.00
1,068,000.00
357,002.50
1,100,000.00
10,000,000.00
16,279,901.04
6,755,980.00
540,000.00
1,440,000.00
588,455.00
666,000.00
474,750.00
540,000.00
14,666,400.00
135,600.00
210,000.00
42,490.36
15,000.00
227,082.48
225,000.00
26,700.00
1,040,000.00
19,100.00
Jumlah I (a) 75,419,576.48
PPN + PPH (11,5%) (b) 8,673,251.29
Jumlah (a) + (b) 84,092,827.77

25,760,000.00
8,280,000.00
12,420,000.00
4,370,000.00 31,084,615.50
4,370,000.00
JUMLAH II (c) 55,200,000.00 #VALUE!
JUMLAH (a+b+c) 139,292,827.77
PEMBULATAN 139,292,800.00

LUH DUA RIBU DELAPAN RATUS RUPIAH

Balapulang, 2016

Pelaksana Kegiatan

MUCHAMMAD MUGIONO
RINCIAN MATERIAL DAN UPAH TENAGA (MC 100%)
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016

Harga Jumlah Jumlah


No Uraian Volume Satuan Material Harga Semua
(Rp) (Rp) (Rp)

A MATERIAL
1 Kayu lokal 1.70 m3 1,494,000.00 2,539,800.00
2 Paku 18.50 kg 18,800.00 347,800.00
3 Besi 1,530.00 kg 6,941.67 10,620,755.10
5 Bendrat 16.86 kg 16,000.00 269,760.00
6 Semen 3,300.00 kg 1,280.00 4,224,000.00
7 Pasir 8.00 m3 125,000.00 1,000,000.00
8 Split 6.00 m3 178,000.00 1,068,000.00
10 Usuk 0.31 m3 1,170,500.00 357,002.50
11 Papan Kayu pinus 0.50 m3 2,200,000.00 1,100,000.00
12 bata 9,740.00 bt 1,000.00 9,740,000.00
13 Baja IWF 200x100 1,228.25 kg 13,254.55 16,279,901.04
14 Lipped Channel (Kanal C) C 125x50x20 x 2.3 614.18 kg 11,000.00 6,755,980.00
15 Baut Kuda 72.00 bh 7,500.00 540,000.00
16 Baut Angkur 72.00 bh 20,000.00 1,440,000.00
17 Plat simpul 51.17 kg 11,500.00 588,455.00
18 Jarum antar gording 44.40 kg 15,000.00 666,000.00
19 Ikatan angin 31.65 kg 15,000.00 474,750.00
20 Plat landas 36.00 kg 15,000.00 540,000.00
21 Galvalum Gelombang Tebal 0,3 laminasi 252.00 lbr 65,000.00 16,380,000.00
22 Paku Hak pj 15cm 6.00 kg 22,600.00 135,600.00
23 Kawat las 7.00 kg 30,000.00 210,000.00
24 Solar 5.50 lt 7,725.52 42,490.36
25 Olie 0.50 lt 30,000.00 15,000.00
26 Sewa Alat (welding Machine) 8.00 jam 28,385.31 227,082.48
27 Menie besi 9.00 kg 25,000.00 225,000.00
28 Kuas 3.00 bh 8,900.00 26,700.00
29 Cat baja 20.00 kg 52,000.00 1,040,000.00
30 Pengencer 1.00 lt 19,100.00 19,100.00
31 bubungan galvalum laminasi 20.00 m' 60,000.00 1,200,000.00
32 talang 40.00 m' 175,000.00 7,000,000.00
Jumlah I (a) 85,073,176.48
PPN + PPH (11,5%) (b) 9,783,415.29

Jumlah (a) + (b) 94,856,591.77


UPAH TENAGA
Hari ke-1 hari
Pekerja 8 org 45 70,000.00 25,200,000.00
Tukang Batu 2 org 45 90,000.00 8,100,000.00
Tukang Besi 3 org 45 90,000.00 12,150,000.00
Kepala Tukang 1 org 45 95,000.00 4,275,000.00
Mandor 1 org 45 95,000.00 4,275,000.00
lainnya 60,096.00
JUMLAH II (c) 54,060,096.00
JUMLAH (a+b+c) 148,916,687.77
PEMBULATAN 148,916,000.00

TERBILANG : SERATUS EMPAT PULUH TUJUH JUTA LIMA RATUS LIMA PULUH TIGA RIBU RUPIAH

Balapulang, 2016

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan Pelaksana Kegiatan

H. GHAZIM BZ, SH Drs. Edy Pranoto MUCHAMMAD MUGIONO


LAPORAN PRESTASI PEKERJAAN
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016
MINGGU KE - : I
TANGGAL : 23 Juli - 29 Juli 2016

HARGA JUMLAH Nilai Bobot Progress Fisik Total Progress


NO URAIAN PEKERJAAN VOLUME SAT
SATUAN. Rp HARGA . Rp (%) (%) (%)
1 2 3 4 5 6 7 8 9
I PEKERJAAN PASANGAN
1 Membuat ring balok beton bertulang (10 x 15) cm 59.00 m' #REF! #REF! #REF!
2 Pas. Bata 1/2 Bata 1 : 4 76.70 m2 #REF! #REF! #REF!
3 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) 3.25 m3 #REF! #REF! #REF! 25.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 346.5955 kg #REF! #REF! #REF! 75.00 #REF!
Begisting 18.07 m2 #REF! #REF! #REF! 50.00 #REF!
4 Kolom (lanjutan)
Membuat beton mutu f’c = 16,9 MPa (K 200) 2.76 m3 #REF! #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 505.64 kg #REF! #REF! #REF!
Begisting Kolom 20.25 m2 124,727.08 2,525,723.37 #REF!
II PEKERJAAN BONGKARAN
1 Pekerjaan Bongkaran , keramik lantai, Atap, & kolom lama 1.00 ls 990,400.00 990,400.00 #REF! 25.00 #REF!
III PEKERJAAN BAJA
1 Pasang kuda-kuda IWF 1,279.20 kg 27,354.55 34,991,934.55 #REF!
2 Erection kuda-kuda baja 1,279.20 kg 500.04 639,648.22 #REF!
3 Pasang baut kuda-kuda 72.00 bh 7,500.00 540,000.00 #REF!
4 Pasang baut angkur 72.00 bh 20,000.00 1,440,000.00 #REF!
5 Pasang plat simpul 51.17 kg 11,500.00 588,432.00 #REF!
6 Pasang gording canal C 614.18 kg 24,605.00 15,111,800.48 #REF!
7 Pasang Jarum antar gording dia 12 mm 44.40 kg 15,000.00 666,000.00 #REF!
8 Ikatan Angin dia 16mm 31.56 kg 15,000.00 473,400.00 #REF!
9 Plat Landas 36.00 kg 15,000.00 540,000.00 #REF!
10 Pasang Penutup atap galvalum 232.00 m2 147,732.00 34,273,824.00 #REF!
12 Pekerjaan pengelasan 100 kg 2,532.32 253,231.59 #REF!
13 Meni Besi(baja) 55.00 m2 24,126.50 1,326,957.50 #REF!
14 Pengecatan permukaan baja secara manual sistem 3 lapis 55.00 m2 115,500.00 6,352,500.00 #REF!
TOTAL Jumlah I + II + III (a) Rp. #REF! #REF!

Balapulang, 2016

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan Pelaksana Kegiatan

H. GHAZIM BZ, SH Drs. Edy Pranoto MUCHAMMAD MUGIONO


LAPORAN PRESTASI PEKERJAAN
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016
MINGGU KE - : II
TANGGAL : 30 Juli - 5 Agustus 2016

HARGA JUMLAH Nilai Bobot Progress Fisik Total Progress


NO URAIAN PEKERJAAN VOLUME SAT
SATUAN. Rp HARGA . Rp (%) (%) (%)
1 2 3 4 5 6 7 8 9
I PEKERJAAN PASANGAN
1 Membuat ring balok beton bertulang (10 x 15) cm 59.00 m' #REF! #REF! #REF!
2 Pas. Bata 1/2 Bata 1 : 4 76.70 m2 #REF! #REF! #REF!
3 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) 3.25 m3 #REF! #REF! #REF! 100.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 346.5955 kg #REF! #REF! #REF! 100.00 #REF!
Begisting 18.07 m2 #REF! #REF! #REF! 100.00 #REF!
4 Kolom (lanjutan)
Membuat beton mutu f’c = 16,9 MPa (K 200) 2.76 m3 #REF! #REF! #REF! 50.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 505.64 kg #REF! #REF! #REF! 50.00 #REF!
Begisting Kolom 20.25 m2 124,727.08 2,525,723.37 #REF! 50.00 #REF!
II PEKERJAAN BONGKARAN
1 Pekerjaan Bongkaran , keramik lantai, Atap, & kolom lama 1.00 ls 990,400.00 990,400.00 #REF! 25.00 #REF!
III PEKERJAAN BAJA
1 Pasang kuda-kuda IWF 1,279.20 kg 27,354.55 34,991,934.55 #REF!
2 Erection kuda-kuda baja 1,279.20 kg 500.04 639,648.22 #REF!
3 Pasang baut kuda-kuda 72.00 bh 7,500.00 540,000.00 #REF!
4 Pasang baut angkur 72.00 bh 20,000.00 1,440,000.00 #REF!
5 Pasang plat simpul 51.17 kg 11,500.00 588,432.00 #REF!
6 Pasang gording canal C 614.18 kg 24,605.00 15,111,800.48 #REF!
7 Pasang Jarum antar gording dia 12 mm 44.40 kg 15,000.00 666,000.00 #REF!
8 Ikatan Angin dia 16mm 31.56 kg 15,000.00 473,400.00 #REF!
9 Plat Landas 36.00 kg 15,000.00 540,000.00 #REF!
10 Pasang Penutup atap galvalum 232.00 m2 147,732.00 34,273,824.00 #REF!
12 Pekerjaan pengelasan 100 kg 2,532.32 253,231.59 #REF!
13 Meni Besi(baja) 55.00 m2 24,126.50 1,326,957.50 #REF!
14 Pengecatan permukaan baja secara manual sistem 3 lapis 55.00 m2 115,500.00 6,352,500.00 #REF!
TOTAL Jumlah I + II + III (a) Rp. #REF! #REF!

Balapulang, 2016

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan Pelaksana Kegiatan

H. GHAZIM BZ, SH Drs. Edy Pranoto MUCHAMMAD MUGIONO


LAPORAN PRESTASI PEKERJAAN
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016
MINGGU KE - : III
TANGGAL : 6 - 12 Agustus 2016

HARGA JUMLAH Nilai Bobot Progress Fisik Total Progress


NO URAIAN PEKERJAAN VOLUME SAT
SATUAN. Rp HARGA . Rp (%) (%) (%)
1 2 3 4 5 6 7 8 9
I PEKERJAAN PASANGAN
1 Membuat ring balok beton bertulang (10 x 15) cm 59.00 m' #REF! #REF! #REF!
2 Pas. Bata 1/2 Bata 1 : 4 76.70 m2 #REF! #REF! #REF! 20.00 #REF!
3 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) 3.25 m3 #REF! #REF! #REF! 100.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 346.5955 kg #REF! #REF! #REF! 100.00 #REF!
Begisting 18.07 m2 #REF! #REF! #REF! 100.00 #REF!
4 Kolom (lanjutan)
Membuat beton mutu f’c = 16,9 MPa (K 200) 2.76 m3 #REF! #REF! #REF! 100.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 505.64 kg #REF! #REF! #REF! 100.00 #REF!
Begisting Kolom 20.25 m2 124,727.08 2,525,723.37 #REF! 100.00 #REF!
II PEKERJAAN BONGKARAN
1 Pekerjaan Bongkaran , keramik lantai, Atap, & kolom lama 1.00 ls 990,400.00 990,400.00 #REF! 100.00 #REF!
III PEKERJAAN BAJA
1 Pasang kuda-kuda IWF 1,279.20 kg 27,354.55 34,991,934.55 #REF!
2 Erection kuda-kuda baja 1,279.20 kg 500.04 639,648.22 #REF!
3 Pasang baut kuda-kuda 72.00 bh 7,500.00 540,000.00 #REF!
4 Pasang baut angkur 72.00 bh 20,000.00 1,440,000.00 #REF!
5 Pasang plat simpul 51.17 kg 11,500.00 588,432.00 #REF!
6 Pasang gording canal C 614.18 kg 24,605.00 15,111,800.48 #REF!
7 Pasang Jarum antar gording dia 12 mm 44.40 kg 15,000.00 666,000.00 #REF!
8 Ikatan Angin dia 16mm 31.56 kg 15,000.00 473,400.00 #REF!
9 Plat Landas 36.00 kg 15,000.00 540,000.00 #REF!
10 Pasang Penutup atap galvalum 232.00 m2 147,732.00 34,273,824.00 #REF!
12 Pekerjaan pengelasan 100 kg 2,532.32 253,231.59 #REF!
13 Meni Besi(baja) 55.00 m2 24,126.50 1,326,957.50 #REF!
14 Pengecatan permukaan baja secara manual sistem 3 lapis 55.00 m2 115,500.00 6,352,500.00 #REF!
TOTAL Jumlah I + II + III (a) Rp. #REF! #REF!

Balapulang, 2016

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan Pelaksana Kegiatan

H. GHAZIM BZ, SH Drs. Edy Pranoto MUCHAMMAD MUGIONO


LAPORAN PRESTASI PEKERJAAN
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016
MINGGU KE - : IV
TANGGAL : 13 - 19 Agustus 2016

HARGA JUMLAH Nilai Bobot Progress Fisik Total Progress


NO URAIAN PEKERJAAN VOLUME SAT
SATUAN. Rp HARGA . Rp (%) (%) (%)
1 2 3 4 5 6 7 8 9
I PEKERJAAN PASANGAN
1 Membuat ring balok beton bertulang (10 x 15) cm 59.00 m' #REF! #REF! #REF!
2 Pas. Bata 1/2 Bata 1 : 4 76.70 m2 #REF! #REF! #REF! 90.00 #REF!
3 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) 3.25 m3 #REF! #REF! #REF! 100.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 346.5955 kg #REF! #REF! #REF! 100.00 #REF!
Begisting 18.07 m2 #REF! #REF! #REF! 100.00 #REF!
4 Kolom (lanjutan)
Membuat beton mutu f’c = 16,9 MPa (K 200) 2.76 m3 #REF! #REF! #REF! 100.00 #REF!
Pembesian 1 kg dengan besi polos atau besi ulir 505.64 kg #REF! #REF! #REF! 100.00 #REF!
Begisting Kolom 20.25 m2 124,727.08 2,525,723.37 #REF! 100.00 #REF!
II PEKERJAAN BONGKARAN
1 Pekerjaan Bongkaran , keramik lantai, Atap, & kolom lama 1.00 ls 990,400.00 990,400.00 #REF! 100.00 #REF!
III PEKERJAAN BAJA
1 Pasang kuda-kuda IWF 1,279.20 kg 27,354.55 34,991,934.55 #REF!
2 Erection kuda-kuda baja 1,279.20 kg 500.04 639,648.22 #REF!
3 Pasang baut kuda-kuda 72.00 bh 7,500.00 540,000.00 #REF!
4 Pasang baut angkur 72.00 bh 20,000.00 1,440,000.00 #REF!
5 Pasang plat simpul 51.17 kg 11,500.00 588,432.00 #REF!
6 Pasang gording canal C 614.18 kg 24,605.00 15,111,800.48 #REF!
7 Pasang Jarum antar gording dia 12 mm 44.40 kg 15,000.00 666,000.00 #REF!
8 Ikatan Angin dia 16mm 31.56 kg 15,000.00 473,400.00 #REF!
9 Plat Landas 36.00 kg 15,000.00 540,000.00 #REF!
10 Pasang Penutup atap galvalum 232.00 m2 147,732.00 34,273,824.00 #REF!
12 Pekerjaan pengelasan 100 kg 2,532.32 253,231.59 #REF!
13 Meni Besi(baja) 55.00 m2 24,126.50 1,326,957.50 #REF!
14 Pengecatan permukaan baja secara manual sistem 3 lapis 55.00 m2 115,500.00 6,352,500.00 #REF!
TOTAL Jumlah I + II + III (a) Rp. #REF! #REF!

Balapulang, 2016

Mengetahui : Mengetahui :
Ketua BPD Desa Balapulang Wetan Pj. Kepala Desa Balapulang Wetan Pelaksana Kegiatan

H. GHAZIM BZ, SH Drs. Edy Pranoto MUCHAMMAD MUGIONO


MUTUAL CHECK 100% (MC 100%)
KEGIATAN : SILPA TA 2015
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA TAHAP II
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2016

PERENCANAAN MC 100 % PEKERJAAN TAMBAH PEKERJAAN KURANG


NO URAIAN PEKERJAAN ANALISA HARGA HARGA HARGA HARGA
KUANTITAS JUMLAH (Rp) KUANTITAS JUMLAH (Rp) KUANTITAS JUMLAH (Rp) KUANTITAS
SATUAN. Rp SATUAN. Rp SATUAN. Rp SATUAN. Rp
1 2 3 4 5 6 7 4 5 6 7 4 5 6 7 4 5 6
I PEKERJAAN PASANGAN
1 Membuat ring balok beton bertulang (10 x 15) cm A.4.1.1.36 59.00 m' #REF! #REF! 48.60 m' #REF! #REF! 10.40 M2 #REF!
2 Pas. Bata 1/2 Bata 1 : 4 A.4.4.1.9 76.70 m2 #REF! #REF! 74.70 m2 #REF! #REF! 2.00 m2 #REF!
3 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.3 3.25 m3 #REF! #REF! 3.25 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.10 346.5955 kg #REF! #REF! 346.5955 kg #REF! #REF!
Begisting A.4.1.1.17 18.07 m2 #REF! #REF! 18.07 m2 #REF! #REF!
4 Kolom (lanjutan)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 m3
2.76 #REF! #REF! 2.76 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 505.64kg #REF! #REF! 505.64 kg #REF! #REF!
Begisting Kolom A.4.1.1.22 20.25 m2 124,727.08 2,525,723.37 20.25 m2 124,727.08 2,525,723.37
II PEKERJAAN BONGKARAN
1 Pekerjaan Bongkaran Atap lama dan kolom lama taksir 1.00 ls 990,400.00 990,400.00 1.00 ls 990,400.00 990,400.00

III PEKERJAAN BAJA


1 Pasang kuda-kuda IWF A.4.2.1.2. 1,279.20 kg 27,354.55 34,991,934.55 1,279.20 kg 27,354.55 34,991,934.55
2 Erection kuda-kuda baja A.4.2.1.3. 1,279.20 kg 500.04 639,648.22 1,279.20 kg 500.04 639,648.22
3 Pasang baut kuda-kuda taksir 72.00 bh 7,500.00 540,000.00 72.00 bh 7,500.00 540,000.00
4 Pasang baut angkur taksir 72.00 bh 20,000.00 1,440,000.00 72.00 bh 20,000.00 1,440,000.00
5 Pasang plat simpul taksir 51.17 kg 11,500.00 588,432.00 51.17 kg 11,500.00 588,432.00
6 Pasang gording canal C A.4.2.1.1b. 614.18 kg 24,605.00 15,111,800.48 614.18 kg 24,605.00 15,111,800.48
7 Pasang Jarum antar gording dia 12 mm taksir 44.40 kg 15,000.00 666,000.00 44.40 kg 15,000.00 666,000.00
8 Ikatan Angin dia 16mm taksir 31.56 kg 15,000.00 473,400.00 31.56 kg 15,000.00 473,400.00
9 Plat Landas taksir 36.00 kg 15,000.00 540,000.00 36.00 kg 15,000.00 540,000.00
10 Pasang Penutup atap galvalum A.4.5.2.40a 232.00 m2 147,732.00 34,273,824.00 243.60 m2 147,732.00 35,987,515.20 232.00 m2 147,732.00
11 Pekerjaan pengelasan A.4.2.1.5a. 100 kg 2,532.32 253,231.59 100 kg 2,532.32 253,231.59
12 Meni Besi(baja) A.4.7.1.16. 55.00 m2 24,126.50 1,326,957.50 55.00 m2 24,126.50 1,326,957.50
13 Pengecatan permukaan baja secara manual sistem 3 lapis A.4.7.1.20 55.00 m2 115,500.00 6,352,500.00 55.00 m2 115,500.00 6,352,500.00
14 Pasang Penutup atap galvalum laminasi 232.00 m2 160,122.00 37,148,304.00 232.00 m2 160,122.00 37,148,304.00
15 Pasang Bubungan atap galvalum laminasi 20.00 m' 60,000.00 1,200,000.00 20.00 m' 60,000.00 1,200,000.00
16 Pekerjaan talang 40.00 m' 175,000.00 7,000,000.00 40.00 m' 175,000.00 7,000,000.00
Jumlah (a) #REF! #REF! 45,348,304.00
PPN + PPH 11,5% (b) 8,673,251.29 9,783,415.29
(dari material kena pajak)
Jumlah Semua #REF! #REF!
Pembulatan #REF! #REF!

Catatan : Kekurangan pembiayaan adalah hutang terhadap pemasangan atap sisa terhutang #REF!
98,911,419.54 Balapulang,
PEKERJAAN KURANG

JUMLAH (Rp)
7

#REF!
#REF!

34,273,824.00

#REF!

Balapulang, 2016
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN :
PEKERJAAN : REHABILITASI BALAI DESA BALAPULANG WETAN TA
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2015

NO URAIAN PEKERJAAN ANALISA VOLUME SAT


1 2 3 4 5
I PEKERJAAN TANAH
1 Pek. Galian tanah A.2.3.1.1 31.45 M3
2 Pek. Urugan kembali bekas galian A.2.3.1.9 7.86 M3
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 1.60 M3

II PEKERJAAN BETON
1 Pemasangan pondasi batu belah campuran 1SP : 4PP A.3.2.1.2 9.75 m3
2 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.61 m3
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 434.71 kg
Pemasangan bekisting untuk sloof A.4.1.1.21 20.07 m2
3 Pondasi Plat Menerus (tidak Termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 4.14 m3
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 699.19 kg
Pemasangan bekisting untuk pondasi A.4.1.1.20 19.68 m2
4 Kolom (tidak termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 6.48 m3
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,197.15 kg
Pemasangan bekisting untuk kolom A.4.1.1.22 20.25 m2

Jumlah Total
PPN + PPH 11.5%
Jumlah

SARANA DAN PRASARANA (SARPAS)


SMA NEGERI 5 KOTA TEGAL
SUWITNO, S.Pd
NIP. 19671208 200012 1 002

Mengetahui,

KEPALA SMA NEGERI 5


KOTA TEGAL

MASDUKI, S.Pd., M.Pd.


NIP. 19661007 199003 1 009
BIAYA ( RAB )

AI DESA BALAPULANG WETAN TAHAP I

HARGA JUMLAH JUMLAH


SATUAN. Rp HARGA . Rp SEMUA . Rp
6 7 8

#REF! #REF!
#REF! #REF!
#REF! #REF!
Jumlah #REF!

#REF! #REF!

#REF! #REF!
#REF! #REF!
#REF! #REF!

#REF! #REF!
#REF! #REF! Err:520
#REF! #REF!

#REF! #REF!
#REF! #REF! 9.775
#REF! #REF!
Jumlah #REF!
Err:520

Jumlah Total Rp. #REF! 480,000,000.00


PPN + PPH 11.5% Rp. #REF! #REF!
#REF!

Tegal, …………………………… 2015

Perencana
CV. SINAR KONSULTAN JAYA
Drs. KOMAR SOFIHUDIN
Direktur
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN :
PEKERJAAN : PEMBANGUNAN/REHABILITASI GEDUNG BALAI DESA
LOKASI : DESA HARJOSARI LOR
TAHUN ANGGARAN :

HARGA JUMLAH JUMLAH


NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN. Rp HARGA . Rp SEMUA . Rp
1 2 3 4 5 6 7 8
I PEKERJAAN TANAH
1 Pek. Galian tanah A.2.3.1.1 75.00 M3 #REF! #REF!
2 Pek. Urugan kembali bekas galian A.2.3.1.9 18.75 M3 #REF! #REF!
3 Pek. Urugan pasir bawah pondasi A.2.3.1.11 1.60 M3 #REF! #REF!
Jumlah I #REF!
II PEKERJAAN PASANGAN
1 Pemasangan pondasi batu belah campuran 1SP : 4PP A.3.2.1.2 29.25 m3 #REF! #REF!
2 Pondasi Plat Menerus (tidak Termasuk teras)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 4.14 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 699.19 kg #REF! #REF!
Pemasangan bekisting untuk pondasi A.4.1.1.20 19.68 m2 #REF! #REF!
3 Sloof 15/20 A 026 l 80.00 m' #REF! #REF!
4 Pasang Sloof 20/30
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 6.86 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 782.00 kg #REF! #REF!
Pemasangan bekisting untuk sloof A.4.1.1.21 40.00 m2 #REF! #REF!
5 Kolom (30x30)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.24 m3 #REF! #REF!
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,107.00 kg #REF! #REF!
Pemasangan bekisting untuk kolom A.4.1.1.22 54.00 m2 124,727.08 6,735,262.32
6 Kolom praktis A.4.1.1.35 70.00 m' #REF! #REF!
7 Membuat ring balok beton bertulang (10 x 15) cm A.4.1.1.36 240.00 m' #REF! #REF!
8 Pas. Bata 1/2 Bata 1 : 4 A.4.4.1.9 880.00 m2 #REF! #REF!
Jumlah II #REF!
III PEKERJAAN BONGKARAN
1 Pekerjaan Gedung balai desa lama taksir 1.00 ls 2,000,000.00 2,000,000.00
Jumlah III 2,000,000.00
IV PEKERJAAN BAJA
1 Pasang kuda-kuda IWF A.4.2.1.2. 1,279.20 kg 27,354.55 34,991,934.55
2 Erection kuda-kuda baja A.4.2.1.3. 1,279.20 kg 500.04 639,648.22
3 Pasang baut kuda-kuda taksir 72.00 bh 7,500.00 540,000.00
4 Pasang baut angkur taksir 72.00 bh 20,000.00 1,440,000.00
5 Pasang plat simpul taksir 51.17 kg 11,500.00 588,432.00
6 Pasang gording canal C A.4.2.1.1b. 614.18 kg 24,605.00 15,111,800.48
7 Pasang Jarum antar gording dia 12 mm taksir 44.40 kg 15,000.00 666,000.00
8 Ikatan Angin dia 16mm taksir 31.56 kg 15,000.00 473,400.00
9 Plat Landas taksir 36.00 kg 15,000.00 540,000.00
10 Pasang Penutup atap galvalum A.4.5.2.40a 352.00 m2 147,732.00 52,001,664.00
12 Pekerjaan pengelasan A.4.2.1.5a. 100 kg 2,532.32 253,231.59
13 Meni Besi(baja) A.4.7.1.16. 55.00 m2 24,126.50 1,326,957.50
14 Pengecatan permukaan baja secara manual sistem 3 lapis A.4.7.1.20 55.00 m2 115,500.00 6,352,500.00

V PEKERJAAN FINISHING
1 Pengecatan dinding A.4.7.1.10 1,760.00 m2 #REF! #REF!
2 Pasang pintu tunggal stainless + kaca taksir 9.00 bh 1,750,000.00 15,750,000.00
3 Pasang pintu ganda stainless + kaca taksir 2.00 bh 3,350,000.00 6,700,000.00
4 Pasang jendela rata2 0,7m x 2,3 m taksir 40.00 bh 750,000.00 30,000,000.00
5 Pasang keramik A.4.4.3.35 306.00 m2 #REF! #REF!
6 Dak Pemanis (ceiling brick) taksir 35.00 m2 400,000.00 14,000,000.00
Jumlah III #REF!
Jumlah I s.d V Rp. #REF!
PPN + PPH 11,5% (b) Rp. #REF!
(dari material kena pajak) #REF!
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : ADD 2017
PEKERJAAN : REHABILITASI BALAI DESA BALAPULANG WETAN TAHAP III
LOKASI : DESA BALAPULANG WETAN
TAHUN ANGGARAN : 2017

HARGA JUMLAH JUMLAH


NO URAIAN PEKERJAAN ANALISA VOLUME SAT
SATUAN. Rp HARGA . Rp SEMUA . Rp
1 2 3 4 5 6 7 8
I PEKERJAAN ATAP
1 Selisih Atap Galvalum Biasa dengan laminasi taksir 1.00 ls 2,874,480.00 2,874,480.00
2 Pek. Bubungan atap galvalum laminasi taksir 20.00 m' 60,000.00 1,200,000.00
3 Pemasangan talang datar seng BJLS 28 A.4.2.1.18 40.00 m' 197,575.00 7,903,000.00
4 Penangkal petir taksir 1.00 ls 3,000,000.00 3,000,000.00
5 Pemasangan Pipa PVC 4" A.5.1.1.32 30.00 m' 109,002.50 3,270,075.00
6 Pemasangan rk.atap berikut atapnya (galvalum laminasi) taksir 32.00 m2 250,000.00 8,000,000.00
Jumlah I 26,247,555.00
II PEKERJAAN PASANGAN
1 Kolom (30x30) Peninggian (1,25m)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.5 0.15625 m3 846,023.57 132,191.18
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 12.83 kg 10,900.50 139,853.42
Pemasangan bekisting untuk kolom A.4.1.1.20 2.50 m2 173,966.00 434,915.00
2 Ring Balok teras
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.5 0.24 m3 846,023.57 203,045.66
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 50.52 kg 10,900.50 550,693.26
Pemasangan begisting utk balok A.4.1.1.23 6.40 m2 291,355.00 1,864,672.00
3 Plesteran Dinding 1:5 tebal 15mm A.4.4.2.5 399.60 m2 43,912.40 17,547,395.04
4 Pekerjaan Keramik Dinding A.4.4.3.54a 40.50 m2 177,598.00 7,192,719.00
5 Pekerjaan keramik lantai teras A.4.4.3.35. 11.15 m2 153,328.00 1,709,607.20
6 Pekerjaan keramik lantai unpolish A.4.4.3.35.e 86.45 m2 171,100.00 14,791,595.00
Jumlah II 44,566,686.76
III PEKERJAAN AKSESORIS
1 Aksesoris GRC untuk kolom taksir 7.00 ls 600,000.00 4,200,000.00
2 Pemasangan Loggo Kab. Tegal taksir 1.00 ls 364,331.49 364,331.49
Jumlah III 4,564,331.49
IV PEKERJAAN BESI
1 Pasang Pintu Hollow taksir 13.20 m2 600,000.00 7,920,000.00
2 Pasang teralis Jendela taksir 12.75 m2 500,000.00 6,375,000.00
Jumlah IV 14,295,000.00
V PEKERJAAN FINISHING
1 Pengecatan dinding A.4.7.1.10 301.50 m2 17,714.50 5,340,921.75
5,340,921.75
Jumlah I s.d V Rp. 95,014,495.00
Pembulatan Rp. 95,014,495.00

Terbilang : Sembilan Puluh Lima Juta Empat Belas Ribu Empat Ratus Sembilan Puluh Lima Rupiah

Balapulang, 2017
DIBUAT OLEH
MENGETAHUI : DISETUJUI/MENGESAHKAN TPK DESA BALAPULANG WETAN
KETUA BPD BALAPULANG WETAN Pj. KEPALA DESA BALAPULANG WETAN

................................... .................................. .....................................


Daftar Harga Satuan Dasar Tenaga Kerja, Bahan dan Peralatan
Feb-18

No. Uraian Satuan Kode Harga Satuan Dasar (Rp)


I. UPAH
1 Pekerja Hari 63,100.00 L.01
2 Tukang Gali Hari 63,100.00 L.02
3 Mandor Hari 74,100.00 L.03
4 Tukang cat/ plitur / batu Hari 79,500.00 L.04
5 Kepala tukang cat/ plitur / batu Hari 79,500.00 L.05
6 Tukang kayu Hari 85,100.00 L.06
7 Kepala tukang kayu Hari 85,100.00 L.07
8 Tukang Besi Hari 79,500.00 L.08
9 Kepala Tukang besi Hari 79,500.00 L.09
10 Tukang Besi Profil Hari 74,100.00 L.10
11 Kepala Tukang besi Profil Hari 79,500.00 L.11
12 Mekanik Hari 93,300.00 L.12
13 Mekanik Pembantu Hari 65,900.00 L.13
14 Operator terlatih/ masinis Hari 109,800.00 L.14
15 Operator kurang terlatih Hari 82,300.00 L.15
16 Pembantu operator/ pemb. masinis Hari 71,300.00 L.16
17 Sopir truk Hari 112,500.00
18 Sopir personil Hari 90,500.00
19 Pembantu sopir Hari 63,100.00
20 Buruh lapangan tak terlatih Hari 57,600.00
21 Buruh lapangan kurang terlatih Hari 60,300.00
22 Buruh lapangan terlatih Hari 63,100.00
23 Tukang masak aspal Hari 67,200.00
24 Penjaga malam Hari 57,600.00
0.00
II BAHAN 0.00
1 Abu batu M 3
297,300.00
2 Air liter 0.00
3 Amplas Lbr 3,800.00
4 Asbes Gelombang 300 x 102 x 0.5 cm (besar) LBR 116,700.00
5 Asbes Gelombang 180 x 105 x 0.5 cm (kecil) LBR 57,100.00 M.08
6 Aspal curah Kg 8,700.00 M.09.a
7 Aspal drum Kg 5,700.00 M.09.b
8 Bahan bakar Lt 0.00
9 Atap sirap 4 lapis Bh 0.00 M.09.c
10 Bak Cuci Stainless Steel "Royal" (0,4 x 1) m Bh 300,300.00 M.09.d
11 Bak Cuci Stainless Steel "Viega" ( 1,00 x 0,90 ) m2 Bh 466,700.00 M.09.e
12 Bak Cuci Stainless Steel 80 Cm Bh 174,600.00 M.09.f
13 Bak Mandi Fibreglass, Vol 120 ltr Sudut Bh 300,200.00 M.09.g
14 Bak Mandi Fibreglass, Vol 120 ltr Kotak Bh 288,200.00 M.09.h
15 Bak Mandi Fibreglass, Vol 150 ltr Bh 338,600.00 M.09.i
16 Batu apung ( gosok ) Kg 17,500.00 M.09.j
17 Batu Bata Bh 1,000.00 M.09.k
18 Batu Belah ( 3 Muka ) M3 258,600.00 M.09.l
19 Batu Belah (Batu Kenting) M3 329,500.00 M.09.m
20 Batu Belah 40% M3 260,600.00 M.10.a
21 Batu Blonos M 3
216,700.00 M.10.b
22 Batu pecah dg mesin (1-2cm) M3 283,500.00 M.10.c
23 Batu pecah dg mesin (0,5-<1 cm) / Screening M 3
276,300.00 M.10.d
24 Batu pecah dg mesin (2-3 cm) M3 298,800.00 M.10.e
25 Batu pecah dg mesin (3-5 cm) M3 303,600.00 M.10.f
26 Batu Split 1-2 (pecah tangan) M 3
308,500.00 M.10.g
27 Batu Split 2-3 (pecah tangan) M3 308,500.00
28 Batu Split 3 - 4 (pecah tangan), gambiran M3 295,100.00 M.11
29 Batu Split 3/5 - 5/7 (pecah tangan) M 3
295,100.00 M.12
30 Batu Tempel ( Muka Segi 6 ) tebal 10 cm Bh 3,500.00 M.13
31 Batu Tempel Palimanan Hijau M 2
126,200.00 M.14.a
32 Batu Tempel Palimanan Kuning M2 120,800.00 M.14.b
33 Batu Tempel ( Tidak Beraturan ) Kecil M2 76,800.00 M.14.c
34 Batu Tempel ( Tidak Beraturan ) Besar M 2
82,300.00 M.14.d
35 Batu Teraso Bh 0.00 M.15
36 Batu Candi Tempel 20/20, 5/20 M2 120,800.00
37 Batu Andesit 139,000.00
38 Besi Beton M2 9,700.00 M.16
39 Besi IWF KG 13,800.00 M.17.a
40 Besi Siku / Profil KG 11,500.00 M.17.b
41 Besi Prestressed polos KG 12,900.00 M.17.c
42 Besi Strip ( tebal 5mm, lebar 5 cm ) KG 13,300.00 M.18.a
43 Beton K 175 Ready Mix M3 914,600.00 M.18.b
44 Beton K 225 Ready Mix M3 947,000.00 M.18.c
45 Beton K 300 Ready Mix M 3
1,025,500.00 M.18.d
46 Bondex ( plat beton ) 3 mm 1,2 x 2,4 M2 183,900.00 M.18.e
47 BRC tinggi 60 cm ( Pagar ) 5,2 mm, panjang 2,4 m M' 57,100.00 M.18.f
48 BRC tinggi 90 cm ( Pagar ) 5,2 mm, panjang 2,4 m M' 83,000.00 M.19.a
49 BRC tinggi 120 cm ( Pagar ) 5,2 mm, panjang 2,4 m M' 96,000.00 M.19.b
50 Bubungan Asbes (besar) M' 65,500.00 M.19.c
51 Bubungan Asbes (kecil) M' 30,500.00 M.19.d
52 Bubungan Genteng beton abu-2 (isi 3 / M') Bh 17,100.00 M.19.e
53 Bubungan genteng beton warna (isi 3 bh) Bh 20,000.00
54 Bubungan Genteng keramik "KIA" Bh 35,900.00
55 Bubungan Genteng keramik pertigan "KIA" Bh 151,000.00
56 Bubungan Genteng "Morando" natural Bh 7,200.00
57 Bubungan Genteng "Morando" Glazur Bh 12,400.00 M.30.a
58 Bubungan genteng pres JTW ( isi 4 / M' ) Bh 6,400.00 M.30.b
59 Cat Besi / Kayu "Bee Brand" KG 58,700.00 M.31.a
60 Cat Besi / Kayu "Yunior" KG 54,700.00 M.31.b
61 Cat Besi / Kayu "Glotex" KG 59,500.00 M.31.c
62 Cat Tembok (shintex) KG 29,200.00 M.31.d
63 Cat Tembok ex Metrolite KG 28,600.00 M.32
64 Dempul kayu KG 30,700.00 M.33.a
65 Dolken Kayu Galam Ø 8-10/400 cm (Kalimantan) Batang 89,100.00 M.33.b
66 Dolken Kayu Galam Ø 8-10 / 4 m' Batang 64,500.00
67 Dolken Kayu Lokal Ø 8-10 / 4 m' Batang 48,000.00
68 Engsel Jendela Psg 20,100.00
69 Engsel Jendela Kuningan Psg 31,300.00
70 Engsel Pintu Kuningan Psg 40,900.00
71 Engsel Pintu Biasa Psg 20,100.00
72 Eternit 1 x 1 m2 t = 4 mm "Jabesmen" / Harflex t=2,7 mm Bh 18,900.00
73 Eternit (saflex) 1 x 1 m , t = 5 mm
2
Bh 14,900.00
74 Fiber glass gelombang 180 x 0,8 Lbr 62,800.00
75 Fiber glass plat lebar 1 M M' 41,500.00
76 Flincote Kg 36,900.00
77 Floor Drain / Saringan pembuang pada lantai KM/WC (Stainless) Bh 28,500.00
78 Formika untuk Pintu Lbr 0.00
79 Formtie / penjaga jarak bekisting / spacer Bh 0.00
80 Genteng beton abu-2 (isi 9 bh / m2 ) M2 64,100.00
81 Genteng beton warna (isi 9 bh / m2 ) M2 101,200.00
82 Genteng Keramik Glazur "KIA" (isi 15 bh / m2), warna muda Bh 11,700.00
83 Genteng Keramik Glazur "KIA" (isi 15 bh / m2), warna tua Bh 12,800.00
84 Genteng type "Morando" Glazur ( isi 20/M2 ) 1550x20 M 2
87,700.00
85 Genteng Pres JTW ( isi 25/M2 ) 750x25 M2 58,900.00
86 Genteng Tipe "Morando" Natural ( isi 20/M2 ) M2 67,200.00
87 Genteng Kaca 5 mm Buah 12,100.00
88 Grefel beton ø 20 cm BUAH 30,100.00
89 Grefel beton ø 30 cm BUAH 38,400.00
90 Grendel jendela kuningan Psg 14,900.00
91 Grendel jendela biasa Psg 11,100.00
92 Grendel pintu kuningan Bh 19,200.00
93 Grendel pintu biasa Bh 10,700.00
94 Glass block Bh 24,300.00
95 Gypsum uk. 1,2 x 2,4, tebal 9 mm Lbr 61,900.00
96 Hak angin kuningan Psg 25,200.00
97 Hak angin biasa Psg 11,500.00
98 Hard flex uk. 0,5 x 2 M LBR 31,500.00
99 Hard flex 0,35 mm 1,22 x 2,44 m, kalsiboard ( tahan api ) LBR 60,100.00
100 Hotmix jadi + alat besar, tenaga dan bahan bakar ton 0.00
101 Injuk KG 0.00
102 Jendela Nako (+ Tralis ) BUAH 0.00
103 Kaca bening 5 mm M 2
139,000.00
104 Kaca ryban 5 mm M2 155,500.00
105 Kawat Beton (Bendrat) KG 19,800.00
106 Kawat Bronjong ø 4 mm ( Galvanis ) KG 22,700.00
107 Kawat duri ( 1rol = 20 m ) M' 7,900.00
108 Kawat Las KG 25,400.00
109 Kawat Las Listrik RD 26 KG 26,900.00
110 Kawat Las Listrik RB 26 KG 31,700.00
111 Kayu bakar M 3
203,500.00
112 Kayu bangkirai uk 6x12x400 , 8x12x400 M3 12,357,200.00
113 Kayu jati ø 22 s/d 28 M3 13,635,200.00
114 Kayu Kempas uk 6 x12x400 , 8x12x400 M3 6,865,100.00
115 Kayu Punak Sumatra M3 5,675,100.00
116 Kayu Punak Kalimantan M 3
6,773,500.00
117 Kayu Meranti Batu M3 5,492,100.00
118 Kayu reng 3/4 Meranti Batu M3 4,723,200.00
119 Kayu reng 2/3 Meranti Batu M 3
4,668,200.00
120 Kayu stoot ( bambu ), 5 m Btg 27,400.00
121 Keramik 20/25, putih M 2
54,300.00
122 Keramik 20/25, warna/polos M2 54,400.00
123 Keramik 20/20, anti slip ( u/lantai Km/wc) M 2
62,100.00
124 Keramik 20/20, putih M2 60,000.00
125 Keramik 20/20, warna M2 57,500.00
126 Keramik 30/30 (putih polos) M 2
45,600.00
127 Keramik 30/30, warna M2 58,400.00
128 Keramik 40/40, (putih polos) M2 52,700.00
129 Keramik 40/40, warna M 2
60,300.00
130 Kerikil sungai/Manggaran uk. 0,5 - 1 cm M3 0.00
131 Kloset duduk / Monoblok "INA", Putih (tanpa pembilas) Bh 491,500.00
132 Kloset duduk / Monoblok "INA", Warna Tua (tanpa pembilas) Bh 528,500.00
133 Kloset duduk / Monoblok + pembilas otomatis "INA", warna tua Bh 1,578,900.00
134 Kloset duduk / Monoblok + pembilas otomatis "INA", warna putih Bh 1,386,600.00
135 Kloset jongkok INA, warna tua Bh 166,700.00
136 Kloset jongkok INA, warna muda Bh 153,300.00
137 Kloset jongkok Traso dicat Bh 0.00
138 Kloset duduk / Monoblok + pembilas otomatis "TOTO", warna tua 2,628,800.00
139 Kloset duduk / Monoblok + pembilas otomatis "TOTO", warna putih 2,299,300.00
140 Kran Ø 1/2" ex Fiba Bh 77,700.00
141 Kuas 3" Bh 12,000.00
142 Kuas 2" Bh 11,000.00
143 Kunci tanam 2 slag "Kuda Besar" Bh 85,900.00
144 Lampu bohlam 25 watt "Philip" Bh 39,000.00
145 Lampu TL 20 watt ( komplit ) Travo Sinar Set 122,100.00
146 Lem kayu Fox (Kuning) KG 75,400.00
147 Lem Kuning ( Aica Aibon ) KG 42,500.00
148 Lem Putih ( Fox ) KG 18,600.00
149 Lempengan Rumput Biasa M2 0.00
150 Lempengan Rumput Jepang / Rumput Golf / Rumput Gajah M 2
0.00
151 List Kayu Profil M' 18,500.00
152 Melamik putih 1,2 x 2,4 Lbr 113,100.00
153 Melamik ( lapisan ) uk. 0,9 x 2,1 LBR 96,600.00
154 Menie Besi (Payung warna hijau) KG 35,100.00
155 Menie Besi ( Nippon ), zinchcromate KG 57,400.00
156 Menie kayu KG 24,400.00
157 Minyak aspal Lt 0.00
158 Minyak Bekisting (olie bekas) Lt 5,400.00
159 Minyak Cat Ltr 23,600.00
160 Minyak pelumas Lt 26,300.00
161 Minyak tanah Lt #VALUE!
162 Multiplek 9 mm uk. 1,2 x 2,4 m Lbr 133,200.00
163 Multiplek 12 mm uk. 1,2 x 2,4 m Lbr 171,900.00
164 Mur + Baut f 1/2 " Kg 24,900.00
165 Oker Putih Kg 0.00
166 Oker Warna Kg 0.00
167 Oli Lt 0.00
168 Paku KG 14,200.00
169 Paku Pancing 10 cm Kg 45,200.00
170 Panel beton pracetak 0.00
171 Papan Meranti Batu ( 2 x 20 x 400 ) M 3
6,499,800.00
172 Papan Meranti Batu ( 2 x 25 x 400 ) M3 7,322,700.00
173 Papan bangkirai ( 2 x 20 x 400 ) M 3
12,906,400.00
174 Papan bangkirai ( 2 x 25 x 400 ) M3 13,592,900.00
175 Papan bangkirai ( 3 x 30 x 400 ) M3 14,554,100.00
176 Papan Cetak (kayu pinus) uk 2 x 20 x 200 M 3
2,567,500.00 20,540
177 Papan kayu jati M3 16,710,800.00
178 Papan Kempas (kruing) uk 3x20x400 M3 7,249,500.00
179 Papan Punak Kalimantan uk 3x20x400 M 3
7,139,700.00
180 Pas. Kanstin 15 x 20 x 30 x 50 M' 82,500.00
181 Pas. Kanstin 10 x 15 x 30 x 50 M' 68,300.00
182 Pas. Kanstin 10 x 20 x 50 M' 43,000.00
183 Pas. Kanstin Taman M' 65,900.00
184 Pasir plesteran/Tabur / ayak M 3
240,900.00
185 Pasir Beton M3 243,100.00 1400 kg/m3
186 Pasir Pasang M3 243,100.00
187 Pasir Halus M 3
194,300.00
188 Pasir Urug M3 151,000.00
189 Paving Block type Hexagonal tebal 6 cm (K175) M 2
85,200.00
190 Paving Block type Holland natural 6 cm (K 175 ) M2 85,200.00
191 Paving Block type Holland natural 8 cm (K 175 ) M2 102,400.00
192 Paving Block warna type Hexagonal tebal 6 cm (K175) M2 101,300.00
193 Paving Block warna type Holland natural 6 cm (K 175 ) M2 99,800.00
194 Paving Block warna type Holland natural 8 cm (K 175) M2 120,900.00
195 P C ( 50 Kg ) ZAK 55,000.00
196 PC Putih ( 40 kg / Zak ) ZAK 70,000.00
197 P C ( 50 Kg ) (Harga DO = 160 zak) ZAK 54,300.00
198 Pipa Besi ø 1" t = 1,8 mm M' 24,900.00
199 Pipa Besi ø 1/2" t = 1,6 mm M' 14,100.00
200 Pipa Besi ø 1/2" t = 2,6 mm 18,200.00
201 Pipa Besi ø 2" t = 1,8 mm M' 47,000.00
202 Pipa Besi ø 3" t = 3,5 mm M' 129,400.00
203 Pipa Besi ø 3/4" t = 1,6 mm M' 19,100.00
204 Pipa Besi ø 3/4" t = 2,6 mm 23,100.00
205 Pipa Besi ø 4" t = 1,8 mm M' 83,800.00
206 Pipa Beton ø 20 cm ( Buis Beton ) M' 58,500.00
207 Pipa Beton ø 30 cm ( Buis Beton ) M' 80,500.00
208 Pipa Beton ø 40 cm ( Buis Beton ) M' 111,600.00
209 Pipa Beton ø 60 cm ( Buis Beton ) M' 215,900.00
210 Pipa Beton ø 80 cm ( Buis Beton ) M' 318,500.00
211 Pipa Galvanis ø 1" t = 1,8 mm M' 34,800.00
212 Pipa Galvanis ø 1/2" t = 1,6 mm M' 23,000.00
213 Pipa Galvanis ø 1/2" t = 2,6 mm 75,500.00
214 Pipa Galvanis ø 2" t = 1,8 mm M' 150,100.00
215 Pipa Galvanis ø 3" t = 3,5 mm M' 114,200.00
216 Pipa Galvanis ø 3/4" t = 1,8 mm M' 25,400.00
217 Pipa Galvanis ø 3/4" t = 2,6 mm 32,900.00
218 Pipa Galvanis ø 4" t = 4,5 mm M' 236,500.00
219 Pipa PVC ø 1" ( AW ) ex Wavin M' 9,600.00
220 Pipa PVC ø 1/2" ( AW ) ex Wavin M' 5,200.00
221 Pipa PVC ø 1 1/4" ( AW ) ex Wavin M' 14,000.00
222 Pipa PVC ø 1 1/2" ( AW ) ex Wavin M' 16,200.00
223 Pipa PVC ø 2"( AW ) ex Wavin M' 20,600.00
224 Pipa PVC ø 2 1/2"( AW ) ex Wavin M' 30,500.00
225 Pipa PVC ø 3" ( AW ) ex Wavin M' 42,200.00
226 Pipa PVC ø 3/4" ( AW ) ex Wavin M' 7,000.00
227 Pipa PVC ø 4" ( AW ) ex Wavin M' 69,800.00
228 Pipa PVC ( hitam ) 4" M' 37,400.00
229 Pintu Aluminium ( 1,8 x 0,65 ) Set 208,800.00
230 Plamur Kayu KG 34,900.00
231 Plamur tembok KG 20,200.00
232 Plat alumunium 0,5 mm M2 64,100.00
233 Plat alumunium 0,6 mm M2 84,500.00
234 Plat alumunium ( Aluminium Sheet ) 0,3 mm M 2
76,800.00
235 Plat alumunium unt lap. pintu (1x2) tebal 0,3 mm LBR 67,500.00
236 Plywood 3 mm uk. 0,9 x 2,2 m LBR 68,700.00
237 Plywood 4 mm LBR 68,700.00
238 Plywood 9 mm uk. 1,2 x 2,4 m LBR 136,100.00
239 Polixarbonat Twinlite 3,322,600.00
240 Pompa air Nasional 125 watt (dlm negeri), biasa Bh 392,600.00
241 Pompa air Nasional 125 watt (dlm negeri), otomatis Bh 453,000.00
242 Pompa air Sanyo 100 watt (dlm negeri) Bh 1,015,900.00
243 Pompa air Shimitzu 125 watt (dlm negeri), biasa 429,600.00
244 Pompa air Shimitzu 125 watt (dlm negeri), otomatis 527,200.00
245 Reng kayu Bengkirai 3/4 ikat M 3
8,457,800.00
246 Reng Kayu Kempas 2/3, 3/3, 3/4 (ikat) M3 5,107,600.00
247 Reng Kayu Meranti Batu 2/3 M 3
4,640,700.00
248 Residu ltr 0.00
249 Rol Cat Bh 33,600.00
250 Reservoir (Tangki air) Stainless + Kaki merk "Kettler" 1000 Lt Bh 2,636,200.00
251 Reservoir (Tangki air) Stainless + Kaki merk "Kettler" 500 Lt 1,949,600.00
252 Reservoir (Tangki air) Plastik "PENGUIN" 1000 Lt 1,757,400.00
253 Reservoir (Tangki air) Plastik "PENGUIN" 500 Lt 1,060,800.00
254 Roster Bh 42,000.00
255 Salang Kg 13,800.00
256 Seal Tape Bh 3,500.00
257 Sekrup asbes / pengait Bh 1,200.00
258 Seng BJLS 20, uk 90 cm M' 27,800.00
259 Seng BJLS 30, Uk. 55 cm M' 25,300.00
260 Seng BJLS 30, Uk. 90 cm M' 38,600.00
261 Seng Gelombang ( 210 x 80 x 0.2 cm ) lbr 57,800.00
262 Seng Gelombang 3' - 6' ( 90 x 180 x 0.2 cm ) lbr 51,500.00
263 Seng glb BJLS 20(80 x 80) lbr 47,700.00
264 Seng plat 3' x 6' ( 90 cm x 180 cm ) bjls 28 lbr 53,100.00
265 Seng Plat BJLS 20 Lebar 90 M2 29,900.00
266 Seng Plat BJLS 30 lebar 90 M 2
39,800.00
267 Sewa Wales 1,254,100.00
268 Shear Connector Ls 0.00
269 Sirlak Kg 256,200.00
270 Sirtu M3 224,400.00
271 Sirtu Dontu M 3
151,400.00
272 Solar Ltr 6,700.00
273 Spiritus Ltr 10,400.00
274 Tanah urug pilihan M3 67,800.00
275 Tanah liat 0.00
276 Teakwood 0,9 x 2,1 ,t = 3 mm Lbr 75,100.00
277 Teakwood 0,9 x 2,1 t = 4 mm Lbr 93,300.00
278 Teakwood 1,2 x 2,4 t = 4 mm / 3mm Lbr 113,600.00
279 Tempat Sabun ( INA ) Bh 33,000.00
280 Terpentin ltr 18,000.00
281 Triplek 1,2 x 2,4 ,T = 3 mm LBR 52,000.00
282 Triplek 1,2 x 2,4 ,T = 4 mm LBR 65,100.00
283 Triplek 1,2 x 2,4 ,T = 6 mm LBR 78,200.00
284 Triplek 0,9 x 2,1 ( uk. Pintu ), t = 4mm LBR 57,100.00
285 Triplek 0,9 x 2,1 ( uk. Pintu ), t = 3mm LBR 46,400.00
286 Urinoir "KIA" Bh 1,107,500.00
287 Usuk ky. Bangkirai ( Ikat ) 5/7 uk 4x6x400 M3 7,963,500.00
288 Usuk ky. Bangkirai ( Lepas ) 4x6x400 M3 10,874,300.00
289 Usuk ky. Kempas ( Ikat ) M3 5,034,400.00
290 Usuk ky. Kempas ( Lepas ) M3 6,151,100.00
291 Usut ky. Meranti Batu ( Ikat ) M3 4,585,800.00
292 Usut ky. Meranti Batu ( Lepas ) uk 5x7x400 M 3
5,464,600.00
293 Wastafel ( INA ) warna tua Bh 432,400.00
294 Water stop bh 0.00
295 Wiremesh M6 (5,4 x 2,1) m M 2
36,800.00 11.34
296 Wood Filler ( INFRA ) Kg 37,800.00
Bata Ringan (0,75 x 0,20 x 0,60) m & (0,10 x 0,20 x 0,60) m3 786,400.00
Atap Ringan (Genteng Metal) berpasir 800 mm x 770 m T = 0,30 m2 124,100.00
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : PEMBANGUNAN
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, BREBES
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018

HARGA SAT JUMLAH HARGA JUMLAH SEMUA


NO URAIAN PEKERJAAN ANALISA VOLUME SAT (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan dan Bongkaran Atap Taksir 1.00 ls 5,881,000.00 5,881,000.00
2 Bongkaran Pasangan Bata 248.36 m2
3 Bongkar beton (kolom dan Balok) 20.58 m3
2 Bouwplank Taksir 1.00 ls 750,000.00 750,000.00
Jumlah I 6,631,000.00
II PEKERJAAN TANAH
1 Galian Tanah A.2.3.1.1 81.36 m2 39,697.00 3,229,747.92
Timbunan Tanah Kembali A.2.3.1.9 20.34 m2 35,255.00 717,086.70
Jumlah II 3,946,834.62
III PEKERJAAN BETON
1 Pas. Pondasi Batu Belah A.3.2.1.2 53.12 m2 784,227.00 41,658,138.24
1 Pondasi Foot plat
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 26.79 m3 884,089.00 23,684,744.31
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 6,618.95 kg 11,565.00 76,548,179.88
Pemasangan bekisting untuk pondasi A.4.1.1.20 200.66 m2 82,487.00 16,551,841.42
4 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.37 m3 884,089.00 20,661,159.93
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,585.53 kg 11,565.00 29,901,596.63
Pemasangan Begisting untuk kolom A.4.1.1.22 124.60 m2 197,415.00 24,597,909.00
2 Sloof
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.55 m3 884,089.00 3,138,515.95
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,035.83 kg 11,565.00 11,979,316.13
Pemasangan Begisting Untuk Sloof A.4.1.1.21 52.50 m2 88,979.00 4,671,397.50
3 balok utama
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 14.175 m3 884,089.00 12,531,961.58
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,133.97 kg 11,565.00 24,679,334.14
Pemasangan Begisting Untuk Balok A.4.1.1.23 73.50 m2 204,294.00 15,015,609.00
4 balok (anak & tepi)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 7.32 m3 884,089.00 6,471,531.48
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,492.43 kg 11,565.00 17,259,906.69
Pemasangan Begisting Untuk Balok A.4.1.1.23 48.80 m2 204,294.00 9,969,547.20
5 Dak lantai
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 31.39 m3 884,089.00 27,753,321.89
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 4,646.02 kg 11,565.00 53,731,175.04
Pemasangan Bekisting untuk Dak atap A.4.1.1.24 130.80 m2 293,415.00 38,378,682.00
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.89 m3 884,089.00 10,511,818.21
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,535.29 kg 11,565.00 17,755,582.59
Pemasangan Bekisting untuk Dak A.4.1.1.24 41.00 m2 293,415.00 12,030,015.00
JUMLAH II 499,481,283.79

IV PEKERJAAN BAJA
1 Pasang kuda-kuda dan dudukan kubah IWF A.4.2.1.2. 3,906.60 kg 29,418.00 114,924,358.80
3 Pasang baut kuda-kuda taksir 122.00 bh 25,000.00 3,050,000.00
4 Pasang baut angkur taksir 72.00 bh 45,000.00 3,240,000.00
5 Pasang plat simpul taksir 70.00 kg 15,000.00 1,050,000.00
6 Pasang gording canal C 100.50.20.2,6 A.4.2.1.1b. 1,651.89 kg 27,232.00 44,984,268.48
7 Pasang Jarum antar gording (trekstrang) dia 12 mm taksir 85.00 kg 15,000.00 1,275,000.00
8 Ikatan Angin dia 16mm taksir 112.00 kg 15,000.00 1,680,000.00
9 Plat Landas taksir 40.00 kg 15,000.00 600,000.00
10 Pasang Penutup atap metal berpasir taksir 224.50 m2 200,000.00 44,900,000.00
12 Pekerjaan pengelasan A.4.2.1.5a. 350 kg 2,532.32 886,310.57
13 Meni Besi(baja) A.4.7.1.16. 75.00 m2 24,126.50 1,809,487.50
14 Pengecatan permukaan baja secara manual sistem 3 lapis A.4.7.1.20 75.00 m2 123,366.00 9,252,450.00
JUMLAH IV 227,651,875.35

III PEKERJAAN PASANGAN


1 Pasangan Dinding 1/2 bata 1:4 A.4.4.1.9 518.91 m2 121,889.00 63,249,420.99
2 Plesteran 1:4 A.4.4.2.4 1,037.82 m2 45,857.00 47,591,311.74
3 pengecatan khusus Cat exterior Taksir 537.82 m2 40,000.00 21,512,800.00
4 Lantai Granit A.4.4.3.35 240.00 m2 367,477.00 88,194,480.00
5 Dinding Granit A.A.3.54.b 259.46 m2 367,477.00 95,343,745.04
6 Ps. Ornamen GRC tertutup sekaligus mighrab Taksir 305.50 m2 425,000.00 129,837,500.00
7 Ps. Gypsum datar Taksir 262.00 m2 160,000.00 41,920,000.00
8 Ps. Gypsum miring ruang sholat utama Taksir 216.50 m2 180,000.00 38,970,000.00
9 Ps. Kosen Kayu pintu lurus 3 buah Jati Lokal Taksir 21.00 m' 500,000.00 10,500,000.00
10 Ps. Kosen Kayu Lengkung 3 buah jati lokal Taksir 6.00 m' 750,000.00 4,500,000.00
11 Ps. Kosen Jendela (J2) lurus 2 buah Jati Lokal Taksir 20.00 m' 500,000.00 10,000,000.00
12 Ps. Kosen Jendela (J2) Lengkung 2 buah Jati Lokal Taksir 6.00 m' 750,000.00 4,500,000.00
13 Ps. Kosen Jendela (J1) Lurus 8 buah Jati Lokal Taksir 48.00 m' 500,000.00 24,000,000.00
14 Ps. Kosen Jendela (J1) Lengkung 8 Buah Jati Lokal Taksir 12.00 m' 750,000.00 9,000,000.00
15 Ps. Daun Pintu Tinggi ±2,4m (3 buah) Taksir 6.00 Tangkep 2,500,000.00 15,000,000.00
Ps. Daun Jendela J2 Tinggi +- 1,9m(2 buah) Taksir 4.00 Tangkep 2,000,000.00 8,000,000.00
16 Ps. Daun Jendela tunggal Tinggi +- 1,9m(8 buah) Taksir 8.00 Tangkep 2,000,000.00 16,000,000.00
17 Ps. Kaca Patri Pintu Lokal Taksir 13.20 m2 1,600,000.00 21,120,000.00
18 Ps. Kaca Patri Jendela (J1) Lokal Taksir 8.00 m2 1,600,000.00 12,800,000.00
Ps. Kaca Patri Jendela (J2) Lokal Taksir 16.00 m2 1,600,000.00 25,600,000.00
19 Ps. Ornamen Kaligrafi dinding Mighrab dan depan Taksir 1.00 ls 10,000,000.00 10,000,000.00
20 Ps. Paving A.121 151.50 m2 166,834.00 25,275,351.00
21 Ps. Kolom Artistik GRC Taksir 45.00 m' 750,000.00 33,750,000.00
22 Peralatan pintu dan Jendela (handle,kait dll) Taksir 1.00 unit 2,500,000.00 2,500,000.00
23 Pekerjaan Kelistrikan beserta peralatannya Taksir 1.00 ls 5,000,000.00 5,000,000.00
24 Pasang Kubah alu (rangka+finishing) Taksir 1.00 unit 180,000,000.00 180,000,000.00
25 Pasang List Kecil Taksir 350.00 m' 240,000.00 84,000,000.00
26 Ps. List Besar Taksir 105.00 m' 325,000.00 34,125,000.00
Jumlah III 1,062,289,608.77
Jumlah I s.d III Rp. 1,800,000,602.52
Pembulatan Rp. 1,800,000,000.00

Terbilang : Satu Milyar Delapan Ratus Juta Rupiah

PEKERJAAN TAMBAHAN
II PEKERJAAN TANAH
1 Galian Tanah A.2.3.1.1 10.32 m2 39,697.00 409,673.04
Timbunan Tanah Kembali A.2.3.1.9 3.44 m2 35,255.00 121,277.20
Jumlah II 530,950.24

4 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.37 m3 884,089.00 20,661,159.93
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,585.53 kg 11,565.00 29,901,596.63
Pemasangan Begisting untuk kolom A.4.1.1.22 124.60 m2 197,415.00 24,597,909.00

................................... .................................. Fatkhurozak, ST


BILL OF QUNTITY
KEGIATAN : PEMBANGUNAN MASJID
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, BREBES
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018

NO GAMBAR
LANTAI 1
BONGKARAN

1 GALIAN TANAH
=
=
~ Galian Footplat
P1 =
P2 =

~ Pengurangan
P1 =

Total =
~ Timbunan tanah kembali

~ PAS. PONDASI BATU BELAH

~ PENGURANGAN

Total =

4 PAS. PONDASI FOOT PLAT

KOLOM

SLOOF
BALOK

balok (anak & tepi)

DAK Lantai

PEKERJAAN PASANGAN
Pasangan Dinding 1/2 bata 1:4
Plesteran 1:4
pengecatan khusus Cat exterior
Lantai Granit
Dinding Granit
Ps. Ornamen GRC tertutup sekalig
Ps.Ornamen GRC lubang
Kosen Kayu Lengkung 1bh
Ps. Kosen Kayu pintu lurus 1 Bh T
Ps. Kosen Jendela (J1) Lurus 3 bu
Ps. Kosen Jendela (J1) Lengkung
Ps. Daun Pintu Tinggi
Ps. Daun Jendela tunggal Tinggi +
Ps. Kaca Patri Pintu Lokal 1 bh
Ps. Kaca Patri Jendela (J1) Lokal 3
Ps. Ornamen Kaligrafi dinding Migh
Ps. Paving
Ps. Kolom Artistik GRC
Peralatan pintu dan Jendela (hand
Pekerjaan Kelistrikan beserta pera
Pasang Kubah alu (rangka+finishin
Pasang List Kecil
Ps. List Besar
Keramik KM/Wc,Wudlu,Instalasi ai
Pekerjaan Tangga (2 bh)

LANTAI 2
PEKERJAAN BETON
Kolom
Membuat beton mutu f’c = 16,9 Mp
Pembesian 1 kg dengan besi polo
Pemasangan Begisting untuk kolom
balok (anak & tepi)
Membuat beton mutu f’c = 16,9 Mp
Pembesian 1 kg dengan besi polo
Pemasangan Begisting Untuk Balo
Dak lantai 2
Membuat beton mutu f’c = 16,9 MP
Pembesian 1 kg dengan besi polo
Pemasangan Bekisting untuk Dak
Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MP
Pembesian 1 kg dengan besi polo
Pemasangan Bekisting untuk Dak

PEKERJAAN PASANGAN
Pasangan Dinding 1/2 bata 1:4
Plesteran 1:4
pengecatan khusus Cat exterior
Lantai Granit
Dinding Granit
Ps.Ornamen GRC lubang
Kosen Kayu Lengkung 1bh
Ps. Kosen Kayu pintu lurus 1 Bh T
Ps. Kosen Jendela (J1) Lurus 3 bu
Ps. Kosen Jendela (J1) Lengkung
Ps. Daun Pintu Tinggi
Ps. Daun Jendela tunggal Tinggi +
Ps. Kaca Patri Pintu Lokal 1 bh
Ps. Kaca Patri Jendela (J1) Lokal 3

PEKERJAAN BAJA
Pasang kuda-kuda dan dudukan ku
Pasang baut kuda-kuda
Pasang baut angkur
Pasang plat simpul
Pasang gording canal C 100.50.20.
Pasang Jarum antar gording (treks
Ikatan Angin dia 16mm
Plat Landas
Pasang Penutup atap metal berpas
Pekerjaan pengelasan
Meni Besi(baja)
Pengecatan permukaan baja secara

PEKERJAAN GYPSUM
Ps. Gypsum datar
Ps. Gypsum miring ruang sholat ut
9.00 9.00

8.00

2.00
KUDA - KUDA
Bentang 7 m
Blk. Angin 5 / 7
Penyiku 8 / 12

NOK,GORDING,MURPLAT
NOK
Gording

Murplat
Jurai Luar

Total =

RABAT
PAS. BATU BATA
=

PLESTERAN
=

RABAT BETON 8cm


=

URUG PASIR BAWAH RABAT


=

Pasang Hantaran BC ø 50 mm
=

Pasang Hanger BC / Klem bubungan


=
BILL OF QUNTITY ( BQ )

URAIAN VOLUME
LANTAI 1
BONGKARAN

GALIAN TANAH
0.80 x 0.30 x 120.20 = 28.85
=
~ Galian Footplat
1.50 x 1.50 x 1.00 x 20.00 = 45.00
1.50 x 1.20 x 1.00 x 16 = 28.80
Jumlah = 102.65
~ Pengurangan
0.80 x 1.00 x 0.38 x 36.00 = 10.80

Jumlah = 10.80
102.65 - 10.80 = 91.85
~ Timbunan tanah kembali 0.25 x 91.85 = 22.962

~ PAS. PONDASI BATU BELAH


1.10 X 1.00 X 0.5 X 120.20 = 66.11
~ PENGURANGAN
0.30 X 0.40 X 36.00 = 4.32
66.11 - 4.32 = 61.79

PAS. PONDASI FOOT PLAT


Membuat beton
((0,4*0,4*2,5*20)+(0,3*0,3*2,5*4)+(2*3,14*0,15*2,5*12))
Pembesian
((7*2*2*20*1,5*1,58)+(7*2*2*16*1,2*1,58)+(10*1,58*20*2)+(8*1,58*16*2)+(0,888*2*5*1,4*(20+16)))
Begisting
(0,3*6*20)+(0,3*4,8*14)+(1,7*2,5*34)

Membuat beton GLOBAL (0,4*0,4*8*20)+(0,35*0,35*5,5*16)


(0,4*0,4*4*20)+(0,35*0,35*3*16)
Pembesian GLOBAL (10*1,58*20*8)+(8*1,58*16*7)+(0,888*7,5*5*1,4*(20+16))
(10*1,58*20*4)+(8*1,58*16*3)+(0,888*4*5*1,4*(20+16))
Begisting GLOBAL (1,6*6,5*20)+(1,2*7*16)/2
(1,6*6,5*20)+(1,2*7*16)/2

Membuat beton
(0,2*0,25*98)-(0,2*0,25*0,35*34)
Pembesian
(5*98*1,578)+(1*5*98*0,395)
Begisting
0,5*98

Membuat beton
(0,3*0,45*24)
Pembesian
(8*24*1,578)+(1,5*7*24*0,395)+(4*0,888*24)
Begisting
(0,7*24)

balok (anak & tepi)


Membuat beton
(0,2*0,3*(14,5+14,5+9,2+9,2+9,2+9,2+9,2+7+7+7+7))
Pembesian
(8*103*1,578)+(7*103*0,395)
begisting
(0,8*103)/2
DAK Lantai
Membuat beton
(9,2*15)*0,12
Pembesian
138*5*5*0,888
begisting
(1*164)/4

PEKERJAAN PASANGAN
Pasangan Dinding 1/2 bata 1:4
Plesteran 1:4 2.00 x 212.50
pengecatan khusus Cat exterior (9*4)+(0,5*5*4)
Lantai Granit (9,2*14,5)
Dinding Granit 3*7*2
Ps. Ornamen GRC tertutup sekaligus mighrab (3,3)+(5*2)
Ps.Ornamen GRC lubang (2*1,5*10)+(1,5*1*10)
Kosen Kayu Lengkung 1bh 3.00
Ps. Kosen Kayu pintu lurus 1 Bh T 2,4M 2,5+2+2,5
Ps. Kosen Jendela (J1) Lurus 3 buah Jati Lokal (2*2*3)+(1*2*3)
Ps. Kosen Jendela (J1) Lengkung 3 Buah Jati Lokal 1,5*3
Ps. Daun Pintu Tinggi ±2,4m (1 buah) 2*1
Ps. Daun Jendela tunggal Tinggi +- 1,9m(3 buah) 1*3
Ps. Kaca Patri Pintu Lokal 1 bh 1*2,2*2*1
Ps. Kaca Patri Jendela (J1) Lokal 3 bh (1*2*3)
Ps. Ornamen Kaligrafi dinding Mighrab dan depan 1.00
Ps. Paving (5,15*6,5)+(9*3)
Ps. Kolom Artistik GRC 12*2,5
Peralatan pintu dan Jendela (handle,kait dll)
Pekerjaan Kelistrikan beserta peralatannya
Pasang Kubah alu (rangka+finishing)
Pasang List Kecil
Ps. List Besar
Keramik KM/Wc,Wudlu,Instalasi air
Pekerjaan Tangga (2 bh)

PEKERJAAN BETON

Membuat beton mutu f’c = 16,9 Mpa (0,4*0,4*3,5*20)+(0,35*0,35*3*16)


Pembesian 1 kg dengan besi polos atau(10*1,58*20*3,5)+(8*1,58*16*2,5)+(0,888*3,5*5*1,4*(20+16))
Pemasangan Begisting untuk kolom (1,6*6,5*20)+(1,2*7*16)/2
balok (anak & tepi)
Membuat beton mutu f’c = 16,9 Mpa (0,2*0,3*(14,5+14,5+9,2+9,2+9,2+9,2+9,2+7+7+7+7))/2
Pembesian 1 kg dengan besi polos atau besi ulir ((8*103*1,578)+(7*103*0,395))/2
Pemasangan Begisting Untuk Balok (0,8*103)/2
Dak lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) ((3*9)+(2*5*2))*0,12
Pembesian 1 kg dengan besi polos atau0,888*((2*5*5)+(2*2*2)+(2*5*5)+(2*2*2)+(2*5*3)+(2*5*9))
Pemasangan Bekisting untuk Dak atap ((3*9)+(2*5*2))/2
Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200)
Pembesian 1 kg dengan besi polos atau besi ulir
Pemasangan Bekisting untuk Dak

PEKERJAAN PASANGAN
Pasangan Dinding 1/2 bata 1:4
Plesteran 1:4
pengecatan khusus Cat exterior
Lantai Granit 133,4-(3*4)
Dinding Granit 3x7x2
Ps.Ornamen GRC lubang 4*3
Kosen Kayu Lengkung 1bh
Ps. Kosen Kayu pintu lurus 1 Bh T 2,4M 2,5+2+2,5
Ps. Kosen Jendela (J1) Lurus 3 buah Jati Lokal (2*2*3)+(1*2*3)
Ps. Kosen Jendela (J1) Lengkung 3 Buah Jati Lokal 1,5*3
Ps. Daun Pintu Tinggi ±2,4m (1 buah)
Ps. Daun Jendela tunggal Tinggi +- 1,9m(3 buah)
Ps. Kaca Patri Pintu Lokal 1 bh 1*2,2*2*1
Ps. Kaca Patri Jendela (J1) Lokal 3 bh (1*2*3)

PEKERJAAN BAJA
Pasang kuda-kuda dan dudukan kubah IWF (4*4*25,95)+(3,5*8*25,95)+(1,5*4*25,95)+(3,2*4*25,95)
Pasang baut kuda-kuda
Pasang baut angkur
Pasang plat simpul
Pasang gording canal C 100.50.20.2,6 6*(9,2+9,2)*13,43
Pasang Jarum antar gording (trekstrang) dia 12 mm
Ikatan Angin dia 16mm (5+5)*4*2
Plat Landas
Pasang Penutup atap metal berpasir ((12*0,5*4*4,5))
Pekerjaan pengelasan
Meni Besi(baja)
Pengecatan permukaan baja secara manual sistem 3 lapis

PEKERJAAN GYPSUM
Ps. Gypsum datar (9*5)+(2*6,5)
Ps. Gypsum miring ruang sholat utama
KUDA - KUDA
Bentang 7 m = 0.29 x 6 = 1.74
Blk. Angin 5 / 7 = 0.05 x 0.07 x 3.70 x 6 = 0.08
Penyiku 8 / 12 = 0.08 x 0.12 x 0.80 x 12 = 0.09
Jumlah = 1.91

NOK,GORDING,MURPLAT
= 38.00 - 4.00 = 34.00
=[ 38.00 + 4.00 ]x 2
42.00 x 2 = 84.00
= 40.00 x 3 = 120.00
= 5.00 x 4 = 20.00
Jumlah = 258.00
0.08 x 0.12 x 258.00 = 2.48

PAS. BATU BATA 65.60


0.36 x 20.40 = 7.34

PLESTERAN
0.36 x 20.40 = 7.34

RABAT BETON 8cm


0.12 x 1.00 x 18.00 = 2.16

URUG PASIR BAWAH RABAT


0.10 x 1.00 x 18.00 = 1.80

Pasang Hantaran BC ø 50 mm
54.60 : 1.5 = 36.40

Pasang Hanger BC / Klem bubungan


32.00 x 2 = 64.00
TOTAL
VOLUME

91.85 M3

61.79 m3

37.16 M3

3,660.64 kg

200.66 M2

18.68 M3

2,765.82 KG

275.2 M2
4.305 M3

966.77 KG

49 M2

3.24 M3

487.76 KG

16.80 M2

6.18 M3

1,585.07 KG

41.20 m2

16.56 m3

3,063.60 kg

41 m2

212.50 m2
425.00 m2
46.00
133.40
42.00
13.30
45.00
3.00 m'
7.00 m'
18.00 m'
4.50 m
2.00 tangkep
3.00 tangkep
4.40 m2
6.00 m2
1.00 taksir
60.48 m2
30.00 m'
1.00 unit
1.00 ls
1.00 unit
175.00 m'
35.00 m'
1.00 ls
2.00 ls

17.08 m3
2,394.82 kg
275.2 m2

3.09 m3
792.53 kg
41.20 m2

5.64 m3
209.57 kg
23.50 m2

5.95 m3
767.64 kg
41.00 m2

150.00 m2
300.00 m2
46.00 m2
121.40 m2
42.00 m2
12.00 m2
3.00 m'
7.00 m'
18.00 m'
4.50 m'
2.00 Tangkep
3.00 Tangkep
4.40 m2
6.00 m2

1,629.66 kg
100.00 bh
72.00 bh
70.00 kg
1,482.67 kg
75.00 kg
80.00 kg
40.00 kg
108.00 m2
250 kg
55.00 m2
55.00 m2

58.00 m2
108.00 m2
1.91 M3

2.48 M3
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : PEMBANGUNAN
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, BREBES
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018
REVISI (PEKERJAAN ATAP DIMASUKKAN SETELAH LANTAI 2 TERMASUK KUBAH)
HARGA SAT JUMLAH HARGA JUMLAH SEMUA
NO URAIAN PEKERJAAN ANALISA VOLUME SAT (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan dan Bongkaran Atap Taksir 1.00 ls 5,881,000.00 5,881,000.00
2 Bongkaran Pas Bata (TERMASUK R.SEKR &Audio) A.2.2.1.14 248.36 m2 66,744.00 16,576,539.84
3 Bongkar beton (kolom dan Balok) A.2.2.1.13 20.58 m3 890,726.00 18,331,141.08
4 Bongkar kusen dan perapian Taksir 1.00 ls 1,500,000.00 1,500,000.00
5 Bouwplank Taksir 1.00 ls 750,000.00 750,000.00
Jumlah I 43,038,680.92
II PEKERJAAN TANAH
Galian Tanah pondasi Foot Plat K1 A.2.3.1.1. 40.50 m3 39,697.00 1,607,728.50
Galian Tanah Foot Plat K2 A.2.3.1.1. 46.88 m3 39,697.00 1,860,796.88
Galian Tanah pondasi batu kali A.2.3.1.1. 23.04 m3 39,697.00 914,618.88
2 Timbunan Tanah Kembali A.2.3.1.9 27.60 m2 35,255.00 973,170.21
Jumlah II 5,356,314.46
III PEKERJAAN BETON
1 Pas. Pondasi Batu Belah A.3.2.1.2 53.12 m2 784,227.00 41,658,138.24
1 Pondasi Foot plat
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 26.79 m3 884,089.00 23,684,744.31
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 6,618.95 kg 11,565.00 76,548,179.88
Pemasangan bekisting untuk pondasi A.4.1.1.20 200.66 m2 82,487.00 16,551,841.42
1 Pondasi Foot plat Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 2.6 m3 884,089.00 2,298,631.40
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 355.30 kg 11,565.00 4,109,073.41
Pemasangan bekisting untuk kolom A.4.1.1.20 12.10 m2 82,487.00 998,092.70
4 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.37 m3 884,089.00 20,661,159.93
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,585.53 kg 11,565.00 29,901,596.63
Pemasangan Begisting untuk kolom A.4.1.1.22 124.60 m2 197,415.00 24,597,909.00
4 Kolom Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 1.856 m3 884,089.00 1,640,869.18
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 237.57 kg 11,565.00 2,747,541.00
Pemasangan Begisting untuk kolom A.4.1.1.22 6.96 m2 197,415.00 1,374,008.40
4 Kolom Tambahan (4 buah) dekat tangga
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.432 m3 884,089.00 381,926.45
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 158.45 kg 11,565.00 1,832,451.12
Pemasangan Begisting untuk kolom A.4.1.1.22 5.76 m2 197,415.00 1,137,110.40
2 Sloof
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.55 m3 884,089.00 3,138,515.95
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,035.83 kg 11,565.00 11,979,316.13
Pemasangan Begisting Untuk Sloof A.4.1.1.21 52.50 m2 88,979.00 4,671,397.50
2 Sloof tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.41 m3 884,089.00 362,476.49
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 100.62 kg 11,565.00 1,163,705.00
Pemasangan Begisting untuk kolom A.4.1.1.21 5.10 m2 88,979.00 453,792.90
3 balok utama
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 14.175 m3 884,089.00 12,531,961.58
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,133.97 kg 11,565.00 24,679,334.14
Pemasangan Begisting Untuk Balok A.4.1.1.23 73.50 m2 204,294.00 15,015,609.00
3 balok utama tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 1.377 m3 884,089.00 1,217,390.55
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 207.30 kg 11,565.00 2,397,421.03
Pemasangan Begisting Untuk Balok A.4.1.1.23 7.14 m2 204,294.00 1,458,659.16
4 balok (anak & tepi)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 7.32 m3 884,089.00 6,471,531.48
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,492.43 kg 11,565.00 17,259,906.69
Pemasangan Begisting Untuk Balok A.4.1.1.23 48.80 m2 204,294.00 9,969,547.20
5 Dak lantai
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 31.39 m3 884,089.00 27,753,321.89
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 4,646.02 kg 11,565.00 53,731,175.04
Pemasangan bondex A.4.1.1.24 318.36 m2 161,065.00 51,276,653.40
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.89 m3 884,089.00 10,511,818.21
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,535.29 kg 11,565.00 17,755,582.59
Pemasangan Bekisting untuk Dak A.4.1.1.24 41.00 m2 161,065.00 6,603,665.00
6 Dak tambahan dekat tangga dan kanan kiri
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.58 m3 884,089.00 512,771.62
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 74.89 kg 11,565.00 866,125.98
Pemasangan Bekisting untuk Dak A.4.1.1.24 2.00 m2 161,065.00 322,130.00
3 Pembuatan tangga (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.624 m3 884,089.00 3,203,938.54
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 369.52 kg 11,565.00 4,273,480.30
Pemasangan Begisting Untuk tangga A.4.1.1.26 22.92 m2 392,085.00 8,986,588.20
JUMLAH II 548,691,089.01

III PEKERJAAN PASANGAN


1 Pasangan Dinding 1/2 bata 1:4 A.4.4.1.9 518.91 m2 121,889.00 63,249,420.99
2 Plesteran 1:4 (termasuk Acian) A.4.4.2.4 1,037.82 m2 45,857.00 47,591,311.74
3 pengecatan khusus Cat exterior Taksir 537.82 m2 40,000.00 21,512,800.00
4 Lantai Granit A.4.4.3.35 240.00 m2 367,477.00 88,194,480.00
5 Lantai Granit Tangga A.4.4.3.35 50.00 m2 367,477.00 18,373,850.00
5 Dinding Granit A.A.3.54.b 259.46 m2 367,477.00 95,343,745.04
6 Ps. Ornamen GRC tertutup sekaligus mighrab Taksir 305.50 m2 425,000.00 129,837,500.00
7 Ps. Gypsum datar Taksir 262.00 m2 160,000.00 41,920,000.00
8 Ps. Kosen Kayu pintu lurus 3 buah Jati Lokal A.4.6.1.1 1.59 m3 14,611,440.00 23,226,710.31
9 Ps. Kosen Kayu Lengkung 3 buah jati lokal A.4.6.1.1 0.68 m3 14,611,440.00 9,954,304.42
10 Ps. Kosen Jendela (J2) lurus 2 buah Jati Lokal A.4.6.1.1 1.51 m3 14,611,440.00 22,120,676.49
11 Ps. Kosen Jendela (J2) Lengkung 2 buah Jati Lokal A.4.6.1.1 0.68 m3 14,611,440.00 9,954,304.42
12 Ps. Kosen Jendela (J1) Lurus 8 buah Jati Lokal A.4.6.1.1 3.63 m3 14,611,440.00 53,089,623.57
13 Ps. Kosen Jendela (J1) Lengkung 8 Buah Jati Lokal A.4.6.1.1 1.36 m3 14,611,440.00 19,908,608.84
14 Ps. Daun Pintu Tinggi ±2,4m (3 buah) Taksir 34.56 m2 859,806.00 29,714,895.36
15 Ps. Daun Jendela J2 Tinggi +- 1,9m(2 buah) Taksir 22.80 m2 859,806.00 19,603,576.80
16 Ps. Daun Jendela tunggal Tinggi +- 1,9m(8 buah) Taksir 27.36 m2 859,806.00 23,524,292.16
17 Ps. Kaca Patri Pintu Lokal Taksir 13.20 m2 1,600,000.00 21,120,000.00
18 Ps. Kaca Patri Jendela (J1) Lokal Taksir 8.00 m2 1,600,000.00 12,800,000.00
19 Ps. Kaca Patri Jendela (J2) Lokal Taksir 16.00 m2 1,600,000.00 25,600,000.00
20 Melamik Kosen Kayu pintu lurus 3 buah Taksir 27.00 m' 75,000.00 2,025,000.00
21 Melamik Kosen Kayu lengkung Taksir 9.00 m' 75,000.00 675,000.00
22 Melamik Kosen J2 lurus 2 buah Taksir 27.00 m' 75,000.00 2,025,000.00
23 Melamik kosen J2 lengkung Taksir 9.00 m' 75,000.00 675,000.00
24 Melamik Kosen J1 Taksir 48.00 m' 75,000.00 3,600,000.00
25 Melamik Kosen J1 lengkung Taksir 12.00 m' 75,000.00 900,000.00
26 Melamik daun pintu Taksir 28.80 m2 120,000.00 3,456,000.00
27 Melamik Daun J2 Taksir 6.08 m2 120,000.00 729,600.00
28 Melamik Daun J1 Taksir 24.32 m2 120,000.00 2,918,400.00
29 Ps. Ornamen Kaligrafi dinding Mighrab dan depan Taksir 1.00 ls 10,000,000.00 10,000,000.00
30 Ps. Paving A.121 151.50 m2 166,834.00 25,275,351.00
31 Ps. Kolom Artistik GRC Taksir 80.00 m' 750,000.00 60,000,000.00
32 Peralatan pintu dan Jendela (handle,kait dll) Taksir 1.00 unit 2,500,000.00 2,500,000.00
33 Pekerjaan Kelistrikan beserta peralatannya Taksir 1.00 ls 5,000,000.00 5,000,000.00
34 Pasang List Kecil Taksir 350.00 m' 240,000.00 84,000,000.00
35 Ps. List Besar Taksir 105.00 m' 325,000.00 34,125,000.00
Jumlah III 1,014,544,451.12
Jumlah I s.d III Rp. 1,611,630,535.51
Pembulatan Rp. 1,611,630,000.00

Terbilang : Satu Milyar Lima Ratus Sembilan Puluh Tiga Juta Dua Ratus Lima Puluh Enam Ribu Rupiah
RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : PEMBANGUNAN
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, BR
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018

NO URAIAN PEKERJAAN VOLUME SAT

1 2 4 5
REVISI (PEKERJAAN ATAP DIMASUKKAN SETELAH LANTAI 2 TERMASUK KUBAH)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan dan Bongkaran Atap 1.00 ls
2 Bongkaran Pas Bata (TERMASUK R.SEKR &Audio) 248.36 m2
3 Bongkar beton (kolom dan Balok) 20.58 m3
4 Bongkar kusen dan perapian 1.00 ls
5 Bouwplank 1.00 ls
II PEKERJAAN TANAH
Galian Tanah pondasi Foot Plat K1 40.50 m3
Galian Tanah Foot Plat K2 46.88 m3
Galian Tanah pondasi batu kali 23.04 m3
2 Timbunan Tanah Kembali 27.60 m2
III PEKERJAAN BETON
1 Pas. Pondasi Batu Belah 53.12 m2
1 Pondasi Foot plat
Membuat beton mutu f’c = 16,9 MPa (K 200) 26.79 m3
Pembesian 1 kg dengan besi polos atau besi ulir 6,618.95 kg
Pemasangan bekisting untuk pondasi 200.66 m2
1 Pondasi Foot plat Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) 2.6 m3
Pembesian 1 kg dengan besi polos atau besi ulir 355.30 kg
Pemasangan bekisting untuk kolom 12.10 m2
4 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) 23.37 m3
Pembesian 1 kg dengan besi polos atau besi ulir 2,585.53 kg
Pemasangan Begisting untuk kolom 124.60 m2
4 Kolom Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) 1.856 m3
Pembesian 1 kg dengan besi polos atau besi ulir 237.57 kg
Pemasangan Begisting untuk kolom 6.96 m2
4 Kolom Tambahan (4 buah) dekat tangga
Membuat beton mutu f’c = 16,9 MPa (K 200) 0.432 m3
Pembesian 1 kg dengan besi polos atau besi ulir 158.45 kg
Pemasangan Begisting untuk kolom 5.76 m2
2 Sloof
Membuat beton mutu f’c = 16,9 MPa (K 200) 3.55 m3
Pembesian 1 kg dengan besi polos atau besi ulir 1,035.83 kg
Pemasangan Begisting Untuk Sloof 52.50 m2
2 Sloof tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) 0.41 m3
Pembesian 1 kg dengan besi polos atau besi ulir 100.62 kg
Pemasangan Begisting untuk kolom 5.10 m2
3 balok utama
Membuat beton mutu f’c = 16,9 MPa (K 200) 14.175 m3
Pembesian 1 kg dengan besi polos atau besi ulir 2,133.97 kg
Pemasangan Begisting Untuk Balok 73.50 m2
3 balok utama tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) 1.377 m3
Pembesian 1 kg dengan besi polos atau besi ulir 207.30 kg
Pemasangan Begisting Untuk Balok 7.14 m2
4 balok (anak & tepi)
Membuat beton mutu f’c = 16,9 MPa (K 200) 7.32 m3
Pembesian 1 kg dengan besi polos atau besi ulir 1,492.43 kg
Pemasangan Begisting Untuk Balok 48.80 m2
5 Dak lantai
Membuat beton mutu f’c = 16,9 MPa (K 200) 31.39 m3
Pembesian 1 kg dengan besi polos atau besi ulir 4,646.02 kg
Pemasangan bondex 318.36 m2
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) 11.89 m3
Pembesian 1 kg dengan besi polos atau besi ulir 1,535.29 kg
Pemasangan Bekisting untuk Dak 41.00 m2
6 Dak tambahan dekat tangga dan kanan kiri
Membuat beton mutu f’c = 16,9 MPa (K 200) 0.58 m3
Pembesian 1 kg dengan besi polos atau besi ulir 74.89 kg
Pemasangan Bekisting untuk Dak 2.00 m2
3 Pembuatan tangga (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) 3.624 m3
Pembesian 1 kg dengan besi polos atau besi ulir 369.52 kg
Pemasangan Begisting Untuk tangga 22.92 m2

III PEKERJAAN PASANGAN


1 Pasangan Dinding 1/2 bata 1:4 518.91 m2
2 Plesteran 1:4 (termasuk Acian) 1,037.82 m2
3 pengecatan khusus Cat exterior 537.82 m2
4 Lantai Granit 240.00 m2
5 Lantai Granit Tangga 50.00 m2
5 Dinding Granit 259.46 m2
6 Ps. Ornamen GRC tertutup sekaligus mighrab 305.50 m2
7 Ps. Gypsum datar 262.00 m2
8 Ps. Kosen Kayu pintu lurus 3 buah Jati Lokal 1.59 m3
9 Ps. Kosen Kayu Lengkung 3 buah jati lokal 0.68 m3
10 Ps. Kosen Jendela (J2) lurus 2 buah Jati Lokal 1.51 m3
11 Ps. Kosen Jendela (J2) Lengkung 2 buah Jati Lokal 0.68 m3
12 Ps. Kosen Jendela (J1) Lurus 8 buah Jati Lokal 3.63 m3
13 Ps. Kosen Jendela (J1) Lengkung 8 Buah Jati Lokal 1.36 m3
14 Ps. Daun Pintu Tinggi ±2,4m (3 buah) 34.56 m2
15 Ps. Daun Jendela J2 Tinggi +- 1,9m(2 buah) 22.80 m2
16 Ps. Daun Jendela tunggal Tinggi +- 1,9m(8 buah) 27.36 m2
17 Ps. Kaca Patri Pintu Lokal 13.20 m2
18 Ps. Kaca Patri Jendela (J1) Lokal 8.00 m2
19 Ps. Kaca Patri Jendela (J2) Lokal 16.00 m2
20 Melamik Kosen Kayu pintu lurus 3 buah 27.00 m'
21 Melamik Kosen Kayu lengkung 9.00 m'
22 Melamik Kosen J2 lurus 2 buah 27.00 m'
23 Melamik kosen J2 lengkung 9.00 m'
24 Melamik Kosen J1 48.00 m'
25 Melamik Kosen J1 lengkung 12.00 m'
26 Melamik daun pintu 28.80 m2
27 Melamik Daun J2 6.08 m2
28 Melamik Daun J1 24.32 m2
29 Ps. Ornamen Kaligrafi dinding Mighrab dan depan 1.00 ls
30 Ps. Paving 151.50 m2
31 Ps. Kolom Artistik GRC 80.00 m'
32 Peralatan pintu dan Jendela (handle,kait dll) 1.00 unit
33 Pekerjaan Kelistrikan beserta peralatannya 1.00 ls
34 Pasang List Kecil 350.00 m'
35 Ps. List Besar 105.00 m'
REVISI DAN DUA LANTAI (LANTAI DUA)
III PEKERJAAN BETON

1 Pasang Steiger 402.00 m2


2 Kolom Lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) 23.1525 m3
Pembesian 1 kg dengan besi polos atau besi ulir 15,099.49 kg
Pemasangan Begisting untuk kolom 107.10 m2
3 balok utama lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) 2.673 m3
Pembesian 1 kg dengan besi polos atau besi ulir 235.77 kg
Pemasangan Begisting Untuk Balok 13.86 m2
4 balok (anak & tepi) lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) 6.3 m3
Pembesian 1 kg dengan besi polos atau besi ulir 1,284.47 kg
Pemasangan Begisting Untuk Balok 42.00 m2
5 Dak Atap
Membuat beton mutu f’c = 16,9 MPa (K 200) 31.39 m3
Pembesian 1 kg dengan besi polos atau besi ulir 4,646.02 kg
Pemasangan bondex 318.36 m2
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) 11.89 m3
Pembesian 1 kg dengan besi polos atau besi ulir 1,535.29 kg
Pemasangan Bekisting untuk Dak 41.00 m2
IV PEKERJAAN BAJA
1 Erection 3,906.60 kg
2 Pasang kuda-kuda dan dudukan kubah IWF 3,906.60 kg
3 Pasang baut kuda-kuda 122.00 bh
4 Pasang baut angkur 72.00 bh
5 Pasang plat simpul 70.00 kg
6 Pasang gording canal C 100.50.20.2,6 1,651.89 kg
7 Pasang CNP baja ringan 210.00 m2
8 Reng Baja Ringan 210.00 m2
9 Pasang Jarum antar gording (trekstrang) dia 12 mm 85.00 kg
10 Ikatan Angin dia 16mm 112.00 kg
11 Plat Landas 40.00 kg
12 Pasang Penutup atap metal berpasir 224.50 m2
13 Pekerjaan pengelasan 350 kg
14 Meni Besi(baja) 75.00 m2
15 Pengecatan permukaan baja secara manual sistem 3 lapi 75.00 m2
16 Pasang Kosen dan kaca patri Bawah Kubah besar 9.00 unit
17 PS. Kubah alu (rangka+finishing) diameter (5,5m -6m) 1.00 unit
III PEKERJAAN PASANGAN
1 Pasangan Dinding 1/2 bata 1:4 420.00 m2
2 Plesteran 1:4 (termasuk Acian) 840.00 m2
3 pengecatan khusus Cat exterior 840.00 m2
4 Lantai Granit 240.00 m2
5 Ps. Gypsum datar 262.00 m2
6 Ps. Gypsum miring ruang sholat utama 216.50 m2
12 Ps. Kosen Jendela art Lengkung 13 buah 1.11 m3
18 Ps. Kaca Patri Lokal Jendela art 41.60 m2
24 Melamik Kosen Jendela art 98.80 m'
30 Ps. Kolom Artistik GRC 70.00 m'
32 Pekerjaan Kelistrikan lantai 2 beserta peralatannya 1.00 ls
34 Pasang List Kecil 350.00 m'
35 Ps. List Besar 105.00 m'
36 Pasang Railing Stainless lantai 2 22.00 m'
PEKERJAAN MENARA
1 balok
Membuat beton mutu f’c = 16,9 MPa (K 200) 4.48 m3
Pembesian 1 kg dengan besi polos atau besi ulir 1,367.84 kg
Pemasangan Begisting Untuk Balok 19.60 m2
2 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) 6.48 m3
Pembesian 1 kg dengan besi polos atau besi ulir 494.75 kg
Pemasangan Begisting untuk kolom 3.24 m2
3 Dak Topi Menara
Membuat beton mutu f’c = 16,9 MPa (K 200) 4.03 m3
Pembesian 1 kg dengan besi polos atau besi ulir 464.81 kg
Pemasangan Bekisting untuk Dak atap 28.72 m2
PEKERJAAN PEMASANGAN GRC MENARA
1 Kolom IWF dan Rangka Siku Menara (4 menara) 4.00 unit
2 Penangkal Petir 1.00 ls
3 Ps Kosen dan Kaca Patri bwh kubah menara kecil 5.00 unit
4 PS. Kubah alu (rangka+finishing) dia (2,5m-3m) 1.00 unit
MAKA UNTUK 4 BH MENARA 4.00 bh
RAB )
GUNAN MASJID AT-TAQWA BULAKAMBA, BREBES
ULAKAMBA, BREBES

JUMLAH HARGA KEMAJUAN FISIK PEKERJAAN


REALISASI
(Rp) NILAI SD MGG LL MINGGU INI KUM SD MGG INI
BOBOT(%) VOL BOBOT(%) VOL BOBOT(%) VOL BOBOT(%)
7
MASUK KUBAH)

5,881,000.00 0.1245 0.1245 100 0.1245 100


16,576,539.84 0.3510 0.3510 100 0.3510 100
18,331,141.08 0.3881 0.3881 100 0.3881 100
1,500,000.00 0.0318 0.0318 100 0.0318 100
750,000.00 0.0159 0.0159 100 0.0159 100

1,607,728.50 0.0340 0.0340 100 0.0340 100


1,860,796.88 0.0394 0.0394 100 0.0394 100
914,618.88 0.0194 0.0194 100 0.0194 100
973,170.21 0.0206 0.0206 100 0.0206 100

41,658,138.24 0.8820 0.8820 100 0.8820 100

23,684,744.31 0.5015 0.5015 100 0.5015 100


76,548,179.88 1.6208 1.6208 100 1.6208 100
16,551,841.42 0.3505 0.3505 100 0.3505 100
0.0000 100
2,298,631.40 0.0487 0.0487 100 0.0487 100
4,109,073.41 0.0870 0.0870 100 0.0870 100
998,092.70 0.0211 0.0211 100 0.0211 100
0.0000 100
20,661,159.93 0.4375 0.4375 100 0.4375 100
29,901,596.63 0.6331 0.6331 100 0.6331 100
24,597,909.00 0.5208 0.5208 100 0.5208 100
0.0000 100
1,640,869.18 0.0347 0.0347 100 0.0347 100
2,747,541.00 0.0582 0.0582 100 0.0582 100
1,374,008.40 0.0291 0.0291 100 0.0291 100
0.0000 100
381,926.45 0.0081 0.0081 100 0.0081 100
1,832,451.12 0.0388 0.0388 100 0.0388 100
1,137,110.40 0.0241 0.0241 100 0.0241 100

3,138,515.95 0.0665 0.0665 100 0.0665 100


11,979,316.13 0.2536 0.2536 100 0.2536 100
4,671,397.50 0.0989 0.0989 100 0.0989 100
362,476.49 0.0077 0.0077 100 0.0077 100
1,163,705.00 0.0246 0.0246 100 0.0246 100
453,792.90 0.0096 0.0096 100 0.0096 100

12,531,961.58 0.2653 0.2653 100 0.2653 100


24,679,334.14 0.5225 0.5225 100 0.5225 100
15,015,609.00 0.3179 0.3179 100 0.3179 100

1,217,390.55 0.0258 0.0258 100 0.0258 100


2,397,421.03 0.0508 0.0508 100 0.0508 100
1,458,659.16 0.0309 0.0309 100 0.0309 100

6,471,531.48 0.1370 0.1370 100 0.1370 100


17,259,906.69 0.3654 0.3654 100 0.3654 100
9,969,547.20 0.2111 0.2111 100 0.2111 100

27,753,321.89 0.5876 0.5876 100 0.5876 100


53,731,175.04 1.1377 1.1377 100 1.1377 100
51,276,653.40 1.0857 1.0857 100 1.0857 100

10,511,818.21 0.2226 0.2226 100 0.2226 100


17,755,582.59 0.3759 0.3759 100 0.3759 100
6,603,665.00 0.1398 0.1398 100 0.1398 100

512,771.62 0.0109 0.0109 100 0.0109 100


866,125.98 0.0183 0.0183 100 0.0183 100
322,130.00 0.0068 0.0068 100 0.0068 100

3,203,938.54 0.0678 0.0678 100 0.0678 100


4,273,480.30 0.0905 0.0905 100 0.0905 100
8,986,588.20 0.1903 0.1903 100 0.1903 100

63,249,420.99 1.3392 1.3392 100 1.3392 100


47,591,311.74 1.0077 1.0077 100 1.0077 100
21,512,800.00 0.4555
88,194,480.00 1.8674
18,373,850.00 0.3890
95,343,745.04 2.0187
129,837,500.00 2.7491
41,920,000.00 0.8876
23,226,710.31 0.4918 0.4918 100 0.4918 100
9,954,304.42 0.2108 0.2108 100 0.2108 100
22,120,676.49 0.4684 0.4684 100 0.4684 100
9,954,304.42 0.2108 0.2108 100 0.2108 100
53,089,623.57 1.1241 1.1241 100 1.1241 100
19,908,608.84 0.4215 0.4215 100 0.4215 100
29,714,895.36 0.6292 0.6292 100 0.6292 100
19,603,576.80 0.4151 0.4151 100 0.4151 100
23,524,292.16 0.4981 0.4981 100 0.4981 100
21,120,000.00 0.4472
12,800,000.00 0.2710
25,600,000.00 0.5420
2,025,000.00 0.0429
675,000.00 0.0143
2,025,000.00 0.0429
675,000.00 0.0143
3,600,000.00 0.0762
900,000.00 0.0191
3,456,000.00 0.0732
729,600.00 0.0154
2,918,400.00 0.0618
10,000,000.00 0.2117
25,275,351.00 0.5352
60,000,000.00 1.2704
2,500,000.00 0.0529
5,000,000.00 0.1059
84,000,000.00 1.7786
34,125,000.00 0.7225

26,684,760.00 0.5650 0.5650 100 0.5650 100

20,468,870.57 0.4334 0.4334 100 0.4334 100


174,625,642.33 3.6974 3.6974 100 3.6974 100
21,143,146.50 0.4477 0.4477 100 0.4477 100

2,363,169.90 0.0500 0.0500 100 0.0500 100


2,726,662.70 0.0577 0.0577 100 0.0577 100
2,831,514.84 0.0600 0.0600 100 0.0600 100

5,569,760.70 0.1179 0.1179 100 0.1179 100


14,854,837.73 0.3145 0.3145 100 0.3145 100
8,580,348.00 0.1817 0.1817 100 0.1817 100

27,753,321.89 0.5876 0.5876 100 0.5876 100


53,731,175.04 1.1377 1.1377 100 1.1377 100
51,276,653.40 1.0857 1.0857 100 1.0857 100

10,511,818.21 0.2226 0.2226 100 0.2226 100


17,755,582.59 0.3759 0.3759 100 0.3759 100
6,603,665.00 0.1398 0.1398 100 0.1398 100

2,084,386.74 0.0441 0.0441 100 0.0441 100


114,924,358.80 2.4333 2.4333 100 2.4333 100
3,050,000.00 0.0646 0.0646 100 0.0646 100
3,240,000.00 0.0686 0.0686 100 0.0686 100
1,050,000.00 0.0222 0.0222 100 0.0222 100
44,984,268.48 0.9525 0.9525 100 0.9525 100
33,600,000.00 0.7114 0.7114 100 0.7114 100
15,750,000.00 0.3335 0.3335 100 0.3335 100
1,275,000.00 0.0270 0.0270 100 0.0270 100
1,680,000.00 0.0356 0.0356 100 0.0356 100
600,000.00 0.0127 0.0127 100 0.0127 100
44,900,000.00 0.9507 0.9507 100 0.9507 100
886,310.57 0.0188 0.0188 100 0.0188 100
1,809,487.50 0.0383 0.0383 100 0.0383 100
9,252,450.00 0.1959 0.1959 100 0.1959 100
90,000,000.00 1.9056
210,000,000.00 4.4464

51,193,380.00 1.0839 1.0839 100 1.0839 100


38,519,880.00 0.8156 0.8156 100 0.8156 100
33,600,000.00 0.7114
88,194,480.00 1.8674
41,920,000.00 0.8876
38,970,000.00 0.8251
16,168,435.05 0.3423
66,560,000.00 1.4093
7,410,000.00 0.1569
52,500,000.00 1.1116
5,000,000.00 0.1059
84,000,000.00 1.7786
34,125,000.00 0.7225
22,000,000.00 0.4658

3,960,718.72 0.0839 0.0839 100 0.0839 100


15,819,011.78 0.3349 0.3349 100 0.3349 100
4,004,162.40 0.0848 0.0848 100 0.0848 100

5,728,896.72 0.1213 0.1213 100 0.1213 100


5,721,830.01 0.1212 0.1212 100 0.1212 100
311,040.00 0.0066 0.0066 100 0.0066 100

3,564,646.85 0.0755 0.0755 100 0.0755 100


5,375,504.52 0.1138 0.1138 100 0.1138 100
8,426,878.80 0.1784 0.1784 100 0.1784 100

220,000,000.00
5,000,000.00
25,000,000.00
60,000,000.00
1,451,650,759.17 30.7363
4,722,922,351.01 100.0000 30.8330 7.0295 37.8625
ISIK PEKERJAAN
RENCANA
SD MGG LL MINGGU INI KUM SD MGG INI
VOL BOBOT(%) VOL BOBOT(%) VOL BOBOT(%)
1.589625

###
10.50 21
4.50 6
10.00 20
4.50 6
24.00 48
9.00 12
15.00 6
8.00 4
16.00 8
101.50
###
t
t
t
ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN PEMBANGUNAN MASJID AT-TAQWA
DESA BULAKAMBA, BREBES
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A. 2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.400 63,100.00 25,240.00
Tukang Kayu L.02 OH 0.200 85,100.00 17,020.00
Kepala Tukang Kayu L.03 OH 0.020 85,100.00 1,702.00
Mandor L.04 OH 0.020 74,100.00 1,482.00
JUMLAH TENAGA KERJA 45,444.00
B BAHAN
Dolken kayu φ 8-10/400 cm btg 1.250 48,000.00 60,000.00
Semen portland kg 2.500 1,100.00 2,750.00
Seng gelombang ( 90 x 180 x 0.2 cm ) lbr 1.200 51,500.00 61,800.00
Pasir beton m³ 0.005 243,100.00 1,215.50
Koral beton m³ 0.009 308,500.00 2,776.50
Kayu 5/7 (Usuk ky. Meranti Batu (Ikat)) m³ 0.072 4,585,800.00 330,177.60
Paku biasa 2” – 5” kg 0.060 14,200.00 852.00
Meni besi liter 0.450 35,100.00 15,795.00
JUMLAH HARGA BAHAN 475,366.60

C JUMLAH (A+B) 520,810.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 520,810.60
F Jumlah Dibulatkan 520,810.00

A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.100 63,100.00 6,310.00
Tukang Kayu L.02 OH 0.100 85,100.00 8,510.00
Kepala Tukang Kayu L.03 OH 0.010 85,100.00 851.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 16,041.50
B BAHAN
Kayu balok 5/7 m³ 0.120 4,585,800.00 550,296.00
Paku 2”-3” kg 0.020 14,200.00 284.00
Kayu papan 2/20 m' 0.007 2,567,500.00 17,972.50
JUMLAH HARGA BAHAN 568,552.50

C JUMLAH (A+B) 584,594.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 584,594.00
F Jumlah Dibulatkan 584,594.00

A. 2.2.1.5. Pembuatan 1 m2 kantor sementara lantai plesteran


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 2.000 63,100.00 126,200.00
Tukang Kayu L.02 OH 2.000 85,100.00 170,200.00
Tukang batu L.02 OH 1.000 79,500.00 79,500.00
Kepala Tukang Kayu L.03 OH 0.300 85,100.00 25,530.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 405,135.00
B BAHAN
Dolken kayu φ 8-10/400 cm btg 1.250 48,000.00 60,000.00
Kayu m³ 0.180 5,492,100.00 988,578.00
Paku biasa kg 0.080 14,200.00 1,136.00
Besi strip kg 1.100 13,300.00 14,630.00
Semen Portland kg 35.000 1,100.00 38,500.00
Pasir pasang m³ 0.150 243,100.00 36,465.00
Pasir beton m³ 0.100 243,100.00 24,310.00
Koral beton m³ 0.150 308,500.00 46,275.00
Bata merah bh 30.000 1,000.00 30,000.00
Seng plat lbr 0.250 29,900.00 7,475.00
Jendela naco bh 0.200 - -
Kaca polos m² 0.080 139,000.00 11,120.00
Kunci tanam bh 0.150 85,900.00 12,885.00
Plywood 4mm lbr 0.060 68,700.00 4,122.00
JUMLAH HARGA BAHAN 1,275,496.00

C JUMLAH (A+B) 1,680,631.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 1,680,631.00
F Jumlah Dibulatkan 1,680,631.00
A. 2.2.1.9. Pembersihan 1 m2 lapangan dan perataan
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 66,805.00
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 66,805.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 66,805.00
F Jumlah Dibulatkan 66,805.00

A. 2.2.1.10. Pembuatan 1 m2 steger/perancah dari bambu


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Tukang Kayu L.02 OH 2.000 85,100.00 170,200.00
Kepala Tukang Kayu L.03 OH 0.200 85,100.00 17,020.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 254,025.00
B BAHAN
Bambu diameter 6-8/600 cm btg 1.250 27,400.00 34,250.00
Tali ijuk kg 0.186 - -
JUMLAH HARGA BAHAN 34,250.00

C JUMLAH (A+B) 288,275.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 288,275.00
F Jumlah Dibulatkan 288,275.00

A. 2.2.1.12. Pembuatan 1 m2 jalan sementara


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 63,470.50
B BAHAN
Batu belah m³ 0.150 260,600.00 39,090.00
Batu pecah (3/5 - 5/7 (pecah tangan) m³ 0.090 295,100.00 26,559.00
Pasir pasang m³ 0.010 243,100.00 2,431.00
JUMLAH HARGA BAHAN 68,080.00

C JUMLAH (A+B) 131,550.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 131,550.50
F Jumlah Dibulatkan 131,550.00

A. 2.2.1.13. Pembongkaran 1 m3 beton bertulang


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 13.334 63,100.00 841,375.40
Mandor L.04 OH 0.666 74,100.00 49,350.60
JUMLAH TENAGA KERJA 890,726.00
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 890,726.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 890,726.00
F Jumlah Dibulatkan 890,726.00

A. 2.2.1.14. Pembongkaran 1 m2 dinding tembok bata


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.667 63,100.00 42,068.77
Mandor L.04 OH 0.333 74,100.00 24,675.30
JUMLAH TENAGA KERJA 66,744.07
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 66,744.07


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 66,744.07
F Jumlah Dibulatkan 66,744.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.5630 63,100.00 35,525.30
Mandor L.04 OH 0.0563 74,100.00 4,171.83
JUMLAH TENAGA KERJA 39,697.13
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 39,697.13


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 39,697.13
F Jumlah Dibulatkan 39,697.00

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.6750 63,100.00 42,592.50
Mandor L.04 OH 0.0675 74,100.00 5,001.75
JUMLAH TENAGA KERJA 47,594.25
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 47,594.25


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 47,594.25
F Jumlah Dibulatkan 47,594.00

A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.7600 63,100.00 47,956.00
Mandor L.04 OH 0.0760 74,100.00 5,631.60
JUMLAH TENAGA KERJA 53,587.60
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 53,587.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 53,587.60
F Jumlah Dibulatkan 53,587.00
A.2.3.1.4. Menggali 1 m3 tanah keras sedalam 1 m
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Mandor L.04 OH 0.032 74,100.00 2,371.20
JUMLAH TENAGA KERJA 65,471.20
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 65,471.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 65,471.20
F Jumlah Dibulatkan 65,471.00

A.2.3.1.5. Menggali 1 m3 tanah cadas sedalam 1 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.500 63,100.00 94,650.00
Mandor L.04 OH 0.060 74,100.00 4,446.00
JUMLAH TENAGA KERJA 99,096.00
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 99,096.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 99,096.00
F Jumlah Dibulatkan 99,096.00

A.2.3.1.6. Menggali 1 m3 tanah lumpur sedalam 1 m


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.833 63,100.00 52,562.30
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 58,712.60
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 58,712.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 58,712.60
F Jumlah Dibulatkan 58,712.00

A.2.3.1.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.050 63,100.00 3,155.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 3,525.50
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 3,525.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 3,525.50
F Jumlah Dibulatkan 3,525.00

A.2.3.1.8. Pembuangan 1 m3 tanah sejauh 30 meter


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.330 63,100.00 20,823.00
Mandor L.04 OH 0.010 74,100.00 741.00
JUMLAH TENAGA KERJA 21,564.00
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 21,564.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 21,564.00
F Jumlah Dibulatkan 21,564.00
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.500 63,100.00 31,550.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 35,255.00
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 35,255.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 35,255.00
F Jumlah Dibulatkan 35,255.00

A.2.3.1.10. Pemadatan tanah 1 m3 tanah ( per 20 cm)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.500 63,100.00 31,550.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 35,255.00
B BAHAN
-
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 35,255.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 35,255.00
F Jumlah Dibulatkan 35,255.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 63,100.00 18,930.00
Mandor L.04 OH 0.010 74,100.00 741.00
JUMLAH TENAGA KERJA 19,671.00
B BAHAN
Pasir urug m³ 1.200 151,000.00 181,200.00
JUMLAH HARGA BAHAN 181,200.00

C JUMLAH (A+B) 200,871.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 200,871.00
F Jumlah Dibulatkan 200,871.00

A.2.3.1.11.B Pengurugan 1 m3 dengan pasir AYAK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 82,300.00 24,690.00
Mandor L.04 OH 0.010 112,500.00 1,125.00
JUMLAH TENAGA KERJA 25,815.00
B BAHAN
Pasir urug m³ 1.200 240,900.00 289,080.00
JUMLAH HARGA BAHAN 289,080.00

C JUMLAH (A+B) 314,895.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 314,895.00
F Jumlah Dibulatkan 314,895.00
F Jumlah Dibulatkan 314,895.00
A.2.3.1.14. Pengurugan 1 m3 sirtu
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.250 63,100.00 15,775.00
Mandor L.04 OH 0.025 74,100.00 1,852.50
JUMLAH TENAGA KERJA 17,627.50
B BAHAN
Sirtu m³ 1.200 224,400.00 269,280.00
JUMLAH HARGA BAHAN 269,280.00

C JUMLAH (A+B) 286,907.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 286,907.50
F Jumlah Dibulatkan 286,907.00

A.2.3.1.14.A Pengurugan 1 m3 tanah pilihan


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.250 109,800.00 27,450.00
Mandor L.04 OH 0.025 71,300.00 1,782.50
JUMLAH TENAGA KERJA 29,232.50
B BAHAN
Tanah urug pilihan m³ 1.200 67,800.00 81,360.00
JUMLAH HARGA BAHAN 81,360.00

C JUMLAH (A+B) 110,592.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 110,592.50
F Jumlah Dibulatkan 110,592.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.500 63,100.00 94,650.00
Tukang L.02 OH 0.750 79,500.00 59,625.00
Kepala Tukang L.03 OH 0.075 79,500.00 5,962.50
Mandor L.04 OH 0.075 74,100.00 5,557.50
JUMLAH TENAGA KERJA 165,795.00
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Semen Portlan kg 202.000 1,100.00 222,200.00
Pasir pasang m³ 0.485 243,100.00 117,903.50
JUMLAH HARGA BAHAN 652,823.50

C JUMLAH (A+B) 818,618.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 818,618.50
F Jumlah Dibulatkan 818,618.00

A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.500 63,100.00 94,650.00
Tukang L.02 OH 0.750 79,500.00 59,625.00
Kepala Tukang L.03 OH 0.075 79,500.00 5,962.50
Mandor L.04 OH 0.075 74,100.00 5,557.50
JUMLAH TENAGA KERJA 165,795.00
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Semen Portlan kg 163.000 1,100.00 179,300.00
Pasir pasang m³ 0.520 243,100.00 126,412.00
JUMLAH HARGA BAHAN 618,432.00

C JUMLAH (A+B) 784,227.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 784,227.00
F Jumlah Dibulatkan 784,227.00

A.3.2.1.3. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.500 63,100.00 94,650.00
Tukang L.02 OH 0.750 79,500.00 59,625.00
Kepala Tukang L.03 OH 0.075 79,500.00 5,962.50
Mandor L.04 OH 0.075 74,100.00 5,557.50
JUMLAH TENAGA KERJA 165,795.00
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Semen Portlan kg 136.000 1,100.00 149,600.00
Pasir pasang m³ 0.544 243,100.00 132,246.40
JUMLAH HARGA BAHAN 594,566.40

C JUMLAH (A+B) 760,361.40


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 760,361.40
F Jumlah Dibulatkan 760,361.00
A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.500 63,100.00 94,650.00
Tukang L.02 OH 0.750 79,500.00 59,625.00
Kepala Tukang L.03 OH 0.075 79,500.00 5,962.50
Mandor L.04 OH 0.075 74,100.00 5,557.50
JUMLAH TENAGA KERJA 165,795.00
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Semen Portlan kg 117.000 1,100.00 128,700.00
Pasir pasang m³ 0.561 243,100.00 136,379.10
JUMLAH HARGA BAHAN 577,799.10

C JUMLAH (A+B) 743,594.10


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 743,594.10
F Jumlah Dibulatkan 743,594.00

A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.780 63,100.00 49,218.00
Tukang L.02 OH 0.390 79,500.00 31,005.00
Kepala Tukang L.03 OH 0.039 79,500.00 3,100.50
Mandor L.04 OH 0.039 74,100.00 2,889.90
JUMLAH TENAGA KERJA 86,213.40
B BAHAN
Batu belah m³ 1.200 260,600.00 312,720.00
Pasir urug m³ 0.432 151,000.00 65,232.00
JUMLAH HARGA BAHAN 377,952.00

C JUMLAH (A+B) 464,165.40


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 464,165.40
F Jumlah Dibulatkan 464,165.00

A.3.2.1.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 3.400 63,100.00 214,540.00
Tukang L.02 OH 0.850 79,500.00 67,575.00
Kepala Tukang L.03 OH 0.085 79,500.00 6,757.50
Mandor L.04 OH 0.170 74,100.00 12,597.00
JUMLAH TENAGA KERJA 301,469.50
B BAHAN
Batu belah m³ 0.482 260,600.00 125,593.56
Semen portlan kg 194.000 1,100.00 213,400.00
Pasir beton m³ 0.312 243,100.00 75,847.20
Kerikil (Split 1-2 (pecah tangan)) m³ 0.468 308,500.00 144,378.00
Besi beton kg 126.000 9,700.00 1,222,200.00
Kawat beton kg 1.800 19,800.00 35,640.00
JUMLAH HARGA BAHAN 1,817,058.76

C JUMLAH (A+B) 2,118,528.26


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 2,118,528.26
F Jumlah Dibulatkan 2,118,528.00
A.3.2.1.11. Pemasangan 1 m3 pondasi sumuran, diameter 100 cm
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 2.400 63,100.00 151,440.00
Tukang L.02 OH 0.800 79,500.00 63,600.00
Kepala Tukang L.03 OH 0.080 79,500.00 6,360.00
Mandor L.04 OH 0.119 74,100.00 8,817.90
JUMLAH TENAGA KERJA 230,217.90
B BAHAN
Batu belah m³ 0.450 260,600.00 117,270.00
Semen portlan kg 194.000 1,100.00 213,400.00
Pasir beton m³ 0.312 243,100.00 75,847.20
Kerikil (Split 1-2 (pecah tangan)) m³ 0.468 308,500.00 144,378.00
JUMLAH HARGA BAHAN 550,895.20

C JUMLAH (A+B) 781,113.10


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 781,113.10
F Jumlah Dibulatkan 781,113.00

A.4.1.1 HARGA SATUAN PEKERJAAN BETON

A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 63,100.00 104,115.00
Tukang L.02 OH 0.275 79,500.00 21,862.50
Kepala Tukang L.03 OH 0.028 79,500.00 2,226.00
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 134,353.80
B BAHAN
Semen portlan kg 247.000 1,100.00 271,700.00
Pasir beton kg 869.000 173.64 150,895.64
Kerikil Maks 30mm (Split 1-2 (pecah tangan)) kg 999.000 228.52 228,290.00
Air liter 215.000 - -
JUMLAH HARGA BAHAN 650,885.64

C JUMLAH (A+B) 785,239.44


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 785,239.44
F Jumlah Dibulatkan 785,239.00

A.4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 63,100.00 104,115.00
Tukang L.02 OH 0.275 79,500.00 21,862.50
Kepala Tukang L.03 OH 0.028 79,500.00 2,226.00
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 134,353.80
B BAHAN
Semen portlan kg 276.000 1,100.00 303,600.00
Pasir beton kg 828.000 173.64 143,776.29
Kerikil Maks 30mm (Split 1-2 (pecah tangan)) kg 1,012.000 228.52 231,260.74
Air liter 215.000 - -
JUMLAH HARGA BAHAN 678,637.03

C JUMLAH (A+B) 812,990.83


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 812,990.83
F Jumlah Dibulatkan 812,990.00
A.4.1.1.3 Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 63,100.00 104,115.00
Tukang L.02 OH 0.275 79,500.00 21,862.50
Kepala Tukang L.03 OH 0.028 79,500.00 2,226.00
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 134,353.80
B BAHAN
Semen portlan kg 299.000 1,100.00 328,900.00
Pasir beton kg 799.000 173.64 138,740.64
Kerikil Maks 30mm (Split 1-2 (pecah tangan)) kg 1,017.000 228.52 232,403.33
Air liter 215.000 - -
JUMLAH HARGA BAHAN 700,043.98

C JUMLAH (A+B) 834,397.78


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 834,397.78
F Jumlah Dibulatkan 834,397.00
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.200 63,100.00 75,720.00
Tukang L.02 OH 0.200 79,500.00 15,900.00
Kepala Tukang L.03 OH 0.020 79,500.00 1,590.00
Mandor L.04 OH 0.060 74,100.00 4,446.00
JUMLAH TENAGA KERJA 97,656.00
B BAHAN
Semen portlan kg 230.000 1,100.00 253,000.00
Pasir beton kg 893.000 173.64 155,063.07
Kerikil Maks 30mm (Split 1-2 (pecah tangan)) kg 1,027.000 228.52 234,688.52
Air liter 200.000 - -
JUMLAH HARGA BAHAN 642,751.59

C JUMLAH (A+B) 740,407.59


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 740,407.59
F Jumlah Dibulatkan 740,407.00

A.4.1.1.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.600 63,100.00 100,960.00
Tukang L.02 OH 0.275 79,500.00 21,862.50
Kepala Tukang L.03 OH 0.028 79,500.00 2,226.00
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 131,198.80
B BAHAN
Semen portlan kg 326.000 1,100.00 358,600.00
Pasir beton kg 760.000 173.64 131,968.57
Kerikil Maks 30mm (Split 1-2 (pecah tangan)) kg 1,029.000 228.52 235,145.56
Air liter 215.000 - -
JUMLAH HARGA BAHAN 725,714.13

C JUMLAH (A+B) 856,912.93


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 856,912.93
F Jumlah Dibulatkan 856,912.00

A.4.1.1.6 Membuat 1 m³ beton mutu f’c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 63,100.00 104,115.00
Tukang L.02 OH 0.275 79,500.00 21,862.50
Kepala Tukang L.03 OH 0.028 79,500.00 2,226.00
Mandor L.04 OH 0.083 74,100.00 6,150.30
JUMLAH TENAGA KERJA 134,353.80
B BAHAN
Semen portlan kg 352.000 1,100.00 387,200.00
Pasir beton kg 731.000 173.64 126,932.93
Kerikil Maks 30mm (Split 1-2 (pecah tangan)) kg 1,031.000 228.52 235,602.59
Air liter 215.000 - -
JUMLAH HARGA BAHAN 749,735.52

C JUMLAH (A+B) 884,089.32


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 884,089.32
F Jumlah Dibulatkan 884,089.00
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.070 63,100.00 4,417.00
Tukang L.02 OH 0.070 79,500.00 5,565.00
Kepala Tukang L.03 OH 0.007 79,500.00 556.50
Mandor L.04 OH 0.004 74,100.00 296.40
JUMLAH TENAGA KERJA 10,834.90
B BAHAN
Besi beton (polos/ulir) kg 10.500 9,700.00 101,850.00
Kawat beton kg 0.150 19,800.00 2,970.00
JUMLAH HARGA BAHAN 104,820.00

C JUMLAH (A+B) 115,654.90


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 115,654.90
F Harga Satuan Pekerjaan per Kg (E/10) 11,565.49
G Jumlah Dibulatkan 11,565.00

A.4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.520 63,100.00 32,812.00
Tukang L.02 OH 0.260 79,500.00 20,670.00
Kepala Tukang L.03 OH 0.026 79,500.00 2,067.00
Mandor L.04 OH 0.026 74,100.00 1,926.60
JUMLAH TENAGA KERJA 57,475.60
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.040 2,567,500.00 102,700.00
Paku 5 - 10 cm kg 0.300 14,200.00 4,260.00
Minyak bekisting (oli bekas) liter 0.100 5,400.00 540.00
JUMLAH HARGA BAHAN 107,500.00

C JUMLAH (A+B) 164,975.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 164,975.60
F Harga Sewa Bekisting = (0,5xE) 82,487.80
G Jumlah Dibulatkan 82,487.00

A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.520 63,100.00 32,812.00
Tukang L.02 OH 0.260 79,500.00 20,670.00
Kepala Tukang L.03 OH 0.026 85,100.00 2,212.60
Mandor L.04 OH 0.026 74,100.00 1,926.60
JUMLAH TENAGA KERJA 57,621.20
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.045 2,567,500.00 115,537.50
Paku 5 - 10 cm kg 0.300 14,200.00 4,260.00
Minyak bekisting (oli bekas) liter 0.100 5,400.00 540.00
JUMLAH HARGA BAHAN 120,337.50

C JUMLAH (A+B) 177,958.70


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 177,958.70
F Harga Sewa Bekisting = (0,5xE) 88,979.35
G Jumlah Dibulatkan 88,979.00
A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 63,100.00 41,646.00
Tukang L.02 OH 0.330 79,500.00 26,235.00
Kepala Tukang L.03 OH 0.033 79,500.00 2,623.50
Mandor L.04 OH 0.033 74,100.00 2,445.30
JUMLAH TENAGA KERJA 72,949.80
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.040 2,567,500.00 102,700.00
Paku 5 - 10 cm kg 0.400 14,200.00 5,680.00
Minyak bekisting (oli bekas) liter 0.200 5,400.00 1,080.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.015 4,585,800.00 68,787.00
Plywood tebal 9 mm lbr 0.350 136,100.00 47,635.00
Dolken kayu φ 8-10cm – panj. 4 m btg 2.000 48,000.00 96,000.00
JUMLAH HARGA BAHAN 321,882.00

C JUMLAH (A+B) 394,831.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 394,831.80
F Harga Sewa Bekisting = (0,5xE) 197,415.90
G Jumlah Dibulatkan 197,415.00

A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 63,100.00 41,646.00
Tukang L.02 OH 0.330 79,500.00 26,235.00
Kepala Tukang L.03 OH 0.033 79,500.00 2,623.50
Mandor L.04 OH 0.033 74,100.00 2,445.30
JUMLAH TENAGA KERJA 72,949.80
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.040 2,567,500.00 102,700.00
Paku 5 - 10 cm kg 0.400 14,200.00 5,680.00
Minyak bekisting (oli bekas) liter 0.200 5,400.00 1,080.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.018 4,585,800.00 82,544.40
Plywood tebal 9 mm lbr 0.350 136,100.00 47,635.00
Dolken kayu φ 8-10cm – panj. 4 m btg 2.000 48,000.00 96,000.00
JUMLAH HARGA BAHAN 335,639.40

C JUMLAH (A+B) 408,589.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 408,589.20
F Harga Sewa Bekisting = (0,5xE) 204,294.60
G Jumlah Dibulatkan 204,294.00

A.4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 63,100.00 41,646.00
Tukang L.02 OH 0.330 79,500.00 26,235.00
Kepala Tukang L.03 OH 0.033 79,500.00 2,623.50
Mandor L.04 OH 0.033 74,100.00 2,445.30
JUMLAH TENAGA KERJA 72,949.80
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.040 2,567,500.00 102,700.00
Paku 5 - 10 cm kg 0.400 14,200.00 5,680.00
Minyak bekisting (oli bekas) liter 0.200 5,400.00 1,080.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.015 4,585,800.00 68,787.00
Plywood tebal 9 mm lbr 0.350 136,100.00 47,635.00
Dolken kayu φ 8-10cm – panj. 4 m btg 6.000 48,000.00 288,000.00
JUMLAH HARGA BAHAN 513,882.00

C JUMLAH (A+B) 586,831.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 586,831.80
F Harga Sewa Bekisting = (0,5xE) 293,415.90
G Jumlah Dibulatkan 293,415.00
A.4.1.1.25 Pemasangan 1 m2 bekisting untuk dinding
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 63,100.00 41,646.00
Tukang L.02 OH 0.330 79,500.00 26,235.00
Kepala Tukang L.03 OH 0.033 79,500.00 2,623.50
Mandor L.04 OH 0.033 74,100.00 2,445.30
JUMLAH TENAGA KERJA 72,949.80
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.030 2,567,500.00 77,025.00
Paku 5 - 10 cm kg 0.400 14,200.00 5,680.00
Minyak bekisting (oli bekas) liter 0.200 5,400.00 1,080.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.020 4,585,800.00 91,716.00
Plywood tebal 9 mm lbr 0.350 136,100.00 47,635.00
Dolken kayu φ 8-10cm – panj. 4 m btg 3.000 48,000.00 144,000.00
Penjaga jarak bekisting/spacer bh 4.000 - -
JUMLAH HARGA BAHAN 367,136.00

C JUMLAH (A+B) 440,085.80


D Overhead & Profit 66,012.87
E Harga Satuan Pekerjaan (C+D) 506,098.67
F Harga Sewa Bekisting = (0,5xE) 253,049.34
G Jumlah Dibulatkan 253,049.00

A.4.1.1.26 Pemasangan 1 m2 bekisting untuk tangga


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.660 63,100.00 41,646.00
Tukang L.02 OH 0.330 79,500.00 26,235.00
Kepala Tukang L.03 OH 0.033 79,500.00 2,623.50
Mandor L.04 OH 0.033 74,100.00 2,445.30
JUMLAH TENAGA KERJA 72,949.80
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.030 2,567,500.00 77,025.00
Paku 5 - 10 cm kg 0.400 14,200.00 5,680.00
Minyak bekisting (oli bekas) liter 0.200 5,400.00 1,080.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.020 4,585,800.00 91,716.00
Plywood tebal 9 mm lbr 0.350 136,100.00 47,635.00
Dolken kayu φ 8-10cm – panj. 4 m btg 2.000 48,000.00 96,000.00
JUMLAH HARGA BAHAN 319,136.00

C JUMLAH (A+B) 392,085.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 392,085.80
F Harga Sewa Bekisting = (0,5xE)
G Jumlah Dibulatkan 392,085.00

A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.150 63,100.00 9,465.00
Tukang L.02 OH 0.050 79,500.00 3,975.00
Kepala Tukang L.03 OH 0.005 79,500.00 397.50
Mandor L.04 OH 0.008 74,100.00 592.80
JUMLAH TENAGA KERJA 14,430.30
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.0264 2,567,500.00 67,782.00
Paku 5 - 10 cm kg 0.600 14,200.00 8,520.00
Dolken kayu φ 8-10cm – panj. 4 m btg 0.500 48,000.00 24,000.00
JUMLAH HARGA BAHAN 100,302.00

C JUMLAH (A+B) 114,732.30


D Overhead & Profit 17,209.85
E Harga Satuan Pekerjaan (C+D) 131,942.15
F Harga Sewa Bekisting = (0,5xE) 65,971.07
G Jumlah Dibulatkan 65,971.00
A.4.1.1.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 5.300 63,100.00 334,430.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.300 79,500.00 103,350.00
Tukang besi L.02 OH 1.050 79,500.00 83,475.00
Kepala Tukang L.03 OH 0.262 79,500.00 20,829.00
Mandor L.04 OH 0.265 74,100.00 19,636.50
JUMLAH TENAGA KERJA 583,583.00
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.200 2,567,500.00 513,500.00
Paku 5 - 10 cm kg 1.500 14,200.00 21,300.00
Minyak bekisting (oli bekas) liter 0.400 5,400.00 2,160.00
Besi beton polos kg 157.500 9,700.00 1,527,750.00
Kawat beton kg 2.250 19,800.00 44,550.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 308,500.00 249,885.00
JUMLAH HARGA BAHAN 2,860,019.00

C JUMLAH (A+B) 3,443,602.00


D Overhead & Profit 516,540.30
E Harga Satuan Pekerjaan (C+D) 3,960,142.30
F Jumlah Dibulatkan 3,960,142.00

A.4.1.1.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 5.300 63,100.00 334,430.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.560 79,500.00 124,020.00
Tukang besi L.02 OH 1.400 79,500.00 111,300.00
Kepala Tukang L.03 OH 0.323 79,500.00 25,678.50
Mandor L.04 OH 0.283 74,100.00 20,970.30
JUMLAH TENAGA KERJA 638,261.30
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.270 2,567,500.00 693,225.00
Paku 5 - 10 cm kg 2.000 14,200.00 28,400.00
Minyak bekisting (oli bekas) liter 0.600 5,400.00 3,240.00
Besi beton polos kg 210.000 9,700.00 2,037,000.00
Kawat beton kg 3.000 19,800.00 59,400.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 308,500.00 249,885.00
JUMLAH HARGA BAHAN 3,572,024.00

C JUMLAH (A+B) 4,210,285.30


D Overhead & Profit 631,542.80
E Harga Satuan Pekerjaan (C+D) 4,841,828.10
F Jumlah Dibulatkan 4,841,828.00

A.4.1.1.30 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 7.050 63,100.00 444,855.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.650 79,500.00 131,175.00
Tukang besi L.02 OH 2.100 79,500.00 166,950.00
Kepala Tukang L.03 OH 0.403 79,500.00 32,038.50
Mandor L.04 OH 0.353 74,100.00 26,157.30
JUMLAH TENAGA KERJA 823,038.30
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.400 2,567,500.00 1,027,000.00
Paku 5 - 10 cm kg 4.000 14,200.00 56,800.00
Minyak bekisting (oli bekas) liter 2.000 5,400.00 10,800.00
Besi beton polos kg 315.000 9,700.00 3,055,500.00
Kawat beton kg 4.500 19,800.00 89,100.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 308,500.00 249,885.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.150 4,585,800.00 687,870.00
Plywood tebal 9 mm lbr 3.500 136,100.00 476,350.00
Dolken kayu φ 8-10cm – panj. 4 m btg 20.000 48,000.00 960,000.00
JUMLAH HARGA BAHAN 7,114,179.00

C JUMLAH (A+B) 7,937,217.30


D Overhead & Profit 1,190,582.60
E Harga Satuan Pekerjaan (C+D) 9,127,799.90
F Jumlah Dibulatkan 9,127,799.00
A.4.1.1.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 6.350 63,100.00 400,685.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.650 79,500.00 131,175.00
Tukang besi L.02 OH 1.400 79,500.00 111,300.00
Kepala Tukang L.03 OH 0.333 79,500.00 26,473.50
Mandor L.04 OH 0.318 74,100.00 23,563.80
JUMLAH TENAGA KERJA 715,059.80
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.320 2,567,500.00 821,600.00
Paku 5 - 10 cm kg 3.200 14,200.00 45,440.00
Minyak bekisting (oli bekas) liter 1.600 5,400.00 8,640.00
Besi beton polos kg 210.000 9,700.00 2,037,000.00
Kawat beton kg 3.000 19,800.00 59,400.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 9,700.00 7,857.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.140 4,585,800.00 642,012.00
Plywood tebal 9 mm lbr 2.800 136,100.00 381,080.00
Dolken kayu φ 8-10cm – panj. 4 m btg 16.000 48,000.00 768,000.00
JUMLAH HARGA BAHAN 5,271,903.00

C JUMLAH (A+B) 5,986,962.80


D Overhead & Profit 898,044.42
E Harga Satuan Pekerjaan (C+D) 6,885,007.22
F Jumlah Dibulatkan 6,885,007.00

A.4.1.1.32 Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 5.300 63,100.00 334,430.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.300 79,500.00 103,350.00
Tukang besi L.02 OH 1.050 79,500.00 83,475.00
Kepala Tukang L.03 OH 0.265 79,500.00 21,067.50
Mandor L.04 OH 0.265 74,100.00 19,636.50
JUMLAH TENAGA KERJA 583,821.50
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.320 2,567,500.00 821,600.00
Paku 5 - 10 cm kg 3.200 14,200.00 45,440.00
Minyak bekisting (oli bekas) liter 1.600 5,400.00 8,640.00
Besi beton polos kg 157.500 9,700.00 1,527,750.00
Kawat beton kg 2.250 19,800.00 44,550.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 308,500.00 249,885.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.120 4,585,800.00 550,296.00
Plywood tebal 9 mm lbr 2.800 136,100.00 381,080.00
Dolken kayu φ 8-10cm – panj. 4 m btg 32.000 48,000.00 1,536,000.00
JUMLAH HARGA BAHAN 5,666,115.00

C JUMLAH (A+B) 6,249,936.50


D Overhead & Profit 937,490.48
E Harga Satuan Pekerjaan (C+D) 7,187,426.98
F Jumlah Dibulatkan 7,187,426.00

A.4.1.1.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 5.300 63,100.00 334,430.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.300 79,500.00 103,350.00
Tukang besi L.02 OH 1.050 79,500.00 83,475.00
Kepala Tukang L.03 OH 0.262 79,500.00 20,829.00
Mandor L.04 OH 0.265 74,100.00 19,636.50
JUMLAH TENAGA KERJA 583,583.00
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.240 2,567,500.00 616,200.00
Paku 5 - 10 cm kg 3.200 14,200.00 45,440.00
Minyak bekisting (oli bekas) liter 1.600 5,400.00 8,640.00
Besi beton polos kg 157.500 9,700.00 1,527,750.00
Kawat beton kg 2.250 19,800.00 44,550.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 308,500.00 249,885.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.160 4,585,800.00 733,728.00
Plywood tebal 9 mm lbr 2.800 136,100.00 381,080.00
Dolken kayu φ 8-10cm – panj. 4 m btg 24.000 48,000.00 1,152,000.00
JUMLAH HARGA BAHAN 5,260,147.00

C JUMLAH (A+B) 5,843,730.00


D Overhead & Profit 876,559.50
E Harga Satuan Pekerjaan (C+D) 6,720,289.50
F Jumlah Dibulatkan 6,720,289.00

A.4.1.1.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 5.300 63,100.00 334,430.00
Tukang batu L.02 OH 0.275 79,500.00 21,862.50
Tukang kayu L.02 OH 1.560 85,100.00 132,756.00
Tukang besi L.02 OH 1.400 85,100.00 119,140.00
Kepala Tukang L.03 OH 0.323 85,100.00 27,487.30
Mandor L.04 OH 0.283 74,100.00 20,970.30
JUMLAH TENAGA KERJA 656,646.10
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.250 2,567,500.00 641,875.00
Paku 5 - 10 cm kg 3.000 14,200.00 42,600.00
Minyak bekisting (oli bekas) liter 1.200 5,400.00 6,480.00
Besi beton polos kg 210.000 9,700.00 2,037,000.00
Kawat beton kg 3.000 19,800.00 59,400.00
Semen portland kg 336.000 1,100.00 369,600.00
Pasir beton m³ 0.540 243,100.00 131,274.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.810 308,500.00 249,885.00
Balok kayu kelas II Usuk ky. Meranti Batu ( Ikat ) m³ 0.105 4,585,800.00 481,509.00
Plywood tebal 9 mm lbr 2.500 136,100.00 340,250.00
Dolken kayu φ 8-10cm – panj. 4 m btg 14.000 48,000.00 672,000.00
JUMLAH HARGA BAHAN 5,031,873.00

C JUMLAH (A+B) 5,688,519.10


D Overhead & Profit 853,277.87
E Harga Satuan Pekerjaan (C+D) 6,541,796.97
F Jumlah Dibulatkan 6,541,796.00

A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.180 63,100.00 11,358.00
Tukang batu L.02 OH 0.020 79,500.00 1,590.00
Tukang kayu L.02 OH 0.020 79,500.00 1,590.00
Tukang besi L.02 OH 0.020 79,500.00 1,590.00
Kepala Tukang L.03 OH 0.006 79,500.00 477.00
Mandor L.04 OH 0.009 74,100.00 666.90
JUMLAH TENAGA KERJA 17,271.90
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.002 2,567,500.00 5,135.00
Paku 5 - 10 cm kg 0.010 14,200.00 142.00
Besi beton polos kg 3.000 9,700.00 29,100.00
Kawat beton kg 0.450 19,800.00 8,910.00
Semen portland kg 4.000 1,100.00 4,400.00
Pasir beton m³ 0.006 243,100.00 1,458.60
Kerikil (Split 1-2 (pecah tangan)) m³ 0.009 308,500.00 2,776.50
JUMLAH HARGA BAHAN 51,922.10

C JUMLAH (A+B) 69,194.00


D Overhead & Profit 10,379.10
E Harga Satuan Pekerjaan (C+D) 79,573.10
F Jumlah Dibulatkan 79,573.00

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.297 63,100.00 18,740.70
Tukang batu L.02 OH 0.033 79,500.00 2,623.50
Tukang kayu L.02 OH 0.033 85,100.00 2,808.30
Tukang besi L.02 OH 0.033 85,100.00 2,808.30
Kepala Tukang L.03 OH 0.010 85,100.00 851.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 28,943.30
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.003 2,567,500.00 7,702.50
Paku 5 - 10 cm kg 0.020 14,200.00 284.00
Besi beton polos kg 3.600 9,700.00 34,920.00
Kawat beton kg 0.050 19,800.00 990.00
Semen portland kg 5.500 1,100.00 6,050.00
Pasir beton m³ 0.009 243,100.00 2,187.90
Kerikil (Split 1-2 (pecah tangan)) m³ 0.015 308,500.00 4,627.50
JUMLAH HARGA BAHAN 56,761.90

C JUMLAH (A+B) 85,705.20


D Overhead & Profit 12,855.78
E Harga Satuan Pekerjaan (C+D) 98,560.98
F Jumlah Dibulatkan 98,560.00
A026 I Membuat 1 m’ sloof beton bertulang (15 x 20) cm
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.131 63,100.00 8,266.10
Tukang batu L.02 OH 0.008 79,500.00 596.25
Tukang kayu L.02 OH 0.046 85,100.00 3,914.60
Tukang besi L.02 OH 0.029 85,100.00 2,467.90
Kepala Tukang L.03 OH 0.008 85,100.00 706.33
Mandor L.04 OH 0.004 74,100.00 296.40
JUMLAH TENAGA KERJA 16,247.58
B BAHAN
Kayu kelas III Papan Cetak (kayu pinus) uk 2 x 20 x 200 m³ 0.004 2,567,500.00 10,270.00
Paku 5 - 10 cm kg 0.026 14,200.00 369.20
Besi beton polos kg 4.320 9,700.00 41,904.00
Kawat beton kg 0.062 19,800.00 1,227.60
Semen portland zak 0.194 55,000.00 10,670.00
Pasir beton m³ 0.016 243,100.00 3,889.60
Kerikil (Split 1-2 (pecah tangan)) m³ 0.023 308,500.00 7,095.50
JUMLAH HARGA BAHAN 75,425.90

C JUMLAH (A+B) 91,673.48


D Overhead & Profit 13,751.02
E Harga Satuan Pekerjaan (C+D) 105,424.50
F Jumlah Dibulatkan 105,424.00
A.4.1.1.38 Membuat 1 m3 beton tumbuk 1PC : 3PS : 5KR
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 63,100.00 104,115.00
Tukang batu L.02 OH 0.250 79,500.00 19,875.00
Kepala Tukang Batu L.03 OH 0.025 79,500.00 1,987.50
Mandor L.04 OH 0.080 74,100.00 5,928.00
JUMLAH TENAGA KERJA 131,905.50
B BAHAN
Semen portland zak 4.360 55,000.00 239,800.00
Pasir beton m³ 0.520 243,100.00 126,412.00
Kerikil (Split 1-2 (pecah tangan)) m³ 0.870 308,500.00 268,395.00
JUMLAH HARGA BAHAN 634,607.00

C JUMLAH (A+B) 766,512.50


D Overhead & Profit 114,976.88
E Harga Satuan Pekerjaan (C+D) 881,489.38
F Jumlah Dibulatkan 881,489.00

B.22 1 m2 bekisting untuk permukaan beton biasa dengan papan ukuran 2/20 cm (tanpa perancah)
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.220 63,100.00 13,882.00
Tukang Kayu L.02 OH 0.660 85,100.00 56,166.00
Kepala Tukang L.03 OH 0.066 85,100.00 5,616.60
Mandor L.04 OH 0.022 74,100.00 1,630.20
JUMLAH TENAGA KERJA 77,294.80
B BAHAN
Papan 2/20 cm kayu kelas III m³ 0.040 2,567,500.00 102,700.00
Kaso 5/7 cm m³ 0.020 5,464,600.00 109,292.00
Paku 5 cm dan 7 cm kg 0.400 14,200.00 5,680.00
Minyak Bekisting liter 0.200 5,400.00 1,080.00
JUMLAH HARGA BAHAN 218,752.00

C JUMLAH (A+B) 296,046.80


D Overhead & Profit 44,407.02
E Harga Satuan Pekerjaan (C+D) 340,453.82
F Harga Sewa Bekisting = (0,5xE) 170,226.91
F Jumlah Dibulatkan 170,226.00

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.1. Pemasangan 1 kg besi profil


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.060 63,100.00 3,786.00
Tukang las konstruksi L.03 OH 0.060 79,500.00 4,770.00
Kepala tukang L.03 OH 0.060 79,500.00 4,770.00
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 13,548.30
B BAHAN
Besi profil kg 1.150 11,500.00 13,225.00
JUMLAH HARGA BAHAN 13,225.00

C JUMLAH (A+B) 26,773.30


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 26,773.30
F Jumlah Dibulatkan 26,773.00
A.4.2.1.2. Pemasangan 1 kg rangka kuda-kuda baja IWF
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.060 63,100.00 3,786.00
Tukang las konstruksi L.03 OH 0.060 79,500.00 4,770.00
Kepala tukang L.03 OH 0.060 79,500.00 4,770.00
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 13,548.30
B BAHAN
Besi IWF kg 1.150 13,800.00 15,870.00
JUMLAH HARGA BAHAN 15,870.00

C JUMLAH (A+B) 29,418.30


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 29,418.30
F Jumlah Dibulatkan 29,418.00

A.4.2.1.3. Pengerjaan 100 kg pekerjaan perakitan


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.100 63,100.00 6,310.00
Tukang las konstruksi L.03 OH 0.100 79,500.00 7,950.00
Kepala tukang L.03 OH 0.001 79,500.00 79.50
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 14,710.00
B BAHAN
Solar liter 1.000 6,700.00 6,700.00
Minyak pelumas liter 0.100 26,300.00 2,630.00
JUMLAH HARGA BAHAN 9,330.00

C PERALATAN
Sewa alat jam 0.080 -
JUMLAH HARGA ALAT -

C JUMLAH (A+B) 24,040.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 24,040.00
F Harga 1 kg= (E/100) 240.40
F Jumlah Dibulatkan 240.00

A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.040 63,100.00 2,524.00
Tukang besi konstruksi L.03 OH 0.020 79,500.00 1,590.00
Kepala tukang L.03 OH 0.002 79,500.00 159.00
Mandor L.04 OH 0.002 74,100.00 148.20
JUMLAH TENAGA KERJA 4,421.20
B BAHAN
Kawat las listrik kg 0.400 25,400.00 10,160.00
Solar liter 0.300 6,700.00 2,010.00
Minyak pelumas liter 0.040 26,300.00 1,052.00
JUMLAH HARGA BAHAN 13,222.00

C PERALATAN
Sewa alat jam 0.170 33,000.00 5,610.00
JUMLAH HARGA ALAT 5,610.00

C JUMLAH (A+B) 23,253.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 23,253.20
F Harga 1 cm = (E/10) 2,325.32
F Jumlah Dibulatkan 2,325.00
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 63,100.00 18,930.00
Tukang batu L.02 OH 0.100 79,500.00 7,950.00
Kepala tukang L.03 OH 0.010 79,500.00 795.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 28,786.50
B BAHAN
Bata merah buah 70.000 1,000.00 70,000.00
Semen portan kg 11.500 1,100.00 12,650.00
Pasir pasang m³ 0.043 243,100.00 10,453.30
JUMLAH HARGA BAHAN 93,103.30

C JUMLAH (A+B) 121,889.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 121,889.80
F Jumlah Dibulatkan 121,889.00

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm (termasuk acian)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.300 63,100.00 18,930.00
Tukang batu L.02 OH 0.150 79,500.00 11,925.00
Kepala tukang L.03 OH 0.015 79,500.00 1,192.50
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 33,159.00
B BAHAN
Semen portlan kg 6.240 1,100.00 6,864.00
Pasir pasang m³ 0.024 243,100.00 5,834.40
JUMLAH HARGA BAHAN 12,698.40

C JUMLAH (A+B) 45,857.40


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 45,857.40
F Jumlah Dibulatkan 45,857.00

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.35. Pemasangan 1 m² lantai keramik ukuran 30 cm x 30 cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.700 63,100.00 44,170.00
Tukang Batu L.02 OH 0.350 79,500.00 27,825.00
Kepala Tukang L.03 OH 0.035 79,500.00 2,782.50
Mandor L.04 OH 0.035 74,100.00 2,593.50
JUMLAH TENAGA KERJA 77,371.00
B BAHAN
Ubin keramik bh 11.870 3,841.62 45,600.00
Semen Portland kg 10.000 1,100.00 11,000.00
Pasir Pasang m³ 0.045 243,100.00 10,939.50
Semen warna kg 1.500 1,750.00 2,625.00
JUMLAH HARGA BAHAN 70,164.50

C JUMLAH (A+B) 147,535.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 147,535.50
F Jumlah Dibulatkan 147,535.00

A.4.4.3.36. Pemasangan 1m² lantai keramik ukuran 20 cm x 20 cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.700 63,100.00 44,170.00
Tukang Batu L.02 OH 0.350 79,500.00 27,825.00
Kepala Tukang L.03 OH 0.035 79,500.00 2,782.50
Mandor L.04 OH 0.035 74,100.00 2,593.50
JUMLAH TENAGA KERJA 77,371.00
B BAHAN
Ubin keramik bh 26.500 2,264.15 60,000.00
Semen Portland kg 10.400 1,100.00 11,440.00
Pasir Pasang m³ 0.045 243,100.00 10,939.50
Semen warna kg 1.620 1,750.00 2,835.00
JUMLAH HARGA BAHAN 85,214.50

C JUMLAH (A+B) 162,585.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 162,585.50
F Jumlah Dibulatkan 162,585.00

A.4.4.3.36.b Pemasangan 1m² lantai Granit unpolish (40 cm x 40cm)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.700 63,100.00 44,170.00
Tukang Batu L.02 OH 0.350 79,500.00 27,825.00
Kepala Tukang L.03 OH 0.035 79,500.00 2,782.50
Mandor L.04 OH 0.035 74,100.00 2,593.50
JUMLAH TENAGA KERJA 77,371.00
B BAHAN
Ubin keramik m2 1.000 210,000.00 210,000.00
Semen Portland kg 10.400 1,100.00 11,440.00
Pasir Pasang m³ 0.045 243,100.00 10,939.50
Semen warna kg 1.620 1,750.00 2,835.00
JUMLAH HARGA BAHAN 235,214.50

C JUMLAH (A+B) 312,585.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 312,585.50
F Jumlah Dibulatkan 312,585.00
A.4.4.3.54. Pemasangan 1 m² dinding keramik 20 cm x 20 cm
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.900 63,100.00 56,790.00
Tukang Batu L.02 OH 0.450 79,500.00 35,775.00
Kepala Tukang L.03 OH 0.045 79,500.00 3,577.50
Mandor L.04 OH 0.045 74,100.00 3,334.50
JUMLAH TENAGA KERJA 99,477.00
B BAHAN
Keramik artistik bh 26.500 2,049.06 54,300.00
Semen Portland kg 9.300 1,100.00 10,230.00
Pasir Pasang m³ 0.018 243,100.00 4,375.80
Semen warna kg 1.940 1,750.00 3,395.00
JUMLAH HARGA BAHAN 72,300.80

C JUMLAH (A+B) 171,777.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 171,777.80
F Jumlah Dibulatkan 171,777.00

A.4.4.3.54.b Pemasangan 1 m² dinding Granit 60 cm x 60 cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.900 63,100.00 56,790.00
Tukang Batu L.02 OH 0.450 79,500.00 35,775.00
Kepala Tukang L.03 OH 0.045 79,500.00 3,577.50
Mandor L.04 OH 0.045 74,100.00 3,334.50
JUMLAH TENAGA KERJA 99,477.00
B BAHAN
Granit dinding m2 1.000 250,000.00 250,000.00
Semen Portland kg 9.300 1,100.00 10,230.00
Pasir Pasang m³ 0.018 243,100.00 4,375.80
Semen warna kg 1.940 1,750.00 3,395.00
JUMLAH HARGA BAHAN 268,000.80

C JUMLAH (A+B) 367,477.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 367,477.80
F Jumlah Dibulatkan 367,477.00
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.3. Pemasangan 1 m² atap genteng palentong besar / super


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.150 63,100.00 9,465.00
Tukang Kayu L.02 OH 0.075 85,100.00 6,382.50
Kepala Tukang L.03 OH 0.008 85,100.00 638.25
Mandor L.04 OH 0.008 74,100.00 592.80
JUMLAH TENAGA KERJA 17,078.55
B BAHAN
Genteng palentong bh 12.000 3,360.00 40,320.00
JUMLAH HARGA BAHAN 40,320.00

C JUMLAH (A+B) 57,398.55


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 57,398.55
F Jumlah Dibulatkan 57,398.00

A.4.5.2.4. Pemasangan 1 m' bubung genteng palentong


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.400 63,100.00 25,240.00
Tukang Kayu L.02 OH 0.200 85,100.00 17,020.00
Kepala Tukang L.03 OH 0.020 85,100.00 1,702.00
Mandor L.04 OH 0.002 74,100.00 148.20
JUMLAH TENAGA KERJA 44,110.20
B BAHAN
Genteng bubung bh 5.000 6,400.00 32,000.00
Semen Portland kg 8.000 1,100.00 8,800.00
Pasir Pasang m³ 0.032 243,100.00 7,779.20
JUMLAH HARGA BAHAN 48,579.20

C JUMLAH (A+B) 92,689.40


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 92,689.40
F Jumlah Dibulatkan 92,689.00

A.4.5.2.6. Pemasangan 1 m' bubung genteng palentong besar


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.400 63,100.00 25,240.00
Tukang Kayu L.02 OH 0.200 85,100.00 17,020.00
Kepala Tukang L.03 OH 0.020 85,100.00 1,702.00
Mandor L.04 OH 0.002 74,100.00 148.20
JUMLAH TENAGA KERJA 44,110.20
B BAHAN
Genteng bubung bh 4.000 7,200.00 28,800.00
Semen Portland kg 8.000 1,100.00 8,800.00
Pasir Pasang m³ 0.032 243,100.00 7,779.20
JUMLAH HARGA BAHAN 45,379.20

C JUMLAH (A+B) 89,489.40


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 89,489.40
F Jumlah Dibulatkan 89,489.00

A.4.6.1.16. Pemasangan 1 m 2 rangka atap genteng keramik, kayu kelas II


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.100 63,100.00 6,310.00
Tukang Kayu L.02 OH 0.100 85,100.00 8,510.00
Kepala Tukang L.03 OH 0.010 85,100.00 851.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 16,041.50
B BAHAN
Kaso-kaso 5 x 7 cm Usuk ky. Kempas m3 0.014 6,151,100.00 86,115.40
Reng 2 x 3 cm Kayu reng 2/3 Meranti Batu m3 0.036 4,668,200.00 168,055.20
Paku 5 dan 10 cm kg 0.250 14,200.00 3,550.00
JUMLAH HARGA BAHAN 257,720.60

C JUMLAH (A+B) 273,762.10


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 273,762.10
F Jumlah Dibulatkan 273,762.00
A.4.6.1.17. Pemasangan 1 m 2 rangka atap genteng beton, kayu kelas II
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.100 63,100.00 6,310.00
Tukang Kayu L.02 OH 0.100 85,100.00 8,510.00
Kepala Tukang L.03 OH 0.010 85,100.00 851.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 16,041.50
B BAHAN
Kaso-kaso 5 x 7 cm Usuk ky. Kempas m3 0.014 6,151,100.00 86,115.40
Reng 3 x 4 cm Kayu reng 3/4 Meranti Batu m3 0.057 4,723,200.00 269,222.40
Paku 5 dan 10 cm kg 0.250 14,200.00 3,550.00
JUMLAH HARGA BAHAN 358,887.80

C JUMLAH (A+B) 374,929.30


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 374,929.30
F Jumlah Dibulatkan 374,929.00

A.4.7.1.10. Pengecatan 1 m 2 tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.020 63,100.00 1,262.00
Tukang Cat L.02 OH 0.063 79,500.00 5,008.50
Kepala Tukang L.03 OH 0.006 79,500.00 500.85
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 6,993.65
B BAHAN
Plamuur kg 0.100 20,200.00 2,020.00
Cat dasar kg 0.100 28,600.00 2,860.00
Cat penutup kg 0.260 28,600.00 7,436.00
JUMLAH HARGA BAHAN 12,316.00

C JUMLAH (A+B) 19,309.65


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 19,309.65
F Jumlah Dibulatkan 19,309.00

A.4.7.1.11. Pengecatan 1 m 2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.028 63,100.00 1,766.80
Tukang Cat L.02 OH 0.042 79,500.00 3,339.00
Kepala Tukang L.03 OH 0.004 79,500.00 333.90
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 5,662.00
B BAHAN
Cat dasar kg 0.120 28,600.00 3,432.00
Cat penutup kg 0.180 28,600.00 5,148.00
JUMLAH HARGA BAHAN 8,580.00

C JUMLAH (A+B) 14,242.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 14,242.00
F Jumlah Dibulatkan 14,242.00

A.4.7.1.20. Pengecatan 1 m 2 permukaan baja galvanis secara manual sistem 3 lapis


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.400 63,100.00 25,240.00
Tukang Cat L.02 OH 0.800 79,500.00 63,600.00
Kepala Tukang L.03 OH 0.080 79,500.00 6,360.00
Mandor L.04 OH 0.020 74,100.00 1,482.00
JUMLAH TENAGA KERJA 96,682.00
B BAHAN
Cat dasar kg 0.110 58,700.00 6,457.00
Cat antara kg 0.170 58,700.00 9,979.00
Cat penutup kg 0.080 58,700.00 4,696.00
Kuas bh 0.010 11,000.00 110.00
Pengencer ltr 0.010 23,600.00 236.00
JUMLAH HARGA BAHAN 21,478.00

C JUMLAH (A+B) 118,160.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 118,160.00
F Jumlah Dibulatkan 118,160.00
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.1. Pemasangan 1 buah closet duduk / monoblock
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 3.300 63,100.00 208,230.00
Tukang Batu L.02 OH 1.100 79,500.00 87,450.00
Kepala Tukang L.03 OH 0.010 79,500.00 795.00
Mandor L.04 OH 0.160 74,100.00 11,856.00
JUMLAH TENAGA KERJA 308,331.00
B BAHAN
Closet duduk unit 1.000 1,578,900.00 1,578,900.00
Perlengkapan % 0.060 1,578,900.00 94,734.00
JUMLAH HARGA BAHAN 1,673,634.00

C JUMLAH (A+B) 1,981,965.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 1,981,965.00
F Jumlah Dibulatkan 1,981,965.00

A.5.1.1.2. Pemasangan 1 buah closet jongkok porselen


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Tukang Batu L.02 OH 1.500 79,500.00 119,250.00
Kepala Tukang L.03 OH 0.150 79,500.00 11,925.00
Mandor L.04 OH 0.160 74,100.00 11,856.00
JUMLAH TENAGA KERJA 206,131.00
B BAHAN
Closet jongkok Kloset jongkok INA, warna tua unit 1.000 166,700.00 166,700.00
Semen Portland kg 6.000 1,100.00 6,600.00
Pasir pasang m 3
0.010 243,100.00 2,431.00
JUMLAH HARGA BAHAN 175,731.00

C JUMLAH (A+B) 381,862.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 381,862.00
F Jumlah Dibulatkan 381,862.00

A.5.1.1.3. Pemasangan 1 buah closet jongkok teraso


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Tukang Batu L.02 OH 1.500 79,500.00 119,250.00
Kepala Tukang L.03 OH 0.150 79,500.00 11,925.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 197,980.00
B BAHAN
Closet jongkok unit 1.000 2,628,800.00 2,628,800.00
Semen Portland kg 6.000 1,100.00 6,600.00
Pasir pasang m3 0.010 243,100.00 2,431.00
Bata merah bh 7.000 1,000.00 7,000.00
JUMLAH HARGA BAHAN 2,644,831.00

C JUMLAH (A+B) 2,842,811.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 2,842,811.00
F Jumlah Dibulatkan 2,842,811.00
A.5.1.1.4. Pemasangan 1 buah urinoir
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.000 63,100.00 63,100.00
Tukang Batu L.02 OH 1.000 79,500.00 79,500.00
Kepala Tukang L.03 OH 0.100 79,500.00 7,950.00
Mandor L.04 OH 0.050 74,100.00 3,705.00
JUMLAH TENAGA KERJA 154,255.00
B BAHAN
Urinoir unit 1.000 1,107,500.00 1,107,500.00
Semen Portland kg 6.000 1,100.00 6,600.00
Pasir pasang m3 0.010 243,100.00 2,431.00
Perlengkapan % 0.300 1,107,500.00 332,250.00
JUMLAH HARGA BAHAN 1,448,781.00

C JUMLAH (A+B) 1,603,036.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 1,603,036.00
F Jumlah Dibulatkan 1,603,036.00

A.5.1.1.5. Pemasangan 1 buah wastafel


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.200 63,100.00 75,720.00
Tukang Batu L.02 OH 1.450 79,500.00 115,275.00
Kepala Tukang L.03 OH 0.150 79,500.00 11,925.00
Mandor L.04 OH 0.060 74,100.00 4,446.00
JUMLAH TENAGA KERJA 207,366.00
B BAHAN
Wastafel unit 1.200 432,400.00 518,880.00
Semen Portland kg 6.000 1,100.00 6,600.00
Pasir pasang m3 0.010 243,100.00 2,431.00
Perlengkapan % 0.120 518,880.00 62,265.60
JUMLAH HARGA BAHAN 590,176.60

C JUMLAH (A+B) 797,542.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 797,542.60
F Jumlah Dibulatkan 797,542.00

A.5.1.1.6. Pemasangan 1 buah bathtub porselen


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.075 63,100.00 4,732.50
Tukang Batu L.02 OH 0.075 79,500.00 5,962.50
Kepala Tukang L.03 OH 0.075 79,500.00 5,962.50
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 16,879.80
B BAHAN
Bathtub unit 1.000 - -
Perlengkapan % 20% - -
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 16,879.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 16,879.80
F Jumlah Dibulatkan 16,879.00
A.5.1.1.7. Pemasangan 1 buah bak fibreglass vol 1 m 3
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 3.000 63,100.00 189,300.00
Tukang Batu L.02 OH 4.500 79,500.00 357,750.00
Kepala Tukang L.03 OH 0.050 79,500.00 3,975.00
Mandor L.04 OH 0.900 74,100.00 66,690.00
JUMLAH TENAGA KERJA 617,715.00
B BAHAN
Bak fbreglass unit 1.000 288,200.00 288,200.00
Perlengkapan % 12% 288,200.00 34,584.00
JUMLAH HARGA BAHAN 322,784.00

C JUMLAH (A+B) 940,499.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 940,499.00
F Jumlah Dibulatkan 940,499.00

A.5.1.1.8. Pemasangan 1 buah bak mandi batu bata vol 0.30 m 3


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 6.000 63,100.00 378,600.00
Tukang Batu L.02 OH 3.000 79,500.00 238,500.00
Kepala Tukang L.03 OH 0.300 79,500.00 23,850.00
Mandor L.04 OH 0.030 74,100.00 2,223.00
JUMLAH TENAGA KERJA 643,173.00
B BAHAN
Bata merah m3 150.000 1,000.00 150,000.00
Semen Portland kg 120.000 1,100.00 132,000.00
Pasir Pasang m 3
0.300 243,100.00 72,930.00
Porselen 11 x 11 Keramik warna bh 360.000 2,875.00 1,035,000.00
Semen warna kg 6.000 1,750.00 10,500.00
JUMLAH HARGA BAHAN 1,400,430.00

C JUMLAH (A+B) 2,043,603.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 2,043,603.00
F Jumlah Dibulatkan 2,043,603.00

A.5.1.1.12. Pemasangan 1 buah bak cuci piring stainlessteel


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.030 63,100.00 1,893.00
Tukang Batu L.02 OH 0.300 79,500.00 23,850.00
Kepala Tukang L.03 OH 0.030 79,500.00 2,385.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 29,239.50
B BAHAN
Bak cuci piring Bak Cuci Stainless Steel "Viega" unit 1.000 466,700.00 466,700.00
Waterdrain bh 1.000 28,500.00 28,500.00
JUMLAH HARGA BAHAN 495,200.00

C JUMLAH (A+B) 524,439.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 524,439.50
F Jumlah Dibulatkan 524,439.00

A.5.1.1.14. Pemasangan 1 buah floor drain


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.010 63,100.00 631.00
Tukang Batu L.02 OH 0.100 79,500.00 7,950.00
Kepala Tukang L.03 OH 0.010 79,500.00 795.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 9,746.50
B BAHAN
Floor drain unit 1.000 28,500.00 28,500.00
JUMLAH HARGA BAHAN 28,500.00

C JUMLAH (A+B) 38,246.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 38,246.50
F Jumlah Dibulatkan 38,246.00
A.5.1.1.15. Pemasangan 1 buah bak kontrol pasangan bata 30 x 30 tinggi 35 cm
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 2.160 63,100.00 136,296.00
Tukang Batu L.02 OH 0.720 79,500.00 57,240.00
Kepala Tukang L.03 OH 0.072 79,500.00 5,724.00
Mandor L.04 OH 0.011 74,100.00 815.10
JUMLAH TENAGA KERJA 200,075.10
B BAHAN
Bata merah bh 40.000 1,000.00 40,000.00
Semen Portland kg 44.000 1,100.00 48,400.00
Pasir Pasang m3 0.070 243,100.00 17,017.00
Pasir Beton m3 0.060 243,100.00 14,586.00
Kerikil (Split 1-2 (pecah tangan)) m3 0.070 308,500.00 21,595.00
Baja Tulangan kg 1.600 9,700.00 15,520.00
JUMLAH HARGA BAHAN 157,118.00

C JUMLAH (A+B) 357,193.10


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 357,193.10
F Jumlah Dibulatkan 357,193.00

A.5.1.1.16. Pemasangan 1 buah bak kontrol pasangan bata 45 x 45 tinggi 50 cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 3.200 63,100.00 201,920.00
Tukang Batu L.02 OH 1.150 79,500.00 91,425.00
Kepala Tukang L.03 OH 0.011 79,500.00 874.50
Mandor L.04 OH 0.016 74,100.00 1,185.60
JUMLAH TENAGA KERJA 295,405.10
B BAHAN
Bata merah bh 70.000 1,000.00 70,000.00
Semen Portland kg 77.000 1,100.00 84,700.00
Pasir Pasang m 3
0.130 243,100.00 31,603.00
Pasir Beton m3 0.090 243,100.00 21,879.00
Kerikil (Split 1-2 (pecah tangan)) m3 0.020 308,500.00 6,170.00
Baja Tulangan kg 2.600 9,700.00 25,220.00
JUMLAH HARGA BAHAN 239,572.00

C JUMLAH (A+B) 534,977.10


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 534,977.10
F Jumlah Dibulatkan 534,977.00

A.5.1.1.17. Pemasangan 1 buah bak kontrol pasangan bata 60 x 60 tinggi 65 cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 3.200 63,100.00 201,920.00
Tukang Batu L.02 OH 1.150 79,500.00 91,425.00
Kepala Tukang L.03 OH 0.011 79,500.00 874.50
Mandor L.04 OH 0.016 74,100.00 1,185.60
JUMLAH TENAGA KERJA 295,405.10
B BAHAN
Bata merah bh 123.000 1,000.00 123,000.00
Semen Portland kg 114.000 1,100.00 125,400.00
Pasir Pasang m3 0.184 243,100.00 44,730.40
Pasir Beton m3 0.120 243,100.00 29,172.00
Kerikil (Split 1-2 (pecah tangan)) m3 0.033 308,500.00 10,180.50
Baja Tulangan kg 4.850 9,700.00 47,045.00
JUMLAH HARGA BAHAN 379,527.90

C JUMLAH (A+B) 674,933.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 674,933.00
F Jumlah Dibulatkan 674,933.00

A.5.1.1.18. Pemasangan 1 m' pipa galvanis diameter 1/2"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.054 63,100.00 3,407.40
Tukang Batu L.02 OH 0.090 79,500.00 7,155.00
Kepala Tukang L.03 OH 0.009 79,500.00 715.50
Mandor L.04 OH 0.027 74,100.00 2,000.70
JUMLAH TENAGA KERJA 13,278.60
B BAHAN
Pipa galvanis 1/2" m 1.200 23,000.00 27,600.00
Perlengkapan % 35% 27,600.00 9,660.00
JUMLAH HARGA BAHAN 37,260.00

C JUMLAH (A+B) 50,538.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 50,538.60
F Jumlah Dibulatkan 50,538.00
A.5.1.1.19. Pemasangan 1 buah kran diameter 1/2" atau 3/4"
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.010 63,100.00 631.00
Tukang Batu L.02 OH 0.400 79,500.00 31,800.00
Kepala Tukang L.03 OH 0.040 79,500.00 3,180.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 35,981.50
B BAHAN
Kran air m 1.000 77,700.00 77,700.00
Sealtape bh 0.025 3,500.00 87.50
JUMLAH HARGA BAHAN 77,787.50

C JUMLAH (A+B) 113,769.00


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 113,769.00
F Jumlah Dibulatkan 113,769.00

A.5.1.1.20. Pemasangan 1 m' pipa galvanis diameter 3/4"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.054 63,100.00 3,407.40
Tukang Batu L.02 OH 0.090 79,500.00 7,155.00
Kepala Tukang L.03 OH 0.009 79,500.00 715.50
Mandor L.04 OH 0.027 74,100.00 2,000.70
JUMLAH TENAGA KERJA 13,278.60
B BAHAN
Pipa galvanis 3/4" m 1.200 25,400.00 30,480.00
Perlengkapan % 35% 25,400.00 8,890.00
JUMLAH HARGA BAHAN 39,370.00

C JUMLAH (A+B) 52,648.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 52,648.60
F Jumlah Dibulatkan 52,648.00

A.5.1.1.21. Pemasangan 1 m' pipa galvanis diameter 1"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.054 63,100.00 3,407.40
Tukang Batu L.02 OH 0.090 79,500.00 7,155.00
Kepala Tukang L.03 OH 0.009 79,500.00 715.50
Mandor L.04 OH 0.027 74,100.00 2,000.70
JUMLAH TENAGA KERJA 13,278.60
B BAHAN
Pipa galvanis 1" m 1.200 34,800.00 41,760.00
Perlengkapan % 35% 34,800.00 12,180.00
JUMLAH HARGA BAHAN 53,940.00

C JUMLAH (A+B) 67,218.60


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 67,218.60
F Jumlah Dibulatkan 67,218.00

A.5.1.1.22. Pemasangan 1 m' pipa galvanis diameter 1 1/2"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.108 63,100.00 6,814.80
Tukang Batu L.02 OH 0.180 79,500.00 14,310.00
Kepala Tukang L.03 OH 0.018 79,500.00 1,431.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 22,926.30
B BAHAN
Pipa galvanis 1 1/2" m 1.200 - -
Perlengkapan % 35% - -
JUMLAH HARGA BAHAN -

C JUMLAH (A+B) 22,926.30


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 22,926.30
F Jumlah Dibulatkan 22,926.00

A.5.1.1.23. Pemasangan 1 m' pipa galvanis diameter 3"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.135 63,100.00 8,518.50
Tukang Batu L.02 OH 0.225 79,500.00 17,887.50
Kepala Tukang L.03 OH 0.023 79,500.00 1,828.50
Mandor L.04 OH 0.007 74,100.00 518.70
JUMLAH TENAGA KERJA 28,753.20
B BAHAN
Pipa galvanis 3" m 1.200 114,200.00 137,040.00
Perlengkapan % 35% 114,200.00 39,970.00
JUMLAH HARGA BAHAN 177,010.00

C JUMLAH (A+B) 205,763.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 205,763.20
F Jumlah Dibulatkan 205,763.00
A.5.1.1.24. Pemasangan 1 m' pipa galvanis diameter 4"
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.135 63,100.00 8,518.50
Tukang Batu L.02 OH 0.225 79,500.00 17,887.50
Kepala Tukang L.03 OH 0.023 79,500.00 1,828.50
Mandor L.04 OH 0.007 74,100.00 518.70
JUMLAH TENAGA KERJA 28,753.20
B BAHAN
Pipa galvanis 4" m 1.200 236,500.00 283,800.00
Perlengkapan % 35% 236,500.00 82,775.00
JUMLAH HARGA BAHAN 366,575.00

C JUMLAH (A+B) 395,328.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 395,328.20
F Jumlah Dibulatkan 395,328.00

A.5.1.1.25. Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.036 63,100.00 2,271.60
Tukang Batu L.02 OH 0.060 79,500.00 4,770.00
Kepala Tukang L.03 OH 0.006 79,500.00 477.00
Mandor L.04 OH 0.002 74,100.00 148.20
JUMLAH TENAGA KERJA 7,666.80
B BAHAN
Pipa PVC 1/2" m 1.200 5,200.00 6,240.00
Perlengkapan % 35% 5,200.00 1,820.00
JUMLAH HARGA BAHAN 8,060.00

C JUMLAH (A+B) 15,726.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 15,726.80
F Jumlah Dibulatkan 15,726.00

A.5.1.1.26. Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.036 63,100.00 2,271.60
Tukang Batu L.02 OH 0.060 79,500.00 4,770.00
Kepala Tukang L.03 OH 0.006 79,500.00 477.00
Mandor L.04 OH 0.002 74,100.00 148.20
JUMLAH TENAGA KERJA 7,666.80
B BAHAN
Pipa PVC 3/4" m 1.200 7,000.00 8,400.00
Perlengkapan % 35% 7,000.00 2,450.00
JUMLAH HARGA BAHAN 10,850.00

C JUMLAH (A+B) 18,516.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 18,516.80
F Jumlah Dibulatkan 18,516.00

A.5.1.1.27. Pemasangan 1 m' pipa PVC tipe AW diameter 1"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.036 63,100.00 2,271.60
Tukang Batu L.02 OH 0.060 79,500.00 4,770.00
Kepala Tukang L.03 OH 0.006 79,500.00 477.00
Mandor L.04 OH 0.002 74,100.00 148.20
JUMLAH TENAGA KERJA 7,666.80
B BAHAN
Pipa PVC 1" m 1.200 9,600.00 11,520.00
Perlengkapan % 35% 9,600.00 3,360.00
JUMLAH HARGA BAHAN 14,880.00

C JUMLAH (A+B) 22,546.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 22,546.80
F Jumlah Dibulatkan 22,546.00

A.5.1.1.28. Pemasangan 1 m' pipa PVC tipe AW diameter 1 1/2"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.054 63,100.00 3,407.40
Tukang Batu L.02 OH 0.090 79,500.00 7,155.00
Kepala Tukang L.03 OH 0.009 79,500.00 715.50
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 11,500.20
B BAHAN
Pipa PVC 1 1/2" m 1.200 16,200.00 19,440.00
Perlengkapan % 35% 16,200.00 5,670.00
JUMLAH HARGA BAHAN 25,110.00

C JUMLAH (A+B) 36,610.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 36,610.20
F Jumlah Dibulatkan 36,610.00
A.5.1.1.29. Pemasangan 1 m' pipa PVC tipe AW diameter 2"
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.054 63,100.00 3,407.40
Tukang Batu L.02 OH 0.090 79,500.00 7,155.00
Kepala Tukang L.03 OH 0.009 79,500.00 715.50
Mandor L.04 OH 0.003 74,100.00 222.30
JUMLAH TENAGA KERJA 11,500.20
B BAHAN
Pipa PVC 2" m 1.200 20,600.00 24,720.00
Perlengkapan % 35% 20,600.00 7,210.00
JUMLAH HARGA BAHAN 31,930.00

C JUMLAH (A+B) 43,430.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 43,430.20
F Jumlah Dibulatkan 43,430.00

A.5.1.1.30. Pemasangan 1 m' pipa PVC tipe AW diameter 2 1/2"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.081 63,100.00 5,111.10
Tukang Batu L.02 OH 0.135 79,500.00 10,732.50
Kepala Tukang L.03 OH 0.014 79,500.00 1,073.25
Mandor L.04 OH 0.004 74,100.00 296.40
JUMLAH TENAGA KERJA 17,213.25
B BAHAN
Pipa PVC 2 1/2" m 1.200 30,500.00 36,600.00
Perlengkapan % 35% 30,500.00 10,675.00
JUMLAH HARGA BAHAN 47,275.00

C JUMLAH (A+B) 64,488.25


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 64,488.25
F Jumlah Dibulatkan 64,488.00

A.5.1.1.31. Pemasangan 1 m' pipa PVC tipe AW diameter 3"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.081 63,100.00 5,111.10
Tukang Batu L.02 OH 0.135 79,500.00 10,732.50
Kepala Tukang L.03 OH 0.014 79,500.00 1,073.25
Mandor L.04 OH 0.004 74,100.00 296.40
JUMLAH TENAGA KERJA 17,213.25
B BAHAN
Pipa PVC 3" m 1.200 42,200.00 50,640.00
Perlengkapan % 35% 42,200.00 14,770.00
JUMLAH HARGA BAHAN 65,410.00

C JUMLAH (A+B) 82,623.25


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 82,623.25
F Jumlah Dibulatkan 82,623.00

A.5.1.1.32. Pemasangan 1 m' pipa PVC tipe AW diameter 4"


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.081 63,100.00 5,111.10
Tukang Batu L.02 OH 0.135 79,500.00 10,732.50
Kepala Tukang L.03 OH 0.014 79,500.00 1,073.25
Mandor L.04 OH 0.004 74,100.00 296.40
JUMLAH TENAGA KERJA 17,213.25
B BAHAN
Pipa PVC 4" m 1.200 69,800.00 83,760.00
Perlengkapan % 35% 69,800.00 24,430.00
JUMLAH HARGA BAHAN 108,190.00

C JUMLAH (A+B) 125,403.25


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 125,403.25
F Jumlah Dibulatkan 125,403.00

A.5.1.1.35. Pemasangan 1 m' pipa beton Ø 15 - Ø 20 cm


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.140 63,100.00 8,834.00
Tukang Batu L.02 OH 0.070 79,500.00 5,565.00
Kepala Tukang L.03 OH 0.007 79,500.00 556.50
Mandor L.04 OH 0.007 74,100.00 518.70
JUMLAH TENAGA KERJA 15,474.20
B BAHAN
Pipa tanah Ø 15 cm Pipa Beton ø 20 cm ( Buis Beton ) bh 1.100 58,500.00 64,350.00
Bata merah m3 0.027 1,000.00 27.00
Semen Portland kg 3.920 1,100.00 4,312.00
Pasir Pasang m3 0.056 243,100.00 13,613.60
Pasir Urug m3 0.024 151,000.00 3,624.00
JUMLAH HARGA BAHAN 85,926.60

C JUMLAH (A+B) 101,400.80


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 101,400.80
F Jumlah Dibulatkan 101,400.00
A.5.1.1.36. Pemasangan 1 m' pipa beton Ø 30 - Ø 100 cm
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.380 63,100.00 23,978.00
Tukang Batu L.02 OH 0.190 79,500.00 15,105.00
Kepala Tukang L.03 OH 0.019 79,500.00 1,510.50
Mandor L.04 OH 0.019 74,100.00 1,407.90
JUMLAH TENAGA KERJA 42,001.40
B BAHAN
Pipa tanah Ø 30 cm Pipa Beton ø 30 cm ( Buis Beton ) bh 1.100 80,500.00 88,550.00
Bata merah m3 0.550 1,000.00 550.00
Semen Portland kg 10.300 1,100.00 11,330.00
Pasir Pasang m 3
0.061 243,100.00 14,829.10
Pasir Urug m3 0.069 151,000.00 10,419.00
JUMLAH HARGA BAHAN 125,678.10

C JUMLAH (A+B) 167,679.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 167,679.50
F Jumlah Dibulatkan 167,679.00

HARGA SATUAN PEKERJAAN JALAN


W4 Biaya Menggilas sebulan ( 25 hari x 5 jam kerja = 125 jam ) BOW
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Masinis OH 25.000 109,800.00 2,745,000.00
Pembantu Masinis OH 25.000 71,300.00 1,782,500.00
Penjaga Malam OH 30.000 57,600.00 1,728,000.00
JUMLAH TENAGA KERJA 6,255,500.00
B BAHAN
Solar liter 800.000 6,700.00 5,360,000.00
Olie Kaleng liter 30.000 - -
JUMLAH HARGA BAHAN 5,360,000.00

C PERALATAN
Sewa Wales hari 25.000 - -
JUMLAH HARGA ALAT -

D JUMLAH (A+B+C) 11,615,500.00

A.020 A Pemadatan 1 m3 Urugan dengan Wales HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Biaya Menggilas (sewa wales) = 3/7500 (A.WLS.1) OH 0.0004 11,615,500.00 4,646.20
JUMLAH TENAGA KERJA 4,646.20

C JUMLAH (A) 4,646.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 4,646.20
F Jumlah Dibulatkan 4,646.00

A109 1 M2 PAS. ONDERLAG BATU BELAH T. 20 CM HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.200 63,100.00 12,620.00
Mandor L.04 OH 0.020 74,100.00 1,482.00
JUMLAH TENAGA KERJA 14,102.00
B BAHAN
Pasir Pasang m3 0.150 243,100.00 36,465.00
Batu belah m3 0.250 258,600.00 64,650.00
JUMLAH HARGA BAHAN 101,115.00
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00013 11,615,500.00 1,510.02
JUMLAH HARGA ALAT 1,510.02

C JUMLAH (A+B+C) 116,727.02


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 116,727.02
F Jumlah Dibulatkan 116,727.00

A109 A 1 M2 PAS. ONDERLAG BATU BELAH T. 15 CM HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.200 63,100.00 12,620.00
Mandor L.04 OH 0.020 74,100.00 1,482.00
JUMLAH TENAGA KERJA 14,102.00
B BAHAN
Pasir Pasang m3 0.113 243,100.00 27,348.75
Batu belah m3 0.188 258,600.00 48,487.50
JUMLAH HARGA BAHAN 75,836.25
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00013 11,615,500.00 1,510.02
JUMLAH HARGA ALAT 1,510.02

C JUMLAH (A+B+C) 91,448.27


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 91,448.27
F Jumlah Dibulatkan 91,448.00
A111 1 M2 AMPARAN BATU PECAH MESIN 2/3 T = 5 CM HSPK
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.150 63,100.00 9,465.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 10,576.50
B BAHAN
Batu pecah mesin 2/3 m3 0.060 298,800.00 17,928.00
JUMLAH HARGA BAHAN 17,928.00
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00013 11,615,500.00 1,510.02
JUMLAH HARGA ALAT 1,510.02

C JUMLAH (A+B+C) 30,014.52


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 30,014.52
F Jumlah Dibulatkan 30,014.00

A111 A 1 M2 AMPARAN BATU PECAH MESIN 3/4, 2/3, 1/2 T = 5 CM HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.150 63,100.00 9,465.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 10,576.50
B BAHAN
Batu pecah mesin 3/4 m3 0.030 303,600.00 9,108.00
Batu pecah mesin 2/3 m3 0.020 298,800.00 5,976.00
Batu pecah mesin 1/2 m3 0.010 283,500.00 2,835.00
Batu pecah mesin 0,5/1 (Screening) m3 0.005 276,300.00 1,381.50
Aspal drum Kg 4.000 5,700.00 22,800.00
Kayu bakar m3 0.030 203,500.00 6,105.00
JUMLAH HARGA BAHAN 48,205.50
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00040 11,615,500.00 4,646.20
JUMLAH HARGA ALAT 4,646.20

C JUMLAH (A+B+C) 63,428.20


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 63,428.20
F Jumlah Dibulatkan 63,428.00

A113 1 M2 PENGASPALAN MANUAL HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.150 63,100.00 9,465.00
Mandor L.04 OH 0.015 74,100.00 1,111.50
JUMLAH TENAGA KERJA 10,576.50
B BAHAN
Batu abu / Pasir beton m3 0.005 297,300.00 1,486.50
Aspal drum Kg 4.000 5,700.00 22,800.00
Kayu bakar m3 0.030 203,500.00 6,105.00
JUMLAH HARGA BAHAN 30,391.50
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00013 11,615,500.00 1,510.02
JUMLAH HARGA ALAT 1,510.02

C JUMLAH (A+B+C) 42,478.02


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 42,478.02
F Jumlah Dibulatkan 42,478.00

A114 1 M2 HOTMIX TANGAN T = 3 CM (JADI) UNTUK HAL & JLN KLS 6 TON KEBAWAH HSPK
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.200 63,100.00 12,620.00
Mandor L.04 OH 0.020 74,100.00 1,482.00
JUMLAH TENAGA KERJA 14,102.00
B BAHAN
Batu abu / Pasir beton m3 0.035 297,300.00 10,405.50
Aspal drum Kg 5.000 5,700.00 28,500.00
Kayu bakar m3 0.038 203,500.00 7,733.00
JUMLAH HARGA BAHAN 46,638.50
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00013 11,615,500.00 1,510.02
JUMLAH HARGA ALAT 1,510.02

C JUMLAH (A+B+C) 62,250.52


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 62,250.52
F Jumlah Dibulatkan 62,250.00
A114 A 1 M2 HOTMIX TANGAN T = 2 CM (JADI) UNTUK HAL & JLN KLS 6 TON KEBAWAH HSPK
No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.200 63,100.00 12,620.00
Mandor L.04 OH 0.020 74,100.00 1,482.00
JUMLAH TENAGA KERJA 14,102.00
B BAHAN
Batu abu / Pasir beton m3 0.023 297,300.00 6,927.09
Aspal drum Kg 3.333 5,700.00 18,999.81
Kayu bakar m3 0.025 203,500.00 5,148.55
JUMLAH HARGA BAHAN 31,075.45
C PERALATAN
Peralatan (Sewa Wales) = 1/7500 (W4) hari 0.00013 11,615,500.00 1,510.02
JUMLAH HARGA ALAT 1,510.02

C JUMLAH (A+B+C) 46,687.47


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 46,687.47
F Jumlah Dibulatkan 46,687.00

A121 1 m2 Pas. Paving Block Natural 6 cm HSPK


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.250 63,100.00 15,775.00
Tukang Batu L.02 OH 0.500 79,500.00 39,750.00
Kepala Tukang L.03 OH 0.050 79,500.00 3,975.00
Mandor L.04 OH 0.025 74,100.00 1,852.50
JUMLAH TENAGA KERJA 61,352.50
B BAHAN
Paving Block Natural 6 cm m2 1.010 85,200.00 86,052.00
Pasir Halus m3 0.100 194,300.00 19,430.00
JUMLAH HARGA BAHAN 105,482.00

C JUMLAH (A+B) 166,834.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 166,834.50
F Jumlah Dibulatkan 166,834.00

A121 A 1 m2 Pas. Paving Block Natural 6 cm (Lama)


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.250 63,100.00 15,775.00
Tukang Batu L.02 OH 0.500 79,500.00 39,750.00
Kepala Tukang L.03 OH 0.050 79,500.00 3,975.00
Mandor L.04 OH 0.025 74,100.00 1,852.50
JUMLAH TENAGA KERJA 61,352.50
B BAHAN
Pasir Halus m3 0.100 243,100.00 24,310.00
JUMLAH HARGA BAHAN 24,310.00

C JUMLAH (A+B) 85,662.50


D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 85,662.50
F Jumlah Dibulatkan 85,662.00

A121 B 1 m2 Bongkar Paving


No. Uraian Kode Satuan Koefisien Harga Sat. (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.050 63,100.00 3,155.00
Mandor L.04 OH 0.005 74,100.00 370.50
JUMLAH TENAGA KERJA 3,525.50

C JUMLAH (A 3,525.50
D Overhead & Profit
E Harga Satuan Pekerjaan (C+D) 3,525.50
F Jumlah Dibulatkan 3,525.00
a.4.1.1.24.d Pemasangan 1 m2 bondex

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang besi L.02 OH 0.030 100,000.00 3,000.00
Mandor L.04 OH 0.010 105,000.00 1,050.00
JUMLAH TENAGA KERJA 8,050.00
B BAHAN
Bondex m2 1.050 113,500.00 119,175.00
Balok Kayu Lokal m3 0.014 2,350,000.00 33,840.00
JUMLAH HARGA BAHAN 153,015.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 161,065.00


E Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E) 161,065.00

PEKERJAAN KAYU
A.4.6.1.1 Pembuatan dan Pemasangan 1 m ᶟ kusen pintu dan kusen jendela, kayu kelas I

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.000 80,000.00 560,000.00
Tukang Kayu L.02 OH 21.000 100,000.00 2,100,000.00
Kepala Tukang L.03 OH 2.100 105,000.00 220,500.00
Mandor L.04 OH 0.350 105,000.00 36,750.00
JUMLAH TENAGA KERJA 2,917,250.00
B BAHAN
Balok kayu (Jati Perum) m3 1.100 10,590,400.00 11,649,440.00
Paku 10 cm Kg 1.250 23,000.00 28,750.00
Lem kayu kg 1.000 16,000.00 16,000.00
JUMLAH HARGA BAHAN 11,694,190.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 14,611,440.00


E Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E) 14,611,440.00

A.4.6.1.5a Pembuatan dan pemasangan 1 m² daun pintu panel, kayu jati (perum)

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang kayu L.02 OH 3.000 100,000.00 300,000.00
Kepala Tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 105,000.00 5,250.00
JUMLAH TENAGA KERJA 416,750.00
B BAHAN
Papan Kayu Jati (Perum) m3 0.040 10,876,400.00 435,056.00
Lem kayu kg 0.500 16,000.00 8,000.00
JUMLAH HARGA BAHAN 443,056.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 859,806.00


E Overhead + Profit 15% Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E) 859,806.00
A.2.2.1.10 Pembuatan 1 m2 steger/perancah dari bambu

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.170 80,000.00 13,600.00
Tukang Kayu L.02 OH 0.250 100,000.00 25,000.00
Kepala Tukang L.03 OH 0.002 105,000.00 210.00
Mandor L.04 OH 0.001 105,000.00 136.50
JUMLAH TENAGA KERJA 38,946.50
B BAHAN
Bambu diameter 6 - 8 / 600 cm Btg 1.250 16,000.00 20,000.00
Tali Ijuk Kg 0.186 40,000.00 7,440.00
JUMLAH HARGA BAHAN 27,440.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 66,386.50


E Overhead + Profit 15% Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E) 66,380.00

A.4.2.1.3a Pengerjaan 1 Kg pekerjaan perakitan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.001 80,000.00 80.00
Tukang Besi Konstruksi L.03 OH 0.001 100,000.00 100.00
Kepala Tukang L.03 OH 0.00001 105,000.00 1.05
Mandor L.04 OH 0.00005 105,000.00 5.25
JUMLAH TENAGA KERJA 186.30
B BAHAN
Solar Liter 0.010 7,725.52 77.26
Minyak Pelumas Liter 0.001 30,000.00 30.00
JUMLAH HARGA BAHAN 107.26
C PERALATAN
Sewa Alat (Welding Machine) E63 Jam 0.008 30,000.00 240.00
JUMLAH HARGA ALAT 240.00

D Jumlah (A+B+C) 533.56


E Overhead + Profit 15% 15% x D
F Harga Satuan Pekerjaan (D+E) 533.56
RENCANA ANGGARAN BIAYA ( RAB ) PEKERJAAN TAMBAHAN
KEGIATAN : PEMBANGUNAN
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, BREBES
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018

HARGA SAT JUMLAH HARGA JUMLAH SEMUA


NO URAIAN PEKERJAAN ANALISA VOLUME SAT (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8

PEKERJAAN MENARA
1 balok
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 4.48 m3 884,089.00 3,960,718.72
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,367.84 kg 11,565.00 15,819,011.78
Pemasangan Begisting Untuk Balok A.4.1.1.23 19.60 m2 204,294.00 4,004,162.40
2 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 6.48 m3 884,089.00 5,728,896.72
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 494.75 kg 11,565.00 5,721,830.01
Pemasangan Begisting untuk kolom A.4.1.1.22 3.24 m2 96,000.00 311,040.00
3 Dak Topi Menara
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 4.03 m3 884,089.00 3,564,646.85
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 464.81 kg 11,565.00 5,375,504.52
Pemasangan Bekisting untuk Dak atap A.4.1.1.24 28.72 m2 293,415.00 8,426,878.80
JUMLAH III 52,912,689.79
PEKERJAAN PEMASANGAN GRC MENARA
1 Rangka Kubah (4 menara) taksir 4.00 unit 55,000,000.00 220,000,000.00
2 Penangkal Petir taksir 1.00 ls 5,000,000.00 5,000,000.00
3 Ps Kosen dan Kaca Patri bwh kubah menara kecil taksir 5.00 unit 5,000,000.00 25,000,000.00
4 PS. Kubah alu lengkap dg finishing dia 2,5-3m Taksir 1.00 unit 60,000,000.00 60,000,000.00
JUMLAH IV 310,000,000.00
UNTUK 1 BUAH MENARA 362,912,689.79
MAKA UNTUK 4 BH MENARA 4.00 bh 362,912,689.79 1,451,650,759.17
TOTAL UNTUK PEKERJAAN MENARA Rp. 1,480,678,731.10
Pembulatan Rp. 1,480,678,000.00

Terbilang : SATU MILYAR EMPAT RATUS DELAPAN PULUH JUTA ENAM RATUS TUJUH PULUH DELAPAN RIBU RUPIAH
RENCANA ANGGARAN BIAYA ( RAB
KEGIATAN : PEMBANGUNAN
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, B
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018
REVISI (PEKERJAAN ATAP DIMASUKKAN SETELAH LANTAI 2 TERMASUK KUBAH)

NO URAIAN PEKERJAAN ANALISA VOLUME


1 2 3 4

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan dan Bongkaran Atap Taksir 1.00
2 Bongkaran Pas Bata (TERMASUK R.SEKR &Audio) A.2.2.1.14 248.36
3 Bongkar beton (kolom dan Balok) A.2.2.1.13 20.58
4 Bongkar kusen dan perapian Taksir 1.00
5 Bouwplank Taksir 1.00

II PEKERJAAN TANAH
Galian Tanah pondasi Foot Plat K1 A.2.3.1.1. 40.50
Galian Tanah Foot Plat K2 A.2.3.1.1. 46.88
Galian Tanah pondasi batu kali A.2.3.1.1. 23.04
2 Timbunan Tanah Kembali A.2.3.1.9 27.60

III PEKERJAAN BETON


1 Pas. Pondasi Batu Belah A.3.2.1.2 53.12
1 Pondasi Foot plat
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 26.79
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 6,618.95
Pemasangan bekisting untuk pondasi A.4.1.1.20 200.66
1 Pondasi Foot plat Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 2.6
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 355.30
Pemasangan bekisting untuk kolom A.4.1.1.20 12.10
4 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.37
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,585.53
Pemasangan Begisting untuk kolom A.4.1.1.22 124.60
4 Kolom Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 1.856
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 237.57
Pemasangan Begisting untuk kolom A.4.1.1.22 6.96
4 Kolom Tambahan (4 buah) dekat tangga
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.432
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 158.45
Pemasangan Begisting untuk kolom A.4.1.1.22 5.76
2 Sloof
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.55
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,035.83
Pemasangan Begisting Untuk Sloof A.4.1.1.21 52.50
2 Sloof tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.41
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 100.62
Pemasangan Begisting untuk kolom A.4.1.1.21 5.10
3 balok utama
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 14.175
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,133.97
Pemasangan Begisting Untuk Balok A.4.1.1.23 73.50
3 balok utama tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 1.377
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 207.30
Pemasangan Begisting Untuk Balok A.4.1.1.23 7.14
4 balok (anak & tepi)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 7.32
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,492.43
Pemasangan Begisting Untuk Balok A.4.1.1.23 48.80
5 Dak lantai
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 31.39
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 4,646.02
Pemasangan bondex A.4.1.1.24 318.36
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.89
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,535.29
Pemasangan Bekisting untuk Dak A.4.1.1.24 41.00
6 Dak tambahan dekat tangga dan kanan kiri
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.58
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 74.89
Pemasangan Bekisting untuk Dak A.4.1.1.24 2.00
3 Pembuatan tangga (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.624
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 369.52
Pemasangan Begisting Untuk tangga A.4.1.1.26 22.92

III PEKERJAAN PASANGAN


1 Pasangan Dinding 1/2 bata 1:4 A.4.4.1.9 518.91
2 Plesteran 1:4 (termasuk Acian) A.4.4.2.4 1,037.82
3 pengecatan khusus Cat exterior Taksir 537.82
4 Lantai Granit A.4.4.3.35 240.00
5 Lantai Granit Tangga A.4.4.3.35 50.00
5 Dinding Granit A.A.3.54.b 259.46
6 Ps. Ornamen GRC tertutup sekaligus mighrab (REVSI) Taksir 244.65
7 Ps. Gypsum datar Taksir 262.00
8 Ps. Kosen Kayu pintu lurus 3 buah Jati Lokal A.4.6.1.1 1.59
9 Ps. Kosen Kayu Lengkung 3 buah jati lokal A.4.6.1.1 0.68
10 Ps. Kosen Jendela (J2) lurus 2 buah Jati Lokal A.4.6.1.1 1.51
11 Ps. Kosen Jendela (J2) Lengkung 2 buah Jati Lokal A.4.6.1.1 0.68
12 Ps. Kosen Jendela (J1) Lurus 8 buah Jati Lokal A.4.6.1.1 3.63
13 Ps. Kosen Jendela (J1) Lengkung 8 Buah Jati Lokal A.4.6.1.1 1.36
14 Ps. Daun Pintu Tinggi ±2,4m (3 buah) Taksir 34.56
15 Ps. Daun Jendela J2 Tinggi +- 1,9m(2 buah) Taksir 22.80
16 Ps. Daun Jendela tunggal Tinggi +- 1,9m(8 buah) Taksir 27.36
17 Ps. Kaca Patri Pintu Lokal Taksir 13.20
18 Ps. Kaca Patri Jendela (J1) Lokal Taksir 8.00
19 Ps. Kaca Patri Jendela (J2) Lokal Taksir 16.00
20 Melamik Kosen Kayu pintu lurus 3 buah Taksir 27.00
21 Melamik Kosen Kayu lengkung Taksir 9.00
22 Melamik Kosen J2 lurus 2 buah Taksir 27.00
23 Melamik kosen J2 lengkung Taksir 9.00
24 Melamik Kosen J1 Taksir 48.00
25 Melamik Kosen J1 lengkung Taksir 12.00
26 Melamik daun pintu Taksir 28.80
27 Melamik Daun J2 Taksir 6.08
28 Melamik Daun J1 Taksir 24.32
29 Ps. Ornamen Kaligrafi dinding Mighrab dan depan Taksir 1.00
30 Ps. Paving A.121 151.50
31 Ps. Kolom Artistik (membuat lingkaran)
- Membuat beton k200 A.4.1.1.6 6.69
- begisting (lingkaran) A.4.1.1.22 56.65
32 Peralatan pintu dan Jendela (handle,kait dll) Taksir 1.00
33 Pekerjaan Kelistrikan beserta peralatannya Taksir 1.00
34 Pasang List Kecil Taksir 101.50
35 Ps. List Besar Taksir 60.00

Terbilang : Satu Milyar Lima Ratus Sembilan Puluh Tiga Juta Dua Ratus Lima

REVISI DAN DUA LANTAI (LANTAI DUA)

NO URAIAN PEKERJAAN ANALISA VOLUME


1 2 3 4

III PEKERJAAN BETON

1 Pasang Steiger A.2.2.1.10 402.00


2 Kolom Lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.1525
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 15,099.49
Pemasangan Begisting untuk kolom A.4.1.1.22 107.10
3 balok utama lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 2.673
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 235.77
Pemasangan Begisting Untuk Balok A.4.1.1.23 13.86
4 balok (anak & tepi) lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 6.3
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,284.47
Pemasangan Begisting Untuk Balok A.4.1.1.23 42.00
5 Dak Atap
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 31.39
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 4,646.02
Pemasangan bondex A.4.1.1.24 318.36
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.89
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,535.29
Pemasangan Bekisting untuk Dak A.4.1.1.24 41.00

IV PEKERJAAN BAJA
1 Erection A.4.2.1.3a 3,906.60
2 Pasang kuda-kuda dan dudukan kubah IWF A.4.2.1.2. 3,906.60
3 Pasang baut kuda-kuda taksir 122.00
4 Pasang baut angkur taksir 72.00
5 Pasang plat simpul taksir 70.00
6 Pasang gording canal C 100.50.20.2,6 A.4.2.1.1b. 1,651.89
7 Pasang CNP baja ringan taksir 210.00
8 Reng Baja Ringan taksir 210.00
9 Pasang Jarum antar gording (trekstrang) dia 12 mm taksir 85.00
10 Ikatan Angin dia 16mm taksir 112.00
11 Plat Landas taksir 40.00
12 Pasang Penutup atap metal berpasir taksir 224.50
13 Pekerjaan pengelasan A.4.2.1.5a. 350
14 Meni Besi(baja) A.4.7.1.16. 75.00
15 Pengecatan permukaan baja secara manual sistem 3 lapis A.4.7.1.20 75.00
16 Pasang Kosen dan kaca patri Bawah Kubah besar taksir 9.00
17 PS. Kubah alu (rangka+finishing) diameter (5,5m -6m) Taksir 1.00

III PEKERJAAN PASANGAN


1 Pasangan Dinding 1/2 bata 1:4 A.4.4.1.9 420.00
2 Plesteran 1:4 (termasuk Acian) A.4.4.2.4 840.00
3 pengecatan khusus Cat exterior Taksir 840.00
4 Lantai Granit A.4.4.3.35 240.00
5 Ps. Gypsum datar Taksir 262.00
6 Ps. Gypsum miring ruang sholat utama Taksir 216.50
12 Ps. Kosen Jendela art Lengkung 13 buah A.4.6.1.1 1.11
18 Ps. Kaca Patri Lokal Jendela art Taksir 41.60
24 Melamik Kosen Jendela art Taksir 98.80
30 Ps. Kolom Artistik (membuat lingkaran)
- Membuat beton k200 Taksir 1.14
- begisting (lingkaran) Taksir 24.73
32 Pekerjaan Kelistrikan lantai 2 beserta peralatannya Taksir 1.00
34 Pasang List Kecil Taksir 101.50
35 Ps. List Besar Taksir 60.00
36 Pasang Railing Stainless lantai 2 Taksir 22.00

Terbilang : Satu Milyar Tiga Ratus Enam Juta Tujuh Ratus Dua Puluh D
................................... ..................................
GARAN BIAYA ( RAB )
N MASJID AT-TAQWA BULAKAMBA, BREBES
AMBA, BREBES

HARGA SAT JUMLAH HARGA JUMLAH SEMUA


SAT (Rp) (Rp) (Rp)
5 6 7 8

ls 5,881,000.00 5,881,000.00
m2 66,744.00 16,576,539.84
m3 890,726.00 18,331,141.08
ls 1,500,000.00 1,500,000.00
ls 750,000.00 750,000.00
Jumlah I 43,038,680.92

m3 39,697.00 1,607,728.50
m3 39,697.00 1,860,796.88
m3 39,697.00 914,618.88
m2 35,255.00 973,170.21
Jumlah II 5,356,314.46

m2 784,227.00 41,658,138.24

m3 884,089.00 23,684,744.31 9.775


kg 11,565.00 76,548,179.88
m2 82,487.00 16,551,841.42

m3 884,089.00 2,298,631.40 9.775


kg 11,565.00 4,109,073.41
m2 82,487.00 998,092.70

m3 884,089.00 20,661,159.93
kg 11,565.00 29,901,596.63
m2 197,415.00 24,597,909.00

m3 884,089.00 1,640,869.18
kg 11,565.00 2,747,541.00
m2 197,415.00 1,374,008.40

m3 884,089.00 381,926.45
kg 11,565.00 1,832,451.12
m2 197,415.00 1,137,110.40

m3 884,089.00 3,138,515.95
kg 11,565.00 11,979,316.13
m2 88,979.00 4,671,397.50
m3 884,089.00 362,476.49
kg 11,565.00 1,163,705.00
m2 88,979.00 453,792.90
261.6
m3 884,089.00 12,531,961.58
kg 11,565.00 24,679,334.14
m2 204,294.00 15,015,609.00
261.6
m3 884,089.00 1,217,390.55
kg 11,565.00 2,397,421.03
m2 204,294.00 1,458,659.16

m3 884,089.00 6,471,531.48 5232


kg 11,565.00 17,259,906.69 ((2,6*15*2)+(3,6*17*3))*5*2*2
m2 204,294.00 9,969,547.20

m3 884,089.00 27,753,321.89 150.525


kg 11,565.00 53,731,175.04
m2 161,065.00 51,276,653.40

m3 884,089.00 10,511,818.21
kg 11,565.00 17,755,582.59
m2 161,065.00 6,603,665.00

m3 884,089.00 512,771.62
kg 11,565.00 866,125.98
m2 161,065.00 322,130.00
261.6
m3 884,089.00 3,203,938.54
kg 11,565.00 4,273,480.30
m2 392,085.00 8,986,588.20
JUMLAH II 548,691,089.01

294.16
m2 121,889.00 63,249,420.99
m2 45,857.00 47,591,311.74
m2 40,000.00 21,512,800.00
m2 367,477.00 88,194,480.00
m2 367,477.00 18,373,850.00
m2 367,477.00 95,343,745.04
m2 425,000.00 103,976,250.00 129,837,500.00
m2 160,000.00 41,920,000.00
m3 14,611,440.00 23,226,710.31
m3 14,611,440.00 9,954,304.42
m3 14,611,440.00 22,120,676.49
m3 14,611,440.00 9,954,304.42
m3 14,611,440.00 53,089,623.57
m3 14,611,440.00 19,908,608.84
m2 859,806.00 29,714,895.36
m2 859,806.00 19,603,576.80
m2 859,806.00 23,524,292.16
m2 1,600,000.00 21,120,000.00
m2 1,600,000.00 12,800,000.00
m2 1,600,000.00 25,600,000.00
m' 75,000.00 2,025,000.00
m' 75,000.00 675,000.00
m' 75,000.00 2,025,000.00
m' 75,000.00 675,000.00
m' 75,000.00 3,600,000.00
m' 75,000.00 900,000.00
m2 120,000.00 3,456,000.00
m2 120,000.00 729,600.00
m2 120,000.00 2,918,400.00
ls 10,000,000.00 10,000,000.00
m2 166,834.00 25,275,351.00

m3 884,089.00 5,914,555.41
60,000,000.00
m2 197,415.00 11,183,559.75
unit 2,500,000.00 2,500,000.00
ls 5,000,000.00 5,000,000.00
m' 240,000.00 24,360,000.00
m' 325,000.00 19,500,000.00
Jumlah III 871,516,316.28
Jumlah I s.d III Rp. 1,468,602,400.67
Pembulatan Rp. 1,468,602,000.00

luh Tiga Juta Dua Ratus Lima Puluh Enam Ribu Rupiah

HARGA SAT JUMLAH HARGA JUMLAH SEMUA


SAT
(Rp) (Rp) (Rp)
5 6 7 8
(1,5*1,5*2)+(1,5*1,2*22)+(0,8*0,3*
#VALUE!

m2 66,380.00 26,684,760.00

m3 884,089.00 20,468,870.57
kg 11,565.00 174,625,642.33
m2 197,415.00 21,143,146.50

m3 884,089.00 2,363,169.90
kg 11,565.00 2,726,662.70
m2 204,294.00 2,831,514.84

m3 884,089.00 5,569,760.70
kg 11,565.00 14,854,837.73
m2 204,294.00 8,580,348.00

m3 884,089.00 27,753,321.89
kg 11,565.00 53,731,175.04
m2 161,065.00 51,276,653.40

m3 884,089.00 10,511,818.21
kg 11,565.00 17,755,582.59
m2 161,065.00 6,603,665.00
JUMLAH II 447,480,929.39

kg 533.56 2,084,386.74
kg 29,418.00 114,924,358.80
bh 25,000.00 3,050,000.00
bh 45,000.00 3,240,000.00
kg 15,000.00 1,050,000.00
kg 27,232.00 44,984,268.48
m2 160,000.00 33,600,000.00
m2 75,000.00 15,750,000.00
kg 15,000.00 1,275,000.00
kg 15,000.00 1,680,000.00
kg 15,000.00 600,000.00
m2 200,000.00 44,900,000.00
kg 2,532.32 886,310.57
m2 24,126.50 1,809,487.50 150.525
m2 123,366.00 9,252,450.00
unit 10,000,000.00 90,000,000.00
unit 210,000,000.00 210,000,000.00
JUMLAH IV 579,086,262.09

m2 121,889.00 51,193,380.00
m2 45,857.00 38,519,880.00
m2 40,000.00 33,600,000.00
m2 367,477.00 88,194,480.00
m2 160,000.00 41,920,000.00
m2 180,000.00 38,970,000.00
m3 14,611,440.00 16,168,435.05
m2 1,600,000.00 66,560,000.00
m' 75,000.00 7,410,000.00

m3 884,089.00 1,007,861.46
60,000,000.00
m2 197,415.00 4,881,085.88
ls 5,000,000.00 5,000,000.00
m' 240,000.00 24,360,000.00
m' 325,000.00 19,500,000.00
m' 1,000,000.00 22,000,000.00
Jumlah III 459,285,122.38
Jumlah I s.d III Rp. 1,485,852,313.86
Pembulatan Rp. 1,485,852,000.00

Juta Tujuh Ratus Dua Puluh Delapan Ribu Rupiah


....................... Fatkhurozak, ST
96
*2)+(3,6*17*3))*5*2*2

12.2688630280071

99.0833333333334

4.83333333333333

1.589625

103,976,250.00 25,861,250.00
211,096,992.36
10.50 21
4.50 6
10.00 20
4.50 6
24.00 48
9.00 12
15.00 6 t
8.00 4 t
16.00 8 t
101.50

17,004,000.00

17,098,115.16 42,901,884.84

*2)+(1,5*1,2*22)+(0,8*0,3*(10))-((0,3*2)*0,3)
12.2688630280071

5,888,947.34 54,111,052.67

total selisih 122,874,187.51


PERHITUNGAN TAMBAH KURANG (MUTULA CHECK)
KEGIATAN : PEMBANGUNAN
PEKERJAAN : PEMBANGUNAN MASJID AT-TAQWA BULAKAMBA, BREBES
LOKASI : DESA BULAKAMBA, BREBES
TAHUN ANGGARAN : 2018
LANTAI 1 MC 100 PEKERJAAN TAMBAH PEKERJAAN KURANG
HARGA SAT JUMLAH HARGA JUMLAH SEMUA HARGA SAT JUMLAH HARGA HARGA SAT JUMLAH HARGA HARGA SAT JUMLAH HARGA
NO URAIAN PEKERJAAN ANALISA VOLUME SAT (Rp) (Rp) (Rp) VOLUME SAT (Rp) (Rp) VOLUME SAT (Rp) (Rp) VOLUME SAT (Rp) (Rp)
1 2 3 4 5 6 7 8 4 5 6 7 4 5 6 7 4 5 6 7

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan dan Bongkaran Atap Taksir 1.00 ls 5,881,000.00 5,881,000.00
2 Bongkaran Pas Bata (TERMASUK R.SEKR &Audio) A.2.2.1.14 248.36 m2 66,744.00 16,576,539.84
3 Bongkar beton (kolom dan Balok) A.2.2.1.13 20.58 m3 890,726.00 18,331,141.08
4 Bongkar kusen dan perapian Taksir 1.00 ls 1,500,000.00 1,500,000.00
5 Bouwplank Taksir 1.00 ls 750,000.00 750,000.00
Jumlah I 43,038,680.92
II PEKERJAAN TANAH
Galian Tanah pondasi Foot Plat K1 A.2.3.1.1. 40.50 m3 39,697.00 1,607,728.50
Galian Tanah Foot Plat K2 A.2.3.1.1. 46.88 m3 39,697.00 1,860,796.88
Galian Tanah pondasi batu kali A.2.3.1.1. 23.04 m3 39,697.00 914,618.88
2 Timbunan Tanah Kembali A.2.3.1.9 27.60 m2 35,255.00 973,170.21
Jumlah II 5,356,314.46
III PEKERJAAN BETON
1 Pas. Pondasi Batu Belah A.3.2.1.2 53.12 m2 784,227.00 41,658,138.24
1 Pondasi Foot plat
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 26.79 m3 884,089.00 23,684,744.31
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 6,618.95 kg 11,565.00 76,548,179.88
Pemasangan bekisting untuk pondasi A.4.1.1.20 200.66 m2 82,487.00 16,551,841.42
1 Pondasi Foot plat Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 2.6 m3 884,089.00 2,298,631.40
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 355.30 kg 11,565.00 4,109,073.41
Pemasangan bekisting untuk kolom A.4.1.1.20 12.10 m2 82,487.00 998,092.70
4 Kolom
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.37 m3 884,089.00 20,661,159.93
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,585.53 kg 11,565.00 29,901,596.63
Pemasangan Begisting untuk kolom A.4.1.1.22 124.60 m2 197,415.00 24,597,909.00
4 Kolom Tambahan (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 1.856 m3 884,089.00 1,640,869.18
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 237.57 kg 11,565.00 2,747,541.00
Pemasangan Begisting untuk kolom A.4.1.1.22 6.96 m2 197,415.00 1,374,008.40
4 Kolom Tambahan (4 buah) dekat tangga
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.432 m3 884,089.00 381,926.45
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 158.45 kg 11,565.00 1,832,451.12
Pemasangan Begisting untuk kolom A.4.1.1.22 5.76 m2 197,415.00 1,137,110.40
2 Sloof
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.55 m3 884,089.00 3,138,515.95
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,035.83 kg 11,565.00 11,979,316.13
Pemasangan Begisting Untuk Sloof A.4.1.1.21 52.50 m2 88,979.00 4,671,397.50
2 Sloof tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.41 m3 884,089.00 362,476.49
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 100.62 kg 11,565.00 1,163,705.00
Pemasangan Begisting untuk kolom A.4.1.1.21 5.10 m2 88,979.00 453,792.90
3 balok utama
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 14.175 m3 884,089.00 12,531,961.58
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 2,133.97 kg 11,565.00 24,679,334.14
Pemasangan Begisting Untuk Balok A.4.1.1.23 73.50 m2 204,294.00 15,015,609.00
3 balok utama tambahan
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 1.377 m3 884,089.00 1,217,390.55
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 207.30 kg 11,565.00 2,397,421.03
Pemasangan Begisting Untuk Balok A.4.1.1.23 7.14 m2 204,294.00 1,458,659.16
4 balok (anak & tepi)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 7.32 m3 884,089.00 6,471,531.48
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,492.43 kg 11,565.00 17,259,906.69
Pemasangan Begisting Untuk Balok A.4.1.1.23 48.80 m2 204,294.00 9,969,547.20
5 Dak lantai
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 31.39 m3 884,089.00 27,753,321.89
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 4,646.02 kg 11,565.00 53,731,175.04
Pemasangan bondex A.4.1.1.24 318.36 m2 161,065.00 51,276,653.40
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.89 m3 884,089.00 10,511,818.21
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,535.29 kg 11,565.00 17,755,582.59
Pemasangan Bekisting untuk Dak A.4.1.1.24 41.00 m2 161,065.00 6,603,665.00
6 Dak tambahan dekat tangga dan kanan kiri
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 0.58 m3 884,089.00 512,771.62
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 74.89 kg 11,565.00 866,125.98
Pemasangan Bekisting untuk Dak A.4.1.1.24 2.00 m2 161,065.00 322,130.00
3 Pembuatan tangga (2 buah)
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 3.624 m3 884,089.00 3,203,938.54
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 369.52 kg 11,565.00 4,273,480.30
Pemasangan Begisting Untuk tangga A.4.1.1.26 22.92 m2 392,085.00 8,986,588.20
JUMLAH II 548,691,089.01
III PEKERJAAN PASANGAN
1 Pasangan Dinding 1/2 bata 1:4 A.4.4.1.9 518.91 m2 121,889.00 63,249,420.99
2 Plesteran 1:4 (termasuk Acian) A.4.4.2.4 1,037.82 m2 45,857.00 47,591,311.74
3 pengecatan khusus Cat exterior Taksir 537.82 m2 40,000.00 21,512,800.00
4 Lantai Granit A.4.4.3.35 380.00 m2 367,477.00 139,641,260.00
5 Lantai Granit Tangga A.4.4.3.35 50.00 m2 367,477.00 18,373,850.00
6 Dinding Granit A.A.3.54.b 259.46 m2 367,477.00 95,343,745.04
7 Ps. Ornamen GRC tertutup sekaligus mighrab Taksir 305.50 m2 425,000.00 129,837,500.00
8 Ps. Ornamen GRC Lubang (krawangan) Taksir 79.36 m2 750,000.00 59,520,000.00
9 Ps. Gypsum datar Taksir 262.00 m2 160,000.00 41,920,000.00
10 Ps. Gypsum Drop
11 Ps. Kosen Kayu pintu lurus 3 buah Jati Lokal A.4.6.1.1 1.59 m3 14,611,440.00 23,226,710.31
12 Ps. Kosen Kayu Lengkung 3 buah jati lokal A.4.6.1.1 0.68 m3 14,611,440.00 9,954,304.42
13 Ps. Kosen Jendela (J2) lurus 2 buah Jati Lokal A.4.6.1.1 1.51 m3 14,611,440.00 22,120,676.49
14 Ps. Kosen Jendela (J2) Lengkung 2 buah Jati Lokal A.4.6.1.1 0.68 m3 14,611,440.00 53,089,623.57
15 Ps. Kosen Jendela (J1) Lurus 8 buah Jati Lokal A.4.6.1.1 3.63 m3 14,611,440.00 19,908,608.84
16 Ps. Kosen Jendela (J1) Lengkung 8 Buah Jati Lokal A.4.6.1.1 1.36 m3 14,611,440.00 19,908,608.84
17 Ps. Daun Pintu Tinggi ±2,4m (3 buah) Taksir 34.56 m2 859,806.00 29,714,895.36
18 Ps. Daun Jendela J2 Tinggi +- 1,9m(2 buah) Taksir 22.80 m2 859,806.00 19,603,576.80
19 Ps. Daun Jendela tunggal Tinggi +- 1,9m(8 buah) Taksir 27.36 m2 859,806.00 23,524,292.16
20 Ps. Kaca Patri Pintu Lokal Taksir 13.20 m2 1,600,000.00 21,120,000.00
21 Ps. Kaca Patri Jendela (J1) Lokal Taksir 8.00 m2 1,600,000.00 12,800,000.00
22 Ps. Kaca Patri Jendela (J2) Lokal Taksir 16.00 m2 1,600,000.00 25,600,000.00
23 Melamik Kosen Kayu pintu lurus 3 buah Taksir 27.00 m' 75,000.00 2,025,000.00
24 Melamik Kosen Kayu lengkung Taksir 9.00 m' 75,000.00 675,000.00
25 Melamik Kosen J2 lurus 2 buah Taksir 27.00 m' 75,000.00 2,025,000.00
26 Melamik kosen J2 lengkung Taksir 9.00 m' 75,000.00 675,000.00
27 Melamik Kosen J1 Taksir 48.00 m' 75,000.00 3,600,000.00
28 Melamik Kosen J1 lengkung Taksir 12.00 m' 75,000.00 900,000.00
29 Melamik daun pintu Taksir 28.80 m2 120,000.00 3,456,000.00
30 Melamik Daun J2 Taksir 6.08 m2 120,000.00 729,600.00
31 Melamik Daun J1 Taksir 24.32 m2 120,000.00 2,918,400.00
32 Ps. Ornamen Kaligrafi dinding Mighrab dan depan Taksir 1.00 ls 10,000,000.00 10,000,000.00
33 Ps. Paving A.121 151.50 m2 166,834.00 25,275,351.00
34 Ps. Kolom Artistik GRC Taksir 80.00 m' 750,000.00 60,000,000.00
35 Peralatan pintu dan Jendela (handle,kait dll) Taksir 1.00 unit 2,500,000.00 2,500,000.00
36 Pekerjaan Kelistrikan beserta peralatannya
Penempatan Titik Lampu Taksir 70.00 titik 60,000.00 4,200,000.00
Penempatan Titik saklar Taksir 12.00 titik 80,000.00 960,000.00
Penempatan Titik Stop Kontak Taksir 8.00 titik 80,000.00 640,000.00
Peralatan (tempat downlight, Kabel, lampu dsb) 300% Taksir 4.00 23,200,000.00 29,000,000.00
37 Pasang List Kecil Taksir 350.00 m' 240,000.00 84,000,000.00 102.00 m' 240,000.00 24,480,000.00 248.00 m' 240,000.00 59,520,000.00
38 Ps. List Besar Taksir 105.00 m' 325,000.00 34,125,000.00 60.00 m' 325,000.00 19,500,000.00 45.00 m' 325,000.00 14,625,000.00
Jumlah III 1,159,465,535.54
Jumlah I s.d III Rp. 1,756,551,619.93 JUMLAH JUMLAH 29,000,000.00 JUMLAH 117,046,884.84
Pembulatan Rp. 1,756,551,000.00

Terbilang : Satu Milyar Tujuh Ratus Lima Puluh Enam Juta Lima Ratus Lima Puluh Satu Ribu Rupiah
REVISI DAN DUA LANTAI (LANTAI DUA) MC PEKERJAAN TAMBAH PEKERJAAN KURANG
HARGA SAT JUMLAH HARGA JUMLAH SEMUA HARGA SAT JUMLAH HARGA HARGA SAT JUMLAH HARGA HARGA SAT JUMLAH HARGA
NO URAIAN PEKERJAAN ANALISA VOLUME SAT VOLUME SAT VOLUME SAT VOLUME SAT
(Rp) (Rp) (Rp) (Rp) (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8 4 5 6 7 4 5 6 7 4 5 6 7

III PEKERJAAN BETON

1 Pasang Steiger A.2.2.1.10 402.00 m2 66,380.00 26,684,760.00


2 Kolom Lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 23.1525 m3 884,089.00 20,468,870.57
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 15,099.49 kg 11,565.00 174,625,642.33
Pemasangan Begisting untuk kolom A.4.1.1.22 107.10 m2 197,415.00 21,143,146.50
3 balok utama lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 2.673 m3 884,089.00 2,363,169.90
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 235.77 kg 11,565.00 2,726,662.70
Pemasangan Begisting Untuk Balok A.4.1.1.23 13.86 m2 204,294.00 2,831,514.84
4 balok (anak & tepi) lantai 2
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 6.3 m3 884,089.00 5,569,760.70
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,284.47 kg 11,565.00 14,854,837.73
Pemasangan Begisting Untuk Balok A.4.1.1.23 42.00 m2 204,294.00 8,580,348.00
5 Dak Atap
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 31.39 m3 884,089.00 27,753,321.89
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 4,646.02 kg 11,565.00 53,731,175.04
Pemasangan bondex A.4.1.1.24 318.36 m2 161,065.00 51,276,653.40
6 Dak lengkung dan pemanis
Membuat beton mutu f’c = 16,9 MPa (K 200) A.4.1.1.6 11.89 m3 884,089.00 10,511,818.21
Pembesian 1 kg dengan besi polos atau besi ulir A.4.1.1.17 1,535.29 kg 11,565.00 17,755,582.59
Pemasangan Bekisting untuk Dak A.4.1.1.24 41.00 m2 161,065.00 6,603,665.00
JUMLAH II 447,480,929.39

IV PEKERJAAN BAJA
1 Erection A.4.2.1.3a 4,770.30 kg 533.56 2,545,218.37
2 Pasang kuda-kuda dan dudukan kubah IWF A.4.2.1.2. 4,770.30 kg 29,418.00 140,332,685.40 4,770.30 kg 29,418.00 140,332,685.40 0.00 kg 29,418.00 0.00
3 Pasang baut kuda-kuda taksir 122.00 bh 25,000.00 3,050,000.00
4 Pasang baut angkur taksir 72.00 bh 45,000.00 3,240,000.00
5 Pasang plat simpul taksir 70.00 kg 15,000.00 1,050,000.00
6 Pasang gording canal C 125.50.20.4,5 (8,32kg/m') A.4.2.1.1b. 1,668.99 kg 27,232.00 45,449,935.68 1,668.99 kg 27,232.00 45,449,990.14 0.00 kg 27,232.00 54.46
7 Pasang CNP baja ringan taksir 210.00 m2 160,000.00 33,600,000.00
8 Reng Baja Ringan taksir 210.00 m2 75,000.00 15,750,000.00
9 Pasang Jarum antar gording (trekstrang) dia 12 mm taksir 85.00 kg 15,000.00 1,275,000.00
10 Ikatan Angin dia 16mm taksir 112.00 kg 15,000.00 1,680,000.00
11 Plat Landas taksir 40.00 kg 15,000.00 600,000.00
12 Pasang Penutup atap metal berpasir taksir 224.50 m2 200,000.00 44,900,000.00
13 Pekerjaan pengelasan A.4.2.1.5a. 350 kg 2,532.32 886,310.57
14 Meni Besi(baja) A.4.7.1.16. 75.00 m2 24,126.50 1,809,487.50
15 Pengecatan permukaan baja secara manual sistem 3 lapis A.4.7.1.20 75.00 m2 123,366.00 9,252,450.00
16 Pasang Kosen dan kaca patri Bawah Kubah besar taksir 9.00 unit 10,000,000.00 90,000,000.00
17 PS. Kubah alu (rangka+finishing) diameter (5,5m -6m) Taksir 1.00 unit 210,000,000.00 210,000,000.00
JUMLAH IV 605,421,087.52
III PEKERJAAN PASANGAN
1 Pasangan Dinding 1/2 bata 1:4 A.4.4.1.9 420.00 m2 121,889.00 51,193,380.00
2 Plesteran 1:4 (termasuk Acian) A.4.4.2.4 840.00 m2 45,857.00 38,519,880.00
3 pengecatan khusus Cat exterior Taksir 840.00 m2 40,000.00 33,600,000.00
4 Lantai Granit A.4.4.3.35 240.00 m2 367,477.00 88,194,480.00
5 Ps. Gypsum datar Taksir 262.00 m2 160,000.00 41,920,000.00
Ps. Gypsum Drop 262.00 m2 170,000.00 44,540,000.00 2,620,000.00
6 Ps. Gypsum miring ruang sholat utama Taksir 216.50 m2 180,000.00 38,970,000.00
12 Ps. Kosen Jendela art Lengkung 13 buah A.4.6.1.1 11.10 m3 14,611,440.00 162,186,984.00 11.00 m3 14,611,440.00 160,725,840.00 -0.10 m3 14,611,440.00 -1,461,144.00
18 Ps. Kaca Patri Lokal Jendela art Taksir 41.60 m2 1,600,000.00 66,560,000.00
24 Melamik Kosen Jendela art Taksir 98.80 m' 75,000.00 7,410,000.00
30 Ps. Kolom Artistik GRC Taksir 70.00 m' 750,000.00 52,500,000.00
- Membuat beton k200 Taksir 1.14 m3 884,089.00 1,007,861.46
- begisting (lingkaran) Taksir 24.73 m2 197,415.00 4,881,085.88 46,611,052.67
32 Pekerjaan Kelistrikan lantai 2 beserta peralatannya
Penempatan Titik Lampu Taksir 70.00 titik 60,000.00 4,200,000.00
Penempatan Titik saklar Taksir 12.00 titik 80,000.00 960,000.00
Penempatan Titik Stop Kontak Taksir 8.00 titik 80,000.00 640,000.00
Peralatan (tempat downlight, Kabel, lampu dsb) 400% Taksir 4.00 23,200,000.00 29,000,000.00
34 Pasang List Kecil Taksir 185.00 m' 240,000.00 44,400,000.00 102.00 m' 240,000.00 24,480,000.00 83.00 m' 240,000.00 19,920,000.00
35 Ps. List Besar Taksir 80.00 m' 325,000.00 26,000,000.00 60.00 m' 325,000.00 19,500,000.00 20.00 m' 325,000.00 6,500,000.00
36 Pasang Railing Stainless lantai 2 Taksir 70.00 m' 1,000,000.00 70,000,000.00
Jumlah III 750,454,724.00
Jumlah I s.d III Rp. 1,803,356,740.91 Jumlah Jumlah 30,158,910.46 Jumlah 73,031,052.67
Pembulatan Rp. 1,803,356,000.00

Terbilang : Satu Milyar Delapan Ratus Tiga Juta Tiga Ratus Lima Puluh Enam Ribu Rupiah

TOTAL LANTAI 1 DAN 2 1,756,551,000.00 + 1,803,356,000.00 3,559,907,000.00


TIGA MILYAR LIMA RATUS LIMA PULUH SEMBILAN JUTA SEMBILAN RATUS TUJUH RIBU RUPIAH

II PEKERJAAN PEREDAM GETARAN


1 Galian Tanah pondasi Foot Plat K1 A.2.3.1.1. 60.00 m3 39,697.00 2,381,820.00
2 Urug Pasir halus A.2.3.1.9 60.00 m3 314,895.00 18,893,700.00
3 Membuang tanah galian A.2.3.1.8 60.00 m3 21,564.00 1,293,840.00
Jumlah II 22,569,360.00