PEMERINTAH PROVINSI SUMATERA SELATAN

DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER

Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Prod Tggl : 17-03-2008


Paket / Ruas : PALEMBANG - TANJUNG API-API Space : - 90°
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : STA 41+505 s/d 42+375
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi15 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
Baca Alat ( Kg / Cm )2
( Kg / Cm )
2

1 32 280 19.30 372.49 s bm = S s bi


2 32 280 19.30 372.49 N

3 32 280 19.30 372.49 = 260.70 Kg/Cm2

4 27 210 -50.70 2570.49

5 28 250 -10.70 114.49

6 28 250 -10.70 114.49 S = S ( s bi - s bm)2


N -1
7 28 280 19.30 372.49

8 28 280 19.30 372.49 = 33.41 Kg/Cm2

9 30 250 -10.70 114.49

10 28 220 -40.70 1656.49


 s = s bm - (1.64 x S)
11 28 310 49.30 2430.49

12 28 310 49.30 2430.49 = 205.92 Kg/Cm2

13 29 310 49.30 2430.49

14 29 238 -22.70 515.29 v= S X 100 %


s bm
15 28 220 -40.70 1656.49

16 30 198 -62.70 3931.29 = 12.81 %

17 30 250 -10.70 114.49

18 32 280 19.30 372.49 Fcf = 3.13 x 0.75 x (s bk)0.5

19 32 280 19.30 372.49 = 33.69 Kg/Cm2

20 29 238 -22.70 515.29 = 74.9 %

5214 21202

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER


Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Prod Tggl :
Paket / Ruas : PALEMBANG - TANJUNG API-API Space : - 90°
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : 21+220 s/d 21+290
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi 3 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
Baca Alat ( Kg / Cm2 ) ( Kg / Cm2 )

1 24 170 25.75 663.0625 s bm = S s bi


2 24 170 25.75 663.0625 N

3 24 170 25.75 663.0625 = 144.25 Kg/Cm2

4 23 160 15.75 248.0625

5 20 125 -19.25 370.5625

6 24 170 25.75 663.0625 S = S ( s bi - s bm)2


N -1
7 24 170 25.75 663.0625

8 24 170 25.75 663.0625 = 22.02 Kg/Cm2

9 24 170 25.75 663.0625

10 20 125 -19.25 370.5625


 s = s bm - (1.64 x S)
11 20 125 -19.25 370.5625

12 20 125 -19.25 370.5625 = 108.14 Kg/Cm2

13 20 125 -19.25 370.5625

14 23 160 15.75 248.0625 v= S x100 %


s bm
15 20 125 -19.25 370.5625

16 20 125 -19.25 370.5625 = 15.27 %

17 20 125 -19.25 370.5625

18 20 125 -19.25 370.5625 Fcf = 3.13 x 0.75 x (s bk)0.5

19 20 125 -19.25 370.5625 = 9.17 Kg/Cm2

20 20 125 -19.25 370.5625 = 20.4 %

2885 9214

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER


Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Prod Tggl : 16 dan 17-11-2007
Paket / Ruas : PALEMBANG - TANJUNG API-API Space : - 90°
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : 21+220 s/d 21+290
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi 14 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
Baca Alat ( Kg / Cm2 ) ( Kg / Cm2 )

1 24 170 -17.45 304.5025 s bm = S s bi


2 24 170 -17.45 304.5025 N

3 28 220 32.55 1059.5025 = 187.45 Kg/Cm2

4 28 220 32.55 1059.5025

5 29 238 50.55 2555.3025

6 29 238 50.55 2555.3025 S = S ( s bi - s bm)2


N -1
7 26 198 10.55 111.3025

8 29 238 50.55 2555.3025 = 41.24 Kg/Cm2

9 29 238 50.55 2555.3025

10 20 125 -62.45 3900.0025


 s = s bm - (1.64 x S)
11 25 180 -7.45 55.5025

12 29 238 50.55 2555.3025 = 119.82 Kg/Cm2

13 21 135 -52.45 2751.0025

14 21 135 -52.45 2751.0025 v= S x100 %


s bm
15 26 198 10.55 111.3025

16 20 125 -62.45 3900.0025 = 63.92 %

17 21 135 -52.45 2751.0025

18 24 170 -17.45 304.5025 Fcf = 3.13 x 0.75 x (s bk)0.5

19 26 198 10.55 111.3025 = 25.70 Kg/Cm2

20 25 180 -7.45 55.5025 = 73.4 %

3749 32306.95

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER


Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Prod Tggl : 16 dan 17-11-2007
Paket / Ruas : PALEMBANG - TANJUNG API-API Space : - 90°
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : 21+220 s/d 21+290
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi 21 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
Baca Alat ( Kg / Cm2 ) ( Kg / Cm2 )

1 26 198 9.70 94.09 s bm = S s bi


2 21 135 -53.30 2840.89 N

3 24 170 -18.30 334.89 = 188.30 Kg/Cm2

4 26 198 9.70 94.09

5 28 220 31.70 1004.89

6 28 220 31.70 1004.89 S = S ( s bi - s bm)2


N -1
7 28 220 31.70 1004.89

8 27 210 21.70 470.89 = 33.24 Kg/Cm2

9 28 220 31.70 1004.89

10 28 220 31.70 1004.89


 s = s bm - (1.64 x S)
11 27 210 21.70 470.89

12 26 198 9.70 94.09 = 133.79 Kg/Cm2

13 26 198 9.70 94.09

14 24 170 -18.30 334.89 v= S x100 %


s bm
15 20 125 -63.30 4006.89

16 26 198 9.70 94.09 = 17.65 %

17 26 198 9.70 94.09

18 20 125 -63.30 4006.89 Fcf = 3.13 x 0.75 x (s bk)0.5

19 21 135 -53.30 2840.89 = 27.15 Kg/Cm2

20 26 198 9.70 94.09 = 77.6 %

3766 20990.2

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER


Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Prod Tggl : 17-03-2008
Paket / Ruas : PALEMBANG - TANJUNG API-API Space : - 90°
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : 41 + 505 s/d 42+375
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi 14 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
Baca Alat ( Kg / Cm2 ) ( Kg / Cm2 )

1 30 250 41.90 1755.61 s bm = S s bi


2 26 198 -10.10 102.01 N

3 27 210 1.90 3.61 = 208.10 Kg/Cm2

4 25 180 -28.10 789.61

5 25 180 -28.10 789.61

6 26 198 -10.10 102.01 S = S ( s bi - s bm)2


N -1
7 26 198 -10.10 102.01

8 28 220 11.90 141.61 = 18.81 Kg/Cm2

9 28 220 11.90 141.61

10 26 198 -10.10 102.01


 s = s bm - (1.64 x S)
11 26 198 -10.10 102.01

12 26 198 -10.10 102.01 = 177.25 Kg/Cm2

13 26 198 -10.10 102.01

14 28 220 11.90 141.61 v= S x100 %


s bm
15 27 210 1.90 3.61

16 28 220 11.90 141.61 = 9.04 %

17 28 220 11.90 141.61

18 30 250 41.90 1755.61 Fcf = 3.13 x 0.75 x (s bk)0.5

19 26 198 -10.10 102.01 = 31.25 Kg/Cm2

20 26 198 -10.10 102.01 = 89.3 %

4162 6723.8

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER

Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Diproduksi :''29-09-2007


Paket / Ruas : PALEMBANG - TANJUNG API-API Space :
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : Sta 57 + 285
Konsultan : SEECONS KSO Kontruksi : BOX CULVERT

No Nilai s bi 28 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
90 ° Baca Alat ( Kg / Cm2 ) ( Kg / Cm2 )

1 25 204 -122.40 14981.76 s bm = S s bi


2 35 306 -20.40 416.16 N

3 34 306 -20.40 416.16 = 326.40 Kg/Cm2

4 44 408 81.60 6658.56

5 36 306 -20.40 416.16

6 38 306 -20.40 416.16 Mpa = K /10*0,83


7 33 306 -20.40 416.16

8 40 408 81.60 6658.56 = 27.09 Mpa

9 30 306 -20.40 416.16

10 45 408 81.60 6658.56

11

12

13

14

15

16

17

18

19

20

S 3264 37454.4

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER


Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Diproduksi :'08-09-2007
Paket / Ruas : PALEMBANG - TANJUNG API-API Space : Fs' 45
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi : Sta 21+125 s/d 18+ 000
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi 28 Hari ( s bi - s bm )


( s bi - s bm )2 PERHITUNGAN
0° Baca Alat ( Kg / Cm )2
( Kg / Cm )
2

1 10 250 15.50 240.25 s bm = S s bi


2 35 260 25.50 650.25 N

3 34 220 -14.50 210.25 = 234.50 Kg/Cm2

4 44 220 -14.50 210.25

5 36 220 -14.50 210.25

6 38 260 25.50 650.25 S = S ( s bi - s bm)2


N -1
7 33 250 15.50 240.25

8 40 220 -14.50 210.25 = 16.69 Kg/Cm2

9 30 250 15.50 240.25

10 45 220 -14.50 210.25


 s = s bm - (1.64 x S)
11 28 220 -14.50 210.25

12 28 220 -14.50 210.25 = 207.12 Kg/Cm2

13 28 220 -14.50 210.25

14 100 250 15.50 240.25 v= S x 100 %


s bm
15 30 250 15.50 240.25

16 30 250 15.50 240.25 = 7.12 %

17 30 250 15.50 240.25

18 28 220 -14.50 210.25 Fcf = 3.13 x 0.75 x (s bk)0.5

19 28 220 -14.50 210.25 = 33.78 Kg/Cm2

20 28 220 -14.50 210.25 = 75.1 %


S 4690 5295

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER

Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Prod Tggl :


Paket / Ruas : PALEMBANG - TANJUNG API-API Space : Fs' 45
Penyedia Jasa : WIKA - CIA - TRJ, JO Lokasi :
Konsultan : SEECONS KSO Kontruksi : RIGID PAVEMENT

No Nilai s bi 28 Hari ( s bi - s bm ) ( s bi - s bm )2 PERHITUNGAN


Baca Alat ( Kg / Cm )
2
( Kg / Cm )
2

1 s bm = S s bi
2 N

3 = Kg/Cm2

6 S = S ( s bi - s bm)2
N -1
7

8 = Kg/Cm2

10
 s = s bm - (1.64 x S)
11

12 = Kg/Cm2

13

14 v= S x 100 %
s bm
15

16 = %

17

18 Fcf = 3.13 x 0.75 x (s bk)0.5

19 = Kg/Cm2

20 = %

Approved by PU Checked by CONSULTANT Tested by CONTRACTOR


16

S = S ( s bi - s bm)2
N -1

 s = s bm - (1.64 x S)

132.68

11.51868048

66.3

311.4663

0.0032106202

0
PEMERINTAH PROVINSI SUMATERA SELATAN
DINAS PEKERJAAN UMUM BINA MARGA

EVALUASI KUAT TEKAN BETON DENGAN ALAT HAMMER


Kegiatan : PEMBANGUNAN JALAN PALEMBANG - TANJUNG API-API Lokasi :
Paket / Ruas : PALEMBANG - TANJUNG API-API Space :
Penyedia Jasa : WIKA - CIA - TRJ, JO Tanggal :
Konsultan : SEECONS KSO

No  ‫ק‬d
( Kg / Cm2 )

GRADATION OF MIX
No Sieve No. 1½ 1 ¾ ½ 3/8 # 4 #8 # 16 # 30 # 50 # 200

6 Cold Bin

7 Hot Bin

Specification 100 90 - 100 Max. 90 19 - 45 3-7

MARSHALL PROPERTIES
No MIX PROPERTIES TEST RESULTS REQUIREMENT
8 Kadar Aspal Optimum (%)
9 Bulk Density Standart ( gr/cc )
10 Bulk Density PRD ( gr/cc )
11 VIM Standart (%)
12 VIM Refusal (%)
13 Prosen Rongga terhadap Aggregat ( VMA )
14 Prosen Rongga terisi Aspal ( VFB )
15 Stabilitas (%)
16 Kelelehan ( mm )
17 QM ( Kg/mm)

18 Stabilitas Marshall sisa setelah perendaman


selama 24 jam pada suhu 60 º C (%)
19
20
21
39.5
BINA MARGA KONSULTAN PENYEDIA JASA