Kelas KA 223
Kampus LP3I Cilodong Depok
Matkul Cost Acc
Produk selesai
bahan baku 700 60
UTKL 700 90
BOP 700 50
BBB UTKL
Rp 54,000 Rp 42,000 Rp 77,400 Rp 63,000
Rp 12,000 Rp 14,400
Rp 54,000 Rp 54,000 Rp 77,400 Rp 77,400
Rp - Rp -
BOP BDP
Rp 43,000 Rp 35,000 Rp 54,000 Rp 42,000
Rp 8,000 Rp 77,400 Rp 63,000
Rp 43,000 Rp 43,000 Rp 43,000 Rp 35,000
Rp - Rp 174,400 Rp 140,000
Rp 34,400
b. Biaya UTKL c. BOP
700 700 100% 700 700
200 160 80% 200 160
860 860
Rp 42,000
Rp 63,000
Rp 35,000
Rp 140,000
Rp 12,000
Rp 14,400
Rp 8,000
Rp 34,400
Rp 174,400
Persediaan brg jadi
Rp 42,000
Rp 63,000
Rp 35,000
Rp 140,000
Nama ILHAM MAHESA
Kelas KA 223
Kampus LP3I Cilodong Depok
Matkul Cost Acc
Produk selesai
bahan baku 1000 30
UTKL 1000 45
BOP 1000 25
BBB UTKL
Rp 36,000 Rp 30,000 Rp 52,200 Rp 45,000
Rp 6,000 Rp 7,200
Rp 36,000 Rp 36,000 Rp 52,200 Rp 52,200
Rp - Rp -
BOP BDP
Rp 29,000 Rp 29,000 Rp 36,000 Rp 30,000
Rp - Rp 52,200 Rp 45,000
Rp 29,000 Rp 29,000 Rp 29,000 Rp 25,000
Rp - Rp 117,200 Rp 100,000
Rp 17,200
Rp 30,000
Rp 45,000
Rp 25,000
Rp 100,000
Rp 6,000
Rp 7,200
Rp 4,000
Rp 17,200
Rp 117,200
Persediaan brg jadi
Rp 45,000
Rp 25,000
Rp -
Rp 70,000
DAPARTEMEN 1
1. Lap biaya Dapartemen produksi
Dapartemen 2
Biaya produksi
Bahan Baku Rp -
UTKL Rp 27,750
Overhead Pabrik Rp 18,500
Total Biaya Rp 46,250
HPP DEP 1
Rp - 1000 Rp 100
Produk selesai
bahan baku 700 100
UTKL 700 30
BOP 700 20
BBB UTKL
Rp 100,000 Rp 70,000 Rp 27,750 Rp 21,000
Rp 30,000 Rp 6,750
Rp 100,000 Rp 100,000 Rp 27,750 Rp 27,750
Rp - Rp -
BOP BDP
Rp 18,500 Rp 14,000 Rp 27,750 Rp 21,000
Rp 4,500 Rp 18,500 Rp 14,000
Rp 18,500 Rp 18,500 Rp 46,250 Rp -
Rp - Rp 92,500 Rp 35,000
Rp 57,500
Rp 70,000
Rp 21,000
Rp 14,000
Rp 105,000
Rp 30,000
Rp 6,750
Rp 4,500
Rp 41,250
Rp 146,250
Persediaan brg jadi
Rp 21,000
Rp 14,000
Rp 100,000
Rp 135,000
DAPARTEMEN 2