No Item Description Volume Satuan Harga Satuan Total
(%) Vol Bobot JUMLAH
Pekerjaan Pasangan Dinding Plaster & Acian

1 Pasangan Hebel - 0.400 ~ + 6.000 815 m2 Rp 25.000 Rp 20.373.278 13.00% 162.99 20.00% Rp 4.074.750

Pasangan Hebel + 6.000 ~ + 10.734 51 m2 Rp 30.000 Rp 1.540.800 0.98% 7.65 14.89% Rp 229.500

2 Kolom Praktis dan Balok Lintel 100 - 150 737 m Rp 28.500 Rp 21.016.005 13.41% 331.83 45.00% Rp 9.457.155

Kolom Praktis dan Balok Lintel 100 - 200 183 m Rp 29.913 Rp 5.483.141 3.50% 82.49 45.00% Rp 2.467.563

Kolom Praktis dan Balok Lintel 125 - 300 365 m Rp 44.641 Rp 16.307.313 10.41% 164.39 45.00% Rp 7.338.514

3 Plasteran - 0.400 ~ + 6.000 2.243 m2 Rp 20.000 Rp 44.867.915 28.64% 0.00% Rp -

Plasteran + 6.000 ~ + 10.734 107 m2 Rp 24.000 Rp 2.566.892 1.64% 0.00% Rp -

4 Acian - 0.400 ~ + 6.000 2.243 m2 Rp 15.000 Rp 33.650.937 21.48% 0.00% Rp -

Acian + 6.000 ~ + 10.734 107 m2 Rp 18.000 Rp 1.925.169 1.23% 0.00% Rp -

5 Pemasangan Rooster 46 m2 Rp 28.000 Rp 1.290.240 0.82% 0.00% Rp -

6 Pekerjaan Scafolding - 0.400 ~ + 6.000 1.030 m2 Rp 7.000 Rp 7.209.094 4.60% 154 15.00% Rp 1.081.360

Pekerjaan Scafolding + 6.000 ~ + 10.734 53 m2 Rp 8.400 Rp 449.206 0.29% 8 15.00% Rp 67.368

TOTAL Rp 156.679.990 100% TOTAL Rp 24.716.210


RETENSI 5% Rp 1.235.811
TOTAL Rp 23.480.400