TIME S C H E D U L E

ROW SLOPE REINFORCEMENT PHASE III


Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Agust-23 Sep-23 Okt-23
No. Description Work (%) REMARK
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Galian tanah dengan alat berat 0.020 0.020

2 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Urugan pasir tebal 10 cm 0.009 0.009

3 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Lantai kerja mutu beton K125, Tebal 5 cm 0.020 0.020

4 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh M6x150, cast in place, K-250 0.758 0.189 0.189 0.189 0.189

5 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200- Mengurug kembali bekas galian menggunakan tanah bekas galian 0.039 0.039

PEK. U-DRAIN
6 + RAMBU -RAMBU di ROW AS KP 1+200- Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton mutu K225 ukuran 0,5x0,5x0,4
0.023(m) 0.023

7 PEK. BRONJONG di ROW AS KP 1+200 - Galian tanah dengan alat berat 0.129 0.129

8 PEK. BRONJONG di ROW AS KP 1+200 - Pengadaan + Pemancangan Micro Pile Ø10 cm, 3 buah untuk 1 m dengan kedalaman 5 m 3.748 0.937 0.937 0.937 0.937

9 PEK. BRONJONG di ROW AS KP 1+200 - Kawat Bronjong Galvanized 2 x 1 x 0,5 (m) dia. 2,7 mm + Batu Pecah 5.056 1.264 1.264 1.264 1.264

10 PEK. BRONJONG di ROW AS KP 1+200 - Lapisan Geotextile di depan pasangan Gabion (vertikal) 0.322 0.081 0.081 0.081 0.081

11 PEK. BRONJONG di ROW AS KP 1+200 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 0.094 0.094

12 SURVEY MICRO TREMOR 2.706 1.353 1.353

13 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Galian tanah dengan alat berat 0.049 0.049

14 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Urugan pasir tebal 10 cm 0.022 0.022

15 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Lantai kerja mutu beton K125, Tebal 5 cm 0.049 0.049

16 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh M6x150, cast in place, K-250 1.840 0.613 0.613 0.613

17 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500- Mengurug kembali bekas galian menggunakan tanah bekas galian 0.098 0.098

PEK. U-DRAIN
18 + RAMBU -RAMBU di ROW AS KP 1+500- Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton mutu K225 ukuran 0,5x0,5x0,4
0.023(m) 0.023

GUARD POST + RAMBU -RAMBU


19di ROW AR STA 12+350 & STA 12+390 - Guard Post dari pipa besi dia. 4" (sesuai gambar) + pondasi ukuran 0,35 x 0,35 x 1,2 (m) concrete K225 dengan pembesian
2.358dia. 10 mm dan stirrups dia. 6 mm. 0.58958 0.58958 0.58958 0.58958

20 PEK. SHEET PILE di ROW AS KP 1+500 - Galian tanah dengan alat berat 0.381 0.3811

1.46749 1.46749 1.46749 1.46749 1.46749


21 PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III 400 x 100 x 10.5mm, Length 12 m 7.337
1.32074

22 PEK. SHEET PILE di ROW AS KP 1+500 - Pekerjaan beton Pile Cap, Multipleks 9mm, Pembesian D16 mm , Cast in Place, K-300 2.613 1.30631 1.30631

23 PEK. SHEET PILE di ROW AS KP 1+500 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 0.181 0.181

24 PEK. SHEET PILE di ROW AS KP 1+500 - Penggalian existing soil material di badan ROW 2.368 2.368

25 PEK. SHEET PILE di ROW AS KP 1+500 - Pembuangan soil material 2.368 1.18389 1.18389

26 PEK. SHEET PILE di ROW AS KP 1+500 - Penggantian soil material di badan ROW dan dipadatkan CBR Min. 95% 3.078 1.02604 1.02604 1.02604

27 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Galian tanah dengan alat berat 0.022 0.02199

28 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Urugan pasir tebal 10 cm 0.010 0.00991

29 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Lantai kerja mutu beton K125, Tebal 5 cm 0.022 0.02195

30 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh M6x150, cast in place, K-250 0.893 0.22325 0.22325 0.22325 0.22325

31 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800- Mengurug kembali bekas galian menggunakan tanah bekas galian 0.044 0.04432

32 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800- Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton mutu K225 ukuran
0.023 0,5x0,5x0,4 (m) 0.023

33 PEK. BRONJONG di ROW AS KP 1+800 - Galian tanah dengan alat berat 0.251 0.12553 0.12553

34 PEK. BRONJONG di ROW AS KP 1+800 - Pengadaan + Pemancangan Micro Pile Ø10 cm, 3 buah untuk 1 m dengan kedalaman 5 m 19.229 2.40358 2.40358 2.40358 2.40358 2.40358 2.40358 2.40358 2.40358

35 PEK. BRONJONG di ROW AS KP 1+800 - Kawat Bronjong Galvanized 2 x 1 x 0,5 (m) dia. 2,7 mm + Batu Pecah 12.532 1.56654 1.56654 1.56654 1.56654 1.56654 1.56654 1.56654 1.56654

36 PEK. BRONJONG di ROW AS KP 1+800 - Lapisan Geotextile di depan pasangan Gabion (vertikal) 0.810 0.10125 0.10125 0.10125 0.10125 0.10125 0.10125 0.10125 0.10125

37 PEK. BRONJONG di ROW AS KP 1+800 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 0.188 0.09402 0.09402

38 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Galian tanah dengan alat berat 0.049 0.04886

39 Pengadaan dan Pemasangan Corrugated Pipe dia. 1000 mm thickness 3,5 mm 0.479 PLAN 0.23939 0.23939

40 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Urugan pasir tebal 10 cm 0.022 0.02199

41 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Lantai kerja mutu beton K125, Tebal 5 cm 0.049 0.04886

42 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh m6x150, cast in place, K-250 1.984 0.39688 0.39688 0.39688 0.39688 0.39688

43 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Mengurug kembali bekas galian menggunakan tanah bekas galian 0.098 0.0985

PEK. U-DRAIN
44 + RAMBU -RAMBU di ROW AS KP 2+400 - Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton mutu K225 ukuran 0,5x0,5x0,4
0.023(m) 0.023

45 PEK. BRONJONG di ROW AS KP 2+400 - Galian tanah dengan alat berat 0.425 0.212 0.212

46 PEK. BRONJONG di ROW AS KP 2+400 - Pengadaan + Pemancangan Mini Pile Persegi 20 x 20 cm, panjang 6.0 m 13.171 2.1952 2.1952 2.1952 2.1952 2.1952 2.1952

47 PEK. BRONJONG di ROW AS KP 2+400 - Kawat Bronjong Galvanized 2 x 1 x 0,5 (m) dia. 2,7 mm + Batu Pecah 10.711 1.33892 1.33892 1.33892 1.33892 1.33892 1.33892 1.33892 1.33892
ACTUAL 0.08885 0.08885 0.08885 0.08885 0.08885 0.08885 0.08885 0.08885
48 PEK. BRONJONG di ROW AS KP 2+400 - Lapisan Geotextile di depan pasangan Gabion (vertikal) 0.711

49 PEK. BRONJONG di ROW AS KP 2+400 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 1.894 0.94688 0.94688

50 Pengadaan dan Pemasangan Corrugated Pipe dia. 1500 mm thickness 3,5 mm 0.672 0.336 0.336

Total 100.000
Plan 3.202 2.821 1.467 1.467 1.467 3.800 5.113 3.587 3.478 3.500 4.633 5.274 5.274 4.759 1.872 1.668 1.668 1.668 2.766 1.276 2.599 2.505 1.824 3.775 2.224 2.215 4.052 4.052 4.148 1.993 1.450 1.428 1.477 1.450 1.393 1.344 0.397 0.397 0.495 0.023

Actual - - 1.3207 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Commulative Plan 3.20 6.02 7.49 8.96 10.42 14.22 19.34 22.93 26.40 29.90 34.54 39.81 45.09 49.84 51.72 53.38 55.05 56.72 59.49 60.76 63.36 65.87 67.69 71.46 73.69 75.90 79.95 84.01 88.15 90.15 91.60 93.03 94.50 95.95 97.34 98.69 99.09 99.48 99.98 100.00

Commulative Actual - - 1.321

Deviation - 6.17

Aceh Timur, 26 Januari 2023

PT. ADAM GLOBAL MANDIRI


Disetujui Oleh;

Dibuat oleh,

Aris Munandar TEUKU MUSTAFA KAMAL


Project Control Project Manager
DAILY ACTIVITY REPORT
CONSTRUCTION PT. ADAMGLOBAL MANDIRI
Contractor & Leveransir
BLOCK A GAS DEVELOPMENT PROJECT
LOCATION : BLOCK A PAGE : 1 of 3
REPORT NO. : 001-AGM-CVL/I/2023 DATE : 28 JANUARY 2023 / SATURDAY
CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASE III

WORKING HOUR : 08:00 - 18:00

Progres Realisasi %
No Description Satuan Volume Remaks
Previous Today Cumulative

PEK. SHEET PILE di ROW AS KP


1+500 - Pengadaan dan pemancangan - jam 08.00 s/d 12.00 kondisi lapangan
21 Ls 1.00 1.101 0.220 1.321
Sheet Pile Steel Metal Type III 400 x 100 Lokasi mendung
x 10.5mm, Length 12 m
- jam 14.00 s/d 17.00 kondisi lapangan
21a Mobilisasi Alat Crane Cpp lokasi kerja Mendung, Kegiatan penurunan alat crane dari
Trailer bisa dilakukan

21b Stake Out Lokasi - Minus Pekerjaan 6.17 %

DIBUAT OLEH ; DISETUJUI OLEH ;

ARIS MUNANDAR TEUKU MUSTAFA KAMAL


Project Control Project Manager
DAILY ACTIVITY REPORT
CONSTRUCTION PT. ADAM GLOBAL MANDIRI
Contractor & Leveransir
BLOCK A GAS DEVELOPMENT PROJECT
LOCATION : BLOCK A PAGE : 2 of 3
REPORT NO. : 001-AGM-CVL/I/2023 DATE : 28 JANUARY 2023 / SATURDAY
CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASE III
: 08:00 - 18:00
WORKING HOUR : 08:00 - 18:00

ACTIVITIES AREA OF CONCERN


No. Today Activities No. Description
PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III
21 Setting Alat Crane
400 x 100 x 10.5mm, Length 12 m
- Membuat area dudukan crane di lokasi kerja Membuat Dudukan Landasan Crane
- Setting Crane

No. Plan Activities WEATHER


TIME CLEAR CLOUDY RAIN
PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III 400 x 100 x 10.5mm, Length 12
21
m
- Simulasi alat Crane untuk pemancangan
- Pemancanngan Sheet Pile

07:00 - 12:00 Clear


13:00 - 17:00 Clear
18:00 - 24:00
DAILY ACTIVITY REPORT
CONSTRUCTION PT. ADAM GLOBAL MANDIRI
Contractor & Leveransir
BLOCK A GAS DEVELOPMENT PROJECT
LOCATION : BLOCK A PAGE : 3 of 3
REPORT NO. : 001-AGM-CVL/I/2023 DATE : 28 JANUARY 2023 / SATURDAY
CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASE III

WORKING HOUR 08:00 - 18:00

NA
PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III
III 400 x 100 x 10.5mm, Length 12 m 400 x 100 x 10.5mm, Length 12 m
Mobilisasi alat crane dari pereulak ke cpp lokasi kerja Mobilisasi alat crane dari pereulak ke cpp lokasi kerja

Row Kp 1 + 500 Row Kp 1 + 500


Penurunan alat Crane Stake lokasi Penentuan elevasi pemancangan sheet dan titik pemancangan
DAILY ACTIVITY REPORT CONSTRUCTION
PT. ADAM GLOBAL MANDIRI
Contractor & Leveransir
DATA POB & HSE STATISTIC

LOCATION : BLOCK -A SITE DEVELOPMENT PROJECT REPORT NO. : 001-AGM-CVL/I/2023


CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASEE III
DATE : 26 JANUARY 2023 / THURSDAY WORKING HOUR : 08 : 00 - 18 : 00

PERSONNEL HSE
Manpower Manhours Remarks HSE Statistic
No. Description
Unit Today Unit Prev. Today Cum. No Description Unit Total
A PT. ADAM GLOBAL MANDIRI
Indirect 1 Fatality - -

1 Project Manager Person M/H 59 8 67 T. Mustafa Kamal 2 Lost Time Incident - -

2 Site Manager Person 1 M/H 57 8 65 Indra Saputra 3 RWI (Restricted Work Incident) - -
3 Project Control Person 1 M/H 56 8 64 Aris Munandar 4 Medical Treatment Incident - -
4 Quality Control Person 1 M/H 57 8 65 Fajar Kurniawan 5 Firt Aid - -
5 Supervisor Person 2 M/H 65 8 73 Baihaqqi 5 Traffic Incident - -
6 Safety Officer Person 1 M/H 65 8 73 Abdul Khalik 7 Fire / Explotion - -
7 Safety Man Person 1 M/H 65 8 73 Usman 8 Enviromenmental Incident - -
8 Administrasi Person M/H 52 8 60 Chairul Fattaya 9 Near Miss - -
10 Equipment Incident - -
11 Property Damage - -

Total Indirect 7 476 64 540 EQUIPMENT


B Direct No Equipment & Tools Unit Qty
1 Foreman Person 1 M/H 57 8 65 Sofyan 1 Pick Up Double Cabin 4 x 4 Unit 1
2 Driver Person 1 M/H 35 8 43 Bactiar 2 Excavator Unit 1
3 Op Crane Person 1 M/H 8 8 16 Obbi 3 Truck Trailer Unit 1
4 Rigger Person 1 M/H 48 8 56 Usman 4 Crane Unit 3
5 Helper Person 1 M/H 122 8 130 Rio Wirandani 5 Webbing Sling Pcs 3
6 Op Excavator Person 1 M/H 41 8 49 Jefri Irawan Sakle
7 Op Excavator Person 1 M/H 40+8 8 8
8 Helper Crane Person 1 M/H 8 8 16

Total Direct 8 319 64 383


Total Manpower 15 795 128 923
SCHEDULE
ROW SLOPE REINFORCEMENT PHASE III
Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Agust-23 Sep-23 Okt-23
No. Description Work (%) REMARK
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

1 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Galian tanah dengan alat berat 0.014 0.014
100
2 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Urugan pasir tebal 10 cm 0.006 0.006

3 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Lantai kerja mutu beton K125, Tebal 5 cm 0.014 0.014

4 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh M6x150, cast in place, K-250 0.531 0.133 0.133 0.133 0.133

5 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200- Mengurug kembali bekas galian menggunakan tanah bekas galian 0.028 0.028

0.016
6 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+200- Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton 0.016
mutu K225 ukuran 0,5x0,5x0,4 (m) 90
7 PEK. BRONJONG di ROW AS KP 1+200 - Galian tanah dengan alat berat 0.091 0.091

8 PEK. BRONJONG di ROW AS KP 1+200 - Pengadaan + Pemancangan Micro Pile Ø10 cm, 3 buah untuk 1 m dengan kedalaman 5 m 2.627 0.657 0.657 0.657 0.657

9 PEK. BRONJONG di ROW AS KP 1+200 - Kawat Bronjong Galvanized 2 x 1 x 0,5 (m) dia. 2,7 mm + Batu Pecah 3.543 0.886 0.886 0.886 0.886

10 PEK. BRONJONG di ROW AS KP 1+200 - Lapisan Geotextile di depan pasangan Gabion (vertikal) 0.226 0.056 0.056 0.056 0.056

11 PEK. BRONJONG di ROW AS KP 1+200 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 0.066 0.066
80
12 Survey Micro Tremor 1.896 0.9482 0.9482

13 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Galian tanah dengan alat berat 0.034 0.0342

14 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Urugan pasir tebal 10 cm 0.015 0.0154

15 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Lantai kerja mutu beton K125, Tebal 5 cm 0.034 0.0342

16 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh M6x150, cast in place, K-250 1.290 0.430 0.430 0.430
70
17 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500- Mengurug kembali bekas galian menggunakan tanah bekas galian 0.069 0.069

18 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+500- Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton 0.016
mutu K225 ukuran 0,5x0,5x0,4 (m) 0.016

19 PEK. GUARD POST + RAMBU -RAMBU di ROW AR STA 12+350 & STA 12+390 - Guard Post dari pipa besi dia. 4" (sesuai gambar) + pondasi ukuran
1.653 0,35 x 0,35 x 1,2 (m) concrete K225 dengan pembesian dia. 10 mm dan stirrups dia. 6 mm. 0.551 0.551 0.551

20 PEK. SHEET PILE di ROW AS KP 1+500 - Galian tanah dengan alat berat 0.267 0.267

21 PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Prestress Concrete type A W-350, Length 12 m 0.000
60
22 PEK. SHEET PILE di ROW AS KP 1+500 - Penanganan Kepala Sheet Pile (Sheet Pile Head Treatment) 0.000
2.530 2.530 4.286 4.286 4.286 4.286 4.286 4.286 4.286
23 PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III 400 x 100 x 10.5mm, Length 12 35.061
m 5.259 0.701

24 PEK. SHEET PILE di ROW AS KP 1+500 - Pekerjaan beton Pile Cap, Multipleks 9mm, Pembesian D16 mm , Cast in Place, K-300 1.831 0.9155 0.9155

25 PEK. SHEET PILE di ROW AS KP 1+500 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 0.127 0.1271

26 PEK. SHEET PILE di ROW AS KP 1+500 - Penggalian existing soil material di badan ROW 1.659 1.6594
50
27 PEK. SHEET PILE di ROW AS KP 1+500 - Pembuangan soil material 1.659 0.830 0.830

28 PEK. SHEET PILE di ROW AS KP 1+500 - Penggantian soil material di badan ROW dan dipadatkan CBR Min. 95% 2.157 0.719 0.719 0.719

29 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Galian tanah dengan alat berat 0.015 0.015

30 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Urugan pasir tebal 10 cm 0.007 0.007

31 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Lantai kerja mutu beton K125, Tebal 5 cm 0.015 0.015
40
32 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh M6x150, cast in place, K-250 0.626 0.156 0.156 0.156 0.156

33 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800- Mengurug kembali bekas galian menggunakan tanah bekas galian 0.031 0.031

34 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 1+800- Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton 0.016
mutu K225 ukuran 0,5x0,5x0,4 (m) 0.016

35 PEK. BRONJONG di ROW AS KP 1+800 - Galian tanah dengan alat berat 0.176 0.088 0.088

36 PEK. BRONJONG di ROW AS KP 1+800 - Pengadaan + Pemancangan Micro Pile Ø10 cm, 3 buah untuk 1 m dengan kedalaman 5 m 13.476 1.684 1.684 1.684 1.684 1.684 1.684 1.684 1.684

1.098 1.098 1.098 1.098 1.098 1.098 1.098 1.098


30
37 PEK. BRONJONG di ROW AS KP 1+800 - Kawat Bronjong Galvanized 2 x 1 x 0,5 (m) dia. 2,7 mm + Batu Pecah 8.783

38 PEK. BRONJONG di ROW AS KP 1+800 - Lapisan Geotextile di depan pasangan Gabion (vertikal) 0.568 0.071 0.071 0.071 0.071 0.071 0.071 0.071 0.071

39 PEK. BRONJONG di ROW AS KP 1+800 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 0.132 0.066 0.066

40 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Galian tanah dengan alat berat 0.034 0.034

41 Pengadaan dan Pemasangan Corrugated Pipe dia. 1000 mm thickness 3,5 mm 0.336 0.16777 0.1678

0.015 20
42 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Urugan pasir tebal 10 cm 0.015

43 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Lantai kerja mutu beton K125, Tebal 5 cm 0.034 0.034

44 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Saluran U-Ditch 500 x 500mm, thk 80mm, wiremesh m6x150, cast in place, K-250 1.391 0.2781 0.2781 0.27814 0.2781 0.27814

45 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Mengurug kembali bekas galian menggunakan tanah bekas galian 0.069 0.069

46 PEK. U-DRAIN + RAMBU -RAMBU di ROW AS KP 2+400 - Rambu Jalan Ganda dengan Permukaan Pemantul Engineer Grade + pondasi beton0.016
mutu K225 ukuran 0,5x0,5x0,4 (m) 0.016

47 PEK. BRONJONG di ROW AS KP 2+400 - Galian tanah dengan alat berat 0.298 0.149 0.149 10
48 PEK. BRONJONG di ROW AS KP 2+400 - Pengadaan + Pemancangan Mini Pile Persegi 20 x 20 cm, panjang 6.0 m 9.231 1.8461 1.84612 1.8461 1.84612 1.84612

49 PEK. BRONJONG di ROW AS KP 2+400 - Kawat Bronjong Galvanized 2 x 1 x 0,5 (m) dia. 2,7 mm + Batu Pecah 7.507 1.25112 1.2511 1.25112 1.25112 1.25112 1.2511

50 PEK. BRONJONG di ROW AS KP 2+400 - Lapisan Geotextile di depan pasangan Gabion (vertikal) 0.498 0.08302 0.083 0.08302 0.08302 0.08302 0.083

51 PEK. BRONJONG di ROW AS KP 2+400 - Hamparan / Urugan menggunakan "SIRTU" untuk lapisan diatas Jalan dipadatkan CBR Min. 95% 1.327 0.6636 0.66359

52 Pengadaan dan Pemasangan Corrugated Pipe dia. 1500 mm thickness 3,5 mm 0.471 0.23547 0.23547 0

Total 100.000
Plan 0.948 0.948 2.797 2.530 4.286 4.286 4.286 4.286 4.286 4.286 4.286 3.527 4.286 2.833 3.384 4.030 3.420 2.853 3.601 3.510 2.790 2.940 2.267 1.333 2.328 3.329 3.313 3.313 3.576 1.753 1.502 0.698 0.679 0.034 0.278 0.278 0.278 0.278 0.347 0.016
Actual - - 5.3 0.7 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Commulative Plan 0.95 1.90 4.69 7.22 11.51 15.80 20.08 24.37 28.65 32.94 37.22 40.75 45.04 47.87 51.25 55.29 58.71 61.56 65.16 68.67 71.46 74.40 76.67 78.00 80.33 83.66 86.97 90.28 93.86 95.61 97.11 97.81 98.49 98.52 98.80 99.08 99.36 99.64 99.98 100.00

Commulative Actual - - 5.26 5.96


Deviation 0.57

Kuta Binje, 29 Desember 2022


PT. ADAM GLOBAL MANDIRI
GRAND TOTAL Prepared By

TEUKU MUSTAFA KAMAL


Project Manager
DAILY ACTIVITY REPORT
CONSTRUCTION PT. ADAMGLOBAL MANDIRI
Contractor & Leveransir
BLOCK A GAS DEVELOPMENT PROJECT
LOCATION : BLOCK A PAGE : 1 of 3
REPORT NO. : 001-AGM-CVL/I/2023 DATE : 28 JANUARY 2023 / SATURDAY
CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASE III

WORKING HOUR : 08:00 - 18:00

Progres Realisasi %
No Description Satuan Volume Remaks
Previous Today Cumulative

PEK. SHEET PILE di ROW AS KP


1+500 - Pengadaan dan pemancangan - jam 08.00 s/d 12.00 kondisi lapangan
21 Ls 1.00 1.101 0.220 1.321
Sheet Pile Steel Metal Type III 400 x 100 Lokasi mendung
x 10.5mm, Length 12 m
- jam 14.00 s/d 17.00 kondisi lapangan
21a Mobilisasi Alat Crane Cpp lokasi kerja Mendung, Kegiatan penurunan alat crane dari
Trailer bisa dilakukan

21b Stake Out Lokasi - Minus Pekerjaan 6.17 %

DIBUAT OLEH ; DISETUJUI OLEH ;

ARIS MUNANDAR TEUKU MUSTAFA KAMAL


Project Control Project Manager
DAILY ACTIVITY REPORT
CONSTRUCTION PT. ADAM GLOBAL MANDIRI
Contractor & Leveransir
BLOCK A GAS DEVELOPMENT PROJECT
LOCATION : BLOCK A PAGE : 2 of 3
REPORT NO. : 001-AGM-CVL/I/2023 DATE : 28 JANUARY 2023 / SATURDAY
CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASE III
: 08:00 - 18:00
WORKING HOUR : 08:00 - 18:00

ACTIVITIES AREA OF CONCERN


No. Today Activities No. Description
PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III
21 Setting Alat Crane
400 x 100 x 10.5mm, Length 12 m
- Membuat area dudukan crane di lokasi kerja Membuat Dudukan Landasan Crane
- Setting Crane

No. Plan Activities WEATHER


TIME CLEAR CLOUDY RAIN
PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III 400 x 100 x 10.5mm, Length 12
21
m
- Simulasi alat Crane untuk pemancangan
- Pemancanngan Sheet Pile

07:00 - 12:00 Clear


13:00 - 17:00 Clear
18:00 - 24:00
DAILY ACTIVITY REPORT
CONSTRUCTION PT. ADAM GLOBAL MANDIRI
Contractor & Leveransir
BLOCK A GAS DEVELOPMENT PROJECT
LOCATION : BLOCK A PAGE : 3 of 3
REPORT NO. : 001-AGM-CVL/I/2023 DATE : 28 JANUARY 2023 / SATURDAY
CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASE III

WORKING HOUR 08:00 - 18:00

NA
PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type PEK. SHEET PILE di ROW AS KP 1+500 - Pengadaan dan pemancangan Sheet Pile Steel Metal Type III
III 400 x 100 x 10.5mm, Length 12 m 400 x 100 x 10.5mm, Length 12 m
Mobilisasi alat crane dari pereulak ke cpp lokasi kerja Mobilisasi alat crane dari pereulak ke cpp lokasi kerja

Row Kp 1 + 500 Row Kp 1 + 500


Penurunan alat Crane Stake lokasi Penentuan elevasi pemancangan sheet dan titik pemancangan
DAILY ACTIVITY REPORT CONSTRUCTION
PT. ADAM GLOBAL MANDIRI
Contractor & Leveransir
DATA POB & HSE STATISTIC

LOCATION : BLOCK -A SITE DEVELOPMENT PROJECT REPORT NO. : 001-AGM-CVL/I/2023


CLIENT : MEDCO E&P MALAKA SCOPE OF WORK : ROW SLOPE REINFORCEMENT PHASEE III
DATE : 26 JANUARY 2023 / THURSDAY WORKING HOUR : 08 : 00 - 18 : 00

PERSONNEL HSE
Manpower Manhours Remarks HSE Statistic
No. Description
Unit Today Unit Prev. Today Cum. No Description Unit Total
A PT. ADAM GLOBAL MANDIRI
Indirect 1 Fatality - -

1 Project Manager Person M/H 59 8 67 T. Mustafa Kamal 2 Lost Time Incident - -

2 Site Manager Person 1 M/H 57 8 65 Indra Saputra 3 RWI (Restricted Work Incident) - -
3 Project Control Person 1 M/H 56 8 64 Aris Munandar 4 Medical Treatment Incident - -
4 Quality Control Person 1 M/H 57 8 65 Fajar Kurniawan 5 Firt Aid - -
5 Supervisor Person 2 M/H 65 8 73 Baihaqqi 5 Traffic Incident - -
6 Safety Officer Person 1 M/H 65 8 73 Abdul Khalik 7 Fire / Explotion - -
7 Safety Man Person 1 M/H 65 8 73 Usman 8 Enviromenmental Incident - -
8 Administrasi Person M/H 52 8 60 Chairul Fattaya 9 Near Miss - -
10 Equipment Incident - -
11 Property Damage - -

Total Indirect 7 476 64 540 EQUIPMENT


B Direct No Equipment & Tools Unit Qty
1 Foreman Person 1 M/H 57 8 65 Sofyan 1 Pick Up Double Cabin 4 x 4 Unit 1
2 Driver Person 1 M/H 35 8 43 Bactiar 2 Excavator Unit 1
3 Op Crane Person 1 M/H 8 8 16 Obbi 3 Truck Trailer Unit 1
4 Rigger Person 1 M/H 48 8 56 Usman 4 Crane Unit 3
5 Helper Person 1 M/H 122 8 130 Rio Wirandani 5 Webbing Sling Pcs 3
6 Op Excavator Person 1 M/H 41 8 49 Jefri Irawan Sakle
7 Op Excavator Person 1 M/H 40+8 8 8
8 Helper Crane Person 1 M/H 8 8 16

Total Direct 8 319 64 383


Total Manpower 15 795 128 923