PERIODE 2 MEI S/D 7 MEI 2023 SCHEDULE PEKERJAAN MAPPING PEKERJAAN KURVA S DOKUMENTASI KEGIATAN 2 MEI S/D 7 MEI 2023
Selasa, 2 Mei 2023
- Tool Box Meeting - Safety induction pekerja baru - Wiring power DL-01 PTB L0 area toilet - Instalasi Power DL-01 PTB L0 area Waiting room DOKUMENTASI KEGIATAN 2 MEI S/D 7 MEI 2023
Rabu, 3 Mei 2023
- Tool box meeting - Koordinasi lapangan dengan Bp. Kardi PT. WG - Instalasi power DL-01A PTB L.0 - Piping power DL-01 PTB L.0 area mushola DOKUMENTASI KEGIATAN 2 MEI S/D 7 MEI 2023
Kamis, 4 Mei 2023
- Tool box meeting - Wiring power DL-01 PTB L.0 area toilet - Instalasi power DL-01a PTB L.0 - Piping power PTB L.0 area toilet difable DOKUMENTASI KEGIATAN 2 MEI S/D 7 MEI 2023
Jum’at, 5 Mei 2023
- Tool box meeting - Weekly meeting lapangan bersama PT. WG & Subkon lain - Instalasi data DL-01 PTB L.0 area toilet - Instalasi power DL-01 PTB L.0 area toilet difable - Wiring power PTB L.0 as 5 DOKUMENTASI KEGIATAN 2 MEI S/D 7 MEI 2023
Sabtu, 6 Mei 2023
- Tool box meeting - Instalasi power DL-01 PTB L.0 area toilet wanita - Instalasi power Dl-01a PTB L.0 as 7-8 - Instalasi data DL-01 PTB L.0 area toilet - Wiring power DL-02 PTB L.0 as 6-7 - Pengecekan sparingan area floor DOKUMENTASI KEGIATAN 2 MEI S/D 7 MEI 2023
Minggu, 7 Mei 2023
- Tool box meeting - Wiring power DL-02 PTB L.0 as 7 - Piping data DL-02 PTB L.0 as 5-6 - Wiring power Dl-01a PTB L.0 as 5 - Piping power Dl-01a PTB L.0 as 9 - Piping power & data Dl-01 PTB L.0 area ruang menyusui KEGIATAN HSE
Minggu, 7 Mei 2023
- Inspeksi & tagging Bodyharness - Cek Kesehatan & WG KENDALA - Material Tray ditolak WG-Kandu dikarenakan tidak sesuai dengan Approval material dari WG - Shop drawing VVIP masih dikandu - Masih menunggu Shop drawing Special Lighting Interior VVIP dari MPP dan SI dari WG - Titik Saklar khusus ditoilet Belum ada info dari WG - Approval material kabel kontrol menunggu persetujuan dari PT Kandu