B Pekerjaan Tanah
1 pekerjaan pondasi tapak tipe 1 ( jumlah pondasi 32 unit )
a.galian pondasi tapak 186.62 M³
b.urugan kembali galian pondasi tapak 139.96 M³
c. pasir Alas/ Urug 8.18 M³
d. Pas batu kosong 10.37 M³
e. lantai kerja 5.18 M³
f. Pondasi uk. 170 x 170 cm
a. ( Bagian 1) 36.92 M³
b. (Bagian 2) 10.62 M³
g. Tiang Poor 6.66 M³
LANTAI 1
C PEKERJAAN BETON BERTULANG LANTAI 1
1 SLOFF
a. Sloof 25/40 7.22 M³
b. Sloof gantung 20/30 4.06 M³
c. Sloof gantung 25/40 13.26 M³
2 KOLOM
a. Kolom 35/35 (K1) 16.07 M³
b. Kolom 30/60 (K2) 23.61 M³
c. Kolom 13/13(K4) 2.77 M³
REKAPITULASI VOLUME
No. Uraian Volume Sat.
1 2 3 4
D PEKERJAAN PASANGAN DAN PLASTERAN
a. Pasangan Dinding 1/2 Bata 1:2 144. 60 M³
b. Pasangan Dinding 1/2 Bata 1:2 (Selasar) 10.43 M³
c. Pasangan Dinding 1/2 Bata 1:4 604.28 M³
d. Plasteran 1:2 192.80 M³
e. Plasteran 1:2 selasar 20.86 M³
f. Plasteran 1:4 577.47 M³
G PEKERJAAN PLAFOND
a. Rangka plafond lantai 274.42 M2
b, Rangka plafond selasar 29.04 M2
c. Total volume list Profil 303.46 M2
REKAPITULASI VOLUME
No. Uraian Volume Sat.
1 2 3 4
H PEKERJAAN PINTU, JENDELA, VENTILASI
a. Pemasangan Kusen pintu, Jendela, dan Ventilasi
1. Kusen pintu tipe 1 ( 3 unit) 0.13 M³
Daun pintu 5.46 M³
2. Kusen pintu tipe 2 (2 unit) 0.12 M³
Daun pintu 5.04 M³
3. Kusen pintu tipe 3 (7 unit) 0.37 M³
Daun pintu 12.94 M³
4. Kusen pintu tipe 4 ( 11 unit) 0.42 M³
Daun pintu 16.17 M³
5. Kusen Jendela J1 ( 4 unit) 0.23 M³
Daun jendela 6.10 M³
6. Kusen Jendela J2 (11 unit) 0.33 M³
Daun jendela 7.43 M³
7. Kusen Jendela J3 (1 unit) 0.06 M³
Daun jendela 0.76 M³
8. Kusen Jendela J4 (1 unit) 0.03 M³
9. Kusen pintu/ jendela PJ1 (2 unit) 0.19 M³
Daun pintu/Jendela 19.94 M³
10. Kusen ventilasi tipe V1 (9 unit) 0.15 M³
Daun ventilasi 2.25 M³
11. Kusen ventilasi tipe V2 (1 unit) 0.07 M³
Daun ventilasi 0.85 M³
12. Kusen ventilasi tipe V3 ( 3 unit) 0.07 M³
LANTAI 11
A PEKERJAAN BETON BERTULANG LANTAI 11
1 BALOK
a. Balok 25/40 (B1) 19.40 M³
b. Balok 20/30 (B2) 3.03 M³
c. Balok Latai 15/20 (B3) 5.41 M³
d. Plat lantai 29. 58 M³
2 KOLOM
a. Kolom 35/35 (K1) 9.60 M³
b. Kolom 20/20 (K3) 3.20 M³
c. Kolom Praktis 13/13 (K4) 1.37 M³
d. Ring Balok 20/30 (RB1) 12.28 M³
e. Ring Balok 15/20 (RB2) 2.03 M³
f. Plat lantai di kurangi void 30.83 M³
REKAPITULASI VOLUME
No. Uraian Volume Sat.
1 2 3 4
B PEKERJAAN PASANGAN DAN PLASTERAN
a.Pasangan Dinding 1/2 Bata 1:4 580.00 M³
b. Plasteran 567.23 M³
C PEKERJAAN KUSEN
Lantai l l
1. Kusen pintu tipe 1 ( 1 unit) 0.06 M³
Daun pintu tipe 1 2.73 M³
2. Kusen pintu tipe 2 (3 unit) 0.18 M³
Daun pintu tipe 2 7.56 M³
3. Kusen pintu tipe 3 (7 unit) 0.37 M³
Daun pintu tipe 3 12.94 M³
4. Kusen pintu tipe 4 ( 9 unit) 0.34 M³
Daun pintu tipe 4 13.32 M³
5. Kusen Jendela J1 ( 3 unit) 0.17 M³
Daun Jendela tipe 1 4.58 M³
6. Kusen Jendela J2 (10 unit) 0.30 M³
Daun Jendela tipe 2 7.43 M³
7. Kusen ventilasi tipe V1 (7 unit) 0.12 M³
Daun Ventilasi tipe 1 2.25 M³
8. Kusen ventilasi tipe V3 ( 2 unit) 0.04 M³
9. Kusen ventilasi tipe V4 ( 3 unit) 0.15 M³
D PENGECATAN
1. Total Pengecatan Kusen Pintu 94.54 M2
2. Total Pengecatan Kusen Jedelas 39.40 M2
3. Total Pengecatan Kusen Ventilasi 14.280 M2
4. Pengecatan Dinding Lantai 1 577.470 M2
5. Pengecatan Dinding Lantai 11 567.230 M2
E PEKERJAAN PLAFOND
c. Rangka plafond lantai 11 274.42 M2
d. plafond luar atap 86.61 M2
e. Total volume list profil 361.03 M2
G PEKERJAAN ELEKTRIKAL
a. Pekerjaan Instalasi Panel
1. Box panel 2.00 Unit
2. Kabell out put 2.00 m
3. Kabel in put 2.00 m
Jenis Pekerjaan : Membuat Beton Mutu F'c = 7,4 Mpa (K 100), Slump (12 ± 2) cm, W/c = 0,87
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.1
Jenis Pekerjaan : Membuat Beton Mutu F'c = 9,8 Mpa (K 125), Slump (12 ± 2) cm, W/c = 0,78
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.2
Jenis Pekerjaan : Membuat Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jenis Pekerjaan : Membuat Beton Mutu F'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, W/c = 0,61
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.6
Jenis Pekerjaan : Membuat Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7
Jenis Pekerjaan : Membuat Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jenis Pekerjaan : Membuat Beton Mutu F'c = 24,0 Mpa (K 275), Slump (12 ± 2) cm, W/c = 0,53
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jenis Pekerjaan : Membuat Beton Mutu F'c = 26,4 Mpa (K 300), Slump (12 ± 2) cm, W/c = 0,52
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 2 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.7
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 3 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.8
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 4 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9
Jenis Pekerjaan : Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 5 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.10
Jenis Pekerjaan : Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas I
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.1
Jenis Pekerjaan : Membuat dan Memasang Daun Pintu Panel Kayu Kelas II
Satuan / Unit : M2
Analisa : AHSP PU A.4.6.1.5
Jenis Pekerjaan : Memasang listplank Uk. 2.5 x 20 Cm Kayu Kelas I atau Kelas II
Satuan / Unit : M'
Analisa : AHSP PU A.4.6.1.21
Jenis Pekerjaan : Pengecatan Bidang kayu Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4
Jenis Pekerjaan : Pengecetan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
B. HARGA BAHAN
1 Air Liter 120.00
2 Batu Bata Buah 700.00
3 Batu Kali/Batu Belah (Sungai/Gunung) M³ 180,000.00
4 Batu Belah 5 - 7 cm M³ 170,000.00
5 Batu Pecah 2 - 3 Cm M³ 325,000.00
6 Besi Beton Polos Kg 12,000.00
7 Besi Beton Ulir Kg 15,000.00
8 Bubungan Genteng M¹ 3,000.00
9 Bubungan Seng M¹ 35,000.00
10 Cat Dasar Tembok/Sealer Setara Vinilex Kg 25,000.00
11 Cat Kayu Dasar Kg 40,000.00
12 Cat Kayu Mengkilat Kg 55,000.00
13 Cat Menie besi Kg 30,000.00
14 Cat Tembok Setara Vinilex Kg 25,000.00
15 Dempul Kayu Kg 16,000.00
16 Dolken Kayu ø 8 -10/400 cm Batang 62,000.00
17 Door Holder Pasang 120,000.00
18 Engsel Jendela Pasang 22,000.00
19 Engsel Pintu Pasang 22,000.00
20 Floor Drain Buah 20,000.00
21 Gypsum Board tebal 9 mm Lembar 90,000.00
22 Jaring Kawat Baja Kg 25,000.00
23 Hak Angin Pasang 14,000.00
24 Kaca Bening Uk. 3 mm M² 75,000.00
25 Kaca Bening Uk. 5 mm M² 100,000.00
26 Kaca Rayband Uk. 5 mm M² 120,000.00
27 Kaso- kaso ( 5 x 7 ) cm M³ 3,000,000.00
28 Kawat Beton Kg 20,000.00
29 Kayu Bakau 10 Cm Batang 50,000.00
30 Kayu Klas I ( Seumantok / Ulim / dll ) M³ 5,500,000.00
31 Kayu Klas II ( Kamper / Kruing / dll ) M³ 4,500,000.00
32 Kayu Klas III ( Borneo / dll ) M³ 3,800,000.00
33 Kayu Klas IV ( Sengon / dll ) M³ 3,000,000.00
34 Keramik Non Pholised 20 X 20 Cm Setara I Bh 4,000.00
35 Keramik Uk. 40 X 40 Cm Bh 10,500.00
36 Keramik Uk. 20 x 25 Cm Bh 3,500.00
37 Keramik Uk. 30 x 30 cm Bh 6,200.00
38 Kertas Amplas Lembar 3,400.00
39 Kloset Duduk Keramik Setara toto + Tabun Buah 1,350,000.00
40 Klost Jongkok Keramik Setara toto Buah 350,000.00
41 Kran Air 3/4" Buah 12,000.00
42 Kuas Cat Buah 15,000.00
43 Kunci Pintu (standar) Buah 125,000.00
44 Kunci Pintu Biasa Buah 85,000.00
45 Lampu Hemat Energi 11 watt setara hanno Buah 30,000.00
46 Lampu Hemat Energi 18 watt setara hanno Buah 40,000.00
47 Lampu hemat Energi 20 watt setara hanno Buah 45,000.00
48 Lem Kayu Kg 18,000.00
49 List Eternit Kayu M¹ 7,000.00
50 Minyak Cat Liter 23,000.00
51 Minyak Bekisting Liter 10,410.00
52 Multipleks 3 mm Lembar 70,000.00
53 Multipleks 4 mm Lembar 75,000.00
54 Multipleks 6 mm Lembar 105,000.00
55 Multipleks 9 mm Lembar 140,000.00
56 Pacok Jendela dan Ventilasi Pasang 7,500.00
57 Paku Asbes Kg 18,000.00
58 Paku Beton 8 Inci Kotak 18,000.00
59 Paku Kait Buah 1,080.00
60 Paku Kayu Kg 17,500.00
61 Paku Triplek Kg 17,000.00
62 Paku Seng Kg 19,400.00
63 Paku Sumbat Buah 1,200.00
64 Paku Sekrup Kg 24,200.00
65 Pasir Batu ( Sirtu ) - Material Jalan M³ 314,800.00
66 Pasir Beton / Kerikil M³ 178,000.00
67 Pasir Pasang M³ 178,000.00
68 Pasir Urug M³ 98,000.00
73 Plamur Tembok Kg 30,000.00
74 Plin Keramik Buah 16,400.00
75 Plywood tebal 9 mm Lembar 140,000.00
76 Residu Kg 15,000.00
77 Reservoir Air 500 ltr Buah 1,100,000.00
78 Reservoir Air 1000 ltr Buah 1,800,000.00
79 Reservoir Air 500 ltr Stainless Steel Buah 1,960,000.00
80 Schakelar Buah 12,500.00
81 Semen @ 40 Kg Zak 55,000.00
82 Semen @ 50 Kg Zak 1,375.00
83 Semen Putih @ 50 Kg Zak 220,000.00
84 Semen Warna Kg 4,400.00
85 Seng Genteng Metal M² 65,000.00
86 Seng BJLS 0,20 Cat Pabrik M² 47,000.00
87 Seng Gelombang BJLS 30 M² 50,000.00
88 Seng Gelombang BJLS 30 Cat Pabrik M² 54,000.00
89 Seng Plat BJLS 20 M² 41,000.00
90 Seng Plat BJLS 30 M² 52,000.00
91 Stut Werk (Ska Folding) M³ 2,500,000.00
92 Sekrup fixer Buah 500.00
93 Sealant Kg 15,500.00
94 Tanah Timbun M³ 65,000.00
95 Teralis Besi M² 375,000.00
96 Titik Lampu + Instalasi Titik 150,000.00
97 Urinoir Keramik Buah 1,100.00
98 Zakering ( Kast Lokal 1 Zekering ) Buah 250,000.00
99 Zakering ( Kast Lokal 2 Zekering ) Buah 400,000.00
100 Pemasangan Atap Baja Ringan M² 250,000.00
C. ALAT
1 Stamper Jam 125,000.00
2 Dump Truck Jam 225,000.00
3 Molen Jam 50,000.00
BILL OF QUANTITY (BOQ)
Harga Satuan Jumlah Harga
No. Uraian Volume Sat. Analisa
(Rp.) (Rp.)
1 2 3 4 5 6 7=(3x6)
I LANTAI I
A PEKERJAAN TANAH
Jumlah Rp 15,568,253.25
B PEKERJAAN PONDASI
Timbunan Pasir Bawah Pondasi Tapak 5.55 M³ AHSP PU A.2.3.1.11 Rp 142,450.00 Rp 790,170.15
Timbunan Pasir Bawah Pondasi Menerus 3.07 M³ AHSP PU A.2.3.1.11 Rp 142,450.00 Rp 437,036.60
Jumlah Rp 25,747,783.30
C PEKERJAAN STRUKTUR PONDASI
Pondasi Tapak tipe 1
Beton K-250 52.49 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 54,200,421.00
Besi Tulangan Pokok Ø 16 4139.92 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 59,399,536.53
Bekisting + Perawatan Beton 131.22 M³ AHSP PU A.4.1.1.20 Rp 233,821.00 Rp 30,681,991.62
jumlah Rp 144,281,949.15
Pondasi Tapak tipe 2
Beton K-250 4.85 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 5,010,296.50
Besi Tulangan Pokok Ø 14 234.40 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 3,363,178.49
Bekisting + Perawatan Beton 9.70 M³ AHSP PU A.4.1.1.20 Rp 233,821.00 Rp 2,268,998.98
jumlah Rp 10,642,473.98
Pondasi Menerus
Galian Pondasi menerus 61.173 M³ AHSP PU A.2.3.1.8 Rp 62,125.00 Rp 3,800,372.63
Pasir Alas pondasi menerus 3.07 M³ AHSP PU A.2.3.1.11 Rp 142,450.00 Rp 437,036.60
Pas Batu kosong 8.88 M³ AHSP PU A.3.2.1.9 Rp 371,631.00 Rp 3,300,083.28
Pas batu gunung 22.743 M³ AHSP PU A.3.2.1.2 Rp 901,750.00 Rp 20,508,500.25
Timbunan 15.293 M³ AHSP PU A.2.3.1.11.a Rp 102,850.00 Rp 1,572,885.05
jumlah Rp 29,618,877.81
Total keseluruhan Rp 184,543,300.93
D PEKERJAAN BETON LANTAI 1
Sloof (25/40)
Beton K-250 7.22 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 7,455,552.50
Besi Tulangan Pokok Ø 16 797.64 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 11,444,574.53
Besi Tulangan Sengkang Ø 8 3279.31 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 47,051,507.05
Besi Tulangan Pinggang Ø 14 174.48 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 2,503,500.68
Bekisting + Perawatan Beton 28.88 M³ AHSP PU A.4.1.1.21 Rp 252,821.00 Rp 7,301,470.48
jumlah Rp 75,756,605.24
Sloof (20/30)
Beton K-250 4.068 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 4,200,718.50
Besi Tulangan Pokok Ø 16 535.02 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 7,676,515.17
Besi Tulangan Sengkang Ø 8 227.84 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 3,269,043.98
Besi Tulangan Pinggang Ø 14 163.85 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 2,350,932.77
Bekisting + Perawatan Beton 20.34 M³ AHSP PU A.4.1.1.21 Rp 252,821.00 Rp 5,142,379.14
jumlah Rp 22,639,589.56
Sloof (25/40)
Beton K-250 13.26 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 13,692,607.50
Besi Tulangan Pokok Ø 16 1464.92 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 21,018,706.14
Besi Tulangan Sengkang Ø 8 6022.66 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 86,413,155.60
Besi Tulangan Pinggang Ø 14 320.45 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 4,597,841.97
Bekisting + Perawatan Beton 53.04 M³ AHSP PU A.4.1.1.21 Rp 252,821.00 Rp 13,409,625.84
jumlah Rp 139,131,937.05
Kolom K1 (35/35)
Beton K-250 16.07 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 16,596,349.00
Besi Tulangan Pokok Ø 14 1268.27 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 18,197,190.53
Besi Tulangan Sengkang Ø 8 435.97 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 6,255,284.25
Besi Tulangan Pinggang Ø 14 634.14 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 9,098,595.27
Bekisting + Perawatan Beton 91.84 M³ AHSP PU A.4.1.1.22 Rp 497,447.00 Rp 45,685,532.48
jumlah Rp 95,832,951.52
Kolom K2 (30/60)
Beton K-250 23.62 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 24,386,472.00
Besi Tulangan Pokok Ø 14 951.21 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 13,647,892.90
Besi Tulangan Sengkang Ø 14 584.23 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 8,382,591.52
Besi Tulangan Pinggang Ø 14 1268.27 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 18,197,190.53
Bekisting + Perawatan Beton 118.08 M³ AHSP PU A.4.1.1.22 Rp 497,447.00 Rp 58,738,541.76
jumlah Rp 123,352,688.71
BILL OF QUANTITY (BOQ)
Harga Satuan Jumlah Harga
No. Uraian Volume Sat. Analisa
(Rp.) (Rp.)
1 2 3 4 5 6 7=(3x6)
Kolom K4 (13/13)
Beton K-250 2.77 M³ AHSP PU A.4.1.1.8 Rp 1,032,625.00 Rp 2,860,371.25
Besi Tulangan Pokok Ø 14 582.03 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 8,351,029.10
Besi Tulangan Sengkang Ø 8 159.73 Kg AHSP PU A.4.1.1.17 Rp 14,348.00 Rp 2,291,833.23
Bekisting + Perawatan Beton 42.62 M³ AHSP PU A.4.1.1.22 Rp 497,447.00 Rp 21,198,895.23
jumlah Rp 34,702,128.80
Total Keseluruhan` Rp 843,577,635.29
E PEKERJAAN PASANAGAN DAN PLASTERAN
a. Pasangan Dinding 1/2 Bata 1:2 144.60 M³ AHSP PU A.4.4.1.7 Rp 119,295.25 Rp 17,250,093.15
b. Pasangan Dinding 1/2 Bata 1:4 604.28 M³ AHSP PU A.4.4.1.9 Rp 109,941.50 Rp 66,435,449.62
c. Pasangan Dinding 1/2 Bata 1:2 (Selasar) 10.43 M³ AHSP PU A.4.4.1.7 Rp 119,295.25 Rp 1,244,249.46
d. Plasteran 1:2 selasar 20.86 M³ AHSP PU A.4.4.2.2 Rp 61,193.00 Rp 1,276,485.98
e. Plasteran 1:4 577.47 M³ AHSP PU A.4.4.2.4 Rp 56,427.00 Rp 32,584,899.69
jumlah Rp 118,791,177.90
F PLAT LANTAI
Beton K-250 30.83 M³ AHSP PU A.4.1.1.8 Rp 1,035,583.00 Rp 31,927,023.89
Pembesian Tulangan Pokok Ø 12 4,208.66 Kg AHSP PU A.4.1.1.17 Rp 14,452.00 Rp 60,823,626.00
Bekisting + Perawatan Beton 308.30 M³ AHSP PU A.4.1.1.24 Rp 750,583.00 Rp 231,404,738.90
jumlah Rp 324,155,388.79
G PLAT TANGGA
Beton K - 175 1.63 M³ AHSP PU A.4.1.1.5 Rp 965,157.00 Rp 1,573,205.91
Pembesian Tulangan Pokok Ø 12 222.51 Kg AHSP PU A.4.1.1.17 Rp 14,452.00 Rp 3,215,780.42
Bekisting + Perawatan 16.30 M² AHSP PU A.4.1.1.26 Rp 460,638.50 Rp 7,508,407.55
Anak Tangga
Beton K - 175 1.42 M³ AHSP PU A.4.1.1.5 Rp 965,157.00 Rp 1,370,522.94
Pembesian Tulangan Ø 12 193.85 Kg AHSP PU A.4.1.1.17 Rp 14,452.00 Rp 2,801,477.42
Bekisting + Perawatan 14.20 M³ AHSP PU A.4.1.1.26 Rp 460,638.50 Rp 6,541,066.70
jumlah Rp 23,010,460.94
H BALOK BORDES 18/25
Beton K-175 0.09 M³ AHSP PU A.4.1.1.5 Rp 965,157.00 Rp 86,864.13
Pembesian Tulangan Pokok Ø 12 7.10 M³ AHSP PU A.4.1.1.17 Rp 14,452.00 Rp 102,639.26
Pembesian Tulangan Sengkang Ø 8 4.31 Kg AHSP PU A.4.1.1.17 Rp 14,452.00 Rp 62,307.16
Bekisting + Perawatan 0.86 M³ AHSP PU A.4.1.1.23 Rp 252,821.00 Rp 217,426.06
Plat Bordes
Beton K-175 0.60 M³ AHSP PU A.4.1.1.5 Rp 965,157.00 Rp 579,094.20
Pembesian Tulangan Pokok Ø 12 81.91 Kg AHSP PU A.4.1.1.17 Rp 14,452.00 Rp 1,183,722.85
Bekisting + Perawatan 6.00 M³ AHSP PU A.4.1.1.26 Rp 460,638.50 Rp 2,763,831.00
jumlah Rp 4,995,884.67
I PEKERJAAN TANGGA DEPAN
a. Galian Tanah 16.98 M³ AHSP PU A.2.3.1.8 Rp 38,940.00 Rp 661,201.20
b. Beton cor 0.73 M³ AHSP PU A.4.1.1.2 Rp 905,485.00 Rp 661,004.05
c. Urugan pasir Tangga Depan 7.05 M³ AHSP PU A.2.3.1.11 Rp 29,788.55 Rp 210,009.28
d. Pasir Alas 0.36 M³ AHSP PU A.2.3.1.11 Rp 142,450.00 Rp 51,282.00
jumlah Rp 1,583,496.53
I PEKERJAAN PLAFOND
a. plafond Multyplek 4mm 274.42 M² AHSP PU A.4.5.1.7 Rp 43,695.00 Rp 11,990,781.90
b. plafond selasar 29.04 M² AHSP PU A.4.5.1.7 Rp 43,695.00 Rp 1,268,902.80
c. Rangka plafond 303.46 M² AHSP PU A.4.6.1.20 Rp 106,725.00 Rp 32,386,768.50
c. List profil 303.46 M² AHSP PU A.4.5.1.9 Rp 17,880.00 Rp 5,425,864.80
jumlah Rp 51,072,318.00
J PEKERJAAN PENGECATAN
a. Cat Dinding 577.47 M² AHSP PU A.4.7.1.10 Rp 24,098.50 Rp 13,916,160.80
b. Cat plafond 303.46 M² Taksir Rp 22,000.00 Rp 6,676,120.00
jumlah Rp 20,592,280.80
K PEKERJAAN KUSEN
Kusen pintu tipe 1 ( 2 unit) 0.13 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 1,164,444.75
Daun pintu tipe 1 5.46 M² Taksir Rp 235,000.00 Rp 1,283,100.00
Kusen pintu tipe 2 ( 2 unit) 0.12 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 1,136,719.88
Daun pintu tipe 2 5.04 M² Taksir Rp 235,000.00 Rp 1,184,400.00
Kusen pintu tipe 3 ( 7 unit) 0.37 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 3,373,193.13
Daun pintu tipe 3 12.94 M² Taksir Rp 235,000.00 Rp 3,039,960.00
Kusen pintu tipe 4 ( 11 unit) 0.42 M² AHSP PU A.4.2.1.11 Rp 59,438.50 Rp 24,964.17
Daun pintu tipe 4 Aluminium 16.17 M² Taksir Rp 90,000.00 Rp 1,455,300.00
Kusen jendela tipe J1 (4 unit) 0.23 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 2,088,607.25
Daun jendela tipe 1 6.10 M² Taksir Rp 235,000.00 Rp 1,433,970.00
Kusen jendela tipe J2 (11 unit) 0.33 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 3,086,702.75
Daun jendela tipe J2 7.43 M² Taksir Rp 235,000.00 Rp 1,744,875.00
Kusen jendela tipe J3 (1 unit) 0.06 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 554,497.50
Daun jendela tipe J3 0.76 M² Taksir Rp 235,000.00 Rp 179,070.00
Kusen jendela tipe J4 (1 unit) 0.03 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 314,215.25
Kusen pintu/jendela tipe PJ1 (2 unit) 0.19 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 1,792,875.25
Daun pintu/jendela tipe PJ1 19.94 M² Taksir Rp 235,000.00 Rp 4,684,725.00
Kusen ventilasi tipe V1 (9 unit) 0.15 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 1,423,210.25
Daun Ventilasi Kaca T 8 2.25 M² Taksir Rp 235,000.00 Rp 528,750.00
Kusen ventilasi tipe V2 ( 1 unit) 0.07 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 674,638.63
Daun Ventilasi Kaca T 8 0.85 M² Taksir Rp 235,000.00 Rp 199,750.00
Kusen ventilasi tipe V3 (3 unit) 0.07 M² AHSP PU A.4.6.1.1 Rp 9,241,625.00 Rp 600,705.63
jumlah Rp 31,968,674.42
BILL OF QUANTITY (BOQ)
Harga Satuan Jumlah Harga
No. Uraian Volume Sat. Analisa
(Rp.) (Rp.)
1 2 3 4 5 6 7=(3x6)
F [EKERJAAN KERAMIK
a. Lantai Keramik 20x20 (KM/WC) 33.90 M² AHSP PU A.4.4.3.36 Rp 237,113.00 Rp 8,038,130.70
b. Dinding 20x25 (KM/WC) 19.76 M² Taksir Rp 255,000.00 Rp 5,038,800.00
c. Lantai 40x40 529.21 M² AHSP PU A.4.4.3.34.a Rp 198,495.00 Rp 105,045,538.95
Jumlah Rp 118,122,469.65
G PEKERJAAN PENGECATAN
a. Cat Dinding 567.23 M² AHSP PU A.4.7.1.10 Rp 24,098.50 Rp 13,669,392.16
b. Cat Plafond 361.03 M² Taksir Rp 22,000.00 Rp 7,942,660.00
Jumlah Rp 21,612,052.16
H PEKERJAAN ATAP
a. Rangka Kuda-Kuda kayu 7.38 M³ AHSP PU A.4.6.1.14 Rp 9,714,675.00 Rp 71,665,157.48
b. Atap seng Genteng 386.13 M² AHSP PU A.4.5.2.32 Rp 106,915.00 Rp 41,283,088.95
c. Rabung seng genteng 42.98 M1 AHSP PU A.4.5.2.39.a Rp 35,430.40 Rp 1,522,798.59
d. Lisplank 3/30 83 M1 AHSP PU A.4.6.1.21 Rp 83,175.00 Rp 6,903,525.00
Jumlah Rp 121,374,570.02
K PEKERJAAN SANITASI
a. Kolset Duduk Keramik 8.00 bh Taksir Rp 550,000.00 Rp 4,400,000.00
b. Bak mandi fibre 8.00 bh Taksir Rp 200,000.00 Rp 1,600,000.00
c. Kran air 14.00 bh AHSP PU A.4.5.1.19 Rp 25,425.00 Rp 355,950.00
d. Floor drain 8.00 bh AHSP PU A.4.5.1.14 Rp 33,425.00 Rp 267,400.00
e. Wastefel 6.00 bh Taksir Rp 1,043,000.00 Rp 6,258,000.00
f. Pipa leiding (Ø 3/4) 18.40 M Taksir Rp 267,000.00 Rp 4,912,800.00
g. Pipa PVC (Ø 4) 60.00 M Taksir Rp 475,000.00 Rp 28,500,000.00
Jumlah Rp 46,294,150.00
1
Rp 184,543,300.93
Rp 491,415,900.89
Rp 352,161,734.40
843,577,635.29
Rp 198,495.00
Rp 198,495.00
Rp 203,629.00
Rp 346,886,040.32
Rp 118,122,469.65
59,061,234.83
AHSP PU A.4.4.3.35
228,000.00
Rp 6,138,000.00
3,340,000.00
PERHITUNGAN BESI DAN BEKISTING
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
95,000,000.00
NO. BENTUK / DIMENSI / UKURAN
1 2
PERHITUNGAN
8 Balok Void ( 0.20 x 0.50 ) M
1 2
PERHITUNGAN
14 Balok latai/ ( 0.13 x 0.13
1 2
PERHITUNGAN
14 top gravel ( 0.15 x 0.25
Total Be = 201.38 Kg
Papan m = 4.800 M2
NSI / UKURAN PERHITUNGAN VOLUME
Total Be = 345.16 Kg
Papan m = 4.438 M2
Total Be = 201.69 Kg
Papan m = 5.467 M2
REKAPITULASI BILL OF QUANTITY
Jumlah Harga
No. Uraian %
(Rp.)
1 2 3 4.00
PEKERJAAN PERSIAPAN Rp 15,568,253.25 0.71
PEKERJAAN TANAH Rp 25,747,783.30 1.18
I LANTAI I
II LANTAI II
Terbilang : DUA MILYAR EMPAT RATUS EMPAT BELAS JUTA SEMBILAN RATUS SEMBILAN PULUH RIBU RUPIAH
PERHITUNGAN JUMLAH MATERIAL / BAHAN
B. PEKERJAAN PONDASI
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. Galian Tanah Pondasi Tapak 193.88 m³
7. Timbunan 15.293
AHSP PU A.2.3.1.11.a
Tanah Timbun 1.200 x 15.29 18.35
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. Sloof (25/40) 7.56 m³
AHSP PU A.4.1.1.8
Beton Cor Mutu f'c = 19,3 Mpa (K = 250)
Semen Portland 406.000 x 7.56 3,069.36 kg
Pasir Beton 684.00 x 7.56 5,171.04 m³
Kerikil 1026 x 7.56 7,756.56 m³
air 215.00 x 7.56 1,625.40 liter
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. Pasangan Dinding 1/2 Bata 1:2 144.60 m²
AHSP PU A.4.4.1.7
Air 215.000 x 144.60 31,089.00 Bh
Semen Portland 371.000 x 144.60 53,646.60 kg
Pasir Beton (PB) 698.000 x 144.60 100,930.80 m³
Kerikil (KR) 1047.000 x 144.60 151,396.20 kg
F. PLAT LANTAI
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. PLAT LANTAI 30.83 m²
AHSP PU A.4.1.1.8
Beton Cor Mutu f'c = 19,3 Mpa (K = 250)
Semen Portland 384.000 x 30.83 11,838.72 kg
Pasir Beton 692.000 x 30.83 21,334.36 m³
Kerikil 1039.000 x 30.83 32,032.37 m³
air 215.000 x 30.83 6,628.45 liter
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. PLAT TANGGA 1.63 m³
AHSP PU A.4.1.1.5
Beton Cor Mutu F'c = 14,5 Mpa (K 175)
Semen Portland 326.000 x 1.63 531.38 kg
Pasir Beton 760.000 x 1.63 1,238.80 m³
Kerikil 1029.000 x 1.63 1,677.27 m³
Air 215.000 x 1.63 350.45 liter
Pasir Alas
Pasir Urug 1.20 x 0.36 0.43 m³
H. PEKERJAAN PLAFOND
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. plafond Gypsum Tebal 9 mm 274.42 m²
AHSP PU A.4.5.1.7
Gypsum 0.36 x 274.42 99.89 Lbr
Paku Skrup 0.11 x 274.42 30.19 Kg
I. PEKERJAAN PENGECETAN
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1 a. Cat Dinding 577.47
AHSP PU A.4.7.1.10
Plamir 0.10 x 577.47 57.75 Kg
Cat Dasar Tembok 0.100 x 577.47 57.75 Kg
Cat Tembok / Penutup 2x 0.26 x 577.47 150.14 Kg
J. PEKERJAAN KUSEN
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. Kusen pintu tipe 1 ( 2 unit) 0.13 m³
AHSP PU A.4.6.1.1
Balok Kayu Kelas I 1.100 x 0.13 0.14 m³
Paku Kayu 1.250 x 0.13 0.16 kg
Lem Kayu 1.000 x 0.13 0.13 kg
LANTAI II
A. PEKERJAAN BETON lantai 11
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. Balok (25/40) 19.40 m³
AHSP PU A.4.1.1.8
Beton Cor Mutu f'c = 19,3 Mpa (K = 250)
Semen Portland 384.000 x 19.40 7,449.60 kg
Pasir Beton 692.000 x 19.40 13,424.80 kg
Kerikil 1039.000 x 19.40 20,156.60 kg
air 215.00 x 19.40 4,171.00 liter
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. Kolom K1 (35/35) 9.60 m³
AHSP PU A.4.1.1.8
Beton Cor Mutu f'c = 19,3 Mpa (K = 250)
Semen Portland 384.000 x 9.60 3,686.40 kg
Pasir Beton 692.000 x 9.60 6,643.20 kg
Kerikil 1039.000 x 9.60 9,974.40 kg
air 215.00 x 9.60 2,064.00 liter
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. Pasangan Dinding 1/2 Bata 1:4 580.00 m²
AHSP PU A.4.4.1.9
Batu Bata 70.000 x 580.00 40,600.00 Bh
Semen Portland 11.500 x 580.00 6,670.00 Kg
Pasir Pasang 0.043 x 580.00 24.94 m³
2 b. Plasteran 567.23 m²
AHSP PU A.4.4.2.4
Semen Portland 6.240 x 567.23 3,539.52 Kg
Pasir Pasang 0.024 x 567.23 13.61 m³
C. PEKERJAAN KUSEN
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. Kusen Pintu tipe 1 (1 Unit) 0.06 m³
AHSP PU A.4.6.1.1
Balok Kayu Kelas I 1.100 x 0.06 0.07 m³
Paku Kayu 1.250 x 0.06 0.08 kg
Lem Kayu 1.000 x 0.06 0.06 kg
D. PEKERJAAN PLAFOND
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. plafond Gypsum Tebal 9 mm 786.24 m²
AHSP PU A.4.5.1.7
Gypsum 0.3640 x 786.24 286.19 lbr
Paku Skrup 0.1100 x 786.24 86.49 kg
F. PEKERJAAN KERAMIK
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1 Cat Dinding Tembok (L/D) 567.23 M²
AHSP PU A.4.7.1.10
Cat Menie 0.10 x 567.23 56.72 Kg
Cat Dasar Tembok 0.100 x 567.23 56.72 Kg
Cat Tembok / Penutup 2x 0.26 x 567.23 147.48 Kg
H PEKERJAAN ATAP
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. Rangka Kuda-Kuda kayu 7.38 M³ M³
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. a. Engsel Pintu 108.00 bh
AHSP PU A.4.6.2.5
Engsel Pintu 1.000 x 108.00 108.00 bh
J. PEKERJAAN ELEKTRIKAL
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
1. Pekerjaan instalasi stop kontak
a. Saklar 1 arah 8.00 bh
b. Saklar 2 arah 18.00 bh
c. Saklar 3 arah 3.00 bh
K. PEKERJAAN SANITASI
BANYAK BAHAN
JENIS BAHAN BANYAK BAHAN UNTUK 1 M³
UNTUK VOLUME
a. Kolset Duduk Keramik 8.00 bh
b. Bak mandi fibre 8.00 bh
c. Kran air 14.00 bh
d. Floor drain 8.00 bh
e. Wastefel 6.00 bh
f. Pipa leiding (Ø 3/4) 18.40 bh
g. Pipa PVC (Ø 4) 60.00 bh
REKAPITULASI ANALISA BAHAN
BANYAKNYA
NO URAIAN BAHAN
BAHAN
1. Kayu Balok 5/7 (kayu klas III) 1.099
2 Kayu Kelas III 46.409
3 Pasir Urug 11.810
4 Kayu Papan 3/20 (kayu klas IV) 0.640
5 Paku 5 Cm - 10 Cm 380.624
7 Semen Portland #REF!
8 Paku Triplek 121.715
9 Batu Gunung / Batu Kali 37.948
10 Besi Beton Polos #REF!
11 Pasir Beton 136570.784
12 Kerikil 195110.596
13 Air 40551.580
14 Kawat Beton #REF!
15 Minyak Bekisting 126.847
17 Balok Kayu Kelas II 14.240
18 Plywood Tebal 9 mm 321.764
19 Kayu Dolken dia. 8 - 10 Cm, L = 4 M 1838.653
20 Batu Bata 114718.700
21 Pasir Pasang #REF!
22 Tanah Timbun 18.352
25 Balok Kayu Kelas I 25.108
26 Lem Kayu 23.862
29 Semen Warna #REF!
30 Kunci pintu standar 48.000
32 Engsel Pintu 108.000
35 Engsel Jendela 89.000
37 Hak Angin 57.000
38 Grendel Jendela 57.000
39 Multypleks 4 mm 402.766
41 List Profil Err:509
42 Box Sekering 2.000
43 Saklar tunggal 8.000
44 Saklar Ganda 21.000
46 TL 2x36 W Louver in Bow Mark philip 14.000
47 . PL 18 W 12.000
48 TL 2x18 W Louver in Bow Mark philip 32.000
49 E27 Down Light Ball x1 18 W in Bow 32.000
50 XL Philip 18 W 9.000
51 Box panel 2.000
52 kabel out put 2.000
53 kabel input 2.000
54 Plamir 57.747
55 Cat Dasar Tembok 114.470
56 Cat Tembok Penutup 2x 205.23
57 Cat Manie 56.72
58 Err:509 Err:509
59 Paku Kayu #REF!
60 Paku 5 Cm - 10 Cm 398.41
61 Atap Genteng Metal 393.85
62 Rabung Seng Genteng 47.28
63 Paku Seng 14.08
AHAN
SATUAN
m³
m³
m³
m3
kg
kg
kg
m³
Kg
m³
Kg
Liter
kg
Liter
m³
Lbr
Btg
Bh
m³
m³
m³
kg
m³
Bh
Bh
Bh
Bh
Bh
Lbr
M
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Kg
Kg
Kg
Kg
Err:509
Err:509
Bh
Lebar
M
Kg
ANALISA TEKNIS
V 557.27
Durasi Pelaksanaan (D) = = = 1.393 = 1 hari
nxP 60 x 6.67
V 91.85
Durasi Pelaksanaan (D) = = = 0.99 = 1 hari
nxP 20 x 4.65
B. PEKERJAAN TANAH
1. Galian Tanah Pondasi Tapak AHSP PU A.2.3.1.8a
Volume (V) = 193.88 m³
Jumlah Tenaga Kerja (n) = 65 Orang (taksir)
Indeks Tenaga Kerja (N) = 0.809
1 1 1.24 m³/org/hari
Produktifitas = = =
N 0.809
V 193.88
Durasi Pelaksanaan (D) = = = 2.41 = 2 hari
nxP 65 x 1.24
V 145.40
Durasi Pelaksanaan (D) = = = 1.08 = 1 hari
nxP 45 x 3.00
V 15.29
Durasi Pelaksanaan (D) = = = 0.51 = 1 hari
nxP 10 x 3.00
V 11.09
Durasi Pelaksanaan (D) = = = 1.38 = 1 hari
nxP 10 x 0.80
V 8.88
Durasi Pelaksanaan (D) = = = 1.11 = 1 hari
nxP 10 x 0.80
1 1
Produktifitas = = = 3.2258 m³/org/hari
N 0.310
V 5.55
Durasi Pelaksanaan (D) = = = 0.86 = 1 hari
nxP 2 x 3.23
1 1
Produktifitas = = = 3.2258 m³/org/hari
N 0.310
V 3.07
Durasi Pelaksanaan (D) = = = 0.95 = 1 hari
nxP 1 x 3.23
V 52.49
Durasi Pelaksanaan (D) = = = 1.26 = 1 hari
nxP 85 x 0.49
V 4139.92
Durasi Pelaksanaan (D) = = = 9.1 = 9 hari
nxP 85 x 5.35
V 131.22
Durasi Pelaksanaan (D) = = = 1.46 = 1 hari
nxP 75 x 1.20
V 4.85
Durasi Pelaksanaan (D) = = = 0.99 = 1 hari
nxP 10 x 0.49
V 234.40
Durasi Pelaksanaan (D) = = = 1.46 = 1 hari
nxP 30 x 5.35
V 9.70
Durasi Pelaksanaan (D) = = = 0.81 = 1 hari
nxP 10 x 1.20
D. PEKERJAAN BETON
1. Sloof 25/40 AHSP PU A.4.1.1.8
Beton K-250
Volume (V) = 7.22 m 3
Jumlah Tenaga Kerja (n) = 10 Orang (taksir)
Indeks Tenaga Kerja (N) = 2.036
1 1
Produktifitas = = = 0.49 kg/org/hari
N 2.036
V 7.22
Durasi Pelaksanaan (D) = = = 1.47 = 1 hari
nxP 10 x 0.49
V 797.64
Durasi Pelaksanaan (D) = = = 1.86 = 2 hari
nxP 80 x 5.35
V 3279.31
Durasi Pelaksanaan (D) = = = 7.2 = 7 hari
nxP 85 x 5.35
V 174.48
Durasi Pelaksanaan (D) = = = 0.73 = 1 hari
nxP 45 x 5.35
V 28.88
Durasi Pelaksanaan (D) = = = 1.20 = 1 hari
nxP 20 x 1.20
V 4.07
Durasi Pelaksanaan (D) = = = 1.04 = 1 hari
nxP 8 x 0.49
V 535.02
Durasi Pelaksanaan (D) = = = 1.47 = 1 hari
nxP 68 x 5.35
V 227.84
Durasi Pelaksanaan (D) = = = 1.1 = 1 hari
nxP 40 x 5.35
V 163.85
Durasi Pelaksanaan (D) = = = 0.88 = 1 hari
nxP 35 x 5.35
V 20.34
Durasi Pelaksanaan (D) = = = 1.00 = 1 hari
nxP 17 x 1.20
V 13.26
Durasi Pelaksanaan (D) = = = 0.90 = 1 hari
nxP 30 x 0.49
V 1464.92
Durasi Pelaksanaan (D) = = = 3.22 = 3 hari
nxP 85 x 5.35
V 6022.66
Durasi Pelaksanaan (D) = = = 13.2 = 13 hari
nxP 85 x 5.35
V 320.45
Durasi Pelaksanaan (D) = = = 1.20 = 1 hari
nxP 50 x 5.35
V 53.04
Durasi Pelaksanaan (D) = = = 1.26 = 1 hari
nxP 35 x 1.20
V 16.07
Durasi Pelaksanaan (D) = = = 1.09 = 1 hari
nxP 30 x 0.49
V 1268.27
Durasi Pelaksanaan (D) = = = 2.96 = 3 hari
nxP 80 x 5.35
V 286.21
Durasi Pelaksanaan (D) = = = 0.82 = 1 hari
nxP 65 x 5.35
V 634.14
Durasi Pelaksanaan (D) = = = 1.40 = 1 hari
nxP 85 x 5.35
V 40.29
Durasi Pelaksanaan (D) = = = 1.06 = 1 hari
nxP 40 x 0.95
V 23.62
Durasi Pelaksanaan (D) = = = 1.1 = 1 hari
nxP 45 x 0.49
V 951.21
Durasi Pelaksanaan (D) = = = 2.1 = 2 hari
nxP 85 x 5.35
V 584.23
Durasi Pelaksanaan (D) = = = 1.37 = 1 hari
nxP 80 x 5.35
V 1268.27
Durasi Pelaksanaan (D) = = = 2.79 = 3 hari
nxP 85 x 5.35
V 118.08
Durasi Pelaksanaan (D) = = = 1.47 = 1 hari
nxP 15 x 5.35
V 2.77
Durasi Pelaksanaan (D) = = = 1.1 = 1 hari
nxP 5 x 0.49
V 582.03
Durasi Pelaksanaan (D) = = = 1.3 = 1 hari
nxP 85 x 5.35
V 159.73
Durasi Pelaksanaan (D) = = = 1.19 = 1 hari
nxP 25 x 5.35
V 42.62
Durasi Pelaksanaan (D) = = = 1.00 = 1 hari
nxP 8 x 5.35
V 4208.66
Durasi Pelaksanaan (D) = = = 9.3 = 9 hari
nxP 85 x 5.35
V 24.10
Durasi Pelaksanaan (D) = = = 1.3 = 1 hari
nxP 20 x 0.95
V 1.63
Durasi Pelaksanaan (D) = = = 0.57 = 1 hari
nxP 5 x 0.57
V 138.99
Durasi Pelaksanaan (D) = = = 1.30 = 1 hari
nxP 20 x 5.35
V 1.42
Durasi Pelaksanaan (D) = = = 0.58 = 1 hari
nxP 5 x 0.49
V 193.85
Durasi Pelaksanaan (D) = = = 1.21 = 1 hari
nxP 30 x 5.35
V 0.09
Durasi Pelaksanaan (D) = = = 0.2 = 1 hari
nxP 1 x 0.49
V 7.10
Durasi Pelaksanaan (D) = = = 0.66 = 1 hari
nxP 2 x 5.35
V 4.31
Durasi Pelaksanaan (D) = = = 0.81 = 1 hari
nxP 1 x 5.35
V 0.86
Durasi Pelaksanaan (D) = = = 0.91 = 1 hari
nxP 1 x 0.95
V 0.60
Durasi Pelaksanaan (D) = = = 0.61 = 1 hari
nxP 2 x 0.49
V 81.91
Durasi Pelaksanaan (D) = = = 0.77 = 1 hari
nxP 20 x 5.35
V 6.00
Durasi Pelaksanaan (D) = = = 1.06 = 1 hari
nxP 6 x 0.95
V 144.60
Durasi Pelaksanaan (D) = = = 1.2 = 1 hari
nxP 50 x 2.35
V 10.43
Durasi Pelaksanaan (D) = = = 0.9 = 1 hari
nxP 5 x 2.35
V 604.28
Durasi Pelaksanaan (D) = = = 3.02 = 3 hari
nxP 85 x 2.35
V 20.86
Durasi Pelaksanaan (D) = = = 1.3 = 1 hari
nxP 8 x 2.08
V 577.47
Durasi Pelaksanaan (D) = = = 3.3 = 3 hari
nxP 85 x 2.08
V 16.98
Durasi Pelaksanaan (D) = = = 1.01 = 1 hari
nxP 13 x 1.29
V 0.73
Durasi Pelaksanaan (D) = = = 0.7 = 1 hari
nxP 2 x 0.49
V 7.05
Durasi Pelaksanaan (D) = = = 1.1 = 1 hari
nxP 2 x 3.23
V 0.36
Durasi Pelaksanaan (D) = = = 0.1 = 1 hari
nxP 1 x 3.23
G. PEKERJAAN PELAFOND
a. Rangka Pelafond AHSP PU A.4.6.1.20
Volume (V) = 303.46 m 2
Jumlah Tenaga Kerja (n) = 85 Orang (taksir)
Indeks Tenaga Kerja (N) = 0.540
1 1
Produktifitas = = = 1.85 kg/org/hari
N 0.540
V 303.46
Durasi Pelaksanaan (D) = = = 1.93 = 2 hari
nxP 85 x 1.85
V 274.42
Durasi Pelaksanaan (D) = = = 1.25 = 1 hari
nxP 35 x 6.25
V 29.04
Durasi Pelaksanaan (D) = = = 0.93 = 1 hari
nxP 5 x 6.25
V 303.46
Durasi Pelaksanaan (D) = = = 1.31 = 1 hari
nxP 25 x 9.26
H. PEKERJAAN KUSEN
a. Kusen Pintu tipe 1 (2 unit) AHSP PU A.4.6.1.1
Volume = 0.13 M²
Jumlah Tenaga Kerja (n) = 10 Orang (taksir)
Indeks Tenaga Kerja (N) = 30.450
1 1
Produktivitas = = = 0.03 m²/org/hari
N 30.450
V 0.13
Durasi Pelaksanaan (D) = = = 0.38 = 1 hari
nxP 10 x 0.03
Daun pintu 1
Volume (V) = 5.46 M²
Jumlah Tenaga Kerja (n) = 4 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
V 0.12
Durasi Pelaksanaan (D) = = = 0.94 = 1 hari
nxP 4 x 0.03
V 0.15
Durasi Pelaksanaan (D) = = = 1.17 = 1 hari
nxP 4 x 0.03
V 0.42
Durasi Pelaksanaan (D) = = = 0.06 = 1 hari
nxP 1 x 7.63
V 0.23
Durasi Pelaksanaan (D) = = = 0.86 = 1 hari
nxP 8 x 0.03
V 0.33
Durasi Pelaksanaan (D) = = = 5.09 = 1 hari
nxP 2 x 0.03
V 19.76
Durasi Pelaksanaan (D) = = = 1.30 = 1 hari
nxP 2 x 7.63
V 0.03
Durasi Pelaksanaan (D) = = = 0.002 = 1 hari
nxP 2 x 7.30
V 0.19
Durasi Pelaksanaan (D) = = = 0.01 = 1 hari
nxP 2 x 7.30
V 0.15
Durasi Pelaksanaan (D) = = = 0.01 = 1 hari
nxP 2 x 7.30
V 0.07
Durasi Pelaksanaan (D) = = = 0.01 = 1 hari
nxP 2 x 7.30
V 0.07
Durasi Pelaksanaan (D) = = = 0.01 = 1 hari
nxP 1 x 7.30
V 33.90
Durasi Pelaksanaan (D) = = = 1.27 = 1 hari
nxP 30 x 0.89
b. Dinding 20 x 25 (KM/MC)
Volume (V) = 19.76 M²
Jumlah Tenaga Kerja (n) = 15 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
V 529.21
Durasi Pelaksanaan (D) = = = 6.97 = 7 hari
nxP 85 x 0.89
V 25.89
Durasi Pelaksanaan (D) = = = 1.45 = 1 hari
nxP 20 x 0.89
V 18.20
Durasi Pelaksanaan (D) = = = 1.36 = 1 hari
nxP 15 x 0.89
PEKERJAAN BETON
a. Balok 25/40
Beton K-250 AHSP PU A.4.1.1.8
Volume = 19.40 M³
Jumlah Tenaga Kerja (n) = 30 Orang (taksir)
Indeks Tenaga Kerja (N) = 2.036
1 1
Produktivitas = = = 0.49 m²/org/hari
N 2.036
V 19.40
Durasi Pelaksanaan (D) = = = 1.32 = 1 hari
nxP 30 x 0.49
V 1875.34
Durasi Pelaksanaan (D) = = = 4.13 = 4 hari
nxP 85 x 5.35
V 589.78
Durasi Pelaksanaan (D) = = = 1.38 = 1 hari
nxP 80 x 5.35
V 937.67
Durasi Pelaksanaan (D) = = = 2.06 = 2 hari
nxP 85 x 5.35
V 67.84
Durasi Pelaksanaan (D) = = = 1.43 = 1 hari
nxP 50 x 0.95
V 3.03
Durasi Pelaksanaan (D) = = = 1.23 = 1 hari
nxP 5 x 0.49
V 244.08
Durasi Pelaksanaan (D) = = = 1.14 = 1 hari
nxP 40 x 5.35
V 126.99
Durasi Pelaksanaan (D) = = = 1.19 = 1 hari
nxP 20 x 5.35
V 71.73
Durasi Pelaksanaan (D) = = = 1.34 = 1 hari
nxP 10 x 5.35
V 12.32
Durasi Pelaksanaan (D) = = = 1.30 = 1 hari
nxP 10 x 0.95
V 5.41
Durasi Pelaksanaan (D) = = = 1.10 = 1 hari
nxP 10 x 0.49
V 640.61
Durasi Pelaksanaan (D) = = = 1.41 = 1 hari
nxP 85 x 5.35
V 392.27
Durasi Pelaksanaan (D) = = = 1.22 = 1 hari
nxP 60 x 5.35
b Kolom k1 35/35
Beton K-250 AHSP PU A.4.1.1.8
Volume = 9.60 M³
Jumlah Tenaga Kerja (n) = 15 Orang (taksir)
Indeks Tenaga Kerja (N) = 2.036
1 1
Produktivitas = = = 0.49 m²/org/hari
N 2.036
V 9.60
Durasi Pelaksanaan (D) = = = 1.30 = 1 hari
nxP 15 x 0.49
V 757.56
Durasi Pelaksanaan (D) = = = 1.67 = 2 hari
nxP 85 x 5.35
V 260.41
Durasi Pelaksanaan (D) = = = 1.08 = 1 hari
nxP 45 x 5.35
V 378.78
Durasi Pelaksanaan (D) = = = 1.29 = 1 hari
nxP 55 x 5.35
V 54.86
Durasi Pelaksanaan (D) = = = 1.16 = 1 hari
nxP 50 x 0.95
V 3.20
Durasi Pelaksanaan (D) = = = 1.09 = 1 hari
nxP 6 x 0.49
V 580.00
Durasi Pelaksanaan (D) = = = 1.28 = 1 hari
nxP 85 x 5.35
V 137.05
Durasi Pelaksanaan (D) = = = 0.85 = 1 hari
nxP 30 x 5.35
V 193.33
Durasi Pelaksanaan (D) = = = 1.21 = 1 hari
nxP 30 x 5.35
V 32.00
Durasi Pelaksanaan (D) = = = 1.13 = 1 hari
nxP 30 x 0.95
V 1.37
Durasi Pelaksanaan (D) = = = 0.93 = 1 hari
nxP 3 x 0.49
V 287.87
Durasi Pelaksanaan (D) = = = 1.35 = 1 hari
nxP 40 x 5.35
V 79.00
Durasi Pelaksanaan (D) = = = 1.14 = 1 hari
nxP 13 x 5.35
V 21.08
Durasi Pelaksanaan (D) = = = 1.11 = 1 hari
nxP 20 x 0.95
V 12.28
Durasi Pelaksanaan (D) = = = 1.00 = 1 hari
nxP 25 x 0.49
V 908.47
Durasi Pelaksanaan (D) = = = 2.12 = 2 hari
nxP 80 x 5.35
V 687.78
Durasi Pelaksanaan (D) = = = 1.51 = 2 hari
nxP 85 x 5.35
V 363.39
Durasi Pelaksanaan (D) = = = 1.05 = 1 hari
nxP 65 x 5.35
V 16.80
Durasi Pelaksanaan (D) = = = 1.18 = 1 hari
nxP 15 x 0.95
V 2.03
Durasi Pelaksanaan (D) = = = 0.83 = 1 hari
nxP 5 x 0.49
V 240.29
Durasi Pelaksanaan (D) = = = 1.12 = 1 hari
nxP 40 x 5.35
V 147.14
Durasi Pelaksanaan (D) = = = 1.20 = 1 hari
nxP 23 x 5.35
V 10.49
Durasi Pelaksanaan (D) = = = 1.11 = 1 hari
nxP 10 x 0.95
V 580.00
Durasi Pelaksanaan (D) = = = 2.90 = 3 hari
nxP 85 x 2.35
V 567.23
Durasi Pelaksanaan (D) = = = 3.20 = 3 hari
nxP 85 x 2.08
V 0.06
Durasi Pelaksanaan (D) = = = 0.91 = 1 hari
nxP 2 x 0.03
V 0.18
Durasi Pelaksanaan (D) = = = 1.37 = 1 hari
nxP 4 x 0.03
V 0.37
Durasi Pelaksanaan (D) = = = 1.13 = 1 hari
nxP 10 x 0.03
V 0.34
Durasi Pelaksanaan (D) = = = 0.09 = 1 hari
nxP 2 x 1.93
V 0.17
Durasi Pelaksanaan (D) = = = 1.29 = 1 hari
nxP 4 x 0.03
V 0.30
Durasi Pelaksanaan (D) = = = 1.14 = 1 hari
nxP 8 x 0.03
V 0.12
Durasi Pelaksanaan (D) = = = 0.91 = 1 hari
nxP 4 x 0.03
V 0.04
Durasi Pelaksanaan (D) = = = 0.61 = 1 hari
nxP 2 x 0.03
V 0.15
Durasi Pelaksanaan (D) = = = 1.14 = 1 hari
nxP 4 x 0.03
D PEKERJAAN PLAFOND
a. Rangka plafond AHSP PU A.4.6.1.20
Volume = 303.46 M²
Jumlah Tenaga Kerja (n) = 85 Orang (taksir)
Indeks Tenaga Kerja (N) = 0.540
1 1
Produktivitas = = = 1.85 m²/org/hari
N 0.540
V 303.46
Durasi Pelaksanaan (D) = = = 1.93 = 2 hari
nxP 85 x 1.85
V 786.24
Durasi Pelaksanaan (D) = = = 1.48 = 2 hari
nxP 85 x 6.25
V 16.80
Durasi Pelaksanaan (D) = = = 0.54 = 1 hari
nxP 5 x 6.25
V 11.76
Durasi Pelaksanaan (D) = = = 0.64 = 1 hari
nxP 2 x 9.26
E PEKERJAAN KERAMIK
a. Lantai Keramik 20 x20 (KM/WC) AHSP PU A.4.4.3.36
Volume = 33.90 M²
Jumlah Tenaga Kerja (n) = 30 Orang (taksir)
Indeks Tenaga Kerja (N) = 1.120
1 1
Produktivitas = = = 0.89 m²/org/hari
N 1.120
V 33.90
Durasi Pelaksanaan (D) = = = 1.27 = 1 hari
nxP 30 x 0.89
b. Dinding 20 x 25 (KM/WC)
Volume (V) = 19.76 M²
Jumlah Tenaga Kerja (n) = 15 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
V 529.21
Durasi Pelaksanaan (D) = = = 6.97 = 7 hari
nxP 85 x 0.89
F PEKERJAAN PENGECATAN
a. Cat Dinding AHSP PU A.4.7.1.10
Volume = 567.23 M²
Jumlah Tenaga Kerja (n) = 40 Orang (taksir)
Indeks Tenaga Kerja (N) = 0.092
1 1
Produktivitas = = = 10.89 m²/org/hari
N 0.092
V 567.23
Durasi Pelaksanaan (D) = = = 1.30 = 1 hari
nxP 40 x 10.89
b. Cat Plafond
Volume (V) = 361.00 M²
Jumlah Tenaga Kerja (n) = 20 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
G PEKERJAAN ATAP
a Rangka Kuda-Kuda kayu AHSP PU A.4.6.1.14
Volume = 7.38 M³
Jumlah Tenaga Kerja (n) = 85 Orang (taksir)
Indeks Tenaga Kerja (N) = 29.145
1 1
Produktivitas = = = 0.03 m²/org/hari
N 29.145
V 7.38
Durasi Pelaksanaan (D) = = = 2.53 = 3 hari
nxP 85 x 0.03
V 386.13
Durasi Pelaksanaan (D) = = = 1.41 = 1 hari
nxP 85 x 3.22
V 42.98
Durasi Pelaksanaan (D) = = = 1.06 = 1 hari
nxP 10 x 4.05
V 83.00
Durasi Pelaksanaan (D) = = = 1.08 = 1 hari
nxP 25 x 3.08
V 108.00
Durasi Pelaksanaan (D) = = = 1.30 = 1 hari
nxP 15 x 5.53
b. Kunci Pintu
Volume (V) = 48.00 bh
Jumlah Tenaga Kerja (n) = 12 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
c. Pegangan Pintu
Volume (V) = 48.00 bh
Jumlah Tenaga Kerja (n) = 12 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
V 89.00
Durasi Pelaksanaan (D) = = = 1.24 = 1 hari
nxP 13 x 5.53
V 57.00
Durasi Pelaksanaan (D) = = = 1.27 = 1 hari
nxP 25 x 1.79
V 57.00
Durasi Pelaksanaan (D) = = = 0.79 = 1 hari
nxP 13 x 5.53
b. Saklar 2 arah
Volume (V) = 18.00 bh
Jumlah Tenaga Kerja (n) = 4 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
c. Saklar 3 arah
Volume (V) = 3.00 bh
Jumlah Tenaga Kerja (n) = 1 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
b. PL 18 W
Volume (V) = 12.00 bh
Jumlah Tenaga Kerja (n) = 2 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
e. XL Philip 18 W
Volume (V) = 9.00 bh
Jumlah Tenaga Kerja (n) = 2 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
c. Kabel input
Volume (V) = 2.00 bh
Jumlah Tenaga Kerja (n) = 1 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
V 14.00
Durasi Pelaksanaan (D) = = = 0.88 = 1 hari
nxP 2 x 8.00
V 8.00
Durasi Pelaksanaan (D) = = = 0.08 = 1 hari
nxP 13 x 8.00
e. Wastafel
Volume (V) = 6.00 bh
Jumlah Tenaga Kerja (n) = 3 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
f. Pipa leiding (Ø 4)
Volume (V) = 18.40 M
Jumlah Tenaga Kerja (n) = 4 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
g. Pipa PVC ( Ø 4)
Volume (V) = 60.00 M
Jumlah Tenaga Kerja (n) = 8 Orang (taksir)
Waktu yang dibutuhkan = 1 hari
PEKERJAAN LANTAI 1
A. PEKERJAAN PERSIAPAN
1. Pembersihan Lapangan M² 557.27
2. Pemasangan Bouwplank M 106.00
JUMLAH
B. PEKERJAAN TANAH
1 Galian Tanah Pondasi Tapak M³ 193.880
2 Galian Tanah Pondasi Menerus M³ 61.17
3 Urugan Kembali Galian Pondasi Tapak M³ 145.40
4 Urugan Kembali Galian Pondasi Menerus M³ 15.29
5 Pasangan Batu Kosong Pondasi Tapak M³ 11.09
6 Pasangan Batu Kosong Pondasi Menerus M³ 8.88
7 Timbunan Pasir Bawah Pondasi Tapak M³ 5.55
8 Timbunana Pasir Bawah Pondasi Menerus M³ 3.07
JUMLAH
2 Sloof 20/30
Beton K-250 M³ 4.07
Besi Tulangan Pokok Ø 16 kg 535.02
Besi Tulangan Sengkang Ø 8 kg 227.84
Besi Tulangan Pinggang Ø 14 kg 163.85
Bekisting + Perawatan Beton M³ 20.34
4 Kolom K1 35/35
Beton K-250 M³ 16.07
Besi Tulangan Pokok Ø 14 kg 1268.27
Besi Tulangan Sengkang Ø 8 kg 435.97
Besi Tulangan Pinggang Ø 14 kg 634.14
Bekisting + Perawatan Beton M³ 91.84
5 Kolom K2 30/60
Beton K-250 M³ 23.62
Besi Tulangan Pokok Ø 14 kg 951.21
Besi Tulangan Sengkang Ø 14 kg 584.23
Besi Tulangan Pinggang Ø 14 kg 1268.27
Bekisting + Perawatan Beton M³ 118.08
6 Kolom K4 13/13
Beton K-250 M³ 2.77
Besi Tulangan Pokok Ø 14 kg 582.03
Besi Tulangan Sengkang Ø 8 kg 159.73
Bekisting + Perawatan Beton M³ 42.62
7 Pelat Lantai
Beton K-250 M³ 30.83
Pembesian Tulangan Pokok Ø 12 kg 4208.66
Bekisting + Perawatan Beton M³ 308.30
8 Pelat Tangga
Beton K - 175 M³ 1.63
Pembesian Tulangan Pokok Ø 12 kg 222.51
Bekisting + Perawatan M³ 16.30
a. Anak Tangga
Beton K - 175 M³ 1.42
Pembesian Tulangan Ø 12 kg 193.85
Bekisting + Perawatan M³ 14.20
10 Balok 25/40
Beton K-250 M³ 19.40
Besi Tulangan Pokok Ø 14 kg 1875.34
Besi Tulangan Sengkang Ø 8 kg 589.78
Besi Tulangan Pinggang Ø 2 - 16 cm kg 937.67
Bekisting + Perawatan Beton M³ 67.84
11 Balok (20/30)
Beton K-250 M³ 3.03
Besi Tulangan Pokok Ø 14 kg 244.08
Besi Tulangan Sengkang Ø 8 - 10 cm kg 126.99
Besi Tulangan Pinggang Ø 12 kg 71.73
Bekisting + Perawatan Beton M³ 12.32
JUMLAH
E PEKERJAAN PASANGAN DAN PELASTERAN
Pasangan Dinding 1/2 Bata 1Pc : 2Ps M³ 144.60
Pasangan Dinding 1/2 Bata 1Pc : 2Ps Selasar M³ 10.43
Pasangan Dinding 1/2 Bata 1Pc :4Ps M³ 604.28
Pelasteran 1Pc : 2P M³ 20.86
Pelasteran 1Pc : 4Ps M³ 577.47
JUMLAH
F PEKERJAAN TANGGA DEPAN
Galian Tanah M³ 16.98
Beton K-125 M³ 0.73
Urugan pasir Tangga Depan M³ 7.05
Pasair Alas M³ 0.36
JUMLAH
G PEKERJAAN PELAFOND
Rangka Pelafond m2 303.46
Pelafond Tripleks 4 mm m2 274.42
Pelafond Selasar Tripleks 4 mm m2 29.04
List Pelafond m2 303.46
JUMLAH
H PEKERJAAN KUSEN
a Kusen Pintu tipe 1 (2 unit) m2 0.13
Daun pintu 1 m2 5.46
b Kusen pintu tipe 2 (2 unit) m2 0.12
Daun pintu tipe 2 m2 5.04
c Kusen pintu tipe 3 (7 unit) m2 0.15
Daun pintu tipe 3 m2 12.94
d Kusen pintu tipe 4 (11 unit ) m2 0.42
Daun pintu tipe 4 Aluminium m2 0.85
e Kusen jendela tipe J1 (4 unit ) m2 0.23
Daun jendela tipe J1 (4 unit) m2 6.10
f Kusen jendela J2 (11 unit ) m2 0.33
Daun jendala J2 (11 unit) m2 7.43
g Kusen jendela tipe J3 (1 Unit ) m2 19.76
Daun jendela tipe J3 m2 0.76
h Kusen jendela tipe J4 ( 1 unit ) m2 0.03
i Kusen pintu/jendela tipe pj1 (2 unit ) m2 0.19
Daun pintu/jendela tipe Pj1 m2 19.94
j Kusen vantilasi tipe V1 (9 unit ) m2 0.15
Daun vantilasi kaca T 8 m2 2.25
k Kusen vantilasi tipe V2 (1 unit) m2 0.07
Daun vantilasi kaca T 8 m2 0.85
l Kusen vantilasi tipe V2 (1 unit) m2 0.07
JUMLAH
I PEKERJAAN KERAMIK LANTAI 1
Lantai Keramik 20 x 20 (KM/WC) M² 33.90
Dinding 20 x 25 (KM/MC) M² 19.76
Keramik Lantai 40 x 40 M² 529.21
Keramik 40 x 40 Unpolisshed (Selasar) M² 25.89
Keramik 30 x 30 Anak Tangga M² 18.20
JUMLAH
PEKERJAAN LANTAI II
2 Kolom k1 35/35
Beton K-250 M³ 9.60
Besi Tulangan pokok Ø 14 kg 757.555
Besi Sengkang Polos Ø 8 kg 260.410
Besi Pinggang Polos Ø 14 kg 378.778
Bekisting + perawatan Beton M³ 54.857
1 PEKERJAAN LANTAI I
2 PEKERJAAN LANTAI II
TOTAL
DURASI SATUAN
1 Hari
1 Hari
2 Hari
2 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
9 Hari
SI
Hari
1 Hari
9 Hari
1 Hari
Hari
1 Hari
1 Hari
1 Hari
14 Hari
1
1 Hari
2 Hari
7 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
3 Hari
13 Hari
1 Hari
1 Hari
1 Hari
3 Hari
1 Hari
1 Hari
1 Hari
1 Hari
2 Hari
1 Hari
3 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
9 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
4 Hari
1 Hari
2 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
93 Hari
STERAN
1 Hari
1 Hari
3 Hari
1 Hari
3 Hari
9 Hari
1 Hari
1 Hari
1 Hari
1 Hari
4 Hari
2 Hari
1 Hari
1 Hari
1 Hari
5 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
22 Hari
1
1 Hari
1 Hari
7 Hari
1 Hari
1 Hari
11 Hari
DURASI SATUAN
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
2 Hari
1 Hari
1 Hari
1 Hari
1 `
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
2 Hari
2 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
30 Hari
TERAN
3 Hari
3 Hari
6 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
16 Hari
2 Hari
2 Hari
1 Hari
1 Hari
6 Hari
1 Hari
1 Hari
7 Hari
9 Hari
1 Hari
1 Hari
2 Hari
3 Hari
1 Hari
1 Hari
1 Hari
6 Hari
NTUNG
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
6 Hari
Dan II
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
1 Hari
11 Hari
an II
1
1
1
1
1
1
1
7 Hari
DURASI SATUAN
169 Hari
99 Hari
268 Hari