LOWOKWARU 2015
NO URAIAN SAT
a b c
1 Mandor org/hr
2 Kepala Tukang Batu org/hr
3 Kepala Tukang Kayu org/hr
4 Kepala Tukang Besi org/hr
5 Kepala Tukang Cat org/hr
6 Kepala Tukang Listrik org/hr
7 Tukang Gali org/hr
8 Tukang Batu org/hr
9 Tukang Kayu org/hr
10 Tukang Besi org/hr
11 Tukang Cat org/hr
12 Tukang Plitur org/hr
13 Tukang Pipa org/hr
14 Tukang Listrik org/hr
15 Tukang Aspal org/hr
16 Tukang Kapur org/hr
17 Pembantu Tukang org/hr
18 Pekerja Biasa org/hr
19 Penjaga Malam org/hr
20 Sopir org/hr
21 Operator org/hr
22 Mekanik org/hr
23 Pembantu Sopir org/hr
24 Pembantu Operator org/hr
25 Pembantu Mekanik org/hr
26 Juru Ukur org/hr
27 Engineer dan Crew Ls
1 Galian mᵌ
2 Urugan Tanah Kembali mᵌ
3 Urugan Pasir mᵌ
4 Pas. Pondasi Batu Kali mᵌ
5 Pas. Batu Kosong mᵌ
6 Pas. Bata Merah 1/2 Bata m²
7 Pas. Kusen Pintu & Jendela mᵌ
8 Sloof Beton Bertulang mᵌ
9 Kolom Beton Bertulang mᵌ
10 Balok Beton Bertulang (Ring Balk) mᵌ
Total
WOKWARU 2015
Rp 2,880.00
Rp 25,200.00
Rp 28,080.00 Rp 28,080.00
Rp 1,368.00
Rp 12,096.00
Rp 13,464.00 Rp 13,464.00
Rp 7,200.00
Rp 9,504.00
Rp 16,704.00 Rp 16,704.00
Rp - Rp - Rp -
Rp -
I ANGGARAN BIAYA
Rp0
a. Pembersihan site/lokasi tanah
v = pxl p 20.00
200.00 mᵌ l 10.00
v = (p+l) x 2 a 0.80
60.00 mᵌ b 1.00
h 0.70
p 59.40
va = (a+b) / 2 x h x p a 0.80
37.42 mᵌ b 1.00
h 0.70
p 59.40
e. Pekerjaan pondasi
1. Pondasi batu kali
va = (a+b) / 2 x h x p a 0.50
27.03 mᵌ b 0.80
4. Pondasi setempat
va = a x b x h a 1.00
0.53 mᵌ b 0.30
h 1.75 tinggi pondasi
f. Sloof Beton 15 x 15
va = b x h x p b 0.15
1.34 mᵌ h 0.15
g. Balok 15 x 15
va = b x h x p b 0.15
1.34 mᵌ h 0.15
h. Kolom
Type 1
vb = (b x h x t)∑k b 0.15
2.34 mᵌ h 0.15
t 4.00
∑k 26.00
vb = (b x h x t)∑k b 0.40
1.28 mᵌ h 0.40
t 4.00
∑k 2.00
Type 2
Total volume kolom 3.62 mᵌ
2. Lantai 2
v = (h x p) - ∑lp - ∑lj
93.06
Total pasangan dinding bata me
i. Lantai keramik 30 x 30
v=pxl p 8.85
69.47 m² l 7.85
kusen
j1
v = p x l x unit l 0.78
1.40 p 1.80
unit 1.00
j2
v = p x h x unit
6.37 l 1.18
p 1.80
unit 3.00
pj1
v = (p x h x unit) - v tidak terpakai v v tidak terpakai
2.69 v = (p x h x unit) l 1.36 v = p x l
2.86 p 2.10 0.17
unit 1.00
pj2
v = (p x h x unit) - v tidak terpakai v v tidak terpakai
4.12 v = (p x h x unit) l 2.12 v = p x l x 2
4.45 p 2.10 0.34
unit 1.00
p2
v = p x h x unit l 0.80
6.72 p 2.10
unit 4.00
p3 l 0.70
1.47 p 2.10
unit 1.00
v kusen 22.77
2. Lantai 2
vb = (b x h x t)∑k b 0.50
4.50 mᵌ h 0.50
t 3.00
∑k 6.00
2. Lantai 2
v = (h x p) - ∑lp - ∑lj h 3.00
mᵌ p 33.40
∑lp 2.73 (profil bata)
∑lj 4.41 plester, panjang, tinggi
Total pasangan dinding bata merah 1 : 5 323.52 m²
2. Lantai 2
vs = {(h plesteran x p plesteran) - L pintu} x 2 h 3.00
p 33.40
L pintu 2.73
Total plesteran dan aci 1 : 5 lantai 1 & lantai 2 = 664.68
v tidak terpakai
p 0.3
l 0.56
v tidak terpakai
v=pxlx2 p 0.3
l 0.56
DAFTAR UPAH KERJA WIL. LOWOKWARU 2015
NO URAIAN SAT HARGA SATUAN
a b c d
1 Mandor org/hr Rp 72,000.00
2 Kepala Tukang Batu org/hr Rp 67,500.00
3 Kepala Tukang Kayu org/hr Rp 67,500.00
4 Kepala Tukang Besi org/hr Rp 67,500.00
5 Kepala Tukang Cat org/hr Rp 67,500.00
6 Kepala Tukang Listrik org/hr Rp 67,500.00
7 Tukang Gali org/hr Rp 63,000.00
8 Tukang Batu org/hr Rp 63,000.00
9 Tukang Kayu org/hr Rp 63,000.00
10 Tukang Besi org/hr Rp 63,000.00
11 Tukang Cat org/hr Rp 63,000.00
12 Tukang Plitur org/hr Rp 63,000.00
13 Tukang Pipa org/hr Rp 63,000.00
14 Tukang Listrik org/hr Rp 63,000.00
15 Tukang Aspal org/hr Rp 63,000.00
16 Tukang Kapur org/hr Rp 63,000.00
17 Pembantu Tukang org/hr Rp 49,500.00
18 Pekerja Biasa org/hr Rp 49,500.00
19 Penjaga Malam org/hr Rp 49,500.00
20 Sopir org/hr Rp 63,000.00
21 Operator org/hr Rp 67,500.00
22 Mekanik org/hr Rp 72,000.00
23 Pembantu Sopir org/hr Rp 58,500.00
24 Pembantu Operator org/hr Rp 58,500.00
25 Pembantu Mekanik org/hr Rp 54,500.00
26 Juru Ukur org/hr Rp 126,000.00
27 Engineer dan Crew Ls Rp 720,000.00
015
KETERANGAN
e
DAFTAR ANALISA HARGA SATUAN
MENURUT SNI 2015
HARGA SAT
NO URAIAN
(Rp)
a b c
A.018 1 mᵌ GALIAN TANAH BIASA SEDALAM 1.00 m
Upah
0,040 Oh Mandor Rp 72,000.00
0,400 Oh Pekerja Rp 49,500.00
SUB JUMLAH
A.026 1 mᵌ URUGAN TANAH KEMBALI
Upah
0.019 Oh Mandor Rp 72,000.00
0.192 Oh Pekerja Rp 49,500.00
SUB JUMLAH
A.028 1 mᵌ URUGAN PASIR
Bahan
1.200 m3 Pasir Urug
Upah
0.010 Oh Mandor Rp 72,000.00
0.192 Oh Pekerja Rp 49,500.00
SUB JUMLAH
A.037 1 mᵌ PASANGAN BATU KALI PC : 4 PS
Bahan
1.100 m3 Batu kali
163.000 kg Semen PC (50kg)
0,520 m3 Pasir Pasang
Upah
0.075 Oh Mandor Rp 72,000.00
0.060 Oh Kepala Tukang Batu Rp 67,500.00
0.600 Oh Tukang Batu Rp 63,000.00
1.500 Oh Pekerja Rp 49,500.00
SUB JUMLAH
A.046 1 mᵌ PASANGAN BATU KOSONG (AANSTAMPING)
Bahan
1.200 m3 Batu Kali
0.300 m3 Pasir Urug
Upah
0.039 Oh Mandor Rp 72,000.00
0.039 Oh Kepala Tukang Batu Rp 67,500.00
0.390 Oh Tukang Batu Rp 63,000.00
0.780 Oh Pekerja Rp 49,500.00
SUB JUMLAH
A.061 1 mᵌ PASANGAN BATU MERAH 1/2 BATA 1PC : PS
Bahan
A.061
Rp 2,880.00
Rp 19,800.00
Rp 22,680.00 Rp 22,680.00
Rp 1,368.00
Rp 9,504.00
Rp 10,872.00 Rp 10,872.00
Rp 96,900.00
Rp 7,200.00
Rp 9,504.00
Rp 16,704.00 Rp 16,704.00
Rp 147,900.00
Rp 1,564.68
Rp 132,600.00
Rp - Rp 282,064.68 Rp 282,064.68
Rp 147,900.00
Rp 96,900.00
Rp - Rp 244,800.00 Rp 244,800.00
Rp 159.00
Rp 1,564.68
Rp 132,600.00
Rp 8,568,000.00
Rp 9,180,000.00
Rp 16,320.00
Rp 5,100.00
Rp 19,380.00
Rp 19,380.00
Rp 1,564.68
Rp 137,700.00
Rp 275,400.00
Rp 9,180,000.00
Rp 16,320.00
Rp 5,100.00
Rp 3,978,000.00
Rp 214,200.00
Rp 10,800.00
Rp 19,380.00
Rp 19,380.00
Rp 1,564.68
Rp 137,700.00
Rp 275,400.00
REKAPITULASI ANGGARAN BIAYA
1 Galian mᵌ 155.8
2 Urugan Tanah Kembali mᵌ 155.8
3 Urugan Pasir mᵌ
4 Pas. Pondasi Batu Kali mᵌ
5 Pas. Batu Kosong mᵌ
6 Pas. Bata Merah 1/2 Bata m²
7 Pas. Kusen Pintu & Jendela mᵌ
8 Sloof Beton Bertulang mᵌ
9 Kolom Beton Bertulang mᵌ
10 Balok Beton Bertulang (Ring Balk) mᵌ
Total
N BIAYA
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp0