1. GALIAN 11.76 m³
2. PASIR URUG 0.294 m³
3. BATU KOSONG 0.588 m³
4. BATU KALI 4.3953 m³
5. TIMBUNAN 6.4827 m³
6. SLOOF 0.2646 m³
7. BALOK 0.1264 m³
8. KOLOM 0.6075 m³
9. PAS. BATA 35.28 m²
10. PLESTERAN 70.56 m²
HARGA SATUAN UPAH DAN BAHAN
NO Tenaga Kerja satuan harga satuan (Rp)
1 Kepala Tukang OH Rp 175,000.00
2 Pekerja OH Rp 160,000.00
3 Mandor OH Rp 225,000.00
4 Tukang batu OH Rp 160,000.00
5 Tukang kayu OH Rp 160,000.00
6 Tukang besi OH Rp 160,000.00
keterangan
ANALISA HARGA BAHAN
NO. URAIAN PEKERJAAN SAT KOEF
a b c d
PEKERJAAN TANAH
1 m³ Pek. Galian Tanah Keras
1
Pondasi
Pekerja OH 1.000
Mandor OH 0.032
JUMLAH
1 m³ Pek. Urugan Tanah
2
Kembali
Pekerja OH 0.333
Mandor OH 0.011
JUMLAH
PEKERJAAN PONDASI
1 m³ Urugan Pasir di Bawah
1
Pondasi (t = … cm)
Pasir Urug m³ 1.200
Pekerja OH 0.300
Mandor OH 0.010
JUMLAH
1 m³ Pasangan Batu Kosong (t
2
= … cm)
Batu Belah 15/20 cm m³ 1.200
Pasir Urug m³ 0.432
Tukang OH 0.390
Kepala Tukang OH 0.039
Pekerja OH 0.780
Mandor OH 0.039
JUMLAH
1 m³ Pekerjaan Pondasi Batu
3
Kali Camp. 1 : 4
Batu Belah 15/20 cm m³ 1.200
Portland Cement (PC) kg 163.00
Pasir Pasang m³ 0.520
Tukang OH 0.750
Kepala Tukang OH 0.075
Pekerja OH 1.500
Mandor OH 0.075
JUMLAH
PEKERJAAN DINDING
1 m² Pasangan Dinding Bata
1
Merah tebal ½ Bata Camp 1 : 4
Batu Bata bh 70.000
Portland Cement (PC) kg 11.500
Pasir Pasang m³ 0.043
Pekerja OH 0.300
Tukang OH 0.100
Kepala Tukang OH 0.010
Mandor OH 0.015
JUMLAH
1 m² Plesteran Dinding Camp.
2
1 : 5 (t = 15 mm)
Portland Cement (PC) kg 5.184
Pasir Pasang m³ 0.026
Pekerja OH 0.300
Tukang OH 0.150
Kepala Tukang OH 0.015
Mandor OH 0.015
JUMLAH
RGA BAHAN
HARGA (Rp.) JUMLAH (Rp.)
e f
160,000.00 160,000.00
225,000.00 7,200.00
JUMLAH 167,200.00
160,000.00 53,333.33
225,000.00 2,400.00
JUMLAH 55,733.33
350,000.00 420,000.00
160,000.00 48,000.00
225,000.00 2,250.00
JUMLAH 470,250.00
275,000.00 330,000.00
350,000.00 151,200.00
160,000.00 62,400.00
175,000.00 6,825.00
160,000.00 124,800.00
225,000.00 8,775.00
JUMLAH 684,000.00
275,000.00 330,000.00
2,500.00 407,500.00
450,000.00 234,000.00
160,000.00 120,000.00
175,000.00 13,125.00
160,000.00 240,000.00
225,000.00 16,875.00
JUMLAH 1,361,500.00
2,280,000.00 615,600.00
20,000.00 40,000.00
20,000.00 12,000.00
0.00
45,000.00 3,694,500.00
38,000.00 1,896,200.00
20,000.00 60,000.00
2,500.00 840,000.00
450,000.00 243,000.00
320,000.00 259,200.00
160,000.00 904,000.00
160,000.00 44,000.00
160,000.00 24,960.00
160,000.00 224,000.00
175,000.00 56,525.00
225,000.00 63,675.00
JUMLAH 8,977,660.00
2,280,000.00 912,000.00
20,000.00 80,000.00
20,000.00 12,000.00
0.00
45,000.00 4,924,845.00
38,000.00 1,949,400.00
20,000.00 90,000.00
2,500.00 840,000.00
450,000.00 243,000.00
320,000.00 259,200.00
2,580,000.00 387,000.00
95,000.00 332,500.00
15,000.00 300,000.00
160,000.00 1,128,000.00
160,000.00 44,000.00
160,000.00 24,960.00
160,000.00 224,000.00
175,000.00 56,525.00
225,000.00 63,675.00
JUMLAH 11,871,105.00
2,280,000.00 729,600.00
20,000.00 64,000.00
20,000.00 32,000.00
0.00
45,000.00 3,694,500.00
38,000.00 1,896,200.00
20,000.00 60,000.00
2,500.00 840,000.00
450,000.00 243,000.00
320,000.00 259,200.00
2,580,000.00 464,400.00
95,000.00 266,000.00
15,000.00 240,000.00
160,000.00 1,016,000.00
160,000.00 44,000.00
160,000.00 264,000.00
160,000.00 224,000.00
175,000.00 58,275.00
225,000.00 71,550.00
JUMLAH 10,466,725.00
1,200.00 84,000.00
2,500.00 28,750.00
450,000.00 19,350.00
160,000.00 48,000.00
160,000.00 16,000.00
175,000.00 1,750.00
225,000.00 3,375.00
JUMLAH 201,225.00
2,500.00 12,960.00
450,000.00 11,700.00
160,000.00 48,000.00
160,000.00 24,000.00
175,000.00 2,625.00
225,000.00 3,375.00
JUMLAH 102,660.00
REKAPITULASI KEBUTUHAN BAHAN
PAGAR BETON
JUMLAH
NO. URAIAN PEKERJAAN SATUAN
MATERIAL
PEMASANGAN BATU KALI, 1 PC : 4 PS
1 Batu Belah 15/20 cm m³ 5,184
2 Semen (PC) kg 704,16
3 Pasir Pasang m³ 22,464
URUGAN PASIR
1 Pasir Urug m³ 1,536
JUMLAH KESELURUHAN
KETERANGAN
NO. MATERIAL
PC : 4 PS 1 Batu Belah Pondasi 15/20 cm
2 Semen (PC)
3 Pasir Pasang
4 Pasir Urug
5 Bata Merah
KOSONG 6 Kayu Kelas III
7 Paku 5 cm - 12 cm
8 Minyak Bekisting
9 Besi Beton uk. 24
10 Kawat Beton
11 Pasir Beton
12 Kerikil Beton
5 PS 13 Multipleks 9 mm
14 Bambu
15 mm
BESI + BEKISTING)
KG BESI + BEKISTING )
150 KG + BEKISTING)
RUHAN
TOTAL
8,256
5.339,848
15.1296
1,536
7.616
2,564
15,63
9,3
1.309,2
18,7
3,624
5,43
13,41
76,65
RANCANGAN ANGGARAN BIAYA
NO. URAIAN PEKERJAAN SATUAN
I. PEKERJAAN PONDASI
1. Galian Tanah Pondasi m³
2. Pondasi Pasangan Batu Kali m³
3. Urugan Tanah Kembali m³
4. Pasangan Batu Kosong m³
5. Urugan Pasir m³
HARGA
8,852,220.93
10,910,179.16
14,342,907.60
34,105,307.69