Anda di halaman 1dari 32

HARGA SATUAN UPAH DAN BAHAN

TAHUN ANGGARAN 2020


A UPAH
1 Upah Pekerja
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Pekerja OH 80,000
Pekerja terlatih OH 90,000
2 Tukang
Tukang Batu OH 110,000
Tukang Kayu OH 110,000
Tukang Besi Beton OH 110,000
Tukang Las OH 110,000
Tukang Pelitur OH 110,000
Tukang Cat OH 110,000
Tukang Pipa PVC OH 110,000
Tukang Pipa Besi OH 110,000
Tukang Listrik OH 110,000
Tukang Alluminium OH 110,000
3 Kepala tukang
Kepala Tukang Batu OH 125,000
Kepala Tukang Kayu OH 125,000
Kepala Tukang Besi Beton OH 125,000
Kepala Tukang Las OH 125,000
Kepala Tukang Cat OH 125,000
Kepala Tukang Listrik OH 125,000
Kepala Tukang Alluminium OH 125,000

4 Pekerja ahli
Mandor OH 150,000
B HARGA SATUAN BAHAN
1 Bahan Pasangan dan Tanah
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Batu belah 15 cm - 20 cm m3 163,000 489,000
2 Batu Paras m3 196,000
3 Batu kali alam m3 175,000
4 Batu pecah 5-7 cm m3 224,000
5 Batu pecah 3-5 cm m3 281,000
6 Batu pecah 2-3 cm m3 304,000
7 Batu pecah 2-3 cm (kg) kg 150
8 Kerikil alam 2/3 cm m3 303,000
9 Kerikil Sungai - Royalti m3 287,000
10 Kerikil pecah 1/2 cm m3 294,000
11 Kerikil alam 1 cm m3 294,000
12 Koral Beton m3 163,000
13 Agregate 2-3 (stone crusher) m3 323,000
14 Agregate 1-2 (stone crusher) m3 398,000
15 Bata merah kelas 1 buah 500
16 Bata merah kelas 2 buah 400
17 Bata Ringan / Hebel t = 10 cm Biasa m3 690,000
18 Pasir Beton (PB) m3 163,000
19 Pasir Beton (PB) - kg kg 100
20 Pasir pasang m3 147,000
21 Pasir urug m3 116,000
22 Sirtu m3 115,000
23 Tanah urug biasa m3 74,000
24 Tanah urug pilihan m3 98,000
25 Semen Merah (SM) m3 87,000
26 Semen Warna kg 13,000
27 Semen Portland kg 1,500 75,000
28 Mortar Utama (MU-380) Perekat Bata Ringan kg 4,400
29 Rumput Gebalan m2 21,000
30 Kapur gamping kg 1,600
31 Kapur biasa kg 6,650
32 List plafon (propil) 4/4 cm m' 21,000
33 Air Liter 180

2 Bahan Atap
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Genteng keramik Buah 17,000
2 Atap multiroof 3,5 mm (lapis butiran) m² 263,000
3 Seng Spandek 3 mm lebar 70 cm m' 61,000
4 Genteng beton type flat Buah 8,500
5 Nok genteng beton type flat Buah 9,500

3 Bahan Kayu
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Papan
Papan Kayu Klas I m³ 14,900,000
Papan Kayu Klas II m³ 9,000,000
Papan Kayu Klas III m³ 3,000,000
Papan kayu bekisting m³ 1,500,000
2 Balok
Balok Kayu Klas I m³ 14,500,000
Balok Kayu Klas II m³ 8,700,000
Balok Kayu Klas III m³ 2,500,000
Balok kayu bekisting m³ 1,000,000
Dolken / Perancah Dia. 7 cm - 4 M batang 18,000
Kayu usuk 5/7 cm m³ 6,000,000
Penjaga jarak bekisting/spacer m¹ 4,500

4 Bahan Bambu
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Bambu (dia.12,5 cm, P - 6 m) batang 21,000
2 Bambu (dia.10 cm, P- 6 m) batang 19,000
3 Bambu (dia.7 cm, P- 6 m) batang 16,000
5 Bahan Cetak
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Buis Beton Dia. 30 cm. bh.L= 0.5M. 82,000
2 Buis Beton Dia. 40 Cm. bh.L= 0.5M. 82,000
3 Buis Beton Dia. 60 Cm. bh.L= 0.5M. 103,000
4 Buis Beton Dia. 80 Cm. bh.L= 0.5M. 136,000
6 Bahan Lantai
Harga (Rp.)
No. Uraian Satuan Keterangan
No. Uraian Satuan Keterangan
P. Lombok
1 Keramik dinding m² 66,000
2 Keramik KW I (Motif) m² 85,000
3 Keramik KW II (Motif) m² 72,000
4 Keramik KW I (polos) m² 58,000
5 Keramik KW II (polos) m² 52,000
Ubin Keramik
1 Ubin Keramik 40/40 m² 61,000
2 Ubin Keramik 20/20 m² 61,000
3 Ubin Keramik 10/33 m² 70,000
3 Batu tempel paras m² 121,000
4 Batu tempel hitam m² 130,000
5 Ubin Granit 40/40 m² 188,000.00
6 Ubin Granit 60/60 m² 215,000.00
Batu
1 Batu Teraso (Krikil Sikat) kg 5,200
2 Batu Granit (Krikil Sikat) kg 11,000

7 Bahan Besi
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Besi Beton Ulir kg 15,900
2 Besi Beton Polos kg 15,000
3 Besi Profil Siku ST 33 kg 14,200
4 Besi Plat kg 15,000
5 Besi profil siku ST 37 kg 15,000
6 Besi Baja WF dan Sejenisnya ST 37 kg 15,500
7 Besi Black steel (S40) kg 16,100
8 Alluminium Kuzen tebal 1,2 mm (natural) m' 98,800
9 Alluminium Kuzen tebal 1,2 mm (warna) m' 105,900
10 Besi canal C kg 16,000
11 Kawat Ikat Beton kg 23,200
12 Kawat Nyamuk Besi m2 23,200
13 Kawat Nyamuk Plastik m2 18,000
14 Kawat Las kg 33,100
15 Rolling door alluminium m2 500,200
16 Alluminium strip m2 46,200
17 Pintu Alluminium m' 113,000
18 Profil kaca alluminium m' 47,000
19 Venetions blinds dan vertical blinds (tirai) m2 210,100
20 Rangka metal hollow 40.40.2 mm m 25,500
21 Rangka metal hollow 40.20.1 mm m 20,400
22 Main Trust C 75 - 85 m¹ 22,000
23 Main Trust C 75 - 75 m¹ 19,500
24 Reng TS 40 - 0,50 m¹ 1,200
25 Srew 12-14x20 Bh 600
26 Srew 10-16x16 Bh 400
27 Anchor Bolt Bh 12,750
28 Wiremesh M 8 m2 59,730
29 Wiremesh M 10 m2 93,968
30 Bondex Tebal 0,75 mm m2 156,000

8 Bahan Langit-langit
Harga (Rp.)
No. Uraian Satuan Keterangan
No. Uraian Satuan Keterangan
P. Lombok
1 Triplek 120x240x 6 mm lembar 95,000
2 Triplek 120x240x 9 mm lembar 152,000
3 Triplek 120x240x 12 mm lembar 197,000
4 Triplek 120x240x 18 mm lembar 275,000
5 Triplek lapis alluminium lembar 132,000
6 Multipleks 120 x 240 x 12 mm lembar 203,000
7 Multipleks 120 x 240 x 18 mm lembar 286,000
8 Multipleks 120 x 240 x 4 mm lembar 89,000
9 Multipleks 120 x 240 x 6 mm lembar 89,000
10 Multipleks 120 x 240 x 9 mm lembar 152,000
11 Calsiboard 120 x 240 x 3,5 mm lembar 74,000
12 Gypsum board 120 x 240 x 9 mm lembar 108,000
13 List Gypsum Profil 10 cm m¹ 22,000
14 List Gypsum Profil besar m¹ 29,000
15 List Kayu Profil m¹ 6,400
16 Lem Kayu kg 39,000
17 Lem kg 28,000
18 Kalsiplang L=20 cm. m¹ 27,000
19 Teakwood 90x290x3 mm lembar 121,000

9 Bahan Pipa
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
Pipa PVC
1 Pipa PVC Ø 1/2" M' 5,600
2 Pipa PVC Ø 3/4" M' 7,000
3 Pipa PVC Ø 1" M' 11,000
4 Pipa PVC Ø 1 1/2" M' 34,000
5 Pipa PVC Ø 2" M' 84,000
6 Pipa PVC Ø 3" M' 123,000
7 Pipa PVC Ø 4" M' 131,000
8 Pipa PVC Dia. 2" Type D M' 25,000
9 Pipa PVC Dia. 2½" Type D M' 37,000
10 Pipa PVC Dia. 3" Type D M' 22,000
11 Pipa PVC Dia. 4" Type D M' 25,000
12 Lem PVC kg 122,000
ACESSORIS PIPA
1 Stop Kran
1 Dia ½" Buah 57,000
2 Dia ¾" Buah 87,000
3 Dia 1" Buah 216,000
4 Dia 2" Buah 576,000
5 Dia 3" Buah 1,571,000
2 Kran
1 Kran Ø ½" Buah 30,000
2 Kran Ø ¾" Buah 43,000
10 Bahan Kaca
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Kaca Polos 3 mm m² 93,000
2 Kaca Polos 5 mm m² 123,000
11 Bahan Finishing
No. Uraian Satuan Harga (Rp.)
1 Ampelas lembar 3,500
2 Plamir Kayu kg 25,000
3 Minyak Cat liter 10,000
4 Residu liter 13,000
5 Melamin lembar 81,000
6 Meni Besi liter 24,000
7 Meni Kayu kg 41,000
8 Cat Kayu Mutu Menengah kg 35,000
9 Cat Kayu Mutu Tinggi kg 53,000
10 Cat Tembok Mutu Menengah Kg 39,000
11 Cat Tembok Mutu Tinggi kg/ kaleng 66,000
12 Cat Dasar Kayu kg 24,000
13 Cat Besi kg 30,000
14 Kuas bh 10,000
15 Plamir Tembok kg 9,000
16 Tepung Gypsum kg 18,000
17 Minyak Cat liter 37,000
18 Aqua Proff kg 50,000
19 Cat dasar anti alkali kg 54,000
20 Roll cat buah 12,000
21 Cat Dasar Tembok Kg 47,000
12 Bahan Pengunci
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Kunci pintu mutu menengah buah 110,000
2 Kunci pintu mutu Tinggi buah 220,000
3 Yale Kecil buah 60,000
4 Yale Besar buah 108,000
5 Kuda Terbang Kecil buah 62,000
6 Kuda Terbang Besar buah 77,000
7 Haag Angin Besar stel 7,000
8 Haag Angin Kecil stel 5,600
9 Grendel Besar buah 12,000
10 Grendel Kecil buah 9,000
11 Engsel Nylon buah 14,000
12 Engsel Biasa buah 9,000
13 Expagnolet buah 58,000
14 Kunci Tanam Biasa buah 95,000
15 Kunci Tanam Biasa Mutu Menengah buah 158,000
16 Kunci Tanam Antik buah 254,000
17 Kunci Silinder buah 44,000
18 Kunci Slot buah 63,000
19 Door Holder buah 38,000
20 Door Closer buah 190,000
13 Bahan Sanitaire
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Closet Jongkok porselain buah 138,000
2 Closed duduk keramik buah 2,115,000
3 Wastafel buah 1,322,000
4 Urinoir Porselin (Kw.1) buah 1,542,000
5 Saringan Air Besi Stainless buah 155,000
6 Saringan air besi buah 56,000
7 Floor Drain buah 17,000
8 Seal tape buah 3,000
9 Jetspray Buah 120,000
14 Bahan Paku
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Paku 1 cm - 2.5 cm kg 21,000
2 Paku 5 cm - 10 cm kg 20,000
3 Paku 5 cm - 7 cm kg 20,000
4 Paku 5 cm - 12 cm kg 19,000
5 Paku Skrup kg 19,000
6 Paku Kait buah 1,900
7 Skrup / Piles 1,5 cm. doos kecil 9,200
8 Skrup / Piles 2,0 cm. doos kecil 11,000
9 Paku Skrup 5 cm kg 22,000
10 Paku Skrup 10 cm kg 22,000
11 Paku Skrup 1 cm - 2,5 cm buah 400
12 Skrup Fixer buah 17,000
13 Paku kg 19,000
15 Bahan Listrik
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Titik Lampu buah 264,000
2 Stop Kontak Tanam buah 211,000
3 Stop Kontak Luar buah 201,000
4 Saklar ganda buah 26,000
5 Saklar tunggal buah 21,000
6 Zekering Boxes 1 Group buah 286,000
7 Zekering Boxs 2 Group buah 370,000
8 Zekering Boxs 3 Group buah 455,000
9 Box Skring 2 Grup buah 165,000
10 NYA 2,5 mm klas biasa m' 3,000
11 Pipa paralon 5/8" batang 5,000
16 Bahan Tambahan
Harga (Rp.)
No. Uraian Satuan Keterangan
P. Lombok
1 Minyak Pelumas liter 23,000
2 Minyak Begisting liter 14,000
3 Sealent tube 19,000
4 Solar liter 6,800
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
TAHUN ANGGARAN 2020

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A.2.2.1.4 Pengukuran dan pemasangan 1 m’ Bouwplank
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.100 80,000 8,000.00
2 Tukang Kayu L.02 OH 0.100 110,000 11,000.00
3 Kepala Tukang Kayu L.03 OH 0.010 125,000 1,250.00
4 Mandor L.04 OH 0.005 150,000 750.00
Jumlah Tenaga Kerja 21,000.00
B Bahan
1 Balok Kayu Klas III m³ 0.012 2,500,000 30,000.00
2 Paku 5 cm - 7 cm kg 0.020 20,000 400.00
3 Papan kayu bekisting m³ 0.007 1,500,000 10,500.00
Jumlah Harga Bahan 40,900.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 61,900.00
E Overhead & Profit 10 % 10% x D 6,190.00
F Harga Satuan Pekerjaan (D+E) 68,090.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.750 80,000 60,000.00
2 Mandor L.04 OH 0.025 150,000 3,750.00
Jumlah Tenaga Kerja 63,750.00
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 63,750.00
E Overhead & Profit 10 % 10% x D 6,375.00
F Harga Satuan Pekerjaan (D+E) 70,125.00
A.2.3.1.2 Penggalian 1 m3 tanah biasa sedalam 2 m
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.900 80,000 72,000.00
2 Mandor L.04 OH 0.045 150,000 6,750.00
Jumlah Tenaga Kerja 78,750.00
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 78,750.00
E Overhead & Profit 10 % 10% x D 7,875.00
F Harga Satuan Pekerjaan (D+E) 86,625.00
A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.500 80,000 40,000.00
2 Mandor L.04 OH 0.050 150,000 7,500.00
Jumlah Tenaga Kerja 47,500.00
B Bahan

Jumlah Harga Bahan


C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 47,500.00
E Overhead & Profit 10 % 10% x D 4,750.00
F Harga Satuan Pekerjaan (D+E) 52,250.00
A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.300 80,000 24,000.00
2 Mandor L.04 OH 0.010 150,000 1,500.00
Jumlah Tenaga Kerja 25,500.00
B Bahan
1 Pasir urug m3 1.200 116,000 139,200.00
Jumlah Harga Bahan 139,200.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 164,700.00
E Overhead & Profit 10 % 10% x D 16,470.00
F Harga Satuan Pekerjaan (D+E) 181,170.00
A.2.3.1.11a Pengurugan 1 m3 dengan tanah urug
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.300 80,000 24,000.00
2 Mandor L.04 OH 0.010 150,000 1,500.00
Jumlah Tenaga Kerja 25,500.00
B Bahan
1 Tanah urug biasa m3 1.200 74,000 88,800.00
Jumlah Harga Bahan 88,800.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 114,300.00
E Overhead & Profit 10 % 10% x D 11,430.00
F Harga Satuan Pekerjaan (D+E) 125,730.00
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 1.500 80,000 120,000.00
2 Tukang Batu L.02 OH 0.750 110,000 82,500.00
3 Kepala Tukang Batu L.03 OH 0.075 125,000 9,375.00
4 Mandor L.04 OH 0.075 150,000 11,250.00
Jumlah Tenaga Kerja 223,125.00
B Bahan
1 Batu belah 15 cm - 20 cm m3 1.200 163,000 195,600.00
2 Semen Portland kg 136.000 1,500 204,000.00
3 Pasir Pasang m3 0.544 147,000 79,968.00
Jumlah Harga Bahan 479,568.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 702,693.00
E Overhead & Profit 10 % 10% x D 70,269.30
F Harga Satuan Pekerjaan (D+E) 772,962.30
A.3.2.1.9 Pemasangan 1 m3 batu kosong (anstamping)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.780 80,000 62,400.00
2 Tukang Batu L.02 OH 0.390 110,000 42,900.00
3 Kepala Tukang Batu L.03 OH 0.039 125,000 4,875.00
4 Mandor L.04 OH 0.039 150,000 5,850.00
Jumlah Tenaga Kerja 116,025.00
B Bahan
1 Batu belah 15 cm - 20 cm m3 1.200 163,000 195,600.00
2 Pasir urug m3 0.432 116,000 50,112.00
Jumlah Harga Bahan 245,712.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 361,737.00
E Overhead & Profit 10 % 10% x D 36,173.70
F Harga Satuan Pekerjaan (D+E) 397,910.70
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100) slump (3-6) cm, w/c = 0,87
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 1.200 80,000 96,000.00
2 Tukang Batu L.02 OH 0.200 110,000 22,000.00
3 Kepala Tukang Batu L.03 OH 0.020 125,000 2,500.00
4 Mandor L.04 OH 0.060 150,000 9,000.00
Jumlah Tenaga Kerja 129,500.00
B Bahan
1 Semen Portland kg 230.000 1,500 345,000.00
2 Pasir Beton (PB) - kg kg 893.000 100 89,300.00
3 Batu pecah 2-3 cm (kg) kg 1,027.000 150 154,050.00
4 Air Liter 200.000 180 36,000.00
Jumlah Harga Bahan 624,350.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 753,850.00
E Overhead & Profit 10 % 10% x D 75,385.00
F Harga Satuan Pekerjaan (D+E) 829,235.00
A.4.1.1.7 Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 2) cm, w/c = 0,58
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 1.650 80,000 132,000.00
2 Tukang Batu L.02 OH 0.275 110,000 30,250.00
3 Kepala Tukang Batu L.03 OH 0.028 125,000 3,500.00
4 Mandor L.04 OH 0.083 150,000 12,450.00
Jumlah Tenaga Kerja 178,200.00
B Bahan
1 Semen Portland kg 371.000 1,500 556,500.00
2 Pasir Beton (PB) - kg kg 698.000 100 69,800.00
3 Batu pecah 2-3 cm (kg) kg 1,047.000 150 157,050.00
4 Air Liter 215.000 180 38,700.00
Jumlah Harga Bahan 822,050.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 1,000,250.00
E Overhead & Profit 10 % 10% x D 100,025.00
F Harga Satuan Pekerjaan (D+E) 1,100,275.00
A.4.1.1.17a Pembesian 1 kg dengan besi polos
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.007 80,000 560.00
2 Tukang Besi Beton L.02 OH 0.007 110,000 770.00
3 Kepala Tukang Besi Beton L.03 OH 0.001 125,000 87.50
4 Mandor L.04 OH 0.000 150,000 60.00
Jumlah Tenaga Kerja 1,477.50
B Bahan
1 Besi Beton Polos kg 1.050 15,000 15,750.00
2 Kawat Ikat Beton kg 0.015 23,200 348.00
Jumlah Harga Bahan 16,098.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 17,575.50
E Overhead & Profit 10 % 10% x D 1,757.55
F Harga Satuan Pekerjaan (D+E) 19,333.05
A.4.1.1.17b Pembesian 1 kg dengan besi ulir
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.007 80,000 560.00
2 Tukang Besi Beton L.02 OH 0.007 110,000 770.00
3 Kepala Tukang Besi Beton L.03 OH 0.001 125,000 87.50
4 Mandor L.04 OH 0.000 150,000 60.00
Jumlah Tenaga Kerja 1,477.50
B Bahan
1 Besi Beton ulir kg 1.050 15,900 16,695.00
2 Kawat Ikat Beton kg 0.015 23,200 348.00
Jumlah Harga Bahan 17,043.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 18,520.50
E Overhead & Profit 10 % 10% x D 1,852.05
F Harga Satuan Pekerjaan (D+E) 20,372.55
A.4.1.1.17c Memasang 1 m2 wire mesh M8 ( 2 lapis )
Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.070 80,000 5,600.00
2 Tukang Besi Beton L.02 OH 0.050 110,000 5,500.00
3 Kepala Tukang Besi Beton L.03 OH 0.004 125,000 500.00
4 Mandor L.04 OH 0.002 150,000 300.00
Jumlah Tenaga Kerja 11,900.00
B Bahan
1 Wiremesh M 8 m2 2.200 59,730 131,406.35
2 Kawat Ikat Beton kg 1.820 23,200 42,224.00
2 Besi tumpuan kg 0.100 15,900 1,590.00
Jumlah Harga Bahan 175,220.35
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 187,120.35
E Overhead & Profit 10 % 10% x D 18,712.03
F Harga Satuan Pekerjaan (D+E) 205,832.38
A.4.1.1.17d Memasang 1 m2 wire mesh M10 ( 2 lapis )
Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.070 80,000 5,600.00
2 Tukang Besi Beton L.02 OH 0.050 110,000 5,500.00
3 Kepala Tukang Besi Beton L.03 OH 0.004 125,000 500.00
4 Mandor L.04 OH 0.002 150,000 300.00
Jumlah Tenaga Kerja 11,900.00
B Bahan
1 Wiremesh M 10 m2 2.200 93,968 206,730.16
2 Kawat Ikat Beton kg 1.820 23,200 42,224.00
2 Besi tumpuan kg 0.100 15,900 1,590.00
Jumlah Harga Bahan 250,544.16
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 262,444.16
E Overhead & Profit 10 % 10% x D 26,244.42
F Harga Satuan Pekerjaan (D+E) 288,688.57
A.4.1.1.17e Memasang 1 m2 Bondek
Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.050 80,000 4,000.00
2 Tukang Besi Beton L.02 OH 0.030 110,000 3,300.00
3 Kepala Tukang Besi Beton L.03 OH 0.010 125,000 1,250.00
4 Mandor L.04 OH 0.010 150,000 1,500.00
Jumlah Tenaga Kerja 10,050.00
B Bahan
1 Bondex Tebal 0,75 mm m2 1.010 156,000 157,560.00
2 Kayu usuk 5/7 cm m3 0.016 6,000,000 94,500.00
3 Balok Kayu Klas III m3 0.015 2,500,000 36,875.00
4 Paku 5 cm - 10 cm kg 0.100 20,000 2,000.00

Jumlah Harga Bahan 290,935.00


C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 300,985.00
E Overhead & Profit 10 % 10% x D 30,098.50
F Harga Satuan Pekerjaan (D+E) 331,083.50
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.660 80,000 52,800.00
2 Tukang Kayu L.02 OH 0.330 110,000 36,300.00
3 Kepala Tukang Kayu L.03 OH 0.033 125,000 4,125.00
4 Mandor L.04 OH 0.033 150,000 4,950.00
Jumlah Tenaga Kerja 98,175.00
B Bahan
1 Balok Kayu Klas III m³ 0.040 2,500,000 100,000.00
2 Paku 5 cm - 12 cm kg 0.400 19,000 7,600.00
3 Minyak begisting liter 0.200 14,000 2,800.00
5 Triplek 120x240x 9 mm lembar 0.350 152,000 53,200.00
Jumlah Harga Bahan 163,600.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 261,775.00
E Overhead & Profit 10 % 10% x D 26,177.50
F Harga Satuan Pekerjaan (D+E) 287,952.50
A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.660 80,000 52,800.00
2 Tukang Kayu L.02 OH 0.330 110,000 36,300.00
3 Kepala Tukang Kayu L.03 OH 0.033 125,000 4,125.00
4 Mandor L.04 OH 0.033 150,000 4,950.00
Jumlah Tenaga Kerja 98,175.00
B Bahan
1 Balok Kayu Klas III m³ 0.040 2,500,000 100,000.00
2 Paku 5 cm - 12 cm kg 0.400 19,000 7,600.00
3 Minyak begisting liter 0.200 14,000 2,800.00
4 Balok kayu bekisting m³ 0.015 1,000,000 15,000.00
5 Triplek 120x240x 9 mm lembar 0.350 152,000 53,200.00
6 Dolken / Perancah Dia. 7 cm - 4 M batang - 18,000 -
Jumlah Harga Bahan 178,600.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 276,775.00
E Overhead & Profit 10 % 10% x D 27,677.50
F Harga Satuan Pekerjaan (D+E) 304,452.50
A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.660 80,000 52,800.00
2 Tukang Kayu L.02 OH 0.330 110,000 36,300.00
3 Kepala Tukang Kayu L.03 OH 0.033 125,000 4,125.00
4 Mandor L.04 OH 0.033 150,000 4,950.00
Jumlah Tenaga Kerja 98,175.00
B Bahan
1 Balok Kayu Klas III m³ 0.040 2,500,000 100,000.00
2 Paku 5 cm - 12 cm kg 0.400 19,000 7,600.00
3 Minyak begisting liter 0.200 14,000 2,800.00
4 Balok kayu bekisting m³ 0.018 1,000,000 18,000.00
5 Triplek 120x240x 9 mm lembar 0.350 152,000 53,200.00
6 Dolken / Perancah Dia. 7 cm - 4 M batang - 18,000 -
Jumlah Harga Bahan 181,600.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 279,775.00
E Overhead & Profit 10 % 10% x D 27,977.50
F Harga Satuan Pekerjaan (D+E) 307,752.50
A.4.1.1.24 Pemasangan 1 m2 bekisting untuk lantai
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.660 80,000 52,800.00
2 Tukang Kayu L.02 OH 0.330 110,000 36,300.00
3 Kepala Tukang Kayu L.03 OH 0.033 125,000 4,125.00
4 Mandor L.04 OH 0.033 150,000 4,950.00
Jumlah Tenaga Kerja 98,175.00
B Bahan
1 Balok Kayu Klas III m³ 0.040 2,500,000 100,000.00
2 Paku 5 cm - 12 cm kg 0.400 19,000 7,600.00
3 Minyak begisting liter 0.200 14,000 2,800.00
4 Balok Kayu Klas III m³ 0.015 2,500,000 37,500.00
5 Triplek 120x240x 9 mm lembar 0.350 152,000 53,200.00
6 Dolken / Perancah Dia. 7 cm - 4 M batang 6.000 18,000 108,000.00
Jumlah Harga Bahan 309,100.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 407,275.00
E Overhead & Profit 10 % 10% x D 40,727.50
F Harga Satuan Pekerjaan (D+E) 448,002.50
A.4.1.1.25 Pemasangan 1 m2 bekisting untuk dinding
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.660 80,000 52,800.00
2 Tukang Kayu L.02 OH 0.330 110,000 36,300.00
3 Kepala Tukang Kayu L.03 OH 0.033 125,000 4,125.00
4 Mandor L.04 OH 0.033 150,000 4,950.00
Jumlah Tenaga Kerja 98,175.00
B Bahan
1 Balok Kayu Klas III m³ 0.030 2,500,000 75,000.00
2 Paku 5 cm - 12 cm kg 0.400 19,000 7,600.00
3 Minyak begisting liter 0.200 14,000 2,800.00
4 Balok Kayu Klas II m³ 0.020 8,700,000 174,000.00
5 Triplek 120x240x 9 mm lembar 0.350 152,000 53,200.00
6 Dolken / Perancah Dia. 7 cm - 4 M batang 3.000 18,000 54,000.00
7 Penjaga jarak bekisting/spacer m¹ 4.000 4,500 18,000.00
Jumlah Harga Bahan 384,600.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 482,775.00
E Overhead & Profit 10 % 10% x D 48,277.50
F Harga Satuan Pekerjaan (D+E) 531,052.50
A.4.1.1.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 5.3000 80,000 424,000.00
2 Tukang Batu L.02 OH 0.0275 110,000 3,025.00
3 Tukang Kayu L.02 OH 1.3000 110,000 143,000.00
4 Tukang Besi Beton L.02 OH 1.0500 110,000 115,500.00
5 Kepala Tukang Batu L.03 OH 0.2620 125,000 32,750.00
6 Mandor L.04 OH 0.2650 150,000 39,750.00
Jumlah Tenaga Kerja 758,025.00
B Bahan
1 Balok Kayu Klas III m³ 0.200 2,500,000 500,000.00
2 Paku 5 cm - 12 cm kg 1.500 19,000 28,500.00
3 Minyak begisting liter 0.400 14,000 5,600.00
4 Besi Beton Polos kg 157.500 15,000 2,362,500.00
5 Kawat Ikat Beton kg 2.250 23,200 52,200.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
Jumlah Harga Bahan 3,787,060.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 4,545,085.00
E Overhead & Profit 10 % 10% x D 454,508.50
F Harga Satuan Pekerjaan (D+E) 4,999,593.50
A.4.1.1.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 5.6500 80,000 452,000.00
2 Tukang Batu L.02 OH 0.2750 110,000 30,250.00
3 Tukang Kayu L.02 OH 1.5600 110,000 171,600.00
4 Tukang Besi Beton L.02 OH 1.4000 110,000 154,000.00
5 Kepala Tukang Batu L.03 OH 0.3230 125,000 40,375.00
6 Mandor L.04 OH 0.2830 150,000 42,450.00
Jumlah Tenaga Kerja 890,675.00
B Bahan
1 Balok Kayu Klas III m³ 0.270 2,500,000 675,000.00
2 Paku 5 cm - 12 cm kg 2.000 19,000 38,000.00
3 Minyak begisting liter 0.600 14,000 8,400.00
4 Besi Beton Polos kg 210.000 15,000 3,150,000.00
5 Kawat Ikat Beton kg 3.000 23,200 69,600.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
Jumlah Harga Bahan 4,779,260.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 5,669,935.00
E Overhead & Profit 10 % 10% x D 566,993.50
F Harga Satuan Pekerjaan (D+E) 6,236,928.50
A.4.1.1.29a Membuat 1 m³ sloof beton bertulang 15 x 20 cm (162,63 kg besi + bekisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 5.6500 80,000 452,000.00
2 Tukang Batu L.02 OH 0.2750 110,000 30,250.00
3 Tukang Kayu L.02 OH 1.5600 110,000 171,600.00
4 Tukang Besi Beton L.02 OH 1.4000 110,000 154,000.00
5 Kepala Tukang Batu L.03 OH 0.3230 125,000 40,375.00
6 Mandor L.04 OH 0.2830 150,000 42,450.00
Jumlah Tenaga Kerja 890,675.00
B Bahan
1 Balok Kayu Klas III m³ 0.270 2,500,000 675,000.00
2 Paku 5 cm - 12 cm kg 2.000 19,000 38,000.00
3 Minyak begisting liter 0.600 14,000 8,400.00
4 Besi Beton Polos kg 143.292 15,000 2,149,374.86
5 Kawat Ikat Beton kg 3.000 23,200 69,600.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
Jumlah Harga Bahan 3,778,634.86
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 4,669,309.86
E Overhead & Profit 10 % 10% x D 466,930.99
F Harga Satuan Pekerjaan (D+E) 5,136,240.84
A.4.1.1.30g Membuat 1 m3 kolom beton bertulang (175,44 kg Besi + Bekisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)

1 Beton Mutu K225 A.4.1.1.7 m³ 1.0000 1,100,275 1,100,275.00


2 Begesting kolom A.4.1.1.22 m² 13.3333 304,453 4,059,366.67
3 Pembesian polos A.4.1.1.17a Kg 69.6968 19,333 1,347,451.44
4 Pembesian ulir A.4.1.1.17b Kg 175.4413 20,373 3,574,186.04

D Jumlah (A+B+C) 10,081,279.15


E Overhead & Profit 10 % 10% x D 1,008,127.92
F Harga Satuan Pekerjaan (D+E) 11,089,407.07
A.4.1.1.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 6.3500 80,000 508,000.00
2 Tukang Batu L.02 OH 0.2750 110,000 30,250.00
3 Tukang Kayu L.02 OH 1.6500 110,000 181,500.00
4 Tukang Besi Beton L.02 OH 1.4000 110,000 154,000.00
5 Kepala Tukang Batu L.03 OH 0.3330 125,000 41,625.00
6 Mandor L.04 OH 0.3180 150,000 47,700.00
Jumlah Tenaga Kerja 963,075.00
B Bahan
1 Balok Kayu Klas III m³ 0.320 2,500,000 800,000.00
2 Paku 5 cm - 12 cm kg 3.200 19,000 60,800.00
3 Minyak begisting liter 1.600 14,000 22,400.00
4 Besi Beton Polos kg 210.000 15,000 3,150,000.00
5 Kawat Ikat Beton kg 3.000 23,200 69,600.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
9 Balok Kayu Klas II m³ 0.140 8,700,000 1,218,000.00
10 Triplek 120x240x 9 mm lembar 2.800 152,000 425,600.00
11 Dolken / Perancah Dia. 7 cm - 4 M batang 16.000 18,000 288,000.00
Jumlah Harga Bahan 6,872,660.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 7,835,735.00
E Overhead & Profit 10 % 10% x D 783,573.50
F Harga Satuan Pekerjaan (D+E) 8,619,308.50
A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.1800 80,000 14,400.00
2 Tukang Batu L.02 OH 0.2000 110,000 22,000.00
3 Tukang Kayu L.02 OH 0.2000 110,000 22,000.00
4 Tukang Besi Beton L.02 OH 0.2000 110,000 22,000.00
5 Kepala Tukang Batu L.03 OH 0.0060 125,000 750.00
6 Mandor L.04 OH 0.0090 150,000 1,350.00
Jumlah Tenaga Kerja 82,500.00
B Bahan
1 Balok Kayu Klas III m³ 0.002 2,500,000 5,000.00
2 Paku 5 cm - 12 cm kg 0.010 19,000 190.00
3 Minyak begisting liter - 14,000 -
4 Besi Beton Polos kg 3.000 15,000 45,000.00
5 Kawat Ikat Beton kg 0.450 23,200 10,440.00
6 Semen Portland kg 4.000 1,500 6,000.00
7 Pasir Beton (PB) m3 0.006 163,000 978.00
8 Batu pecah 2-3 cm m3 0.009 304,000 2,736.00
Jumlah Harga Bahan 70,344.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 152,844.00
E Overhead & Profit 10 % 10% x D 15,284.40
F Harga Satuan Pekerjaan (D+E) 168,128.40
A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2970 80,000 23,760.00
2 Tukang Batu L.02 OH 0.0330 110,000 3,630.00
3 Tukang Kayu L.02 OH 0.0330 110,000 3,630.00
4 Tukang Besi Beton L.02 OH 0.0330 110,000 3,630.00
5 Kepala Tukang Batu L.03 OH 0.0100 125,000 1,250.00
6 Mandor L.04 OH 0.0150 150,000 2,250.00
Jumlah Tenaga Kerja 38,150.00
B Bahan
1 Balok Kayu Klas III m³ 0.003 2,500,000 7,500.00
2 Paku 5 cm - 12 cm kg 0.020 19,000 380.00
3 Minyak begisting liter 0.020 14,000 280.00
4 Besi Beton Polos kg 3.600 15,000 54,000.00
5 Kawat Ikat Beton kg 0.050 23,200 1,160.00
6 Semen Portland kg 5.500 1,500 8,250.00
7 Pasir Beton (PB) m3 0.009 163,000 1,467.00
8 Batu pecah 2-3 cm m3 0.015 304,000 4,560.00
Jumlah Harga Bahan 77,597.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 115,747.00
E Overhead & Profit 10 % 10% x D 11,574.70
F Harga Satuan Pekerjaan (D+E) 127,321.70
A.4.1.1.36a Membuat 1 m’ balok late beton bertulang (10 x 15) cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2970 80,000 23,760.00
2 Tukang Batu L.02 OH 0.0330 110,000 3,630.00
3 Tukang Kayu L.02 OH 0.0330 110,000 3,630.00
4 Tukang Besi Beton L.02 OH 0.0330 110,000 3,630.00
5 Kepala Tukang Batu L.03 OH 0.0100 125,000 1,250.00
6 Mandor L.04 OH 0.0150 150,000 2,250.00
Jumlah Tenaga Kerja 38,150.00
B Bahan
1 Balok Kayu Klas III m³ 0.003 2,500,000 7,500.00
2 Paku 5 cm - 12 cm kg 0.020 19,000 380.00
3 Minyak begisting liter 0.020 14,000 280.00
4 Besi Beton Polos kg 2.680 15,000 40,200.00
5 Kawat Ikat Beton kg 0.050 23,200 1,160.00
6 Semen Portland kg 5.500 1,500 8,250.00
7 Pasir Beton (PB) m3 0.009 163,000 1,467.00
8 Batu pecah 2-3 cm m3 0.015 304,000 4,560.00
Jumlah Harga Bahan 63,797.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 101,947.00
E Overhead & Profit 10 % 10% x D 10,194.70
F Harga Satuan Pekerjaan (D+E) 112,141.70
SNI 2008.6.32 Membuat 1 m3 Plat beton bertulang ( 150 Kg Besi + Begisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 5.3000 80,000 424,000.00
2 Tukang Batu L.02 OH 0.2750 110,000 30,250.00
3 Tukang Kayu L.02 OH 1.3000 110,000 143,000.00
4 Tukang Besi Beton L.02 OH 1.0500 110,000 115,500.00
5 Kepala Tukang Batu L.03 OH 0.2650 125,000 33,125.00
6 Mandor L.04 OH 0.2650 150,000 39,750.00
Jumlah Tenaga Kerja 785,625.00
B Bahan
1 Papan Kayu Klas III m³ 0.320 3,000,000 960,000.00
2 Paku 5 cm - 12 cm kg 3.200 19,000 60,800.00
3 Minyak begisting liter 1.600 14,000 22,400.00
4 Besi Beton Polos kg 157.500 15,000 2,362,500.00
5 Kawat Ikat Beton kg 2.250 23,200 52,200.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
9 Balok Kayu Klas III m³ 0.120 2,500,000 300,000.00
10 Triplek 120x240x 6 mm lembar 2.800 95,000 266,000.00
11 Dolken / Perancah Dia. 7 cm - 4 M batang 32.000 18,000 576,000.00
Jumlah Harga Bahan 5,438,160.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 6,223,785.00
E Overhead & Profit 10 % 10% x D 622,378.50
F Harga Satuan Pekerjaan (D+E) 6,846,163.50
SNI 2008.6.32a Membuat 1 m3 Plat beton bertulang T = 12 cm ( 121,98 Kg Besi + Begisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 5.3000 80,000 424,000.00
2 Tukang Batu L.02 OH 0.2750 110,000 30,250.00
3 Tukang Kayu L.02 OH 1.3000 110,000 143,000.00
4 Tukang Besi Beton L.02 OH 1.0500 110,000 115,500.00
5 Kepala Tukang Batu L.03 OH 0.2650 125,000 33,125.00
6 Mandor L.04 OH 0.2650 150,000 39,750.00
Jumlah Tenaga Kerja 785,625.00
B Bahan
1 Balok Kayu Klas III m³ 0.320 2,500,000 800,000.00
2 Paku 5 cm - 12 cm kg 3.200 19,000 60,800.00
3 Minyak begisting liter 1.600 14,000 22,400.00
4 Besi Beton Polos kg 121.976 15,000 1,829,633.14
5 Kawat Ikat Beton kg 2.250 23,200 52,200.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
9 Triplek 120x240x 6 mm lembar 2.800 95,000 266,000.00
10 Dolken / Perancah Dia. 7 cm - 4 M batang 32.000 18,000 576,000.00
Jumlah Harga Bahan 4,445,293.14
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 5,230,918.14
E Overhead & Profit 10 % 10% x D 523,091.81
F Harga Satuan Pekerjaan (D+E) 5,754,009.96
SNI 2008.6.32b Membuat 1 m3 Plat beton bertulang T = 10 cm ( 146,37 Kg Besi + Begisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
Pekerja L.01 OH 5.3000 80,000 424,000.00
Tukang Batu L.02 OH 0.2750 110,000 30,250.00
Tukang Kayu L.02 OH 1.3000 110,000 143,000.00
Tukang Besi Beton L.02 OH 1.0500 110,000 115,500.00
Kepala Tukang Batu L.03 OH 0.2650 125,000 33,125.00
Mandor L.04 OH 0.2650 150,000 39,750.00
Jumlah Tenaga Kerja 785,625.00
B Bahan
Balok Kayu Klas III m³ 0.320 2,500,000 800,000.00
Paku 5 cm - 12 cm kg 3.200 19,000 60,800.00
Minyak begisting liter 1.600 14,000 22,400.00
Besi Beton Polos kg 146.371 15,000 2,195,559.77
Kawat Ikat Beton kg 2.250 23,200 52,200.00
Semen Portland kg 336.000 1,500 504,000.00
Pasir Beton (PB) m3 0.540 163,000 88,020.00
Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
Triplek 120x240x 6 mm lembar 2.800 95,000 266,000.00
Dolken / Perancah Dia. 7 cm - 4 M batang 32.000 18,000 576,000.00
Jumlah Harga Bahan 4,811,219.77
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 5,596,844.77
E Overhead & Profit 10 % 10% x D 559,684.48
F Harga Satuan Pekerjaan (D+E) 6,156,529.25
SNI 2008.6.32c Membuat 1 m3 Plat beton bertulang T = 8 cm ( 77,9 Kg Besi + Begisting) tul. non rangkap
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 5.3000 80,000 424,000.00
2 Tukang Batu L.02 OH 0.2750 110,000 30,250.00
3 Tukang Kayu L.02 OH 1.3000 110,000 143,000.00
4 Tukang Besi Beton L.02 OH 1.0500 110,000 115,500.00
5 Kepala Tukang Batu L.03 OH 0.2650 125,000 33,125.00
6 Mandor L.04 OH 0.2650 150,000 39,750.00
Jumlah Tenaga Kerja 785,625.00
B Bahan
1 Balok Kayu Klas III m³ 0.320 2,500,000 800,000.00
2 Paku 5 cm - 12 cm kg 3.200 19,000 60,800.00
3 Minyak begisting liter 1.600 14,000 22,400.00
4 Besi Beton Polos kg 77.929 15,000 1,168,932.29
5 Kawat Ikat Beton kg 2.250 23,200 52,200.00
6 Semen Portland kg 336.000 1,500 504,000.00
7 Pasir Beton (PB) m3 0.540 163,000 88,020.00
8 Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
9 Triplek 120x240x 6 mm lembar 2.800 95,000 266,000.00
10 Dolken / Perancah Dia. 7 cm - 4 M batang 32.000 18,000 576,000.00
Jumlah Harga Bahan 3,784,592.29
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 4,570,217.29
E Overhead & Profit 10 % 10% x D 457,021.73
F Harga Satuan Pekerjaan (D+E) 5,027,239.01
SNI 2008.6.32d Membuat 1 m3 Plat beton bertulang T = 15 cm ( 97,580 Kg Besi + Begisting)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
Pekerja L.01 OH 5.3000 80,000 424,000.00
Tukang Batu L.02 OH 0.2750 110,000 30,250.00
Tukang Kayu L.02 OH 1.3000 110,000 143,000.00
Tukang Besi Beton L.02 OH 1.0500 110,000 115,500.00
Kepala Tukang Batu L.03 OH 0.2650 125,000 33,125.00
Mandor L.04 OH 0.2650 150,000 39,750.00
Jumlah Tenaga Kerja 785,625.00
B Bahan
Balok Kayu Klas III m³ 0.320 2,500,000 800,000.00
Paku 5 cm - 12 cm kg 3.200 19,000 60,800.00
Minyak begisting liter 1.600 14,000 22,400.00
Besi Beton Polos kg 97.580 15,000 1,463,706.51
Kawat Ikat Beton kg 2.250 23,200 52,200.00
Semen Portland kg 336.000 1,500 504,000.00
Pasir Beton (PB) m3 0.540 163,000 88,020.00
Batu pecah 2-3 cm m3 0.810 304,000 246,240.00
Triplek 120x240x 6 mm lembar 2.800 95,000 266,000.00
Dolken / Perancah Dia. 7 cm - 4 M batang 32.000 18,000 576,000.00
Jumlah Harga Bahan 4,079,366.51
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 4,864,991.51
E Overhead & Profit 10 % 10% x D 486,499.15
F Harga Satuan Pekerjaan (D+E) 5,351,490.67
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
A.4.2.1.11 Pemasangan 1 m kusen pintu alluminium
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.043 80,000 3,440.00
2 Tukang Alluminium L.02 OH 0.043 110,000 4,730.00
3 Kepala Tukang Alluminium L.03 OH 0.004 125,000 537.50
4 Mandor L.04 OH 0.002 150,000 315.00
Jumlah Tenaga Kerja 9,022.50
B Bahan
1 Alluminium Kuzen tebal 1,2 mm (natural) m' 1.100 98,800 108,680.00
2 Skrup Fixer buah 2.000 17,000 34,000.00
3 Sealent tube 0.060 19,000 1,140.00
Jumlah Harga Bahan 143,820.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 152,842.50
E Overhead & Profit 10 % 10% x D 15,284.25
F Harga Satuan Pekerjaan (D+E) 168,126.75
A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alluminium
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0850 80,000 6,800.00
2 Tukang Alluminium L.02 OH 0.0850 110,000 9,350.00
3 Kepala Tukang Alluminium L.03 OH 0.0090 125,000 1,125.00
4 Mandor L.04 OH 0.0050 150,000 750.00
Jumlah Tenaga Kerja 18,025.00
B Bahan
1 Pintu Alluminium m' 4.400 113,000 497,200.00
2 Profil kaca alluminium m' 4.500 47,000 211,500.00
3 Sealent tube 14.600 19,000 277,400.00
Jumlah Harga Bahan 986,100.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 1,004,125.00
E Overhead & Profit 10 % 10% x D 100,412.50
F Harga Satuan Pekerjaan (D+E) 1,104,537.50
A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, dinding partisi
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2500 80,000 20,000.00
2 Tukang Besi Beton L.02 OH 0.2500 110,000 27,500.00
3 Kepala Tukang Besi Beton L.03 OH 0.0250 125,000 3,125.00
4 Mandor L.04 OH 0.0130 150,000 1,950.00
Jumlah Tenaga Kerja 52,575.00
B Bahan
1 Rangka metal hollow 40.20.1 mm m 3.500 20,400 71,400.00
2 Assesoris (perkuatan, las dll) Ls 100% 20,400 20,400.00
Jumlah Harga Bahan 91,800.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 144,375.00
E Overhead & Profit 10 % 10% x D 14,437.50
F Harga Satuan Pekerjaan (D+E) 158,812.50
A.4.2.1.21 Pemasangan 1 m² rangka besi hollow 1x40.40.1mm, modul 60 x 60 cm, plafon
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.3500 80,000 28,000.00
2 Tukang Besi Beton L.02 OH 0.3500 110,000 38,500.00
3 Kepala Tukang Besi Beton L.03 OH 0.0350 125,000 4,375.00
4 Mandor L.04 OH 0.0180 150,000 2,700.00
Jumlah Tenaga Kerja 73,575.00
B Bahan
1 Rangka metal hollow 40.20.1 mm m 4.000 20,400 81,600.00
2 Assesoris (perkuatan, las dll) Ls 100% 20,400 20,400.00
Jumlah Harga Bahan 102,000.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 175,575.00
E Overhead & Profit 10 % 10% x D 17,557.50
F Harga Satuan Pekerjaan (D+E) 193,132.50
A.4.2.1.21a Pemasangan 1 m² atap baja ringan
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
Pekerja L.01 OH 0.3500 80,000 28,000.00
Tukang Besi Beton L.02 OH 0.3500 110,000 38,500.00
Kepala Tukang Besi Beton L.03 OH 0.0350 125,000 4,375.00
Mandor L.04 OH 0.0180 150,000 2,700.00
Jumlah Tenaga Kerja 73,575.00
B Bahan
Main Trust C 75 - 75 m¹ 4.4000 19,500 85,800.00
Reng TS 40 - 0,50 m¹ 4.4700 1,200 5,364.00
Srew 12-14x20 Buah 12.0000 600 7,200.00
Srew 10-16x16 Buah 16.0000 400 6,400.00
Anchor Bolt Buah 1.0000 12,750 12,750.00
Jumlah Harga Bahan 117,514.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 191,089.00
E Overhead & Profit 10 % 10% x D 19,108.90
F Harga Satuan Pekerjaan (D+E) 210,197.90
A.4.2.1.21b Pemasangan 1 m² rangka usuk dan reng baja ringan
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.3500 80,000 28,000.00
2 Tukang Besi Beton L.02 OH 0.3500 110,000 38,500.00
3 Kepala Tukang Besi Beton L.03 OH 0.0350 125,000 4,375.00
4 Mandor L.04 OH 0.0180 150,000 2,700.00
Jumlah Tenaga Kerja 73,575.00
B Bahan
Main Trust C 75 - 75 m¹ 2.2000 19,500 42,900.00
Reng TS 40 - 0,50 m¹ 4.4700 1,200 5,364.00
Srew 12-14x20 Buah 12.0000 600 7,200.00
Srew 10-16x16 Buah 16.0000 400 6,400.00
Jumlah Harga Bahan 61,864.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 135,439.00
E Overhead & Profit 10 % 10% x D 13,543.90
F Harga Satuan Pekerjaan (D+E) 148,982.90
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
A.4.4.1.2 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6000 80,000 48,000.00
2 Tukang Batu L.02 OH 0.2000 110,000 22,000.00
3 Kepala Tukang Batu L.03 OH 0.0200 125,000 2,500.00
4 Mandor L.04 OH 0.0300 150,000 4,500.00
Jumlah Tenaga Kerja 77,000.00
B Bahan
1 Bata merah kelas 2 buah 140.000 400 56,000.00
2 Semen Portland kg 32.950 1,500 49,425.00
3 Pasir pasang m3 0.091 147,000 13,377.00
Jumlah Harga Bahan 118,802.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 195,802.00
E Overhead & Profit 10 % 10% x D 19,580.20
F Harga Satuan Pekerjaan (D+E) 215,382.20
A.4.4.1.3 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6000 80,000 48,000.00
2 Tukang Batu L.02 OH 0.2000 110,000 22,000.00
3 Kepala Tukang Batu L.03 OH 0.0200 125,000 2,500.00
4 Mandor L.04 OH 0.0300 150,000 4,500.00
Jumlah Tenaga Kerja 77,000.00
B Bahan
1 Bata merah kelas 2 buah 140.000 400 56,000.00
2 Semen Portland kg 26.550 1,500 39,825.00
3 Pasir pasang m3 0.093 147,000 13,671.00
Jumlah Harga Bahan 109,496.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 186,496.00
E Overhead & Profit 10 % 10% x D 18,649.60
F Harga Satuan Pekerjaan (D+E) 205,145.60
A.4.4.1.8 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.3000 80,000 24,000.00
2 Tukang Batu L.02 OH 0.1000 110,000 11,000.00
3 Kepala Tukang Batu L.03 OH 0.0100 125,000 1,250.00
4 Mandor L.04 OH 0.0150 150,000 2,250.00
Jumlah Tenaga Kerja 38,500.00
B Bahan
1 Bata merah kelas 2 buah 70.000 400 28,000.00
2 Semen Portland kg 14.370 1,500 21,555.00
3 Pasir pasang m3 0.040 147,000 5,880.00
Jumlah Harga Bahan 55,435.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 93,935.00
E Overhead & Profit 10 % 10% x D 9,393.50
F Harga Satuan Pekerjaan (D+E) 103,328.50
A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 4PP
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.3000 80,000 24,000.00
2 Tukang Batu L.02 OH 0.1000 110,000 11,000.00
3 Kepala Tukang Batu L.03 OH 0.0100 125,000 1,250.00
4 Mandor L.04 OH 0.0150 150,000 2,250.00
Jumlah Tenaga Kerja 38,500.00
B Bahan
1 Bata merah kelas 2 buah 70.000 400 28,000.00
2 Semen Portland kg 11.500 1,500 17,250.00
3 Pasir pasang m3 0.043 147,000 6,321.00
Jumlah Harga Bahan 51,571.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 90,071.00
E Overhead & Profit 10 % 10% x D 9,007.10
F Harga Satuan Pekerjaan (D+E) 99,078.10
A.4.4.1.23b 1 m2 Pasangan Bata Ringan setara CELCON BLOK tebal 10 cm, ukr. 60x20x10 cm; standard
Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0935 80,000 7,480.00
2 Tukang Batu L.02 OH 0.3740 110,000 41,140.00
3 Kepala Tukang Batu L.03 OH 0.0374 125,000 4,675.00
4 Mandor L.04 OH 0.0374 150,000 5,610.00
Jumlah Tenaga Kerja 58,905.00
B Bahan
1 Bata Ringan / Hebel t = 10 cm Biasa m3 0.108 690,000 74,819.28
2 Mortar Utama (MU-380) Perekat Bata Ringan kg 4.000 4,400 17,600.00

Jumlah Harga Bahan 92,419.28


C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 151,324.28
E Overhead & Profit 10 % 10% x D 15,132.43
F Harga Satuan Pekerjaan (D+E) 166,456.70

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.3 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15 mm.
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.3000 80,000 24,000.00
2 Tukang Batu L.02 OH 0.1500 110,000 16,500.00
3 Kepala Tukang Batu L.03 OH 0.0150 125,000 1,875.00
4 Mandor L.04 OH 0.0150 150,000 2,250.00
Jumlah Tenaga Kerja 44,625.00
B Bahan
1 Semen Portland kg 7.776 1,500 11,664.00
2 Pasir pasang m3 0.023 147,000 3,381.00
Jumlah Harga Bahan 15,045.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 59,670.00
E Overhead & Profit 10 % 10% x D 5,967.00
F Harga Satuan Pekerjaan (D+E) 65,637.00
A.4.4.2.27 Pemasangan 1 m2 acian.
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2000 80,000 16,000.00
2 Tukang Batu L.02 OH 0.1000 110,000 11,000.00
3 Kepala Tukang Batu L.03 OH 0.0100 125,000 1,250.00
4 Mandor L.04 OH 0.0100 150,000 1,500.00
Jumlah Tenaga Kerja 29,750.00
B Bahan
1 Semen Portland kg 3.250 1,500 4,875.00

Jumlah Harga Bahan 4,875.00


C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 34,625.00
E Overhead & Profit 10 % 10% x D 3,462.50
F Harga Satuan Pekerjaan (D+E) 38,087.50
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
A.4.4.3.35 Pemasangan 1m2 lantai keramik Granit Ukuran 60cm x 60cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.7000 80,000 56,000.00
2 Tukang Batu L.02 OH 0.3500 110,000 38,500.00
3 Kepala Tukang Batu L.03 OH 0.0350 125,000 4,375.00
4 Mandor L.04 OH 0.0350 150,000 5,250.00
Jumlah Tenaga Kerja 104,125.00
B Bahan
1 Ubin Granit 60/60 m² 1.000 215,000 215,000.00
2 Semen Portland kg 8.190 1,500 12,285.00
3 Pasir pasang m3 0.045 147,000 6,615.00
4 Semen warna kg 1.620 13,000 21,060.00
Jumlah Harga Bahan 254,960.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 359,085.00
E Overhead & Profit 10 % 10% x D 35,908.50
F Harga Satuan Pekerjaan (D+E) 394,993.50
A.4.4.3.35a Pemasangan 1m2 lantai keramik ukuran 40cm x 40cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.7000 80,000 56,000.00
2 Tukang Batu L.02 OH 0.3500 110,000 38,500.00
3 Kepala Tukang Batu L.03 OH 0.0350 125,000 4,375.00
4 Mandor L.04 OH 0.0350 150,000 5,250.00
Jumlah Tenaga Kerja 104,125.00
B Bahan
1 Keramik KW I (polos) m² 1.000 58,000 58,000.00
2 Semen Portland kg 8.190 1,500 12,285.00
3 Pasir pasang m3 0.045 147,000 6,615.00
4 Semen warna kg 1.620 13,000 21,060.00
Jumlah Harga Bahan 97,960.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 202,085.00
E Overhead & Profit 10 % 10% x D 20,208.50
F Harga Satuan Pekerjaan (D+E) 222,293.50
A.4.4.3.36 Pemasangan 1m2 lantai keramik ukuran 25 x 25 cm.
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.7000 80,000 56,000.00
2 Tukang Batu L.02 OH 0.3500 110,000 38,500.00
3 Kepala Tukang Batu L.03 OH 0.0350 125,000 4,375.00
4 Mandor L.04 OH 0.0350 150,000 5,250.00
Jumlah Tenaga Kerja 104,125.00
B Bahan
1 Ubin Keramik 20/20 m² 1.000 61,000 61,000.00
2 Semen Portland kg 10.400 1,500 15,600.00
3 Pasir pasang m3 0.045 147,000 6,615.00
4 Semen warna kg 1.620 13,000 21,060.00
Jumlah Harga Bahan 104,275.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 208,400.00
E Overhead & Profit 10 % 10% x D 20,840.00
F Harga Satuan Pekerjaan (D+E) 229,240.00
A.4.4.3.54 Pemasangan 1 m2 dinding keramik 25cm x 40cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.9000 80,000 72,000.00
2 Tukang Batu L.02 OH 0.4500 110,000 49,500.00
3 Kepala Tukang Batu L.03 OH 0.0450 125,000 5,625.00
4 Mandor L.04 OH 0.0450 150,000 6,750.00
Jumlah Tenaga Kerja 133,875.00
B Bahan
1 Keramik dinding m² 1.000 66,000 66,000.00
2 Semen Portland kg 9.300 1,500 13,950.00
3 Pasir pasang m3 0.018 147,000 2,646.00
4 Semen warna kg 1.940 13,000 25,220.00
Jumlah Harga Bahan 107,816.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 241,691.00
E Overhead & Profit 10 % 10% x D 24,169.10
F Harga Satuan Pekerjaan (D+E) 265,860.10
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
A.4.5.1.5a Pemasangan 1 m2 langit-langit calsiboar ukuran (120 x 240) cm, tebal 3,5 mm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.1000 80,000 8,000.00
2 Tukang Kayu L.02 OH 0.1000 110,000 11,000.00
3 Kepala Tukang Kayu L.03 OH 0.0100 125,000 1,250.00
4 Mandor L.04 OH 0.0050 150,000 750.00
Jumlah Tenaga Kerja 21,000.00
B Bahan
1 Calsiboard 120 x 240 x 3,5 mm lembar 0.375 74,000 27,750.00
2 Paku 1 cm - 2.5 cm kg 0.030 21,000 630.00
Jumlah Harga Bahan 28,380.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 49,380.00
E Overhead & Profit 10 % 10% x D 4,938.00
F Harga Satuan Pekerjaan (D+E) 54,318.00
A.4.5.1.9a Pemasangan 1 m¹ kalsiplang 2x L=20 cm.
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0500 80,000 4,000.00
2 Tukang Kayu L.02 OH 0.0500 110,000 5,500.00
3 Kepala Tukang Kayu L.03 OH 0.0050 125,000 625.00
4 Mandor L.04 OH 0.0030 150,000 450.00
Jumlah Tenaga Kerja 10,575.00
B Bahan
1 Kalsiplang L=20 cm. m¹ 1.000 20,000 20,000.00
2 Paku kg 0.110 19,000 2,090.00
Jumlah Harga Bahan 22,090.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 32,665.00
E Overhead & Profit 10 % 10% x D 3,266.50
F Harga Satuan Pekerjaan (D+E) 35,931.50
A.4.5.1.9b Pemasangan 1 m’ list langit-langit Gypsun profil 10 cm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0500 80,000 4,000.00
2 Tukang Kayu L.02 OH 0.0500 110,000 5,500.00
3 Kepala Tukang Kayu L.03 OH 0.0050 125,000 625.00
4 Mandor L.04 OH 0.0030 150,000 450.00
Jumlah Tenaga Kerja 10,575.00
B Bahan
1 List Gypsum Profil 10 cm m¹ 1.050 22,000 23,100.00
2 Paku kg 0.110 19,000 2,090.00
Jumlah Harga Bahan 25,190.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 35,765.00
E Overhead & Profit 10 % 10% x D 3,576.50
F Harga Satuan Pekerjaan (D+E) 39,341.50
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.38a Pemasangan 1 m2 atap seng metal
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.1200 80,000 9,600.00
2 Tukang Kayu L.02 OH 0.0600 110,000 6,600.00
3 Kepala Tukang Kayu L.03 OH 0.0060 125,000 750.00
4 Mandor L.04 OH 0.0060 150,000 900.00
Jumlah Tenaga Kerja 17,850.00
B Bahan
1 Atap Metal m2 1.000 52,000 52,000.00
2 Paku Skrup kg 0.020 19,000 380.00
Jumlah Harga Bahan 52,380.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 70,230.00
E Overhead & Profit 10 % 10% x D 7,023.00
F Harga Satuan Pekerjaan (D+E) 77,253.00
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.5 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 1.0000 80,000 80,000.00
2 Tukang Kayu L.02 OH 3.0000 110,000 330,000.00
3 Kepala Tukang Kayu L.03 OH 0.3000 125,000 37,500.00
4 Mandor L.04 OH 0.0500 150,000 7,500.00
Jumlah Tenaga Kerja 455,000.00
B Bahan
1 Papan Kayu Klas II m³ 0.040 9,000,000 360,000.00
2 Lem Kayu kg 0.500 39,000 19,500.00
Jumlah Harga Bahan 379,500.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 834,500.00
E Overhead & Profit 10 % 10% x D 83,450.00
F Harga Satuan Pekerjaan (D+E) 917,950.00
A.4.6.1.27.1 Pemasangan 1 m² lapis dinding gypsum 9 mm.
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0250 80,000 2,000.00
2 Tukang Kayu L.02 OH 0.0750 110,000 8,250.00
3 Kepala Tukang Kayu L.03 OH 0.0080 125,000 1,000.00
4 Mandor L.04 OH 0.0010 150,000 150.00
Jumlah Tenaga Kerja 11,400.00
B Bahan
1 Gypsum board 120 x 240 x 9 mm lembar 0.6944 108,000 74,999.52
2 Paku 1 cm - 2.5 cm kg 0.0500 21,000 1,050.00
Jumlah Harga Bahan 76,049.52
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 87,449.52
E Overhead & Profit 10 % 10% x D 8,744.95
F Harga Satuan Pekerjaan (D+E) 96,194.47
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
A.4.6.2.16 Pemasangan 1 m2 kaca polos tebal 3 mm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0150 80,000 1,200.00
2 Tukang Kayu L.02 OH 0.1500 110,000 16,500.00
3 Kepala Tukang Kayu L.03 OH 0.0150 125,000 1,875.00
4 Mandor L.04 OH 0.0008 150,000 120.00
Jumlah Tenaga Kerja 19,695.00
B Bahan
1 Kaca Polos 3 mm m² 1.1000 93,000 102,300.00
2 Sealent tube 0.0500 19,000 950.00
Jumlah Harga Bahan 103,250.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 122,945.00
E Overhead & Profit 10 % 10% x D 12,294.50
F Harga Satuan Pekerjaan (D+E) 135,239.50
A.4.6.2.17 Pemasangan 1 m2 kaca polos tebal 5 mm
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0150 80,000 1,200.00
2 Tukang Kayu L.02 OH 0.1500 110,000 16,500.00
3 Kepala Tukang Kayu L.03 OH 0.0150 125,000 1,875.00
4 Mandor L.04 OH 0.0008 150,000 120.00
Jumlah Tenaga Kerja 19,695.00
B Bahan
1 Kaca Polos 5 mm m² 1.1000 123,000 135,300.00
2 Sealent tube 0.0500 19,000 950.00
Jumlah Harga Bahan 136,250.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 155,945.00
E Overhead & Profit 10 % 10% x D 15,594.50
F Harga Satuan Pekerjaan (D+E) 171,539.50
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lps plamir, 1 lps cat dasar, 2 lps cat penutup)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0700 80,000 5,600.00
2 Tukang Cat L.02 OH 0.0090 110,000 990.00
3 Kepala Tukang Cat L.03 OH 0.0060 125,000 750.00
4 Mandor L.04 OH 0.0030 150,000 450.00
Jumlah Tenaga Kerja 7,790.00
B Bahan
1 Meni Kayu kg 0.2000 41,000 8,200.00
2 Plamir Kayu kg 0.1500 25,000 3,750.00
3 Cat Dasar Kayu kg 0.1700 24,000 4,080.00
4 Cat Kayu Mutu Menengah kg 0.2600 35,000 9,100.00
5 Kuas bh 0.0100 10,000 100.00
6 Minyak Cat liter 0.0300 10,000 300.00
7 Ampelas lembar 0.2000 3,500 700.00
Jumlah Harga Bahan 26,230.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 34,020.00
E Overhead & Profit 10 % 10% x D 3,402.00
F Harga Satuan Pekerjaan (D+E) 37,422.00
A.4.7.1.10 Pengecatan 1 m2 tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0200 80,000 1,600.00
2 Tukang Cat L.02 OH 0.0630 110,000 6,930.00
3 Kepala Tukang Cat L.03 OH 0.0063 125,000 787.50
4 Mandor L.04 OH 0.0030 150,000 450.00
Jumlah Tenaga Kerja 9,767.50
B Bahan
1 Plamir Tembok kg 0.1000 9,000 900.00
2 Cat Dasar Tembok Kg 0.1000 47,000 4,700.00
3 Cat Tembok Mutu Menengah Kg 0.2600 39,000 10,140.00
15,740.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 25,507.50
E Overhead & Profit 10 % 10% x D 2,550.75
F Harga Satuan Pekerjaan (D+E) 28,058.25
A.4.7.1.10a Pengecatan 1 m² tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) mutu tinggi
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0200 80,000 1,600.00
2 Tukang Cat L.02 OH 0.0630 110,000 6,930.00
3 Kepala Tukang Cat L.03 OH 0.0063 125,000 787.50
4 Mandor L.04 OH 0.0030 150,000 450.00
Jumlah Tenaga Kerja 9,767.50
B Bahan
1 Plamir Tembok kg 0.1000 9,000 900.00
2 Cat Dasar Tembok Kg 0.1000 47,000 4,700.00
3 Cat Tembok Mutu Tinggi kg/ kaleng 0.2600 38,000 9,880.00
15,480.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 25,247.50
E Overhead & Profit 10 % 10% x D 2,524.75
F Harga Satuan Pekerjaan (D+E) 27,772.25
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.2a Pemasangan 1 buah closet duduk
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 1.0000 80,000 80,000.00
2 Tukang Batu L.02 OH 1.5000 110,000 165,000.00
3 Kepala Tukang Batu L.03 OH 0.1500 125,000 18,750.00
4 Mandor L.04 OH 0.1600 150,000 24,000.00
Jumlah Tenaga Kerja 287,750.00
B Bahan
1 Closed duduk keramik buah 1.0000 2,115,000 2,115,000.00
2 Semen Portland kg 6.0000 1,500 9,000.00
3 Pasir pasang m3 0.0100 147,000 1,470.00
2,125,470.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 2,413,220.00
E Overhead & Profit 10 % 10% x D 241,322.00
F Harga Satuan Pekerjaan (D+E) 2,654,542.00
A.5.1.1.4 Pemasangan 1 buah urinoir
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
Pekerja L.01 OH 1.0000 80,000 80,000.00
Tukang Batu L.02 OH 1.0000 110,000 110,000.00
Kepala Tukang Batu L.03 OH 0.1000 125,000 12,500.00
Mandor L.04 OH 0.0500 150,000 7,500.00
Jumlah Tenaga Kerja 210,000.00
B Bahan
Urinoir Porselin (Kw.1) Unit 1.0000 1,542,000 1,542,000.00
Semen Portland kg 6.0000 1,500 9,000.00
Pasir pasang m3 0.0100 147,000 1,470.00
Perlengkapan % 30.0000 1,542,000 462,600.00
2,015,070.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 2,225,070.00
E Overhead & Profit 10 % 10% x D 222,507.00
F Harga Satuan Pekerjaan (D+E) 2,447,577.00
A.5.1.1.5a Pemasangan 1 buah wastafel
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 1.2000 80,000 96,000.00
2 Tukang Batu L.02 OH 1.4500 110,000 159,500.00
3 Kepala Tukang Batu L.03 OH 0.1500 125,000 18,750.00
4 Mandor L.04 OH 0.0600 150,000 9,000.00
Jumlah Tenaga Kerja 283,250.00
B Bahan
1 Wastafel buah 1.0000 454,200 454,200.00
2 Semen Portland kg 6.0000 1,500 9,000.00
3 Pasir pasang m3 0.0100 147,000 1,470.00
4 Perlengkapan Ls 12% 454,200 54,504.00
519,174.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 802,424.00
E Overhead & Profit 10 % 10% x D 80,242.40
F Harga Satuan Pekerjaan (D+E) 882,666.40
A.5.1.1.14 Pemasangan 1 buah floor drain
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0100 80,000 800.00
2 Tukang Batu L.02 OH 0.1000 110,000 11,000.00
3 Kepala Tukang Batu L.03 OH 0.0100 125,000 1,250.00
4 Mandor L.04 OH 0.0050 150,000 750.00
Jumlah Tenaga Kerja 13,800.00
B Bahan
1 Saringan Air Besi buah 1.0000 56,000 56,000.00

56,000.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 69,800.00
E Overhead & Profit 10 % 10% x D 6,980.00
F Harga Satuan Pekerjaan (D+E) 76,780.00
A.5.1.1.19 Pemasangan 1 buah kran diameter ½”
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0100 80,000 800.00
2 Tukang Batu L.02 OH 0.4000 110,000 44,000.00
3 Kepala Tukang Batu L.03 OH 0.0400 125,000 5,000.00
4 Mandor L.04 OH 0.0050 150,000 750.00
Jumlah Tenaga Kerja 50,550.00
B Bahan
1 Kran Ø ½" Buah 1.0000 30,000 30,000.00
2 Seal tape Ls 0.0250 3,000 75.00
30,075.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 80,625.00
E Overhead & Profit 10 % 10% x D 8,062.50
F Harga Satuan Pekerjaan (D+E) 88,687.50
A.5.1.1.25 Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0360 80,000 2,880.00
2 Tukang Batu L.02 OH 0.0600 110,000 6,600.00
3 Kepala Tukang Batu L.03 OH 0.0060 125,000 750.00
4 Mandor L.04 OH 0.0020 150,000 300.00
Jumlah Tenaga Kerja 10,530.00
B Bahan
1 Pipa PVC Ø 1/2" M' 1.2000 5,600 6,720.00
2 Perlengkapan (35% x pipa) Ls 35% 5,600 1,960.00
8,680.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 19,210.00
E Overhead & Profit 10 % 10% x D 1,921.00
F Harga Satuan Pekerjaan (D+E) 21,131.00
A.5.1.1.26 Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0360 80,000 2,880.00
2 Tukang Batu L.02 OH 0.0600 110,000 6,600.00
3 Kepala Tukang Batu L.03 OH 0.0060 125,000 750.00
4 Mandor L.04 OH 0.0020 150,000 300.00
Jumlah Tenaga Kerja 10,530.00
B Bahan
1 Pipa PVC Ø 3/4" M' 1.2000 7,000 8,400.00
2 Perlengkapan (35% x pipa) Ls 35% 7,000 2,450.00
10,850.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 21,380.00
E Overhead & Profit 10 % 10% x D 2,138.00
F Harga Satuan Pekerjaan (D+E) 23,518.00
A.5.1.1.31 Pemasangan 1 m’ pipa PVC tipe AW diameter 3”
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0810 80,000 6,480.00
2 Tukang Batu L.02 OH 0.1350 110,000 14,850.00
3 Kepala Tukang Batu L.03 OH 0.0135 125,000 1,687.50
4 Mandor L.04 OH 0.0040 150,000 600.00
Jumlah Tenaga Kerja 23,617.50
B Bahan
1 Pipa PVC Ø 3" M' 1.2000 123,000 147,600.00
2 Perlengkapan (35% x pipa) Ls 35% 123,000 43,050.00
190,650.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 214,267.50
E Overhead & Profit 10 % 10% x D 21,426.75
F Harga Satuan Pekerjaan (D+E) 235,694.25
A.5.1.1 HARGA SATUAN PEKERJAAN MEKANIKAL DAN ELEKTRIKAL (ME)
ME.1 Pemasangan 1 Titik lampu
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0500 80,000 4,000.00
2 Tukang Listrik L.02 OH 0.5000 110,000 55,000.00
3 Kepala Tukang Listrik L.03 OH 0.0500 125,000 6,250.00
Jumlah Tenaga Kerja 65,250.00
B Bahan
1 NYA 2,5 mm klas biasa m' 15.0000 3,000 45,000.00
2 Pipa paralon 5/8" batang 2.0000 5,000 10,000.00
3 Acsesories set 1.0000 35,000 35,000.00
90,000.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 155,250.00
E Overhead & Profit 10 % 10% x D 15,525.00
F Harga Satuan Pekerjaan (D+E) 170,775.00
ME.2 Pemasangan 1 Titik stop kontak
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0500 80,000 4,000.00
2 Tukang Listrik L.02 OH 0.5000 110,000 55,000.00
3 Kepala Tukang Listrik L.03 OH 0.0500 125,000 6,250.00
Jumlah Tenaga Kerja 65,250.00
B Bahan
1 NYA 2,5 mm klas biasa m' 15.0000 3,000 45,000.00
2 Pipa paralon 5/8" batang 2.0000 5,000 10,000.00
3 Acsesories Set 1.0000 25,000 25,000.00
80,000.00
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 145,250.00
E Overhead & Profit 10 % 10% x D 14,525.00
F Harga Satuan Pekerjaan (D+E) 159,775.00
EXTRAS
LMR 1 Pembuatan 1m2 Pintu Tempered Glass (Framless)
Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Upah Pemasangan Unit 1.0000 850,000 850,000
Jumlah Tenaga Kerja 850,000
B Bahan
List Alumunium U M1 1.00 39,500 39,500
Kaca Tempered 12mm M2 1.00 1,250,000 1,250,000
Floor Hinges set 1.00 400,000 400,000
Over Panel set 1.00 500,000 500,000
Top Patch Fitting set 1.00 500,000 500,000
Bottom Patch Fitting set 1.00 150,000 150,000
Bottom Patch Lock + Cylinder set 1.00 150,000 150,000
Pull Handle set 1.00 300,000 300,000
3,289,500
C Peralatan
Jumlah Harga Alat
D Jumlah (A+B+C) 4,139,500
E Overhead & Profit 10 % 10% x D 413,950
F Harga Satuan Pekerjaan (D+E) 4,553,450

LMR 1 Pembuatan 1m2 Pintu Tempered Glass (Framless)


Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Upah Pemasangan Unit 1.0000 850,000 850,000
Jumlah Tenaga Kerja 850,000
B Bahan
List Alumunium U M1 1.00 39,500 39,500
Kaca Tempered 12mm M2 1.00 900,000 900,000
939,500
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 1,789,500
E Overhead & Profit 10 % 10% x D 178,950
F Harga Satuan Pekerjaan (D+E) 1,968,450

LMR 3 Pemasangan 1 m3 Gording


Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Mandor L1 OH 0.120 150,000 18,000
2 Kepala Tukang Kayu L2 OH 0.700 125,000 87,500
3 Tukang Kayu L3 OH 7.000 110,000 770,000
1 Pekerja L4 OH 2.4000 80,000 192,000
Jumlah Tenaga Kerja 1,067,500
B Bahan
Balok Kayu Klas II M3 1.10 8,700,000 9,570,000
Paku KG 2.20 19,000 41,800
9,611,800
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 10,679,300
E Overhead & Profit 10 % 10% x D 1,067,930
F Harga Satuan Pekerjaan (D+E) 11,747,230

LMR 4 Pemasangan 1 m3 Gording


Harga
No Uraian Kode Satuan Koefisien Satuan Jumlah Harga
(Rp) (Rp)
A Tenaga
1 Mandor L1 OH 0.005 105,100 526
2 Kepala Tukang Kayu L2 OH 0.010 99,000 990
3 Tukang Kayu L3 OH 0.100 99,000 9,900
1 Pekerja L4 OH 0.1000 72,600 7,260
Jumlah Tenaga Kerja 18,676
B Bahan
Kayu usuk 5/7 cm M3 0.01 6,000,000 72,000
Paku KG 0.15 19,000 2,850
74,850
C Peralatan

Jumlah Harga Alat


D Jumlah (A+B+C) 93,526
E Overhead & Profit 10 % 10% x D 9,353
F Harga Satuan Pekerjaan (D+E) 102,878

A.4.2.1.15 Pemasangan 1 m2 terali besi strip (2x3) mm


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koef.
No Uraian Kode Satuan Koef.
Rp Rp
A TENAGA
Pekerja L.01 OH 1.670 80,000.00 133,600.00
Tukang las L.03 OH 1.670 110,000.00 183,700.00
Kepala tukang L.03 OH 0.167 125,000.00 20,875.00
Mandor L.04 OH 0.083 150,000.00 12,450.00
TOTAL UPAH TENAGA 350,625.00
B BAHAN
Besi strip Kg 6.177 6,000.00 37,062.00
Pengelasan Cm 27.080 250.00 6,770.00
TOTAL BIAYA BAHAN 43,832.00
C PERALATAN
0.00
0.00
TOTAL BIAYA PERALATAN 0.00
D Total upah tanaga, biaya material dan peralatan (A + B + C) 394,457.00
E Overhead + profit 15 % x D 59,168.55
D Harga satuan pekerjaan (D + E) 453,625.55

Anda mungkin juga menyukai