Anda di halaman 1dari 42

DAFTAR ANALISA HARGA SATUAN BAHAN DAN UPAH

No URAIAN HARGA Upah (Rp) Bahan (Rp) Jumlah


. SATUAN (Rp) Harga (Rp)
a b c d e f
1 Pekerjaan Persiapan
1.1 1 M³ PEMBERSIHAN LAPANGAN
Upah
0.025 OH Mandor 295,204.42 7,380.11
0.1 OH Pekerja 168,688.24 16,868.82
Sub Jumlah 24,248.93 24,248.93
1.2 PEMBUATAN 1 M³ PAGAR SEMENTARA SENG
BERGELOMBANG
Bahan
1.25 btg Btg Dolken kayu Ø 8-10 / 400 8,500.00 10,625.00
0.05 zak cm
Semen portland ( 50kg) 66,000.00 3,300.00
0.005 m³ Pasir beton 232,100.00 1160.5
0.009 m³ Batu Pecah 2 /3 262,000.00 2,358.00
0.072 m³ Kayu Meranti Usuk 4/6, 5/7 4,500,000.00 324,000.00
1.2 Lembar Cat Meni Besi 59,000.00 70,800.00
0.45 kg Cat Meni Besi 60,000.00 27,000.00
Upah
0.02 OH Mandor 295,204.42 5,904.09
0.02 OH Kepala Tukang 110,000.00 2,200.00
0.2 OH Tukang 105,000.00 21,000.00
0.4 OH Pekerja 168,688.24 67,475.30
SUB JUMLAH 96,579.38 439,243.50 535,822.88
1.3 PEMBUATAN GUDANG
Bahan
0.7 Zak Semen PC 50 Kg 66,000.00 46,200.00
0.08 m^2 Kaca Polos 5 mm 100,000.00 8,000.00
0.15 m^3 Pasir Pasang/Plester 168,400.00 25,260.00
0.1 m^3 Pasir Cor/Beton 232,000.00 23,200.00
0.15 m^3 Batu Pecah Mesin 2/3 cm 262,000.00 39,300.00
30 buah Batu Bata Merah Kelas 1 (Uk. 950 28,500.00
22x11x4.5 cm)
0.25 lembar Seng Gelombang BJLS 30, Uk. 59000 14,750.00
(0,8 x 1,50)
1.1 kg Plat Besi/Baja 25000 27,500.00
0.15 buah Kunci Tanam 70000 10,500.00
30 Doz Paku Biasa 2 - 5 inchi 27000 810,000.00
0.25 lembar Triplek Uk.110 x 210 x 4 mm 67700 16,925.00
1.1 m^3 Kayu Meranti Usuk 4/6, 5/7 4500000 4,950,000.00
0.15 batang Dolken kayu gelam dia 8-10 cm, 8500 1,275.00
panjang 4m
Upah
0.05 OH Mandor 295,204.42 14,760.22

0.3 OH Kepala Tukang Kayu 110,000.00 33,000.00


1 OH Tukang Kayu 105,000.00 105,000.00
2 OH Tukang 105,000.00 210,000.00
2 OH Pekerja 168,688.24 337,376.48
SUB JUMLAH 700,136.70 6,001,410.00 6,701,546.70
1.4 PENGUKURAN DAN PEMASANGAN BOWPLANK
Bahan
0.012 m³ Kayu Meranti Usuk 4/6, 5/7 4,500,000.00 54,000.00
0.008 m³ Kayu Meranti Bekisting 3,200,000.00 25,600.00
0.05 Doz Paku biasa 2-5 inchi 27,000.00 1,350.00
Upah
0.0045 OH Mandor 295,204.42 1,328.42
0.01 OH Kepala tukang kayu 110,000.00 1,100.00
0.1 OH Tukang kayu 105,000.00 10,500.00
0.1 OH Pekerja 168,688.24 16,868.82
SUB JUMLAH 29,797.24 80,950.00 110,747.24
2 Pekerjaan Tanah dan Pondasi
2.1 Pekerjaan Galian Tanah
2.1 1 M³ GALIAN TANAH BIASA SEDALAM 1 M
Upah
0.025 OH Mandor 295,204.42 7,380.11
0.75 OH Pekerja 168,688.24 126,516.18
SUB JUMLAH 133,896.29 133,896.29
2.1 1 M³ GALIAN TANAH BIASA SEDALAM 2 M
.2
Upah
0.045 OH Mandor 295,204.42 13,284.20
0.900 OH Pekerja 168,688.24 151,819.42
SUB JUMLAH 165,103.61 165,103.61
2.2 Urugan Tanah
2.2 1 M³ URUGAN KEMBALI GALIAN TANAH
.1 Upah
0.019 OH Mandor 295,204.42 5,608.88
0.102 OH Pekerja 168,688.24 17,206.20
SUB JUMLAH 22,815.08 22,815.08
2.2 1 M³ URUGAN TANAH PENINGGIAN ELEVASI
.2 Bahan
1.2 m^1 Tanah urug 57,200.00 68,640.00
Upah
0.05 OH Mandor 295,204.42 14,760.22
0.25 OH Pekerja 168,688.24 42,172.06
SUB JUMLAH 56,932.28 68,640.00 125,572.28
2.3 1 M³ URUGAN PASIR URUG
Bahan
1.2 m³ Pasir Urug 143,500.00 172,200.00
Upah
0.01 OH Mandor 295,204.42 2,952.04
0.300 OH Pekerja 168,688.24 50606.472
SUB JUMLAH 53,558.52 172,200.00 225,758.52
2.4 Pasangan Batu Belah
2.4 1 M³ PASANGAN BATU KOSONG (AANSTAMPING -t = 30 cm)
.1 Bahan
1.200 kg Batu belah 15/20 319,100.00 382,920.00
0.432 m³ Pasair urug 224,400.00 96,940.80
Upah
0.039 OH Mandor 295,204.42 11,512.97
0.039 OH Kepala tukang batu 253,032.36 9,868.26
0.390 OH Tukang Batu 210,860.30 82,235.52
0.780 OH Pekerja 168,688.24 131,576.83
SUB JUMLAH 235,193.58 479,860.80 715,054.38
2.4 1 M³ PEKERJAAN PASANGAN PONDASI BATU KALI 1 PC : 4 PS
.2 Bahan
163.00 Kg Semen Portland 1,680.00 273,840.00
0
1.200 m³ Batu belah 319,000.00 382,800.00
0.520 m³ Pasir pasang 350,500.00 182,260.00
Upah
1.500 OH Pekerja 168,688.24 253,032.36
0.750 OH Tukang Batu 210,860.30 158,145.23
0.075 OH Kepala Tukang Batu 253,032.36 18,977.43
0.075 OH Mandor 259,204.42 19,440.33
SUB JUMLAH 449,595.34 838,900.00 1,288,495.34
3 Pekerjaan Beton
3.1 Pekerjaan Beton Non Struktur
3.1 1 M³ PEKERJAAN LANTAI KERJA BETON MUTU F'C 7,4 Mpa
.1 Bahan
227 kg Semen Portland 1,680.00 381,360.00
0.618 m³ Pasir Beton 301,900.00 186,574.20
0.744 m³ Krikil 303,300.00 225,655.20
215 ltr Air 207.49 44,610.35
Upah
0.132 OH Mandor 295,204.42 38,966.98
0.022 OH Kepala tukang batu 253,032.36 5,566.71
0.220 OH Tukang Batu 210,860.30 46,389.27
1.320 OH Pekerja 168,688.24 222,668.48
Sub Jumlah 313,591.44 838,199.75 1,151,791.19
3.1 PEMASANGAN 1 M2 BEKISTING UNTUK
.2 PONDASI
Bahan
0.040 m³ Kayu kelas III 10,439,400.00 417,576.00
0.300 kg Paku Biasa 18,100.00 5,430.00
0.100 ltr Minyak bekisting 36,200.00 3,620.00
Upah
0.0260 OH Mandor 295,204.42 7,675.31
0.0260 OH Kepala tukang kayu 253,032.36 6,578.84
0.2600 OH Tukang kayu 210,860.30 54,823.68
0.5200 OH Pekerja 168,688.24 87,717.88
SUB JUMLAH 156,795.72 426,626.00 583,421.72
3.2 Pekerjaan Beton Struktur
3.2 PEMBUATAN 1 M³ PONDASI BETON BETULANG
.1 Bahan
0.003 m³ Kayu kelas III 10,439,400.00 31,318.20
0.020 kg Paku Biasa 18,100.00 362.00
0.000 ltr Minyak Bekisting 36,200.00 0.00
3.600 kg Besi beton polos 89,000.00 320,400.00
0.050 kg Kawat ikat beton 25,900.00 1,295.00
5.500 kg Semen Portland 1,680.00 9,240.00
0.009 m³ Pasir beton 301,900.00 2,717.10
0.015 m³ Batu pecah 2/ 3 303,300.00 4,549.50
Upah
0.015 OH Mandor 295,204.42 4,428.07
0.01 OH Kepala tukang 253,032.36 2,530.32
0.0330 OH Tukang besi 210,860.30 6,958.39
0.0330 OH Tukang kayu 210,860.30 6,958.39
0.0330 OH Tukang batu 210,860.30 6,958.39
0.2970 OH Pekerja 168,688.24 50,100.41
SUB JUMLAH 77,933.97 369,881.80 447,815.77
3.2 PEMASANGAN 1 M2 BEKISTING UNTUK SLOOF
.2 Bahan
0.045 m³ Kayu kelas III 10,439,400.00 469,773.00
0.300 kg Paku Biasa 18,100.00 5,430.00
0.100 ltr Minyak Bekisting 36,200.00 3,620.00
Upah
0.0260 OH Mandor 295,204.42 7,675.31
0.0260 OH Kepala tukang kayu 253,032.36 6,578.84
0.2600 OH Tukang kayu 210,860.30 54,823.68
0.5200 OH Pekerja 168,688.24 87,717.88
SUB JUMLAH 156,795.72 478,823.00 635,618.72
3.2 PEMBUATAN 1 M³ SLOOF BETON BETULANG
.3 Bahan
0.270 m³ Kayu kelas III 10,439,400.00 2,818,638.00
2.000 kg Paku Biasa 18,100.00 36,200.00
0.600 ltr Minyak Bekisting 36,200.00 21,720.00
210.00 kg Besi beton polos 12,200.00 2,562,000.00
3.000 kg Kawat ikat beton 25,900.00 77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/ 3 248,200.00 201,042.00
Upah
0.283 OH Mandor 295,204.42 83,542.85
0.323 OH Kepala tukang 253,032.36 81,729.45
1.400 OH Tukang besi 210,860.30 295,204.42
1.560 OH Tukang kayu 210,860.30 328,942.07
0.275 OH Tukang batu 210,860.30 57,986.58
5.650 OH Pekerja 168,688.24 953,088.56
SUB JUMLAH 1,800,493.93 6,444,806.00 8,245,299.93
3.2 PEMASANGAN 1 M2 BEKISTING UNTUK
4 KOLOM
Bahan
0.040 m³ Kayu kelas III 10,439,400.00 417,576.00
0.400 kg Paku Biasa 18,100.00 7,240.00
0.200 ltr Minyak Bekisting 36,200.00 7,240.00
0.015 m³ Balok Kayu Kelas II 10,746,400.00 161,196.00
0.350 lbr Plywood tebal 9 mm 326,100.00 114,135.00
2.000 btg Kaso 5/7 x 400 41,400.00 82,800.00
Upah
0.0330 OH Mandor 295,204.42 9,741.75
0.0330 OH Kepala tukang kayu 253,032.36 8,350.07
0.3300 OH Tukang kayu 210,860.30 69,583.90
0.6600 OH Pekerja 168,688.24 111,334.24
SUB JUMLAH 199,009.95 790,187.00 989,196.95
3.2 PEMBUATAN 1 M³ KOLOM BETON BETULANG
.5 Bahan
0.400 m³ Kayu kelas III 10,439,400.00 4,175,760.00
4.000 kg Paku Biasa 18,100.00 72,400.00
2.000 ltr Minyak Bekisting 36,200.00 72,400.00
315.00 kg Besi beton polos 89,000.00 28035000
0
4.500 kg Kawat ikat beton 25,900.00 116,550.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.150 m³ Kelas II balok 10,746.40 1,611.96
3.500 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 361,900.00
20.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 828,000.00
Upah
0.350 OH Mandor 295,204.42 103,321.55
0.403 OH Kepala tukang 253,032.00 101,971.90
2.100 OH Tukang besi 210,860.00 442,806.00
1.650 OH Tukang kayu 210,860.00 347,919.00
0.275 OH Tukang batu 210,860.00 57,986.50
7.050 OH Pekerja 168,688.00 1,189,250.40
SUB JUMLAH 2,243,255.34 34,636,800.9 36,880,056.30
3.2 PEMASANGAN 1 M2 BEKISTING UNTUK KOLOM PRAKTIS 6
.6 Bahan
0.040 m³ Kayu kelas III 10,439,400.00 417,576.00
0.400 kg Paku Biasa 18,100.00 7,240.00
0.200 ltr Minyak Bekisting 36,200.00 7,240.00
0.015 m³ Balok Kayu Borneo 6,693,900.00 100,408.50
0.350 lbr Triplek (120 x 240 x 9) mm 326,100.00 114,135.00
2.000 m³ Kaso 5/7 x 400 41,400.00 82,800.00
Upah
0.0330 OH Mandor 6,693,900.00 220,898.70
0.0330 OH Kepala tukang kayu 253,032.36 8,350.07
0.3300 OH Tukang kayu 210,860.30 69,583.90
0.6600 OH Pekerja 168,688.24 111,334.24
SUB JUMLAH 410,166.91 729,399.50 1,139,566.41
3.2 PEMBUATAN 1 M' KOLOM PRAKTIS BETON BETULANG
.7 Bahan
0.002 m³ Kayu kelas III 10,439,400.00 20,878.80
0010 kg Paku Biasa 18,100.00 181,000.00
3.000 kg Besi beton polos 89,000.00 267,000.00
0.450 kg Kawat ikat beton 25,900.00 11,655.00
4.000 kg Semen Portland 1,680.00 6,720.00
0.060 m³ Pasir beton 301,900.00 18,114.00
0.009 m³ Batu pecah 2/3 303,300.00 2,729.70
0 ltr Minyak Bekisting 36200 0.00
Upah
0.0090 OH Mandor 295,204.42 2,656.84
0.0060 OH Kepala tukang 253,032.36 1,518.19
0.0200 OH Tukang besi 210,860.30 4,217.21
0.0200 OH Tukang kayu 210,860.30 4,217.21
0.0200 OH Tukang batu 210,860.30 4,217.21
0.1800 OH Pekerja 168,688.24 30,363.88
SUB JUMLAH 16,826.65 508,097.50 524,924.15
3.2 PEMASANGAN 1 M2 BEKISTING UNTUK BALOK
.8 Bahan
0.040 m³ Kayu kelas III 10,439,400.00 417,576.00
0.400 kg Paku Biasa 18,100.00 7,240.00
0.200 ltr Minyak Bekisting 36,200.00 7,240.00
0.018 m³ Kayu kelas II (kayu kalimantan) 10,746,400.00 193,435.20
0.350 lbr balok
Triplek tebal 9 mm (120x240) 326,100.00 114,135.00
2.000 btg Dolken kayu Ø 8 - 10 /400 cm 41,400.00 82,800.00
Upah
0.0330 OH Mandor 41,400.00 1,366.20
0.0330 OH Kepala tukang kayu 253,032.36 8,350.07
0.3300 OH Tukang kayu 210,860.30 69,583.90
0.6600 OH Pekerja 168,688.24 111,334.24
SUB JUMLAH 190,634.41 822,426.20 1,013,060.61
3.2 PEMBUATAN 1 M³ BALOK BETON BETULANG
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ BALOK INDUL lt 1 BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 077,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ BALOK INDUK lt 2 BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ BALOK LATEI BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 077,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ BALOK GANTUNG BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ BALOK PORTAL BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ BALOK INDUK lt 2 BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ RING BALOK BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ TANGGA BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 077,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
3.2 PEMBUATAN 1 M³ PLAT LANTAI BETON BETULANG 0
.9 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
210.00 kg Besi beton polos 89,000.00 18,690,000.0
0
3.000 kg Kawat ikat beton 25,900.00 0
77,700.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 303,300.00 245,673.00
0.140 m³ Kelas II balok 10,746,400.00 1,504,496.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 103,400.00 289,520.00
16.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41,400.00 662,400.00
Upah
0.318 OH Mandor 295,204.42 93,875.01
0.333 OH Kepala tukang 253,032.36 84,259.78
1.400 OH Tukang besi 210,860.30 295,204.42
1.650 OH Tukang kayu 210,860.30 347,919.50
0.275 OH Tukang batu 210,860.30 57,986.58
6.350 OH Pekerja 168,688.24 1,071,170.32
SUB JUMLAH 1,950,415.60 25,653,743.0 27,604,158.60
4 PEKERJAAN PASANGAN 0
4.1 1 m2 Pasangan Bata Merah (5x11x22) cm campuran 1Pc : 2Ps, Tebal 1
Bata
Bahan
140.00 buah Bata Merah 5 x 11 x 22 1,300.00 182,000.00
0
43.5 Kg Semen portland 1,680.00 73,080.00
0.08 m³ Pasir pasang 350,500.00 28,040.00
Upah
0.030 OH Mandor 295,204.42 8,856.13
0.020 OH Kepala tukang batu 253,032.36 5,060.65
0.200 OH Tukang batu 210,860.30 42,172.06
0.600 OH Pekerja 168,688.24 101,212.94
SUB JUMLAH 157,301.78 283,120.00 440,421.78
4.2 m2 Pasangan Bata Merah 1Pc : 6Ps , Tebal 1 Bata
Bahan 440,421.78
140.00 buah Bata merah 1,300.00 182,000.00
0
18.500 kg Semen portland 1,680.00 31,080.00
0.122 m³ Pasir pasang 350,500.00 42,761.00
Upah
0.030 OH Mandor 295,204.42 8,856.13
0.020 OH Kepala tukang batu 253,032.36 5,060.65
0.200 OH Tukang batu 210,860.30 42,172.06
0.600 OH Pekerja 168,688.24 101,212.94
SUB JUMLAH 157,301.78 255,841.00 413,142.78
4.3 1 m2 Pasangan Bata Merah 1Pc : 4Ps , Tebal 1 Bata
Bahan 413,142.78
140.00 buah Bata merah 1,300.00 182,000.00
0
26.550 kg Semen portland 1,680.00 44,604.00
0.093 m³ Pasir pasang 350,500.00 32,596.50
Upah
0.030 OH Mandor 295,204.42 8,856.13
0.020 OH Kepala tukang batu 253,032.36 5,060.65
0.200 OH Tukang batu 210,860.30 42,172.06
0.600 OH Pekerja 168,688.24 101,212.94
SUB JUMLAH 157,301.78 259,200.50 416,502.28
4.4 PEKERJAAN FINISHING DINDING
4.4 m2 Plesteran Dinding 1Pc : 6Ps ; Tebal 15 mm
.1 Bahan
4.416 kg Semen portland 1,680.00 7,418.88
0.027 m³ Pasir pasang 350,500.00 9,463.50
Upah
0.015 OH Mandor 295,204.42 4,428.07
0.015 OH Kepala tukang batu 253,032.36 3,795.49
0.150 OH Tukang batu 210,860.30 31,629.05
0.300 OH Pekerja 168,688.24 50,606.47
SUB JUMLAH 90,459.07 16,882.38 107,341.45
4.4 1 m2 Plesteran Dinding 1Pc : 6Ps ; Tebal 15 mm
.2 Bahan
4.416 kg Semen Portland 1,680.00 7,418.88
0.027 m³ Pasir Pasang 350,500.00 9,463.50
Upah
0.015 OH Mandor 295,204.42 4,428.07
0.015 OH Kepala tukang batu 253,032.36 3,795.49
0.150 OH Tukang batu 210,860.30 31,629.05
0.300 OH Pekerja 168,688.24 50,606.47
SUB JUMLAH 90,459.07 16,882.38 107,341.45
4.4 1 m2 Pasangan Acian (abu - abu)
.3 Bahan
3.250 kg Semen portland 1,200.00 3,900.00
Upah
0.010 OH Mandor 295,204.42 2,952.04
0.010 OH Kepala tukang batu 253,032.36 2,530.32
0.100 OH Tukang batu 210,860.30 21,086.03
0.200 OH Pekerja 168,688.24 33,737.65
SUB JUMLAH 60,306.05 3,900.00 64,206.05
4.4 1 m² Pasang Dinding Keramik 20 x 20 cm
.4 Bahan
9.30 kg Semen Portland 1,680.00 15,624.00
0.018 m³ Pasir Pasang 350,500.00 6,309.00
26.50 buah Keramik artistik 4,994.00
1.94 kg Semen warna 14500
Upah
0.015 OH Mandor 295,204.42 4,428.07
0.015 OH Kepala tukang batu 253,032.36 3,795.49
0.150 OH Tukang batu 210,860.30 31,629.05
0.300 OH Pekerja 168,688.24 50,606.47
SUB JUMLAH 90,459.07 21,933.00 112,392.07
4.4 1 m^2 Benangan/Tali Air/Sudut Kol Kolan
.5 Bahan
3.7500 kg Semen Portland 1,680.00 6,300.00
0.0300 m³ Pasir Pasang 350,500.00 10,515.00
Upah
0.2 OH Mandor 295,204.42 59,040.88
1.2 OH Kepala tukang batu 253,032.36 303,638.83
12.000 OH Tukang batu 210,860.30 2,530,323.60
4.000 OH Pekerja 168,688.24 674,752.96
SUB JUMLAH 3,567,756.28 16,815.00 3,584,571.28
5 Pekerjaan atap
5.1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
Bahan
1.100 m³ Balok kayu 10,648,200.00 11,713,020.0
15.00 kg Besi strip tebal 5 mm 29,000.00 0
435,000.00
5.600 kg Paku 12 cm 18,100.00 101,360.00
Upah
4.00 OH Pekerja 168,688.24 674,752.96
12.00 OH Tukang 210,860.30 2,530,323.60
1.200 OH Kepala Tukang 253,032.36 303,638.83
0.200 OH Mandor 295,204.42 59,040.88
SUB JUMLAH 3,567,756.28 12,249,380.0 15,817,136.28
5.2 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II 0
Bahan
1.100 m³ Balok kayu kamper 5,644,600.00 6209060
15.000 kg Besi strip tebal 5 mm 29,000.00 435000
3.000 kg Paku 12 cm 18,100.00 54300
Upah
6.700 OH Pekerja 168,688.24 1130211.208
20.100 OH Tukang kayu 210,860.30 4238292.03
2.010 OH Kepala tukang kayu 253,032.36 508595.0436
0.335 OH Mandor 295,204.42 98893.4807
SUB JUMLAH 5975991.762 6698360 12,674,352
5.3 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II
Bahan
0.014 m³ Kaso-kaso 5x7cm 4624200 64738.8
0.036 m³ Reng 2x3cm 4311000 155196
0.250 kg Paku 5 dan 10 cm 18100 4525
Upah
0.100 OH Pekerja 168688.24 16868.824
0.100 OH Tukang kayu 210860.3 21086.03
0.010 OH Kepala tukang kayu 253032.36 2530.3236
0.005 OH Mandor 295204.42 1476.0221
SUB JUMLAH 41961.1997 224459.8 266420.9997
6 Pekerjaan penutup atap
6.1 Pemasangan 1 m2 atap genteng kodok glazuur
Bahan
25.00 buah Genteng kodok 4,400.00 110000
Upah
0.15 OH Pekerja 168,688.24 25303.236
0.075 OH Tukang kayu 15814.5225
0.008 OH Kepala tukang kayu 2024.25888
0.008 OH Mandor 2361.63536
SUB JUMLAH 45503.65274 110000 155503.6527
6.2 Pemasangan 1 m’ bubung genteng kodok glazuur
Bahan
5.00 buah Genteng bubung 7,600.00 38,000.00
8.00 kg Semen Portland 1,680.00 13,440.00
0.032 m³ Pasir pasang 350,500.00 11,216.00
Upah
0.40 OH Pekerja 168688.24 67475.296
0.20 OH Tukang kayu 210,860.30 42172.06
0.02 OH Kepala tukang kayu 253,032.36 5060.6472
0.002 OH Mandor 295,204.42 590.40884
SUB JUMLAH 115298.412 62,656.00 177954.412
7 Pekerjaan Lisplank dan Plafond
7.1 Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Bahan
0.0108 m³ Papan kayu 10,234,700.00 110,534.76
0.1 kg Paku 5 dan 7 cm 18,100.00 1,810.00
Upah
0.1 OH Pekerja 168688.24 16868.824
0.2 OH Tukang kayu 210,860.30 42,172.06
0.02 OH Kepala tukang kayu 253,032.36 5,060.65
0.005 OH Mandor 295,204.42 1,476.02
SUB JUMLAH 65,577.55 112,344.76 177,922.31
7.2 Pemasangan 1 m’ lisplank beton bertulang
Bahan
0.01 m³ Kayu bekisting 3,777,400.00 37,774.00
0.1376 kg Paku biasa 18,100.00 2,490.56
0.16 ltr Minya bekisting 36,200.00 5,792.00
27.54 kg Besi beton/tulangan beton 12,200.00 335,988.00
0.2 kg Kawat beton 25900 5,180.00
14.45 kg Semen Portland 1,680.00 24,276.00
0.0232 m³ Pasir pasang 350,500.00 8,131.60
3 bh Bambu 15600 46,800.00
Upah
0.003 OH Mandor 295,204.42 885.61
0.003 OH Kepala tukang 253,032.00 3,542.45
0.014 OH Tukang besi 210,860.30 2,952.04
0.017 OH Tukang kayu 210,860.30 3,584.63
0.027 OH Tukang batu 210,860.30 5,693.23
0.191 OH Pekerja 168,688.24 32,219.45
SUB JUMLAH 48,877.41 466,432.16 515,309.57
7.3 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon
Bahan
4 m1 Rangkai metal hollow 32,050.00 128,200.00
1 Ls Aksesoris (perkuatan, las, dll) 128,200.00 128,200.00
Upah
0.35 OH Pekerja 168,688.24 59,040.88
0.35 OH Tukang besi/baja 210,860.30 73,801.11
0.035 OH Kepala tukang besi 253,032.00 8,856.12
0.018 OH Mandor 295,204.42 5,313.68
SUB JUMLAH 147,011.79 256,400.00 403,411.79
7.4 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal9 mm
Bahan
0.364 lembar Gypsum board 82,600.00 30,066.40
0.11 kg Paku skrup 5,790.00 636.90
Upah
0.1 OH Pekerja 168,688.24 16,868.82
0.05 OH Tukang kayu 210,860.30 10,543.02
0.005 OH Kepala tukang kayu 253,032.00 1,265.16
0.005 OH Mandor 295,204.42 1,476.02
SUB JUMLAH 30,153.02 30,703.30 60,856.32
8 Pekerjaan pintu dan jendela
8.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Bahan
1.1 m^3 Balok kayu 10,648,200.00 11,713,020.0
1.25 kg Paku 10 cm 18,100.00 022,625.00
1 kg Lem kayu 41,400.00 41,400.00
Upah
7 OH Pekerja 168,688.24 1,180,817.68
21 OH Tukang kayu 210,860.30 4,428,066.30
2.1 OH Kepala tukang kayu 253,032.00 531,367.20
0.35 OH Mandor 295,204.42 103,321.55
SUB JUMLAH 6,243,572.73 11,777,045.0 18,020,617.73
8.2 Pekerjaan daun pintu dan jendela 0
8.2 Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
.1 Bahan
0.025 m^3 Papan kayu 10,967,600.00 274,190.00
0.03 kg Paku 1cm-2.5cm 22,800.00 684.00
0.5 kg Lem kayu 22,800.00 11,400.00
1 lembar Plywood tebal 4mm ukuran 239900 239,900.00
Upah
0.7 OH Pekerja 168,688.24 118,081.77
2.1 OH Tukang 210,860.30 442,806.63
0.21 OH Kepala tukang kayu 253,032.00 53,136.72
0.035 OH Mandor 295,204.42 10,332.15
SUB JUMLAH 624,357.27 526,174.00 1,150,531.27
8.2 Pemasangan daun jendela kayu kaca tebal 10mm
.2 Bahan
0.0025 m^3 Papan kayu 10,967,600.00 27,419.00
1.1 m^2 Kaca bening t=10 mm 278,700.00 306,570.00
0.07 kg Sealant 10400 728
Upah
0.025 OH Pekerja 168,688.24 4,217.21
0.25 OH Tukang kayu 210,860.30 52,715.08
0.025 OH Kepala tukang 253,032.00 6,325.80
0.0013 OH Mandor 295,204.42 383.77
SUB JUMLAH 63,641.85 334,717.00 398,358.85
8.3 Pekerjaan penggantung dan pengunci
8.3 Pemasangan grendel biasa
.1 Bahan
1 bh Grendel biasa 109,400.00 109,400.00
Upah
0.01 OH Pekerja 168,688.24 1,686.88
0.1 OH Tukang kayu 210,860.30 21,086.03
0.01 OH Kepala tukang 253,032.00 2,530.32
0.01 OH Mandor 295,204.42 2,952.04
SUB JUMLAH 28,255.28 109,400.00 137,655.28
8.3 Pemasangan 1 buah engsel
.2 Bahan
1 buah Engsel 36200 36200
Upah
0.015 OH Pekerja 168,688.24 2,530.32
0.15 OH Tukang kayu 210,860.30 31,629.05
0.015 OH Kepala tukang kayu 253,032.00 3,795.48
0.0008 OH Mandor 295,204.42 236.16
SUB JUMLAH 38,191.01 36200 74,391.01
8.3 Pemasangan 1 buah door holder
.3 Bahan
1 buah Door holder 413,600.00 413,600.00
Upah
0.05 OH Pekerja 168,688.24 8,434.41
0.5 OH Tukang kayu 210,860.30 105,430.15
0.05 OH Kepala tukang kayu 253,032.00 12,651.60
0.003 OH Mandor 295,204.42 885.61
SUB JUMLAH 127,401.78 413,600.00 541,001.78
8.3 Pemasangan 1 buah kunci tanam biasa
.4
Bahan
1 buah Kunci tanam biasa 51,700.00 51,700.00
Upah
0.01 OH Pekerja 168,688.24 1,686.88
0.5 OH Tukang kayu 210,860.30 105,430.15
0.05 OH Kepala tukang kayu 253,032.00 12,651.60
0.005 OH Mandor 295,204.42 1,476.02
SUB JUMLAH 121,244.65 51,700.00 172,944.65
8.3 Pemasangan hak angin
.5 Bahan
1 buah Hak angin 41,400.00 41,400.00
Upah
0.1 OH Pekerja 168,688.24 16,868.82
0.5 OH Tukang kayu 210,860.30 105,430.15
0.2 OH Kepala tukang kayu 253,032.00 50,606.40
0.005 OH Mandor 295,204.42 1,476.02
SUB JUMLAH 174,381.40 41,400.00 215,781.40
9 Pekerjaan tegel
9.1 lantai
Pemasangan 1m² lantai keramik ukuran 30cm x 30cm
Bahan
1.05 Doos Ubin keramik 60,000.00 63000
14.15 kg Semen portland 1,680.00 23772
0.039 m^3 Pasir pasang 350,500.00 13669.5
2.00 kg Semen warna 14,500.00 29000
Upah
0.7 OH Pekerja 168,688.24 118,081.77
0.35 OH Tukang batu 210,860.30 73,801.11
0.035 OH Kepala tukang batu 253,032.00 8,856.12
0.035 OH Mandor 295,204.42 10,332.15
SUB JUMLAH 211,071.15 129441.5 340,512.65
9.2 Pemasangan 1m² lantai keramik ukuran 20cm x 20cm
Bahan
1.05 Doos Ubin keramik 60,000.00 63000
10.40 kg Semen portland 1,680.00 17472
0.045 m^3 Pasir pasang 350,500.00 15772.5
0.50 kg Semen warna 14,500.00 7250
Upah
0.7 OH Pekerja 168,688.24 118,081.77
0.35 OH Tukang batu 210,860.30 73,801.11
0.035 OH Kepala tukang batu 253,032.00 8,856.12
0.035 OH Mandor 295,204.42 10,332.15
SUB JUMLAH 211,071.15 103494.5 314,565.65
9.3 Pemasangan 1m' Plint lantai keramik ukuran 5cm x
20cm
Bahan
5.30 bh Plint keramik 60,000.00 318000
0.57 kg Semen portland 1,680.00 957.6
0.0015 m^3 Pasir pasang 350,500.00 525.75
0.013 kg Semen warna 14,500.00 188.5
Upah
0.09 OH Pekerja 168,688.24 15,181.94
9 OH Tukang batu 210,860.30 1,897,742.70
0.035 OH Kepala tukang batu 253,032.00 8,856.12
0.005 OH Mandor 295,204.42 1,476.02
SUB JUMLAH 1,923,256.78 319671.85 2,242,928.63
9.4 Pemasangan 1m² lantai keramik ukuran 10cm x 33cm untuk stepnosing/border
Bahan
33.00 bh Ubin keramik 60,000.00 1980000
9.80 kg Semen portland 1,680.00 16464
0.045 m^3 Pasir pasang 350,500.00 15772.5
4.37 kg Semen warna 14,500.00 63365
Upah
1.05 OH Pekerja 168,688.24 177,122.65
0.525 OH Tukang batu 210,860.30 110,701.66
0.053 OH Kepala tukang batu 253,032.00 13,410.70
0.053 OH Mandor 295,204.42 15,645.83
SUB JUMLAH 316,880.84 2075601.5 2,392,482.34
10 PEMASANGANN 1 BUAH CLOSET DUDUK
10. Pekerjaan Instalasi Air
1 Bahan
1.000 unit Closet duduk putih porselin 2,119,300.00 2,119,300.00
komplit
0.060 unit Perlengkapan 2,119,300.00 127,158.00
Upah
0.160 OH Mandor 295,204.42 47,232.71
0.010 OH Kepala tukang 253,032.00 2,530.32
1.100 OH Tukang batu 210,860.30 231,946.33
3.300 OH Pekerja 168,688.24 556,671.19
SUB JUMLAH 838,380.55 2,246,458.00 3,084,838.55
10. PEMASANGAN 1 BUAH KRAN 1/2" ATAU 3/4"
2 Bahan
1.000 buah Kran air 155,100.00 155,100.00
0.025 buah Seal tape 5,200.00 130.00
Upah
0.005 OH Mandor 295,204.42 1,476.02
0.040 OH Kepala tukang 253,032.00 10,121.28
0.400 OH Tukang batu 210,860.30 84,344.12
0.010 OH Pekerja 168,688.24 1,686.88
SUB JUMLAH 97,628.30 155,230.00 252,858.30
10. PEMASANGANN 1 M' PIPA PVC TIPE AW DIAMETER 3/4"
3 Bahan
1.200 m Pipa PVC 3/4" type AW 8,550.00 10,260.00
35.000 % Perlengkapan 3,591.00
Upah
0.002 OH Mandor 295,204.42 590.41
0.006 OH Kepala tukang 253,032.00 1,518.19
0.060 OH Tukang batu 210,860.30 12,651.62
0.036 OH Pekerja 168,688.24 6,072.78
SUB JUMLAH 20,833.00 13,851.00 34,684.00
10. PEMASANGANN 1 M' PIPA PVC TIPE AW DIAMETER 3"
4 Bahan
1.200 m Pipa PVC 3" type AW 51,700.00 62,040.00
35.000 % Perlengkapan 21,714.00
Upah
0.004 OH Mandor 295,204.42 1,180.82
0.0135 OH Kepala tukang 253,032.00 3,415.93
0.135 OH Tukang batu 210,860.30 28,466.14
0.081 OH Pekerja 168,688.24 13,663.75
SUB JUMLAH 46,726.64 83,754.00 130,480.64
11 Pekerjaan
11. Finishing
PENGECATAN 1 M2 TEMBOK EXTERIOR BARU
1 Bahan
0.100 kg Plamur tembok 13,500.00 1,350.00
0.100 kg Cat dasar exterior 29,800.00 2,980.00
0.260 kg Cat penutup exterior 58,900.00 15,314.00
Upah
0.003 OH Mandor 295,204.42 885.61
0.0063 OH Kepala tukang 253,032.00 1,594.10
0.063 OH Tukang cat 210,860.30 13,284.20
0.020 OH Pekerja 168,688.24 3,373.76
SUB JUMLAH 19,137.68 19,644.00 38,781.68
11. PENGECATAN 1 M2 TEMBOK INTERIOR BARU
2 Bahan
0.100 kg Plamur tembok 13,500.00 1,350.00
0.100 kg Cat dasar interior 11,500.00 1,150.00
0.260 kg Cat penutup interior 31,500.00 8,190.00
Upah
0.003 OH Mandor 295,204.42 885.61
0.0063 OH Kepala tukang 253,032.00 1,594.10
0.063 OH Tukang cat 210,860.30 13,284.20
0.020 OH Pekerja 168,688.24 3,373.76
SUB JUMLAH 19,137.68 10,690.00 29,827.68
11. PENGECATAN 1 M2 BIDANG KAYU BARU
3 Bahan
0.200 kg Cat meni kayu 70,300.00 14,060.00
0.150 kg Plamur kayu 13,500.00 2,025.00
0.170 kg Cat dasar 29,800.00 5,066.00
0.350 kg Cat penutup 77,600.00 27,160.00
0.010 buah Kuas 18,100.00 181.00
0.030 kg Thinner B / Minyak cat 62,100.00 1,863.00
0.200 lbr kertas gosok / Amplas 5,200.00 1,040.00
Upah
0.003 OH Mandor 295,204.42 885.61
0.004 OH Kepala tukang 253,032.00 1,012.13
0.105 OH Tukang cat 210,860.30 22,140.33
0.070 OH Pekerja 168,688.24 11,808.18
SUB JUMLAH 35,846.25 51,395.00 87,241.25
12 Pekerjaan Lain-Lain
12. PEKERJAAN SEPTICTANK
1
12. 1 M³ GALIAN TANAH BIASA SEDALAM 2 M
1.1 Upah
0.045 OH Mandor 295,204.42 13,284.20
0.900 OH Pekerja 168,688.24 151,819.42
SUB JUMLAH 165,103.61 165,103.61
12. 1 M³ URUGAN PASIR URUG
1.2 Bahan
1.200 m³ Pasir Urug 321,550.00 385,860.00
Upah
0.010 OH Mandor 295,204.42 2,952.04
0.300 OH Pekerja 168,688.24 50,606.47
SUB JUMLAH 53,558.52 385,860.00 439,418.52
12. MEMBUAT PLAT PENUTUP SEPTICTANK BETON BERTULANG (100 KG BESI + BEKISTING)
1.3 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
12.84 kg Besi beton polos 12,200.00 156,648.00
2.250 kg Kawat ikat beton 25,900.00 58,275.00
336.00 kg Semen portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 248,200.00 201,042.00
0.120 m³ Kayu kelas II balok 10,746,400.00 1,289,568.00
2.800 lbr Triplek tebal 9 mm (120x240) 10,746,400.00 30,089,920.0
32.800 btg Dolken kayu Ø 8 - 10 /400 cm 41400 0
1,357,920.00
Upah
0.265 OH Mandor 295,204.42 78,229.17
0.265 OH Kepala tukang 253,032.00 67,053.48
1.050 OH Kepala tukang 253,032.00 265,683.60
1.300 OH Kepala tukang 253,032.00 328,941.60
0.275 OH Kepala tukang 253,032.00 69,583.80
5,300 OH Pekerja 168,688.24 894,047,672.
SUB JUMLAH 00
894,857,163. 37,337,327.0 932,194,490.6
12. PEMASANGAN DINDING BATA MERAH SEPTICTANK(5X11X22)CMTEBAL65 1BATU 0CAMPURAN 1PC:2PP
5
1.4 Bahan
140.00 buah Batu merah 1,300.00 182,000.00
43.500 kg Semen portland 1,680.00 73,080.00
0.080 m³ Pasir pasang 350,500.00 28,040.00
Upah
0.030 OH Mandor 295,204.42 8,856.13
0.0200 OH Kepala tukang 253,032.00 5,060.64
0.200 OH Tukang batu 210,860.30 42,172.06
0.600 OH Pekerja 168,688.24 101,212.94
SUB JUMLAH 157,301.78 283,120.00 440,421.78
12. PEKERJAAN SUMUR RESAPAN
2
12. 1 M³ GALIAN TANAH SUMUR RESAPAN SEDALAM 1 M
2.1 Upah
0.025 OH Mandor 295,204.42 7,380.11
0.750 OH Pekerja 168,688.24 126,516.18
SUB JUMLAH 133,896.29 133,896.29
13. 1 M³ URUGAN KEMBALI GALIAN TANAH SUMUR RESAPAN
2.2 Upah
0.050 OH Mandor 295,204.42 14,760.22
0.500 OH Pekerja 168,688.24 84,344.12
SUB JUMLAH 99,104.34 99,104.34
12. PEMBUATAN 1 M³ PLAT PENUTUP SUMUR RESAPAN BETON BETULANG (150KG BESI + BEKISTING)
2.3 Bahan
0.320 m³ Kayu kelas III 10,439,400.00 3,340,608.00
3.200 kg Paku Biasa 18,100.00 57,920.00
1.600 ltr Minyak Bekisting 36,200.00 57,920.00
157.50 kg Besi beton polos 12,200.00 1,921,500.00
0
2.250 kg Kawat ikat beton 25,900.00 58,275.00
336.00 kg Semen Portland 1,680.00 564,480.00
0
0.540 m³ Pasir beton 301,900.00 163,026.00
0.810 m³ Batu pecah 2/3 248,200.00 201,042.00
0.120 m³ Kelas II balok 10,746,400.00 1,289,568.00
2.800 lbr Triplek tebal 9 mm ( 120 x 2 40) 10,746,400.00 30,089,920.0
32.000 btg Dolken kayu Ø 8 - 1 0 / 400 c m 41400 01,324,800.00
Upah
0.265 OH Mandor 295,204.42 78,229.17
0.265 OH Kepala tukang 253,032.00 67,053.48
1.050 OH Tukang besi 210,860.30 221,403.32
1.300 OH Tukang kayu 210,860.30 274,118.39
0.275 OH Tukang batu 210,860.30 57,986.58
5.300 OH Pekerja 168,688.24 894,047.67
SUB JUMLAH 1,592,838.61 39,069,059.0 40,661,897.61
12. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN 60CMx60CM TINGGI 65CM 0
2.4 Bahan
123.00 buah Batu merah 900.00 110,700.00
114.00 kg Semen portland 1,680.00 191,520.00
0.184 m³ Pasir pasang 350,500.00 64,492.00
0.120 m³ Pasir beton 301,900.00 36,228.00
0.033 m³ Batu pecah 2/3 301,900.00 9,962.70
4.850 kg Besi beton polos 12,027.03 58,331.10
Upah
0.016 OH Mandor 295,204.42 4,723.27
0.011 OH Kepala tukang 253,032.00 2,783.35
1.500 OH Tukang batu 210,860.30 316,290.45
3.200 OH Pekerja 168,688.24 539,802.37
SUB JUMLAH 863,599.44 471,233.80 1,334,833.24
12. PEKERJAAN PIPA SALURAN
3
12. 1 M³ GALIAN TANAH PIPA SALURAN SEDALAM 1 M
3.1 Upah
0.025 OH Mandor 295,204.42 7,380.11
0.750 OH Pekerja 168,688.24 126,516.18
SUB JUMLAH 133,896.29 133,896.29
12. 1 M³ URUGAN KEMBALI GALIAN TANAH PIPA SALURAN
3.2 Upah
0.050 OH Mandor 295,204.42 14,760.22
0.500 OH Pekerja 168,688.24 84,344.12
SUB JUMLAH 99,104.34 99,104.34
13. PEMASANGAN 1M' RAILING TANGGA BESI HOLLOW
2.5 Bahan
0.800 btg Besi Hollow 21100 16,880.00
20.000 cm Pengelasaan 28.24 564.80
0.100 kg Cat many besi 70,300.00 7,030.00
Upah
0.006 OH Mandor 295,204.42 1,771.23
0.120 OH Kepala tukang 253,032.00 30,363.84
1.200 OH Tukang besi 210,860.30 253,032.36
1.200 OH Pekerja 168,688.24 202,425.89
SUB JUMLAH 487,593.31 24,474.80 512,068.11
Tabel 3. Rencana Anggaran Biaya (RAB)

N Uraian Pekerjaan Volume Harga Jumlah (Rp)


o. Satuan (Rp)
1 2 3 4 5
I Pekerjaan Persiapan
1 Pembersihan Lokasi 156. M2 24,248.93 3,801,020.48
Pekerjaan pagar keliling 50.9
75 535,822.88 27,273,384.82
gudang 24 6,701,546.70 160,837,120.82
2 Pengukuran dan Pemasangan Bowplank 46.9 M2 110,747.24 5,194,045.74
Air kerja 1 Ls 2,000,000.00 2,000,000.00
Listrik kerja 1 Ls 1,500,000.00 1,500,000.00
Sub Total I
II Pekerjaan Tanah dan Pondasi
2. Galian Tanah Pondasi
1 Galian Tanah Pondasi Batu Kali A dan B 59.8 M3 133,896.29 8,009,542.20
2 Galian Tanah Pondasi Footplat 64
19 M3 133,896.29 8,569,362.59
2. Urugan Tanah
1
2 Urugan Tanah Kembali Pondasi Footplat 66.9 M3 22,815.08 1,527,971.84
Urugan Tanah Kembali Pondasi Batukali 23.6
72 22,815.08 540,261.20
2 Urugan Tanah Peninggian Elevasi Lt. Rumah 17.1
8 M3 125,572.28 2,148,541.73
3 Urugan Tanah Peninggian Elevasi Lt. teras 0.96
1 M3 125,572.28 120,926.11
Urugan Tanah Peninggian Elevasi Lt. inner court 0.93
3 125,572.28 117,284.51
Urugan Tanah Peninggian Elevasi Lt. Mushola 2.07
4 125,572.28 261,064.77
Urugan Tanah Peninggian Elevasi Lt. Tempat 0.43
9 125,572.28 53,996.08
Urugan
wudhu Tanah Peninggian Elevasi Lt. WC/KM 0.72 125,572.28 90,412.04
2. Urugan Pasir
3 Urugan Pasir Bawah Footplat 3.2 225,758.52 722,427.25
1 Urugan Pasir Bawah Anstamping pondasi A & B 7.62 M3 225,758.52 1,720,279.89
Urugan Pasir Bawah Lantai 72.0 225,758.52 16,256,870.75
2. Pasangan Pondasi 1
1
4 Aanstamping pondasi Batu Kali A dan B 7.62 M3 715,054.38 5,448,714.37
Pasangan Pondasi Batu kali A & B 24.8 1,288,495.34 32,006,224.33
4 Sub Total II
III Pekerjaan Beton
3. Pekerjaan Beton Non Struktur
1 Lantai Kerja Footplat 16 M3 1,735,212.91 27,763,406.52
3. Pekerjaan Beton Bertulang
2 Pembuatan Footplat 12.8 #VALUE! #VALUE!
Kolom pendek 1.71
8 #VALUE! #VALUE!
1 Balok Sloof Pondasi Batu Kali A & B 4,45 M3 #VALUE! #VALUE!
2 Kolom induk lt 1 2,42 M3 #VALUE! #VALUE!
3 Kolom Praktik lt 1 1,57 M3 #VALUE! #VALUE!
4 Balok induk lt 1 2,49 M3 #VALUE! #VALUE!
5 Balok anak lt 1 0,73 M3 #VALUE! #VALUE!
6 Plat Tangga 1,54 M3 #VALUE! #VALUE!
7 Anak Tangga 0,37 M3 #VALUE! #VALUE!
8 Plat Lantai 2 5,9 M3 #VALUE! #VALUE!
Kolom induk lt 2 1,03 #VALUE! #VALUE!
Kolom Praktik lt 2 0,37 #VALUE! #VALUE!
9 Balok Ring 0,72 M3 #VALUE! #VALUE!
Sub Total III
IV Pekerjaan Pasangan
4. Trasram Rumah
1 Pasangan Trasram 1:2 3.05 M3 232,666.50 709,632.83
4. Pasangan Dinding
1
2 Pasangan Dinding Lantai 1 (1:6) 131. M3 440,421.78 57,928,677.22
2 Pasangan Dinding Lantai 2 (1:6) 164.
53 M3 440,421.78 72,568,297.32
3 Dinding Kamar Mandi Lantai 1 (1:4) 15.3
77 M3 413,142.78 6,360,333.16
4 Dinding Kamar Mandi Lantai 2 (1:4) 18.0
95 M3 413,142.78 7,473,752.96
4. Pekerjaan Plesteran dan Acian 9
4.
3 Plesteran Dinding Rumah (1pc : 6ps) 601. M3 107,341.45 64,525,091.64
4.
3. Plesteran Dinding Luar Kamar Mandi (1pc : 4ps) 33.4
12 M3 107,341.45 3,594,328.41
4.
3. Plesteran Dinding Dalam Kamar Mandi (1pc : 4ps) 14.9
85 M3 107,341.45 1600890.366
4.
3. Acian Dinding 644.
1 M3 #VALUE! #VALUE!
4.
3. Pasangan dinding Batu Palimanan 8,83
447 M2 140,000.00 1,236,900,000.0
3. Pasangan ornamen dinding 3,18
5 M3 140,000.00 #VALUE!
0
5 Tali Air Kusen 401, M 17,031.25 #VALUE!
6 Tali Ban Keramik 214
8 M 17,031.25 3,644,687.50
Sub Total IV
V Pekerjaan Atap
5. Pekerjaan Kuda-Kuda
1 Rangka Kuda-Kuda A 0,62 m3 22,331,198,0 #VALUE!
Rangka Kuda-Kuda B 0,23
2 m3 22,331,198,0
00.00 #VALUE!
5. Balok Rangkai A 0,79 m3 9,615,346,10
00.00 #VALUE!
2 Balok Rangkai B 0,35 m3 9,615,346,10
0.00 #VALUE!
1 Kerangka atap (usuk/reng) 120, m3 517,250.00
0.00 #VALUE!
36 Sub Total V
VI Pekerjaan Penutup Atap
1 Luas Atap 120, M 41,820.00 #VALUE!
3 Pekerjaan Wuwung Genteng 84
36 M 86,460.00 7,262,640.00
Sub Total VI
VII Pekerjaan Lisplank dan Plafond
7. Pasangan Lisplank 0,19 M3 195,350.00 #VALUE!
7.
1 Pekerjaan Plafond 2
1
2 Rangka Plafond Lantai 1 158, M 202,250.00 #VALUE!
2 Rangka Plafond Lantai 2 146,
7 M 202,250.00 #VALUE!
3 Plafond Lantai 1 74,4
63 Bh 42,600.00 #VALUE!
4 Plafond Lantai 2 66
6 Bh 42,600.00 2,811,600.00
Sub Total VII
VII Pekerjaan Pintu Utama dan Jendela
8.
I Pekerjaan Kusen Pintu dan Jendela
1 Kusen P0-1 0,05 M3 25,018,500.0 #VALUE!
2 Kusen P0-2 0,01 M3 25,018,500.0
0 #VALUE!
3 Kusen P0-3 0,08 M3 25,018,500.0
0 #VALUE!
4 Kusen W-01 0,02 M3 25,018,500.0
0 #VALUE!
5 Kusen W-02 0,02 M3 25,018,500.0
0 #VALUE!
6 Kusen W-03 0,00 M3 25,018,500.0
0 #VALUE!
7 Kusen W-04 0,01
4 M3 25,018,500.0
0 #VALUE!
8 Kusen F2 0,02 M3 25,018,500.0
0 #VALUE!
9 Kusen F3 0,00 M3 25,018,500.0
0 #VALUE!
10 Kusen F4 0,00
5 M4 25,018,500.0
0 #VALUE!
11 Kusen F5 0,05
7 M5 25,018,500.0
0 #VALUE!
12 Kusen F6 0,00 M6 25,018,500.0
0 #VALUE!
7 0
13 Kusen FD-3 0,02 M7 25,018,500.0 #VALUE!
8. Pekerjaan Daun Pintu dan Jendela 2 0.00
0
1
2 Kusen P0-1 15,1 M3 1,634,500.00 #VALUE!
2 Kusen P0-2 5,4
2 M3 1,634,500.00 #VALUE!
3 Kusen P0-3 3,17 M3 1,634,500.00 #VALUE!
4 Kusen W-01 5,75 M3 1,634,500.00 #VALUE!
5 Kusen W-02 2,04 M3 1,634,500.00 #VALUE!
6 Kusen W-03 1,23 M3 1,634,500.00 #VALUE!
7 Kusen W-04 1,1 M3 1,634,500.00 #VALUE!
8 Kusen F2 0,53 M3 1,634,500.00 #VALUE!
9 Kusen F3 0,68 M3 1,634,500.00 #VALUE!
10 Kusen F4 1,29 M4 1,634,500.00 #VALUE!
11 Kusen F5 0,68 M5 1,634,500.00 #VALUE!
12 Kusen F6 0,55 M6 1,634,500.00 #VALUE!
13 Kusen FD-3 4,4 M7 1,634,500.00 #VALUE!
8. Penggantung dan Pengunci
2
3 Engsel Pintu 62 Set 76,465.00 4,740,830.00
3 Handle Pintu Ganda Solid 20 Set 318,965.00 6,379,300.00
5 Kunci tanam 10 Bh 150,000.00 1,500,000.00
6 Hak Angin 18 Set 56,465.00 1,016,370.00
Sub Total VIII
IX Pekerjaan Tegel Lantai
9. Lantai 1 Granit 60x60 64,4 m2 201,774.50 #VALUE!
9.
1 Lantai 2 Granit 60x60 50,6
9 m2 201,774.50 #VALUE!
2 Keramik motif teras lantai 1 40 x 40 32,9
1 m2 830,170.00 #VALUE!
Keramik motif teras lantai 2 40 x 40 5,2 m2 830,170.00 #VALUE!
9. Keramik Kamar Mandi Lantai 1 13,4 m2 184,980.00 #VALUE!
9.
3 Keramik Kamar Mandi Lantai 2 8,7 m2 184,980.00 #VALUE!
9.
4 Keramik Dinding
1
5 Keramik Dinding Lantai 1 30 x 30 18,1 m2 211,565.00 #VALUE!
2 Keramik Dinding Lantai 2 30 x 30 36,6 v 211,565.00 #VALUE!
6 Granit Dinding Tangga 270 M 150,000.00 40,500,000.00
7 Stepnoising Granit Tangga 170 bh 150,000.00 25,500,000.00
Sub Total IX
X Pekerjaan Instalasi Listrik
10 Instalasi Listrik Lantai 1
1
.1 Kabel NYM 3 x 1,5 44 m' 12,000.00 528,000.00
2 Sekering otomat Likon 10A 1 bh 27,500.00 27,500.00
3 Fitingan tempel E 40 1 Bh 12,500.00 12,500.00
4 Lampu Downlight Philips 3 Watt 20 Bh 58,000.00 1,160,000.00
5 Lampu Downlight Philips 5 Watt 5 Bh 65,000.00 325,000.00
6 Saklar Tunggal ex broco 8 Bh 17,000.00 136,000.00
7 Saklar Ganda ex broco 3 Bh 22,500.00 67,500.00
8 MCB 32 A (3 Pas) 1 Bh 250,000.00 250,000.00
9 Stop Kontak ex broco 9 Bh 17,000.00 153,000.00
10 Instalasi Listrik Lantai 2
1
.2 Kabel NYM 3 x 1,5 22 M 12,000.00 264,000.00
2 Sekering otomat Likon 10A 17 Bh 27,500.00 467,500.00
3 Fitingan tempel E 40 1 Bh 12,500.00 12,500.00
4 Lampu Downlight Philips 3 Watt 14 Bh 58,000.00 812,000.00
5 Lampu Downlight Philips 5 Watt 3 Bh 65,000.00 195,000.00
6 Saklar Tunggal ex broco 7 Bh 17,000.00 119,000.00
7 Saklar Ganda ex broco 2 Bh 22,500.00 45,000.00
8 MCB 32 A (3 Pas) 1 Bh 250,000.00 250,000.00
9 Stop Kontak ex broco 8 Bh 17,000.00 136,000.00
Sub Total X
XI Pekerjaan Instalasi Air
11 Instalasi Air Lantai 1
.1 Pipa Air Bersih 3/4" 73 M 11,433.34 834,633.71
Pipa Air Bersih 3" 22,6 M 96,625.84 #VALUE!
Pipa air kotor 3" 87,5 M 96,625.84 #VALUE!
Kloset Duduk 1 Bh 2,500,000.00 2,500,000.00
Kloset jongkok 1 Bh 370,000.00 370,000.00
Keran Air 3/4" 3 Bh 48,187.50 144,562.50
Shower 1 Bh 250,000.00 250,000.00
Wastafel 2 Bh 650,000.00 1,300,000.00
Pompa air 1 Bh 17,000,000.0 17,000,000.00
Meteran air 1 Bh 1,400,000.00
0 1,400,000.00
1 2 3 4 5
11 Instalasi Air Lantai 2
.2 Pipa Air Bersih 3/4" 15,5 M 11,433.34 #VALUE!
Pipa Air Bersih 3" 4,1 96,625.84 #VALUE!
Pipa Air Kotor 3" 6,15 M 96,625.84 #VALUE!
Shower 2 Bh 250,000.00 500,000.00
Wastafel 2 Bh 650,000.00 1,300,000.00
Kloset Duduk 2 Bh 2,500,000.00 5,000,000.00
Keran Air 2 Bh 48,187.50 96,375.00
Sub Total XI
XII Pekerjaan Finishing
12 Pekerjaan Pengencatan
1
.1 Pengecatan Eksterior Lantai 1 dan 2 346, M2 62,733.00 #VALUE!
2 Pengecatan Dinding Interior Lantai 1 184,
67 M2 34,583.00 #VALUE!
3 Pengecatan Dinding Interior Lantai 2 174,
24 M2 34,583.00 #VALUE!
4 Pengecatan Kusen 103,
45 M2 60,600.00 #VALUE!
5 Pengecatan Lisplank 9,54
62 M2 31,333.00 #VALUE!
6 Pengecatan Genteng 141, M2 31,333.00 #VALUE!
36 Sub Total XII
XII Pekerjaan Lain-Lain
13
I Pekerjaan Septictank
1
.1 Galian Tanah Septictank 7 M3 #VALUE! #VALUE!
2 Urugan Pasir Septictank 0,34 M3 #VALUE! #VALUE!
3 Plat dinding septictank 1,56
4 M3 #VALUE! #VALUE!
4 Plat Penutup Septictank 0,34
9 M3 #VALUE! #VALUE!
13 Pekerjaan Sumur Resapan 4
1
.2 Galian tanah Sumur Resapan 0,31 M3 #VALUE! #VALUE!
urugan 0,34
7 #VALUE! #VALUE!
2 Plat Penutup Sumur Resapan 0,31 M3 #VALUE! #VALUE!
13 PekerjaanTanah Bak Control 4,6
4 M3 #VALUE! #VALUE!
.3 Galian tanah pipa saluran 0,48 #VALUE! #VALUE!
urugan 0,43 #VALUE! #VALUE!
13 Railing Tangga 18,8
2 M #VALUE! #VALUE!
13
.4 Pagar Balkon 11,3 M #VALUE! #VALUE!
.5 Tandon 1
6 bh 1,800,000.00 1,800,000.00
Sub Total XIII
Sub Total (Rp)

200,605,571.86

77,593,879.66

#VALUE!
#VALUE!

#VALUE!

#VALUE!

#VALUE!

0.00
6.00

#VALUE!

#VALUE!
4,960,500.00

6.00

#VALUE!

#VALUE!
#VALUE!
Tabel 4. Rekapitulasi Rencana Anggaran Biaya

Rekapitulasi Rencana Anggaran Biaya


Pekerjaan : Pembangunan Rumah 2 Lantai
Lokasi : Jl. Ahmad Yani No.96 A Desa Turen, Kabupaten Malang

No. Jenis Pekerjaan Jumlah (Rp)


I Pekerjaan Persiapan #REF!
II Pekerjaan Tanah dan Pondasi #REF!
III Pekerjaan Beton #REF!
IV Pekerjaan Pasangan #REF!
V Pekerjaan Atap #REF!
VI Pekerjaan Penutup Atap #REF!
VII Pekerjaan Lisplank dan Plafond #REF!
VIII Pekerjaan Kusen #REF!
IX Pekerjaan Tegel Lantai #REF!
X Pekerjaan Instalasi Listrik #REF!
XI Pekerjaan Instalasi Air #REF!
XII Pekerjaan Finishing #REF!
XIII Pekerjaan Lain-Lain #REF!
Jumlah #REF!
Dibulatkan 1,036,213,000.00
Terbilang : Satu Milyar Tiga Puluh Enam Juta Dua Ratus Tiga Belas Ribu
Rupiah
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Time Schedule dan Kurva S
Pekerjaan : Pembangunan Rumah
Lokasi : Jl. Ahmad Yani No.96 A Desa Turen,
N Jenis Pekerjaan Bobo Januari Februari Maret April Mei PRESENTA KETERAN
o. t% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 SE GAN
I Pekerjaan Persiapan #REF 0. 0.
II Pekerjaan Tanah dan #REF 0. 1. 1.
III Pekerjaan Beton #REF 0. 0. 1. 0. 1.
IV Pekerjaan Pasangan #REF 0. 2. 5.6 6. 1. 2.3
V Pekerjaan Atap #REF 1.1 1.
VI Pekerjaan Penutup Atap #REF 0. 0.
VI Pekerjaan Lisplank dan #REF 1. 2. 1.4
VI Pekerjaan Kusen #REF 2. 2. 6. 3.9 7. 7. 6.
IX Pekerjaan Tegel Lantai #REF 1. 4.1 5. 2.
X Pekerjaan Instalasi Listrik #REF 0. 0. 1.2
XI Pekerjaan Instalasi Air #REF 0. 1.
XI Pekerjaan Finishing #REF 1. 1.8
XI Pekerjaan Lain-Lain #REF 1. 1.3
JUMLAH #REF
RENCANA FISIK TIAP
AKUMULASI 0. 1. 1. 3. 0. 2. 4. 5.6 2. 9. 1. 3.4 1. 4. 10 9.5 13 10 8. 4.4
REALISASI 0. 2. 3. 7. 7. 9. 14 19. 22 32 33 37. 39 43 53 63. 76 87 95 100
LEBIH CEPAT (+)
LEBIH LAMBAT (-)

Anda mungkin juga menyukai